Vaishali Qty

Estimate quantity for RCC structure

Uploaded by

Virendra Chavda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
32 views38 pages

Vaishali Qty

Estimate quantity for RCC structure

Uploaded by

Virendra Chavda
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 38

Vaishali Steel requirement

8 10 12 16 20
For footings (+ Lift pardi 6 m
height) 668 2765 305 471 116

For Columns (5.5-6.5 m height


main steel) & (4 m height rings
& links) 1857 0 363 3167 533
For RCC pardi (Details of type - B
wall assumed) 5047 3570 0 0 0
Tie beams & Staircase
(Assumed) 600 600 800 1000 0
8172 6935 1468 4637 649
1/4/2015
25 Total

0 4325

0 5919

0 8617

0 3000
0 21861

918180
TITLE BBS FOR FOOTINGS DRAWING NO
PROJECT VAISHALI, MOTERA DRAWING TITLE
DRAWING DATE
BAR BENDING SCHEDULE REVISION NO.
No. of
Sr. No. of Dia of No.of Cutting Total
Description element 8
No. bars Bar Bar Length length
s
(pu) (mm) (pu) (pu) (m) (m) (Kg)
Vaishali foundation
For Footing Jali - //toW
For A3 21 10 1 21 2.40 50.40
For A8 13 10 1 13 1.70 22.10
For A12 13 10 1 13 1.70 22.10
For A16 13 10 1 13 1.70 22.10
For A23 16 10 1 16 2.10 33.60
For A29 16 10 1 16 2.10 33.60
For C7 21 10 1 21 2.40 50.40
For B11 23 10 1 23 2.50 57.50
For B17 23 10 1 23 2.50 57.50
For C24 21 10 1 21 2.40 50.40
For D3 23 10 1 23 2.70 62.10
For D29 23 10 1 23 2.50 57.50
For F7 16 10 1 16 2.10 33.60
For E11 23 10 1 23 2.50 57.50
For E17 23 10 1 23 2.50 57.50
For F24 16 10 1 16 2.10 33.60
For G2 13 10 1 13 1.70 22.10
For G28 13 10 1 13 1.70 22.10
For H5 16 10 1 16 2.10 33.60
For H10 23 10 1 23 2.70 62.10
For I4 18 10 1 18 2.35 42.30
For I10 23 10 1 23 2.50 57.50
For K4 21 10 1 21 2.40 50.40
For K10 16 10 1 16 2.10 33.60
For J14 21 10 1 21 2.40 50.40
For J21 16 10 1 16 2.10 33.60
For N13 30 12 1 30 3.60 108.00
For L19 13 10 1 13 1.70 22.10
For L26 21 10 1 21 2.40 50.40
For O20 16 10 1 16 2.40 38.40
For O27 13 10 1 13 1.70 22.10
For R1 16 10 1 16 2.10 33.60
For P15 33 10 1 33 3.10 102.30
For P22 15 10 1 15 1.90 28.50
For Footing Jali - //toL
For A3 19 10 1 19 2.75 52.25
For A8 12 10 1 12 1.95 23.40
For A12 12 10 1 12 1.95 23.40
For A16 12 10 1 12 1.95 23.40
For A23 14 10 1 14 2.40 33.60
For A29 14 10 1 14 2.40 33.60
For C7 19 10 1 19 2.75 52.25
For B11 19 10 1 19 2.90 55.10
For B17 19 10 1 19 2.90 55.10
For C24 19 10 1 19 2.75 52.25
For D3 21 10 1 21 3.00 63.00
For D29 19 10 1 19 2.90 55.10
For F7 14 10 1 14 2.40 33.60
For E11 19 10 1 19 2.90 55.10
For E17 19 10 1 19 2.90 55.10
For F24 14 10 1 14 2.40 33.60
For G2 12 10 1 12 1.95 23.40
For G28 12 10 1 12 1.95 23.40
For H5 14 10 1 14 2.40 33.60
For H10 21 10 1 21 3.00 63.00
For I4 15 10 1 15 2.80 42.00
For I10 19 10 1 19 2.90 55.10
For K4 19 10 1 19 2.75 52.25
For K10 14 10 1 14 2.40 33.60
For J14 19 10 1 19 2.75 52.25
For J21 14 10 1 14 2.40 33.60
For N13 27 12 1 27 4.05 109.35
For L19 12 10 1 12 1.95 23.40
For L26 19 10 1 19 2.75 52.25
For O20 16 10 1 16 2.50 40.00
For O27 12 10 1 12 1.95 23.40
For R1 14 10 1 14 2.40 33.60
For P15 29 10 1 29 3.50 101.50
For P22 13 10 1 13 2.20 28.60
For M3 - M6
For Jali 26 10 1 26 5.61 145.86
47 10 1 47 3.11 146.17
6 16 1 6 5.85 35.10
8 20 1 8 5.85 46.80
4 12 1 4 5.25 21.00
Ring 88 8 1 88 2.60 228.80 90.39

For Q9-S6
For Jali 26 10 1 26 2.90 75.40
19 10 1 19 4.00 76.00
9 16 1 9 5.85 52.65
9 16 1 9 5.85 52.65
4 12 1 4 5.25 21.00
Ring 62 8 1 62 2.70 167.40 66.13

For

For H19 - 18
For jali 27 10 1 27 4.78 129.06
31 10 1 31 4.07 126.11
For B5 6 16 1 6 3.78 22.68
6 16 1 6 3.78 22.68
Ring 54 8 1 54 1.96 105.84 41.81
For B4 7 16 1 7 3.07 21.47
7 16 1 7 3.07 21.47
Ring 42 8 1 42 2.60 109.20 43.14
For B6 4 16 1 4 2.89 11.55
4 16 1 4 2.89 11.55
Ring 40 8 1 40 1.87 74.80 29.55
For B3 7 16 1 7 3.29 23.01
7 16 1 7 3.29 23.01
Ring 62 8 1 62 2.56 158.72 62.70
Top jali 34 10 1 34 2.57 87.28
27 10 1 27 3.28 88.56
For Lift pardi
3 m height
28 10 2 56 3.50 196.00
28 10 2 56 3.50 196.00
4 12 3 12 3.50 42.00
19 8 4 76 2.82 213.94 84.52
19 8 4 76 2.75 209.00 82.57
3 m height
28 10 2 56 3.50 196.00
28 10 2 56 3.50 196.00
4 12 3 12 3.50 42.00
19 8 4 76 2.82 213.94 84.52
19 8 4 76 2.75 209.00 82.57

667.91

A type basement wall


CL - 59725
Vertical 400 10 1 400 5.96 2382.00
400 8 1 400 5.96 2382.00 941.04
Horizontal 26 8 2 52 62.73 3261.70 1,288.57
Base
top 400 10 1 400 1.61 642.00
distribution 10 8 2 20 62.73 1254.50 495.60

B type basement wall (Assumed)


CL - 26685
Vertical 200 10 1 200 5.96 1191.00
200 8 1 200 5.96 1191.00 470.52
Horizontal 13 8 2 26 62.73 1630.85 644.29
Base
top 200 10 1 200 1.61 321.00
distribution 10 8 2 20 62.73 1254.50 495.60

C type basement wall


CL - 20435
Vertical 165 10 1 165 5.96 982.58
137 8 1 137 5.96 815.84 322.31
Horizontal 13 8 2 26 21.44 557.31 220.17
Base
top 165 10 1 165 1.61 264.83
distribution 10 8 2 20 21.44 428.70 169.36
5047.465
DRAWING NO DATE 4/2/2015
DRAWING TITLE
DRAWING DATE STEEL GRADE
REVISION NO. STEEL TYPE

10 12 16 20 25 Total

(Kg) (Kg) (Kg) (Kg) (Kg) (Kg)

31.11
13.64
13.64
13.64
20.74
20.74
31.11
35.49
35.49
31.11
38.33
35.49
20.74
35.49
35.49
20.74
13.64
13.64
20.74
38.33
26.11
35.49
31.11
20.74
31.11
20.74
96.00
13.64
31.11
23.70
13.64
20.74
63.15
17.59
32.25
14.44
14.44
14.44
20.74
20.74
32.25
34.01
34.01
32.25
38.89
34.01
20.74
34.01
34.01
20.74
14.44
14.44
20.74
38.89
25.93
34.01
32.25
20.74
32.25
20.74
97.20
14.44
32.25
24.69
14.44
20.74
62.65
17.65

90.04
90.23
55.47
115.56
18.67

46.54
46.91
83.20
83.20
18.67

79.67
77.84
35.84
35.84

33.93
33.93

18.25
18.25

36.36
36.36

53.88
54.67

120.99
120.99
37.33

120.99
120.99
37.33

### 305.20 470.62 115.56 - 4,324.61

1,470.37
396.30

735.19

198.15

606.53

163.47

3570 0 0 0 0
Bar Bending Lengths
No. of Cutting
Bar
Mark & Location of membe
Nos.
Bar Size a b c Bar
member rs Length
No. of
bars Total
Total no Remark 2 legged
per Weight Detailed Sketch
of bars s Stirrup
membe of bars
r a

c
135°

b
ext

135°

b
link Straight L bend C bend Joggeled

135°
Link
Concrete grade
Footing cover 50 mm
Recess over
trapezoide top 100 mm
RCC TRAPEZOIDAL
Column /
Footing size
Pedestal size
No of
Sr. No. Description
footings
Width Length D d Width Depth

(pu) (mm) (mm) (mm) (mm) (mm) (mm)


1 L26,C24,O20,J14,
C7,K4,A3 7 2200 2550 750 200 300 680
2 G28,O27,L19,
A16,A12,A8,G2 7 1600 1850 600 150 300 530
3 A29,A23,F24,J21,
K10,F7,H5,R1 8 1900 2200 680 200 300 600
4 D29,B17,E17,
B11,E11,I10 6 2300 2700 830 200 300 680
5 D3, H10 2 2500 2800 830 200 380 680
6 I4 1 2150 2600 750 200 300 750
7 N13 1 3200 3650 1050 300 380 830
8 P15 1 2800 3200 980 250 380 750
9 P22 1 1800 2100 600 150 300 600
RAPEZOIDAL FOOTINGS
Quantity for Footing Jali

Steel // L Steel // W Steel // L Steel // W Footing RCC Quantity

Total
Cutting Cutting Quantity
Dia Spacing Dia Spacing Nos Nos Quantit
Length Length per No.
y
(mm) (mm) (mm) (mm) (pu) (m) (pu) (m) (m3) (m3)

10 125 10 125 19 2.75 22 2.40 2.52 17.63

10 150 10 150 12 1.95 14 1.70 1.10 7.69

10 150 10 150 14 2.40 16 2.10 1.78 14.21

10 125 10 125 20 2.90 23 2.50 2.99 17.91


10 125 10 125 21 3.00 24 2.70 3.37 6.75
10 150 10 150 16 2.80 19 2.35 2.53 2.53
12 125 12 125 27 4.05 31 3.60 7.23 7.23
10 100 10 100 29 3.50 33 3.10 5.10 5.10
10 150 10 150 13 2.20 15 1.90 1.38 1.38
Total 80.43
Mix proportion

1 1.5 3
Shrinkage 50%
Footing
Footing Formwork
Reinforcement Material requirement (per No.)
Quantity
Quantity
Total Quantit Total
Quantity
Quantit y per Quantit Cement Sand Aggregate
per No.
y No. y
(m2) (m2) (Kg) (Kg) (Bags) (m3) (m3)

1.90 13.30 32.25 225.77 19.91 1.03 2.06

1.04 7.24 14.44 101.11 8.69 0.45 0.90

1.64 13.12 20.74 165.93 14.04 0.73 1.45

2.00 12.00 35.80 214.81 23.60 1.22 2.44


2.12 4.24 38.89 77.78 26.67 1.38 2.76
1.90 1.90 27.65 27.65 19.99 1.03 2.07
4.11 4.11 97.20 97.20 57.18 2.96 5.92
3.00 3.00 62.65 62.65 40.28 2.08 4.17
1.17 1.17 17.65 17.65 10.90 0.56 1.13
Total 60.09 Total 990.56
Wastage
Total
Rate
Amount (Rs.)
Total Amount (Rs.)
Total Material requirement

Steel Formwor
Cement Sand Aggregate
Density k factor

(Bags) (m3) (m3) (Kg/m3)(Sq.m./m3)

139.40 7.21 14.43 12.80 0.75

60.80 3.15 6.29 13.15 0.94

112.30 5.81 11.62 11.68 0.92

141.61 7.33 14.66 11.99 0.67


53.35 2.76 5.52 11.53 0.63
19.99 1.03 2.07 10.94 0.75
57.18 2.96 5.92 13.44 0.57
40.28 2.08 4.17 12.30 0.59
10.90 0.56 1.13 12.81 0.85
635.80 32.90 65.81 Average 12.29 0.74
2% 10% 8%
649 36 71
250 600 1000
162,129 21,716 71,070
254,914
Shrinkage factor 50%
Wastage
MIX PROPORTION

M5 1 5 10
M7.5 1 4 8
M10 1 3 6
M15 1 2 4
M20 1 1.5 3 7.905138 0.409091 0.818182
M25 1 1 2
No. of No.of Bar Cutting Total
Sr. No. Description No. of bars Dia of Bar
elements Length length

A29,A23,F24,J21,P22,K10, 54.00 6.000 324.000


F7,H5,R1 6 16 9
L26,C24,O20,J14,C7, 80.00 6.000 480.000
S6,K4,A3 10 16 8
D29,B17,E17,H18, 84.00 6.000 504.000
B11,E11,I10 12 16 7
G28,O27,H25,L19, 48.00 6.000 288.000
A16,A12,A8,G2 6 16 8
P15,M6 10 20 2 20.00 6.000 120.000
N13 16 20 1 16.00 6.000 96.000
H10,D3,M3 12 16 3 36.00 6.000 216.000
Q9,I4 12 16 2 24.00 6.000 144.000
- -
A29,A23,F24,J21,P22,K10, 36.00 6.000 216.000
F7,H5,R1 4 12 9
L26,C24,O20,J14,C7, - 6.000 -
S6,K4,A3 0 0 8
D29,B17,E17,H18, - 6.000 -
B11,E11,I10 0 0 7
G28,O27,H25,L19, 32.00 6.000 192.000
A16,A12,A8,G2 4 12 8
P15,M6 4 16 2 8.00 6.000 48.000
N13 0 0 1 - 6.000 -
H10,D3,M3 0 0 3 - 6.000 -
Q9,I4 0 0 2 - 6.000 -
- -
A29,A23,F24,J21,P22,K10, 8 9 810.00 1.160 939.600
F7,H5,R1 90
L26,C24,O20,J14,C7, 8 8 720.00 1.160 835.200
S6,K4,A3 90
D29,B17,E17,H18, 8 7 630.00 1.160 730.800
B11,E11,I10 90
G28,O27,H25,L19, 8 8 720.00 0.660 475.200
A16,A12,A8,G2 90
P15,M6 90 8 2 180.00 1.160 208.800
N13 90 8 1 90.00 1.200 108.000
H10,D3,M3 90 8 3 270.00 1.250 337.500
Q9,I4 90 8 2 180.00 1.250 225.000
- -
A29,A23,F24,J21,P22,K10, 9 405.00 0.310 125.550
F7,H5,R1 45 8
L26,C24,O20,J14,C7, 8 360.00 0.310 111.600
S6,K4,A3 45 8
D29,B17,E17,H18, 7 630.00 0.310 195.300
B11,E11,I10 90 8
G28,O27,H25,L19, 8 360.00 0.310 111.600
A16,A12,A8,G2 45 8
P15,M6 90 8 2 180.00 0.380 68.400
N13 180 8 1 180.00 0.380 68.400
H10,D3,M3 90 8 3 270.00 0.380 102.600
Q9,I4 90 8 2 180.00 0.310 55.800
0.3950617 0.617284 0.8888889 1.5802469 2.4691358 3.8580247
8 10 12 16 20 25 Total

512.00

758.52

796.44

455.11
296.30
237.04
341.33
227.56

192.00

170.67
75.85

371.20

329.96

288.71

187.73
82.49
42.67
133.33
88.89

49.60
44.09

77.16

44.09
27.02
27.02
40.53
22.04

1,856.53 - 362.67 3,166.81 533.33 - 5,919.35


Column cover 40 mm 0.75
L in footing 450 mm
Link hook 80 mm

No of Column size Main steel


Columns
Description Length Width Depth Nos Dia Nos Dia
A29,A23,F24,J21,P22,K
10,F7,H5,R1 9 6000 230 530 6 16 4 12
L26,C24,O20,J14,C7,
S6,K4,A3 8 6000 230 600 10 16 0 0
D29,B17,E17,H18,
B11,E11,I10 7 6000 230 600 12 16 0 0
G28,O27,H25,L19,
A16,A12,A8,G2 8 6000 230 450 6 16 4 12
P15,M6 2 6000 300 680 10 20 4 16
N13 1 6000 300 750 16 20 0 0
H10,D3,M3 3 6000 300 600 12 16 0 0
Q9,I4 2 6000 230 680 12 16 0 0

All longitudnal bars have been assumed to be equally spaced for ring cutting length calculation
Column cover will be provided to main steel; not to stirrups. Calcultions are done accordingly.
Rings Links
Nos in No of Cutting Per Total Cutting No of
a set Dia C/C Length rings length Column length Nos length links

2 8 90 6000 136 1.16 157.76 1419.84 1 0.31 68

2 8 90 6000 136 1.16 157.76 1262.08 1 0.31 68

2 8 90 6000 136 1.16 157.76 1104.32 2 0.31 136

2 8 90 6000 136 0.66 89.76 718.08 1 0.31 68


2 8 90 6000 136 1.16 157.76 315.52 2 0.38 136
2 8 90 6000 136 1.2 163.2 163.2 4 0.38 272
2 8 90 6000 136 1.25 170 510 2 0.38 136
2 8 90 6000 136 1.25 170 340 2 0.31 136

g length calculation
done accordingly.
nks
Cutting
length

21.08 189.72

21.08 168.64

42.16 295.12

21.08 168.64
51.68 103.36
103.36 103.36
51.68 155.04
42.16 84.32
Floor to Next Floor Beam Additional
Description Floor height height depth lengths
Foundation to Basement Slab top 5000 3150 600 450
Basement slab to HP slab 3150 3000 600 0
Basement slab to HP slab 3000 3000 600 0
3000 3000 600 0
3000 0 0 0

17150 450
Maximum
Maximum welding
Clear Quarter Max bar lapping (50d) Slab top (15d) (25 Lap Lap splice cutting
length length dia (25mm dia) clearance mm dia) staggering lengths for dowels
2550 637.5 16 800 150 300 300 950 2050
2400 600 16 800 150 300 300 950 2050
2400 600 16 800 150 300 300 950 2050
2400 600 16 800 150 300 300 950 2050
0 0 16 800 150 300 300 0 0

17600
Weld splice cutting Lap splice cutting Weld splice cutting
lengths for dowels lengths lengths
750 1350 6400 7500 6200 6800 1100 600
750 1350 3950 3950 3450 3450 1100 600
750 1350 3800 3800 3300 3300
750 1350 3800 3800 3300 3300
0 0 2850 1750 2550 1950

20800 20800 18800 18800


2000
Stirrup ho 10 d
Beam Cove 25 mm FALSE Beam stirrups continue in Column junction

Fixed length (DL) 150 mm

Beam section Supported (bearing) lengths


Sr. No Description Nos Width Depth Total End 1 End 2 Mid 1
length
B1 2 230 575 3280 230 230 0
B2 3395
B3a 7175
B4 3280
B5 3395
B6 1795
B7a 4845
B8 3395
B9a 7175
B10 3395
B11 1660
B12 5445
B13a-b-c 1 230 575 15675 1975 750 2100
B14a 6145
B15 4180
B16 3395
B17a 10060
B18a 9910
B19 8420
B20 2345

if end bearings have brackets; then bracket length to be added in hanging length of extra top bar.
Only two legged beam stirrups can be calculated; for other types i.e. 4 legged stirrups separate calculatio
In steel reinforcement binding wire required is 8 kg per MT.
Top steel Bottom steel Extra top Extra top
bearing) lengths (Through) (Through) Stirrups (End bearing 1) (End bearing 2)
Mid 2 Nos Dia Nos Dia Dia Spacing Nos Dia Length Nos Dia Length

0 3 10 3 16 8 150 3 12 600 3 12 600

0 3 10 3 16 8 200 3 16 3255 3 12 2200

ngth of extra top bar.


d stirrups separate calculations to be made.
Extra top Extra top Extra bottom total
(Mid 1) (Mid 2) length Cutting length (Top steel)
Nos Dia Length Nos Dia Length Nos Dia Length a b

4 20 2100 0.150 3.230


0.150 3.345
0.150 7.125
0.150 3.230
0.150 3.345
0.150 1.745
0.150 4.795
0.150 3.345
0.150 7.125
0.150 3.345
0.150 1.610
0.150 5.395
2 16 1980 0.150 16.125
0.150 6.095
0.150 4.130
0.150 3.345
0.150 10.010
0.150 9.860
0.150 8.370
0.150 2.295
0.000 0.000
0.000 0.000
Total clear Beam length
g length (Top steel) Cutting length (Bottom steel) length for stirrups
c a b c Cutting
length
0.150 3.530 0.150 3.230 0.150 3.530 2820 2820
0.150 3.645 0.150 3.345 0.150 3.645 3395 3395
0.150 7.425 0.150 7.125 0.150 7.425 7175 7175
0.150 3.530 0.150 3.230 0.150 3.530 3280 3280
0.150 3.645 0.150 3.345 0.150 3.645 3395 3395
0.150 2.045 0.150 1.745 0.150 2.045 1795 1795
0.150 5.095 0.150 4.795 0.150 5.095 4845 4845
0.150 3.645 0.150 3.345 0.150 3.645 3395 3395
0.150 7.425 0.150 7.125 0.150 7.425 7175 7175
0.150 3.645 0.150 3.345 0.150 3.645 3395 3395
0.150 1.910 0.150 1.610 0.150 1.910 1660 1660
0.150 5.695 0.150 5.395 0.150 5.695 5445 5445
0.150 16.425 0.150 16.425 0.150 16.725 10850 10850
0.150 6.395 0.150 6.095 0.150 6.395 6145 6145
0.150 4.430 0.150 4.130 0.150 4.430 4180 4180
0.150 3.645 0.150 3.345 0.150 3.645 3395 3395
0.150 10.310 0.150 10.010 0.150 10.310 10060 10060
0.150 10.160 0.150 9.860 0.150 10.160 9910 9910
0.150 8.670 0.150 8.370 0.150 8.670 8420 8420
0.150 2.595 0.150 2.295 0.150 2.595 2345 2345
0.000 0.000 0.000 0.000 0.000 0.000 0 0
0.000 0.000 0.000 0.000 0.000 0.000 0 0
Stirrup calculations Extra top (End bearing 1)
Nos a b c Total

20 0.180 0.525 0.080 1.522


0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
56 0.180 0.525 0.080 1.522
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
0 0.000 0.000 0.000 0
Column Cover 40 mm
Hook size 80 mm

Sr. No. Description Length Width Depth


1 3500 300 600
1 3500 300 750
Ring set
Max. Dia. No of bars // to Clear spacing
Cover Hook size Main steel Depth between bars Nos Dia
40 80 16 5 100.8 2 8
40 80 20 8 81.25 2 8
Ring Cutting
No of bars covered by
the ring
4 334.4 236 1.3008
6 442.25 156 1.1965
Assumptions

Foundation PCC to Tie beam top 1.8 m


Tie beam top to Basement slab top 3.2 m
Basement Slab top to Hollow plinth top 3m
Hollow plinth top to FF slab top 3m