Upper Paunglaung HPP - Completion Report Volume 1
Upper Paunglaung HPP - Completion Report Volume 1
July 2015
www.afconsult.com/switzerland
Volume Index of Completion Report
3.8 Powerhouse
5.1 General
5.1 General
5.2 River Diversion
2.1 Climate
2.2 Topography
2.3 Hydrology
2.4 Geology
2.5 Seismic
Thermal Mass Gradient Report, Main Dam - RCC, January 2009 .........................................Vol. 4
Full Scale Trial Procedures, Main Dam - RCC, October 2009 ...............................................Vol. 5
Design Report, RCC Transportation System, Main Dam - RCC, April 2010
Dam Foundation Treatment - Curtain Grouting Procedure / Specification, September 2010
Special Technical Specifications, Section 3.17: Main Dam Instrumentation, December 2010
Design Report, Main Dam - Block Joint Spacing, Main Dam - RCC, December 2010
Design Report - RCC Dam, Horizontal Thermal Stresses, October 2011
Design Criteria, Main Dam - Design, November 2008_rev. 2011
Specifications and Procedures for Dam Grout & Drainage Curtains, July 2012
Design Report - Main Dam, Reservoir Impounding, November 2012
RCC Dam - Thermal Post-Analysis, December 2013
Construction Design Report for Main Dam, February 2015 .................................................Vol. 6
Main Dam - Report on Additional Instrumentation, February 2015
3.4 Spillway
HMT, Spillway and Bottom Outlet General Specifications Report, October 2007
Hydraulic Design Report, Spillway Structure, January 2009
Report on Hydraulic Model Study of Spillway, August 2009
Design Report, Spillway Chute & Flip Bucket, October 2011
Design Report, Spillway Bridge & Piers, October 2011
Construction Design Report for Spillway, February 2015
Bottom Outlet Structure, Stability and Structural Safety Report, June 2009
Report on Hydraulic Model Study of Bottom Outlet August 2009
Bottom Outlet, Gate Chamber, December 2010
Bottom Outlet, Alternative Gate Chamber Precast Design, June 2011
Bottom Outlet, Gate Chamber Precast Design, June 2011
Bottom Outlet, Structural Design, Access Portal, September 2011
Bottom Outlet, Anchorage of Hydraulic Hoist of Radial Gate
3.7 Penstocks
3.8 Powerhouse
– Design Report, Left Tailrace Channel Wall, D/S of TR 61.75, Preliminary Design, July 2012
– Construction Design Report for Tailrace Channel, February 2015
3.12 Switchyard
4 System Definition
5.1 General
July 2015
www.afconsult.com/switzerland
Impressum
Customer Contractor
Document Information
Project name Upper Paunglaung Hydropower Project
Document title Completion Report
Project number 3853
Name of department Hydro Power
Document path D:\HTTK\UPL\Reports\--- COMPLETION REPORT ---\Chapter 0 - Covers\00 CR Chapter_0_Completion Report Cover Page
2015.07.13 R1.docx
First edition
Approved
Index of revisions
Created Approved
No. Page(s) Date Remark (Initial/Signature) (Initial/Signature)
Distributor
Project Director DHPI Con. 1
Director General DHPI Nay Pyi Taw
February 2015
www.afconsult.com/switzerland
Table of Contents
1 Introduction ....................................................................................................................................... 1
1.1 General
The Project Completion Report (PCR) comprises of sections 1 to 8 as per table of content:
1. Introduction
4. System Definition
9. As built Drawings
All documents compiled in this report have been produced during design and construction of Upper
Paunglaung Hydropower Project.
The compilation of all relevant documents in one set represents together with the AS BUILT Drawings the
reference documentation of UPL HPP.
The basic project design data are given in the Basic Feasibility Report, Colenco Power Engineering (CPE) in
September 2005.
No further complete reports have been produced with respects to Climate, Topography, Hydrology and
Seismicity whereas reports on Geology and Geotechnics were required to define the further design of the
project.
Main Dam. Design Documents for the RCC dam comprise RCC design and technology related documents
and dam design analysis documents. For the dam design analysis itself, the Design Criteria, Stability and
Structural Analysis, Thermal Analysis and RCC dam block spacing report is provided. For the RCC design and
technology documents covering the Full Scale trial and RCC Transportation System are included. The RCC
mix design reports are included in Chapter 5.2. Also included in this subchapter is the design impounding
report.
Spillway. Hydraulic Design Report and Hydraulic Model Test report as well as structural analysis reports are
presented for the ungated Spillway of Upper Paunglaung.
Bottom Outlet. Hydraulic Model Test report and structural analysis reports are included in this subchapter.
All HSS related documents for the bottom outlet are included in Chapter 6.
Power Intake. The Structural Analysis report of the Power Intakes is presented in this subchapter.
Penstocks. The structural analysis of the upper penstock parts and penstock shafts are compiles here. The
open penstock is designed by the HSS contractor and is not part of AF-Colenco design.
Tailrace Channel. A design report which covers design and analysis of the concrete training wall as well as
the erosion protection measures is provided.
The System Definitions present in a concise form the main data relevant to the function and design of the
systems of the project, including main features, structures and equipment. They are devoid of design com-
putations and specification texts and hence particularly facilitate cross referencing and coordination of main
data between the multi-disciplinary aspects of the project and the different Contract Lots.
The System Definition provides the central reference for ensuring key data are available within the multi-
disciplinary design and implementation processes and for the future references.
1. General Systems
4. Mechanical Works
5. Generators
6. Electrical Equipment
7. Auxiliary Systems
8. Switchyard
9. Transmission lines
The updated System Definition June 2008 will be given here, which represents the contract document given
to the HSS/EM Equipment Contractor.
The principle subjects on civil construction works are arranged under the following subtitles.
General. Includes work programs, river diversion programs, construction management and general site visit
reports
Conventional Concrete Works. Includes Method Statements for different civil works, Site Visit Reports of
AF-Colenco Construction Specialists
Roller Compacted Concrete Works. Include Site Visit Reports of the RCC Expert, Dr. M. Dunstan, Notes
prepared during early construction, RCC QC Reports and the first two dam inspection report of the senior
dam design engineer K. Steiger.
The Site Visit reports of AF-Colenco’s Hydraulic Steel Structure Specialist are compiled here, as well as the
HSS review reports.
– The Minutes of Meetings of the major Coordination Meetings with the HSS and EM Equipment Con-
tractor
– …
The Site Photographic Records are compiled in this section. The Reports will only be provide as soft copy.
The CD is attached.
February 2015
www.afconsult.com/switzerland
Table of Contents
In the Project Design data included are Climate, Topography, Hydrology, Geology, Seismicity and Geotech-
nics.
The topographical information did not change for the construction design, therefore no documents are
included in this report.
Climate and Hydrological data recorded on site from 2007 to 2015 will be presented in this chapter.
Detailed geological information has been discovered during the construction period of the project, namely
from the excavation, drilling of consolidation grouting, curtain grouting and drain curtain. Geological and
geotechnical expertise has been provided on regular basis during construction. All the geological and ge-
otechnical reports are provided in this section.
The seismic reports which represents the basic design information for all structural design analysis is pro-
vided in this section.
2.1 Climate
In the Subchapter Climate the Ambient Temperature record, relative Humidity record and rainfall data are
presented which had been measured during the construction period.
2.2 Topography
– Report No. UPL–72-RUM-8.02.06, Survey Mission, 30. January - 3. February 2006, February 2006
Compiled in this subchapter are the following hydrological data measured during construction time.
– The water level plotted against the discharge which presents the tailwater curve
– The reservoir impounding water level and rate of water level rising
– Basic Feasibility Study, Site Visit Report, Mission No. 3, 21.02.- 02.03.2005
– Site Visit Report, Report No. UPL-74-VOB-02.06, 22.01.2006 - 04.02.2006, February 2006
– Mission Report, Report No. UPL-00-VOB/FRH-JAN 09, 27.01.09 - 28.01.09, January 2009
– Limestone Quarry Prospection, Report No. UPL-00-VOB-MAR 09, Mission Report, 18.03.2009, March
2009
2.5 Seismicity
– Preliminary Basic Feasibility Report, Report No. UPL-00-BFR-PREL/0405, Attachment No. 1, Seismic
Hazard Study, April 2005
2.6 Geotechnics
The following geotechnical reports are provide for the UPL Completion Report.
– Mission Report, Report No. UPL-00-FRH/MAY 06, 20.04.2006 - 05.05.2006, May 2006
– Mission report, Report No. UPL-00-FRH/SEPT 07, 24/09/07 – 25/09/07, September 2007
– Mission Report, Report No. UPL-00-FRH/MAY 08, 23.05.2008 - 25.05.2008, May 2008
– Mission Report, Report No. UPL-00-FRH/AUG 08, 05.08.2008 - 15.08.2008, August 2008
– Reconnaissance Geological Prospecting of RCC Aggregate Quarry, Interim Report, 26.02.09 - 27.02.09,
February 2009
– Dam Foundation, Geotechnical Parameters, Report No. UPL-FRH-MAR 2011, March 2011
February 2015
www.afconsult.com/switzerland
Table of Contents
2.1 Climate
2.1.1 General
The climatic characteristics of the country are dominated by the monsoon. The southwest monsoon blowing
form the Indian Ocean feeds wet air and produces the rainy season from May to October. The northeast
monsoon prevails during the dry season form end of October to May.
The dry season can be divided into the cooler winter season with little rain from October to February and
the hot summer season from March to May.
Tropical cyclones may occur at the time when the monsoon changes the direction. According to records,
cyclones hit the country mostly in November.
The nearest meteorological station in the West of the catchment area is located in Pyinmana. The average
manual rainfall in Pyinmana is 1328mm/year and is quite variable. The months from November to May often
have no rainfall at all. The average annual daily temperature is 26.8°C, with a maximum of 31°C in April and
a minimum of 22.3°C in January. The relative humidity is usually low during the January to March period
under 60%, the lowest value of 45% occurring in March. The average number of sunshine hours exceeds
eight per day between November and April, and is only about five per day during the rainy season, with
figures varying significantly from year to year.
The Ambient Temperature record measured at UPL Construction Site between 2008 and 2015 is shown in
the following Figure 2-1. The relative Humidity is shown in Figure 2-2.
Figure 2-2: Relative Humidity measured at 6:00, 10:00, 12:00, 14:00 and 18:00 hours
February 2015
6605 -Contens-
UPL Hydropower Project Survey Mission Report
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
February 2006
List of Contents
1 Introduction....................................................................................................... 1
3 Mission Program............................................................................................... 1
4 Survey Instruments........................................................................................... 2
11 Recommendation.............................................................................................. 5
11.1 Determination of DHP high accurate Points...........................................................5
11.2 Checking or setting out Axis Points or Shuttering ..................................................5
11.3 Contourline Measurement......................................................................................6
11.4 Survey Equipment..................................................................................................7
Annex
Annex 1: Differences existing to adjusted Coordinates and Elevation
(Extent of LTOP-Program)
1 Introduction
The construction of the Upper Paung Lang Hydro Power Project has started in 2005.
Therefore it was necessary to install a Triangulation Network, which covers the entire
Construction site. The following Points were found on the site:BM1, BM2, BM-5. DHP
installed five new Survey monuments as advised by CPE, TRP 1 – TRP 5.
It was decided that the Survey-Expert has to check the remaining and new Triangulation
Points on UPL-site. It was also decided that during this Survey mission, the Survey staff of
the Department of Hydroelectric Power (DHP) should be advised in their further surveying
procedures and full use of the survey equipment, including survey software installed on
their theodolites and adjustment software.
The present report summarizes the activities and findings during the mission of the Survey
Expert.
3 Mission Program
Survey Mission of Peter Rumpf, Colenco’s Associated company, Straub Consulting
Engineers Baden, Switzerland, from 30. January to 3. February 2006.
To find out how the Survey staff from DHP are carrying out the measurements and
calculations and to assist in establishing triangulation point measurements and calcula-
tions of coordinates and elevations, the following program of activities was carried out::
• Overview of Survey instruments and Material from DHP
• Checking condition of Survey instruments
• Software an Programs used for Calculations inside and outside the Office
• How Measurements are carried out.
• Triangulation measurement.
• Calculation of adjusted Coordinates
• Training Survey staff in Using Instrument- and Calculating-Programs
• Training Survey staff in making contour line measurements
• Visit to SUNTAC LTD in Yangon
4 Survey Instruments
The following Instruments and Survey equipment were available for use:
Instrument ore
Angular Accuracy Distance Accuracy
Equipment Type
DHP 1 ZEISS TR 3305 5“ 5mm ±3ppm
1 Zeiss Reflector
axial
2 WILD Reflectors
coaxial
2 Metal tripods
1 Prism holder
The Fixation screw of the horizontal angle at Theodolite does not work properly.
Distance
error
Axial
Theodoli-
t
7 Triangulation Measurement
The measurements carried out were not according to the standard practice, because of
the lack of reflectors. Each point has to be measured in II(both) faces before moving from
one point to the other. A lot of time is required to complete the measurements. First item
to be addressed was to find out which of the 3 remaining Survey points fit together. The
difference in the distance between BM1 and BM2 (119m) was found to be 5cm. The
difference in the distance between BM1 and BM5 (458m) was found to be 3cm. It was
decided to use the Bases BM1 and BM5 to connect the entire grid.
BM 1 BM 5
BM 2 is during rainy season not accessible. The fixation screw (between Pillarplate and
Tribratch) on Pillar TRP 3 is not permanently installed.
The raw data was measured, that means ppm (pars per million) was set on 0.0. The
advantage of this procedure is to be able to better understand the calculations right from
the beginning.
8 Coordinate Adjustment
After finishing measurements, Horizontal and vertical Angles and Distances have been
averaged and reduced by applying temperature and pressure to the distances and
transferred into the Adjustment program (LTOP).
To get a network free of errors, the following procedures has been applied:
• Coordinate input from the coordinate lists (see Chapter 2)
• Point BM1 and the Bearing to BM5 have been considered as fixed in horizontal
coordinates, BM 1and BM5 in the elevation.
• 1. Run will show the differences to the used coordinate list (Annex No1.)
• The adjusted coordinates are going to be applied in the program
• 2. Run, Final Coordinates with no discrepancies are given (Capture 9)
X Y E
Point Nr.
Eastings Northings Elevation
BM 1 247935.118 2186183.630 289.313
BM 2 248037.776 2186122.805 287.192
BM 5 247725.179 2186641.897 290.115
TRP 502 248031.274 2185749.768 442.452
TRP 503 247576.387 2186024.928 456.052
TRP 504 248070.654 2186413.356 383.862
TRP 505 248385.693 2186267.911 426.998
DAM Axis 101 left
248154.004 2185791.475 408.833
Bank
11 Recommendation
11.1 Determination of DHP high accurate Points
If DHP is going to determine new high order accuracy Points, the best accuracy possible
with the available instruments can be achieved for this by setting their instrument
directly on the new Point, using the Unknown Station program to get the coordinates and
elevation. Target minimum 3 adjusted Survey Points.
If they have to check other accurate points, put up their Instrument as close as possible to
this point, but of course not closer than 3m, so that they can see other points which are
already determined and adjusted.
8
2
7
6
3 5
Breakline
7/04/10 – 09/04/10
APRIL 2010
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 1
1 INTRODUCTION
The construction of the important structures of Upper Paunglaung Hydropower Project (UPL)
started in 2009. The condition and accuracy of the survey net at UPL weren't satisfactory to
start with the construction of RCC dam, PH and Bottom Outlet. Also the education of the local
survey staff should be improved in using Instrument software, setting out of axis and check of
concrete shuttering.
There for it was decided that the specialist for geodetic survey, P. Rumpf (CPE) should visit the
UPL site to fulfil the following tasks:
3 PROGRAM
1.4.10 Travel to Yangon
4.4.10 Set out and find old pillars, search new location for relocation
points, set measurements
6.4.10 Meeting with Stuart Cowie, travel to Nay Pyi Taw, meeting DG
8.4.10 Training local survey staff in using intersection and known station
program, check coordinates and elevation of separation wall,
check BM NRD1, set out penstock axis,
4 SURVEY EQUIPMENT
The following survey equipment was used from DHP to execute measurements for construction
site:
- Set up
- Known station
- Multiple point resection
- Reference Line
- Stake out
4.2 TRIPODS
3 metal tripods
4.3 REFLECTORS
reflector holders
tribraches
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 3
The use of the shown reflector holder is tricky, because of the height reading, 10 cm has to be
added to get the real reflector height. If this additional constant is not considered, the measured
elevation will be 10cm to high.
The survey equipment is in good condition and will fulfil the requirements of executing
measurements like setting out. The amount of reflectors should be increased to be able to
accelerate the measurements up to 6 reflectors.
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 4
5 SURVEY NET
BM –NRD 01
TRP - 504
TRP - 503
The view to the site was limited trough houses, bushes or the terrain.
View from pillar 504 to the site View from pillar 505 to the site
The pillar condition, the locations and therefore the survey net is not satisfactory.
TRP – 501 should not be used anymore TRP - 503 is in good condition but not stable
because:
- Too far from site - The view to the site is covered by a house
- The view from site to this pillar often not clear
- Not stable
TRP - 505
TRP - 504 good conditions - centre screw is missing
- View to the site after clearing ok - too much trees and bushes cover the view to
the site
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 6
The net situation for a dam site of this size was not satisfactory. The existing pillars did not fit
together anymore, because they were moving slightly down the hills, because execution of
enormous excavations. The view from the pillars to the site was very limited, because new built
up houses, bushes and the existing terrain. The only stable area, at the moment, to install new
survey points is on top of the separation wall.
To improve the survey net, the following program was carried out:
- Set measurements on the remaining pillars (Chap 6.1)
- Adjustment of the new survey net (Chap 6.2)
- Determination of new survey points SPW3, SPW3, TP3 (Chap 6.3.1 und 6.3.3)
TRP – 505
SPW 2 SPW 3
999
TP3
TRP – 504
TRP 503
The new calculated survey points can be used for set out measurement (accuracy of ±2-3cm).
SPW 2 SPW 3
TP3
No relocation points have been used until March 2010 because it's difficult to find stabel aereas
to install new points.
To test, if the remaining pillars fit together, set measurements has been executed by DHP staff
conducted by Peter Rumpf, using the available DHP Totalstation NPL 362 on pillar TRP 503
with target TRP 5044 and TRP 505.
The following settings were used: zenith
0.0 gon
- GON
- PPM = 00
- vertical angle zenith, clock wise 100.0 gon = horizon
3 sets have been measured. These measurements were used to adjust new coordinates with
the intention to have as small as possible differences in E, N, E.
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 8
E N E Remarks
TRP - 503 247'576.387 2'186'024.928 456.052
TRP – 503 247'576.396 2'186'024.931 455.924
Δ 0.009 0.003 -0.128
Legend:
02.2006 Survey Mission 2006
07.04.2010 Kyaw Tint
07.04.2010 Adjustment RUM
The coordinates have been adjusted by Peter Rumpf, using the adjustment program "LTOP".
The position of the remaining two pillars has changed by maximum 1.6 cm. The differences in
elevation are bigger. The elevation error from BM – NRD 01 can be caused trough the tricky
prism holder (Chap 4.4). And the pillars could have been moved down because the enormous
excavations. The later checked separation wall (Chap. 6.2.2) shows, that the adjusted elevation
fits together with the theoretical elevation on top of separation wall. The position of the
separation wall is twisted 28 cm in direction to the river on the upstream side and 8 cmin
direction to the river on the downstream side. The differences are not resulting from the shifted
pillars.
To train DHP staff in using Totalstation programs, to determine a temporary new point (999)
closer to the site on left bank and to check the position of the separation wall, different programs
were used.
The sub program from setup "multiple point resection" was trained using the new adjusted
coordinates from points TRP 503 and TRP 504 to get the coordinates of point 999:
E N E Remarks
999 248'090.055 2'185'834.931 377.591 Elevation on top of wooden peg
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 9
If the "multiple point resection" program is used, be aware, that the shown
elevation on the Totalstation display is identical with the axis of the
Totalstation and not with the elevation top of the bottom point.
Axis of Totalstation
The reason is, the program does not ask for Instrument high.
To check the position of the separation wall, the program "reference line" was executed, from
Station 999.
To prepare survey points close to the site, 3 steel sticks (TP3, SPW2, SPW1) were determined
on the separation wall using stabilized prism holder with bamboo sticks.
7 RECOMMENDATION
Set out mesurments or axis and shutterings checking (accurycy ±2 -3 cm) can be executed from
survey points on separation wall using the setup programms "knonwn station" and " multiple
point resection":
- known station
Set up instrument on one of the tree points on the separation wall and us one of the points for
orientation which is further away.
The longer the construction works are continuing, the more accuracy is required.
(For exaple to set out axis for steel structures).
The existing three points SPW2, SPW3, TP3 have to be determained with higher accuracy.
Use tripods (not prismholder) on SPW3, TP3 and 999. Don't remove tripods between instrument
setup on from one to the other station.
- Setup instrument SPW3
- Tragets TRP4, SPW2, TP3, 999
As soon as the dam constructions reaches the dam crest, the survey net has to be adapted to
execute dam monitoring deformation measurements (Chap. 7.3).
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 11
that the whole monitoring system is in good condition and the network is stable and
relayed on relocation points.
that the measurements are executed by the same experienced survey team, with
instruments of the same high accuracy (TCA2003).
to present the deformation results in a quick and easy readable graph (see example
annex 3)
The established survey net to execute dam deformation measurements is not satisfactory. To
improve the situation sustainable 4 or 5 relocation points (600 – 604) and three pillars (TRP 700
-702 have to be installed.
At this time it's too early to decide the exact position of all new pillars and to find enough stable
position for relocation points.
At the moment the position of one new pillar and two relocation points has been defined.
It's not important, if the two pillars (700 and 701) are not absolutely stable between two
measurement periods. The existing pillars TRP 503, TRP504 and TRP505 ca not be used as
relocation points, because they are not stable. They can only be used to connect the existing
old survey net to the new deformation net.
TRP 701
TRP 702
TRP 503
604 603
600
TRP 700
601
602
TRP 505
TRP 504
New pillars
It's important that the DOP are easily accessible and that reflectors can be mounted easily. It's
recommended to install the DOP vertical on top of the dam crest on stable elements. It's
important that the crest elements are stable connected to the dam crest concrete.
DOP
TRP 700
TRP 701
604
602
603
TRP 702
601
600
Upper Paung Laung Hydropower Project
Site Visit P. Rumpf - 7.04.10 - 9.04.10 14
The following survey equipment is recommended to carry out deformation measurements. This
equipment exists on YEYWA Hydropower Project. It's recommended, that the same survey
group from DHPI (U Kyi Thein (surveyor), U Nay Myo Aung (staff officer) and crew) will execute
the deformation measurements.
According to DHPI, this survey group has to hand over the survey equipment and their
knowledge at the beginning of 2011 to HPGE (Hydro Power Generator Enterprise).
8 -16 reflectors
1 barometer 1 thermometer
If this equipment has to be transported to another site, the Totalstation must be protected in the
portable case whit foam material an fixed inside the car on the back seat. Before starting
measurements, the following check have to be done:
7.6 0 - MEASUREMENT
When the new survey net is installed, a 0-measurement must be executed. We suggest a
procedure with two following advantages because there are only a limited number of reflectors
available.
Advantages:
no programm has to be installed on Totalstation
only one adpter (seriel /USB) for data download is required
- Determination of approximate global coordinates and elevation of pillars, relocation points and
dam observation points (accuracy only ±1m). This has to be done only ones before the
0-measurment. Use pillars TRP 3 – 5 and coordinate list (annex 4).
- Create a new user template "SET OF ANGEL" on Totalstation TCA2003 (annex 5, chap 1)
- Execute set measurements (annex 5, chap 2.1)
- Data download over serial data interface cable and LGO free software
http://www.leica-geosystems.com/en/page_catalog.htm?cid=5111
- Transmit data to a specialist
Set measurements
General procedure for set measurement at UPL:
Use umbrella to protect the Totalstation and more important the triput.
Important, filling out readable all information on set protocol (Annex 2) as:
- Temperature
- Air pressure
- Instrument name
- Station No. and hight
- Observer name
- Date
- GON
- PPM = 00
Measuring 4 sets
Adjustement in Switzerland
[email protected]
0041 56 483 02 32
Baden, 25. April 2010
1
Instr. Name Observer Page
Set-Protokol Job Name Date
Weather Pressure mmHg/mbar Temp. C°
Stat. No. I. Face II. Face Average Reduced Total V V' VV Slope Distance Distance Target
Station Hight Target No. gon gon Average Average + - + - m mm mm mm Average Higth
Annex 2
O:\O003_sbd\01 Admin\Vorlagen\Formulare\Stationsprot.xls
Annex 3
Annex 4
Adjust Date of
Point No. ment E N E Determination Type Remarks
TRP1 - don't use
BM-NRD 01 - 370.295 8.4.2010 Iron in Concrete don't use
TRP 3 3 247576.396 2186024.931 455.924 8.4.2010 Pillar
TRP 4 4 248070.643 2186413.341 383.710 8.4.2010 Pillar
TRP 5 5 248423.560 2186325.260 456.722 8.4.2010 Pillar
999 999 248090.055 2185834.931 377.591 8.4.2010 Wodden stick check alwais
SPW 1 from 999 248206.34 2186013.67 295.25 8.4.2011 Iron in Concrete determained from 999
SPW 2 from999 248212.46 2186025.18 295.32 8.4.2012 Iron in Concrete determained from 999
TP 3 from 999 248120.11 2186059.66 290.81 8.4.2013 Iron in Concrete determained from 999
The reason because SPW 1, SPW 2, TP 3 in [cm], because measured by handhold Reflectorstick
SPW 2
TP3 SPW 1
Main Menu
Conf (F3)
User template
SET (F4)
CE
SET OF ANGEL
Cont
Changes in List (F4)
Language: English
REC format: GSI8
Distance: Meter 4 Dec
Angles 400 gon 4 Dec
Temperature °C
Atm. Press.: mbar/hpa
Coord. Display: Easting/Northing
Hz-system : Clockwise +
Face I: V-drive left
SET (F4)
F2 (RMASK)
2. word 21 HZ
3. word 22 V
6 – 12 has to be empty
CONT OK
1
6605
UPL Hydropower Project Annex 5
2. In the field
Set up Totalstation on pillar 700, adapt instrument during 10 minutes to the temperature.
Set up reflectors on pillar 701, 702, relocation points 600 – 604 and DOP 1 and 2
2
6605
UPL Hydropower Project Annex 5
- Calibration (CAL) F2
(Manual page
176 - )
Use a point whit vertical angel I face between 90 and 110 gon
aF…
- ATR on (F1)
- MEAS
-Target (F4)
3
6605
UPL Hydropower Project Annex 5
- Code
Info 1 Station No.
Info 2 Instr. Hight in [mm]
Info 3 Temperature in °C
Info 4 Air pressure in bar or hpasc
REC
Face I
Point no. 600
Target hight 0.000
All (F1)
Face II
Point no. 600 or shift "last"
Target hight 0.000
All (F1)
4
6605
UPL Hydropower Project Annex 5
3. In the office
Download File 01 over free Leica-geo-office software and serial data interface cable
(Adapter Serial / USB will be provided)
http://www.leica-geosystems.com/en/page_catalog.htm?cid=5111
Adjustement in Switzerland
[email protected]
0041 56 483 02 32
Baden, 25. Mai 2010
5
Intrumentname T CA2 0 0 3 Observer P E T E R Page 0 1
Station-Protocol Jobname Date 2 3 . 0 5 . 1 1 Target-Nr. TH
7 0 1 0 2 3 3
Station 7 0 0 7 0 2 0 2 3 2
IH 0 2 3 4 R E 6 0 0 0 0 0 0
°C 4 1 R E 6 0 1 0 0 0 0
mbar 7 2 3 R E 6 0 2 0 0 0 0
Time R E 6 0 3 0 0 0 0
R E 6 1 4 0 0 0 0
Station D O P 1 - 26 0 0 0 0
IH
°C
mbar
Time
7 0 0 0 2 3 4
Station 7 0 1 7 2 2 0 2 3 2
IH 2 3 3 R E 6 0 0 0 0 0 0
°C 4 3 R E 6 0 1 0 0 0 0
mbar 7 2 4 R E 6 0 2 0 0 0 0
Time R E 6 0 3 0 0 0 0
R E 6 0 4 0 0 0 0
Station D O P 1 - 26 0 0 0 0
IH
°C
mbar
Time
Station
IH
°C
mbar
Time
Station
IH
Annex 6
°C
mbar
Time
O:\O003_sbd\01 Admin\Vorlagen\Formulare\Stationsprot.xls
THE REPUBLIC OF THE UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROPOWER IMPLEMENTATION
GEOETIC SURVEY
Measurement M0
August 2014
AF-Colenco Ltd
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 i/32
Document path
Index of revisions
Created Approved
No. Page(s) Date Remark
(Initial/Signature) (Initial/Signature)
1
Table of Contents
Page
1 Introduction .................................................................................................................................... 5
8 Result ............................................................................................................................................... 21
8.1 Consideration regarding the Theory of Errors .................................................................. 21
8.2 Coordinates and Ellipse Errors................................................................................................ 21
8.3 Base Coordinate and Orientation .......................................................................................... 22
8.4 Adjusted Coordinate List M0 .................................................................................................. 22
8.5 Coordinate Ellipses Error .......................................................................................................... 24
8.6 Network Plot ................................................................................................................................. 26
Appendixes
1 Introduction
The UPL Hydropower RCC-dam has been completed at the beginning of 2014.
Impounding has been started begin of July 2014. For safety reasons and to observe the
movements of the RCC-Dam it was decided to undertake dam deformation
measurements periodically.
This report deals therefore with the interpretation of the measurements M0.
2 Explanation of Terms
Dam Observation Point (DOP): Point to determine the dam deformation in east and
north direction and in elevation.
Relocation Point (REP): Stable points which are used to determine the
coordinate and elevation of survey pillars and DOP's.
Telescope staff
Invar staff
Tribrach
25.07.14 Set measurement on pillar 600, recognition of new levelling REP’s, teaching
levelling instrument check and adjustment.
30.07.14 Re-installing levelling relocation point right bank, levelling right bank,
STARNET adjustment training for DHP
Parallel-plate micrometre
GPM3 GPM3, in container, measuring 1 For level instrument
range 10mm
4.2 Laptop
To run the STARNET adjustment program a Lenovo Laptop with the following
performance was ordered and delivered on UPL side:
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 9/32
It’s difficult to find stable relocation points on UPL Dam side, which have many visual
connections that are accessible in a short time. From today’s view on, 5 points seems
to be stable (603,701 – 703,705). The stability of these points can be examined after a
few follow-up measurements. If future measurements indicate that there aren’t enough
stable REP’s, additional pillars must be installed.
In general, REP’s should be established outside around the unstable observation pillars
601 and 602, because error ellipse can be improved. The survey pillars which are
equipped with ground plate had to be improved by installing a screw to measure the
Instrument or target height at a clearly defined point. All survey points where first
temporary labelled with point numbers to prevent point mix-up during the zero
measurement M0.
Levelling relocation points had to be installed on stable areas left and right bank (801 –
810). These points must be labelled and protected permanently.
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 10/32
Stability from
Point No. Type Shaping Remarks
today’s view
Rusty/little visual
503 Pillar Ground plate Not stable
connection
Dam
10 - 271 observation Reflector stick
point
6 Instrument Training
No body of the participating surveyors had knowledge neither using the delivered Total
station Leica TM30 nor the levelling instrument Leica NAK2. Before starting the
measurements, the handling with these instruments was exercised first in the office and
then applied directly while executing measurement M0.
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 11/32
The following general settings of the instrument where checked, tuned and saved in the
config set file named UPL:
Unit & Formats
Hot keys
Start up
The system Ram file was stored on computer flash card (CF-Card) and on Lenovo
Laptop on path C:\Users\user\Documents\Leica\system.ram.
2 Programs
2 Setup
Job 140725
Config Set UPL
F1 Cont
Method Known BS Point
Station coordinate Frm Fixpoint job
Fixpoint job UPLFIXADJ
Station ID 601
Instrument Ht. 0.237
F5 PPM
Temperature 30.0 C
Atm pressure 962 hpa
Cont
Check if ATR is on
DIST
SET ok
2 Programs
3 Set of angles
Fix point job: UPLFIXPADJ (CF-Card)
Job 140728
Cont
3 Measure sets
No. Of sets 2
Cont
On pillar 600, 601 and 602 three sets of set measurements where executed. Station
protocol was filed out on each Pillar.
Main Menu
4 Convert
After a longer period of storage or transport, always check the instrument before
starting the measurements!
Chose a flat terrain between 45 and 60 m. Divide the distance in three equal
sections.
Mark the instrument location and use two levelling staff shoes ore install two nails
that stick clearly out of the surrounding subsoil.
The new delivered level instrument NAK2 had an error in line of sight of 3 mm before
adjusting. This error could be adjusted to an error of 0.8 mm.
6.3.4 Barometer
Once some elevation relocation points where installed (501 – 505 right bank, 506 – 510
left bank) the following level lops has been executed:
Pillar 601 – REP 810 – Dam crest points 1010 – 1270 – REP 805 – 602
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 17/32
A level loop difference of 0.3 mm between pillars 601 – 602 was achieved after some
re-measurements.
The outgoing elevation for M0, received from Kyaw Ko Ko, is Pillar 601 = 387.846
MASL. All levelling REP (801 – 810) and DOP (1010 – 1270) are connected to this
elevation. The elevations of M0 are listed in appendix 3.
Leica DBX-File has to be transfer using the delivered ”Leica DBX to Star*Net Converter
v7.2.2.7” which was unfortunately Key protected.
Once the license is accepted, you have to Input the DBX project path to select the used
Jobs in the field.
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 18/32
7.2 Adjustment
C:\Users\user\Documents\MicroSurvey\StarNet\UPL\M0
adjusted
Add the measurement file
Change all code C to # in the measurement files
After running the adjustment, the result must be investigated very careful.
Go to View
Output and searching for error messages or marked lines with * (STAR) in the folder
Listings in the following chapter:
Adjusted angle observations
Adjusted distance observations
Adjusted zenith observations
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 20/32
Reduce the accuracy of the horizontal and vertical angle ore the distance, in the
measurement files (see below) until no * will appear.
In the below example the accuracy of the slope distance was set on 2 mm.
M 600-602-601 48.16169 388.487 105.06885 1 .002 1 0.237/0.167
In the below example the accuracy of the horizontal angle was set on 2Gon.
M 600-602-201 11.32187 611.372 110.35106 2 .001 1 0.237/0.000
In the below example the accuracy of the vertical angle was set on 3Gon.
M 601-602-600 291.1386 388.47 94.9553 1 .001 3 0.241/0.178
If you find a (*) in the measurement file, it’s possible that this point, who presumed to
be fix, was moving. Remove the (!!!) behind the coordinates and run the adjustment
again and compare the new adjusted coordinates with the coordinates of MO. If the
movement is in a logical direction, this indicates the point is moving. If not it might be
an error in the measurement.
If a pillar is moving only in elevation, you can let the elevation be floated. The elevation
will be new calculated.
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 21/32
8 Result
The average accuracy of the coordinates can be calculated out of the adjusted
coordinate and the rectification of the observation. On the base of a mean error and
the network disposition, the mean error of ellipse can be determined and plotted in:
Large semi-axis = MFA
Small semi-axis = MFB
The coordinates and the ellipse error of the measurement M0 are listed in chapt.8.3 and
8.4. The achieved ellipse errors m3 are listed in column:
MFA = semi-major-axis and azimuth (AZI)
MFB = semi-minor-axis
MFE = error bar in elevation
The averaged standard error (confidence level 99.7 %) of achieved ellipse error are
listed below:
To get a good overview of the achieved accuracy of the adjustment, regard the yellow
marked errors in the list “UPLM0Adjusted.lst”.
The whole free constrained network is based on the coordinate of pillar 601
N=185886.5329 E=248000.2091 E=387.8460 and the bearing to pillar 602 =
47.5065 Gon.
The coordinate and the elevation received from DHP chief surveyor Kyaw Ko Ko. The
scale factor is 1.000000.
Point No.
N E Elevation
Total station
Point No.
N E Elevation
Total station
Point No.
N E Elevation
Total station
24.07.2014 328.7
M0 174.3
25.07.2014 330.0
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 27/32
10.1 Conclusion
The 10 days survey mission program could be performed successfully. The delivered
survey equipment is in good condition. The delivered Laptop including the adjustment
program STAR*NET worked properly. The key for the STAR*NET converter has do be
delivered or purchased. Most of the survey net was installed satisfactory. Only a few
improvements had to be realised, in installing some levelling REP’s. The achieved
accuracy during measurement M0 was:
MFA = ± 3 mm
MFB = ± 2 mm Set measurement
MFE = ± 5 mm
MFE = ± 0.8 mm Precision levelling
It’s obvious the levelling accuracy in elevation is much better. If this persists in the
future depends on the condition of the levelling staff.
If the chosen REP’s are stable will be shown after the next few measurements. If the
instructed adjustment program was understood completely, will be shown in the future.
Any way, after the training, no more questions emerged.
10.2 Recommendation
1. Levelling Rep’s and DOP’s must be labelled and protected permanently (see
appendix 1)
3. Repeat the deformation measurements every month with the experienced survey
group.
4. Check and adjust the levelling instrument before starting the measurements
8. If future measurements indicates that there aren’t enough stable REP’s, additional
pillars must be installed
UPL HYDROPOWER PROJECT
GEODETIC SURVEY REPORT M0
RUP – 10.08.2014 28/32
9. Make photos of REP and DOP inclusive caps and labels and implement it in the
survey report.
Thank you very much for the cooperation during instrument and software training and
the executed measurements. I’m looking forward to achieve highest accurate results
and implementation of the recommendations.
February 2015
www.afconsult.com/switzerland
Table of Contents
2.3 Hydrology
The water level was measured during the Construction period, as shown in the following Figure 2-1.
The reservoir level had been recorded during impounding period and is presented in Figure 2-4.
The reservoir water level rising rate in meter is presented in the following Figure 2-5.
February 2015
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
BASIC FEASIBILITY STUDY
ONDREJ VOBORNY
SENIOR GEOLOGIST
Upper Paunglaung HPP 1
Site Visit No. 3, Feb-March 2005
List of Contents
1 INTRODUCTION .................................................................................................2
1.1 GENERAL ........................................................................................................... 2
1.2 PROGRAM OF THE VISIT ................................................................................. 2
1.3 LIST OF PARTICIPANTS ................................................................................... 3
3 FINDINGS............................................................................................................4
3.1 TOPOGRAPHY................................................................................................... 4
3.2 GEOLOGY, DAM FOUNDATION ....................................................................... 5
3.3 CONSTRUCTION MATERIALS .......................................................................... 6
ANNEX 1: Photos showing the Right and Left Abutment of Dam Axis C1.5
1 INTRODUCTION
1.1 GENERAL
Following the Mission No. 2 in November 2004, launching the preparation of the Basic
Feasibility Study, Colenco’s UPL project geologist has conducted a 3rd visit to the UPL
dam site with the primary objective to review and collect the actual geological and to-
pographical information available from the ongoing investigations and survey. The lo-
gistics of the site trip were very well organized by the DHP team. The UPL dam site is
now accessible in less than 3 hours from PL along the new access road, presently un-
der construction by DHP and Olympic. However, under the present condition the road
is only viable in the dry season due to very steep gradients negotiating the difficult to-
pography. Since last November, a very substantial progress of works has been
achieved at the UPL dam site in terms of clearing, benching, local access roads and
camp facilities. Vehicle access is available at both abutments between the C1 and C2
dam sites, using a temporary bridge made of tree logs at the C2 camp site. Extensive
benching was completed at both abutments of C1.5, providing access to the top abut-
ments, previously concealed by dense vegetation.
23.02.2005 Field trip to UPL site along the access road, afternoon inspection
of the left abutment C1.5 and upstream area (C1 axis and quarry
site), overnight at camp site
24.02.2005 Site inspection right abutment C1.5 and C1 axis, inspection of core
boxes, 14:30 departure from site to Paunglaung HPP
2.4 TOPOGRAPHY
The terrestrial 1:5’000 map of the dam site area as requested in November 04 was still
under preparation by DHP during the site visit.
RECEIVED: A copy of the DHP 1:5’000 map in Yangon in “last minute” before depar-
ture on 1. March 05. The 1-m contour lines of the map are drawn (and interpolated?) by
hand, digital format is not available. A first visual check of this map has revealed some
evident inaccuracies, especially on the right bank, which where notified to the present
DHP engineers from design Branch for verification.
2.5 HYDROLOGY
No additional information received
3 FINDINGS
3.1 TOPOGRAPHY
The enlarged map 1:10’000, produced by SUNTEC from the 1:50’000 photogrammetric
map, provides a general indication of the overall topography, good for preliminary con-
siderations regarding the site selection and basic layout. It was well known that the
photogrammetric map is inaccurate in the river valleys and abutments, and does not
provide detailed information as required for dam alignment studies and layout optimiza-
tions. In a first step, the preparation of a 1:5’000 terrestrial mapping of the larger dam
area was requested. However, this map seems to be inaccurate in several areas (see
above) and does not allow a proper selection of the dam axis that would be consistent
with the field observations.
Besides a revised 1:5’000 map of the general project area, it will be mandatory for the
forthcoming project design to establish a reliable topographical mapping at 1:1’000
scale covering the dam site and appurtenant structures.
After the completed bush clearing at both river abutments it is evident that the topogra-
phy at the C1.5 site is more complex than previously assumed, given that the irregular
erosional relief was concealed by vegetation. In particular the upstream side of the right
abutment (RA) is dissected by a deep and branched erosion gully. The extent of this
feature affecting the upper portion of the abutment was not evident from the river bank
during the earlier visits. The left abutment is sharply limited by a deep valley with a
tributary stream (known before), and also by branched erosion features on the up-
stream side. Hence, the topographic constraints for setting out the dam axis are more
severe than previously expected on the basis of visual impression and the available
photogrammetric map. The suitable location for the dam axis is physically limited by the
deep tributary downstream valley at LA (critical for dam stability against sliding!) and by
the upstream gully on RA (not critical), see Annex 1.
The dam axis actually set out in the field by DHP does not follow the alignment recom-
mended during the November 04 site visit. For some reason, it has been rotated by
some 15˚ and runs across the upstream gullies of RA and over the shoulder of the
deep downstream gully on LA, resulting in a longer dam crest and larger dam volume
than the optimum alignment (Annex 1, red alignment).
The C1 dam axis, considered as 2nd priority after November 04, has also topographic
constraints on both abutments. The axis alignment as set out in the field has been also
rotated and intersects the right abutment at its downstream slope.
Conclusions Topography:
(1) On site, the dam axis has been moved “back to its place” based on visual judge-
ment. Due to lack of reference points, the selected axis alignment has to be con-
firmed (and eventually adjusted) by topographic survey, in particular with respect
to the orientation of the powerhouse and tailrace axis.
(2) The mandatory criteria for setting out the correct dam axis on site are: i) maxi-
mum possible clearance of the left abutment to the downstream valley; ii) the re-
sulting bearing of the powerhouse axis (perpendicular to the dam axis) shall be
oriented such as not to point into the hill slope, and iii) avoiding the upstream gul-
lies on the right bank, if necessary by introducing a “kink” pointing in downstream
direction into the upper part of the right abutment. Hence, the bearing (azimuth)
of the dam alignment should be approximately N60-55˚E (to be checked by sur-
vey), eventually introducing a kink in the right wing.
(3) The terrestrial topographic map elaborated by DHP at 1:5’000 scale and deliv-
ered to CPE just before departure is of limited accuracy only. The interpolation of
the survey points (obtained by total stations) was obviously performed by hand,
and at least in some areas does not reflect the “real” topographic conditions. This
is in particular the case for the right dam abutment where the existing morphol-
ogic features such as the broad abutment face toward the river and the upstream
gullies are not adequately represented.
(4) Therefore, it is concluded that the actual version of the 1:5’000 map cannot be
used for the ongoing Feasibility Study design studies that will be completed on
the basis of enlarged SUNTEC map. For further design studies, including a
proper definition of the dam axis, diversion tunnel portals and other structures, a
revised digital map at 1:5’000 and a new 1:1’000 map will be required!
The geological information from subsoil investigations obtained during the site visit was
rather limited, given that the core drillings were still in execution and the results of geo-
physical survey, Lugeon testing and laboratory tests were not available yet.
C1.5 Dam Axis: So far, the fresh bedrock can be confirmed as sandstone and siltstone
of good quality, the only critical parameter -so far- being the thickness of overburden in
the abutments. The borehole BH-07 at the left river bank shows only 1.5m thick allu-
D:\Reports\UPL\UPL Doc\Reports\VOB UPL_Site visit3_rep.doc March 2005
Upper Paunglaung HPP 6
Site Visit No. 3, Feb-March 2005
Quarry location: The status of knowledge regarding the location of prospective quarry
is still very limited. According the present understanding, the suitable location for a
quarry is considered to be on the left bank of the Small Paunglaung River upstream of
the confluence, rather than between the two streams (requiring a bridge). Further field
reconnaissance including mapping of outcrops and sampling/testing is required to con-
firm the availability of granitic rocks. The petrographic analysis of a sample marked as
Q1 (location?) has indicated a quartz-biotite schists which is not deemed a favourable
material for RCC aggregates.
A drilling at the existing outcrop near to the confluence has been recommended (ac-
cess available). No potential quarry candidates have been identified so far along the
new access road in the downstream area of the dam. Virtually all road cuts are located
in weathered sandstone/shales.
River alluvions: The only significant deposit of river gravel is available in the delta of
the lateral stream downstream of the left abutment of C1.5 site. The gravel, cobbles
and blocks are presently being exploited manually by DHP as source for CVC aggre-
gates and masonry structures. River sand is available in abundance as river flood de-
posits covering the terraces, but most likely not suitable for fine aggregates due to fine-
ness.
Low permeable core material for coffer dams: readily available on both abutments
of the dam site as product of in-situ weathering of rock: reddish residual clay, silt, sand
and gravel.
Conclusions Geology: As the site investigations are still ongoing, the present status
of information is insufficient to allow a conclusive judgement on the foundation condi-
tions.
The main issues to clarify are:
Depth of excavation (thickness of overburden and weathered rock) in the abutment
slopes (boreholes correlated with geophysical profiling)
Bedrock permeability (results of Lugeon tests in boreholes)
Rock strength (testing on rock samples, UCS, density and water absorption)
Availability of quarried rock for RCC aggregates: location and extent of quarry,
properties and reserves (mapping, core drilling and testing required, see below)
As a general practice for concrete gravity dams of the height such as the UPL project,
exploratory adits in the abutments are usual. Such will be required in the next design
stage.
1. Set out dam axis at the site as indicated during site visit. Check by topo survey
required, also regarding the correct alignment of the powerhouse and tailrace
2. Geophysical data: Provide the results of seismic survey from SUNTEC a.s.a.p.
3. Topographic survey:
3.1 Check the validity of the recently completed terrestrial survey in the field, revi-
sion and correction of the 1:5’000 map as required, elaboration in digital form.
3.2 It is emphasized that the availability of an accurate topographic map in digital
form is of prime importance for further design studies. Such requires also the
elaboration of a 1:1’000 scale digital map for the construction design of the dam
and appurtenant structures.
3.3 Therefore, it is recommended to subcontract the preparation/revision of the
above digital maps to an experienced company (Concordia, Suntec?). Possibly,
D:\Reports\UPL\UPL Doc\Reports\VOB UPL_Site visit3_rep.doc March 2005
Upper Paunglaung HPP 8
Site Visit No. 3, Feb-March 2005
the existing total station data can be used, as it appears that the problems with the
recently completed 1:5’000 map may be related rather to data processing than to
data acquisition (lack of topographic software?).
4. Site investigations for Dam:
Left Bank: One additional borehole BH-04 underway, another instructed
(BH-09 at elev. 390) into sound rock, approx. depth 30m
Right Bank: One additional drilling in upper part may be eventually required
later, depending on the ongoing investigations
Results of Lugeon tests in boreholes to be provided to Colenco asap.
Next design stage: Investigation adit at each abutment to be planned
5. Quarry
Geological reconnaissance and mapping by DHP Site Geologist required:
along the Small Paunglaung River, to about 500 m upstream of the conflu-
ence along the left bank; contact sandstone-granite along the right bank
(ridge separating the two streams).
Ample sampling and petrographic analyses to delimit granite from meta-
morphic schists and sandstone/quartzite
Core drilling at granite outcrop at the confluence, as instructed during site
visit.
6. Laboratory Testing:
Same as instructed in November 2004:
Rock foundations: samples of intact (undisturbed) rock cores from all drill-
ings at different depths for UCS testing, to start asap.
Construction material: first priority has concrete aggregate testing on po-
tential quarried rock, second priority river alluvions for CVC, third priority
soil testing for core material from test pits on abutments
View of the Left Abutment (TOP) and Right Abutment (BOTTOM) with the actual (RED)
and optimum (BLUE) dam axis alignment (February 2005)
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
BASIC FEASIBILITY STUDY
MISSION REPORT
JULY 20 – 21, 2005
Upper Paunglaung Hydropower Project 1
Mission Report July 2005
LIST OF CONTENTS
1 INTRODUCTION .................................................................................................2
1.1 GENERAL ........................................................................................................... 2
1.2 PROGRAM.......................................................................................................... 2
1.3 LIST OF PARTICIPANTS TO CHECK............................................................... 2
5 WATER MANAGEMENT.....................................................................................9
5.1 PRELIMINARY CORRECTION OF RESULTS ................................................... 9
5.2 ENERGY PRODUCTION AT PL & UPL ............................................................. 9
6 CONCLUSIONS ................................................................................................10
1 INTRODUCTION
1.1 GENERAL
After the last joint mission of Colenco Specialists in November 2004, the opportunity
was taken to visit the UPL site after returning from a reconnaissance trip to the Taman-
thi HPP on the upper Chindwin River. The principal objective of this visit was to review
the latest investigation results, in particular the new boreholes concluded after the last
mission of Colenco’s Geologist in April 05, and – on the basis of these data – to con-
firm the definite location of the dam axis.
Thanks to thorough preparation works by DHP, the access road to UPL was in good
conditions despite the ongoing rainy season. The dam site could be reached without
any obstructions in 2 ½ hours from PL, including a stop at the Namcho Crossing. The
party could return to Paunglaung in the afternoon prior to any rainfall.
1.2 PROGRAM
All core drillings according to established investigation program have been completed.
This extended drilling program included additional boreholes on top right abutment of
C1.5 and in possible portal areas of diversion tunnel, boreholes along the C1 axis as
set out during the April Mission of Colenco’s Geologist, and a borehole at the potential
quarry location.
The complete list of core drillings available up to date is presented as follows:
Explanations:
Boreholes at C1.5 axis; LA / RA = Left / Right Abutment
WPT, In-situ tests, Water pressure (Lugeon),
SPT Standard penetration in soil
SW Slightly Weathered rock: top of potential foundation grade
BH-01 40 m +SPT +Perm; MW rock at 39m C1 LA 348.268
BH-02 40 m +WPT C1 LA granite 288.25
BH-03 40 m +WPT C1 RA 309
BH-04 45 m SW sandstone (sst) at 37m C1.5 RA mid level 354.543
BH-05 42 m +SPT, SW sst starting at 38m C1.5 old LA 381.735
BH-06 60 m +WPT, fresh rock at 30m C1.5 mid LA 340.912
BH-07 80 m +WPT, SW sst at 4m C1.5 LA river bank 289.051
BH-08 60 m +WPT, SW sst at 23m C1.5 RA first bench 308.384
BH-09 13.5 m u/s gully, fresh sst at 8.5m C1.5 Diversion inlet 315.056
BH-10 45 m sound rock not reached C1.5 top RA 377.871
BH-11 30 m, sound granite at 2m QUARRY 310
Explanations:
Boreholes at C1.5 axis; LA / RA = Left / Right Abutment
WPT, SPT In-situ tests, Water pressure (Lugeon), Standard penetration in soil
SW Slightly Weathered rock: top of potential foundation grade
The second investigation campaign was conducted by SUNTAC in April during Mission
No. 4 of Colenco’s Geologist. The data cover the revised alignment of C1 axis up to
elev. 400 on both abutments, and the extension on the left abutment of C1.5 from elev.
380 to 460 (briefing hall). Seismic profiling along the right abutment of the adjusted
C1.5 axis could not be repeated due to presence of benches. The report on additional
seismic investigations was received in Baden on May 17, 2005.
2.4 TOPOGRAPHY
• The Terrestrial Map 1:5’000 of the dam site area, prepared by DHP was received at
the end of Colenco’s Mission No. 3 on March 1st, 2005. As pointed out in the mission
report, the hand interpolation of the 1-m contour lines was not deemed reliable.
• In May 2005, surveyed cross-sections along the new dam alignments at C1.5 and
C1 dam site were obtained from DHP. These new cross sections are adjusted to the
new absolute elevations provided by a second levelling traverse connecting the ex-
isting grid at PL to the UPL site.
2.5 HYDROLOGY
3 FINDINGS TOPOGRAPHY
The following revised measurement values of the Bench Marks BM1 and BM2 have
been confirmed by DHP, the chronology of the establishment and revision of the bench
mark elevations being summarised below to assist understanding of reports provided to
date:
BM1: x = 247894.38 m, y = 2186137 m, z = 289.313 (New Value)
BM2: x = 247997.00 m, y = 2186077 m, z = 287.189 (New Value)
According to the letter from DHP, dated December 23, 2004 the Z- coordinates of the
two benchmarks BM1 and BM2 were the following:
BM1 z =298.722 m, i.e. a difference of 9.409 m too high
BM2 z =296.5975 m, i.e. a difference of 9.4085 too high
The coordinates of these benchmarks represent an important basis for the layout of the
dam structures and the water management calculations. The Feasibility Report UPL-
00-BFR—PREL/0405 was based on the initial information provided.
From January to March 2005 a new topography was established by DHP indicating that
the correct heights of the two benchmarks are 289.313 m (BM1) and 287.189 m (BM2).
This result indicates that the river bed level is about 10 m (9.41 m) lower than that pro-
vided for use in the FS up to then. According to DHP, this systematic error arises from
the bad weather conditions prevailing in November 2004, when the first topographic
levelling was established.
The new coordinates of the benchmarks were also checked independently by
SUNTAC. Combined with differential GPS, SUNTAC has performed a levelling from
Pyinmana to the dam site in March 2005 (Report available, reviewed by Colenco on
July 20). The height of BM5 resulted in 290.092 m. The new levelling of DHP, per-
formed by DHP in February 2005 from PL to the dam site of UPL resulted in 290.115 m
for BM5. Thus, independently the almost exactly the same result (difference: 2 cm) was
achieved by DHP and SUNTAC.
The maps of the dam site area made available for the carrying out of the Preliminary
Basic Feasibility Study thus include an error of some 10m. For finalising the Basic Fea-
sibility Study, the contours of the existing map will be adjusted by 10m and the more
accurate river sections used for structure elevations, the maps thus only being indica-
tive. For further design works 1:1000 scale maps of the C1 Dam area and 1: 500 scale
maps of the Diversion Intake and Outlet portals are required.
From January to March 2005 a terrestrial survey of the UPL dam area has been carried
out by DHP. Based on the surveyed points (total station), a topographical map was
drawn by hand with contour intervals of 1m. However, the plotted contour lines are at
0.6 m offsets from normal mapping techniques (i.e., 300.6, 301.6 etc.). Moreover, it
was noted during Colenco’s field visit March 2005 (O. Voborny) that the contours did
not appear to match the actual morphological features in the field. During the field visit
of July 19-20 (A. Dredge, HR. Frei and O. Voborny) it was concluded together with
DHP site staff that the map could not be used for design purposes and that it would be
replaced. Where previous survey results are used, the map needs checking in the field
and complimentary surveys needs to be carried out prior to finalising the map.
On July 21, the further discussions were held between D. Job / COLENCO and U San
Maung / DHP as follows:
• With the new interpolation software recently acquired by DHP, a 1:10’000 map with
10m contour interval lines shall be produced by DHP to allow for a direct compari-
son with the map established by SUNTAC in November 2004, used so far in the FS
(Drawing Nr. 71.4763.56.002). Date of delivery to Colenco: August 15, 2005. The
importance of considering abrupt changes in elevations for the establishing of the
contour maps was pointed out by Colenco.
• The new 1: 10’000 map by DHP will be reviewed by SUNTAC before it is sent to
Colenco
• A 1:1’000 map with contour intervals of 2 m will also be produced by DHP by August
15. (This map shall be checked in the field by DHP to confirm general compatibility
with actual conditions prior to submittal to CPE and other parties).
The coordinates of the Boreholes and actual C1 dam axis as marked in the field require
inclusion on the layout drawings of the geological investigations. It is good practice also
to provide such for the lines of geophysical profiles.
DHP site want to check the coordinate values received prior to submitting these to CPE
(this checking is very much appreciated)
Requests to DHP site for 1:500 / 1:1000 Maps required to be made to DHP Yangon
and are hence were repeated in the meeting held in DHP Yangon.
The correlation between BM’s on the upper valley plains and the dam area require
checking and confirming, preferably by a levelling survey between BM’s in each area.
4 FINDINGS GEOLOGY
The additional seismic refraction survey, performed with better equipment than the first
campaign, has provided a first clear indication for better rock conditions on the right
abutment of C1 dam axis as compared to those at C1.5. On the seismic sections, a
relatively steeply rising surface of “blue” rock was evident below the right abutment of
C1 axis. “Blue” is indicative for seismic velocities exceeding 4 km/sec and suggests
very good rock conditions. According to seismic data, the surface of this rock layer
reaches the elev. of 350 approximately beneath the top of right abutment. In compari-
son, no “blue rock” conditions were detected below the abutments of dam axis C1.5.
The left-abutment conditions seem to be similar for both dam axis alternatives accord-
ing to seismic data, suggesting depth of “fair” rock (circa 2.5 km/sec) at 50m approxi-
mately at dam crest elevation.
Additional core drillings, performed since the last site visit in April 05, have definitively
proved better rock conditions of the right abutment at dam axis C1. The seismic data
were fully confirmed. The new corresponding boreholes at the top of each right abut-
ment have indicated the following elevations of sound rock:
If the comparison is made for the mid level of both abutments, which corresponds ap-
proximately to the intersection of dam axis with the diversion tunnel, the following ele-
vations of sound rock are detected:
The borehole results are presented along the main sections of C1.5 and C1 axis in An-
nex 1 and Annex 2 respectively.
The results leave no doubts about better rock conditions of the C1 dam axis. This is of
particular importance for the excavation of the 10m-diameter diversion tunnel. Beneath
the respective dam axis, the surface of good rock is at C1 25m higher than at C1.5.
Needless to say, that this fact results in a substantially lesser volume of dam excava-
tion and of dam concrete for the C1 alternative.
The additional boreholes at C1 axis have further confirmed that the geological condi-
tions of the river section and left abutment are more or less the same for both alterna-
tives C1.5 and C1. The borehole BH-15 in the river terrace of C1 (powerhouse site) has
shown only 7.5m of river deposits, underlain by sound rock.
4.3 CONCLUSIONS
To firm up the results of the present Basic Feasibility Study, the minimum program for
next-to-do subsoil investigations focus on the diversion tunnel at the C1 axis and on
confirmation of granitic rocks at the foreseen quarry location along the left bank of the
Small PL River.
One borehole is proposed at each likely portal location of the diversion tunnel on the
right bank of C1 axis. These locations have been approximately identified during the
site inspection. A third additional drillhole with a permanent piezometer is proposed on
the top platform of the left abutment, behind (i.e. SW of) the briefing hall and shall be
aligned with BH-14 farther below. The purpose is to investigate the surface of sound
rock and groundwater table in the lateral extension of the left dam abutment.
Another two drillholes shall investigate the granite extension at the foreseen quarry lo-
cation on the left bank of the Small PL River, following the preparation of an access
into the valley. Bush clearing and dozer/backhoe benching is required to access the
proposed quarry area along the left bank of SPL River. The possible approach to the
target area has been discussed on site.
A next stage of required foundation investigations would include the excavation of ex-
ploration drifts in both abutments of C1 axis, with first priority to be given to the right
abutment. This would also enable experience at a smaller scale to be gained for the
excavation of the diversion tunnel.
5 WATER MANAGEMENT
Since the river bed level is around 10m (9.41 m) lower than was assumed in the pre-
liminary FS (April 2005), the layout of the structures as well as the water management
results will be affected by this fact. Assuming the same NSL and dam crest elevation
as before (370 and 378 m a.s.l.), the new dam height will be now 100 m instead of the
90m considered so far in the FS.
Accordingly, the rated head will increase from 71 m to around 81 m. Hence, the energy
and power production at UPL will be increased by 81:71 = 14%. During the field visit,
preliminary calculations were performed. The results are shown in Annex 3, corre-
sponding to updated Annex 4-17 in the preliminary FS from April 2005.
From Annex 3 it can be seen that the average energy production of PL and UPL is 500
GWh more than that of PL as a stand-alone plant. Therefore, an increase of almost
60% is achieved, even though no additional catchment area is introduced into the sys-
tem. At PL itself, the actual energy was calculated as 901 GWh/y as a stand-alone
plant, after the construction of UPL the average energy production of PL is 932 GWh/y.
Therefore, the energy production of the existing PL Plant alone will increase by 31
GWh due to the presence of UPL. The reason for this increase lies almost entirely in
the fact that the amount of spill water can be largely reduced at PL due to the regulat-
ing effect of UPL after commissioning.
On the other hand the Firm Energy (Primary Energy) even at PL alone is increased by
a remarkable 60% and for both PL and UPL combined, the increase in Firm Energy is
130%. This is a main point of the water management, i.e., the maximisation of firm en-
ergy at PL. As a stand-alone HPP, the firm energy of PL is 399 GWh, which is
399:901=44% of the total energy production. In conjunction with UPL, 640 GWh of firm
energy are achieved, corresponding to 640:932=69% of the total energy production.
These figures well illustrate the considerable benefits induced by UPL on the operation
of existing PL.
6 CONCLUSIONS
The short site visit by Colenco’s Project Team jointly with DHP Site Representatives
proved very efficient in terms of reviewing the recent investigation results and allowing
decisions upon the definite location of the dam axis.
The results of the recently completed additional subsoil investigations speak clearly in
favour of the alternative dam axis C1, the decisive factor being the better foundation
conditions of the right abutment. These have a significant impact on the excavation and
stability of the diversion tunnel (10m in diameter!) and on the excavation depth and
RCC volume of the dam. Although the left-abutment foundation conditions are the
same (poor) for both alignments due to deep weathering, the overall stability of dam
against sliding is also considered better for the left abutment of C1 than for that of
C1.5. The reason is the presence of deep gully with lateral stream immediately down-
stream of C1.5.
Based on the conclusive findings of site investigation, the dam alignment C1 has been
recommended for further design studies at the concluding meeting at DHP Headquar-
ters in Yangon on July 22, 2005.
As a next immediate action, the following additional surveys and investigations have
been requested:
1. Revised Topo Map 1:10’000 of the project site based on existing data (SUNTAC
photogrammetry), and recently confirmed absolute elevations, and new DHP soft-
ware. Contour intervals 10m
2. New Topo Map 1: 1’000 with 2-m contours covering the dam and powerhouse ex-
cavation area C1; additionally Topo Map 1 :500 with 1-m contour intervals of the
C1 diversion tunnel inlet and outlet area.
Both maps shall be based on new ground survey, eventually using existing total-
station points, prepared by using new DHP software and duly considering the lines
of abrupt changes in elevations
3. Boreholes at diversion tunnel portals of C1, inlet and outlet location respectively,
depth 30m each. One borehole at the top platform of left abutment behind the
briefing hall, minimum depth 50m
4. Clearing, access track and 2 boreholes along the approach to the quarry hill: thick-
ness of overburden and contact of granite to overlying sandstone (intrusion from
below)
5. Logistic preparations for excavating an investigation adit at the middle elevation of
the right bank (above planned diversion tunnel), dam axis C1
Annual Energy 911 N/A N/A N/A 994 1029 329 1358 901 932 469 1401 Overestimation by Kansai due to simplified
(GWh) Additional 55% procedure. Overall efficiency Norconsult 89%, CPE 87%
Firm Energy 329 N/A N/A N/A 505 675 142 817 399 640 280 920 CPE includes 95% availability criterion, Norconsult 100%
(GWh) Additional 131% Kansai's over-simplification gives incorrect values
(Kansai study is based on an average hydrological year.
Critical period of drought was not considered)
Continuous Firm 37.5 N/A N/A N/A (57.7) (77) (16) (93) 45.5 73 32 105
Power (MW) Additional 131% ditto
Firm Peaking (113) N/A N/A N/A 173 231 (48) 279 137 219 96 315 8 hours for peaking production selected by Kansai
Capacity (MW) Additional 130% (also adopted by CPE)
(8 hours)
Installed Capacity 280 N/A N/A N/A 280 280 85 365 280 280 140 420
Additional 50%
Additional Values Annual Energy (GWh) 364 Annual Energy (GWh) 500
(Comparison PL+UPL Firm Energy (GWh) 312 Firm Energy (GWh) 521
to PL Stand-alone) Cont. Firm Power (MW) 35 Cont. Firm Power (MW) 60
Firm Peaking Cap. (MW) 106 Firm Peaking Cap. (MW) 178
February 2006
Table of Contents
page
1 Activities......................................................................................... 1
2 List of Participants......................................................................... 1
Annex 1: Situation Map UPL showing the location of investigation points, access to
the Quarry Ridge and the assumed contact of granite and sedimentary
rocks
Annex 2: Photos of Investigation Trench, UPL Dam Axis Left Abutment, elev. 320
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 1
1 Activities
2 List of Participants
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 2
3 YEYWA HPP
In view of the approaching key date for first RCC placement, rather intensive activities
of excavating, cleaning and consolidation grouting were under way on the right bank, in
particular at Block 18 adjacent to the existing leveling-concrete platform in the riverbed.
Excavation (blasting) works on the right abutment above Block 18 were stopped on the
27. January, to allow for cleaning and grouting of Block 18. DHP was instructed on Jan.
25 to start the drilling and grouting works with high priority, i.e. prior to cleaning of the
surface. Due to the generally very favorable foundation conditions in the central dam
area, the grouting process is very smooth. Except for a few individual holes, the grout
takes are generally low. As stated earlier, the main purpose of consolidation grouting is
to deal with the blasting damage zone, causing relaxation in the blocky massive
sandstone.
We were pleased to notify that constructive measures are finally being undertaken to
deal with the instable blocks at elev. 139 and above on the left abutment. The
overhanging blocks between elev. 139 and 147 were the subject of serious safety
concerns during the past 1.5 years, in particular after appearance of seepage on the
principal sliding planes in September 2005. At the present, retaining concrete walls are
being raised along the berm 139 to support the overhanging blocks. After completion,
scaling of all loose material and instable block wedges at higher locations will be
required.
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 3
4 UPL HPP
This was the first visit of CPE Geologist to the Site since July 2005 (one day only from
Tamanthi). The planned visit during the September 05 mission was cancelled due to
lack of access. The purpose of this visit (jointly with CPE Chief Surveyor P. Rumpf and
CPE Site Coordinator M. Buchli) was to review new data, to confirm the location of the
quarry, to assess the dam foundation conditions and instruct additional investigations
required. The corresponding hand written Site Instructions were delivered to DHP
before departure.
The first priority of this site visit was to confirm the most favorable location of the quarry
site based on former findings, new drilling information and field reconnaissance.
Based on an early field evidence at the dam site (C1 left bank) and in the Gully 2 (later
Borehole BH 25), it had been assumed in mid 2005 that the contact of granite toward
the overlying sedimentary rocks would be at elev. of 350 approximately, rising towards
the steep valley of the Small Paunglaung River (SPL). Hence, access to the
prospective quarry area was foreseen from elev. 290 approximately. Borehole BH23,
drilled in the Gully 2 in early December 05, seemed to confirm this assumption. At 12 m
depth, the drilling has penetrated the contact between the overlying sandstone
(exposed in the gully) and fresh intrusive granite. During the reconnaissance for a
triangulation point along the old access road by Colenco team in December, outcrops
of fresh granite were identified in the slope at elev. of 500 – 600 approximately,
followed by quartzite on top of the ridge. Investigation boreholes No. 25-27 along the
access road and No. 28 at the top were instructed during the December CPE visit
(Report UPL-56-001-BUM, Dec.05).
The findings of the latest reconnaissance are summarized as follows (Annex 1):
(1) The prospective Quarry Ridge extends from the top at elev. 693 (ridge with
mammoth tree) down to SPL River at elev. 300. The slope towards the dam site
is very steep and dissected by active erosion gullies. The ridge itself towards the
SPL valley (“nose”) is less inclined in the upper part. Access to the ridge is
provided by the old access road to the briefing hall; however, it must be further
extended by dozer tracks further towards NE
(2) Field reconnaissance of the slope from top (el. 690) to bottom (el. 300) by slide-
over rather than walk-over confirms earlier observations: flat laying quartzite at
top, granite appearing at el. 600 approx. Therefore, the roof of the granite
intrusion that occupies the narrow SPL valley is confirmed at elev. 600 m asl.
(3) Boreholes BH-25 at elev. 552 (Annex 1), instructed last December, confirms the
occurrence of fresh granite below 12m of overburden. In the nearby Gully 2,
sound granite daylights at the surface. This situation needs to be confirmed by
additional borehole further towards NE, after extending the dozer track along the
contour line towards the flat ridge overlooking the SPL valley. A corresponding
instruction for Borehole BH-28 has been given. The previously foreseen location
of BH-28 at the top of the quartzite hill was cancelled. The Drillhole BH-27 below
the top at elev. 590 has found 21m of residual soil with many granite boulders
and was terminated at 23m depth in highly weathered granite.
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 4
It can be confirmed at this stage, that the Quarry Ridge building the steep left bank of
the SPL River is constituted by a granitic intrusion up to the elevation of 600 m asl.
approximately. A critical factor for quarry development will be the thickness of
overburden. Given the very restricted accessibility at this time, additional dozer track
and trenching excavations at several elevations are required, together with at least one
additional borehole B28. At the present, it is concluded that the most promising target
area to start quarry development is the flat ridge (nose) at elev. 550, with benching
from top to bottom, also including the eastern face of the 693-hill (see map in Annex 1).
Coarse and fine aggregates will be required for early concrete works (diversion tunnel,
shotcrete), most likely before the proper quarry can be developed. A possible
alternative to obtain these would be from alluvial deposits. The Paunglaung River itself
has probably no suitable sand deposits (only small gravel terraces and shoals of fine
sand as flood deposits). On the other hand, delta deposits of small lateral creeks have
been identified as prospective borrow areas for fine and coarse aggregates. The delta
of the “Minihydro-Creek” (name unknown) at the riverside camp has been already
partly exploited by DHP for manufacturing pre-cast culverts. A yet larger creek, the
Yemon-chaung, builds a relatively large delta about 1 km further downstream
(destroyed bridge of the access road). According to a visual inspection, gravel and well
graded sand of 2m thickness or more could be obtained from the delta terrace.
Sampling and testing is required (gradation, fineness, Los Angeles as a minimum
requirement).
After completing the clearing works, also the island at the confluence of the PL and
SPL River should be investigated by test pitting and sampling.
The two boreholes made at the approximate location of the inlet and outlet portals
respectively show very different rock conditions. BH-20 at the inlet (elev. 311) shows
fractured and weathered silty sandstone down to 30m of depth. The intensive
weathering along joints with black manganese staining suggests hydrothermal
alteration by hot fluids, attributed to the vicinity of granite intrusion. In turn, the outlet
borehole BH-21 (elev. 302) shows fresh and intact sandstone from 10 to 30m depth
(RQD 100!). The ongoing bench excavation above the outlet portal was still in
overburden material consisting of decomposed and highly weathered rock.
There is a reason to believe that the conditions of in-situ rock mass are better than
those indicated by exploration drillings due to the small diameter and poor quality of
drillings. A first hint gives the road cut just behind the guesthouse at the C1 dam axis.
The slope consists of highly to moderately weathered bedrock with intact rock-mass
structure. Weathering occurs along joints with abundant manganese stains. In contrast
to this observation, the boreholes suggest an overburden of 40m depth due to a
complete lack of core recovery (e.g. BH-14 at 395 m, BH-22 at 440m).
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 5
To investigate the in-situ conditions, in particular the weathering profile above sound
rock, a trench was excavated by a backhoe at the berm elev. 320 along the dam axis of
the left abutment. Two sample bags of “overburden” (highly weathered rock) were
obtained from the trench.
The trench excavation has reached the surface of non rippable firm rock (light
excavator) at a depth of 2-3 m beneath the bench or some 5 m below the original
surface respectively. This observation indicates that highly to moderately weathered
rock with intact framework occurs at a depth of 5 m approximately below the natural
slope, this in contrast to the drilling information. Even though the rock material at this
depth is probably of low mechanical strength, it has an intact rock mass structure and
is groutable. Therefore, if this condition is confirmed by additional investigations and
testing, the theoretical dam excavation line at the left abutment can be shifted upwards
and the excavation volume significantly reduced. Based on the present assessment, an
excavation depth of 15m in parallel to the natural slope may be considered as realistic.
The foundation grade for the RCC dam is assumed to be in the lower part of the
moderately weathered and fractured rock (CM-class) in the abutments and in the fresh
rock (CH class) in the central river section with the maximum dam height.
The firm, moderately weathered rock observed in the trench is fractured and weathered
along two perpendicular joint systems J1 115/85 or 310/85 and J2 030-050/70
respectively. The bedding appears to be dipping gently into the slope at B 200/12.
These are the first structural observations of the in-situ rock mass at the dam axis! The
trenching has also been extended downslope to reach the contact to the granite.
Instructions were given for an additional trench at elev. 370 to confirm the rock
conditions at a higher elevation of the abutment slope. An additional borehole BH 30
should be also drilled from the bottom of the trench (i.e., eliminating the overburden)
into sound rock, if possible by dry drilling method through the weathered part. A third
similar trench is foreseen also in the middle of the right abutment.
1. Quarry 1.1 Extend dozer track to the flat ridge by keeping the elev. of approx. 550
1.2 New Borehole BH-28 at extended dozer track (previous location of BH-28
cancelled). Depth 50m into granite to check material homogeneity!
1.3 Blasting tests at natural granite outcrop at existing dozer track
2. Dam 2.1 Additional boreholes:
BH-24 in river bed left bank started
BH-26 Top Left Abutm behind guesthouse, 50m deep, drilling without
water flushing as far as possible (tungsten bit required)
BH-30 Left Abutment on dam axis, from bottom of trench No. DA-LA2
2.2 Trenching by excavator, sampling
DA-LA1: dam axis left abutment at el. 320 Done 1.02.
DA-LA2: ditto, elev. 370 toward 380
DA-RA1: dam axis Right Abutment, location to be decided by site superv.
Extraction of large disturbed samples of overburden
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 6
B. Laboratory Testing:
B1. On Rock:
- All rock samples obtained from core drillings and eventually from excavations shall
be subjected to standard testing consisting of Specific Gravity, Water Absorption
and Unconfined Compressive Strength (UCS). Five samples were taken from the
core boxes during the site visit (BH-20, -21, 25). Petrographic analysis shall be
performed on a few representative rock samples (granite, sandstone, siltstone).
Annexes:
Annex 1: Situation map showing investigation points, access to Quarry Ridge and estimated
contact between granite and sandstone/siltstone
Annex 2: Photos of investigation trench at dam axis, left abutment, elev. 320
Baden, 21/02/2006
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 Annex 1
New BH-28
Quarry Ridge
Annex 1: Situation map showing the location of boreholes (BH), access to the prospective
Quarry Area and the assumed contact of granite (red) to sedimentary rock
February 2006
YWA & UPL HPP, Site Visit Report O. Voborny, Jan-Febr 2006 Annex 2
Right:
Detail of the highly weathered rock
showing intact mass structure with
black stained joints, 2 systems
plus bedding
V
Left:
View from the 320 berm into the
trench showing the weathering
profile according to ISRM grades:
V Completely weathered /
decomposed rock
IV
IV Highly weathered
III Moderately weathered rock
forming the bottom of excavation,
non-rippable
III
Annex 2: Trench excavation DA-LA1 from the berm at elev. 320, left abutment,
looking upstream.
February 2006
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
27/01/09 – 28/01/09
JANUARY 2009
Upper Paunglaung Hydropower Project Page 1
Mission Report of O.Voborny and H.R.Frei 27.01.-28.01.2009
TABLE OF CONTENTS
1 PROGRAM............................................................................................................... 2
2 ANNEXES ................................................................................................................ 2
3 GENERAL ................................................................................................................ 2
4 COFFERDAM EMBANKMENT ................................................................................ 2
5 RIGHT ABUTMENT ................................................................................................. 3
6 SEPARATION WALL............................................................................................... 3
7 DIVERSION TUNNEL OUTLET CHANNEL ............................................................. 3
8 ALTERNATIVE QUARRIES..................................................................................... 3
1 PROGRAM
27/01/09 Transfer from Nancho to UPL, site visit dam
28/01/09 Site visit quarry and right abutment, transfer to NPT
2 ANNEXES
1 Right Abutment, modified dam axis
2 Proposed alternative quarry locations
3 Photos 1 and 2
4 Photos 3 and 4
3 GENERAL
The main purpose of the visit was the inspection of the ongoing dam excavation and cof-
ferdam embankment works as well as the inspection of new potential quarry sites.
4 COFFERDAM EMBANKMENT
The U/S cofferdam is actually on elevation 292. The compacted red core is looking good
(Photo 1). The contact to the rock on the right abutment is made manually, including in-
crease of water content (Photo 2). The overhanging rock nose on the left abutment shall
be shaped to an inclination of 5V:1H in order to allow proper compaction of the core con-
tact.
At the upstream side of the central part of the core, “yellow clay” is placed, which is actu-
ally a rather silty material without cohesion. This should not be used as shell material be-
cause of the lower shear strength properties. It could be used as transition material on
the D/S side of the core with actually 4 m width, decreasing to 2 m at elevation 300 (but
not necessarily required).
Actually enough shell material is available from separation wall and riverbed excavation.
Generally the more permeable material shall be used for the downstream shell. The red
clay core may be reduced to the following minimum dimensions: 3 m at the top and an
inclination of 2V:1H on both sides of the core.
The clay cut-off below the D/S cofferdam has not yet been constructed. It is planned to
excavate some test pits in order to decide if it is necessary or not.
5 RIGHT ABUTMENT
The dam excavation on the right abutment has proceeded from top hill down to the dam
crest elevation. The rock at the foreseen dam location is still highly weathered and frac-
tured and can be easily excavated by backhoe (Photo 3). However, a ridge of strong me-
tasandstone occurs further downstream (Photo 4).
An inspection of the cut slope along the berm 235 revealed that the rock quality is gener-
ally better on the D/S side of the dam and decreases in the U/S part of the dam footprint,
probably due to the presence of a shallow gully in the center of the dam footprint area. It
bears noting, that some 10-15 m of excavation still has to be made before reaching the
foundation level.
Based on these field observations, it has been jointly decided to relocate the right end of
the dam axis by 15 m in D/S direction (Annex 1). However, this decision shall be con-
firmed by the CPE Dam Designer, considering also the shape of the block at the kink.
Modified excavation drawings will be prepared by CPEM and forwarded to the site in due
time.
6 SEPARATION WALL
The excavation of the separation wall reached about elevation 280, at the D/S end nearly
foundation level 278. The foundation has not yet been cleaned but the lowest part had to
be blasted into sound rock and the foundation quality is hence certainly sufficient. The
rock surface in the area is generally at elevation 278-280. Some seepage water was
flowing into the excavation trench at the D/S end from the slope side, at the contact
rock/alluvium. It is at the moment not clear, if it comes from the slope or from the river.
Some internal discussions were held regarding the required excavation depth for the re-
taining wall. It shall be mentioned, that the excavation depth on the slope side of the wall
is given by the shape of the tailrace channel and not by assumed geological conditions. It
can therefore not be changed, no matter how good the rock conditions are. The riverside
excavation depth of the higher sections has been defined by stability calculations and
should also not be changed without confirmation from CPEM.
8 ALTERNATIVE QUARRIES
On the first day of site visit, HiTech has presented his evaluation study of the riverside
granite occurrence on the right bank at the mouth of Small PL River. The estimated re-
serve is indicated as 300,000 cum net. The quarry site can start production immediately
On the following day, a potential alternative location for the MSP quarry has been in-
spected by Representatives of DHPI, MSP and CPE. The location has been previously
prospected by CPEM Geologist and MSP. It is located in a deep gully on the reverse side
of the Army Camp Hill. Fresh massive granite can be observed in two adjacent gully and
apparently on a flat deforested hill in between (Farm Hill). A situation map showing tenta-
tive locations is given in Annex 2. Besides the Quarry Area 2 in the gully, confirmed dur-
ing the site visit, another candidate Area 1 is also proposed for exploration along the
steep cliff of the Small PL River. This area has never been visited and an access path
from Area 2 shall be prepared for inspection.
In order to confirm the presence of fresh granite in the identified area 2, exploration either
by seismic refraction (profiles indicated in Annex 2) or by crawler drill have been recom-
mended. The second method is considered faster, provided that the crawler drill can be
brought in on a dozed track from top of the hill (old access road to UPL site). For con-
struction access, a road from the existing MSP camp following the contour line is pro-
posed.
The next geological inspection by CPEM shall be carried out when foot access to Area 2
and 1 is arranged, approximately in 2-3 weeks from now. The next exploration steps can
be decided accordingly.
P:\3853_wk\REPORTSCPEB(745)\SV_Frh-Vob_Jan 09_UPL.doc
January 2009
Upper Paunglaung Hydropower Project Annex 2
Mission Report of O.Voborny and H.R.Frei 27.01.-28.01.2009
Potential Quarry Area 1 and 2 for alternative MSP Quarry, subject to confirmation
P:\3853_wk\REPORTSCPEB(745)\SV_Frh-Vob_Jan 09_UPL.doc
January 2009
Upper Paunglaung Hydropower Project Annex 3
Mission Report of O.Voborny and H.R.Frei 27.01.-28.01.2009
P:\3853_wk\REPORTSCPEB(745)\SV_Frh-Vob_Jan 09_UPL.doc
January 2009
Upper Paunglaung Hydropower Project Annex 4
Mission Report of O.Voborny and H.R.Frei 27.01.-28.01.2009
Photo 3: Excavation at the Dam Crest of Right Abutment, highly weathered sandstone
P:\3853_wk\REPORTSCPEB(745)\SV_Frh-Vob_Jan 09_UPL.doc
January 2009
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
18/03/2009
MARCH 2009
Upper Paunglaung Hydropower Project Page 1
Mission Report of O.Voborny 18.03.2009
TABLE OF CONTENTS
1 INTRODUCTION ...................................................................................................... 2
2 PROGRAM............................................................................................................... 2
3 CONCLUSIONS QUARRY (ANNEX 1 & 2).............................................................. 2
4 SEPARATION WALL (ANNEX 3) ............................................................................ 3
1 INTRODUCTION
The mission of Mr. Voborny was set up on a short notice in response to the urgent situa-
tion regarding the UPL quarry issue. First, the alternative granite quarry location identified
during the January 09 mission [1] has turned out to be not suitable due to 1) unexpected
overburden of 10m and more, and 2) results of petrographic analysis showing 70%
quartz content and hence excessive abrasivity. Based on the negative outcome, a joint
agreement was reached among DHPI, Colenco and Contractors to look for alternative
quarry sources other than granite, namely for limestone, identified in a desk study by
Thein Han, CPEM/NEPS geologist. A first field reconnaissance of the proposed area was
carried out on 26-27.February 2009 by Thein Han and party (representatives of DHPI,
MSP and HTCT). The promising outcome of the field inspection was documented in
CPEM Quarry Report from 28.02.2009 [2], indicating the presence of massive limestone
outcrops forming a ridge, with virtually no overburden present.
In order to definitively confirm the availability of adequate limestone resources for quarry-
ing and to proceed with quarry development, Colenco’s Project Geologist has visited the
potential quarry area on 18.03.2009, together with Representatives of DHPI, MSP and
HTCT. A second purpose of the UPL site visit was to inspect and approve the excavation
of the separation wall for concreting.
2 PROGRAM
After inspecting the separation wall excavation, the party has departed by several vehi-
cles and motorcycles along the newly excavated access road from top of the right abut-
ment across the hill ridge to the Paunlaung River valley at the location of the KYWE YOE
village (see Annex 1 for location map). The bulldozed track across difficult topography
has been just completed thanks to exceptional efforts of DHPI personnel. After crossing
the river by small boats at 9.00 AM, the party started the ascent to the New Sinkwin Vil-
lage by means of two cargo elephants and two motorcycles. The elephant ride took about
2 hours to reach the village, which can be used as adequate headquarters for quarry de-
velopment. From the village, the toe of the limestone can be reached by walking along a
narrow gully in 45 minutes. After inspecting the slopes of the ridge, constituted of in-situ
limestone, the party returned to the village and departed at 2 p.m. toward the river cross-
ing (1.5 hours by walking or 20 min by motorcycles)
2) In view that practically no stripping is required, the start of quarry operation depends
only on the construction of the access road
3) Quarry Features
Based on the preliminary information available, the quarry can be qualified as follows:
• Zero Overburden (Zero-O Quarry), only minimum stripping required
• Material quality eventually only affected by local karstification (requires selective
quarrying if present)
• unlimited quantity along a prominent ridge, 2-3 km long, 150m high above valley
• Ample space for the development of two separate quarries (Site North and Site
South)
• Space for crushing plant available on flat ridge areas
4) Access conditions
All party members reach agreement on the best approach to the quarry, following princi-
pally the route taken during the site visit. An alternative approach across the Small
Paunglaung River has been discarded. The access road is estimated to about 10km
length, consisting of:
• Access road from UPL Dam Site (Top of Right abutment) to Kywe Yoe Village on
the right bank of PL River, NE of the dam site. Difficult topography, following the
steep right bank of the PL River
• River Crossing at Kywe Yoe, favourable conditions with an island, narrow river
channels. Kywe Yoe village as base camp for road construction (men and material)
• Access from the river to the New Sinkwin Village and onwards to the quarry hill
5) Investigations
The brittle metasandstone is jointed along several discontinuity systems, the most fre-
quent one being oriented perpendicular to the river (parallel to dam axis). Geological
mapping of important features is required prior to start of concrete works. A wedge failure
of significant volume has occurred the left hand excavation slope, following inclined slabs
developing parallel to the river valley. These slabs reach a major lateral extent in massive
brittle sandstone layers (similar to Yeywa left abutment) and will also affect the excava-
tion of the powerhouse.
References
[1] Site Visit Report No. UPL-00-VOB/FRH-Jan09, Colenco Baden Febr. 2009
Annexes
Potential Quarry Area 1 and 2 for alternative MSP Quarry, subject to confirmation
Fig 2: River crossing, view towards island and potential bridge location
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
JUNE 2009
Upper Paunglaung Hydropower Project Page 1
Mission Report of H.R. Frei & O.Voborny 15.06.2009
TABLE OF CONTENTS
1 INTRODUCTION ...................................................................................................... 2
2 PROGRAM............................................................................................................... 2
3 RIGHT ABUTMENT ................................................................................................. 2
4 LEFT ABUTMENT.................................................................................................... 3
5 SEPARATION WALL............................................................................................... 3
6 POWERHOUSE EXCAVATION ............................................................................... 4
7 ROCK MASS PARAMETERS .................................................................................. 4
8 ANNEXES ................................................................................................................ 4
June 2009
Upper Paunglaung Hydropower Project Page 2
Mission Report of H.R. Frei & O.Voborny 15.06.2009
1 INTRODUCTION
Colenco’s Senior Geotechnical Engineer and Geologist have visited the UPL Project Site
on 15.06.2009 for general inspection of ongoing works in the dam foundation area. The
new limestone quarry could not be visited due to lack of access.
Fig. 1: Participant of the joint DHPI/CPE site visit on 15.June 09, view from right bank
2 PROGRAM
15/06/09 Visit to UPL Site, overnight at CPE Guesthouse PL
16/06/09 Site Visit Nancho, meeting with DHPI in NPT
3 RIGHT ABUTMENT
The dam excavation on the right abutment is proceeding from the top. The actual working
platform at elev. 385 has been inspected, progressing in hard metasandstone, 7m above
the dam crest elevation. The introduced kink of the dam axis towards downstream can be
confirmed as fully justified (January 2009).
The metasandstone nose on elevation 385 D/S is being removed in order to get space
for the quarry access road. The width of the berm on el. 395 will be reduced from 5m to
3m in order to gain 2 m for the road. No adverse effect on stability is expected by this
shifting of the slope.
June 2009
Upper Paunglaung Hydropower Project Page 3
Mission Report of H.R. Frei & O.Voborny 15.06.2009
4 LEFT ABUTMENT
The general foundation conditions are roughly described in our site visit report UPL-00-
FRH/MAY 08. This is generally still valid after the shifting of the axis in U/S direction.
Since then, no activities except for the bottom part around the granite outcrop. The exca-
vation platform at elev. 320 in the roof of the granite intrusion has been expected. D/S of
the granite contact, a rather week moderately weathered sandstone/siltstone occurs
within (and below) the final excavation line. The extensive black staining of the joint sur-
faces by Mn-Oxide is a sign of substantial hydrothermal weathering in a “contact dome”
surrounding the intruded granite body. Therefore, at least in this area, the theoretical ex-
cavation line of the foot print area needs to be shifted to greater depth by steepening the
cut slopes above.
An inspection on a higher berm (elevation 335) has revealed somewhat better foundation
conditions and lowering of the foundation design line does not seem to be necessary (ac-
tual excavation level is still 2-3 m above the design level).
5 SEPARATION WALL
The excavation has been completed and placing of RCC is well under way, reaching the
elevation of 281. All excavation was done in hard blocky metasandstone. Several wedge
failures have occurred from the left excavation wall, reported in the March 09 site visit re-
port. The most prominent discontinuities are slabs parallel to the river, inclined at 55-to
70º into (and undercut by) the excavation pit (Fig. 3). These slabs (mean orientation
045/60) will have a similar adverse impact on the stability of the permanent left-hand side
powerhouse excavation slope. The upstream corner of the separation wall excavation
shows top of sound rock in the river channel at elev. 282. The unknown granite contact
beneath the river channel could be also observed, dipping at 330/50 into the river and
towards the DT inlet.
Fig. 2 Curing of the RCC of separation wall Fig. 3: Wedge failure along inclined
slabs in the separation wall pit, view
downstream
June 2009
Upper Paunglaung Hydropower Project Page 4
Mission Report of H.R. Frei & O.Voborny 15.06.2009
6 POWERHOUSE EXCAVATION
Based on the experience from the separation wall excavation (see above, Fig. 3) it is pro-
posed to modify the excavation design of the powerhouse in order to avoid undercutting
the critical slabs.
The rock mass properties have been estimated according to Hoek-Brown, based on the
UCS results (wet tests) presented in Annex 1. The estimated values for the different geo-
logical formations are given in Annex 2. The values are average values, locally higher
and lower values are possible. For the dam design, generally the peak values shall be
used except for the post earthquake stability analysis.
A check/confirmation of the values is required after the excavation to the final depth, par-
ticularly for the right abutment and the riverbed area.
8 ANNEXES
1 Results of Laboratory Tests on Rock Core Samples
2 Rock Mass Properties for Dam Design
June 2009
Upper Paunglaung Hydropower Project Annex 1
Mission Report of H.R. Frei & O.Voborny 15.06.2009
June 2009
Upper Paunglaung Hydropower Project Annex 2
Mission Report of H.R. Frei & O.Voborny 15.06.2009
June 2009
Customer The Republic of the Union of Myanmar
Ministry of Electric Power
Department of Hydropower Implementation
February 2015
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
PRELIMINARY
BASIC FEASIBILITY REPORT
Report No.
UPL-00-BFR-PREL/0405
ATTACHMENT NO.1
SEISMIC HAZARD STUDY
April 2005
Hydropower Plants
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 2
Table of Contents
page
1 General ........................................................................................................................... 3
2 Seismotectonic framework.............................................................................................. 3
2.1 Global setting.................................................................................................................. 3
2.2 Structural provinces and their seismicity ........................................................................ 4
2.2.1 The Indoburman Ranges or Folded Belt......................................................................... 4
2.2.2 Central Lowlands ............................................................................................................ 4
2.2.3 Eastern Highlands .......................................................................................................... 5
8 FIGURES...................................................................................................................... 29
9 List of References......................................................................................................... 36
10 APPENDIX.................................................................................................................... 39
10.1 Appendix 1a - Relationship Magnitude - Fault Rupture Length .................................... 39
10.2 Appendix 1b - Relationship Magnitude - Maximum Fault Displacement....................... 39
10.3 Appendix 1c - Seismic Moment relationships ............................................................... 39
10.4 Appendix 1d - Attenuation relationships ....................................................................... 40
10.5 RELATIONSHIP : Campbell, 1997 ............................................................................... 41
10.6 RELATIONSHIP : Boore et al, 1997, for Western North America................................. 42
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 3
1 General
During the last 200 years, Myanmar has suffered from more than 20 large earthquakes.
This high level of seismicity is related to the active tectonic processes that affect this
region, seated across a zone of complex interaction between the Indian and the South-
east Asia lithospheric plates.
This situation calls for a careful evaluation of the seismic environment of the Upper
Paung Laung dam project.
In order to provide basis for such evaluation, the earthquake exposure of the dam site
must be characterized in terms of likely seismic ground motions, through an analysis of
the regional seismic history, its level and its relationship with the regional tectonic pat-
tern and evolution. The delineation of the geological structures (e.g. large active faults)
causing or likely to cause the seismic activity, i.e. the earthquake sources, as well as
the characterization of these sources in term of seismic potential and earthquake sizes,
are the main purpose of such analysis.
2 Seismotectonic framework
The tectonics of the region has been, from early Mesozoic times up to present, largely
governed by the interaction of the northward to north-eastward moving Indian plate with
the Eurasian/Southeast Asia plate to the N and NE. The Indian plate comprises most of
the Indian ocean floor, carrying on its back an “island” of continental lithosphere, result-
ing from the fragmentation of former Gondwanaland in late Paleozoic times, later to be
India. Up to early Cenozoic, most of the convergence between the N-NE moving Indian
plate and Asia was probably accommodated by underthrusting of ocean floor (subduc-
tion) at the southern continental margin of Asia. With the arrival of India, a continental
fragment, at this margin, interaction changed from subduction to collision, which origi-
nated the building up of the Himalayan chain during Cenozoic times. Meanwhile, un-
derthrusting of the north-eastern/eastern part of the Indian plate, made of oceanic
crust, beneath southeast Asia, continued at the Sunda, Andaman-Nicobar and bur-
mese arcs.
Yet, the northward drift of the Indian plate did not stop with the collision. Acting as a
huge indenter, deeply driven into south Eurasia, the continental crust of India has con-
tinued to move by underthrusting beneath the Himalayas and the southern Tibet Pla-
teau. Such a process of continental subduction, which involves considerable friction,
has originated a regime of high compressional stresses, which affect the Eurasian plate
over considerable distances inland to the N, NE and E of the collision zone.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 4
Located at the north-eastern edge of the “Indian indenter”, Myanmar and its surround-
ing regions represent a transition zone between the main Himalayan collision belt and
the Indonesian Arc (where the Indian plate is at present subducting under Southeast
Asia), which must accommodate the large strike-slip movement of India with respect to
southeast Asia.
This complex history of changing tectonic styles, involving subduction, collision and
strike-slip deformation, is well reflected in the regional physiography and structural
provinces of Myanmar.
The description of the structural provinces is partly borrowed from Le Dain et al. (1984),
from which the structural map figure 1 (in section 8 of this report) is extracted.
The ranges display a curved shape in plan, with structural trends swinging from a NE-
SW direction in the north to NW-SE direction in the south. They are mostly formed of
thick turbiditic Cretaceous to upper Eocene shales and mudstones (flysh), which were
tightly folded and sliced into thrust sheets during cenozoic times as a result of the sub-
duction of the Indian plate under the Asian plate. The flysh is overlain by Miocene del-
taic or freshwater molasse along the western edge of the ranges.
The roughly parallel, overall NS trending folds imply EW shortening, becoming NW-SE
farther north. This deformation has probably continued until recent times, as suggested
by the presence of affected Pleistocene beds in the eastern part of the Ganges plain.
Following the alignment of the ranges is a well developed and elongated zone of inter-
mediate and large depth earthquakes, dipping eastward at about 45° (Benioff zone).
This distribution of foci suggests the existence of a subducted slab of oceanic litho-
sphere under the eastern part of the ranges. In the recent (past half century) seismic
history of the ranges, the largest earthquakes (M ≥ 7) in the ranges have originated
from intermediate and deep foci. Scattered shallow seismicity is also present, though in
the form of small events.
East of the Indoburman ranges, the Central Lowlands extend NS as a broad fluvial
plain, approximately 200 km wide. A NS line of volcanic rocks divides the Lowlands into
a western and an eastern trough. Both troughs are filled with molasse, deposited under
deltaic and fluvial conditions. Sedimentation started in Eocene times in the western
trough and in late Oligocene-early Miocene in the eastern trough. Total thickness of
Tertiary and Quaternary in the SE part of the Lowlands could be in excess of 10 km,
and might reach 17 km. Curray et al. (1979) suggest that the sediments are underlain
by oceanic crust continuous with the Andaman Basin.
The Pegu Yoma volcanic line is marked by discontinuous outcrops of essentially ande-
sitic but locally basaltic and rhyolitic volcanic rocks, interbedded with fluvial sediments.
Volcanic activity began in intermittent bursts in the late Oligocene to early Miocene,
apparently peaked in the Pliocene, and ceased in the Quaternary.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 5
At places along the western side of the lowlands, the Tertiary molasse is thrust over the
Upper Cretaceous and Eocene flysch series of the Indoburman ranges. Gentle folding
also affects the lowlands in many places.
Except for its eastern boundary, which is marked by the large seismically active Sa-
gaing Fault, the seismicity of the whole area is scarce and characterized by small
earthquakes only.
The NS trending right-lateral strike-slip Sagaing Fault, which can be traced for about
1000 km, is probably the most significant tectonically active feature of Myanmar, with a
history of numerous large earthquakes (see below).
East of the Shan scarp, and of the Sagaing Fault, the Shan Plateau rises above the
central lowlands. Structurally it belongs to the Indochina Platform, the south-western
part of the continental Eurasian plate. Its basement is composed of Precambrian gran-
ites, gneisses and schists and its western part has been affected by folding and meta-
morphism.
The most tectonically active area of the Plateau develops essentially east of meridian
98°, and is affected by several systems of conjugate strike-slip faults with an history of
significant earthquakes.
The western part, which comprises the project area, is of low seismic activity. North of
latitude 19°, only a few faults of significant length are present, oriented NNW-SSE to N-
S. Some are suspected to be active, but definite evidence is still lacking. Le Dain et al.
(1994) indicate that, in most of the Eastern Highlands, it is difficult to separate active
from older tectonic structures with Landsat imagery.
On the seismotectonic map of figure 2 (section 8), whose background is the structural
map figure 1, two of the faults indicated as “less important” on figure 1 of Le Dain et al.,
have been added (note : thick bold lines are well recognized major active faults).
One, south of 20.40°, appear to be a portion of the large Paung Laung Fault, which, to-
gether with the Nwalabo Fault to the north (not represented on the map), is part of the
Shan scarp (Bender, 1983). This is a structure possibly dating back to the Paleozoic,
with clear evidences of displacement during the Jurassic and mostly during the Ceno-
zoic. The small lineament, branching from the Paung Laung Fault in NW-SE direction
at about latitude 20° (see figure 6 and 9 in section 8), is displayed in Le Dain et al. as
“major active fault” (named in this report the Panga-Bawhan Fault, dealt with under
3.4.1). To the south, the Paung Laung Fault merges with the large NW-SE trending ac-
tive Papun Fault system, responsible for a magnitude 6 earthquake on February 17,
1975.
1
CNSS = Council of the National Seismic System (US organism)
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 6
From an examination of this map, it appears that the distribution of seismicity well re-
flects the general structural subdivisions of the region and the pattern of large faults :
- The zone of intermediate and deep earthquakes is well confined to the Indoburman
Ranges, with some eastward extension for the deeper earthquakes. The Ranges
are also a region of scattered shallow seismicity, with predominantly small earth-
quakes and rare moderate events.
- East of the Indoburman Ranges, all earthquakes with magnitude ≥ 6 occurred dur-
ing the last 40 years show a good spatial relationship with known large faults. This
is the case also for most earthquakes of the period prior to 1962. Among these
large faults, the Sagaing Fault emerges as the most seismically active.
- The Central Lowlands and the western part of the Eastern Highlands exhibit a low
seismicity, in line with their relatively passive tectonic character.
This quite consistent seismotectonic picture allows a relatively simple and unambigu-
ous definition of the seismic sources likely to influence the ground motion hazard at the
dam site, although with some uncertainty concerning the seismotectonic status of faults
like the Paung Laung Fault and the Kintha-Kyaukse Fault (Kyaukse in a small locality at
about 20.06 N/96.22 E, not to be confused with the largest town of the same name
south of Mandalay).
2
NEIC = National Earthquake Information Center of the US Geological Survey
3
The different symbols refer to different focal depth ranges : open circles = “shallow” earthquakes from 0 to 33 km, open
squares = “intermediate” earthquakes from 34 to 79 km, open triangles = “deep” earthquakes ≥ 80 km. The different
symbol sizes refer to the following magnitude ranges, from small to large : 4.0 - 4.9, 5.0 - 5.9, 6.0 - 6.9 and ≥ 7.0.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 7
Subduction zones are well known worldwide as sources of very large and even giant
earthquakes. Subduction occurs at convergent (active, consuming) plate boundaries
when one of the two plates (most often of oceanic character) plunges underneath the
other and continues its descent as an inclined slab into the asthenosphere up to depths
which, in some subduction system, can exceed 600 km. The contact zone between the
lithospheric, rigid parts of the two plates, which can extend up to depths generally not
exceeding 40-50 km, can generate, by shallow thrust mechanism, giant earthquakes
(largest world recorded magnitude approachs Mw = 9). Such events are referred to as
“interplate” earthquakes.
Figure N°3 - Vertical EW section at latitude 22.15°N illustrating surface geology and the underlying
seismic zones. Geological index : 1 = crystalline basement, 2 = metamorphics, 3 = flysch, 4 = molasse,
5 = volcanics, 6 = ophiolites. From Mukhopadhyay and Dasgupta (1988)
At larger depths, the descending slab is mostly subjected to gravitational forces and
breakage occurs predominantly by “intraplate” normal faulting, which very seldom origi-
nate earthquakes exceeding Mw =7.5-7.8 (Mw = 8.3 as recorded during the 1994 boliv-
ian deep earthquake, at 640 km depth, is unique so far).
As pictured on figure 3 above, the subducted slab beneath the Indoburman Ranges
reaches about 160 km only. However it is quite active : the seismic record indicates no
less than 7 earthquakes of Mw = 7.6 in the time span from 1964 at depths in excess of
60 km, within the area of latitudes between 21.5° and 26° and longitudes between
94.5° and 95.5°.
However the presence of a subducted slab is not proof that the subduction process is
still continuing, and actually there are contradictory evidences regarding this issue.
On one side, a number of fault plane solutions from some intermediate depth earth-
quakes as reported by Le Dain et al. show P-axes (maximum compression axes) al-
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 8
most parallel to the strike of the zone instead of perpendicular to it, an unusual situa-
tion. Also the fault plane solution of 3 shallow events shows largely strike-slip faulting
with P-axes that trend nearly NS. These orientations are confirmed by Kumar and Rao
(1995). Of course, this is in contradiction with the assumption of EW or even NE-SW
convergence between the Indian and Southeast Asia plates, as implied by the orienta-
tion of the Indoburman Ranges. As additional possible indicators of inactive, or very
slow, subduction, are the absence of a well developed inland quaternary volcanism and
of a developed trench, although even the most active trench would not accommodate
the rate of sediment deposition in the Ganges-Brahmaputra Delta region.
On the other side, for Hamilton (1979), the trench is presently active, although buried,
for even the youngest turbidites of the Bengal abyssal fan are deformed near the base
of the continental slope.
Mukhopadhyay and Dasgupta (1988), in an extensive study of the available fault plane
solutions, where they partly reinterpret the solutions from Le Dain et al., report a num-
ber of low angle thrust events at the upper edge of the Benioff zone, which they regard
as evidence of continued eastward underthrusting of the Indian plate beneath Myan-
mar.
Finally, as further possible evidence of continued subduction, is the great and very de-
structive earthquake of 1762, which was felt all over Bengal, Arakan, etc., chiefly and
most severely in the north part of the east coast of the Bay of Bengal, and produced ex-
tensive changes of coast level. Richter (1958) : “In 1878 a maximum uplift of 20 feet on
the west coast of Ramree Island at 19° 10’ N was described [..] Farther north the verti-
cal displacement reversed, and there was submergence in the Chittagong district”.
Owing to such effects and location, it is very tempting to regard the 1762 earthquake as
a possible great shallow thrust, “interplate” event.
During the 19th century, other earthquakes have affected the coast :
Table 1 - Major earthquakes in the coastal area during the 19th century.
Descriptions and qualified locations from Chhibber (1934) as reported in
Le Dain et al. (1984).
Longitude figures for earthquakes in the table above point to locations close to the Sa-
gaing Fault, and one can be surprised by the position of this False Island about 210 km
due north from Rangoon ! Note that location of Ramree Island is centered about 19° N
93.8° E. Two possibilities arise : either this series of earthquakes had a location near
the coast, in which case they could be of shallow-thrust type and the longitude values
could be in error by 2 degrees (transcription error ?) or the longitude values are correct
and the earthquakes might have originated from intermediate depth in the subducted
slab. In either possibilities, the earthquakes would be related to the subduction zone,
not to the Sagaing Fault (shallow strike-slip earthquakes attenuate too strongly to pro-
duce effects of the type described at more than 200 km from their source).
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 9
On December 26, 2004 a giant earthquake of magnitude 9.0 was generated by rupture
of a segment of the Indian-Eurasian plate interface off the coast of Sumatra, at the ori-
gin of the catastrophic tsunami still in everybody memory.
Although, structural environment of the subduction zone in Burma differs from the one
in Sumatra, the fact that we are dealing in both regions with the same plate interfaced
cannot obviously be eluded.
Finally, for the purpose of the present study, we will assume that :
• subduction of the Indian plate beneath the Eurasian plate is still active, even at
a slow rate, off the Myanmar coast, and can produce, in the future, large shal-
low thrust earthquakes of up to magnitude Mw = 9.0 (similar to the magni-
tude of the December 2004 event off Sumatra) with rupture area extending to
50 km depth as a maximum along the plate interface in east direction, and ap-
proaching the Upper Paung Laung dam site by a minimum distance of 260
km (as calculated from the geometry of the Benioff zone as pictured on figure 3
above),
• the subducted slab of oceanic Indian plate lithosphere below the Indoburman
Ranges, of very high seismic activity, can produce, in the future, large interme-
diate to deep focus earthquakes of up to magnitude Mw = 8.0 at a minimum
distance of 200 km from the Upper Paung Laung dam site (as calculated
from the geometry of the Benioff zone as pictured on figure 3). This corre-
sponds to a focal depth of 100 km.
The Sagaing Fault is visible on Landsat imagery as a very clear-cut lineament, a nearly
straight and narrow furrow, characteristic of very active strike-slip faults, which can be
traced for about 1000 km. It is known to extend southward in the Andaman Sea floor,
where it merges with a system of north-northwest striking transform faults, these being
in turn connected in the south with the Great Sumatra Fault. The strike-slip movement
of India with respect to southeast Asia is accommodated, in large part, by displacement
along this extended system of dextral faults, the other part being accounted for by
oblique subduction of the Indian plate beneath the Asian plate along the Sunda arc
(Sumatra), the Andaman-Nicobar arc and, possibly also (as seen above), along the
burmese arc.
Actually, the possibility that the latter subduction zone might be no longer active would
increase in proportion the importance of the Sagaing Fault in the kinematics of the In-
dian plate, to the point that this fault could be viewed as the modern Indian/Asian plate
boundary in the Myanmar region.
Curray et al. (1979) suggest some 460 km of cumulative movement (450 km of post-
early Miocene dextral displacement according to Mitchell, 1993) along the fault, assum-
ing that slip on it absorbs the full opening of the Andaman Sea. With an inception time
for such opening dating back to middle Miocene (about 13 millions years ago), this
would amount to an average displacement of 3.5 cm/year along the fault during this pe-
riod, a very high figure.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 10
In a recent study, Chamot-Rooke et al. (submitted), using GPS data from the Geo-
dyssea project results, propose a velocity of India relative to Sundaland (southwestern
part of southeast Asia) of 3.6 cm/year along a south-north direction.
However, there is geological evidence from the faulted regions that the Sagaing Fault
probably accomodates only a fraction of the relative displacement between the Indian
plate and southeast Asia : radiometric ages for the recent Singu basaltic flows (Man-
dalay district), offset by the fault, as reported by Bertrand et al. (1998), suggest relative
displacements of the fault comprised between 10 ± 1 and 23 ± 3 mm/year for the last
0.25 to 0.31 million years. As we will see below, these figures match very well the value
calculated from the total seismic moment of earthquakes occurred along the fault dur-
ing the 20th century.
The recent history of large earthquakes along the Sagaing Fault between latitudes 17°
N and 27° N is summarized in the table 2 below :
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 11
The location at 21° N / 97° E places the epicenter 1° (105 km) east off the fault trace.
However, such location on the coordinate grid reflects the limited resolution accuracy of
the seismic network in the first decades of the 20th. In 1912, location errors by (at least)
one degree were not uncommon in this region of the world, even for large magnitude
earthquakes, and the earthquake may actually be mislocated. As a matter of fact, an
isoseismal map established by Brown in 1914, of the 1912 earthquake, known as the
“Mandalay earthquake”, shows the zone of maximum intensity IX very close to Man-
dalay, strongly suggesting an origin at the Sagaing Fault. The importance of the event,
initially assigned a magnitude of 8 (7.6 according to a recent reevaluation by Pacheco
and Sykes, 1992) provides additional support to this origin, as there are not many faults
in the region able to release such an earthquake.
As the seismotectonic map shows, the fault apparently exhibits more seismicity in its
south and north segments than in the central segment, the one closest to the dam site.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 12
16.5 to 17.0
17.0 to 17.5
17.5 to 18.0
18.0 to 18.5
18.5 to 19.0
19.0 to 19.5
19.5 to 20.0
20.0 to 20.5
20.5 to 21.0
21.0 to 21.5
21.5 to 22.0
22.0 to 22.5
22.5 to 23.0
23.0 to 23.5
23.5 to 24.0
24.0 to 24.5
24.5 to 25.0
25.0 to 25.5
25.5 to 26.0
26.0 to 26.5
26.5 to 27.0
27.0 to 27.5
Figure 4 - Distribution of earthquakes along the Sagaing Fault during the
20th century.
In the bar chart of figure 4, the X-axis represents latitudes by intervals of 0.5 degree.
Bar heights are a representation of the total number of earthquakes recorded in each
latitude interval for different periods and magnitude ranges as indicated in the legend.
The 1912 and 1956 earthquakes are emphasized in consideration of the fact that they
may NOT be related with the Sagaing Fault (alternate location and alternate focal depth
for the 1912 and 1956 events respectively). If these two uncertain Sagaing earthquakes
are removed from the chart, there appears a seismic quiet zone, a “seismic gap” ex-
tending from latitude 19° N to latitude 23° N, an approximately 440 km long segment of
the Fault with no earthquake of magnitude 7 and more during the 20th century and no
earthquake of magnitude 5.5 and more during the past 40 years. The complete record
includes only one event of magnitude 5 and very few events of lesser magnitude lo-
cated in the “gap” during the latter period.
Seismic gaps, i.e. zones of temporary seismic quiescence, known to have hosted large
earthquakes in the past, are common along major seismic zones. They are considered,
and actually turn, to be the sites of future large events. The size of the gap provides an
estimate of the size of the future rupture, i.e. an estimate of the size of the earthquake
itself, as the gap tend to be “filled” in one single large event rather than in successive
smaller events.
Using a recent relationship between magnitude and length of fault rupture in strike-slip
earthquakes (see appendix 1a), we calculated that the size of the earthquake neces-
sary to break the whole 440 km of the possible gap along the Sagaing Fault is Mw = 8.1
(median value). This provides a reasonable measure of the Maximum Credible Earth-
quake along the Sagaing Fault at the shortest distance from the dam site (see below).
This is also a conservative estimate, since the 1912 and 1956 earthquakes are dis-
counted. Re-incorporation of the 1912 earthquake would reduce the “gap” to approxi-
mately 160 km (Mw = 7.6), and to about 100 km (Mw = 7.4) if the 1956 earthquake is
added.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 13
We have now to consider the possible recurrence interval of such large events.
In this purpose, we calculated an estimate of the total seismic moment (see appendix
1c for details) along the Sagaing Fault for the data period 1900 - 2004. There are dis-
tinctive advantages in using seismic moment as a measure of earthquake size, as the
moment is directly related to the geometry of the fault rupture and to the co-seismic
displacement along the fault, and scales linearly with the energy released in the earth-
quake.
Entering this value of 18.6×1020 N.m into the equation for the moment (see appendix
1c) yields an average annual rate of displacement along the fault of 14.3 mm/y well in
the range of values (10 to 23 mm/y) calculated by Bertrand et al. (1998) from radiomet-
ric data (see above).
From table 3, it can be seen that the seismic energy released by the fault during the
second half of the last century (1951-2001) only amounts to one third of the corre-
sponding value for the first half of the century (1900-1950). This is not a contingent fea-
ture of this particular fault : Triep and Sykes (1997) have shown that, following the giant
Assam earthquake of August 15, 1950, and the Gobi-Altai earthquake of 1957, the rate
of moment release dropped by a factor of 5.6 in the whole of continental Asia. The As-
sam earthquake is the largest earthquake worldwide in an intracontinental area of the
past 100 years and the largest event in that period outside subduction zones. Its mag-
nitude was Mw = 8.6 and its seismic moment reached 90 to 95×1020 N.m, i.e. more than
5 times as large as the total moment released by earthquakes along the Sagaing Fault
during the past century. The epicenter was located at 28.7° N / 96.6° E, quite in the
alignment of the northernmost branch of the Sagaing Fault. Although this looses sur-
face expression north of 26° N, a deep connection should be regarded as possible. Ac-
cording to Triep and Sykes, the location of aftershocks (Chen and Molnar, 1977) sug-
gest a complex pattern of rupture on more than a single plane that appears to have in-
volved both thrust faulting at the eastern end of the Himalayan plate boundary and de-
formation, perhaps strike-slip motion, along the adjacent NNW striking plate boundary
in Myanmar.
The regional influence of the Assam earthquake on the rate of moment release in Asia,
and along the Sagaing Fault, is of relevance for assessing the recurrence interval of
large earthquakes along the Sagaing Fault. The pre-1950 annual rate has been 23.5
mm/y and the current, post-1950, rate is 7.2 mm/y only, whereas the overall 20th cen-
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 14
tury rate amounted 14.3 mm/y, similar to the long-term (several thousands years) rate
calculated from geological data by Bertrand et al. (1998).
This similarity between rates calculated from geological and earthquake data is impor-
tant in another respect. It means that, along the Sagaing Fault, the total long-term dis-
placement can be accounted for by summation of individual displacements produced
during successive large earthquakes. Since the size of an earthquake is directly related
to the relative displacement achieved by rupture along the fault (see appendix 1b for a
relationship), this provides a means of assessing the recurrence interval of earthquakes
of different sizes, given the knowledge of the long-term displacement. For example : if
along a given segment of a fault having a long-term displacement rate of 0.5 cm/y, a
100-cm relative displacement is achieved during a single earthquake of a certain size
(M = 6.8 with the relationship used in this report), a crude estimate of the average re-
currence interval of events of the same size along this segment can be obtained sim-
ply : 100/0.5 = 200 years.
The following table 4 presents estimates of recurrence intervals calculated in this way
for earthquakes of different sizes along the Sagaing Fault and for the three displace-
ment rates mentioned above.
The post-1950 rate is certainly temporary, in any case not likely to last more than a few
decades, so that it may underestimate the recurrence interval of earthquakes of magni-
tude ≥ 7 in the next future. The overall rate is the most appropriate for the purpose of
assessing the long-term hazard at a particular site. The pre-1950 rate corresponds to
the upper bound of the long-term displacement rate calculated by Bertrand et al.
(1998), thus allowing to place a lower bound on the recurrence interval.
Finally we will consider, for the largest earthquake, a magnitude Mw = 8.1 earthquake
affecting a segment of the Sagaing Fault at the closest distance from the Upper Paung
Laung Dam Site, i.e. 45 km.
The Paung Laung Fault runs NNW-SSE at a shortest distance of 3-4 km east of the
UPL Project Dam Site (see figures 8 and 9 in section 8).
As mentioned under 2.2.3, this large fault, together with the Nwalabo Fault to the north,
is part of the Shan scarp (Bender, 1983). Garson et al (1976, quoted in Bender) were
able to show that the movements along the Paung Laung Fault commenced in the Ju-
rassic but took places for the most part during the Tertiary. However, the region in the
immediate vicinity of the Paung Laung Fault was already tectonically active during the
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 15
Paleozoic. It separates the Jurassic-Cretaceous Paung Laung Formation from the Or-
dovician to Jurassic sedimentary series of the Shan Plateau in the area of Neyaungga,
towards the south as far as latitude 20° N. The fault appears clearly still further S on
satellite images, then it changes direction to the SE as a bundle of lineaments E of Py-
inmana and, where the Salween forms the border between Burma and Thailand, it runs
into the territory of Thailand.
On the Geological Map of Burma (Bender, 1983, not reproduced herein) the fault
shows up as a discontinuous feature, especially in the UPL region, where it appears
quite segmented and offset.
On the Structural Map of Burma (not reproduced herein) included in Bender, which is a
Landsat imagery interpretation, the fault appears as a set of disconnected photo-
lineaments, but none can be seen in the close vicinity of the site.
From these references, and from the historical earthquake record, the fault shows no
evidence of present-day tectonic activity nor of any possibly related seismic activity.
However in view of the closeness of this once important fault to the UPL dam site, we
realized an independent analysis of Landsat 7 satellite images over most of the length
of the fault, especially within 20 km of the dam site area.
Actually, the fault does appear very segmented and offset by minor faults, and it is im-
possible to trace individual fault segments over distances in excess of a few km, with
gaps in between of about the same length. In addition, parallel segments are present,
in such a way that it seems more appropriate to talk of a fault zone than of a single
fault. Geomorphic features associated with the fault segments are erosional, and none
can be interpreted as indicative of present-day tectonic activity.
However, as a conservative step and on a trial basis, we checked the potential effect of
a nearby fault segment (see figure 8 in section 8), under the unlikely assumption that
this fault segment could be presently active. In view of the segment length the associ-
ated magnitude could reach Mw = 5.5 in case of rupture, with a minimum site-
rupture distance of 6 km.
The Panga-Bawhan Fault (so named by us from two nearby localities), has been iden-
tified by Le Dain et al, 1984, as an active fault based on satellite image examination.
From our independent analysis, we agree with this attribution at least for a segment of
10-12 km, which shows a distinct fault scarp in the eastern part of the trace (see figure
9 in section 8). The fault runs in NW-SE direction to the east of the Paung Laung Fault,
but, according to our observation, it would not intersect the latter. Assuming that the
fault is an active fault, and that a rupture would involve the full length of the fault trace,
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 16
The Kintha – Kyaukse Fault , NW from the site (see figure 9), shows up as a con-
spicuous fault lineament on satellite image (again the fault has been named from two
nearby localities). Note that the second one should not be confused with the larger
town of Kyaukse, just south from Mandalay. The trace is especially sharp in the west-
ern portion of the fault, close to Kintha. Although there is no indication that the fault
could be tectonically or seismically active, we considered such activity as possible.
Based on the fault length (24 km) a maximum magnitude of 6.7 is assumed at a
closest distance to site of 22 km.
Based on these two parameters, the ground motion at the site (most frequently the
peak horizontal ground acceleration) is calculated by the means of an attenuation rela-
tionship.
For this study, the following attenuation relationships have been used : Youngs et al,
1997, for subduction zone environment and Campbell, 1997, for intraplate environment
(see Appendix 1d for details on the attenuation relationships). It is important to note
that both relationships are considered particularly relevant to the seismotectonics of the
Upper Paung Laung project region. The subduction zone relationship has been devel-
oped from data recorded in regions of plate convergence worldwide, quite similar to the
Indoburman subduction zone, and most records used in the development of the intra-
plate relationship come from California, a region dominated by strike-slip tectonics (San
Andreas Fault) similar to the Sagaing Fault environment. An alternate choice for such
environment would be the relationship of Boore et al (1997), which is even more spe-
cific of strike-slip fault environment than the Campbell’s one. However Campbell pro-
vides prediction models for both the vertical and the horizontal components of the
ground motion, while the alternate model is for peak horizontal acceleration only. In
addition differences are not very significant between the two models, as can be seen
by the results in table 5 below.
In the use of the attenuation relationships, we consider soft to hard rock foundation
conditions.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 17
[1] Campbell (1997), for strike-slip fault mechanism and hard rock foundation condition
[2a] Youngs et al (1997) – Slab Interface, rock foundation
[2b] Youngs et al (1997) – Slab Interior, rock foundation
[3] Boore et al. (1997), for strike-slip fault mechanism and hard rock foundation condition
[4] Vertical accelerations produced by the strike-slip earthquakes are calculated directly from the
Campbell’s relationship. Vertical accelerations for the other earthquakes are estimated from the
ratio between the vertical and horizontal components of the Campbell’s relationship
[5] For the Campbell’s relationship, we use a distance of 12 km for the PLF Fault, in accordance with
the distance definition considered in the derivation of this relationship, i.e “the shortest distance
between the site and the presumed zone of seismogenic rupture” (re. Appendix 1d), assuming a
rupture depth of 10 km, a standard value for the depth of the seismogenic zone. For the Boore et
al relationship, the definition of distance is the “closest distance to the surface projection of the
fault rupture”, (re. Appendix 1d), so the distance entered in the formula is 6 km, the surface dis-
tance. For the Kintha-Kyaukse Fault, at 22 km, the focal depth is no longer a controlling factor.
Only the top four seismic sources of table 5 are of consideration, and it can be seen
that they give quite similar results.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 18
So, the Sagaing Fault earthquake is considered the controlling event for the MCI, and
the peak ground acceleration of 0.15 g is assumed to result from this event.
MCE = 0.15 g from a magnitude 8.1 earthquake along the Sagaing Fault.
For a given seismic source (extended source) and an observation period of sufficient
duration, there exists, from Gutenberg and Richter (1954), a simple relationship be-
tween the magnitude M and the number N of earthquakes with m ≥ M occurring during
the observation period. The Gutenberg-Richter (GR) is commonly expressed in the
form :
Log N = a – bM (equation 1)
with a and b, empirically determined parameters. For computational purpose, the more
tractable exponential form is frequently adopted :
NM = α.e-βM (equation 2)
λM = λ0e-βM (equation 3)
where λM = the average annual number of events with m ≥ M and λ0 = the average an-
nual number of events with m ≥ 0.
The annual probability of occurrence of at least an event during a t years period would
be :
The Poisson-exponential recurrence model assumes that the times between earth-
quake occurrences are exponentially distributed and that there is some time between
occurrences of particular magnitudes. Therefore, the time of occurrence of the next
earthquake is independent of the elapsed time since the previous one. Also, the Pois-
son process has no “memory” in that the magnitude of the next earthquake will not de-
pend on the magnitude of any past events. Finally, the magnitude, locations and times
of occurrence of earthquakes are independent.
- The seismic source must be clearly delineated on the basis of its geological
and seismotectonic features,
- The time period of the catalog must be long enough to satisfy the assumption
of stationarity, i.e. the number of earthquakes must provide a satisfactory ap-
proximation of the long-term earthquake rate and seismotectonic regime of
the source,
- For the period, the catalog must be as complete as possible for all magnitudes
within the range of interest,
Provided these statistical requirements are met, the GR-model used in combination
with a Poisson-exponential recurrence distribution represents a satisfactory basis for
the probabilistic evaluation of earthquake hazard in seismic environments character-
ized by large area sources encompassing many faults, because the model implies a
relatively stationary process, whereby seismic events of all sizes occur continually.
However, when the hazard is dominated by a single large fault, like the Sagaing Fault,
it has been shown (in particular by Wesnousky, 1994) that the GR/Poisson model is not
representative of the seismic distribution of the largest earthquakes. However the
model is acceptable within magnitude ranges whose upper bound is 1 to 1.5 magni-
tude unit below maximum and will not underestimate the occurrence of events of a
given size where the elapsed time since the last event of this size does not exceed the
average time between such events (Cornell and Winterstein, 1988).
There is only one source in Myanmar for which the model could apply : the subducted
slab of Indian plate lithosphere below the Indoburman Ranges. However this source
appears practically irrelevant to the earthquake hazard at the dam site. At closer dis-
tance, and with the notable exception of the Sagaing Fault, other potential sources of
earthquake exhibit a very low rate of activity, if any.
Owing to the fact that a classical probabilistic hazard assessment appears not applica-
ble to the case of the Upper Paung Laung dam site, we will select the OBE accelera-
tion based on the following procedure and assumptions :
• The Sagaing Fault controls almost exclusively the earthquake hazard, both in
terms of rate and size, at the dam site for acceleration levels of engineering in-
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 20
terest (say ≥ 0.1 g), and consequently will be considered the sole source of
earthquakes for this purpose,
• the knowledge of the average displacement rate of the Sagaing Fault provides
a means of estimating the recurrence time of earthquakes of different sizes,
• the recurrence time between earthquake can be described by the Poisson-
exponential recurrence model.
We will consider concurrently two levels of exceedence probability often used in OBE
selection procedures : Level 1 as this event with 50% probability of exceedence during
a 100-year period, and Level 2 as this event with 10% probability of exceedence dur-
ing a 50-year period (the basis for seismic zoning in the United States, see below) both
events resulting from earthquakes occurred along the Sagaing Fault at the closest dis-
tance from the site.
MLevel 1 = 7.13
MLevel 2 = 7.63
The resulting peak ground accelerations (PGA) at the site can be finally obtained by
application of an attenuation relationship to these values of magnitude and a distance
of 45 km.
The recommendable OBE value lies in the range 0.07 - 0.12 g and selecting the final
level in a matter of engineering judgement, including the evaluation of the degree of
conservatism involved in the procedure implemented for the derivation of the above
values. In this respect, two aspects deserve mention :
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 21
- The time elapsed since the occurrence of the 1912 “Mandalay” earthquake (pro-
vided it occurred along the Sagaing Fault) is 89 years, and the time since the previ-
ous “Mandalay” earthquake of 1839 is 162 years. In both cases the rupture is likely
to have reached the closest point to the dam site along the Sagaing Fault. For the
Level 1 earthquake we may be at the limit of applicability of the Poisson-recurrence
model (i.e. the model may underpredict the future occurrence of such event).
- We consider, in the procedure, the sole influence of the Sagaing Fault. Although it
is very doubtful that such simplification might lead to a severe underestimation of
the hazard, not all experts, probably, would agree that the procedure is sufficiently
conservative.
In conclusion, we consider appropriate to recommend selecting, for the OBE, the Level
2 event, with 10% exceedence probability in 50 years, at the highest value of the
range, i.e.
The world record so far lists 11 cases where the largest triggered earthquake had a
magnitude of 5 or more. In 5 of these cases, the earthquake exceeded magnitude 6.
In only one case (Koyna, India, 1967), damages inflicted to the dam were severe
enough to be of concern. However, these damages were related to a quite unusual de-
sign which turned out very unfavorable upon seismic loading. In addition, provisions for
earthquake resistance were minimal, as the dam region was, prior to the 1967 event,
considered free of seismic activity. Loss of live resulted from the direct effects of the
earthquake, not from the damages to the dam.
These eleven cases represent only a small fraction of the large and deep artificial res-
ervoirs in the world. Of course, many more reservoirs produced RIS in the form of small
to very small quakes, posing no serious threat to the dams nor to public safety.
Depth and size of the reservoirs are major factors controlling the size of the earth-
quake. The smallest height of dams reportedly associated with some form of RIS, al-
though not damaging whatsoever, is 36 m.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 22
Table 7 - The largest earthquakes related to accepted RIS cases (data from Gupta,
1985, except for Tillari dam, USGS, 1996, and Marathon Dam, Vladut, 1993)
The incidence of even very small increments of stress is well illustrated by the fact that,
in several well documented cases of RIS, earthquakes tend to occur in close time rela-
tionship with sharp changes in reservoir level, even of moderate amplitude, rather than
at maximum reservoir level. This is especially clear for Koyna and Oroville. Rate of
level variation is also important, and Gupta (1985, 1992) recommends that, where con-
trollable, smooth emptying/refilling operation be implemented. It seems that, at Koyna,
rates of less than 12 meters per week are sufficient to prevent RIS of magnitude 5.0
and more from occurring.
In most cases of large events triggered by reservoir, the existence of a pre-existing ac-
tive fault in the close vicinity of or crossing the reservoir has been proved. Several
times however, the definite proof of the fault activity was the occurrence of the earth-
quake itself and its fore- and/or aftershocks.
In some cases, RIS events have occurred, and are still occurring, well outside the pe-
rimeter of the reservoir and up to 20 km. In these cases however, the earthquakes
were generated along a fault crossing the reservoir. Koyna, Aswan and Oroville cases
are good illustrations of remote fault link between reservoir and hypocenters. Interest-
ingly, these reservoirs are those in which several years elapsed between first filling and
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 23
As regards the several factors likely to influence the level of RIS hazard, Woodward-
Clyde Consultants (1977), summarizing the results of a worldwide study, mentioned the
following :
The Upper Paung Laung reservoir is a large and deep reservoir which enters the cate-
gory of impoundment sizes for which the largest induced earthquake magnitudes have
been recorded. However size controls only the level of the RIS, given RIS occurs. Oc-
currence of RIS depends on other factors, as indicated above.
On the other side, the Paung Laung Fault will be affected by the reservoir, and we
know that it should be considered as potentially active.
In conclusion, the potential for reservoir induced seismicity can be regarded as small to
medium, although the occurrence of a RIS event of magnitude between 5 and 6 as a
maximum should be considered a worst case. Provision for such an event is already
included through consideration of the possible occurrence of a local Paung Laung Fault
earthquake of magnitude 5.5 at 6 km from the dam site.
The median value of the Maximum Credible Earthquake (MCE) acceleration is 0.15 g
and the controlling event would be an earthquake of magnitude Mw = 8.1 along the
Sagaing Fault, at 45 km to the south of the Upper Paung Laung dam site. However, in
view of the large uncertainties inherent to attenuation relationships, it is a common
practice for safety purpose to take for the MCE the peak ground acceleration at one
standard deviation above the median (in a lognormal distribution, this corresponds to
the 84th-percentile). The standard deviation σlnPGA is 0.52 for the Boore et al relation-
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 24
ship and 0.44 for the Campbell’s relationship (see appendix 1b). The former value will
be selected, and the 84th-percentile peak ground acceleration (PGA84) is calculated in
the following way:
Following this well established and conservative practice, the acceleration value rec-
ommended for the Maximum Credible Earthquake (MCE) is:
MCE = 0.25 g
The controlling event would be an earthquake of magnitude Mw = 8.1 along the Sa-
gaing Fault, having a recurrence interval comprised between 870 and 1500 years (ta-
ble 4).
The extra-conservatism introduced in the selection of the MCE is not justified for the
selection of the OBE, which is a non-safety related parameter. Since the determination
of the OBE already includes some conservative steps (see section 5), there is no rea-
son to further increase its value. The acceleration value recommended for the Operat-
ing Basis Earthquake (OBE) is:
OBE = 0.12 g
In spite of the high seismic activity of Myanmar, and of the high level of conservatism
attached to the delineation of the seismic sources and to the assignment of their maxi-
mum magnitude (Mw > 6.5 for all but one source), the MCE can be regarded as quite
low. This is due to the favourable location of the dam site at some distance from the
major seismic sources.
In principle any well designed dam of all types can resist the effects of such a level of
MCE without detrimental effects.
In order to evaluate the stability of the dam subjected to earthquake load, it has been
often considered sufficient to carry out a pseudo-static or “seismic coefficient” analysis.
Such procedure uses ratios of assumed accelerations of the structure to the accelera-
tion of gravity to define the horizontal inertial force acting on the dam (seismic coeffi-
cient). In United States, for example, most regulatory agencies accept this procedure
for the seismic safety evaluation, both at feasibility and design stages, of concrete
gravity structures or well-compacted embankments with dense foundation soils in ar-
eas of low or moderate seismic activity. The selection of the seismic coefficient is made
by consideration of the seismic zone (according to the definitions of the Uniform Build-
ing Code [UBC]) in which the dam site is located.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 25
In the UBC, seismicity has been treated by designating areas with different seismic
zones. The areas with highest seismicity are designated Seismic Zone 4, while the ar-
eas of lowest seismicity are designated Seismic Zone 0. The zones are each assigned
a Seismic Zone Factor (SZF) , with Zone 4 being assigned a SZF factor of 0.4 and
Zone 0 being assigned a SZF of 0. The SZF factor can approximately be taken as the
effective zero period ground acceleration (in g’s) on soft rock that has a 10% probability
of exceedence in 50 years. In turn, the effective acceleration has be shown to be equal
or lower than the peak ground acceleration in the spectral range 0.1 to 0.5 second. In
the UBC, the seismic design ground motions for a given site are a function of the Z fac-
tor, the site soil conditions, and in Seismic Zone 4, the relative location of the site to
known active fault source zones.
Table 8 - Seismic Zones and Seismic Zone Factor in the Uniform Building
Code.
The values of the seismic coefficient recommended as minimum values by most regu-
latory agencies in the United States are as follows :
At the Upper Paung Laung dam site, the acceleration with 10% probability of ex-
ceedence in 50 years is 0.12 g, and has been taken as OBE acceleration. This would
place the dam site in Seismic Zone 1.
For Zone 1, the recommended minimum value of the seismic coefficient is equal to
0.05 time the weight of the structure. While this minimum value appears appropriate for
pseudo-static analysis under the OBE load case, a more conservative approach may
be recommendable where the design is governed by safety considerations, as for in-
stance selecting a seismic coefficient in the range between 0.06 and 0.08, or 0.09 as a
conservative maximum.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 26
At a latter stage of the project, it will be highly advisable to carry out a full dynamic re-
sponse analysis using response spectrum methods.
Until the beginning of the eighties, and based on the observation that the response
spectrum scales approximately with the peak acceleration, the common practice in the
earthquake engineering community was to use normalized spectral shapes. These had
been obtained by averaging the response spectra of several earthquakes recorded un-
der similar conditions after proper normalization at 1 g peak acceleration. Normalized
spectra were available for a set of damping ratios, for horizontal and vertical compo-
nents, for different foundation conditions and for two levels of exceedence probability
(50 % and 16 %). For a given project site, design spectra were then derived by multi-
plying the design peak ground acceleration by the ordinates of the normalized spectra
best matching the foundation conditions of the site.
Then, with the rapid growth of the strong motion record database, it became apparent
than the spectral shape, the “frequency content”, was also dependent on the magni-
tude of the earthquake and on the distance to the recording station.
At present it is a well established practice to express this dependence in the same way
as the peak ground acceleration, i.e. by the mean of empirical attenuation relationships
obtained by regression analysis on magnitude and distance, with the spectral accelera-
tion at a given period as dependent variable. The parameters of the regression vary
from period to period, i.e. there is a distinct attenuation relationship for each separate
period.
The curves are for rock foundation conditions, horizontal component, strike-slip faulting
environment, and for 5 % damping ratio.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 27
The spectral curves from Seed et al (1976), are also given for reference and compari-
son purpose. This is an example of fixed-shaped, non-magnitude and non-distance de-
pendent, normalized spectral curve, which has been widely used until recently. For
plotting, the curves have been scaled by using the average PGA-value of the Camp-
bell’s and Boore et al relationships. Although given as non-magnitude dependent, the
curve is mostly derived from data in the 5.5 ≤ M < 7 magnitude range.
Differences between the two 1997 empirical curves appear rather significant and are
likely to arise from differences in regression models rather than from the data, since the
three studies use essentially the same data base.
Which one is the best is not easy to decide. We recommend considering an average of
the Campbell’s and Boore et al curves
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 28
The complete equations, quite complicated and involving several large tables of pa-
rameters (one set for each spectral period), are not reproduced here. We recommend
obtaining a copy of the original papers.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 29
8 FIGURES
Figure 1 - Structural Map of Myanmar and Surrounding Region (from Le Dain et al., 1984,
modified)
Figure 7 - Earthquake Epicenters in the UPL Dam site region (1900 – 2004)
Figure 8 – The Paung Fault at its closest approach to the UPL Dam site region
Figure 9 – Contributive faults to the seismic hazard at the UPL Dam site.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 30
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 31
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 32
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 33
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 34
Fig. 8 – The Paung Fault at its Closest Approach to the UPL Dam Site Region
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 35
Fig.9 - Contributive Faults to the Seismic Hazard at the UPL Dam Site
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 36
9 List of References
Abrahamson N.A and Silva W.J. (1997) “Empirical Response Spectral Attenuation Re-
lations for Shallow Crustal Earthquakes”, Seismological Research Letters, vol.68, no.1,
pp.94-127
Aki K. (1966) "Generation and Propagation of G-Waves from the Niigata Earthquake of
June 16, 1964, 2, Estimation of Earthquake Moment, Released Energy, and Stress-
Strain Drop from the G-Wave Spectrum" Bull. Earthq. Res. Inst. Tokyo, 44, pp. 73-88
Bertrand G. et al. (1998) "The Singu basalts (Burma) : new Constraints for the Amount
of Recent Offset on the Sagaing Fault" Earth & Planet. Sci., vol. 327, pp. 479-484
Boore D.M. et al (1997) "Equations for Estimating Horizontal Response Spectra and
Peak Acceleration from Western North American Earthquakes : A Summary of Recent
Work” Seismological Research Letters, vol.68, no.1, pp.128-153
Chen W.-P. and Molnar P. (1977) "Seismic Moments of Major Earthquakes and the
rate of Slip in Central Asia" J. Geoph. Res., vol. 82, pp. 2945-2969
Chen W.-P. and Molnar P. (1990) "Source Parameters of Earthquakes and Intraplate
Deformation Beneath the Shillong Plateau and the Northern Indoburman Ranges" J.
Geoph. Res., vol. 95, N° B8, pp. 12527-12552
Cornell C.A. (1968) “Engineering Seismic Risk Analysis”, Bull. Seism. Soc. of Am., Vol.
58, N° 5, pp. 1583-1606.
Cornell C.A. and Winterstein S.R. (1988) “Temporal and Magnitude Dependence in
Earthquake Recurrence Models”, Bull. Seism. Soc. of Am., vol. 28, N°4, pp. 1522-1537
Curray J.R. et al. (1979) "Tectonics of the Andaman Sea and Burma" Am. Assoc. Pet.
Geol., Mem., vol. 29, pp. 189-198
Esteva L. and Villaverde R. (1973) “Seismic Risk, Design Spectra, and Structural Reli-
ability”, Proceedings 5th World Conf. Earthq. Engin., vol. 2, pp.2586-2597, Rome.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 37
Gupta H.K. (1985) “The present status of reservoir induced seismicity investigations
with special emphasis on Koyna earthquakes” Tectonophysics, vol. 118, pp 257-279.
Gupta H.K. (1990) “Worldwide status of Reservoir Induced Seismicity”, Geol. Beitr.
Geophysik, Leipzig
Hamilton W. (1979) "Tectonics of the Indonesian Region", U.S.G.S. Profes. Pap. 1078
Hanks T.C. and Kanamori H. (1979) "A Moment Magnitude Scale" J. Geoph. Res., vol.
84, pp. 2348-2350
Holt W.E. et al. (1991) "The Active Tectonics of the Eastern Himalayan Syntaxis and
Surrounding Regions" J. Geoph. Res., vol. 96, N° B9, pp. 14595-14632
Kumar M.R. and Rao N.P. (1995) "Significant Trends Related to the Slab seismicity
and Tectonics in the Burmese Arc Region from Harvard CMT Solutions" Phys. Earth
Planet. Int., vol. 90, PP. 75-80
Le Dain A.Y. et al. (1984) "Active Faulting and Tectonics of Burma and Surrounding
Regions" J. Geoph. Res., vol. 89, N° B1, pp. 473-479
Mukhopadhyay M. and Dasgupta S. (1988) "Deep Structure and Tectonics of the Bur-
mese Arc : Constraints from Earthquakes and Gravity Data" Tectonophysics, vol. 149,
pp. 299-322
Ni J.F. et al. (1989) "Accretionary tectonics of Burma and the Three-Dimensional Ge-
ometry of the Burma Subduction Zone" Geology, vol. 17, PP 68-71
Pacheco J.F. and Sykes L.R. (1992) "Seismic Moment Catalog of Large Shallow Earth-
quakes, 1900 to 1989" Bull. Seism. Soc. of Am., vol. 82, N° 3, pp. 1306-1349
Richter C.F. (1958) "Elementary Seismology" W.H. Freeman, San Francisco, Calif.
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 38
Seed H.B. et al (1976) “Site-Dependent Spectra for Earthquake resistant Design”, Bull.
Seism. Soc. of Am., vol. 66, N° 1, pp. 221-243
Seed H.B. (1982) "The Selection of design Earthquakes for Critical Structures" Bull.
Soc. Seism. of Am., vol. 72, N° 6, pp. S7-S12
Triep E.G. and Sykes L.R. (1997) "Frequency of Occurrence of Moderate to Great
Earthquakes in Intracontinental Regions : Implications for Changes in Stress, Earth-
quake Prediction, and Hazards Assessments" J. Geoph. Res., vol. 102, N° B5, pp.
9923-9948
USGS Auburn Project Review Team (1996) “Review of seismic-hazard issues associ-
ated with the Auburn Dam project, Sierra Nevada foothills, California”. Preliminary U.S.
Geological Survey Open File Report 96-0011.
Wang E. and Chu J.J. (1988) "Collision Tectonics in the Cenozoic Orogenic Zone Bor-
dering China, India and Burma" Tectonophysics, vol. 147, pp. 71-84
Wells D.L. and Coppersmith K.J. (1994) "New Empirical Relationships among Magni-
tude, Rupture Length, Rupture Width, Rupture Area, and Surface Displacement" Bull.
Seism. Soc. of Am., vol. 84, pp. 974-1002
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 39
10 APPENDIX
with :
M = Moment magnitude Mw
SRL = Surface rupture length in km for strike-slip fault
Standard deviation : 0.28
Correlation coefficient : 0.91
Magnitude range : 5.6 to 8.1
Length/Width range (km) : 1.3 to 432
From Wells D.L. and Coppersmith K.J. (1994) see List of References
with :
M = Moment magnitude Mw
MD = Maximum displacement in m for strike-slip fault
Standard deviation : 0.34
Correlation coefficient : 0.90
Magnitude range : 5.6 to 8.1
Displacement range (km) : 0.01 to 14.6
From Wells D.L. and Coppersmith K.J. (1994) see List of References
Mο = μ × L × l × d
with :
Mο = Seismic Moment in Newton.meters (Nm)
μ = Rigidity Modulus in Newton per square meter (N/m2) = 5 × 1010, a value commonly
adopted for shallow earthquake
L = Length of the fault rupture in m
l = Width of the fault rupture in m, taken equal to 20 000 in this study, a common value for
the maximum depth of the seismically active portion of most strike-slip fault
d = Average Fault Displacement in m
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 40
The relationship between Moment magnitude Mw and Seismic Moment is, according to
Hank and Kanamori (1979) :
EQUATION :
STANDARD DEVIATION :
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 41
EQUATION :
STANDARD DEVIATION :
REFERENCE : Campbell K.W. (1997) “Empirical Near-Source Attenuation Relationships for Hori-
zontal and Vertical Components of Peak Ground Acceleration, Peak Ground Velocity, and Pseudo-
Absolute Acceleration Response Spectra” Seismological Research Letters, vol.68, no.1, pp.128-
153
April 2005
DHP – Upper Paunglaung Hydropower Project
Preliminary Basic Feasibility Report – Attachment No.1: Seismic Hazard Study 42
EQUATION :
STANDARD DEVIATION :
σlnPGA = 0.520
APPLICABILITY : Magnitude in the range 5.5 to 7.5, distance no greater than 80 km,
rock and soil foundation, region of active tectonics dominated by large strike-slip fault
(California, Philippines, etc.)
April 2005
Customer The Republic of the Union of Myanmar
Ministry of Electric Power
Department of Hydropower Implementation
February 2015
UNION OF MYANMAR
MINISTRY OF ELECTRIC POWER
DEPARTMENT OF HYDROELECTRIC POWER
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
20/04/06 – 05/05/06
MAY 2006
Upper Paunglaung Hydropower Project 1
Mission Report of H.R.Frei 20.04.2006-05.05.2006
TABLE OF CONTENTS
1 PROGRAM............................................................................................................... 2
2 APPENDICES .......................................................................................................... 2
3 GENERAL................................................................................................................ 3
4 SITE VISIT TO UPPER PAUNGLAUNG, 25.-28.04.06 ............................................ 3
4.1 MEETINGS WITH DHP ON 25. AND 26.04.06 AT PL GUEST HOUSE ............ 3
4.2 SITE VISIT UPL ON 26.04.06 ........................................................................... 3
4.3 MEETING WITH DHP ON 27.04.06 AT MINISTRY OF ELECTRIC POWER .... 4
5 INVESTIGATIONS ................................................................................................... 4
5.1 GENERAL......................................................................................................... 4
5.2 DAM …………………………………………………………………………………….5
5.3 QUARRY .......................................................................................................... 5
6 DESIGN ISSUES...................................................................................................... 5
6.1 DIVERSION TUNNEL ....................................................................................... 5
6.1.1 Rock Support of Outlet Portal................................................................... 5
6.1.2 Inlet Portal Area ....................................................................................... 6
6.2 DAM FOUNDATION LEFT ABUTMENT ........................................................... 6
7 RECOMMENDATIONS ............................................................................................ 6
1 PROGRAM
20/04/06 Flight Zürich - Bangkok
21/04/06 Flight Bangkok – Yangon, meeting with resident Engineer M.Buchli
22/04/06 Flight Yangon – Mandalay, coordination meeting with Ch.Rohrer
23/04/06 Office work in Mandalay (Sunday, half day)
24/04/06 Site visit Yeywa – Coordination meeting with project manager
25/04/06 Transfer from Mandalay to Paunglaung, meeting
26/04/06 Transfer from Paunglaung to Upper Paunglaung, site visit
27/04/06 Transfer from Upper Paunglaung to Paunglaung, meeting with DHP, office
work (site instruction)
28/04/06 Transfer from Upper Paunglaung to Mandalay
29/04/06 Office work in Mandalay (UPL)
30/04/06 Sunday
01/05/06 Office work in Mandalay (Mission Report UPL)
02/05/06 Site Visit Yeywa
03/05/06 Office work in Mandalay (Site Visit Report Yeywa)
04/05/06 Office work in Mandalay
05/05/06 Departure Mandalay -Yangon - Bangkok
2 APPENDICES
1 Site Instruction dated 27/04/06 including:
Annex 1: Location of Boreholes
Annex 2: Sketch SK.CPEB.02.121/1/27.04.06
3 GENERAL
The main purpose of the Mission was the temporary replacement of the resident engi-
neer M.Buchli during his absence, covering his site activities (Upper Paunglaung) and
planning activities (Mandalay). The base of the Mission was the CPE/DHP office in Man-
dalay, from where one site visits to the Upper Paunglaung construction site has been car-
ried out during the period. A second planned visit was cancelled due to heavy rainfalls
and potential access problems.
Additionally, two site visits to Yeywa construction site have been carried out. The present
report summarises the overall program as well as the activities for the Upper Paunglaung
project. A separate report has been made about some issues regarding the Yeywa pro-
ject.
During these meeting, Colenco was informed that the heavy equipment now is mainly
used to upgrade the access road to Upper Paunglaung and that also Nancho is a high
priority project. For these reasons, actually only minimum activities are maintained on the
UPL dam site. Nevertheless, a small mobile crusher as well as three small pumps have
been brought to the site in order to be able to start some shotcrete support works at the
diversion tunnel outlet portal below elevation 306.00 m a.s.l.
Furthermore, Colenco was informed by the Deputy Minister U Myo Myint that during the
rainy season only minor activities will be maintained on the UPL dam site and that par-
ticularly the diversion tunnel excavation will not be started during this period. Therefore,
only a very limited presence of the Colenco Resident Engineer is required on site during
that time.
For the reasons mentioned above, virtually no progress was achieved since the last site
visit of M.Buchli.
The slope cut of the downstream DT tunnel outlet is now excavated down to elevation
298 m a.s.l., but the drainage trenches on the berms are not yet all excavated. Some
drilling works with jack-hammer on platform at elevation 306 m a.s.l. were being carried
out in order to install short anchors for the fixation of wiremesh.
On the left bank, investigation drilling BH32 on elevation 320 (dam axis) has been com-
pleted (metasandstone from 3-9 m depth and granite from 9-15 m) and the drilling rig will
be moved down to the toe of the dam on approximate elevation 330 m a.s.l.
In the quarry area, the drilling rig was still installed at BH31 (corner of the ridge), but no
drilling activities were going on. The granite was reportedly reached in 29 m depth and
the drilling rig will be moved to borehole BH 34 (see below). A further investigation walk-
ing tour starting from the upper bulldozer track branch revealed a granite outcrop and
granite blocks below drilling BH31 at approximate elevation 515 m a.s.l. However, the
tour could not be continued as intended in downhill direction because of heavy rain
showers in the afternoon (steep and slippery).
After the site visit, a “Site Instruction” regarding further investigation works and required
rock support measures in the outlet area has been handed over to U Kyaw Nyein in
Paunglaung (App.1 including Annexes 1 and 2).
DHP was shortly informed about the findings of the site visit, the main purposes of the
meeting were, however, other issues related to Yeywa and Tamanthi projects.
5 INVESTIGATIONS
5.1 GENERAL
The following documents were received from DHP during the site visit in UPL:
• Updated list of borehole coordinates and elevations
• List of compressive strength results (10 dry condition plus 5 in wet condition)
• Results of geotechnical tests of three samples of residual soil taken in the test
trenches of the left abutment (identification, compaction, permeability, direct shear
tests)
The rock samples selected in January and March 2006 have not yet been tested. The
Lugeon test carried out in BH32, 10-15 m depth (granite) gave a value of 5 LU. The avail-
able rock compressive strength values are scattering from about 7-200 MPa, the absorp-
tion is below 2% (with one exception).
The residual soil (overburden) consists of clayey-silty gravel with a plasticity of 10-15%,
the permeability varies from 5 x 10-6 to 3 x 10-7 cm/s. Friction angles from 28-33° were
measured and cohesion values between 15 and 60 kPa.
5.2 DAM
The next investigation drilling in the dam foundation will be BH33, on elevation 330 m
a.s.l., at the downstream toe of the dam. The following hole shall be BH26, behind the
guest house, which shall be drilled without water.
In all boreholes of the dam foundation, waterpressure tests shall be carried out. If ground
water is encountered, piezometers shall be placed in order to monitor the ground water
table.
5.3 QUARRY
The three quarry boreholes BH 28, 29 and 31 along the bulldozer track around the ridge
(Annex 1) showed important overburden heights. The next borehole to be drilled in the
quarry area has been instructed at the end of the lower branch of the track at approxi-
mate elevation of 507 m a.s.l. This borehole lies between observed granite outcrops on
similar elevations.
6 DESIGN ISSUES
The slope between the access road elevation 306 m a.s.l. and elevation 298 m a.s.l. is
now exposed. The main part of the portal face and the upstream part of the slope parallel
to the tunnel axis consists of heavily fractured rock. The rock quality is deemed to im-
prove by depth (as already visible at some locations) and the location of the tunnel portal
can hence be confirmed.
At least one unfavourable joint system regarding the tunnel slope could be identified. The
rock slopes shall therefore be systematically supported by shotcrete, welded steel fabric
and rock bolts as indicated in Annex 2 (7-10 cm shotcrete with wiremesh and 4-6 m long
grouted rock bolts). The uppermost bolt row shall have a smaller bolt spacing (1.50 m)
and longer rock bolts (6 m) in order to account for the heavy truck loads to be carried by
the access road on elevation 306 m a.s.l.
The inlet portal shall be kept as simple as possible, a transition is not considered required
downstream of the stoplogs. This reduces considerably the portal tunnel section, space
requirement for the inlet construction and reinforcement requirement in the first tunnel
stretch (the round shape is optimal to withstand possible high external water pressures
after placing of the stoplogs).
Drawing No. 65.3853.02.012, Rev.0, shall hence be revised according to the indications
given in the following sketches:
• SK.CPEB.02.012/1/01.05.06 (attached)
• SK.CPEB.02.012/2/01.05.06 (attached)
• SK.CPEB.56.000/9/01.11.05 (old sketch)
• SK.CPEB.56.000/10/01.11.05 (old sketch)
• SK.CPEB.56.000/11/01.11.05 (old sketch)
• SK.CPEB.56.000/12/01.11.05 (old sketch)
It shall be noted, that the old sketches still show the access road on elevation 308 m
a.s.l. instead of the new elevation 306 m a.s.l. according to drawing No. 65.3853.02.110,
Rev.0.
On the left abutment, possible bedding planes dipping 030/45 are prone to daylight in the
gully downstream of the dam. The orientation of the bedding planes and their mechanical
properties shall therefore carefully be investigated.
7 RECOMMENDATIONS
• Bush clearing shall be carried out at the location of the planned crushing plant
• All drainage trenches shall be completed on the berms of the downstream portal
area of the diversion tunnel
• Systematic rock slope support with shotcrete, wiremesh and grouted rockbolts
shall be carried out below elevation 306 m a.s.l. on the downstream portal face of
the diversion tunnel and on the upstream part of the rock slope parallel to the dam
axis (Jumbo and more powerful crushing and shotcrete equipment will be re-
quired).
• The requested survey works (sections) shall be carried out as soon as possible.
• Check measurement of all survey points shall be performed
• Test results of the core samples taken in January and March 2006 to be provided
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
24/09/07 – 25/09/07
SEPTEMBER 2007
1 PROGRAM
24/09/07 Transfer from Mandalay to Upper Paunglaung, site visit
25/09/07 Site meeting, transfer back to Mandalay
27/09/07 Report writing in Mandalay office
28/09/07 Flight Mandalay-Yangon-Bangkok
2 ANNEXES
1 SK.CPEB.02.032/1/26.09.07
Diversion Outlet – Additional Training Walls – Longitudinal Section
2 SK.CPEB.02.032/2/26.09.07
Diversion Outlet – Additional Training Walls – Cross Section
3 GENERAL
The main purpose of the short visit to the UPL site was the inspection of the diversion
tunnel works. The second main item which has been discussed concerned the revision of
the work schedule.
4 DIVERSION TUNNEL
GENERAL
Break through of the crown section has been celebrated in July 2007. Presently benching
of the lower part is ongoing and is scheduled to be terminated by beginning of November
2007.
INLET
The inlet excavation (Photo 1) is not yet terminated; the right side rock face of the up-
stream part has to be set back by about another 10 m. The berms have not been carried
out according to the drawings, e.g. the berm at elevation 296 m a.s.l. is completely miss-
ing. Rock bolts have been installed and a very thin layer of shotcrete applied partly. The
general stability conditions seem acceptable for a temporary structure, however, in the
lower part (below elevation 296 m a.s.l.) of both slopes, additional rock bolts and shot-
crete with welded steel fabric shall be applied upstream of the future inlet structure.
TUNNEL
The rock conditions in the tunnel are generally good and so far, only a minimum of rock
support has been applied (mainly some rock bolts in the crown), except in both portal ar-
eas, where steel ribs have been placed. However, the rock is mostly blocky and at some
locations, subvertical joints in unfavourable direction affect the stability of the rock wall
(Photo 2) and additional rock bolts have to be placed for safety reasons.
Generally, and particularly in the downstream part, considerable overbreak occurred and
the lining concrete quantity is estimated to be about twice as large as the nominal one.
OUTLET
So far, virtually no rock support has been applied in the slopes of the outlet channel.
About 10 m downstream of the portal, the rock of the right channel slope is heavily frac-
tured and unstable (Photo 3). It is therefore proposed to protect both channel slopes for a
length of 15 m by reinforced concrete walls connected to the already foreseen invert slab
(U-shape channel as shown in Annexes 1 and 2).
Photo 3: Right Bank of Diversion Outlet Slope, highly fractured zone (24.09.07)
Downstream of the concrete structure, the slopes below elevation 292 m a.s.l shall be
protected by rock bolts and shotcrete with welded steel fabric.
DIVERSION TUNNEL
The completion of the diversion tunnel including inlet and outlet structures by the end of
the coming dry season shall have first priority. The following main steps are foreseen
(see detailed program established by the CPE Site):
OTHER WORKS
As the general work schedule has been further squeezed (start of operation in 2010), the
following works shall also be carried out (see special CPE report):
Excavation in riverbed area for Separation Wall, placing of levelling concrete (or
CVC) at least to protect the foundation (bottom outlet now moved to the adjacent
block on the right side)
Excavation for dam and intake tower foundation near the riverbed area (benching
down from existing berm approx. 320 m a.s.l.)
Left bank excavation of overburden material, starting from the top
Closure of the river by placing of the upstream and downstream cofferdams
The works in the riverbed area shall be protected against dry season floods by small lon-
gitudinal embankments.
6 MISCELLANEOUS
Crown filling grouting for the diversion tunnel shall be carried out systematically
on the whole tunnel length
Any rock suitable for the cofferdam shall be stockpiled (particularly granite rock
from the intake tower and dam excavation)
Design for the separation wall and intake towers (especially foundation) has to be
carried out as soon as possible
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
23/05/08 – 25/05/08
MAY 2008
1 PROGRAM
20/05/08 Flight Zurich-Bangkok
21/05/08 Flight Bangkok-Yangon-Mandalay
22/05/08 Site Visit Yeywa (see separate report)
23/05/08 Office work Mandalay, transfer to Naypyitaw, meeting DHP
24/09/07 Site Visit Upper Paunglaung
25/09/07 Office work at Paunglaung (data collection and reporting)
2 ANNEXES
1 Excavation Left Bank – Geological Formations on the Dam Footprint area as per
24.05.08
2 Preliminary Rock Mass Parameters
3 GENERAL
The main purpose of the short visit to the UPL site was the inspection of the left bank ex-
cavation and the preliminary definition of the rock mass parameters for the dam founda-
tion. Other items discussed concerned the Powerhouse relocation and tunnel lining
works.
Participants:
been reached, with exception of the area at elevation 315-320 (see sections prepared by
Ch. Rohrer). Above this elevation, the actual excavation line is still 5-10 m higher than
the design excavation line. So far, virtually no drill and blast excavation procedure has
been applied, with exception of the access berm at el. 315 and above el. 378 (= crest
elevation).
It appears that the excavation surface is not yet as even as required but shows rather a
stair-stepped shape. At the time of inspection, a substantial part of the excavation sur-
face area was covered by loose material or material washed in from the adjacent excava-
tion slopes (heavy rains reportedly have occurred some days before our site visit). Thus,
the rock mass was exposed mainly along the steep slopes and the subhorizontal parts
were rather covered (Photo 1).
The best metasandstone rock quality was encountered along the ridge following the origi-
nal topography, i.e. coming from downstream above the crest level and joining the dam
axis somewhat further below, as shown in Annex 1. In this area, mostly slightly to moder-
ately weathered rock was encountered. However, U/S and D/S of this area, the rock
quality is rather moderately to highly weathered. This rock mass quality is less suitable,
as far as the dam footprint area is affected; in the U/S part because of the grouting and
drainage curtains, in the D/S part (which applies for the major stretch) because of the
highly stressed dam toe area. Therefore, the excavation shall be continued until the de-
sign level in the area between el. 320-378 (design excavation levels). After completion of
the excavation down to the design level, it will be possible to decide if a slight kink of the
dam axis in the uppermost area or a D/S enlargement of the abutment is required.
The granite-metasandstone contact was encountered at el. 315-320, where the excava-
tion has already reached the design level. The upstream part of the dam footprint is lo-
cated in slightly weathered granite, but the downstream part consists of moderately to
highly weathered metasandstone. It is assumed, that this relatively bad metasandstone
rock quality is related to the granite contact (roof shaped contact). The extent of the af-
fected area can not yet be estimated in detail, but probably an additional excavation
down to or near the contact will be required.
Below this area (design excavation level < 315), the dam footprint will mainly consist of
fresh to slightly weathered granite. In the U/S part, good granite rock is encountered 10-
24 m above the design excavation level. In the D/S part, the rock is not yet exposed, but
it is considerably lower and possibly partly in metasandstone. In this area, the former
contact granite-metasandstone is exposed as 10 m high subvertical granite cliff, about
parallel to the dam axis, located in the downstream part of the dam footprint (Photo 2).
This will hardly provide an adequate dam foundation shape and further more detailed
considerations are required to decide to which extent the granite block has to be re-
moved in order to achieve an acceptable dam footprint shape.
Photo 2: Granite cliff parallel to dam axis, former contact to metasandstone (24.05.08)
• Start with drill and blast excavation at crest level, excavating according to the ex-
isting drawings down to approx. el. 320
• Excavation below el. 320 considering also the points mentioned above (weak me-
tasandstone in D/S area, acceptable dam foundation shape)
Rock mass parameters are provided for the following rock formations:
• Slightly weathered granite: Valid for the U/S part of the dam, considering also a
potentially weaker contact zone (to metasandstone), i.e. in the core of the intru-
sion really fresh rock with even higher parameters is possible
The Hoek-Brown method was applied, the results are presented in Annex 2. Generally
the mean values are assumed to be the most representative for a large foundation area,
whereas the low and high values may rather apply for smaller areas.
6 POWERHOUSE RELOCATION
Internal discussions were held regarding the location of the powerhouse and it has been
agreed that a relocation of the powerhouse parallel to the dam axis by 20 m towards the
right abutment would be beneficial and represent a reasonable compromise between the
PH excavation requirements on the left bank and the spillway confinement on the right
bank. However, such relocation would reasonably require slightly convergent spillway
side walls (angle 6-7°) in order to reduce the probability of right bank instabilities due to
the formation of a scour hole.
Photo 3: Fill adjacent to batching plant platform, showing cracks and erosion holes
(24.05.08)
8 MISCELLANEOUS
• About 40 m tunnel lining has been made (whole tunnel length 240 m). So far only
5 m long shuttering was used, concrete volume ~ 250 m / 5m tunnel length
• Crown filling grouting for the diversion tunnel shall be carried out systematically
on the whole tunnel length
UPPER PAUNGLAUNG
HYDROPOWER PROJECT
05/08/08 – 15/08/08
AUGUST 2008
TABLE OF CONTENTS
1 PROGRAM............................................................................................................... 2
2 ANNEXES ................................................................................................................ 2
3 GENERAL ................................................................................................................ 3
4 SITE VISITS ............................................................................................................. 3
4.1 ADDITIONAL INVESTIGATIONS ...................................................................... 3
4.2 TUNNEL LINING............................................................................................... 3
4.3 MSP QUARRY .................................................................................................. 4
5 COFFERDAM CONCEPT ........................................................................................ 4
5.1 INTRODUCTION............................................................................................... 4
5.2 BASIC DATA..................................................................................................... 5
5.3 COFFERDAM LAYOUT .................................................................................... 5
5.3.1 Upstream Cofferdam ................................................................................ 5
5.3.2 Downstream Cofferdam ........................................................................... 6
5.4 MAIN COFFERDAM CONSTRUCTION SEQUENCES ..................................... 6
5.4.1 General .................................................................................................... 6
5.4.2 Upstream Cofferdam ................................................................................ 6
5.4.3 Downstream Cofferdam ........................................................................... 7
5.4.4 Dewatering............................................................................................... 8
5.5 REQUIRED QUANTITIES OF EMBANKMENT MATERIAL............................... 8
5.6 COFFERDAM CONSTRUCTION SCHEDULE.................................................. 8
6 POSSIBLE RELOCATION OF DAM AND POWERHOUSE AXES .......................... 8
1 PROGRAM
05/08/08 Flight Zurich-Bangkok
06/08/08 Flight Bangkok-Yangon-Mandalay
07/08/08 Office Mandalay, transfer to Mektila
08/08/08 Transfer to UPL, site visit UPL
09/08/08 Transfer to Paunglaung and further to Mandalay
10/08/08 Short site visit to Yeywa, office work in Mandalay
11/08/08 Study of UPL cofferdams
12/08/08 Preparation of Annexes and presentation, transfer to Mektila
13/08/08 Transfer to Nay Pyi Taw, transfer to UPL, site visit
14/08/08 Transfer to Paunglaung, meeting with DHPI, site visit report
15/08/08 Site visit report, flight to Yangon and Bangkok
2 ANNEXES
1 River Discharges
2 Tunnel Capacity and Tailwater Curves
3 U/S Cofferdam – Layout
4 U/S Cofferdam – Typical Section
5 U/S Cofferdam – Construction Phase 1: Precofferdam - Plan
6 U/S Cofferdam – Construction Phase 1: Precofferdam - Sections
7 U/S Cofferdam – Construction Phase 2: Upstream Blanket - Plan
8 U/S Cofferdam – Construction Phase 2: Upstream Blanket – Sections
9 U/S Cofferdam – Construction Phase 3: Working Platform - Plan
10 U/S Cofferdam – Construction Phase 3: Working Platform - Sections
11 U/S Cofferdam – Construction Phase 4: Cutoff Excavation and Fill - Plan
12 U/S Cofferdam – Construction Phase 4: Cutoff Excavation and Fill - Sections
13 U/S Cofferdam – Construction Phase 5: Compacted Cofferdam - Plan
14 U/S Cofferdam – Construction Phase 5: Compacted Cofferdam - Sections
15 D/S Cofferdam – Layout
16 D/S Cofferdam – Typical Sections
17 D/S Cofferdam – Construction Phase 1: Precofferdam / Working Platform - Plan
18 D/S Cofferdam – Construction Phase 1: Precofferdam / Working Platform - Sec-
tion
D/S Cofferdam – Construction Phase 2: Cutoff Excavation and Fill - Section
19 D/S Cofferdam – Construction Phase 2: Cutoff Excavation and Fill – Plan
20 D/S Cofferdam – Construction Phase 3: Compacted Embankment – Plan
21 D/S Cofferdam – Construction Phase 3: Compacted Embankment – Section
22 Cofferdams - Construction Schedule
23 Geology Left Abutment – Plan and Longitudinal Section
24 Geology Left Abutment – Cross Sections SB12 and PX1
25 Geology Left Abutment – Cross Sections SB9 and SB6
26 Geology Left Abutment – Cross Section SB3
3 GENERAL
The main purpose of the present mission was the development of the concept for the di-
version cofferdams. Two site visits were carried out (8./9. and 13./14.), staying overnight
in UPL both times. Other items discussed concerned the relocation of the powerhouse
and dam axis and tunnel lining works.
4 SITE VISITS
The additional drillhole ABH-13, located in the granite of the left abutment was com-
pleted. The drillhole, inclined 45° towards downstr eam, reached a depth of 50 m without
encountering the contact granite-metasandstone. The possible borehole deviation is not
known and the contact shall therefore be confirmed by a vertical or U/S inclined drilling.
The next inclined borehole ABH-14 (40° towards the river) is actually in progress (5 m in
granite). It is targeted to reach the contact zone below the riverbed.
The lining of the bend stretches is completed and the two CIFA formwork segments have
been fitted together to one peace of 10 m length for the concrete placing of the remaining
180 m straight tunnel stretches.
The following issues regarding tunnel lining were discussed with the local site supervision
during the first site visit:
• At two locations of the still unlined tunnel stretches, small water inflows were de-
tected. In order to avoid washing out of the fresh concrete, the water inflows shall
be properly drained, e.g. by fixing plastic sheets to concentrate dispersed water
inflows and draining by a pipe leading to the tunnel bottom and through the lining
concrete into the tunnel. In case of concentrated water inflows, these can be cap-
tured directly by small drainage pipes.
• DHPI intends to use the CIFA formwork also for the circular crown section of the
outlet transition zone, in order to safe time. Sketches shall be provided by DHPI
showing the planned arrangement and procedure (prepared by CIFA representa-
tive on site).
The quality and quantity of the available material for aggregate production are getting
more and more critical. About 10’000 m3 of concrete still have to be produced for the
completion of the tunnel lining. The granite block on the left side of the river confluence
could provide suitable aggregates and should therefore be used as soon as possible
(preparation of access road required).
The future main quarry area (MSP) has also been visited (1 hour walk each way) during
the second visit. The access roads require considerable efforts to be re-established and
improved. The quarry area shows generally deep surface weathering (saprolite) and
overburden, except on the steep slope on the left side of the Small Paunglaung River.
Secondary intrusion dikes within the weathered granite reaching up to the surface show
much better and more competent rock (Photo 1). Further excavations are required to
achieve reasonable quarrying conditions
5 COFFERDAM CONCEPT
5.1 INTRODUCTION
Test pits carried out in December 2007 revealed a very high permeability of the riverbed
alluvium and consequently concerns raised regarding future seepage below the coffer-
dams into the dam and powerhouse excavation areas if this alluvial layer is left untreated.
Discussions were held regarding the necessity and feasibility of a slurry trench as cut-off.
However, this idea was finally abandoned in favour of a simpler alternative with construc-
tion methods more commonly used in Myanmar. The present section gives an overview
about the proposed concept.
The river discharge data are presented in Annex 1. The figure in the bottom of Annex 1
gives the average of the discharges measured at the site gauging station in the years
2005-2007. The dry season discharges recently measured correspond well with the av-
erage 1965-1985. The wet season discharges 2005-2007 are generally higher than the
average discharges 1965-1985.
The diversion tunnel capacity and tailwater curves determining the required pre- and cof-
ferdam crest elevations are given in Annex 2:
• Diversion tunnel capacity for low discharges (free flow) → U/S precofferdam ele-
vation of 290 m a.s.l. for Q=50 m2/s and 2 m freeboard (allowing to pass a small
dry season flood of 150 m3/s)
• Diversion tunnel capacity for high discharges (tunnel flowing under pressure) →
U/S cofferdam elevation of 304 m a.s.l. allowing the passage of Q10=1100 m2/s
without freeboard
• Tailwater curve at tunnel outlet → D/S cofferdam elevation of 291 m a.s.l. allow-
ing to pass Q10=1100 m2/s with 2 m freeboard
According to the available river cross sections, the riverbed elevations are about 386 and
384 for the U/S and D/S cofferdam respectively; with exception of the deep hole on the
right side near the tunnel inlet (el. 275) and a smaller hole on the left side in the D/S cof-
ferdam area (282).
So far, the rock surface is only known along the separation wall (el. 282). It is assumed to
be not considerably lower than 280 m a.s.l.
The general layout of the U/S cofferdam is shown in Annexes 3 and 4. The cofferdam
axis was moved in upstream direction as much as possible in order to provide sufficient
space for a possible U/S relocation of the main dam axis (about 15 m U/S of former loca-
tion).
The material types used are shown in Annex 4. Basically pervious material (tunnel much
or alluvium) is used for the precofferdam and the downstream shell and impervious mate-
rial (clayey silt from dam excavation) is used for the upstream blanket, cut-off and core.
The general layout of the D/S cofferdam is shown in Annexes 15 and 16. The cofferdam
axis is determined by the location of the tunnel outlet channel and the separation wall.
The same materials are used, but the embankment part above the water table is much
smaller than for the U/S cofferdam
5.4.1 General
Before the start of the cofferdam works, sufficient material for the precofferdams and clo-
sure of the U/S cofferdam shall be stockpiled on both sides of the river. The permeable
tunnel muck deposit forming the right abutment of the U/S cofferdam should be removed
at least in the central part of the cofferdam (cut-off and core area).
It is also considered beneficial to lower down the right part of the riverbed downstream of
the tunnel outlet by excavation under water, e.g. until the next river rapids (or removing
simply a part of the rapids). This would help lowering the dry season tailwater level.
After completion of the diversion tunnel, the remaining part of the D/S and U/S diversion
tunnel cofferdams have to be removed down to the tunnel outlet and inlet invert eleva-
tions (283.50 and 284.50 m a.s.l. respectively). Thus already a part of the discharge is
diverted through the diversion tunnel and the proper cofferdam works can start. The
maximum river discharge for the start of the diversion works should be 50 m3/s.
Coarse material is dumped into the flowing water up to elevation 290; from both river
sides but mainly from the right side. It is assumed that the river closure is easier to be
performed on the left shallow river side than on the right deep side. A suitable location
might be 20-30 m from the left abutment (protection of the left abutment is required in any
case). For the river closure sufficiently large boulders shall be stockpiled as well as for
the protection of the already placed precofferdam and the open riverbed.
After the river diversion, impervious material (clayey silt) shall be dumped on the U/S side
of the precofferdam, starting from the left abutment. In order to seal the precofferdam
(and underlying alluvium) a part of the U/S hole in the riverbed shall also be filled with
clayey silt.
After the placing of the impervious blanket, the water table downstream of the precoffer-
dam is assumed to go down to about el. 286 (~ water table at tunnel outlet measured
during the dry season), thus allowing the placement of a working platform (alluvium or
tunnel muck) on elevation 286.50 approximately (these elevations will have to be
adapted to the effective elevation of the water table).
From the working platform 286.50, a cut-off trench down to the rock surface shall be ex-
cavated below the water table. Depending on the location of the water table and rock sur-
face, a big backhoe may be sufficient for the excavation works. However, this may not be
the case if the conditions are worse than expected and therefore it is recommended to
have also a sufficiently big dragline on site.
The bottom width of the trench shall be 5 m and the trench slopes 1:1 to 1:1.5. On the
right abutment, it shall be connected to the weathered rock (not to the tunnel muck), on
the left abutment to the reddish clayey silt.
After excavation, clayey silt material shall be dumped into the trench up to elevation
286.50 where some compaction can be carried out. In case that very coarse material
prevails on the downstream side of the trench, a concrete sealing, placed below the wa-
ter using the “tremie pipe” method might be required in order to avoid washing out of fine
material.
Completion of the cofferdam above water table up to elevation 304 m a.s.l. using conven-
tional embankment methods (sheep foot roller for clayey silt, vibrating roller for perme-
able shell). In order to avoid bridging of the compacted core material across the cut-off
(highly compressible material), the core shall be placed with a water content lying above
the Proctor optimum.
In case of very coarse downstream shell material, a transition layer (sand) should also be
placed between the shell and the core. The core shall be connected to the reddish clayey
silt on the left and to the weathered rock on the right abutment. The upstream dam face
shall be protected by a rip-rap layer.
The foreseen construction phases are shown in Annexes 17-21. The main element of the
D/S cofferdam is the cut-off trench which shall be constructed with the same method like
the U/S cut-off trench, after placing of a working platform above the tailwater level
5.4.4 Dewatering
Dewatering of the area between both cofferdams (~170’000 m3) can start as soon as the
U/S and D/S cut-offs are completed. Sufficient pumping capacity of 500-1000 l/s shall be
available on site.
The required fill and embankment materials are shown in Table 1 hereafter:
The volumes for the U/S and D/S precofferdams are 11’000 and 9’500 m3 and those for
the cut-off trenches 11’000 and 12’000 m3 respectively.
The coarse material will come partly from the tunnel muck stock pile along the right river
bank and partly from alluvium excavation (cut-off trench, separation wall). The clayey silt
is abundantly available. Rip rap and boulders for the precofferdam closure can be col-
lected and produced from the granite block on the left side of the river confluence.
A construction schedule for the cofferdam and related excavation works is given in Annex
22. The schedule is challenging but not impossible, if the diversion tunnel is ready and
adequate resources are available. According to this program, full diversion through the
tunnel is foreseen in early December 2008 and completion of the cofferdams end of April
2009.
A relocation of the powerhouse axis by 15 m towards the river is suitable and will consid-
erably reduce the amount of powerhouse excavation. Further foundation and water im-
pact assessment studies will have to be carried out before the final confirmation.
CONTENT
1 INTRODUCTION 1
3 FINDING 2
4 RESERVE ESTIMATION 5
5 CONCLUSION 5
6 RECOMMENDATION 5
ANNEXES
ANNEX 1. SKETCH OF LOCATION MAP 6
ANNEX 2. GRANITE AND ITS GEOLOGY 7
ANNEX 3. WHAT IS GRANITE 9
1. INTRODUCTION
As the inherent problem of very thick overburden of weathered granite (saprolite) and
soil at UPL Project results in very high stripping ratio and economically not viable to
produce granite RCC aggregate at existing quarry sites. This becomes major constraint
for prospecting of new quarry site with a minimal overburden thickness leading to a desk
study that located potential limestone occurrences and a granitoid batholith in the vicinity
of UPL Dam Site. A ground reconnaissance traverses was followed up on 22nd to 23rd of
January 2009 by the request of Project Director Mr. A. Dredge and Chief Resident
Engineer Mr. S. Cowie. Two potential prospects of granite were selected for further
exploration (ANNEX 1) that required adequate (ADEQUATE) investigation by seismic
survey and systematic close drilling to the depth of minimum 50m thick sound granite.
This task will take certain period to evaluate and to confirm the reserve and economic
viability. On the 25th of February 2009, properties of UPL granite were discussed among
contractors, DHPI and CPEM/NEPS during site inspection of HIS EXCELLENCY
DEPTUY MINISTER FOR MOEP 1 at new MSP Quarry site. It includes uncertainties in
overburden thickness, hardness of granite (wear and tear of crushing equipments)-
possibility of 0-5mm fine aggregate being been dominated by quartz (3-5mm) ≥ 20 %
and mica (~ 5 mm) 3-10%. A common agreement was reached to look for an alternative
rock-type, limestone identified by desk study, if it could have been occurred by minimum
overburden. Limestone is the most commonly used aggregate in RCC Dams and it has
been used as RCC aggregates at Yeywa HPP. At the mean time first exploratory drilling
on the hill between two Paunglaung Rivers intersected overburden of 22.00m
diminishing a hope of HTCT. The probability of uncertainty was increased and
prospecting for a limestone quarry was warranted. A reconnaissance prospecting was
conducted on the 26th and 27th of February 2009.
ACTIVITY
Departed Kywe Yoe Village (12:00 NOON) – Arrived New Sin Kwin
Village (02:00PM)
Departed Old Sin Kwin Village (11:30 AM)-Arrived New Sin Kwin
Village (12:30 NOON)
3. FINDING
It is located in the east and about 1.3 mile far away from New Sin Kwin Village. Base
elevation is about EL. 666.00 m. Pink colour fine grained pure limestone is exposed to
the crest El. ~ 800.00m. It is very massive and occurs as rock cliffs with little or no
overburden.
4. RESERVE ESTIMATION
POTENTIAL RESERVE
LIMESTOPNE QUARRY PROSPECT No.2 is reserved for PROSPECT No.1 and not
urgently required for estimation.
5. CONCLUSION
Limestone Quarry Prospect No. 1 can be used as RCC aggregates by optimum mining
and crushing. The potential reserve 4,000,000m3 is sufficient for UPL RCC Aggregate
Production.Limestone Quarry Prospect No. 2 can be leave as standby reserve for
Prospect No.1.
6. RECOMMENDATION
2) Testing:
THEIN HAN
GEOLOGIST
CPEM/NEPS
UPL aggregate quarries and crushers were visited on the 18-12-2010 during site inspection at
UPL HPP.
HTCT
Plate 1. Ground chute at HTCT quarry. Note: Blasted rocks are caught by of dust
layer forming as a sticky floor on top of chute floor.
MSP
An alternative quarry site was prospected after the occurrences of red argillaceous
limestone beds enough to see at existing quarry. It is located at the east of present quarry
and occurs as massive limestone conglomerate (Plate. 7) composed of limestone
pebbles cemented in limestone matrix. Possibilities in heterogeneity of texture and pebble
types due to heterogeneous sources, it becomes less potential for RCC aggregate
material. Besides, the base of limestone conglomerate is about 100m higher than top
level of existing quarry. MSP is vital to exploit the grey limestone beds continues from
HTCT quarry and occurs at the south. It should be accomplished without any delay.
MSP crusher is well set to produce properly graded RCC aggregate in good shapes.
Average monthly production is design to produce 100,000 tons. Daily explosive supply is
500kgs and crusher is operated by own generator.
Thein Han
DAM FOUNDATION
GEOTECHNICAL PARAMETERS
MARCH 2011
AF-Colenco Ltd.
Hydropower Plants
UPL HPP
Dam Foundation – Geotechnical Parameters
Report No. UPL-FRH-MAR 2011 2/19
Table of Contents
Page
1 INTRODUCTION ........................................................................................................ 4
5 REFERENCES ........................................................................................................... 11
Annexes
2-2 Laboratory Test Results for Granite (not used for the determination of rock mass
parameters)
1 INTRODUCTION
The purpose of this report is the evaluation and presentation of the geotechnical rock
parameters to be used for the geomechanic analyses of the dam foundation and other
structures founded on rock.
The excavation for the dam foundation is generally completed, except the topmost
kink area on the left abutment and two further particular areas [1,2].
Preliminary rock mass properties have been given in previous site visit reports. They
are reviewed regarding the foundation rock mass properties in the present report.
The present report should be read together with the geological report regarding dam
foundation, which will, among others, contain information such as detailed mapping,
zoning of the dam footprint, permeability conditions and joint statistics. These items
are hence not dealt with in the present report.
The only available in situ tests are the seismic refraction surveys carried out by
SUNTAC TECHNOLOGIES in 2005 [3]. The results measured along the dam axis
(at that time a straight axis), are given in Annexes 1-1 and 1-2.
No distinction was made regarding the rock type. In Annex 1-2, the approximate dam
foundation line is indicated in the seismic profile. According to these profiles, a
seismic velocity of vp ~ 3’000 m/s can be attributed to the rock exposed at the actual
dam foundation footprint on the abutments. The velocities of the granite and the rock
in the river section are rather higher.
Based on the velocity of the longitudinal waves, a seismic modulus Eseismic can be de-
termined with the following relation [8]:
( ) ( )
Eseismic = vp2**
( )
Hence Eseismic = 19.9 GPa and 17.7 GPa for =0.25 and =0.30 respectively. These
values are valid for the upper foundation layer of the slightly weathered metasand-
stone. It bears noting, that the static modulus, which generally is used for the struc-
tural design, is considerably lower than the dynamic modulus (see below).
Rock samples have been taken from drillholes and from the surface in order to carry
out classification and compressive strength tests in the laboratory. The results are
shown in Annexes 2-1 and 2-2. A summary of the test results is given in Table 1
hereafter:
It bears noting that all granite samples for the tests have been taken from the former
quarry area with considerably lower rock quality than observed on the dam foot
print. The results given in Table 2 are therefore not considered to be representative
for the granite intrusion in the dam foundation area and hence these results were ex-
cluded from further considerations.
3.1 GENERAL
Basically the Hoek/Brown method [4] will be used for the determination of the rock
mass parameters. The obtained values will then be compared and cross checked with
other available information, using also the rock mass classification according to
CRIEPI (Central Research Institute of the Electric Power Industry, Japan) which is
widespread and popular in Asia and used elsewhere in Myanmar.
C Virtually sound granite (CRIEPI grade CH-B), in the left abutment below
El.315 m a.s.l.
The final limits between the different areas have to be defined based on the geologi-
cal mapping.
A value for the rock deformation modulus of sound metasandstone will also be giv-
en. This geological unit generally does not occur at the surface but in a certain depth
below the foundation level, which can be estimated using the results of the seismic
refraction shown in Annex 1-2 (blue zone). This unit, although not present on the
foundation level, may have a considerable influence on the calculated dam displace-
ments.
The first input-parameter (unconfined compressive strength of intact rock, UCS) has
been determined for the metasandstone by means of laboratory tests.
The overall average value for the metasandstone is UCS = 93 MPa and 59 MPa for
dry and saturated conditions respectively (Table 1). Only a few tests have been car-
ried out in saturated condition, showing a reduction of 25% compared with the com-
pressive strength of dry samples of the same serie of 5 tests. Therefore, it is consid-
ered adequate to adopt a value of UCS = 0.75 * 93 = 70 MPa for the slightly
weathered metasandstone. For the moderately weathered rock, a reduced value of
UCS = 40 MPa is selected.
The overall average value measured for the granite is UCS = 71 MPa and 35 MPa for
dry and saturated conditions respectively (Section 2.2.1). These values are consid-
ered too low and not representative for the granite encountered in the foundation area
(origin of the tested samples is mostly the former quarry area). This is particularly
true for the results in saturated conditions which show a further reduction of 50%
compared with the tests carried out on dry samples.
The mi values can be estimated based on the table given in Annex 3. Values of
mi=20 and mi=33 are selected for the metasandstone and granite respectively.
The GSI-values can be estimated using the table shown in Annex 3-2 (which has
been adapted to the rock conditions encountered on the UPL-site) or alternatively,
based on RMR values. So far, no systematic determination has been made. Some
RMR and GSI values are available from the geological mappings of the diversion
tunnel, but the results do not seem to be very consistent. From these mappings (An-
nex 4), a value of GSI=70 can be derived from the RMR values for the slightly
weathered to sound metasandstone encountered in the diversion tunnel. For the
slightly weathered metasandstone of the dam foundation which is closer to the origi-
nal ground surface, a value of GSI=55 is selected. For the moderately weathered
sandstone, this value is reduced to GSI=40.
For the granite, which is less fractured than the metasandstone, a value of GSI=70
seems appropriate (see also [5]).
Later (2002) Hoek introduced an additional factor D accounting for the degree of
rock disturbance due to blasting and stress relief. This factor depends highly on the
blasting procedure applied during rock excavation. For the dam foundation, the rock
disturbances due to blasting will be treated by contact grouting, this factor is hence
set to D=0.
No elasticity and deformation moduli have been measured on the core samples.
Hence the following values have been selected based on experience and literature
studies [6].
Granite: Ei = 36 GPa
Metasandstone Ei = 21 GPa
The peak values of the mean rock mass properties determined according to the meth-
od of Hoek/Brown are shown in Table 3 below:
Table 3: Mean Rock Mass Properties for Granite and Metasandstone on Dam
Foundation Level – Peak Values
Engineering Geological Zone Metasandstone Granite
Unit Slightly Moderately Virtually sound
weathered weathered
Rock Grade CRIEPI CH CM CH-B
UCS, intact rock, ci MPa 70 50 90
Hoek-Brown constant mi 20 20 33
Geological strength index, GSI 55 40 70
Disturbance factor - 0 0 0
Max. minor principal stress MPa 6 6 6
Intact rock modulus GPa 21 21 36
Friction angle, rock mass, ° 47 40 57
Cohesion, rock mass, MPa 2.3 1.6 3.6
UCS, rock mass, MPa 10.4 6.1 24.3
1)
Deformation mod. rock mass GPa 8.6 3.4 26.4
Poisson’s ratio of rock mass 2)
- 0.30 0.33 0.25
1)=Values determined according to Hoek/Diederichs [6]
2)=Values estimated based on published values
The values for the unconfined compressive strength of the rock mass given in Table
1 have been determined according to the Mohr-Coulomb theory.
Residual rock strength values are used for the dam stability analysis of the post-
earthquake load case. No generally accepted theory is available for the determination
of the residual strength values based on the peak values only. One possibility is re-
ducing the GSI value from the in situ value to al lower value which characterizes dis-
turbed and crushed rock mass (Annex 3-2). The estimated residual values are given
in Table 4:
Table 4: Mean Rock Mass Properties for Granite and Metasandstone on Dam
Foundation Level – Residual Values
Engineering Geological Zone Metasandstone Granite
Unit Slightly Moderately Virtually
weathered weathered sound
Rock Grade CRIEPI CH CM CH-B
UCS, intact rock, ci MPa 70 50 90
Hoek-Brown constant mi 20 20 33
Geological strength index, GSI 40 30 35
Disturbance factor - 0 0 0
Max. minor principal stress MPa 6 6 6
Friction angle, rock mass, ° 42 36 47
Cohesion, rock mass, MPa 1.8 1.4 2.0
UCS, rock mass, MPa 8.1 5.5 10.2
The selected GSI values for the post-failure state represent poor rock. Generally, the
higher the peak strength value the larger the reduction to the post-failure strength.
Hence the assumed reduction of the GSI value is higher for the granite than for the
metasandstone. These values are intended to be used mainly for the analysis of the
post-earthquake dam stability load case carried out with the CADAM program. Re-
sidual strength values used for other calculations may be lower.
The rock mass classification system developed by CRIEPI is widely used in Asia.
Hence the CRIEPI rock grades are also indicated on the first row of Table 3. The
main classification criteria and the correlations with rock mass parameters are given
in Annex 5.
The Hoek/Brown strength values fit well with the ranges given by CRIEPI for the re-
spective rock grades (Annex 5). However, the rock stiffness (deformation modulus)
according to [6] is generally higher than the suggestions made by CRIEPI. The in-
vestigations made by Hoek/Diederichs [6] are more recent and more data were avail-
able for evaluation and hence these values are considered to be more realistic,
whereas the CRIEPI values are considered to be rather on the conservative side.
For the metasandstone dam footprint, the representative compressive wave velocity
is considered to be about vp = 3’000 m/s (see Section 2.1.1 above). The formula giv-
en in section 2.1.1 provides for vp = 4’200 m/s a modulus Eseismic which is about
twice as high as the modulus Eseismic for the slightly weathered metasandstone.
Hence, it can be readily assumed that the static deformation modulus for the sound
metasandstone (blue zone of Annex 1-2) is also about twice as high as that for the
slightly weathered metasandstone, hence D=17 GPa. The same deformation modulus
is obtained, if a GSI=75 is selected in the first column of Table 3, maintaining all the
other parameters unchanged.
This figure shows also, that the RMR- and GSI- classifications made during the ex-
cavation phase (Annex 4) were on the conservative side.
5 REFERENCES
[1] AF-Colenco Ltd. (2010): UPL – Site Visit Report No.UPL-00-VOB-NOV10
[2] AF-Colenco Ltd. (2011): UPL – Site Visit Report No. UPL-FRH-VOB-FEB
2011
[4] Hoek E. and Brown E.T. (1997). Practical estimates of rock mass strength.
Int.J.Rock Mech. & Min. Sci & Geomech. Abstracts. 34(8), 1165-1186
[7] Hoek E., Diederichs M.S. (2006): Empirical Estimation of rock mass modulus.
International Journal of Rock Mechanics & Mining Sciences 43 (2006) 203-
215.
[8] Ballard, R.F. and McLean, F. (1975): Seismic field methods for in situ moduli.
– U.S. Army Engineers Waterway Station, Soil and Pavements Laboratory,
Vicks-burgh Miss. 39180, Misc.Papers S-75-10
Baden, 30.03.2011 / Fr
Dry Condition:
No. 14 14 14 14
Average 2.70 2.63 0.61 93.08
St.Dev. 0.055 0.066 0.475 68.078
Max. 2.80 2.72 1.63 227.6
Min. 2.60 2.48 0.11 9.7
Wet Condition:
No. 5 5 5 5
Average 2.71 2.68 0.77 58.56
St.Dev. 0.064 0.055 0.901 43.872
Max. 2.76 2.76 2.54 118.6
Min. 2.58 2.59 0.16 7.1
Annex 2-2: Laboratory Test Results for Granite (not used for the determination of rock
mass parameters)
Dry Condition
No. 6 6 6 6
Average 2.60 2.52 1.10 70.60
St.Dev. 0.054 0.072 0.234 20.323
Max. 2.67 2.64 1.44 94.7
Min. 2.54 2.4 0.73 35.6
Wet Condition
No. 5 5 5 5
Average 2.62 2.55 0.64 34.84
St.Dev. 0.026 0.037 0.060 26.955
Max. 2.65 2.6 0.74 84.5
Min. 2.58 2.51 0.57 8.7
Annex 3-1: Values for the constant mi for intact rock (Hoek/Brown)
GSI Estimates for Heterogeneous Rock Masses for UPL HPP (modified
from Marinos & Hoek 2001)
Smooth, moderately
Rough + slightly
DISCONTINUITIES (MAINLY
or clay gauge
VERY GOOD:
slickenslided
VERY POOR:
slickenslides
continuous
weathered
weathered
BEDDING PLANES)
GOOD:
POOR:
FAIR:
A B C D E
Metasandstone 1 80
Massive to blocky
minor schists
CH CM
undisturbed rock mass
2 55
Metasandstone 70
very blocky
minor schist intercalation
CH CM CM 35
partly disturbed rock mass 60 25
50 40
3
Sandstone - Schists 20
or only schists/shales
weak, folded, disturbed
45 CM CL
blocky-disturbed rock mass 30
15
30 10
4
Clayey or silty Shale
laminated, crushed,
D
10
Disintegrated rock mass
Annex 4: Rock Mass Classification made in the Diversion Tunnel (right abutment)
Metasandstone
Station (m) RMR RMRmod GSI GSImod Q-value
From To
GSImod = RMRmod -5
February 2015
www.afconsult.com/switzerland
Table of Contents
The main data of the civil works construction design is provided here. The data included are mainly Project
Description, Design Reports, Stability and Structural Analyses.
3.4 Spillway
3.7 Penstocks
3.8 Powerhouse
3.9 Tailrace
3.12 Switchyard
– Design and Construction Aspects of RCC Dam from Asia 2012 paper
– RCC dam – design and construction from ICOLD 2011 Luzern paper
– RCC Placing, Guidelines, UPL- 3853 – RCC PLACING – ROH/APRIL 2009, April 2009
– Trial Embankment, Separation Wall – RCC, UPL – 3853 – SEP WALL TRIAL – ROH/APRIL 2009, April 2009
– Thermal Mass Gradient Report, Main Dam - RCC, UPL - 03 - THERMAL MGC - ROH/JAN 2009, January
2009
– Full Scale Trial Procedures, Main Dam - RCC, UPL - 03 - RCC FST - ROH/OCT 09_rev. 1, October 2009
– Design Report, RCC Transportation System, Main Dam - RCC, UPL - DR - 03 - RCC TRANSPORT -
ROH/APR 2010, April 2010
– Dam Foundation Treatment - Curtain Grouting Procedure / Specification, Report No. UPL-CWS-SEPT
2010, September 2010
– Special Technical Specifications, Section 3.17: Main Dam Instrumentation, UPL-21-STS-3.17, December
2010
– Design Report, Main Dam - Block Joint Spacing, Main Dam - RCC, Report No. UPL - DR - 03 - BLOCK
JOINTS - ROH/DEC2010, December 2010
– Design Report - RCC Dam, Horizontal Thermal Stresses, Report No. UPL-DR-03-ROH/OCT2011, Octo-
ber 2011
– Design Criteria, Main Dam - Design, UPL - 03 - DESIGN CRITERIA - ROH/MAR 2011, November
2008_rev. 2011
– Specifications and Procedures for Dam Grout & Drainage Curtains, Report No. UPL-CWS/JULY 2012,
July 2012
– Design Report - Main Dam, Reservoir Impounding, Report No. UPL-DR-03-ROH/NOV2012, November
2012
– Hydraulic Model Testing, Spillway and Bottom Outlet General Specifications, Report No. UPL-56-HMT-
October 2007, October 2007
– Hydraulic Design Report, Spillway Structure, UPL – 3853 – SPILLWAY HYDRAULIC ANALYSIS –
ROH/JAN2009, January 2009
– Design Report: Spillway Chute & Flip Bucket, UPL – DR – 04.900 – Spillway Chute – MIA / OCT 2011,
October 2011
– Design Report: Spillway Bridge & Piers, UPL – DR – 04.910 – Spillway Bridge – MIA / OCT 2011, October
2011
– Bottom Outlet Structure, Stability and Structural Safety, Report No. 65.3853.05.950 / Rev. 0, June 2009
3.7 Penstocks
– Design Report: Penstock Shafts, UPL – DR – 07.910 – Penstock Shafts – MIA / MAR 2011, March 2011
– Design Report: Penstock Encasement & Inclined Supports, UPL – DR – 07.920 – Penstock Encasement –
MIA / AUG 2011, August 2011
3.8 Powerhouse
– Powerhouse, check of Stability, Stability Analysis, Report No. 60.3853.08.901 dated 28.08.2009
– Powerhouse, Stability / Structural Analysis, Basic Design Data, Report No. 60.3853.08.900 dated
03.09.2009
– Structural Analysis, Powerhouse Slabs Floors 5 to 8, Report No. UPL-DR 08.905, September 2011
– Special Technical Specifications, Section 15.21: Bonded Concrete Floors, UPL - STS - 15.21, December
2012
– Special Technical Specifications for Architectural Works, Sections 24, 25, 26, 27, 28, 33, 37, 39, 40, 41,
42, 43 and 44, July 2013
– Design Report, Powerhouse - Service Bay, Report No. UPL-DR-08.903, February 2015
– Design Report, Powerhouse - Machine Bay, Report No. UPL-DR-08.904, February 2015
– Design Report: Left Tailrace Channel Wall, Downstream of TR 61.75, Preliminary Design, UPL – DR –
09.900 – Tailrace Channel Wall – Mia / Jul 2012, July 2012
– Design Report, 33 kV Switchgear Building, Report No. UPL-DR-10-PPM/AUG 2012, August 2012
February 2015
Customer The Republic of the Union of Myanmar
Ministry of Electric Power
Department of Hydropower Implementation
February 2015
www.afconsult.com/switzerland
Table of Contents
The Upper Paunglaung Hydropower Project is located on the Paunglaung River 40 km upstream of
Paunglaung Rockfill Dam and just downstream of the confluence of Paunglaung and small Paunglaung
River, and located 50km east of the Capital City of Myanmar, Nay Pyi Taw. The Project Area belongs to
Mandalay Division, but the Reservoir is mainly in Shan State. The Dam Site location is 19°45’22’’N (Latitude)
and 96°35’44’’E (Longitude).
The Project is located on the river stretch of direction east to west where the river crosses the border be-
tween Shan Stage and Mandalay Division and turns from north to north-west almost 180 degrees. Just up-
stream of the Dam Axis is the confluence of Paunglaung River and Paunglaung Nge Chaung. Upstream of
the Dam Axis on the main Paunglaung is a 2km long narrow gorge.
Figure 1-2: Project Location, Paunglaung River and downstream Power Station
Upper Paunglaung Hydropower Project is the third project on the Paunglaung River and its distributaries.
Paunglaung with 280MW is in operation since 2004 and Nancho with 40MW on Nancho River a distributary
of Paunglaung River is in operation since 2014.
The Upper Paunglaung HPP consists of a 102m high RCC Gravity Dam with crest length of 444m across the
Paunglaung River. Incorporated in the Dam body are a Bottom Outlet in the River Section, the ungated
Spillway with three openings located in the middle of the dam section, and the power intakes which are
attached at the upstream face of the dam face of the dam body and the penstock which connect the wa-
terway from the Power Intakes to the Powerhouse.
– A concrete lined diversion tunnel with 10m diameter is design to divert the 10years wet season flood
without overtopping the upstream cofferdam during the construction period. At end of construction
when the Bottom Outlet is in operation, the tunnel will be plugged with a 20m long concrete plug.
– The Power Intakes consists of 2 individual Structures which are attached to the upstream face of the
RCC dam and supported by a RCC dam upstream extension. The Power Intakes are equipped with roll-
er type service gates and maintenance gates.
The powerhouse is located at the left bank downstream of the dam toe. The powerhouse is housing 2 Fran-
cis units, and includes unloading, assembly bay and control building. The plant has an installed capacity of
140MW.
The Key Design Data presented in the present chapter are subdivided into key subjects and key project
structures. Comprehensive information regarding the parameters of the structures and equipment is pro-
vided in the Upper Paunglaung Systems Definition.
Location
Division / State Mandalay / Shan State
River Paunglaung River
Dam Site Location 40 km upstream Paunglaung
Rockfill Dam
Latitude 19°45'22.63"N
Longitude 96°35'39.98"E
Nearest Town Pyinmana
Nearest Airport Nay Pyi Taw International Airport
(70km)
Hydrology
Catchment Area 2570 km2
Average annual Rainfall 1750 mm (approximately)
Average Runoff 82 m3/s
Floods:
10 years 1,100 m3/s
50 years 1,750 m3/s
100 years 2,100 m3/s
1,000 years 3,500 m3/s
PMF 7,000 m3/s
Reservoir
Maximum Exceptional Water Level (PMF) 377.10 m a.s.l.
Full Supply Level 370.00 m a.s.l.
Minimum Operating Level 352.00 m a.s.l.
Gross Res. Storage at Full Supply Level 1,700 M. m3
Live Reservoir Storage 1,000 M. m3
Reservoir Area at Full Supply Level 72.0 km2
River Diversion
Diversion Tunnels
Location on the right bank hill side
Number of Openings 1
Length of Tunnel 290 m
Tunnel diameter 10.0 m
Tunnel type concrete lined
Sill Elevation 284.50 m a.s.l.
Separation wall
Max Crest Elevation 295.50 m a.s.l.
Min Crest Elevation 291.00 m a.s.l.
Flood Protection level 3500 m3/s (1000 years wet season
flood)
Max Height 25.60 m
Min Height 13.00 m
Width 15.0 m
Length 99.6 m
Type RCC wall
Bottom Outlets
Location Integrated in the RCC Block 15
Number of Openings 2
Type of the Maintenance Gates sliding type bonnet gates
Opening Height 3.0 m
Width 2.0 m
Type of the Service Gates radial gates
Height 2.8 m
Width 2.0 m
3
Discharge at Full Supply Level (two openings) 400 m /s
Main Dam
Type RCC Gravity Dam
Crest Elevation 378.00 m a.s.l.
Crest width 10 m
Crest length 536.5 m
Lowest design Foundation Level 275.00 m a.s.l.
Maximum Height 103 m
Number of Blocks 27
Design Block Width Spacing 20 m
Max Block width 20 m
Upstream face slope vertical
Spillway
Location in the river section at dam block
16 to 19
Type ogee crest, ungated spillway
Crest Elevation 370.20 m a.s.l.
Number of Gates 3
Width of Openings 17.00 m
Discharge Capacity
at 1000 year Flood level (El. 374.0) 710 m3/s
at Maximum Exceptional Water Level (PMF) 1,750 m3/s
Number of Piers 2
Width of Piers 3 m
Overall width of Spillway 65.60 m
Power Intakes
Location on the left bank at dam block 12
to 13
Number 2
Width of Intake blocks 20 m
Intake Axis Level 340.00 m a.s.l.
Design Discharge 100 m3/s
Submergence on Minimum Operating Level 5.10 m
Trash Rack Dimensions
Gross Width 3 x 4.40 m
Gross Height 14.00 m
Slope vertical
Maintenance and Service Gates
Width 4.80 m
Height 4.80 m
Sill Elevation 337.60 m a.s.l.
Penstocks
Location on the left bank at dam block 12
to 13, connecting the Intake with
the Powerhouse
Number of Penstocks 2
Diameter 4.80 m
Number of bends 2
Powerhouse
Location on the left bank downstream toe
of the dam
Type Outdoor
No of Units 2
Unit Spacing 20 m
Length of Unit Bays 40 m
Length of Assembly Bay / Unloading Bay 20 m
Length of Control Building 16.58 m
Width of Substructure (upstream – downstream) 30.6 m
Width of Superstructure Powerhouse 17.8 m
Width of Superstructure Control Building 7.5 m
Height of Substructure 26.4 m
Height of Superstructure 18.4 m
Foundation Elevation at Units 265.50 m a.s.l.
Turbine Setting Level 278.40 m a.s.l.
Machine Hall Elevation 290.90 m a.s.l.
Unloading Bay Elevation 290.90 m a.s.l.
Switchyard
Upper Paunglaung
Plant Capacity and Energy Production
Average Operation hours 9.1 hours
Guaranteed Minimum Peak Power 34.2 MW
Annual Firm Energy Production 447 GWh/year
Annual Average Total Energy Production 466 GWh/year
Paunglaung
Plant Capacity and Energy Production
Average Operation hours 9.7 hours
Guaranteed Minimum Peak Power 91.7 MW
Annual Firm Energy Production 912 GWh/year
Annual Average Total Energy Production 1003 GWh/year
Construction Schedule
Duration of Construction Period 10 years
Commissioning December 2014
Introduction
The 140 MW Upper Paunglaung Hydropower Project comprises a RCC (Roller Compacted Concrete) dam with a
powerhouse located on the left bank at the toe of the dam, housing two power generation units. The project on
Paunglaung River upstream of the existing 280MW Paunglaung Hydropower Plant is located 50km east of the
Capital City Nay Pyi Taw, in Myanmar.
The construction of the Upper Paunglaung project started in late 2005 with the excavation of the river diversion
tunnel of 10m diameter. At the same time the basic design, construction design as well as assistance in site
supervision of the project had been carried out by AF-Colenco Ltd. (now AF-Consult Switzerland Ltd.). End of
2008 the Paunglaung River had been diverted, and construction of the upstream and downstream cofferdam started.
The construction of the powerhouse started in 2010 and the RCC dam construction started in January 2011. The
RCC dam has been competed in December 2013 and the impounding will start at beginning of 2014. The
commissioning of the plant will be in 2014.
The paper concentrates on the design and construction of the RCC dam. It gives first an overview of the RCC dam
layout and describes the main appurtenant structures. The paper then focuses on the RCC dam design and
construction details by presenting some specific design features of Upper Paunglaung RCC dam. It will be assessed
if they have been or will perform successfully for construction and operation.
The paper also presents the RCC mix design, the most important RCC hardened properties and construction
sequences as well as the changes made during construction.
Finally a short conclusion to the project is given, which is presenting the opinion of the author.
Fig. 2. Appurtenant Structures: Spillway and Penstocks Fig. 3. Appurtenant Structure: Power Intakes
The bottom outlet with two openings of 3m x 2m each, is equipped with radial and sliding gates. The whole
structure built in conventional concrete is incorporated at the bottom of one dam block. The bottom outlet is able to
draw down the reservoir in the dry season and to maintain the riparian discharge during impounding or operation
shut downs.
The power intakes are placed in front of the upstream face. The structure includes emergency closure gates and
maintenance gates, both operated from the dam crest. The two intake structures with intake trumpet, gate chamber,
gate shaft and gate operation room are seated on a RCC platform. The horizontal encased steel penstocks of 4.8m
diameter pass through the dam. They are connected to the inclined steel penstock on the downstream face of the dam
leading to the spiral case of the 70MW turbines in the powerhouse.
2. RCC Construction Sequences and Schedule
The initial construction stages and sequences have been changed many times to suit the condition of the construction
site. Two major changes had been made during construction:
During the construction of RCC stages 1 and 2, it has been observed that the retarder admixture is retarding the RCC
too short, even with high dosages. Therefore the following RCC stages had to be resized into smaller stages [2].
During placing stage 9 of the RCC in the river section, the sudden requirement has been made to keep the dam
construction below El. 312m during the forthcoming wet season. In order not delay the RCC dam construction for a
minimum of one wet season, the construction stages on the right bank have been split into two. With this
arrangement it was made able to continue raising the RCC and constructing the spillway, and at the same time to
leave the RCC at the right bank at a low level as a breach to minimise the risk of flooding in the reservoir area.
Consequently, also the RCC transportation system had to be adjusted, what is not so easy in the middle of the
construction period.
The final RCC stages and construction sequences are shown in Fig. 4.
16 15 20
14 19
13 12
8
18
6 5 11
3 4 10 17
9
2
1 7
It was originally planned to construct the RCC dam of Upper Paunglaung within 18 months. Due to various
challenges such as limited budget, difficult weather condition, topographical and geological issues and aggregate
production capacity, placing equipment condition, the RCC has been finally built in 35 months. Whenever RCC has
been placed, the rate of placing was of good speed.
3. Construction Details
3.1 Introduction of Short Joints
The number of RCC blocks respectively the joint spacing has been defined during the basic and detail design. The
size of the RCC blocks is mainly restricted by the dimensions of the appurtenant structures, mainly the Intakes, and
the specific RCC mix. The block width of 20m was initially found suitable. As the RCC mix containing natural
Pozzolan, which was found out behave quite brittle, and the cementitious content of the RCC mix had to be
increased based on the results of the Trial Mix Phase and in addition, the placing temperature could not be kept
below the specified 20°C during the hot period, the spacing of the RCC blocks had to be reduced. Instead of
rearranging the whole layout, short joints on the upstream face have been introduced at the blocks in the river
section. The short joints are arranged at the centre of the RCC block at the upstream face and consists of a 3m long
joint similar to the normal block joints, with two water stops and a joint drain. The concept of the short joint is based
on the results of the thermal analysis with the aim of reducing the horizontal thermal tensile stresses at the upstream
face where the highest thermal gradients occur. The risk of surface and mass gradient cracking is reduced
considerably and the joint are allowed to open without occurrence of seepage.
In a detailed finite element thermal analysis the effect of the short joints and the thermal stress reduction has been
calculated and assessed as suitable alternative for the UPL RCC dam. A comparison of thermal stresses at a normal
29m wide block and a block with short joints are presented in Fig. 6 and Fig. 7.
In the centre of a few RCC blocks which are equipped with and without short joint, stress meter and strain gauges
have been installed near the upstream face to monitor the real behaviour of the concrete and to allow comparison
with the computed values.
Fig. 6. Thermal Stresses with Normal Block Joint Fig. 7. Thermal Stresses with Short Joint Arrangement
5. RCC performance
The placing performance of the RCC at Upper Paunglaung was heavily influenced by the site condition. The
weather during the dry and cool season (from November until May) was very favourable for the aggregate
production, the quality of the RCC mix and the placing. However, the quality of the aggregates and therefore of the
quality of the RCC mix was negatively affected in the wet season by daily heavy rainfall and contaminated
aggregates. To overcome the problems, it had been decided to increase the production of the aggregates in the dry
season to the limits and to reduce the production in the wet season with simultaneously increase the quality by
temporary measure to limit the contamination. Also by gaining experience the quarry contractors have been able to
cope better with the difficult condition during the wet season in the following years and the impact on the aggregates
and consequently RCC quality decreased.
Fig. 10. RCC cube compressive strength Fig. 11. RCC cylinder tensile strength
References
1. U Myint Zaw, U Zaw Min San, S.L.L. Cowie, Ch. Rohrer, “Experience made with retarder admixtures at two RCC dam
in Myanmar”, 6th International Symposium on RCC Dams 2012, Zargossa, Spain.
2. U Myint Zaw, U Maw Thar Htwe, U Zaw Min San, Ch. Rohrer, “Design and Construction Aspects of the Upper
Paunglaung RCC Dam”, Asia 2012, Chiang Mai, Thailand.
3. U Myint Zaw, U Thaung Han, Ch. Rohrer, K. M. Steiger, “The Upper Paunglaung RCC Dam – Design and
Construction”, ICOLD Annual Meeting 2011, Luzern, Switzerland.
The Authors
U Zaw Min San is Deputy Director of Construction No. (1), Department of Hydropower Implementation. After completion of
his studies in Myanmar, he has been involved in quality control works of the Yeywa Hydropower Project, started as Chief of the
Project Concrete laboratory and later Deputy Director of Design Branch of DHPI. He has been involved in design and
construction management of Upper Paunglaung & Nancho Hydropowers.
Christof Rohrer joined AF-Consult Switzerland Ltd. (formerly AF-Colenco Ltd) in 2002 after obtaining his MSc in Civil
Engineering from the Swiss Federal Institute of Technology Zurich. He was involved in the Son La, Lai Chau, Dong Nai, Yeywa,
and TaSang RCC dam design, and in the construction of Yeywa. He currently is the deputy project manager and designer of the
103m high Upper Paunglaung RCC dam and the project manager and dam designer of the 120m high Shweli 3 RCC dam project,
both in Myanmar.
Design and Construction Aspects of the Upper Paunglaung
RCC Dam
U Myint Zaw (Union Deputy Minister) U Maw Thar Htwe (Director General)
Ministry of Electric Power No. (1) Department of Hydropower Implementation
Nay Pyi Taw Ministry of Electric Power No. (1)
Myanmar Nay Pyi Taw, Myanmar
Introduction
Upper Paunglaung Hydropower project is located on the Paunglaung River, about 50km east of the Capital City Nay
Pyi Taw, in Mandalay Division, Myanmar. The project is owned by the Ministry of Electric Power No. 1 with the
main purpose of power production for the national grid. It has an installed capacity of 140MW and compromises a
103m high RCC gravity dam, with Powerhouse located at the toe of the dam. The Upper Paunglaung Project is the
second RCC dam project in Myanmar, but the first RCC built by local contractors. The design and construction
supervision of the project is carried out by AF-Colenco Ltd.
This paper gives a short overview of the project and its structures. It explains the arrangement of the RCC dam
layout and its relation to the construction sequences. It describes the way the dam construction is restricted due to
the incorporated structures. A brief overview of the RCC mix design and Full Scale Trial embankment is also given.
Finally it is described how the site condition and difficulties during construction influence the quality of
construction material, the RCC mix design and the RCC performance as well as the construction sequence. The
paper shows the challenges of the project and the measures to be taken by the consultant to suit the condition and to
guarantee a high quality of the RCC.
2. Design Aspects
Figure 4: Spillway Section Figure 5: Downstream 3D view with Bottom Outlet and Dam Galleries
Figure 6: Design Construction Sequences
After completion of RCC stage 3 the RCC placing on the left side shall be interrupted due to the installation of the
steel penstocks and conventional concrete works. At this stage of construction the RCC placing needs to continue in
the river section with Stage 4 and the Bottom outlet civil works need to be completed. While constructing the
horizontal penstock CVC blocks, the RCC placing of Stage 4, 5 and partly 6 and 7 can be carried out without
hindrance except for the horizontal galleries. Before the RCC construction of Stage 6 and 7 reachs the top of
penstock level, the horizontal penstock structure needs to be completed to avoid delay in RCC placing.
Subsequently, the RCC Stages 6 and 7 can be completed and Stages 8 and 9 can be carried out without any further
interference. The Spillway does not restrict the construction progress but divides the placing into left and right side
of the Spillway. The Construction of the Power Intake trumpet, gate chamber and shaft are independent from the
further RCC construction. The Gate shafts at the upstream side of the dam can be built either ahead or after the RCC
dam. The inclined parts of the steel penstocks as well as the Spillway chute on the downstream side of the dam shall
be constructed subsequently after the RCC dam.
Successful competition of the RCC dam in time depends mainly on the construction progress of the incorporated
structures, continuous production of aggregates and placing of RCC with a minimum of stops. Therefore the RCC
construction sequence is planned such that the incorporated structures are not on the critical path of the construction
program. If the incorporated structures would be on critical path and delayed, the RCC dam construction would
immediately be affected and RCC placing interrupted.
In September 2010 several cores were extracted from the 90 day old trial embankment and tested in compression
and tension. The first test results were surprisingly low, and it was not clear if the RCC strength would develop
further enough with time to reach the design strength at the lift joints. The conclusion was drawn that the heavy rain,
the contaminated aggregates and the condition of the equipment were the reason for not reaching the targeted RCC
design strength. These unfavourable site conditions have to be expected at any time during the future RCC
construction, and therefore measures, as described later, need to be taken to reach the RCC design strength. A
strength comparison between Trial mixes (with various cement contents) and FST embankment is shown in Figure 7
and the FST embankment construction is shown in Figure 8.
3. Site Conditions
The weather conditions at Upper Paunglaung site are quite difficult. There are three typical seasons in this area, the
cold season from November until February, characterized by very dry weather with cold nights (14°C) and hot days
(36°C), followed by the hot season from March until June, characterized by very hot temperatures of over 40°C in
daytime and relatively dry conditions but with a few strong storms and heavy rain falls, and the rainy season from
July until October, characterised by very humid conditions, daily rain showers and temperatures of about 30 to 35°C
in daytime. To overcome the difficulties the main goal of the construction program is to speed up production and
construction during the dry season. All important and difficult structures where quality really matters shall be built
during the dry season and as much preparation works and material storage shall be completed before the heavy rain
starts. During the rainy season, mostly September and October, the RCC construction progress will be slowed down
or even stopped for some time.
4. Construction Aspects
Figure 9: coated aggregates from the wet season Figure 10: quarry face during the dry season
As a result the final RCC mix proportions have been changed, the cement content has been increased and the placing
temperature has been lowered by 3°C. The final RCC mix for the start of RCC in the dam body was therefore:
90kg/m3 cement, 140kg/m3 pozzolan, 125kg/m3 water.
Figure 11: Adjusted construction sequences for Stage 1 to 3 and 6 Figure 12: RCC placing with reduced area at Stage 2B
4.3 RCC performance
The performance of the RCC at Upper Paunglaung depends very much on the site condition. Producing, transporting
and stockpiling aggregates during the dry season is done very successfully in terms of efficiency and quality and
therefore more economical. During the rainy season the situation is different. The difficult weather condition with
heavy rains and the high humidity reduces the aggregate quality by a large percentage. The difference can be seen in
the material and RCC test results. Figure 13 compares the compressive strength results from RCC in the dam body
during wet and dry season and relates it with the previous RCC test results. It can be seen that the strength reaches
the design target and is much higher than the FST results. The measures taken as described above have been
successful. Nevertheless the comparison shows that the RCC performance is better in the dry season than in the wet
season. As a consequence of this all aggregates used for RCC construction in the rainy season are produced now in
the dry season and then stockpiled for the use in the wet season.
Figure 13: RCC compressive strength in wet and dry season Figure 14: RCC placing at Stage 3A in December 2011
5. Construction Progress
The actual progress of the RCC dam at Upper Paunglaung can be seen in the following figures. RCC Stage 3 has
been finished end of December 2011. In November and December 2011, DHPI placed approximately 110’000 m3
RCC within 7 weeks. The Bottom Outlet concrete structure is completed and RCC stage 4 in the River section can
start at beginning of 2012.
Figure 15: Construction of Stage 3A beginning of December Figure 16: Completed Stage 3 end of December 2011
6. Conclusions
The dam design optimisation to suit RCC construction, to minimise interferences, restrictions and complication has
been successful so far. The dam arrangement and the RCC construction stages allow the necessary flexibility in
construction and changes in the sequences to suit the actual site condition. The incorporated Bottom Outlet is well
advanced in construction and RCC placing of Stage 4 can start in January 2012. Meanwhile the construction of the
Intake and Penstock Structures has started on the left side, on top of RCC Stage 3.
The RCC mix has been successfully adjusted to reach the targeted design strength and the aggregates quality has
been constantly improved. The RCC stages and sequences have been changed to suit the RCC placing. This was
only possible with a great effort by all parties involved and the will to change.
The workmanship of the local contractor at the RCC placement is excellent. Experience has been gained and quality
as well as efficiency of the RCC placement increased. The motivation of the people, from the individual labours up
to the leading engineers, to do their best and willing to learn and improve the work under difficult site conditions, is
the key to the success of the Upper Paunglaung Project.
The Authors
His Excellency U Myint Zaw is currently Union Deputy Minister for Ministry of Electric Power No.(1), former Director
General, and was Project Director of the Yeywa Hydropower Project. After completing his studies in Myanmar, he has involved
in the construction of numerous hydropower projects in Myanmar, being project manager and then project director on many of
these before returning to the Yeywa project as its Project Director.S.C.
U Maw Thar Htwe is Director General of Department of Hydropower Implementation. After obtaining his Bachelor in Civil
Engineering from Rangoon (Yangon) Institute of Technology, he was involved in construction of Concrete Pole Plant, Gas
Turbine Power Plant and Waste Heat Recovery Boiler Power Plant and worked for Planning Section of Hydropower
Implementation. He was involved in construction of numerous hydropower projects throughout Myanmar such as Kun, Phyu,
Kabaung, Thaukyegat, Yenwe and Shwegyin as the Project Director.
U Zaw Min San is Deputy Director of Design Branch, Department of Hydropower Implementation. After completion of his
studies in Myanmar, he was involved in quality control works of the Yeywa Hydropower Project, started as Chief of the Project
Concrete Laboratory and later Assistant Director of the Yeywa Hydropower Project. He has been involved in design and
construction Management of Upper Paunglaung Hydropower Project.
Ch. Rohrer joined AF-Colenco Ltd. (formerly Colenco Power Engineering Ltd.) in 2002 after obtaining his MSc in Civil
Engineering from the Swiss Federal Institute of Technology Zurich. He was involved in the Son La and Lai Chau RCC dam in
Vietnam and Tasang and Yeywa RCC dams in Myanmar. He currently is the dam designer and deputy project director of the
103m high Upper Paunglaung RCC dam in Myanmar and also is involved in the 120m high Shweli RCC dam in Myanmar.
The Upper Paunglaung RCC dam – design and construction
ABSTRACT: The paper gives an overview of the Upper Paunglaung project layout and the cur-
rent situation of the construction and describes how the dam design was adapted for a rapid dam
construction. It also describe the challenges of flood protection during construction, the unfor-
tunate weather condition during the wet season, the challenging access to the site for transporta-
tion of the construction materials, as well as the initial stages of the RCC mix design and the
performance of the RCC full Scale trial embankment in May 2010.
1 INTRODUCTION
The 140 MW Upper Paunglaung hydropower project is owned by the Ministry of Electric Pow-
er No.1 and comprises a 103m high RCC (roller compacted concrete) gravity dam with Power-
house located on the left bank at the toe of the dam. It will be the second RCC dam constructed
in Myanmar and the first built by local contractors. An ungated spillway is located in the central
section of the dam for flood water discharge. The Project situated on the Paunglaung River up-
stream of the existing Paunglaung Hydropower plant (280MW) is located 50km east of the Cap-
ital Nay Pyi Taw, in Mandalay Division, Myanmar (Figure 1).
Figure 1. Project map Figure 2. General layout of the Upper Paunglaung Hydropower Project
The purpose of the project is the production of hydro-electric power. The large reservoir with a
capacity of 1.3 Mia m3 represents a seasonal storage and increases the energy production poten-
tial of the existing power plant.
2 PROJECT LAYOUT
2.1 General Layout
The general layout of the project is shown in Figure 2. The project essentially comprises a 103m
high RCC gravity dam with an ungated spillway and a bottom outlet, both integrated into the
dam body. Two power intakes are placed on the upstream face of the dam. Two penstocks pass
through the dam body, which are connected by steel penstocks on the downstream face leading
to the powerhouse. A separation wall separates the powerhouse from the spillway and river sec-
tion. A diversion tunnel is located in the right bank. It will be plugged prior to impounding.
Figure 3. Diversion Inlet under construction Figure 4. U/s Cofferdam with clay core
For higher floods, the advantage of the over-topping capability of an RCC dam and arrangement
of its construction sequences is taken into account to keep the work site safe against major dam-
ages by floods passing over the river section of the RCC dam. As shown in Figure 3 and 4 the
diversion tunnel and cofferdams have been constructed and river diversion took place success-
fully in December 2008.
Consolidation grouting is foreseen in the entire dam footprint with drilling spacing from 6m to
3m. A grout curtain with 10° inclination towards upstream and maximum dept of 80m is the
main feature to prevent seepage though the underground composed of metasandstone and gra-
nite. A drainage curtain will be executed downstream of the grout curtain. For the RCC gravity
dam stability analysis as well as detailed finite element analysis has been carried out. The static,
dynamic and thermodynamic conditions of the dam body were analyzed.
Taking into account the local conditions and capability of the contractor, the RCC sequences are
defined as follows: RCC stage 1, 2 and 3 are to be built first with short interruptions for the con-
struction of the horizontal galleries. This also allows the contractor to construct the bottom out-
let next to RCC stage 1. After completion of stage 3, the intake towers and penstocks will be
built, while RCC stage 4 and 5, in the centre of the river will be built. As soon as the upper, ho-
rizontal penstock encasement is built, RCC stage 6 shall be constructed. Thereafter RCC stage
7, 8 and 9 will follow, keeping the rule that the left side of the dam is always built ahead of the
right side to guarantee flood protection of the powerhouse area.
Figure 9. Profile of the access road from Paunglaung Plant to Upper Paunglaung construction site
To emphasize the importance of a proper access road some material flow data over the year is
presented. The RCC dam with a concrete volume of approximately 950’000 m3 shall be built
within 17 months. That means on average 120’000 tons of aggregates per month have to be
transported from quarry to the batching plant. 12’300 tons of cementitious materials (cement
and natural pozzolan) have to be transported over the 65km long access road every month. As-
suming the use of 20 ton trucks, an average of 20 trucks journeys are required every day.
Figure 10. Aggregates 20mm-10mm Figure 11. RCC trial mix in the laboratory
The trial mix program was carried out in two stages at DHPI’s (Department of Hydropower Im-
plementation) Concrete and Soil Laboratory in Paunglaung. The first stage of testing started in
September 2009 (Figure 10 and 11), where different cement sources, aggregates materials, vari-
ous mix proportions and admixtures were tested. At this stage the final quarries and crushing
plants for the aggregates production were not yet fully developed. The aggregates had been tak-
en from the rock surface and had been crushed in a temporary plant. Nevertheless the results of
the testing program were quite promising. The Stage 2 trial mix program concentrated on the
optimization of the mixture proportion as well as testing of leveling concrete mixes. The RCC
mix which will most likely be selected is in the order of 70kg of cement and 160kg of natural
pozzolan.
4 CONSTRUCTION IMPEMENTATION
4.1 Separation wall
In parallel with dam and powerhouse excavation works, site installations and concrete testing,
the construction activities continued. After river diversion in December 2008 the excavation in
the river bed started and the construction of the separation wall followed. The separation wall is
located in the river bed downstream of the dam toe, between the powerhouse and the impact
area of the spillway. It is 100m long, 15m wide and 25m high. For ease of construction, to save
time and to use the opportunity to use the structure as a first RCC trial, it has been decided to
build the wall in RCC (Figure 14) and not with conventional concrete. The design of the wall
has been adapted to correspond with RCC placing. Typical RCC features such as block joints,
waterstops and drainage pipes and a gallery system have been introduced for training the RCC
laborers. As result, the construction of the separation wall built by DHPI was a great success
(Figure 15).
Figure 14. Separation wall under construction Figure 15. Separation wall completed
Figure 16. Leveling concrete and RCC Figure 17. Conveyor belt foundation
5 CONCLUSION
The design and construction planning of the Upper Paunglaung RCC dam it is based on well es-
tablished methods, on the experience made in Myanmar and on the experience of the local con-
tractors who have already been involved in a similar project. The original design has been ad-
justed to suit the local conditions, the available equipment and other limitations. Importance has
been given during the design to allow construction of the RCC dam as simple as possible and to
assure continuous RCC placing with the aim to guarantee a high quality of the RCC.
Upper Paunglaung HPP,
Myanmar
The 140 MW Upper Paunglaung hydropower project is periods and increases the power production of the existing
owned by the Ministry of Electric Power and comprises downriver power station Paunglaung.
a 103 m high RCC (roller compacted concrete) dam with The general layout of the Upper Paunglaung project con-
a powerhouse located on the left bank at the foot of the sists of the following structures:
dam. An ungated spillway is located in the central section • 10 m diameter concrete lined diversion tunnel, 290 m
of the dam for flood water discharge. The project on the long on the right bank which will be plugged for
Paunglaung River up-stream of the existing Paunglaung impounding of the reservoir
hydropower plant, with a 280 MW installed capacity, is • 103 m high RCC gravity dam with a crest length of
located 50 km east of the capital city Nay Pyi Taw, in Man- 530 m and a concrete volume of 950,000 m3
dalay Division, Myanmar. • Dam integrated converged spillway, maximum 67 m in
AF-Colenco was awarded a contract for a feasibility study width, designed for flood discharge of 1,750 m3/s
of the project in 2004 followed by contracts for the basic • Dam integrated bottom outlet with two openings 3 m
design in 2006 and finally the construction design of x 2 m and maximum discharge of 350 m3/s, equipped
the civil works in 2008. After completion in 2012, the with radial gates for operation and sliding gates for
Upper Paunglaung dam will be the second RCC dam in maintenance
Myanmar and the first of its kind built in Myanmar by local • Two trumpet shaped power intakes located upstream of
contractors. the dam axis, equipped with trash racks, roller gates for
The reservoir of the Upper Paunglaung hydropower project, operation and sliding gates for maintenance
fed by a 2,570 km2 catchment area, extends to an area of • Two 140 m long open penstocks, 4.8 m in diameter,
61 km2 with a volume capacity of 1.3 Mia m3. The resulting leading from the intakes through the RCC dam to the
reservoir of the Upper Paunglaung project, with its immense powerhouse
retention effect, reduces flooding, stores water for dry
schritte zu einer Anlagengrösse für einen Energieeinsatz von operations in a plant size of approx. 5 MW thermal input.
ca. 5 MW kombiniert. AF-Colenco was identified as being capable of proving the
AF-Colenco wurde für kompetent erachtet und beauftragt die technical plausibility of the plant concept, which is still under
technische Plausibilität des Konzeptes, das derzeit noch ei- confidential status.
nem Geheimhaltungsabkommen unterliegt, zu überprüfen und The result of the assessment confirmed the predicted figures
für die Marktauglichkeit zu bewerten. and was presented to the client. Improvements that were
Das Ergebnis der Prüfung, das dem Kunden vorgestellt wur- made by AF-Colenco concerning some unit operations were
de, war die Bestätigung der avisierten Anlagenparameter. Ver- adapted in the further development to a series production.
besserungsvorschläge, die von AF-Colenco zu einigen Verfah- The first power plant for commercial operation is planned to
rensschritten gemacht wurden, sind in die weitere Entwick- be put into service by mid 2011.
lung zur Serienproduktion eingeflossen. Die erste kommerziell
genutzte Anlage soll Mitte 2011 in Betrieb gehen. Preparation of licensing documents for a biomass
power plant providing industrial customers with pro-
Genehmigungsplanung für eine Biomasse-Anlage zur cess steam for EGP GmbH, Schwerin, Germany
Versorgung von Industriebetrieben mit Prozessdampf Commissioned by Bankhaus Lampe in Hamburg, EGP GmbH,
für die EGP GmbH, Schwerin, Deutschland Schwerin, secured the first commercial operation of the
Den ersten kommerziellen Einsatz des oben beschriebenen system described above. A cheese producing factory and
Verfahrens sicherte sich die Projektentwicklungsgesellschaft a brewery, both located in the city of Dargun, Mecklenburg,
EGP GmbH, Schwerin, im Auftrag des Bankhauses Lampe in Germany, were landed as project partners for heating energy
Hamburg. Als Projektpartner, welche die Wärmeenergie ab- consumption.
nehmen werden, konnten eine Käsefabrik sowie eine Brauerei The design of the plant foresees the construction of a bio-
im mecklenburgischen Dargun, gewonnen werden. mass cogeneration power plant with an electrical power out-
Das Anlagenkonzept sieht die Errichtung eines Heizkraftwer- put of approx. 5.5 MW in addition to the same amount of
kes mit ca. 5.5 MW elektrischer Leistung und noch einmal thermal energy.
der gleichen Menge thermischer Energie als Prozessdampf Because of the acquired knowledge of the plant design result-
vor. ing from the market launch study, the mandate for preparing
Aufgrund der Anlagenkenntnis, die bei AF-Colenco aus der licensing documents was awarded to AF-Colenco. Currently,
Markteinführungsstudie vorlag, konnte der Auftrag für die the administrative approval procedure is stalling but the
Genehmigungsplanung nach Baden geholt werden. Zwar ist partners in the project look forward to the realization by mid
der Genehmigungsprozess im Augenblick etwas ins Stocken 2011.
geraten, die Projektbeteiligten sehen jedoch einer Realisie-
rung der Anlage in 2011 optimistisch entgegen. Assessment of the fuel conveyor system in a biomass
power plant for Holcim, Italia
Studie zur Bewertung der Brennstofffördertechnik in Fusine Energia Srl, a subsidiary of Holcim Italia, constructed
einem Biomasse-Kraftwerk für Holcim, Italia a biomass power plant with approximately 7 MW electrical
Ein Tochterunternehmen der Fa. Holcim Italia, die Fa. Fusine power output in the community of Fusine, Province Sondrio,
Energia Srl, hat in der Gemeinde Fusine, Provinz Sondrio, in the Lombardy Region in Italy.
Region Lombardei ein Biomasse-Kraftwerk mit ca. 7 MW It was discovered during commissioning of the plant, that the
elektrischer Leistung errichtet. fuel conveyor system, which is a very important but normally
underestimated part, did not work according to the require-
ments of the plant.
AF-Colenco was commissioned to
analyze the fuel conveyor system,
installed by the EPC contractor.
This involved identifying the weak
points and assessing the improve-
ment concept elaborated by
another contractor.
Both tasks were handled to the
complete satisfaction of the
customer.
2
AF-Colenco AG INFO
Bei der Inbetriebnahme des Kraftwerks stellte sich heraus, Support with evaluation of tenders and negotiations
dass ein wesentlicher, aber in der Regel unterschätzter, An- of a cogeneration power plant comprising photovol-
lagenteil, nämlich die Brennstofffördertechnik nicht so funk- taics and geothermal energy for Stadtwerke München
tionierte, wie es der Betrieb der Anlage erforderte. (SWM), Munich, Germany
AF-Colenco wurde beauftragt die vom Generalunternehmer Stadtwerke München (SWM) operate a 2 GW district heating
installierte Fördertechnik zu analysieren, d. h. die Schwach- system within the city limits of Munich. In order to supply a
punkte zu identifizieren und das Ertüchtigungskonzept eines new urban district in the west end of the city, SWM is building
anderen Lieferanten, das Fusine Energia Srl mittlerweile vor- a new cogeneration power plant. This power plant will pro-
lag, auf Betriebstauglichkeit zu überprüfen. duce approx. 140 MW of thermal energy in the final step. It
Beide Aufgaben wurden zur vollsten Zufriedenheit des Kunden will comprise gas fired water-boilers, gas-powered combined
bearbeitet. heat and power units as well as photovoltaic and geothermal
energy.
Unterstützung bei der Angebotsauswertung und Auf- The rated output of the photovoltaic plant will be approx. 30
tragsvergabe für ein Heizkraftwerk mit einem Photovol- kW, with a yearly generation of approximately. 33,500 kWh.
taik- und einem Geothermie-Anteil für die Stadtwerke From the geothermal source located at a depth of 3,000 m
München (SWM), Deutschland below the surface, warm water with a temperature of approx.
Die Stadtwerke München, die im Stadtgebiet ein Fernwärme- 85°C and thermal capacity of approx. 25 MW is expected.
netz mit ca. 2 GW Anschlussleistung betreiben, bauen zur According to this relatively low temperature, this source
Erschliessung eines neuen Stadtteiles ein Heizkraftwerk im serves only for heating purposes. In the best case however,
Westen der Stadt. Das Heizkraftwerk, das im Endausbau ca. it will be operated 8,760 h/a.
140 MW Wärme erzeugen wird, umfasst einen Energiemix The tender documents for this cogeneration power plant were
von gasbefeuerten Heisswasserkesseln, Gasmotor-BHKWs, elaborated by SWM themselves. AF-Colenco was mandated
Photovoltaik und Geothermie. to assess the submitted offers regarding technical and com-
Die Leistung der Photovoltaik-Anlage wird ca. 30 kW betragen mercial aspects and to bring up the offers to such a level,
mit einer Jahresausbeute von ca. 33'500 kWh/a. that final negotiations could be performed.
Aus der Geothermie, die aus einer Tiefe von 3'000 m Warm- AF-Colenco managed the final technical negotiations and elab-
wasser von ca. 85°C liefern soll, wird eine Wärmeleistung von orated a proposal for the awarding of the contract. This pro-
ca. 25 MW erwartet. Aufgrund der relativ niedrigen Tempera- posal was accepted and put into effect by SWM.
tur dient diese Energiequelle nur der Wärmeproduktion, dies
allerdings in der Grundlast, d. h. die Geothermie wird im Ideal-
fall 8'760 h/a in Betrieb sein.
Die Ausschreibung für das Heizkraftwerk wurde von SWM
selbst erstellt. AF-Colenco wurde beauftragt, die Angebote,
die auf die Ausschreibung eingegangen waren in technischer
und kommerzieller Hinsicht zu prüfen, auszuwerten und auf
den Stand zu bringen, so dass finale Auf-
tragsverhandlungen durchgeführt werden
konnten.
AF-Colenco führte die technischen Schluss-
verhandlungen im Auftrag der SWM durch
und erarbeitete daraufhin einen Vergabe-
vorschlag, der von den SWM angenommen
und realisiert wurde.
Bohn Architekten, DE
3
INFO AF-Colenco AG
RCC Trennwand
RCC Separation wall
linke Talflanke der Staumauer
Main Dam right Abutment
oberwasserseitiger Fangdamm
Auslauf des Umleitstollens Upstream Cofferdam
Diversion Tunnel Outlet
rechte Talflanke der Staumauer
Zufahrtstrasse zur Mauerkrone Main Dam left Abutment
Access Road to Dam Crest
Plattform für Schaltanlage
Switchyard platform
unterwasserseitiger Fangdamm
Downstream Cofferdam
4
AF-Colenco AG INFO
Eine 103 m hohe RCC-Gewichtsmauer mit einer Kronenlän- Two trumpet shaped power intakes located upstream of
ge von 530 m und einem Betonvolumen von 950’000 m3. the dam axis, equipped with trash racks, roller gates for
Eine 67 m breite Hochwasserentlastungsanlage, welche operation and sliding gates for maintenance.
in der Mauer integriert ist, mit verengender Schussrinne, Two 140 m long open penstocks, 4.8 m in diameter, lead-
ausgelegt für ein Hochwasser von 1’750 m3/s. ing from the intakes through the RCC dam to the power-
Ein in die Mauer integrierter Grundablass mit zwei Öffnun- house.
gen von 3 m x 2 m und einer maximalen Abflusskapazität Powerhouse with two Francis turbine units of 70 MW ca-
von 350 m3/s, ausgestattet mit Segment- und Gleitschütz- pacity each, two vertical 3 phase synchronous generators
en. and two transformer bays.
Zwei Einlaufbauwerke mit Einlauftrompete, oberwassersei- Tailrace channel 45 m wide and 120 m long which diverts
tig angeordnet an die Staumauer, ausgestattet mit einem the water back to the river.
Grobrechen, Rollschützen für Betrieb und Gleitschützen für 230 kV switchyard platform on the downstream left bank
Inspektion und Wartung. above the tailrace channel.
Zwei 140 m lange Druckleitungen mit 4.8 m Durchmesser, 30 km long high voltage transmission line to existing
welche von den Einläufen durch die Mauer zum Maschinen- Paunglaung power plant.
haus führen. The RCC gravity dam is characterized by a vertical upstream
Ein Maschinenhaus mit zwei 70-MW-Francis Turbinen, mit face, a stepped downstream face and a height of 103 m.
vertikalen 3 Phasen-Synchrongeneratoren, und 2 Transfor- The present dam layout has four kinks due to the difficult
matoren-Einheiten. geological conditions of the dam foundation. The foundation
Ein 45 m breiter und 120 m langer Auslaufkanal, der das consists mainly of metasandstone but is discontinued by a
Nutzwasser in den Fluss zurückführt. granite intrusion. There are three horizontal galleries for in-
Eine 230-kV-Schaltanlagen-Plattform an der linken Talflanke spection, monitoring and drainage and two inclined galleries
oberhalb des Auslaufkanals. on both abutments for grouting and drainage purposes. The
Eine 30 km lange Hochspannungsleitung die zum beste- spillway, with a maximum width of 67 m at the crest and a
henden Paunglaung Wasserkraftwerk führt. design discharge of 1,750 m3/s, is integrated in the dam
Die RCC-Staumauer ist eine Gewichtsmauer mit vertikaler body at the river section. The bottom outlet, equipped with
Wasser- und geneigter abgetreppter Luftseite und charakteri- radial and sliding gates, is integrated in the dam body as
siert durch die Höhe von 103 m. Die Mauer weist im Grund- well.
riss 4 Knicke auf, die wegen den schwierigen geologischen With the ambitious target of completing the dam in 2012, it
Verhältnissen in der Fundation erforderlich wurden. Die Mauer- is necessary to minimize the interferences to the RCC place-
fundation besteht hauptsächlich aus Metasandstein, ist aber ment in order to achieve a rapid construction. Due to the size
durch eine Granit-Intrusion in der Mauermitte unterbrochen. of the dam and the capacity of the batching plant, as well
Im Mauerkörper gibt es drei horizontale Galerien für Inspek- as the potentially high floods during the wet season, con-
tions-, Überwachungs- und Entwässerungszwecke, sowie zwei struction of the Upper Paunglaung dam will be split into two
Schräggalerien an den Talflanken für Injektionen und die Ent- halves, the river/spillway section and the powerhouse sec-
wässerung des Untergrundes. Die Hochwasserentlastung mit tion. It is planned to place the RCC in the left (powerhouse)
einer maximalen Breite von 67 m an der Krone und einer ma- section during the wet season and in the right (river/spillway)
ximalen Abflusskapazität von 1’750 m3/s ist in die Staumauer section during the dry season in order to protect the power-
integriert. Der Grundablass ist ausgestattet mit Segment- und house construction from flood water. With this solution, an
Gleitschützen und ist ebenso in die Staumauer integriert. overtopping of the dam during high floods at the river section
Um das ehrgeizige Ziel zu erreichen, die Staumauer bis Ende is acceptable and a factor in the planning.
Walzbeton-Grossversuch (oben). Maschinenhausbau bei Einheit 2 mit Powerhouse construction of Unit 2 with draft tube installation (above).
Einbau des Saugrohrs (rechts) RCC full scale trial embankment (left)
5
INFO AF-Colenco AG
6
AF-Colenco AG INFO
MW (4 Maschinengruppen) wird zur Kontrolle von Störungssi- the load curve of the power system 24 hours a day. The most
tuationen im Versorgungsnetz genutzt, wenn Ausfälle anderer important system services, such as reactive power control,
Erzeuger auftreten oder Teile des Netzes ausfallen. Das Kru- emergency reserve and black start capability, are performed
onis PSW regelt die Netzbelastung rund um die Uhr. Die wich- by the Kruonis PSPP. The electricity from the power plant is
tigsten Aufgaben des Kruonis PSW in Bezug auf das Strom- supplied to a 330 kV network.
versorgungsnetz sind der Lastausgleich und die Bereitstel- The plant was initially planned and projected for 1,800 MW
lung einer Notversorgung, sowie die Schwarzstart-Fähigkeit. (8 units) and the power intake structure, penstock founda-
Die Energie aus dem Kraftwerk wird in eine 330-kV-Leitung tions and powerhouse structure already exist to accommo-
eingespeist. date 8 units.
Die Anlage wurde anfangs für eine Leistung von 1'800 MW In order to meet system regulation demand, Kruonis PSPP is
(8 Maschinengruppen) geplant und ausgearbeitet. Einlaufbau- planning to build a new flexible asynchronous hydro unit with
werk, Fundamente für die Triebwasserleitungen und das Ma- an approximate 250 MW output (referred to as Unit No. 5),
schinenhaus wurden bereits zur Unterbringung von acht expanding the total installed capacity up to 1,150 MW. The
Maschinengruppen ausgeführt. new unit and associated equipment will be introduced in the
Der Betreiber des Kruonis PSW plant den Bau einer neuen, existing powerhouse.
flexiblen Asynchronmaschine mit einem Output von bis zu The enlargement of the plant also foresees the installation of
250 MW (Unit 5), um die entsprechende Nachfrage nach Re- a new 7.5 m diameter and 850 m long penstock. The new
gelenergie zu erfüllen. Dies erweitert die Anlagengesamtleis- penstock will run along the slope between the power intake
tung auf rund 1'150 MW. Die neue Maschinengruppe samt structure and the powerhouse beside the four existing pen-
zugehöriger Ausrüstung wird im bestehenden Maschinenhaus stocks already in operation. The new penstock will be instal-
untergebracht. led and integrated into existing intake and powerhouse struc-
Der Ausbau der Anlage sieht ebenso den Bau einer zusätzli- tures by connecting it to the existing upper and lower existing
chen Druckrohrleitung mit einem Durchmesser von 7.50 m embedded pipes. It is also a requirement for the penstock
und einer Länge von 850 m vor. Die neue Druckrohrleitung design to use the existing pile foundations to transfer the
wird neben den vier in Betrieb stehenden Triebwasserleitun- loads from the penstock and the upper and lower compen-
gen verlegt und an die bereits im Einlaufbauwerk und im Ma- sation beams to the ground.
schinenhaus integrierten Rohrstücke angeschlossen. Eine A challenging part of the work for Kruonis PSPP Project was
Anforderung an die Planung der neuen Druckrohrleitung ist to prepare, in a very tight schedule, the feasibility study and
die Verwendung der schon bestehenden Fundamente zur Ab- tender documents for the implementation of the new Unit No.
leitung der Lasten aus der Druckleitung in den Untergrund. 5 and the penstock in the form of an EPC contract. In order
Eine Herausforderung bei den Arbeiten zum Ausbau des Kru- to define the scope of supply and properly evaluate the future
onis PSW war die zeitlich sehr eng gefasste Erstellung der proposals, taking into account the various mechanical and
Machbarkeitstudie wie auch der Ausschreibungsunterlagen civil design constraints and uncertain parameters, available
für die Ausführung der neuen Unit 5 und der Druckrohrleitung data in Russian relating to the existing power plant was col-
für einen EPC-Vertrag. Zur Beschreibung des Liefer- und Leis- lected, translated, and studied. Some of the key statements
tungsumfangs und zur Ermöglichung einer einwandfreien Be- required to be analysed during the feasibility and tender
wertung der Angebote mussten etliche mechanische und bau- phase were:
liche Zwangsbedingungen berücksichtigt werden. Zu diesem The existing unit setting level, draft tube and penstock
Zweck mussten die teilweise unvollständigen Ausführungsun- interface at the powerhouse to accommodate a bigger
terlagen der Anlage in russischer Sprache zusammengesam- unit and impact on cavitation, eventual repair costs, and
melt, übersetzt und eingesehen werden. Einige ausgewählte plant availability.
in der Machbarkeitsstudie und Ausschreibungsphase zu unter-
suchenden Schlüsselpunkte waren:
Blick auf das bestehende Kruonis PSW mit betonumhüllten View of existing Kruonis PSPP and existing concrete
Druckrohrleitungen encased penstocks
7
INFO AF-Colenco AG
Vorhandene Pfähle und Betonbalken am oberen Ausgleichsblock und Indoor view of existing powerhouse and interface between unit and lo-
Übergang zwischen Druckrohr und Einlaufbauwerk (oben). Innenan- wer connection embedded pipe (above). Existing piles and concrete
sicht des bestehenden Maschinenhauses und Übergang zwischen beams at the upper compensation beam and interface between pen-
Maschinengruppen und eingebauten Anschlussrohren (rechts) stock and power intake (left)
Bestehende Einbaukote der Maschinengruppe, Schnittstel- Limited space in the powerhouse and existing powerhouse
len von Saugrohr und Druckrohrleitung im Maschinenhaus, structural grid to house a bigger state-of-the-art asynchron-
Auswirkungen hinsichtlich Kavitation und allfällig zu erwar- ous machine and its converter.
tenden Reparaturkosten sowie die Anlagenverfügbarkeit. Expected cycle efficiency figures for the big unit (250 MW)
Begrenzter Raum im Maschinenhaus und bestehende Bau- and eventually a smaller one (225 MW).
substanz bzgl. der Unterbringung einer grösseren, dem Change in the penstock concept required by the client,
Stand der Technik entsprechenden Asynchronmaschine from concrete encased (existing penstocks) to exposed
und Umwandler penstock for Unit No. 5 and its consequences on the
Erwartungswerte des Wirkungsgrads der grossen feasibility due to the prevailing uncertain geological and
250-MW-Maschinengruppe und einer eventuell kleineren geotechnical conditions, existing piles settlement, distri-
225-MW-Gruppe. bution of ring girder supports and their interface with the
Änderung des Druckrohrleitungskonzepts von den beste- existing piles and pile capacity, number, location and type
henden betonumhüllten Druckleitungen in eine freiliegende of expansion joints, feasibility and viability of constructing
Druckleitung für die Maschine 5 mit entsprechenden Kon- anchor blocks, geometry and distribution of existing foun-
sequenzen hinsichtlich Machbarkeit. Dabei werden die dations among other constraints.
geologischen und geotechnischen Zustände, bestehende The exposed penstock concept condition and expected
Pfahlsetzungen, Verteilung der Auflager der Ringträger und particular load cases as well as functional, serviceability
ihre Schnittstellen mit den vorhandenen Pfählen, Pfahltrag- and durability requirements like freezing exposure, thermal
fähigkeit, Anzahl, Lage und Art der Dehnungsfugen, Mach- loads and associated deformations, friction forces, in-
barkeit und Brauchbarkeit von Ankerblöcken, Geometrie duced vibration, vacuum conditions, handling and installa-
und Verteilung vorhandener Gründungen und weitere Rand- tion, external corrosion protection, instrumentation among
bedingungen geprüft und verifiziert. others.
Zustände der freiliegenden Druckrohrleitung und jeweilig As a result of works carried out by AF-Colenco, a feasibility
zu erwartende Lastfälle, sowie Anforderungen an die Funk- study was submitted and approved by the
tionalität, Gebrauchstauglichkeit und Dauerhaftigkeit bzgl. client in mid 2010. The assessments and
Frosteinwirkung und Verformungen aus Temperaturbelas- conclusions in the study were used as a
tung, Reibungskräften, induzierten Schwingungen, Vaku- basis for writing up the specifications for
umszuständen, Bearbeitung und Einbau, äusserer Korrosi- the EPC contract which successfully com-
onsschutz, Instrumentierung, etc. bined the boundary conditions and require-
Die aus der Arbeit von AF-Colenco entstandene Machbarkeits- ments of the extension project.
studie wurde dem Kunden Mitte 2010 übergeben und von die-
sem genehmigt. Die Bewertungen und Schlussfolgerungen Claudia Polimanti +41 (0)56 483 17 33
aus dieser Studie wurden als Basis für die Erstellung der Spe- [email protected]
zifikationen für den EPC-Vertrag übernommen, welche in ge-
lungener Weise die Randbedingungen und Anforderungen des
Ausbauprojekts verbinden.
Impressum
Herausgeber: AF-Colenco AG, Täfernstrasse 26, Tel: +41 (0)56 483 12 12
CH-5405 Baden, Schweiz/Switzerland Fax: +41 (0)56 483 12 55
Redaktion: M. Schläpfer +41 (0)56 483 13 54 E-mail: [email protected]
Layout: St. Shulist +41 (0)56 483 15 53 Internet: www.af-colenco.com