CIVIL ENGG DATA - PG 11-20
CIVIL ENGG DATA - PG 11-20
= 0.429 M3
Cement = 0.429 x 30 = 12.50 bags
Sand = 0.429 x 6 = 2.57 M3
Blocks =1122 No’s
STEEL:-
THEROTICAL WEIGHT:-
CMENT REQUIREMENTS:-
M10 : 210 Kg
M20 : 320 Kg
- 10 -
M25 : 340 Kg
M30 : 380 Kg
M35 : 410 Kg
M40 : 430 Kg
M45 : 450 Kg
M50 : 450 + M.S 7.5%
General Notes for civil Engineering
Electrical conduits shall not run in column
Earth work excavation for basement above 3 m Should be
stepped form
Any Back filling shall be compacted 95% of dry density at the
optimum moisture content and in layers not more than 200mm
for filling above structure and 300 mm for no structure
F SOLING IS SPECIFIED THE SOLING STONES SHALL BE LAID
AT45° TO 60° INCLINATION (AND NOT VERTICAL) WITH
INTERSTICES FILLED WITH SAND OR MOORUM.
Y REPRESENTS TOR STEEL GRADE - Fe-415 OF IS:1786. WITH
CHARECTERISTIC YIELD STRENGTH OF 415 N/MM MINIMUM.
REPRESENTS MILD STEEL GRADE - 1 OF IS:432 (PART-1)
ALL REINFORCEMENT SHALL BE FREE FROM MILL SCALES,
LOOSE RUST & COATS OF PAINTS, OIL OR ANY OTHER
SUBSTANCES.
BY PROVIDING PROPER COVER BLOCKS, SPACERS, CHAIRS
ETC.. ALL REINFORCEMENT SHALL BE PLACED AND
MAINTAINED IN POSITION AS SHOWN IN STRUCTURAL
DRAWING
CEMENT SHALL BE 43 GRADE ORDINARY PORTLAND CEMENT
CONFORMING TO IS:8112 OR53 GRADE ORDINARY PORTLAND
CEMENT CONFORMING TO IS:12269-1987.
- 11 -
2. THE FINAL SETTING TIME SHALL NOT BE MORE THAN 10
HOURS.
SAMPLES FROM FRESH CONCRETE SHALL BE TAKEN AND AT
LEAST A SET OF 6 CUBES OF 150mm SHALL BE PREPARED AND
CURED. 3 CUBES EACH AT 7 DAYS AND 28 DAYS SHALL BE
TESTED FOR COMPRESSIVE STRENGTH. THE TEST RESULTS
SHOULD BE SUBMITTED TO ENGINEER FORAPPROVAL. IF
RESULTS ARE UNSATISFACTORY NECESSARY
ACTION/RECTIFICATION/REMEDIAL MEASURES HAS TO BE
EXERCISED.
A SET OF CUBE TESTS SHALL BE CARRIED OUT FOR EACH 30
Cum OF CONCRETE / EACH LEVELS OF CASTING / EACH BATCH
OF CEMENT.
WATER CEMENT RATIO FOR DIFFERENT GRADES OF
CONCRETE SHALL NOT EXCEED 0.45 FOR M20 AND ABOVE
AND 0.50 FOR M10 / M15 CONTRACTOR / MIX DESIGNER TO
CARRY OUT THE NECESSARY INITIAL (PRELIMINARY) TESTS.
FOR CONCRETE GRADES M20 AND ABOVE APPROVED
ADMIXTURE SHALL BE USED AS PER MIX DESIGN
REQUIREMENTS.
CONCRETE COVER
CLEAR COVER TO MAIN REINFORCEMENT IN
1. FOOTINGS : 50 mm
2. RAFT FOUNDATION.TOP : 50 mm
3. RAFT FOUNDATION.BOTTOM/SIDES : 75 mm
4. STRAP BEAM : 50 mm
5. GRADE SLAB : 20 mm
6. COLUMN : 40 mm
7. SHEAR WALL : 25 mm
8. BEAMS : 25 mm
9. SLABS : 15 mm
10. FLAT SLAB : 20 mm
11. STAIRCASE : 15 mm
12. RET. WALL : 20/ 25 mm
on earth
13. WATER RETAINING STRUCTURES : 20 / 30 mm
CONTRACTOR SHALL ALLOW FOR INDEPENDENT TESTING OF
REINFORCEMENT STEEL FOR EACH DIA OF BAR FOR EVERY 50T AND AT
CHANGE OF SOURCE.
ALL BEAM REINF. TO BE ANCHORED FOR A MINIMUM LENGTH OF 46 x
DIA OF BAR INTO COL / SUPPORTING BEAM U.N.
BINDING WIRES SHALL BE 16 GUAGE 1.6mm SOFT ANNEALED STEEL
WIRES FREE FROM RUST AND OTHER CONTAMINANTS.
CONCRETE DESIGN MIX REPORT.
1. CONCRETE DESIGN MIX REPORT ALONG WITH THE
TEST RESULTS FOR CONCRETE CUBES SHALL BE
- 12 -
SUBMITTED IN ADVANCE FOR APPROVAL BEFORE
RELEVANT CONCRETING. AND THE MINIMUM
CEMENT CONTENT SHALL BE NOT LESS THAN 300
Kg/m
2. SLUMP SHALL BE 100 + 25mm.
POURING OF CONCRETE.
NO CONCRETING OPERATION SHALL BE CARRIED OUT DURING
INCLEMENT WEATHER CONDITIONS LIKE HEAVY RAIN, STORM AND
HIGH WINDS.
REPAIRS
CONCRETE REPAIRS IN ANY STRUCTURAL ELEMENTS SHALL
BE CARRIED OUT ONLY AFTER INSPECTION AND AS PER THE
APPROVED METHOD. CONTRACTOR TO SUBMIT DETAIL
METHOD STATEMENT FOR ENGINEER'S REVIEW AND
RESPONSE
CONCRETE FLOOR SCREED SHALL BE IN PANELS OF 3M x 3M
WITH JOINTS SEALED WITH SEALANT TO MATCH WITH JOINTS
IN SLAB. LOCATIONS TO BE APPROVED BY ENGINEER PRIOR
TO CONCRETING.
ALL CONCRETING MUST STOP AT A SHUTTERED SURFACE
ONLY.
AT ALL CONSTRUCTION JOINTS THE REINFORCEMENT SHALL
BE CONTINUOUS.
CONSTRUCTION JOINT IN RETAINING WALLS & WATER TANK
SHALL BE PROVIDED WITH AN APPROVED SEALANT
ALL DEEPER EXCAVATION BELOW THE GROUND LEVEL SLAB
SHALL BE RETAINED BY A LOCALIZED SOIL AND WATER
RETENTION SYSTEM, AS MAY BE RETAINED BY A LOCALIZED
SOIL AND WATER RETENTION SYSTEM, AS MAY BE
DEWATERING BY SUITABLE MEANS TO BE ADOPTED
(ENSURING NO FINES ARE DRAWN OUT) TO KEEP THE
FOUNDING STRATA COMPLETELY DRY AND SHALL BE
CONTINUED UNTIL THE GROUND FLOOR SLAB / BEAMS ARE
CAST AND CURED TO ACHIEVE SPECIFIED DESIGN STRENGTH.
CEMENT PROPORTION: CONCRETE MIX IN ABOVE SUCH
FOUNDATIONS SHALL CONTAIN 10 PERCENT EXTRA CEMENT
THAN SPECIFIED.
AT LOCATIONS OF ISOLATION / EXPANSION JOINT PROVIDE
POLYSULPHIDE SEALANT WITH BACKER ROD POLYSTYRENE
BOARDS.
NO THROUGH BOLTS SHALL BE USED IN FORMWORK OF
RETAINING WALL. AND WATER TANK WALLS.
FOUNDATIONS
ALL LOOSE POCKETS AND SOFT SPOTS ARE TO BE FILLED IN MASS
CONCRETE OF GRADE M-10.
BACK FILLING BEHIND THE RETAINING WALL SHALL BE CARRIED
OUT ONLY AFTER THEGROUND FLOOR SLAB IS CAST AND HAS
ATTAINED DESIGN STRENGTH.
- 13 -
THE SPACE BETWEEN HARD STRATA (TO ACHIVE A MINIMUM OF 25
MT/M2) AND BOTTOM OF RAFT/ FOUNDATION SHALL BE FILLED
WITH PLUM CONCRETE.
SIZE STONE MASONRY SHALL BE IN CM 1:6 UNLESS SPECIFIED
OTHERWISE.
CONTINUOUS WALL FOUNDATION SHALL BE STEPPED IN A RATIO
OF 1 VERTICAL TO 2 HORIZONTAL WHEREVER LEVEL CHANGES ARE
NECESSARY.
SLOPED PORTION TO BE FINISHED SMOOTH WITH TROVEL WITHOUT
USING MORTAR. COLUMN PORTION TO BE FINISHED SMOOTH WITH
CONCRETE.
GRADE OF CONCRETE SHALL BE AS PER FOOTING SHEDULE/ RAFT
DETAILS.
SUPER STRUCTURE
ALL EXPOSED CORNERS OF COLUMNS AND BEAMS SHALL HAVE
STRAIGHT EDGES AND SHALL BE CHAMPHERED IF SPECIFIED IN
ARCHITECTURAL DRAWINGS.
CONCRETING OF COLUMNS , BEAMS, FACIAS, AND THIN SECTIONS
OF CONCRETE MEMBERS SHALL BE CARRIED OUT USING APPROVED
PLASTICISER AS PER MANUFACTURERS SPECIFICATIONS.
CONCRETE POURING , TESTING, REMOVAL OF FORMWORK AND
ACCEPTANCE CRITERIA SHALL BE AS PER RELEVANT INDIAN
STANDERD CODE OF PRACTICE.
CENTERING OF CANTILEVER BEAMS AND SLAB PROJECTIONS SHALL
NOT BE REMOVED UNLESS ROOF SLAB ABOVE IS CAST AND CURED
AND SUFFICIENT BALANCING LOAD IS ATTAINED. PROVIDE PRE
CAMBER TO CANT. BEAMS/SLABS
BEFORE POURING FLOOR LEVEL CONCRETE, THE FLOOR SYSTEMS
BELOW SHALL BE SUFFICIENTLY SUPPORTED BY MEANS OF
PROPPING AND THIS SYSTEM SHALL BE APPROVED BY THE
ENGINEER-IN-CHARGE.
CONCRETE IN TOILET, KITCHEN, WATER BODY AREAS SHALL BE
MIXED WITH APPROVED WATERPROOF COMPOUND AND
WATERPROOFING OVER SLABS AND SIDES OF WALLS SHALL BE
DONE AS PER ARCHITECTURAL DETAILS.
CONTRACTOR SHALL CHECK ALL THE OPENINGS AS PER
ARCHITECTURAL/SERVICE DRAWINGS AND SHALL PROVIDE
NECESSARY TRIMMING BARS.NO ADDITIONAL OPENING SHALL BE
DRILLED IN THE STRUCTURE UNLESS APPROVED.
CONCRETE SHOULD BE PLACED IN THIN LAYERS WHICH CAN BE
EFFECTIVELY COMPACTED AS THE PLACING PROCEEDS SAY IN
300mm.
WHEN CASTING COLUMNS, WALLS OR BEAMS OF DEPTH 700mm OR
MORE, A LAYER OF RICH CEMENT MORTAR SHOULD BE PLACED
FIRST. THIS IS TO AVOID ACCUMULATION OF GRAVEL IN THE
BOTTOM LAYER AND TO HAVE A BETTER BOND.
COMPACTION OF CONCERTE SHALL BE DONE BY MECHANICAL
VIBRATORS. PROPER CARE SHALL BE TAKEN TO AVOID
SEGGREGATION AND HONEYCOMBING.
- 14 -
CONTRACTOR SHALL SUBMIT SHOP DRAWINGS INCLUDING BAR
BENDING SCHEDULE FOR APPROVAL PRIOR TO TAKING UP OF
CONSTRUCTION.
THE SECONDARY BEAM BARS SHALL BE PLACED OVER MAIN BEAM
BARS WHEN THE DEPTH OF BEAMS ARE SAME AT JUNCTIONS.
SHORT SPAN STEEL SHALL BE AT BOTTOM LAYER IN TWO WAY
SLAB SYSTEM AND SPACERS BAR, CHAIRS TO TOP STEEL SHALL BE
PROVIDED WITH ADEQUATE COVER.
NO SPLICING OF BARS SHALL BE MADE AT THE POINT OF MAXIMUM
TENSILE STRESSES.
FOR SPLICES OF REINFORCEMENT, MINIMUM LAP LENGTH FOR
BARSSHALL BE 50 X DIA OF BAR.
NOT MORE THAN 1/3 OF MAIN REINFORCEMENT SHALL BE LAPPED
AT ANY SECTION.
SPLICES IF UN AVOIDABLE, MUST BE LOCATED FROM FACE OF THE
COLUMN AT NOT CLOSER THAN TWICE THE BEAM DEPTH.
SPLICES IN BEAMS SHALL BE CONTAINED BY ADDITIONAL
STIRRUPS AT A SPACING NOT EXCEEDING 150MM OVER THE ENTIRE
LENGTH OF SPLICES.
STIRRUPS SHALL BE CLOSED TYPE WITH ENDS HOOKED AT 135 WITH
10 X BAR DIA EXTENSION (BUT NOT LESS THAN 75MM).
SPACING OF STIRRUPS SHALL NOT EXCEED 200MM.
COLUMNS
CONCRETE MIX SHALL BE AS PER SCHEDULE OF COLUMNS.
P.V.C COVER BLOCKS TO BE USED WITH PRIOR APPROVAL OF
ENGINEER.
RINGS TO BE PROVIDED FOR FULL LENGTH OF MAIN RODS
TOPREVENT DISLOCATION OF MAIN BARS WHILE CONCRETING,
AT A SPACING AS SPECIFIED IN THE SHEDULE.
Ld SHALL BE
1. M25 AND ABOVE 46 x DIA
- 15 -
IN NORMAL CIRCUMSTANCES WHERE AMBIENT TEMP. DOES NOT FALL
BELOW 15 C & WHERE ORDINARY PORTLAND CEMENT IS USED &
ADEQUATE CURING IS DONE. FOLLOWING STRIPPING TIME MAY DEEM
TO SATISFY.
i. VERTICAL FORMWORK TO COLUMNS, WALLS,
BEAMS - 16 TO 24HRS
ii. SOFFIT FORMWORK TO SLABS(PROPS TO BE
REFIXED IMMEDIATELY AFTER REMOVAL OF
FORMWORK) - 3 DAYS
iii. SOFFIT FORMWORK TO BEAMS(PROPS TO BE
REFIXED IMMEDIATELY AFTER REMOVAL OF
FORMWORK) - 7 DAYS
PROPS TO SLABS:
a) SLABS SPANNING UPTO 4500 mm - 7 DAYS
b) SLABS SPANNING OVER 4500 mm - 14 DAYS
PROPS TO BEAMS AND ARCHES:
a) BEAMS SPANNING UPTO 6000 mm - 14 DAYS
b) BEAMS SPANNING ABOVE 6000 mm -21 DAYS
AT TOP
AT BOTTOM
PIN RODS/CHAIRS
- 16 -
OF STOP FORMS.CONSTRUCTION JOINTS LOCATED NEAR MINIMUM
SHEAR SHALL HAVE STOP FORMS PERPENDICULAR TO THE ACTING
FORCES. WHERE THE CONCRETE IS TO BE PLACED IN THE SECOND
POUR, THE OLD CONCRETE SHALL BE THOROUGHLY ROUGHENED
TO EXPOSE AGGREGATES.MOISTENED AND A LAYER OF RICH
FRESH MORTAR SHOULD BE LAID MMEDIATELY BEFORE FRESH
CONCRETE IS PLACED. IT SHOULD BE PLACED TO A THICKNESS OF
20 TO 30mm AND SHALL BE WORKED WELL INTO THE
IRREGULARITIES OF HARDENED CONCRETE.
ALL THE CONSTRUCTION JOINTS SHALL BE PRE-DETERMINED AS
PER THE SEQUENCE OF OPERATION AND SHALL BE GOT APPROVED.
CONSTRUCTION JOINTS SHALL BE IN ACCORDANCE WITH TYPICAL
CONSTRUCTION JOINT DETAILS.
EXPANSION JOINT DETAIL SHALL BE AS PER TYPICAL EXPANSION
JOINT DETAILS.
CURING METHOD
CURING OF SLABS AND BEAMS SHALL BE ACHIEVED BY PONDING ONLY,
FOR A MINIMUM PERIOD OF 7 DAYS.
CURING OF FOOTING TOPS,RCC WALLS,COLUMNS AND EXTERNAL BEAM
FACES SHALL BE DONE BY COVERING THEM WITH GUNNY BAGS OR
HESSIAN AND KEEPING WET CONSTANTLY FOR COMPLETE CURING
PERIOD OF 7 DAYS.
GROOVE CUTTING MACHINE SHALL BE USED FOR CHASING OF WALLS FOR
ALL ELECTRICAL CONDUITS.
4" WIDE TO 7" WIDE EXPANDED METAL MESH SHALL BE USED BEFORE
PLASTERING OF ALL CONDUIT CHASINGS IN WALLS.
FOR COLUMN-WALL JUNCTIONS & BEAM-WALL JUNCTIONS 4" WIDE
EXPANDED METAL MESH SHALL BE USED, BEFORE PLASTERING OF
CONCRETE AND WALL JUNCTIONS.
WATER RETAINING STRUCTURE
CONCRETE MIX M-25 SHALL BE USED FOR ALL WATER RETAINING
STRUCTURE WITH 330Kg/CU.M OF CEMENT MINIMUM.UNLESS OTHERWISE
SPECIFIED.
DITCHTMENT D.M OR CONPLAST LIQUID ADMIXTURE SHALL BE USED
WITH M-25 CONCRETE AT 150 ml PER BAG OF CEMENT.
PLASTERING SHALL BE DONE WITH C.M 1:4 USING PUTZ DITCHMENT D.M
OR CONPLAST LIQUID ADMIXTURE AT 150ml PER BAG OF CEMENT.
Steel =3 to 5 kg / sft
Cement =.5bags/ sft
RMC =.05 m3/sft
Block =12.5 nos /sqm
Electrical cast = Rs 133/sft
Plumbing cost = Rs 126/sft
Fire fighting cost = Rs 40/sft
External development = Rs 94.5/sft
Civil works-Structure = RS 751.25/sft
- 17 -
Finishing works = RS 467.50/sft
- 18 -
Ant terminate treatment chemical Name is chloropyrifoc 20% . Diluting
5 Lit of Chemical with 95 Lit of water and usage is 7.5 Sqm Per
liter {Diluted} .To Provide 1” Dia hole And Deep1Foot.
Labour Productivity:
Carpenter 1 Skilled
1 Un skilled 4 Sqm
- 19 -