Project: PSR3 Bridge
Date: June 13, 2023
Subject: Site Inspection Report -2
DATE FINDINGS RECOMMENDATIONS REMARKS
June 08, 2023 ❖ Consultant arrived ❖ AMH consultancy ❖ Consultant
at 10:10am provided left at
locations map or 11:50am
❖ Well Built Contractor points for the
arrived at 10:45am testing
❖ Mud and Water ❖ Engineer of Well
accumulated in the Built recommend
foundation/slab area to pump out the
during Conducting water and mud in
of coring and the testing area.
rebound test
❖ They conduct ❖ Suggest to As soon as possible
2 coring tests, 1 for reschedule the 4 if the weather will
Slab/foundation and Rebound be good
1 for wall (W-2) Hammer test for
For Rebound Slab/foundation
Hammer Test, 4 for due to the poor
slab/foundation, 4 condition of the
for wall (W-1) and 4 Slab.
for wall (W-2)
❖ Taking of pictures
and videos are
required during
conducting of test
and taking of
concrete sample
as documentation
purposes.
❖ The releasing of final Release on or
report or test result before June 15,
are 7 days after the 2023
testing which is
specified in the
contract
PLEASE SEE ATTACHED PICTURE AS REFERENCES
Prepared by:
__________________
ROBERTO NOLLORA JR
SITE ENGINEER
Received by:
__________________
REBOUND HAMMER TEST
WALL (W1)
REBOUND HAMMER TEST
WALL (W2)
REBAR SCANNING
TO DETERMINE THE REBAR SPACING AND REBAR LOCATION
MAP/LAYOUT - LOCATION OF POINTS
CORING OF CONCRETE
SAMPLE CONCRETE SPECIMEN