MATERIALS ESTIMATES FOR CONSTRUCTION CLASSROOM BUILDING FOR AT
SPRINGS EDUCATION SERVICES
SECOND FLOOR - COLUMNS AND SLAB
AMOUNT
ITEM MATERIAL UNIT QTY RATE
(UGX)
1 T20mm Rebar Pc 10 130,000 1,300,000
2 T16mm Rebar Pc 150 77,500 11,625,000
3 T12mm Rebar Pc 250 46,000 11,500,000
4 R8mm Rebar-Rings Pc 150 22,000 3,300,000
5 Binding wire Roll 7 110,000 770,000
6 BRC A142 Roll 5 1,000,000 5,000,000
7 Lake sand Trip 3 1,800,000 5,400,000
8 Machine Crushed Aggregates Trip 4 2,200,000 8,800,000
9 Cement -CEM2 Bag 300 33,000 9,900,000
10 Max Pan 6 Inch Pc 1100 5,300 5,830,000
11 Max Pan 6 Inch Pc 400 4,700 1,880,000
12 Timber 12x1 Pc 600 8,000 4,800,000
13 Timber 8x1 Pc 100 8,500 850,000
14 Polythene sheeting Roll 5 200,000 1,000,000
15 Marine Boards Pc 40 70,000 2,800,000
16 Timber 6x2 Pc 20 10,000 200,000
17 Timber 4x2 Pc 200 8,000 1,600,000
18 Timber 3x2 Pc 150 5,000 750,000
19 Poles Pc 1100 3,500 3,850,000
20 Nails 5" Bag 1 250,000 250,000
21 Nails 4" Bag 1 250,000 250,000
22 Nails 3" Bag 1 250,000 250,000
23 Nails 2.5" Bag 1 250,000 250,000
24 Transport Item 1 500,000 500,000
Total cost for Materials 82,655,000
Add Machines (Concrete
mixer, tower hoist,
Item 1 1500000 1,500,000
vibrator,board cutting
machine, fuel and transport
Add Labour 26,449,600
Total cost for Second Floor 110,604,600
MATERIALS ESTIMATES FOR CONSTRUCTION CLASSROOM BUILDING FOR AT
SPRINGS EDUCATION SERVICES
THIRD FLOOR - COLUMNS UP TO RING BEAM LEVEL
AMOUNT
ITEM MATERIAL UNIT QTY RATE
(UGX)
1 T16mm Rebar Pc 120 77,500 9,300,000
2 R8mm Rebar-Rings Pc 100 22,000 2,200,000
3 Binding wire Roll 5 110,000 550,000
4 Lake sand Trip 1 1,800,000 1,800,000
5 Machine Crushed Aggregates Trip 1 2,200,000 2,200,000
6 R6mm Rebar-wall plate Pc 25 13,000 325,000
7 Cement -CEM2 Bag 100 33,000 3,300,000
8 Timber 12x1 Pc 100 8,000 800,000
9 Timber 8x1 Pc 100 8,500 850,000
10 Timber 4x2 Pc 50 8,000 400,000
11 Timber 3x2 Pc 80 5,000 400,000
12 Poles Pc 200 3,500 700,000
13 Nails 5" Bag 1 250,000 250,000
14 Nails 4" Bag 1 250,000 250,000
15 Vibrator Days 3 50,000 150,000
16 Burnt clay bricks Pc 6000 500 3,000,000
17 Transport Item 1 300,000 300,000
Total cost for Materials 26,775,000
Add Labour 17,000,000
Total cost for Third Floor 43,775,000