1/24
comap136.17.doc
IN THE HIGH COURT OF JUDICATURE AT BOMBAY
ORDINARY ORIGINAL CIVIL JURISDICTION
COMMERCIAL APPEAL NO. 136 OF 2017
IN
COMMERCIAL ARBITRATION PETITION (L) NO. 208 OF 2017
Heligo Charters Private Limited ... Appellant
V/s.
Aircon Feibars FZE ... Respondents
Mr. Vikram Nankani, Sr. advocate a/w. Mr. Sumeet Nankani, Mr. Akshay
Kishore, Mr. Dhruv Jain I/b. Economics Law Practice for appellants.
Mr. Aspi Chinoy, Sr. advocate a/w. Mr. Kunal Mehta, Ms. Bulbul Singh i/b.
Crawford Bayley & co. for respondents.
CORAM : NARESH H. PATIL AND
NITIN W. SAMBRE, JJ.
RESERVED ON : 7th June, 2018
PRONOUNCED ON : 29th June, 2018.
JUDGMENT [ Per Naresh H. Patil, J.] :
This appeal is directed against an order passed by the learned
Single Judge of this Court on 28th April, 2017 in Comm Arbitration
Petition (l) No. 208/2017. The respondent herein Aircon Beibars FZE
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
2/24
comap136.17.doc
(original petitioner) holds a foreign award passed on 25 th January,
2017 for an amount of approximately US$7 million equivalent to
Rs.46 Crores against the appellant herein Heligo Charters Pvt. Ltd.
The award was made pursuant to reference of disputes under the
Arbitration Clause contained in Clause 7 of the Settlement Deed
dated 9th September, 2014. The Award was passed in Singapore.
2. The original respondentappellant herein did not challenge the
Award in the Singapore Court. It has thus become final. It is the
contention of the respondent herein that the appellant has failed to
pay awarded amount of US$ 7 million/Rs.46 Crores.
3. The Respondent herein had filed Arbitration Petition
No.269/2017 wherein it was pointed out that only significant asset
that the appellant/Heligo has in India, is a helicopter which it uses for
ONGC operations. The respondent expressed apprehension that
appellant might move the helicopter from the jurisdiction of the Court
or might encumber or alienate the same to prevent the same from
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
3/24
comap136.17.doc
being proceeded against in enforcement of the said Award. Therefore,
the petitioner had sought relief under Section 9 of the Arbitration Act,
1996 (as amended by Amendment Act of 2015) to restrain the
respondent from alienating, encumbering, or parting with possession
of the Helicopter and from removing it from the jurisdiction of the
Court, pending enforcement of the Foreign Award under Part II of the
Arbitration Act.
4. The learned Single Judge by an order dated 28 th April, 2017
confirmed the adinterim injunction.
5. The learned Senior Counsel Mr. Vikram Nankani appearing for
the appellant submitted that the question of law arising herein is
what the law in force in India was on the date on which the
Arbitration Agreement was entered into by the parties. Clause 7 of
the Settlement Deed dated 9th September, 2014 reads as under:
“7. GOVERNING LAW AND ARBITRATION
This DEED shall be governed by and construed in
accordance with Singapore Law and any and all
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
4/24
comap136.17.doc
disputes, matters, differences of whatsoever nature
and howsoever arising out of this DEED shall be
referred to arbitration in Singapore in accordance with
the rules of the Singapore International Arbitration
Centre (SIAC) for the time being in force. The
Arbitration shall be conducted in English and the
parties shall endure to have the Arbitration concluded
within three (3) months of it being called for. Each of
the Buyer and the Seller shall be entitled to nominate
an Arbitrator. The two appointed arbitrators shall
within a period of no more than (10) days appoint a
third arbitrator such that the tribunal shall consist of
three arbitrators. If upon the receipt by the Buyer or
the Seller (as the case may be) of the nomination, in
writing, of the appointment of an arbitrator, Buyer or
the Seller (as the case may be) shall appoint their
arbitrator within 14 days, failing which the arbitrator
already appointed shall act as a sole arbitrator.”
6. In the written submissions it is submitted that the Scheme of
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
5/24
comap136.17.doc
the Arbitration Act visavis foreign seated arbitration does not
permit the respondent to approach courts in India under Section 9 of
the Act. This submission is based on the fact that the parties had
executed the Settlement Deed, and consequently the Arbitration
Agreement, prior to the Arbitration and Conciliation (Amendment)
Act, 2015 and had agreed to seat their arbitration in Singapore. The
parties have excluded availability of PartI of the Act, including
Section 9 of the Act. The law in India was settled by the Supreme
Court in Bharat Aluminum Co. vs. Kaiser Technical Service
(2012) 9 SCC 552 ('BALCO' for short). It was held that Section 9 of
the Act was not applicable to foreignseated International Commercial
Arbitration. The BALCO judgment was pronounced on 6th September,
2012. The Arbitration Agreement in the present case was executed on
9th September, 2014. Section 9 of the Act, therefore, is not applicable
to the facts of the case. The dispute between the parties was referred
to arbitration on 12th April, 2015. The amended act came into effect
from 23rd October, 2015. The Counsel, therefore, submitted that the
negative right of the parties under the Settlement Deed – to not have
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
6/24
comap136.17.doc
the ability to approach courts in India under Part I of the Act – had
accrued before the amendment to the Act took effect. It is submitted
that Section 26 of the Amendment Act must be given purposive
interpretation based on the findings of Apex Court in the case of
Thyssen judgment. The Counsel referred to the 246 th report of the
Law Commission of India. It is the submission of the Counsel that
proviso to Section 2(2) of the Arbitration Act cannot be made
applicable retrospectively. One of the written submission of the
appellant reads as under:
“14. Without prejudice to the submissions made
above, and in the alternative, the Appellant
further submits that there is yet another reason by
the petition in the present case is not
maintainable. This because the second condition
in the proviso to Section 2(2) is not fulfilled. The
proviso, inter alia, provides that if the seat of
arbitration is outside India, the foreign award has
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
7/24
comap136.17.doc
to be “enforceable and recognised” under Part II of
the Act. These words indicate that unless and
until the foreign award is first enforced and
recognised (accepted) by this Hon'ble Court, under
Section 48 read Section 49 of the Act, no petition
under Section 9 is maintainable.
15. Enforceability and recognition of foreign
award is a condition precedent for filing petition
under Section 9. This submission is fortified by
the language used in Section 9 itself, which while
covering the situation after award refers only
Section 36 of the Act, which applies to domestic
award. Hence, on a plain reading, Section 9, does
not cover a case of foreign award after arbitration
is concluded and therefore, the petition under
Section 9 in relation to foreign award can only be
maintained, if the second condition under the
proviso to Section 2(2) was also satisfied, namely,
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
8/24
comap136.17.doc
Section 9 of the foreign award should be
enforceable and recognised under Part II of the Act
by the competent court in India.
16. Indeed, since the Respondent has failed to
procure enforcement under Part II of the Act, for
more than twelve (12) months after the Foreign
Award was made, the Foreign Award has not
become enforceable in terms of section 49 of the
Act and remains to be tested for enforceability in
terms of Section 48 of the Act.
7. In the facts, the Counsel submitted that primafacie case is
made out. Balance of convenience is not in favour of the respondent
and irreparable injury would be caused in case the relief is denied to
the appellant herein. The Counsel submitted that Single Judge failed
to appreciate the facts, the import of the judgment and the amended
provisions of the Arbitration Act.
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
9/24
comap136.17.doc
8. The learned Counsel for the appellant placed reliance on
following judgments:
I) Harmony Innovation Shipping Ltd. Vs. Gupta Coal India
Ltd.
& anr.1
ii) Thyssen Stahlunion Gmbh Vs. Steel Authority of India
Ltd.2
iii) Bharat Aluminum Company Vs. Kaiser Aluminum
Technical Services.3
iv) Law Commission of India (Report No.246)
v) Order dtd. 17/4/17 in ARBPL/208/2017 passed by Justice
G.S. Patel.
9. In the case of Thyseen Stahlunion GMBH (cited supra),
the Apex Court observed in Paragraph 32 as under:
“32. Principles enunciated in the judgments show as to
1 (2015) 9 SCC 172
2 (1999) 9 SCC 334
3 (2012) 9 Supreme Court Cases 552.
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
10/24
comap136.17.doc
when a right accrues to a party under the repealed Act.
It is not necessary that for the right to accrue legal
proceedings must be pending when the new Act comes
into force. To have the award enforced when arbitral
proceedings commenced under the old Act under that
very Act is certainly an accrued right. Consequences for
the party against whom award is given after arbitral
proceedings have been held under the old Act though
given after the coming into force of the new Act, would
be quite grave if it is debared from challenging the
award under the provisions of the old Act. Structure of
both the Acts is different. When arbitral proceedings
commenced under the old Act it would be in the mind of
everybody, i.e., the arbitrators and the parties that the
award given should not fall foul of Sections 30 and 32 of
the old Act. Nobody at that time could have thought
that Section 30 of the old Act could be substituted by
Section 34 of the new Act.”
10. The learned Senior Counsel Mr.Chinoy appearing for
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
11/24
comap136.17.doc
respondents submitted that appellant therein has raised
technical/legal pleas to exercise of jurisdiction as follows:
“e(i) that section 9 was not applicable as Part I
including section 9 was excluded by virtue of the
Arbitration being seated in Singapore and subject to
Singapore Law; and
(ii) that orders under section 9 could not be sought till
the Foreign Award had been recognised and held to
enforceable under Section 48. The Respondent had also
pointed out that the Helicopter had already been
provided as security to the Union Bank of India for
obtaining various banking facilities.
11. It is submitted that by an order dated 28 th April, 2017 the
learned Single Judge rejected the respondent's objection to the
exercise of jurisdiction under Section 9 and allowed the petition.
12. In the submission of the Counsel that mere fact that under the
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
12/24
comap136.17.doc
arbitration agreement the arbitration took place in foreign country
could not resolve any exclusion in nonapplicability of Section 9 of the
Act. The learned Single Judge pointed out that since Section 2(2)
proviso is in relation to foreign awards, to accept the appellant's
submission “would be to render the amendment to section 2(2) utterly
otiose. The proviso to Section 2(2), which was added by the Arbitration
and Conciliation Act, 2015 reads as under:
“2(2) Provided that subject to an agreement to
the contrary, the provisions of sections 9, 27 and
clause (a) of subsection (1) and subsection (3) of
section 37 shall also apply to international commercial
arbitration, even if the place of arbitration is outside
India, and an arbitral award made or to be made in
such place is enforceable and recognised under the
provisions of Part II of this Act.”
13. The said proviso was added pursuant to Supreme Court
judgment in the case of BALCO cited supra. The Counsel referred to
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
13/24
comap136.17.doc
Report No.246 of Law Commission of India. In the submission of
learned Senior Counsel Mr. Chinoy notwithstanding that Part I is not
applicable to a Foreign Seated Arbitration, the proviso to Section 2(2)
was introduced to make only Section 9 (and other sections) of Part I
applicable even to Foreign seated Arbitrations, in order to provide a
remedy to a party who obtains a Foreign Award in such a Foreign
seated Arbitration, so that such a Party was not faced with the
situation that “the entity against which it had to enforce the award
has been stripped off its assets and has been converted into a shell
company.” It is submitted that the Amendment Act which introduced
section 2(2) proviso has treated section 9 as being distinct from the
rest of Part I of the Arbitration Act, 1996 and has made Section 9
applicable to the foreign seated arbitration, unless the parties
specifically agrees to the contrary. The Counsel further submitted
that remedy under Section 9 is a transitory provision pending the
process contemplated under Section 48 of the Act. This is obviously
intended to ensure that a Court can step in to protect an asset from
being diverted or dissipated and to ensure that the holder of a foreign
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
14/24
comap136.17.doc
Award, if he is able to get his foreign award pronounced enforceable
against an asset which he can proceed. In the written submissions
the respondent has specifically stated in paragraphs (d) (e) and (g) as
under:
“(d) More once a Foreign Award is “recognised” and
held to be “enforceable” under section 48, there would
be no need to resort to section 9, as “the award would
be deemed to be a decree of the Court” (Ref: Section 49)
and orders by way of injunctions, attachment etc. can
be sought in Execution proceedings. It is only in the
interregnum, i.e. till the Foreign Award is held to be
enforceable as a decree if the Court (under sections 48
and 49), that recourse would be required under section
9 for interim protective orders to prevent dissipation
and diversion of assets.
(e) The patent fallacy in the Appellants submission is
apparent from the fact that the proviso to sec 2(2)
makes section 9 applicable to an international
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
15/24
comap136.17.doc
commercial arbitration taking place outside India “and
an arbitral award made, or to be made in such place..”.
Under the plain language of the Proviso to Section 2(2),
an Application under Section 9 could be made even
during the pendency of an Arbitration held outside
India; i.e. even prior to an Award having been made in
such a Foreign Arbitration. It would be ex facie
incongruous/absurd to construe the Proviso to section
2(2) to mean that an Application under section 9 would
be maintainable before the foreign Award was made
BUT would not be maintainable once the foreign
Award was made until the Award had been recognised
and held enforceable under Section 48.
(g) The reliance sought to be placed by the Appellants
between the language proposed by the Law
Commission for the proviso to sec 2(2) i.e. “if an award
made, or to be made, in such place would be
enforceable and recognised under Part II of this Act”,
and the section as enacted “if an award made, or to be
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
16/24
comap136.17.doc
made, in such place is enforceable and recognised
under Part II of this Act”, is misplaced. The change in
language is inconsequential and merely a matter of
phrasing. In both cases the said last sentence, is
merely descriptive of the “arbitral award made, or to be
made” as being a Foreign Award required to be
recognised and enforced under Part II of the Act. The
last sentence does not stipulate a second/additional
precondition for making an Application under section
9.
14. We have perused the judgments cited supra and written
submissions of the parties.
15. Heard learned Counsel appearing for the respective parties. We
agree with the submissions advanced by the Counsel appearing for the
respondents. The amended provisions of Section 2(2) clearly stipulates
that subject to an agreement to the contrary, the provisions of Section
9 shall apply to international commercial arbitration even if the place
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
17/24
comap136.17.doc
of arbitration is outside India. The contention that unless the award
is put to execution in accordance with provisions of Section 48, a party
is not entitled to seek interimrelief is not sustainable. There is no
such embargo or restriction placed for seeking recourse to interim
measures even if the award is foreignseated one. The amendment
was brought into effect after the Law Commission submitted its report
consequent to judgment in the case of BALCO (cited supra).
Paragraph 194 of the judgment reads as under:
“194. In view of the above discussion, we are of
the considered opinion that the Arbitration Act,
1996 has accepted the territoriality principle
which has been adopted in the UNCITRAL Model
Law, Section 2(2) makes a declaration that Part I
of the Arbitration Act, 1996 shall apply to all
arbitrations which take place within India. We
are of the considered opinion that Part I of the
Arbitration Act, 1996 would have no application
to international commercial arbitration held
outside India. Therefore, such awards would
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
18/24
comap136.17.doc
only be subject to the jurisdiction of the Indian
courts when the same are sought to be enforced
in India in accordance with the provisions
contained in Part II of the Arbitration Act, 1996.
In our opinion, the provisions contained in the
Arbitration Act, 1996 make it crystal clear that
there can be no overlapping or intermingling of
the provisions contained in Part I with the
provisions contained in Part II of the Arbitration
Act, 1996.”
We are, therefore, not inclined to accept the contentions of the
appellant on that ground. In view of the amended provisions and
facts, we are of the view that operation of provisions of Section 9
cannot be excluded in absence of a specific agreement to the contrary.
The judgment in BALCO was pronounced on 6th September, 2012.
The dispute between the parties was referred on 8 th April, 2015. The
Arbitration agreement was executed between the parties on 9 th
September, 2014. Whereas the Act was amended on 23 rd October,
2015.
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
19/24
comap136.17.doc
16. In respect of interpretation placed by the Counsel appearing for the
appellant under the provisions of Section 2(2), 9 and 48, we are of the
view that the interim protection in the facts cannot be denied to the
respondent irrespective of as to whether the award was put to
execution or not? Such a measure is made available in law under
Section 9 of the Act so as to prevent dissipation and diversion of
assets. This being the object and purpose behind the amended
provisions which is based on the recommendations of the Law
Commission. We do not find any error in the view adopted by the
learned Single Judge on this count. The judgments cited supra by the
Counsel appearing for the appellant do not support and sustain the
interpretation placed by the Counsel.
17. It is to be noted that although the arbitration agreement was
entered into in September 2015, the objection under Section 9 was
filed in April 2017 i.e. 19 months after the amendment.
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
20/24
comap136.17.doc
18. In Paragraph11 of the impugned order dated 28 th April, 2017,
the learned Single Judge quoted the extract of Report No.246 of the
Law Commission of India which reads as under:
While the decision in BALCO is a step in the right
direction and would drastically reduce judicial
intervention in foreign arbitrations, the Commission
feels that there are still a few areas that are likely to
be problematic.
(i) Where the assets of a party are located in
India, and there is a likelihood that that
party will dissipate its assets in the near
future, the other party will lack an
efficacious remedy if the seat of the
arbitration is abroad. The latter party will
have two possible remedies, but neither will
be efficacious. First, the latter party can
obtain an interim order from a foreign Court
or the arbitral tribunal itself and file a civil
suit to enforce the right created by the
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
21/24
comap136.17.doc
interim order. The interim order would not
be enforceable directly by filing an execution
petition as it would not qualify as a
“judgment” or “decree” for the purposes of
sections 13 and 44A of the Code of Civil
Procedure (which provide a mechanism for
enforcing foreign judgments). Secondly, in
the event that the former party does not
adhere to the terms of the foreign Order, the
latter party can initiate proceedings for
contempt in the foreign Court and enforce the
judgment of the foreign Court under sections
13 and 44A of the Code of Civil Procedure.
Neither of these remedies is likely to provide
a practical remedy to the party seeking to
enforce the interim relief obtained by it.
That being the case, it is a distinct possibility
that a foreign party would obtain an arbitral
award in its favour only to realize that the
entity against which it has to enforce the
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
22/24
comap136.17.doc
award has been stripped of its assets and has
been converted into a shell company.
(ii) While the decision in BALCO was made
prospective to ensure that hotly negotiated
bargains are not overturned overnight, it
results in a situation where Courts, despite
knowing that the decision in Bhatia is no
longer good law, are forced to apply it
whenever they are faced with a case arising
from an arbitration agreement executed pre
BALCO.
In Paragraph18 the learned Single Judge observed as under:
18. On the question of whether such an order ought to
be made on merits, Mr.Nankani says that Heligo is
good for the money. Given that this is about a
helicopter, he succumbs to temptation in describing his
client as being “not a flybynight operator”. If that is
so, Mr. Nankani's client's option is simple: his client
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
23/24
comap136.17.doc
must make available by a deposit in Court sufficient
money or security to secure a potential enforcement of
the foreign award that has been rendered against it. If
not, I see no reason why a limited injunction of the
nature that I have described, i.e. subject to a prior
claim by a secured creditor ought not to be made.
Certainly, I am not able to see any prejudice being
caused to the Respondent. On the other hand, as I
have noted, if an injunction is refused, there is every
possibility of irreparable prejudice to Aircon. In my
view, there is not only primafacie case, bu the balance
of convenience also favours the Petitioner.
19. The Award was passed on 25th January, 2017. The learned
Single Judge has rightly dealt with the issue and has reached
reasonable and proper conclusion. We do not find any error or
perversity in the view adopted by the learned Single Judge. In the
facts, we do not notice any prejudice being caused to the appellant. If
the injunction is refused, there is every possibility of irreparable loss
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::
24/24
comap136.17.doc
being caused to the respondent. The respondent has made out a
strong primafacie case and balance of convenience is also in favour of
respondentoriginal petitioner. We, therefore, find no merit in the
Appeal. It stands dismissed. No order as to costs.
(NITIN W. SAMBRE, J) (NARESH H. PATIL, J.)
L.S. Panjwani, P.S.
::: Uploaded on - 02/07/2018 ::: Downloaded on - 03/07/2018 07:29:49 :::