HATC
CONTRACTOR’S STAMP: Sub CONTRACTOR’S STAMP:
The Sub Contractor declares that this submission has passed the
subcontractor's QA/QC procedure and is in accordance with the
requirements of the Contract.
00 First Version Wudi Chengzhu Renshuwei 22-Aug-2024
REV DESCRIPTION PREPARED CHECKED APPROVED DATE
CONTRACTOR Consortium SEPCOIII - METKA S.A.
Sub -CONTRACTOR HATC
PROJECT NAME
AL-Anbar Combined Cycle Power Plant
Project 1642.6MW
LOCATION: TITLE:
WEEKLY PROGRESS REPORT
ANBAR / IRAQ REPORT NO: #005
FROM 12th Oct 2024 to 18th Oct 2024
SUBMITTAL DATE:18th October 2024
SCALE: DOCUMENT No. REVISION:
1642.6MW IQ001-Z000-ZZZ-S000-ABE-2024018-00 00
Table of Contents
Page of
HATC
Section 1: Health, Safety and Environment............................................................................ 1
1.1 HSE Overview....................................................................................................... 1
1.2 HSE activities on site.............................................................................................. 2
Section 2: Quality Assurance/Quality Control.........................................................................3
2.1 ITP/MS Status....................................................................................................... 3
2.2 Inspection completed this week................................................................................ 4
2.3 Inspection planned next week.................................................................................. 4
Section 3: Overall Construction Progress Schedule Status.......................................................5
3.1 Overall Construction Quantity summary.....................................................................5
Section 4: Weekly Completion Status for this week.................................................................5
Section 6: Subcontract Manpower and Machinery Status.........................................................7
6.1 Manpower............................................................................................................. 7
6.2 Machinery............................................................................................................. 7
Section 7: Equipment and Shipment Status...........................................................................8
7.1 Equipment and Material Status................................................................................. 8
7.2 Shipment Receiving Progress.................................................................................. 8
Section 8: Areas of concern need to be supported..................................................................9
Section 9: Construction Pictures........................................................................................ 10
9.1 Progress pictures:...................................................................................................... 10
9.2 Highlight Pictures:............................................................................................... 11
Section 10 Electromechanical Works…………………………………………………………………….12
10.1
Overview………………………………………………………………………………………………………
…………………………………13
10.2 Erection Works Sequence and Manpower……………………………………………….
…………………………………….14
10.3 Activities Photos…………………..
…………………………………………………………………………………………………………15
Page of
HATC
Section 1: Health, Safety and Environment
1.1 HSE Overview
Description This week Cumulative
Project Construction man-hours worked 3304 52272
LTI 0 0
Man-hours without LTI 0 0
LTIFR for this project 0 0
Medical Treatment Case/RWC 0/0 0/0
First Aid Case 0 0
Occupational Illness 0 0
Dangerous Occurrence 0 0
Environmental Incident 0 0
Near Misses 0 0
Fatality
0
0 LTI
Restricted Work Case(RWC) /
0/0 Medical Treatment Case(MTC)
0 First Aid Case( FAC)
0 Near Miss(NM)
6 HSE Observation
Manhours/Manpower
104,008/506 (Cumulative)
* LTI: Lost time Incident
* LTIFR: Lost time incident frequency rate = LTI X 100,000 / total construction man hours worked
* Medical Treatment: Medical Treatment Case(MTC) incidents result in an injury that requires the injured
party (IP) to attend hospital for treatment (as opposed to receiving treatment from the site nurse), but
does not prevent the IP returning to work the next day to carry out his / her former duties.
* First aid Treatment: First Aid Case incidents result in a minor injury that can dealt with by on site first aid
and allows the injured party to return to his / her former duties the same day
Page 1 of 20
HATC
1.2 HSE activities on site
Weekly HSE walk-down.
Weekly tool box talk (TBT) conducted:
1、SEPCO III instructions on the topic of 100 days without accidents were discussed
and everyone was urged to do so
2、Constant reminders to work at heights safely and wear safety equipment for
this work to understand the risks of work and how to avoid accidents
Daily tool box talk (TBT) conducted.
1、PPE, W@H, housekeeping, pinch point, electrical hazard & speed limit
Basic situation on site
1、Personnel: we now have 250- 270 eng., tech., workers etc. at our site with different activities, rebar &
formwork, scaffolding, back filling…etc.
2、 Continue to do daily safety supervision, safety supervisors visit the construction site every day to find
hidden safety hazards, timely rectification and leave the process of information.
3、Conduct on-site safety risk briefing for all site personnel.
4、Monthly fire safety inspection, focusing on whether the water of the fire bucket is sufficient and whether
the pressure of the fire extinguisher is normal。
5、Daily inspection for lifting & electrical tools, implement monthly color code with green for this month.
6、Documents work applied as per SEPCO III requirements.
7、Focus on chemical work (painting, treating...).
8、Take necessary precautions near the rainy season Especially electrical DB & excavation work.
9、Preparation for installing of overhead crane
Page 2 of 20
HATC
Description: Daily TBT, Refresh training (speed limit & safely drive)
Description: Daily site inspection & electrical tools, Daily site
housekeeping & dust control
Page 3 of 20
HATC
Section 2: Quality Assurance/Quality Control
2.1 ITP/MS Status
ITP Status Qty. MS Status Qty. Remark
Issued 0 Issued 0
Rejected 0 Rejected 0
Pending 2 Pending 0
Cumulative 20 Cumulative 20
2.2 Inspection completed this week
LOCATION / REMAR
S.r. DESCRIPTION DATE
DISC. KS
CHECKING Surface treatment and 05-11
bitumen coating of Cable trench which Oct
RFI-HATC- CABLE passes through the pedestals of
C-363 TRENCH 400KV GIB outdoor foundations, of
sides foundations & external sides of
walls.
CHECKING Forms, reinforcement & 05-11
RFI-HATC- CONTROL embedded parts of Cable trench at Oct
C-383 BLDG. level 0.00, from axis 1 to 5 between
axis A to C.
CHECKING Forms & reinforcement of 05-11
columns from level + 5.00 to + Oct
RFI-HATC- 400KV GIS
10.00columns from level + 5.00 to +
C-438 BLDG
10.00, from axis 13 to 20, along axis A,
20 & B
CHECKING Forms, reinforcement & 05-11
RFI-HATC- CABLE embedded parts of foundation, walls & Oct
C-441 TRENCH top slab panel, Cable trench at south of
bus-reactor foundation, section 29-29
final inspection of block wall, Along 05-11
RFI-HATC- 400KV GIS
axis 1 and from axis 1 to 6 along axis A Oct
C-443 BLDG.
& B, from level – 0.06 to level + 14.20
checking the installation of Sleeve 05-11
RFI-HATC- CONTROL pipes between the relay room and Oct
C-446 BLDG. battery, UPS battery & DC battery
rooms.
CHECKING Forms, reinforcement & 05-11
RFI-HATC- 132KV GIS embedded parts of Cable trench Oct
C-469 BLDG between axis 7 & 10, top cover is
checker plate
CHECKING BACKFILLING AND 05-11
COMPACTION Cable trench from line Oct
RFI-HATC- CABLE
reactor foundation to 400kv GIB
C-473 TRENCH
outdoor foundations, section 1-1 & 3-3
of cable trenches.
Page 4 of 20
HATC
CHECKING Forms, reinforcement & 05-11
embedded parts of columns, beams & Oct
corbels, Part of columns, beams and
RFI-HATC- 400KV GIS
corbels of overhead crane at level
C-475 BLDG
+10.00, from axis 13 to 20, along axis
A, 20 & B, and beam of supporting the
cat ladder.
CHECKING Forms, reinforcement & 05-11
embedded parts of foundation, wall, Oct
pedestals & slab, Cable tunnel
RFI-HATC- CABLE
between auto transformers foundations
C-476 TRENCH
and control building, section 9-9, 10-
10, 14-14, 15-15 & 30-30 of cable
trench drawings
checking cement & anti cracking net 05-11
RFI-HATC- 400KV GIS for walls, internal sides only, From axis Oct
C-488 BLDG 1 to 12, along axis A,1 & B, from level -
0.05 to + 14.00, internal side only.
final inspection of block wall, Along 05-11
RFI-HATC- 132KV GIS
axis 1, 12, 10, A & B, from axis 1 to 12, Oct
C-489 BLDG
from level -0.06 to +10.20
CHECKING Forms, reinforcement & 05-11
embedded parts of foundation, walls, Oct
RFI-HATC- 132KV GIS
slab & ventilation shaft of cable
C-503 BUILDING
tunnel.Cable tunnel from axis 3 to 7,
from level – 3.00 to – 3.05
CHECKING FORMS OF Forms OF 05-11
400KV GIB
RFI-HATC- blinding lean concrete under the raft Oct
FOUNDATION
C-506 foundation of 400kv GIB outdoor
S
foundation, Between axis of Z4 to Z10.
CHECKING Forms & reinforcement of 05-11
foundations and walls of Cable Oct
RFI-HATC- CABLE
trenches pass through the pedestals of
C-507 TRENCH
132kv GIB outdoor foundations,
section 1-1 of cable trenches
CHECKING Surface treatment and 05-11
AUTO
RFI-HATC- bitumen coating of sides foundations & Oct
TRANSFORME
C-508 external sides of walls of Foundations
R
of oil tank # 1, 2, 3 & 4.
CHECKING Forms, reinforcement and 05-11
400KV GIB
RFI-HATC- embedded parts OF foundations, Oct
FOUNDATION
C-512 pedestals & trenches pass through,
S
foundations between axis of Z1 to Z10
2.3 Inspection planned next week
LOCATION / REMAR
S.r. DESCRIPTION DATE
DISC. KS
RFI-HATC-C- CABLE TRENCH CHECKING Surface treatment 12-18
363 and bitumen coating of Cable Oct
trench which passes through
the pedestals of 400KV GIB
outdoor foundations, of sides
foundations & external sides of
walls.
Page 5 of 20
HATC
RFI-HATC-C- 132KV GIS checking the Primary treatment 12-18
366 BLDG & setting out & Masonry Oct
construction and curing of Block
wallsBlock walls from level =
6.00 to level + 9.50, from axis
1 to 12 along axis A, B, 1 & 12
RFI-HATC-C- CONTROL CHECKING Forms, 12-18
383 BLDG. reinforcement & embedded Oct
parts of Cable trench at level
0.00, from axis 1 to 5 between
axis A to C.
RFI-HATC-C- CONTROL checking the Primary treatment 12-18
390 BLDG. & setting out & Masonry Oct
construction and curing of Block
walls from axis 1 to 8, between
axis A to C, from level – 0.05 to
+ 5.35
RFI-HATC-C- 400KV GIS CHECKING Forms & 12-18
438 BLDG reinforcement of columns from Oct
level + 5.00 to + 10.00columns
from level + 5.00 to + 10.00,
from axis 13 to 20, along axis
A, 20 & B
RFI-HATC-C- 400KV GIS checking the Primary treatment 12-18
439 BLDG. & setting out & Masonry Oct
construction and curing of Block
walls from level + 10.00 to
level + 14.20, Along axis 1 and
from axis 1 to 12 along axis A &
B
RFI-HATC-C- CABLE TRENCH CHECKING Forms, 12-18
441 reinforcement & embedded Oct
parts of foundation, walls & top
slab panel, Cable trench at
south of bus-reactor foundation,
section 29-29
RFI-HATC-C- 400KV GIS final inspection of block wall, 12-18
443 BLDG. Along axis 1 and from axis 1 to Oct
6 along axis A & B, from level –
0.06 to level + 14.20
RFI-HATC-C- CONTROL checking the installation of 12-18
446 BLDG. Sleeve pipes between the relay Oct
room and battery, UPS battery
& DC battery rooms.
RFI-HATC-C- 132KV GIS CHECKING Forms, 12-18
469 BLDG reinforcement & embedded Oct
parts of Cable trench between
axis 7 & 10, top cover is
checker plate
RFI-HATC-C- CABLE TRENCH CHECKING BACKFILLING AND 12-18
473 COMPACTION Cable trench from Oct
line reactor foundation to 400kv
GIB outdoor foundations,
section 1-1 & 3-3 of cable
trenches.
Page 6 of 20
HATC
RFI-HATC-C- 400KV GIS CHECKING Forms, 12-18
475 BLDG reinforcement & embedded Oct
parts of columns, beams &
corbels, Part of columns, beams
and corbels of overhead crane
at level +10.00, from axis 13 to
20, along axis A, 20 & B, and
beam of supporting the cat
ladder.
RFI-HATC-C- CABLE TRENCH CHECKING Forms, 12-18
476 reinforcement & embedded Oct
parts of foundation, wall,
pedestals & slab, Cable tunnel
between auto transformers
foundations and control
building, section 9-9, 10-10, 14-
14, 15-15 & 30-30 of cable
trench drawings
RFI-HATC-C- 400KV GIS checking cement & anti 12-18
488 BLDG cracking net for walls, internal Oct
sides only, From axis 1 to 12,
along axis A,1 & B, from level -
0.05 to + 14.00, internal side
only.
RFI-HATC-C- 132KV GIS final inspection of block wall, 12-18
489 BLDG Along axis 1, 12, 10, A & B, Oct
from axis 1 to 12, from level -
0.06 to +10.20
RFI-HATC-C- 132KV GIS CHECKING Forms, 12-18
503 BUILDING reinforcement & embedded Oct
parts of foundation, walls, slab
& ventilation shaft of cable
tunnel.Cable tunnel from axis 3
to 7, from level – 3.00 to – 3.05
RFI-HATC-C- 400KV GIB CHECKING FORMS OF Forms OF 12-18
506 FOUNDATIONS blinding lean concrete under Oct
the raft foundation of 400kv GIB
outdoor foundation, Between
axis of Z4 to Z10.
RFI-HATC-C- CABLE TRENCH CHECKING Forms & 12-18
507 reinforcement of foundations Oct
and walls of Cable trenches
pass through the pedestals of
132kv GIB outdoor foundations,
section 1-1 of cable trenches
RFI-HATC-C- AUTO CHECKING Surface treatment 12-18
508 TRANSFORMER and bitumen coating of sides Oct
foundations & external sides of
walls of Foundations of oil tank
# 1, 2, 3 & 4.
RFI-HATC-C- 400KV GIB CHECKING Forms, 12-18
512 FOUNDATIONS reinforcement and embedded Oct
parts OF foundations, pedestals
& trenches pass through,
foundations between axis of Z1
Page 7 of 20
HATC
to Z10
Section 3: Overall Construction Progress Schedule Status
3.1 Overall Construction Quantity summary
S.r Quantit Completed Completed Completed Plan for
Activities Unit Remaining
. y weekly total % next week
Note: The calculation of quantity is based on the available drawings.
Section 4: Weekly Completion Status for this week
4.1 Installation part
4.2 Full Site Grounding Construction
Section 5: Weekly plan for site construction works
Item Description Start Finish Remarks
1 Installation part
2 Full Site Grounding Construction
Page 8 of 20
HATC
Page 9 of 20
HATC
Section 6: Subcontract Manpower and Machinery Status
6.1 Manpower
S.r. Description Work Scope Quantities Sum Remark
6.2 Machinery
S.r. Description Work Scope Quantities Sum. Remark
Page 10 of 20
HATC
Section 7: Equipment and Shipment Status
7.1 Equipment and Material Status
HDPE pipeline is expected to arrive on August 30th.
The plate rolling machine is expected to arrive on September 5th.
7.2 Shipment Receiving Progress
N/A
Page 11 of 20
HATC
Section 8: Areas of concern need to be supported
S.r. Areas of concern Submitted date Remarks
N/A
Page 12 of 20
HATC
Section 9: Construction Pictures
9.1 Progress pictures:
Project Name: AL-Anbar Combined Cycle Power Plant
Project 1642.6MW
Description: Pouting the foundation of oil tank in the line
reactor.
Page 13 of 20
HATC
Project Name: AL-Anbar Combined Cycle Power Plant
Project 1642.6MW
Description: Fixing embedded steel plates in the GIS ground slab of 400kv GIS
bldg..
9.2 Highlight Pictures:
Project Name: AL-Anbar Combined Cycle Power Plant
Project 1642.6MW
Description:fixing wooden forms and scaffolding for the
fire wall of the line reactor foundation.
Section 10. Electromechanical Works
10.1 Overview
Page 14 of 20
HATC
The Electromechanical Department in HATC company is responsible for electromechanical works
in the 400/132 KV Substation. Our responsibility starts from the beginning with the civil team to
review the drawings and ensure that the drawings are matching between electrical and civil to avoid
the nonconformance that happen in future and civil and fully follow up with their works during the
construction works as proactive action to avoid any problem or obstacles that will may be face us
during the Erection works especially the MEP works .The Erection team always should be observe
any mismatching in the drawings in order to notice the Clients and Contractor to do the corrective
actions between all parties. After ensure that all the civil works belong to the MEP are implemented
in good way, we will start the MEP works (LSPAC, LSPDC, HVAC, AC unit, Fire alarm,
Firefighting, CCTV and etc) after handed over the buildings. After complete all the MEP works, we
will start the installation the electrical equipment’s inside buildings then the installation of
equipment’s in outdoor and our works will be in fast tracking as importantly and priority and
depends on the contractor instructions reach to final activity testing and commissioning then ready
for energizing this substation.
10.2 Erection Works Activity Sequence and Manpower
Item
No
Activity Manpower Status
1. Earthing System works. 4 Ongoing
2. MEP works. 5 not start yet
3. MEP Sleeves and Pipes works. 2 Ongoing
4. Transformer installation works. 3 not start yet
5. Reactor installation works. 5 not start yet
6. Outdoor steel Support installation works. not start yet
Page 15 of 20
HATC
7. Outdoor electrical equipment’s installation works. not start yet
8. Cable Tray installation works. not start yet
9. Lightning Protection installation works not start yet
10. 132 KV GIS installation works. not start yet
11. 400 KV GIS installation works not start yet
12. Electrical panels installation works (Control Building) not start yet
13. LV cable Laying. not start yet
14. LV cable termination. not start yet
15. HV Cable Laying. not start yet
16. HV Cable termination. not start yet
17. ACSR Cable works. not start yet
18. Others. not start yet
19. Testing and Commissioning. not start yet
10.3 Activities Photos
Page 16 of 20
HATC
H VAC WORK EARTHING WORK
INSTALIRION OF TRENCH SOPRT Geat the matiral from sepco wearhous
Page 17 of 20
HATC
Lighting works
Page 18 of 20