Acxpnq27 S D 231 0
Acxpnq27 S D 231 0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
RC COLUMN SCHEDULE (L02 TO L03)
C1 2B1
A COLUMN NO. LENGTH WIDTH
UP C1, C37A, C72 300 1000
SW109
MB1
C4, C5, C8, C23, C68 400 1500
SW1 SW3 2B4 SW4 2B5 SW5 2B6 SW6 2B7 SW7 2B8 SW8 C9, C10, C11, C12, C13, C16, C17, C18, 750 650
G B C19, C20, C24, C25, C26, C27, C28,
2B2 SW2
2B3
2Bh
2B78
S-D-131A-0
2B76
S1 S1 S1 C31, C32, C33, C34, C35, C41, C42,
2Bh
2B9 2B10 250 PT 250 PT 2Bc 2B13 2B14 C43, C44, C45, C48, C49, C50, C51,
SW9 SW10 SW14
SLAB SLAB C C52, C56, C57, C58, C59, C60, C63,
SW115
SW107
SW11 SW12 SW13
2Be
2Be
2B12 C64, C65, C66, C67
2B11
250 PT C14, C15, C29, C30, C46, C47, C61, 1300 500
PTB4
PTB4
PTB1
PTB1
PTB1
250 PT N
SLAB 2Ba C62
SLAB
PTB1
PTB2
PTB1
PTB1
PTB1
250 PT 250 PT 250 PT 250 PT 250 PT 250 PT 250 PT C21, C53 AS PER PLAN
PTB1
PTB2
SLAB SLAB SLAB SLAB SLAB SLAB SLAB C36 AS PER PLAN
2Ba 2Ba 2Ba 2Ba C55 AS PER PLAN
2B15 2B17 2B18 2B19 2B22 2B25 2B26 2B27
SW15 SW16 2B16 SW17 SW18 SW19 SW20 SW21 SW22 SW23 SW24 SW25 SW26 SW27 SW28 2B28 SW29 2B29 SW30 2B30 SW31 2AB1
2AB2 C2
D NOTES:
UP UP SW32 2AB3
2B74
2B88
2B20 2B21 2B23 2B24
2AB27
C3
MB1
2Ba
SHEAR WALL SCHEDULE (L02 TO L03) 1. ALL DIMENSIONS ARE IN MM & LEVELS ARE IN METER.
599.03 m THE DIMENSIONS ARE TO BE READ AND NOT
2AB28
SW33 C4 C5 250 PT
600THK PT SW34 WALL NO. THICKNESS
2Ba SLAB SCALED/MEASURED FROM THE DRAWINGS.
2AB36
2B31 BAND SW1, SW2, SW3, SW4, SW5, SW6, SW7, SW8, SW9, 400 2. THE CONTRACTOR SHALL VERIFY ALL DIMENSIONS, DETAILS,
UP 2AB5
SW100 2Bb
2AB26
2B87
S1 SW10, SW11, SW12, SW13, SW14, SW16, SW17, SW18, SPECIFICATIONS & SITE CONDITIONS & SHALL REPORT ANY
2Be
2180 * 2180 *
S1 C6 ERROR, OMISSION AND/OR ANOMALY TO THE ARCHITECT
C7 SW19, SW20, SW21, SW22, SW23, SW24, SW25, SW26,
2B72
S1
2Be C14
2Ba 2Ba
C15
SW35
2ABf
E SW27, SW28, SW29, SW30, SW31, SW38, SW39, SW40, BEFORE COMMENCEMENT OF WORK.
C9 C10 C11 C12 C13 C16 C17 C18 C19 C20 C8 450 PT
2ABe
SW41, SW42, SW43, SW44, SW45, SW46, SW47, SW48, 3. GRADE OF CONCRETE FOR
2AB29
2AB35
2Be SLAB 250 PT
SW105
500 *
SLAB SW49, SW50, SW51, SW52, SW53, SW54, SW55, SW56, a. BEAMS/FLOOR SLAB - M45
B 2AB4
F c. SHEAR WALL/COLUMN - M60
2Be
2AB25
1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * S-D-231C-0 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * 1200 * SW65, SW68, SW70, SW71, SW72, SW73, SW74, SW75, 4. GRADE OF REINFORCEMENT SHALL BE Fe 500D CONFORMING
2AB17
2ABc
SW113
2Be S3
2B86
S-D-231C-0 SW76, SW77, SW78, SW79, SW80, SW81, SW82, SW83, TO IS:1786 WITH MINIMUM ELONGATION OF 14.5%.
4900 *
1170 * 1170 * 1170 * 1170 * 1170 * 1170 * 1170 * 1170 * 1170 * 1170 * C SW85, SW86, SW87, SW88, SW89, SW90, SW91, SW92, 5. ALL STRUCTURAL STEEL SHALL CONFORM TO IS-2062
SW93, SW94, SW95, SW96, SW97, SW98, SW100, 6. CLEAR COVER TO REINFORCEMENT FOR
2AB34
S-D-231C-0 450 PT
2Be
SW38 SLAB
S-D-231C-0
F1 SW108, SW109, SW110, SW111, SW112, SW113, SW114, b. BEAMS/SLABS/STAIRCASE 30mm
SW115, SW116, SW117, SW118, SW120, SW124 7.POUR STRIPS SHALL BE PROVIDED FOR MAX. POUR LENGTH OF
2AB24
599.03 m C22
1050 30M IN ANY DIRECTION IN CONSULTATION WITH PT VENDOR.
4725 *
6mm C21 2Be 600THK PT SW15, SW33, SW34, SW35, SW84 300
CHEQUERED BAND 8.ALL CUTOUTS/SLEEVES SHALL BE AS/RESPECTIVE SERVICES.
SW126
PLATE 597.03 m SW66, SW67, SW121, SW122 350 9. SETTING OUT EXTERNAL STAIRS/RAMPS SHALL BE AS PER
C30 C31 C32 C33 C34 C35 C23 2B34 SW99 325 RESPECTIVE ARCH & CIVIL DRAWINGS.
SW120
C24 C25 C26 C27 C28 C29
2B85
SW104
1050 *
G NOTE: SW119 IS NOT IN USE.
10.SETTING OUT OF SUNKS & CUTOUTS SHALL BE AS PER
SW112
RESPECTIVE ARCH/SERVICE DRAWINGS.
2AB23
RC BEAM SCHEDULE (L02) LEGEND:
4725 *
2ABa
2AB33
SW39 REFER DWG 200 WIDE NO TENDON ZONE (VERTICAL DIRECTION)
L NO :
BEAM NO. BREADTH DEPTH
2B70
3680 300 3960 300 S-D-331C-0 2960 800 450 PT ACXPNQ27-S- 2B1,2B32,2B33,2B65,2B66,2B89,2Be 300 600
2AB6 300 WIDE NO TENDON ZONE (HORIZONTAL DIRECTION)
565
2B84
2B89a
225 PT SLAB F-058B-0 2B2,2B8,2B58,2B64,2Bb,2Bc 400 600
SLAB S1 PTHB1
C38 2B3,2B4,2B5,2B6,2B7,2B9,2B10,2B11,2B1 800 600 500 WIDE NO TENDON ZONE (HORIZONTAL DIRECTION)
SW125
450 210
450 160
SW40 SW41 SW42 SW43 SW44 SW45 PTHB1 SW46 PTHB1 SW47 SW48 SW49 SW50 SW51 SW52 2,2B13,2B14,2B16,2B17,2B18,2B19,2B20,
C36 2B35 C37A C37 PTHB1 H 2B21,2B23,2B24,2B25,2B26,2B27,2B28,2 INDICATES PIPE SLEEVE IN RC/PT SLAB
B38,2B39,2B40,2B41,2B42,2B43,2B45,2B
SW103
2AB16
PTB3
PTB1
PTB1
PTB1
PTB1
PTB1
PTB1
PTB3
PTB1
PTB1
PTB1
PTB1
PTB1
PTB1
225 PT 225 PT 225 PT 225 PT 225 PT 225 PT 225 PT 225 PT 225 PT 225 PT 225 PT
PTHB1 PTHB1 46,2B47,2B48,2B49,2B50,2B52,2B53,2B54 50MM SUNK
SLAB SLAB SLAB SLAB SLAB SLAB SLAB SLAB SLAB SLAB SLAB
SW53 SW54 SW55 SW56 SW57 SW58 SW59 SW60 SW61 SW62 SW63 SW64 SW65 ,2B55,2B56,2B57,2B59,2B60,2B61,2B62,2
2B83
H1 B63,2B67,2B68,2B69,2B70,2B71,2B72,2B WALL/COLUMN STOPS AT FLOOR LEVEL
2AB32
79,2B80,2B81,2B82,2B83
SW118
250 PT 250 PT
SLAB SLAB
250 PT 2B15,2B36,2Bd 300 700 * INDICATES DIMENSIONS PROVIDED FOR NO-TENDON ZONE
2B69
250 PT SLAB 275 PT 2B22,2B44 1200 600 (CENTER) SHALL BE VERIFIED WITH RESPECT TO ARCH LAYOUT
SLAB SLAB
PTB3
2B30,2B34,2B73,2B74,2B84,2B85,2B86,2 400 700 FOR RACK & HAC FRAME.
B87,2B88
4675 *
2AB15
2B82
2B35,2B90 300 650
SW111
C39 C40
SW102
6mm C41 C42 C43 C44 C45 C46 C47 C48 C49 C50 C51 C52 2B51 400 1000 FOR ALL CHARJJA & LINTEL REFER RESPECTIVE ARCH
SW124
CHEQUERED DRAWING.
1050 *
SW117
C53 2Be CONTRACTOR SHALL COORDINATE WITH PT VENDOR FOR ANCHORS,
2Bi 200 450
D 599.03 m POUR STRIPS, STRESSING AND OTHER CONSTRUCTION DETAILS.
2ABc 2AB14
2Bj 150 600
5025 *
2AB31
S-D-231C-0 2ABc 200 THK 2Bk 200 700
2B81
SLAB AT ALL FLOORS SHALL BE FINISHED TO ENSURE FLOOR
2B68
PARDI
S1 FLATNESS FF=35 AND FLOOR LEVELNESS FL=25 AS PER ACI 117 AND
K RC COLUMN SCHEDULE (L02 TO L03)-ADMIN
ACI 302(LATEST EDITION). THIS SHALL BE VERIFIED BY THE
2Be
SW123
2ABc SW66 2ABa
S-D-331C-0
J1
SW110
2AB22
C55 450 PT
2B80
2Ba 2Ba C2, C6 300 1200
SW101
K
2Bf
SW67
C7, C22, C38, C39, C40, C54 700 700
C63 C64 C65 C66 C67 2ABa
2ABe
2B67
2AB12
2Bd 2Ba 2Ba
S1 2ABe 597.03 m
E PD 600 600
2Be
2AB30
SW99
S1 S1 2ABe
S-D-231C-0 599.03 m 2Be
2B79
SW68 2B37 250 PT
PTB5
2Ba 250 PT 225 PT SLAB
C68 SLAB
SW116
2B36 SLAB
RC BEAM SCHEDULE (L02) ADMIN BLOCK
2B66
2Be
J
2B73
UP 2B38 2B39 2B40 2B41 2B42 2B43 2B44 2B45 2B46 2B47 2B48 2B49 2B50
SW71 SW72 SW73 SW74 SW75 SW76 SW77 SW78 SW79 SW80 SW81 SW82 2AB8 SW69 2AB9 C69 2AB10 C70 2AB11 C71 S-D-231C-0 BEAM NO. BREADTH DEPTH
SW70 SW83 2B51 2AB1,2AB2,2AB8,2AB9,2AB10,2AB11,2AB 400 700
SW84 12,2AB14,2AB15,2AB16,2AB17,2AB23,2A 0 22-Dec-2023 ISSUED FOR CONSTRUCTION (IFC)
2Ba 2Ba I 2Ba 2Ba B24,2AB25,2AB30,2AB31,2AB32,2AB33,2 REV DATE DESCRIPTION
G L
PTB2
PTB1
PTB1
PTB1
PTB2
PTB1
PTB1
2Be PTB1
250 PT
PTB4
PTB4
SW114
S-D-231C-0
2B52 2B53 2B54 2B55 2B56 2B57 2AB22,2AB27 300 1200
2Be
SW87 S1 SW88
SW85 SW86 SW89 SW90
M 2AB28 300 1600 11th Floor, Aravalli Adani Corporate House, Shantigram road,
2Bc 2ABa 400 600 Shantigram, Ahmedabad, Gujarat - 382 421
2B77
S1 S1
2B75
2Bh
S1 www.adaniconnex.com
2Bh
U.O.N RC SLAB SHALL BE S1. The information contained in this document produced by AECOM is solely for the use of the Client identified on the cover sheet for the
purpose for which it has been prepared and AECOM undertakes no duty to or accepts any responsibility to any third party who may rely upon
RC SLAB SCHEDULE this document. All rights reserved. No section or element of this document may be removed from this document, reproduced, electronically
stored or transmitted in any form without the written permission of AECOM.
ACXPNQ27-S-D-231-0 0
THE DRAWING IS INTENDED TO PRINT IN COLOUR. DRAWN BY DESIGNED BY CHECKED BY APPROVED BY
RN HS VSP MJ
FOR BEAMS AROUND CUTOUTS, PARAPETS, EQUIPMENT PEDESTALS SCALE @ A1 DATE OF FIRST ISSUE PROJECT NO. AECOM PROJECT NO.
REFER TO THE RESPECTIVE PART PLANS/DRAWINGS.
As indicated 27-Oct-2023 ACXPNQ27 60716918