G71770-AC 281-V181-J08 - GIS Roof Floor Slab DWG For GIS BLDG - R0
G71770-AC 281-V181-J08 - GIS Roof Floor Slab DWG For GIS BLDG - R0
T.O.SLAB T.O.SLAB
SECTION EL.15.200M. EL.15.200M.
H-H
T.O.SLAB T.O.SLAB EL.15.200M. EL.15.200M.
SECTION
H1-H1
SECTION SECTION T.O.SLAB T.O.SLAB
J-J J1-J1
SECTION
H-H
SECTION
7 H1-H1
8
SECTION
6 J1-J1 7
SECTION
J-J
EL.15.200M.
T.O.SLAB
SECTION
6 G1-G1 7 8
SECTION
G-G
SECTION
SECTION SECTION K2-K2
K-K K1-K1
EL.15.200M. EL.15.200M.
SECTION
F-F
SECTION T.O.SLAB T.O.SLAB
F1-F1
E D B A
SECTION SECTION
L-L L1-L1
EL.15.200M.
T.O.SLAB
SECTION SECTION
F-F
6 F1-F1
7 8
SECTION SECTION
E L-L L1-L1 D B A
EL.15.200M. EL.15.200M.
T.O.SLAB T.O.SLAB SECTION
SECTION SECTION
E-E SECTION M-M M1-M1
E1-E1
EL.15.200M.
T.O.SLAB
SECTION
E-E
SECTION
M1-M1
SECTION
E D B A
E D E1-E1 B A
SECTION SECTION
N-N SECTION
EL.15.200M. EL.15.200M. M-M
N1-N1
T.O.SLAB T.O.SLAB
SECTION
D-D SECTION
D1-D1
EL.15.200M.
SECTION EL.15.200M.
T.O.SLAB
SECTION SECTION
D1-D1
E N1-N1
C B T.O.SLAB A
D-D
SECTION
N-N EL.15.200M. EL.15.200M.
T.O.SLAB T.O.SLAB
E D B A EL.15.200M.
T.O.SLAB
SECTION SECTION
C-C C1-C1
EL.15.200M.
EL.15.200M. EL.15.200M. T.O.SLAB
T.O.SLAB T.O.SLAB
SECTION
Drawing Control
SECTION
C-C C1-C1
EL.15.200M.
T.O.SLAB
E D B A
SECTION
B-B
SECTION
B1-B1
SECTION
B1-B1
Submission
Purpose of
PRELIMINARY
Project:
ENGINEERING APPROVAL
400kV GIS SUBSTATION AT DHOLERA
CONSTRUCTION
Scale Paper Size LOA No. (SUPPLY): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1763 DTD. 13.12.2023
Sign. Date LOA No. (ERECTION): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1764 DTD. 13.12.2023
SECTION
1:40 A0 LOA No. (CIVIL): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1768 DTD. 13.12.2023
1 A1-A1 2 3 4 5 6'
Responsible Dept. Drawn By Document Type GETCO Document NO.
SECTION
A-A
SE GP T SO SS MOHIT 2024.12.04 SWITCHYARD DRAWING XXX
SECTION SECTION
R-R R1-R1 SECTION
SECTION
S-S S1-S1
E D B A
E D B A
SECTION
T-T SECTION
SECTION
Q-Q T1-T1
SECTION
Q1-Q1
EL.15.200M. EL.15.200M.
T.O.SLAB T.O.SLAB
SECTION SECTION
T-T T1-T1
SECTION SECTION
Q-Q Q1-Q1
E D B A
E D B A
EL.15.200M. EL.15.200M.
T.O.SLAB T.O.SLAB
EL.15.200M. EL.15.200M.
T.O.SLAB T.O.SLAB
E D B A
A B C D E
IMPORTANT NOTES
A GENERAL
1. ALL DIMENSIONS ARE IN MILLIMETER UNLESS OTHERWISE SPECIFIED & LEVELS ARE IN
METER.
2. DO NOT SCALE THE DRAWING, ONLY WRITTEN DIMENSIONS SHALL BE FOLLOWED.
3. THE DRAWING MUST BE READ IN CONJUNCTION WITH ALL OTHER RELEVANT DRAWING
i.e ARCHITECTURAL, ELECTRICAL & STRUCTURAL DRAWING. (GA DRAWING OF
MANUFACTURER).
B CONCRETE
4. THE CEMENT SHALL BE ORDINARY PORTLAND CEMENT WITH C3A CONTENT FROM 5 TO
8 % FOR ALL CIVIL WORK.
5. ALL THE RCC WORK SHALL BE CARRIED OUT AS PER IS 456-2000, WITH LATEST
REVISION.
6. THE GRADE OF CONCRETE SHALL BE M-30, WITH MINIMUM CEMENT CONTENT OF 450
KG/M³. EXCEPT LEAN CONCRETE, MIX DESIGN SHALL BE DONE CONSIDERING 'SEVERE
ENVIRONMENT' EXPOSURE CONDITIONS.
7. THE GRADE OF LEAN CONCRETE SHALL BE M-20
C REINFORCEMENT
8. TMT (HIGH YIELD STRENGTH DEFORMED STEEL BARS) CRS (CORROSION RESISTANT
Drawing Control
1 2 3 4 5 6' 6 7 8 STEEL) BARS COATED WITH FUSION BONDED EPOXY PAINT OF GRADE FE-500 D BARS
CONFORMING TO IS-1786 SHALL BE USED IN ALL CIVIL WORKS.
9. REINFORCEMENT SHALL BE BENT & FIXED IN ACCORDANCE WITH THE PROCEDURE
SPECIFIED IN IS 2502-1963.
10. CLEAR COVER TO THE MAIN REINFORCEMENT SHALL BE AS UNDER
TOP BOTTOM SIDES
· FOOTING (RAFT & ISOLATED) 50 75 50
· PILE CAPS 50 100 50
· PILE 75 75 75
· GRADE BEAM - 40 40 Employer's Approval Stamp
· COLUMNS & PEDESTALS 50 - 50
A · BEAMS ABOVE GROUND LEVEL 35 35 35
RB-5(300x650) RB-19(300x650)
· GRADE SLAB 30 30 30
· LINTEL BEAMS 25 25 25
· SLABS & STAIRCASE 25 25 25
· CABLE TRENCHES BASE SLAB 20 35 35
· WALL 20 35 35
· CAP BEAM 45 45 45
11. LAP LENGTH SHOULD BE 50 TIMES OF DIA..
12. LAP AT SUPPORT SECTION, JOINT SECTION & MID SPAN SHALL BE AVOIDED.
13. OVERLAPPING OF REINFORCEMENT SHALL BE STAGGERED.
RB-6(300x500)
14. IN CASE OF CONTINUOUS SUPPORT, REINFORCEMENTS ARE DEFERENT FOR TWO
ADJACENT BEAMS / SLABS, THE HIGHER SUPPORT REINFORCEMENT OF THE TWO SHALL
B BE PROVIDED AT THE SUPPORT.
RB-20(300x500) FOR OPEN FOUNDATION (IF REQUIRED)
RB-24(300x400)
RB-8A(450x1000)
RB-8B(450x1000)
RB-23A(400x950)
EL. 15.200 M. 15. NO FOUNDATION SHALL REST ON FILLED-UP SOIL / BLACK COTTON SOIL.
RB-8(400x950)
RB-9(300x400)
RB-9(300x400)
RB-9(300x400)
VIRGIN SOIL.
C · IF FOUNDATION FALLS ON EXCAVATED TRENCHES OF ADJOINING FOUNDATION, THEN
FOUNDATION SHALL BE EXTENDED UP TO THE DEPTH OF ADJOINING FOUNDATION. Rev. Rev. Date Modification Drawn By Created By Approved By
RB-21(300x500)
· IF BLACK COTTON SOIL ENCOUNTERED, AT FOUNDATION DEPTH, THEN FOUNDATION
Drawing/Document Number
LEGEND SHALL REST ON COMPACTED SAND BED OF 300MM THICK. LOCATION DHOLERA
RB-25(300x400)
RB-26(300x550)
16. BACK FILLING OF FOUNDATION TRENCHES SHALL BE DONE WITH USE OF NON
(0)-G71770-AC 281-V181-J08 P- 091281_E_C5_8843_DHO_0
RB-23(400x950)
Submission
SPACING 18. THE GRADE OF CONCRETE FOR PILE SHALL BE M-30, CONFIRMING TO IS 456 WITH
Purpose of
RB-5(300x650) RB-19(300x650) MINIMUM CEMENT CONTENT AS 450 kg. / M³. WITH TREMIE CONCRETE. PRELIMINARY
BAR MARKING 19. THE PILE SHOULD PROJECT 100MM. IN TO THE PILE CAP CONCRETE.
E 20. INTEGRITY TEST TO BE DONE FOR ALL PILES, PRIOR TO CAST PILE CAP. Project:
21. PILE CONCRETE SHALL BE DONE WITH MINIMUM LEAD TIME AFTER “PILE BORE” IS
ENGINEERING APPROVAL
DIA OF BARS 400kV GIS SUBSTATION AT DHOLERA
ACCEPTED & CLEARED FOR REINFORCEMENT PLACEMENT AND CONCRETING. IN NO
CASE, PILE BORE SHALL REMAIN OPEN FOR MORE THAN FOUR HOURS AFTER CONSTRUCTION
DIAMETER(FE500,IS:1786)H.Y.S.D. ACCEPTANCE.
D FOUNDATION BOLT (IF REQUIRED) LOA No. (SUPPLY): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1763 DTD. 13.12.2023
No.OF BARS 22. BEFORE CONCRETING, LOCATION OF FOUNDATION BOLT SHALL BE CHECKED &
Scale Paper Size
Sign. Date LOA No. (ERECTION): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1764 DTD. 13.12.2023
APPROVED BY ENGINEER IN CHARGE. 1:100 A0 LOA No. (CIVIL): ACE(P&C)/Contract/E-100/400kV Dholera GIS/1768 DTD. 13.12.2023
23. FOUNDATION BOLT SHALL BE CONNECTED TO REINFORCEMENT CAGE BY MEANS OF
12 MM. DIA. BAR. (TO PROVIDE THE EARTHING TO THE FOUNDATION) Responsible Dept. Drawn By Document Type GETCO Document NO.
1 2 3 4 5 6' 6 7 8 24. IF FOUNDATION BOLTS FOUL WITH STIRRUPS, STIRRUPS MAY BE ADJUSTED AT SITE.
2024.12.04 SWITCHYARD DRAWING XXX
SE GP T SO SS MOHIT