Finna Aegen Feasibility Design Report.9
Finna Aegen Feasibility Design Report.9
ENGINEERING REPORT
FINAL
CLIENT CONSULTANT
OROMIA IRRIGATION & PASTORALIST ENGINEERING CORPORATION OF
DEVELOPMENT BUREAU OROMIA
P. O. Box P.O.Box. 870/1250
Tel +251 Tel +251 11 4392162/2470
Email: Fax:+251 11 439 2008
Finfinne/Addis Ababa, Ethiopia Email: [email protected]
Finfinne/Addis Ababa, Ethiopia
July ,2022
Oromia Irrigation & Pastoralist Development Bureau(OIPDB) Finna Aegen Project Engineering report
Table of Contents
TABLE OF CONTENTS ...............................................................................................................................................I
LIST OF TABLE ...................................................................................................................................................V
LIST OF FIGURE ................................................................................................................................................. VI
1. INTRODUCTION........................................................................................................................................1
1.1 BACKGROUND..............................................................................................................................................1
1.2 OBJECTIVES OF THE STUDY ..............................................................................................................................2
1.3 LOCATION OF THE PROJECT ..............................................................................................................................2
1.4 DESCRIPTION OF WORKS...........................................................................................................................3
1.4.1 GENERAL DESCRIPTION ................................................................................................................................3
6.6.3 PROCEDURES FOR SEISMIC DESIGN OF INTAKE TOWERS ...................... ERROR! BOOKMARK NOT DEFINED.
REFERENCES ................................................................................................................................................... 66
LIST OF TABLE
Table 1 Annual peak Rainfall data................................................................................................................. 6
Table 2 Design Rainfall for different return period ....................................................................................... 7
Table 3. Aegen Micro- Reservoir Flood Routing Results for Various Special Events ............................... 11
Table 4: Summary of engineering properties of foundation materials of Aegen Dam site. ........................ 17
Table 5: Summary of construction materials of Aegen Dam site. ............................................................... 17
Table 6: Summary of construction materials source of distance materials. ................................................. 20
Table 7 Summary of Investigation and Assumed of Construction Materials .............................................. 25
Table 8 Recommended factor of safety under different loading conditions ................................................ 35
Table 9 Factor of Safety Analysis Result Summary .................................................................................... 38
Table 10:Aegen Micro- Reservoir Flood Routing Results for Various Special Events .............................. 40
Table 11: Shape of Downstream Quadrant of Ogee Profile ........................................................................ 44
Table 12: Shape of Upstream Quadrant of Ogee Profile ............................................................................. 45
Table 13: Water surface profile computations ............................................................................................. 45
Table 14: Summery computation of loss coefficients and head losses ........................................................ 54
Table 15. Material Properties for Design ..................................................................................................... 59
Table 16: Bill of Quantity ............................................................................................................................ 67
LIST OF FIGURE
Figure 1 Locations Map of the Project Site ................................................................................................... 3
Figure 2: Geological Map of the project area and its surroundings. ............................................................ 14
Figure 3: Seismic Zoning Map of the Aegen Site........................................................................................ 15
Figure 4 Aegen Dam Axis Cross Section .......................................................................................... 18
Figure 5 Aegen Dam Spillway Cross Section ............................................................................................ 19
Figure 6 Aegen Intake Cross Section ......................................................................................................... 19
Figure 7 Graph showing relative wave run-up ............................................................................................ 29
Figure 8: Cross Section of the Dam ............................................................................................................. 33
Figure 9: Results of the steady-state seepage analysis................................................................................. 36
Figure 10: Results of the rapid drawdown seepage analysis ....................................................................... 36
Figure 11: Results of D/s Slope Stability Analysis for Steady-state Seepage (long term) Loading Condition
...................................................................................................................................................................... 37
Figure 12: Results of U/s Slope Stability Analysis for Rapid Drawdown Loading Condition ................... 37
Figure 13: Results of D/s Slope Stability Analysis for Short Term Loading (During Construction) .......... 37
Figure 14: Results of U/s Slope Stability Analysis for Short Term Loading (During Construction) .......... 38
Figure 15: Intake tower and Access Bridge Plan and Longitudinal Section ............................................... 57
Figure 16. Axial force and bending moment interaction diagram ............................................................... 58
Figure 17: Tower Cross Section .................................................................................................................. 60
Region --------------------------------------Oromia
Zone------------------------------------------Jimma
District----------------------------------------- Xollay Botor
Genda (kebele) ---------------------------------Kamiso Golla
Geographic location 37N (UTM, ADINDAN)
B) Hydrology
Catchment area up to----------------------------17.70sq km
the proposed Dam
Average Annual Rainfall-----------------------1494 mm
C) Command Area ---------------------------------------400ha
D) Dam
E) Intake Tower
Intake pipe diameter----------------------------------0.50m
Intake Distance from Left abutment----------------137.0m
Intake Gate by ----------------------------------------slide gate
Intake pipe inverted Level --------------------------1608.0m
F) Spillway (Un-gated)
Location ------------------------------------------Right side of Dam (E-314790.19, N-934986.40)
Type of Spillway---------------------------------Un-gated Ogee type
Design flood (PMF)------------------------------53.7 m3/sec
Crest of ogee---------------------------------------EL 1628.50m
Spillway outflow (routed Discharge) -----------49 m3/s
Crest level of Non over flow
Clear width of spillway crest----------------------20.0 m
Maximum flood lift over crest---------------------1.0 m
G) Reservoir
Maximum Water Level (MWL)--------------------EL 1629.50 m
Full Reservoir Level (FRL)-------------------------EL 1628.50 m
Reservoir Area @ MWL----------------------------20.05ha
H) Minimum Draw down Level
Minimum Draw Down Level (MDDL)------------EL 1610.0 m
River Bed Level--------------------------------------EL 1597. 0 m
I) Reservoir Capacity
a. Full Reservoir Level (FRL)----------------------2.19 Mm3
b. Minimum Draw down Level (MDDL)---------0.14 Mm3
c. Live storage-----------------------------------------2.05 Mm3
Source of Irrigation water------------------------------------Aegen river (Flood)
LIST OF ABBREVIATION
DEM Digital Elevation Model
D/s Downstream
ECO Engineering Corporation of Oromia
El Elevation
Eth Birr Ethiopia Birr (currently approx.
ETo Reference Evapotranspiration
FRL Full Reservoir Level
GIS Geographic Information system
GPS Geographical Position System
ha hectare
km Kilometer
km2 Square Kilometer
m meter
m.a.s.l. Meters above sea level
m3 Cubic meter
m3/s meter cube per second
MDDL Minimum Drawdown Level
MCM Million Cubic Meter
MWL Maximum Water Level
MSIP Medium Scale Irrigation Project
OBANR Oromia Bureau of Agriculture and Natural Resource
OIPDB Oromia Irrigation and Pastoralist Development Bureau
UTM Universal Transverse Mercator
U/s Upstream
EXECUTIVE SUMMARY
Aegen Micro Dam irrigation project is located in Oromia regional state, Jimma zone, Xollay Botor
district, Aegen Kebele. It is at 245km from Finfinne of which 151km asphalt, 62km all weathered road,
and 158km from Zonal town Jimma.
The beneficiaries of the project are residents of Kamiso Golla Kebele which includes at least 525
households benefit from this project, so that equitable use of land and water resources could be established
at the site under consideration.
The component of this medium-scale irrigation project includes the Dam, Intake Tower, and Spillway and
other related infrastructures.
The total project cost is 241,072,573.98 birr including 15%VAT. The detail is explained in the bill of
quantity of the project.
1. INTRODUCTION
1.1 Background
In Ethiopia, as well in Oromia under the prevalent rain-fed agricultural production system, the
progressive degradation of the natural resource base, especially in highly vulnerable areas of the
lowlands coupled with climate variability have aggravated the incidence of poverty and food
insecurity. The major source of growth for the country as well for the region is still conceived to be
the agriculture sector. Hence, this sector has to be insulated from drought shocks through enhanced
utilization of the water resource potential of the country through development of irrigation, water
harvesting, and on-farm diversification coupled with strengthened linkages between agriculture and
industry (agro-industry), thereby creating a demand for agricultural output. In line with the above
premises, efforts have been made by the government and NOGs to improve the situation in the region
in areas of irrigation development, domestic water supply provision, watershed management, etc.
In order to alleviate the situation of food insecurity in lowland areas of the region that resulted from
shortage of Rainfall & recurrent drought, the region has aggressively switch development endeavors
towards effective and efficient use of the existing natural and human resources. A development
strategy that gears on the use of water and land resource endowments. As a result, development of
different scale irrigation schemes is believed to play a significant role not only in solving the current
food insecurity but also in enhancing the economic development of the region as well the country
through import substitution especially wheat, paving the way for Agroindustry development, earning
of more foreign currency and creation of employment opportunities for citizens.
Accordingly, the regional government of Oromia has planned a program to implement through
strategic approach of developing more than two hundred thirty small and medium dam projects for
the upcoming four years period. For implementing these projects hereafter known as Finna (meaning
‘mine’ in Afan Oromo) the regional government has restructured autonomous Irrigation and
pastoralist bureau and allocated great deal of budget for construction and undertaking feasibility and
detailed study and design services. As an output to this enormous investment, the regional
government determined in alleviation of food insecurity situation due to rainfall shortage driven
drought and its impact on crop production and livestock husbandry in lowland areas of the region.
Moreover, those highland areas of the region have been also considered in the program to maximize
their productivity in space and time by utilizing the stored water. For implementing the program, the
previous Bureau of Agriculture and Natural Resources and the current Oromia Irrigation and
Pastoralist Development Bureau (OIPDB) took the leading role as client. From the stage of
comprehending the program and selection of potential areas through ensuring fair and resource-based
distribution in the region, Engineering Corporation of Oromia (ECO) has played significant
contribution. In line with this, the regional government has given direction and awarded ECO to
undertake feasibility study and detail design of Finna projects encompassed within the program.
As part and parcel of the current budget year program, feasibility study and detail design of Finna
Aegen project has been underway with the objective of implementing 400ha irrigation development at
Kamiso Golla kebele of Xollay Botor district located in Jimma Zone. Thus; this first draft feasibility
and detail design report has been prepared with all available secondary data sources of previous
nearby similar projects and masterplan studies and data acquiring technologies have been assessed &
incorporated. Accordingly recent digital elevation models, global land use and cover of 2020 datasets,
worldwide forecasted Precipitation datasets like Climate Hazards Group Infra-Red Precipitation with
Station (CHIRPS) have been utilized for analysis. Moreover, national and regional geologic,
geotechnical and geo physical data including recently conducted Oromia Irrigation potential study
outputs have been utilized which could be further verified and rectified with actual data while
submitting upcoming subsequent reports.
The main objective of the Dam work is to pond sufficient water during the period of high flow and to
use for Agriculture.
The proposed project area, Aegen micro–Dam Project, is situated in Oromia regional State, Jimma
zone, Xollay Botor woreda, The Aegen dam site center is located at geographic location of
315364.6m East and 935131.2m North in UTM projection elevation of the center of the river at an
elevation of 1584m amsl. The distance from the capital city of the region, Finfinne to the Dam site is
about 245 km and from zonal capital, Jimma town, is about 158 km. The woreda town, called Xollay
town, is located at about 22 km. The Dam site is accessed via Asphalt and all weathered road
The principal components of the Works covered by this 1st draft feasibility study and detail design
document are those stated hereunder but further components will be included during the detailed
design.
Main Dam (Zoned Earth fill Dam with Horizontal Filter drains and Rock toe);
Spillway (incorporating Approach Channel, Ogee Spillway, Chute and Stilling basin) and;
Outlet works which includes Irrigation intakes, conduits and outlets control structures
Dam Body
The main dam body is designed with zoned for there is a limited embankment material, during in
such cases it was a common practice, to design a dam with different material without affecting the
intended objectives, that is storage of irrigation water which might be allows seepage with tolerable
limit. As it was indicated in the Geological investigation there is a limited source of sand and core
material. Therefore, the design of zoned embankment needs horizontal filter drains with rock toe at
the end. Accordingly, for safe disposal of seepage water with protection of piping and internal
erosion, based on the base material, inclined chimney and Horizontal drain with filter was
recommended and designed in order to protect migration of soil to drain seepage water and smooth
transition from fine to coarse textured drain materials. Excavation is necessary to remove some areas
of alluvial deposit on the left and right bank of the valley having weak shear strength
Spillway
Ogee spillway with Chute control section and energy dissipater is designed to discharge a maximum
of 189.81 m3/s corresponding to 500 years return period routed outflow. However, the dam crest
level is fixed not to be over topped with this routed outflow. The total crest length of the spillway is
40m. The crest level (Normal Reservoir Pool level) is at 1608.0m and the maximum water level
corresponding to 500 years routed outflow is 1609.66m i.e., with flood surcharge head of 1.66m. The
structure comprises control section, chute and terminal structure. The spilled water leaving the
terminal structure will join the natural Finna Aegen River.
Diversion Arrangements
The construction of Finna Aegen Dam could take two or three years to complete. The construction
shall take place in the dry seasons. Therefore, it is not possible to completely block the river flow
rather creating a provision for safe passage of the river flow during the rainy and dry season becomes
essential.
The followings are considered the main components for the diversion system during construction of
the dam.
Irrigation outlet
The main purpose of the Finna Aegen Dam project is for irrigation. It is planned to develop the
command area estimated to be around 400 ha downstream of the dam. Therefore, during dry months
of the year, regulated water will be released as per the downstream demand. Accordingly, compatible
intake structure has been provided for this purpose.
2. HYDROLOGIC STUDY
2.1 Hydrological and Water Resources potential
The project is found the western part of Northern upstream end of Gibe River Basin, Upper Gibe Sub
Basin. This project site is located at Botor Tolay Woreda, nearby the main Gibe River. The catchment
area and dam site physiographic characteristic shows that the longitudinal profile elevation difference
from dam outlet to the longest remote catchment point is about 468m within the longitudinal length of
9.6km. Most of the topography of the catchment area fall within a moderate elevation range. The
selected cross-sectional width of the dam site is appropriate for the needed dam height.
The Aegen micro-dam head work site is located on small stream of Aegen River before confluence
with other small streams. The Aegen River up to the selected headwork site has a catchment area of
17.7 km2.
The main surface water source for the demand of this area is Aegen Stream, which is a tributary of
Gibe River Basin.
Daily flow data at dam site is necessary for design of dam and its appurtenant structures to estimate
maximum design flood for a given return periods, dependable flow to estimate the reservoir capacity
and low flow to estimate the base flow and decide environmental flow for the downstream
environment. The Aegen Micro-dam site is un-gauged site.
Daily flow data at dam site is necessary for design of dam and its appurtenant structures to estimate
maximum design flood for a given return periods, dependable flow to estimate the reservoir capacity
and low flow to estimate the base flow and decide environmental flow for the downstream
environment.
There is no gauging station on Aegen River and no recorded flow data obtained. Therefore, rainfall
runoff relationship method used to estimate the flow of the catchment.
Design rainfall was analyzed after the peak rainfall fittest curve was determined and based on
that frequency of the rainfall for different return period was derived as follows: The derived
Engineering Corporation of Oromia (ECO)
6
Oromia Irrigation & Pastoralist Development Bureau (OIPDB) Finna Aegen Engineering Design Report
design rainfall frequency is a bit different from the original result as given below.
Return
Period
(yrs) P2 P5 P10 P20 P25 P50 P100 P200 P500 P1000
Design 50.0 55.17 59.1 60.2 63.2 65.5 67.3 69.2 70.3
RF 41.2
Reservoir area silt accumulation volume at different years of services and corresponding elevation.
The Aegen dam reservoir bed level at dam axis is 1597 m above sea level. The estimated sediment
storage (dead storage) of the reservoir was 0.14 MCM using 50yrs service. For reservoir dead storage
of 0.149MCM, the new reservoir elevation (new zero level) was at 1610m with an increment height
of 13m and with new surface area of 4.9ha.
The required reservoir dead storage depends on the design life of the reservoir. Assuming a design
life of about 50 years and trap efficiency ranges from 93 to 100%, the accumulated sediment in the
reservoir will be 0.149 million m3. As stated in the hydrology report, the sediment will be deposited
throughout the reservoir water and the new zero level estimated at 1610m amsl. Hence, the total
reservoir storage is 2.17 MMC at FSL of 1628.50 masl and among this 0.149 MMC occupied by dead
storage. The total live storage is 2.03 MMC. The design life for dead storage can be extended by
either reducing the sediment reaching the reservoir through watershed management or by flushing or
removing the deposited sediments from the reservoir.
The hydrograph of a flood entering a reservoir will change in shape as it emerging out from the
reservoir. This is due to volume of water stored in reservoir temporarily. The peak of the hydrograph
will be reduced, time to peak will be delayed and base of the hydrograph will be increased. The extent
up to which an inflow hydrograph will be modified in the reservoir will be computed by the process is
known as reservoir routing.
Reservoir flood routing was carried out to design the dimension of the spillway. The design flood of
the spillway flooding was carried out based on the criteria of selecting return periods.
From Reservoir Capacity curve, the elevation of the reservoir above the spillway and its
corresponding storage is known, Spillway capacity (Q) versus Spillway head (H) is determined from
the spillway type (Here, uncontrolled Ogee spillway is an option) and inflow hydrograph is
H is total head above Normal Operation Level (NOL), including velocity of approach head in the
spillway;
Reservoir capacity relation with elevation (Storage vs Elevation), and calculated spillway
Capacity (Q vs H) is determined. For instance, for spillway length of 20m and crest level of
1631m.
Table 4: Spillway gross Length and design head relation
L 10 15 20 25 30
V V (1000
Elev H Q Q Q Q Q 2S/t + Q
(MMC) m3)
1620.0 0.00 0.0 0.0 0.0 0.0 0.0 2.77 2768.0 3075.56
1620.5 0.50 7.2 10.9 14.5 18.1 21.7 2.90 2899.7 3240.01
1620.8 0.75 13.3 20.0 26.6 33.3 39.9 2.97 2965.6 3328.34
1621.0 0.97 19.6 29.5 39.3 49.1 58.9 3.02 3024.0 3409.14
1621.1 1.11 23.8 35.7 47.62 59.5 71.4 3.06 3059.1 3458.48
1621.3 1.30 30.3 45.5 60.6 75.8 90.9 3.11 3109.9 3531.23
1621.6 1.60 41.57 62.4 83.1 103.9 124.70 3.19 3190.0 3648.32
1622.0 2.00 58.0 87.0 116.0 145.0 173.9 3.29 3294.8 3805.85
1622.3 2.25 69.2 103.8 138.4 173.0 207.6 3.36 3360.7 3907.02
1622.5 2.50 81.0 121.6 162.1 202.6 243.1 3.43 3426.5 4009.81
1622.8 2.75 93.5 140.2 187.0 233.7 280.5 3.49 3492.4 4114.11
1623.0 3.00 106.5 159.8 213.0 266.3 319.6 3.56 3558.2 4219.86
1623.3 3.25 120.1 180.2 240.2 300.3 360.3 3.62 3624.1 4327.00
1623.5 3.50 134.2 201.3 268.5 335.6 402.7 3.69 3689.9 4435.47
1624.0 4.00 164.0 246.0 328.0 410.0 492.0 3.82 3821.6 4656.22
Table 7: Inflow outflow spillway hydrological routing
Q
Time (hr.) Inflow 2S1/t -Q1 2S2/t + Q2
(Outflow)
0.00 0.0 3075.56 0
0.10 1.6 3076.81 3077.17 0.18
0.19 5.4 3081.98 3083.79 0.91
0.29 10.2 3092.70 3097.55 2.42
0.39 16.6 3109.86 3119.55 4.85
0.48 25.2 3134.96 3151.74 8.39
0.58 35.4 3169.17 3195.64 13.23
Table 1: Routed inflow and outflow and Gross spillway length against Design head
Table 3. Aegen Micro- Reservoir Flood Routing Results for Various Special Events
Ashangi formation are the earliest Tertiary volcanic rocks in north Ethiopia, hence they are in the
lowest position. These formations are weathered, partially eroded and have a sub-horizontal
stratification, particularly at the lower part. These dark porphyritic basalts are separated from the
Mesozoic formations below it by basal conglomerates. The basalts hold phenocrysts that developed
before the magma reached the earth surface. These basalts are weathered, partially eroded and have a
sub-horizontal stratification, particularly at the lower part.
These volcanic rocks formed through melting of the earth mantle. After magma generation, lava
flowed out over the surface, in successive flows.
Flood basalt commonly directly overlying the crystalline basement. The geology of western Ethiopia
is characterized by a variety of rock types ranging in age from Precambrian to Quaternary. The
Precambrian basement of western Ethiopia, extending northwards from 60N for about 650 kilometers
is the largest Precambrian block in Ethiopia. The Precambrian rocks of western Ethiopia studied at
different scales (UNDP, 1972; de Wit, 1977; Kazmin, 1978; Davidson, 1983; Abraham, 1989; Tefera,
1990; Tefera and Berhe, 1987; Ayalew and Moore, 1989; Alemu and Abebe, 2000; Solomon and
Mulugeta, 2000; Getahun, 2002). The low-grade metavolcano-sedimentary and associated intrusive
rocks exposed remarkably persistent and can be traced for the entire length of the Precambrian of
western Ethiopia.
Geochronological investigations from plutonic rocks suggest that the age of the low-grade rocks
range from ~830 to ~540 Ma (Ayalew et al., 1990). The Cenozoic volcanics overlie unconformably
either on Precambrian rocks or Paleozoic–Mesozoic sediments. At places in southwestern Ethiopia,
they found overlying the Precambrian rocks are marked by residual and transported sandstone and
conglomerates (Davidson, 1983). The Cenozoic Ethiopian volcanic province can be divided into two
main series. These are:
(i) the Plateau (trap) volcanic, and
(ii) (ii) the Rift volcanic
The plateau volcanic represented 300,000 Km3 of mid Tertiary generally fissure-fed basaltic lavas.
The plateau volcanic divided into west and southeast plateau, which are bounded in either side by the
Main Ethiopian Rift and Afar Rift. These are; the Jimma Volcanic and the Mekonnen Basalts.
Geochemical (major and trace element and Sr, Nd and Pb isotope) data from the southwestern
Ethiopia volcanic (Ayalew et al., 1999), show that they are derived from a mantle source that is
enriched in U and Th relative to Pb without an associated increase in Rb/Sr. Their trace element and
isotopic signatures are compatible with derivation from isotopically heterogeneous (Nd and Pb)
mantle sources with OIB-like characteristics that probably contains ancient subducted sediments.
Moreover, these authors suggest that the lavas from southwestern Ethiopia show that crustal
contamination had little or no role in the evolution of these lavas.
3.2.3.1 Basalt
These volcanic rock units have wide range weathering degree from fresh or faintly weathered
to moderately weathered and decomposed to soil of silty clay nature. These rocks have
moderate permeability and moderately jointed and fragmented at some spots at their fresh
and moderately weathered condition. These geological units have aphanitic and
amygdaloidal texture.
3.3 Seismicity
The site is found at the boundary of the seismically inactive metamorphic craton and the margin of
the south Ethiopian rift. Plotting the dam axis center on the recent seismic zoning map of Ethiopia
reveled it is characterized by Potential Ground Acceleration of 0.0 - 0.025m2/s, and this value can be
utilized for the design purpose.
Besides, even though the site is located in a zone with relatively low level of seismicity, it may be
subjected to induced seismicity after the water load. This needs monitoring with appropriate
instruments before and after the Dam is finalized and filled with water.
Alluvial deposits occupy intermittent stream bed having a wide ranging from the top and it is
located close to the mouth of the river where it defines alluvial fan about 500 meters
downstream of the site. It mainly comprises grey silty soil and Clay silt in various
proportions and some weathered rock fragments, pebbles and cobbles and the color varies
The thickness of the deposit was estimated to be about fifty Cents, but it can be considerably
thicker since the river channel can be deeply eroded.
Such a unit can be described as: Medium to High plastic, silty soil to silty Clayey of
intermediate relative density. Estimated engineering & index properties of such material
show; cohesion (c) of 13Kpa, friction angle (Φ) 0f 240, plasticity index (PI) of 10, unit
weight (Ɣ) of 20kN/m3, and hydraulic conductivity (k) of 1*10-5.
This unit comprises residual and transported soils occupying flat lands and gently sloping
topography represented by sand, silt, clay, and gravel in various proportions. The color varies
mainly from black, through grey brown sometimes to grayish. The material is found on gentle
slopes areas along the proposed dam axis and areas covered by alluvial deposits downstream
of the dam axis.
Such a unit can be described as: Medium to slightly high plastic, clayey SILT of soft to
medium strength and its depth of thickness around 5m. Estimated engineering & index
properties of such material show; cohesion (c) of 40Kpa, friction angle (Φ) of 250, plasticity
index (PI) of 18, unit weight (Ɣ) of 19kN/m3, and hydraulic conductivity (k) of 10-5.
The bedrock unit is believed to be encountered at shallow depth on the dam abutments and
planes outside the stream course. The bedrock lithology is the black to light-grey and mainly
bedded basalt and rock fragments deposits. It is characterized by textural heterogeneity and is
found as aphanitic, vesicular and pyroclastic variety. The vesicular basalt, the predominant
variety, is dark grey to light grey-grey, fine to medium grained, commonly medium weathered
looking. At places the vesicles are filled with secondary minerals such as quartz and calcite
giving the rock an amygdaloidal appearance.
Analysis of the Hoek Brown Classification rock behavior with rock-lab software using
unit weight of 26kN/m3 for basalt (scoria and rock fragment) and assumed intact UCS
of revealed rock mass properties as shown here; cohesion =2, 075MPa, internal friction
angle of 17.89degree, UCS of 0.579MPa, Bearing capacity of 5.701MPa and modulus
of deformation of 7252MPa.
A) Foundation Material Engineering Property
Property
Foundation Friction Unit
Geotechnica MPa Angle(Ø E weight(Ɣ Remark
thicknes K, UCS,
l Parameters PI Cohes ) BC )
s (m) cm/s MPa
ive (c)
(Degree) MPa kN/m3
Based on
Layer 1 the
0.5 0.01 10 13kpa 24 - - - 20
(Top Soil) Regional
Geological
Layer 2 (Silty Condition.
4 18 40kPa 25 32kpa - - 19
Clay)
Need to be
verified
Layer-3 through
(Basaltic) 2.075
>5 0.01 - 17.89 5.701 0.579 7252 26 test pitting
Mekonin MPa
basslt & other
exploration
B. Construction Material
Table 5: Summary of construction materials of Aegen Dam site.
Property
Construction Internal
Hydraulic Water
Material Type Cohesion Friction Unit weight
conductivity Absorption
(C) KPa Angle Ø (Ɣ) kN/m3
(K), m/s (%)
(Degree)
Rock Fill 0.01 0 35 22 1
Filter Material
1*10-4 0 38 18 -
(Sand)
The selection for material source was made by referring to the geological map, and using
judgment from previous experience of the site. This work also need to be verified during the
construction period as the thickness and volume of material can actually vary, and better quality
and volume of material like sand can be found at closer distance.
Accordingly, in the earth dam design the dam height is fixed based on the physical storage
capacity of the dam site. Although storage requirement to satisfy the irrigation demand and
other losses as computed in the water balance computation of the hydrology report is higher
than the actual physical capacity the reservoir can impound 2.728 M m3 at a height of 24.0m
and at elevation of 1608.0 masl. The dam section is determined based on the nature of the
available embankment materials and the nature of the foundation.
The spillway is designed for a flood of 189.8 m3/sec with crest length of 40.0 m and an
Overflow Ogee weir. The outlet is designed for 0.55 m3/sec to satisfy the maximum irrigation
demand to irrigate 450ha. Both structures are equipped with all necessary components.
The criteria satisfied in the design of the dam are for no overtopping, no seepage failure, no
structural failure, Proper slope protection, proper drainage, and to have safe and economical
dam section.
A 370m long straight dam axis has been selected between (E 314873.23 N 934986.4) Left abutment
and (E 314790.19 N 934986.4) right abutment. Consideration was given to the most economical
alignment fitting the topography while considering geological constraints.
At this stage of study, the following criteria are met:
- The dam is safe against overtopping in the event of occurrence of the design flood
- The slopes of the dam are stable in all reservoir operations and during earthquake
- No foundation failure due to the stresses caused by the embankment
- Safe removal of seepage water is ensured and the amount of seepage loss is controlled.
The Aegen micro dam is located in seismically less active area. However, taking into account the
expected long-life period of the dam and not ruling out the chance of the dam site being hit by a
damaging earthquake which may originate in the Ethiopian rift valley, adequate seismic design
considerations has been taken. Based on the seismic hazard map of Ethiopia prepared by the Institute
of Geophysical Observatory at Addis Ababa University with a return period of 300 years (return
period for Design Base Earthquake – DBE – of dams is generally 300 to 400 years), the nearest
contour to the Aegen dam site is with a maximum peak ground acceleration of 0.1g
Seismic Loading
Pseudo-static approach has been adopted to analyse the behaviour of dam under dynamic loading
caused by a strong earthquake. The dynamic loading is accounted for by using a seismic coefficient.
The design value of horizontal seismic coefficient αh is computed by the following expression:
Α = β I αo
Where β = design response factors a coefficient depending upon the soil foundation
I = a factor depending upon the importance of the structure, and
αo = basic horizontal seismic coefficient applicable for that area.
EBCS specifies that value of ‘β’ for dams be taken as ≤ 2.5 and the value of ‘I’ for dams be taken as
1.0.
The dam Site is considered to be equivalent of lying in zone IV of seismic hazard map identified by
EBCS. The values of basic horizontal seismic coefficient are 0.05.
Accordingly,
αh = 2.5 x 1.0 x 0.1
= 0.25
αv = 0.5* αh = 0.125
The Aegen micro dam has, therefore, been designed to satisfy the minimum required factor of safety
for a 0.125 g peak ground acceleration. Following international practice, the vertical peak
acceleration coefficient is assumed to be half of the horizontal peak acceleration (0.25g/2=0.125 g).
The geotechnical investigation for construction material indicates that there are different types of
embankment materials. The report also shows that there is large amount of shell material available in
qualitatively. and there is sufficient clay/ borrow material within the reservoir area, spillway axis and
around the dam site.
For this reason, a zoned earth dam with a central clay core and with weathered rock shell material for
u/s and d/s is chosen as a suitable earth dam section. This is justified from the point of utilizing the
available materials. Transition zones is required between the impervious clay core and the pervious
shell zone since there is segregation expected between the fine particles of the shell and the clay core.
Availability of suitable impervious clay core and shall materials, the amount of seepage that
can safely be permitted through the dam and the desired resistance to piping caused by
earthquake are considered in determining the thickness of the central core.
Taking the above points into consideration, the dimensions of the core are fixed as follows.
The top width of the core is made 3m. The top level of the core is kept 1.0 m below the dam
crest & 1.22m well above the full supply water level. This difference is sufficient to prevent
seepage by capillary siphoning. The upstream and downstream slopes of the core are made
to be 1:0.5 (V: H). The width of the core at any level is made to exceed the head of water
above it.
Since the central clay core is thicker and impervious; filter is not provided on both upstream
and downstream face of impervious clay core. And significant limit of water is not coming
out of d/s of the sheal resulting from seepage and there by keeping the downstream shell
relatively dry. However horizontal filter is needed to drain the residual seepage comes
through the clay core. The filter should be clean and well graded. The minimum thickness of
filter is determined from the following considerations:
(i) The thickness of filter should have allowance for intermixing with the adjoining
zones. The allowance shall be varying depending on compaction equipment used for
the purpose.
(ii) Minimum width required for compaction depending upon the equipment deployed
Accordingly, 1.0 m thickness horizontal sand filter is provided adjust between over the
foundation of the dam and the beneath of d/s sheal.
Large quantities of shell are provided to ensure stability of the body of the dam and
protection of the central core. The permeability coefficient of the shell material is 2.0 x 10-
6
m/sec, which can be classified as pervious.
The reservoir planning is made based on the water balance calculations of the hydrologic
study. As stated in the report, the sediment will be deposited throughout the reservoir water
and the new zero level estimated at 1610 masl and the dead storage is 0.142 million m3.
Hence, the total reservoir storage is 2.19 Mm3 at FSL of 1628.50 masl and among this 0.142
MMC occupied by dead storage. According to the water balance computations, the live
reservoir capacity to satisfy the annual withdrawals is beyond the physical capacity of the
reservoir, therefore, the reservoir capacity is limited/fixed at 2.19 Mm3. Based on the Aegen
Micro Dam area-elevation capacity curves the normal pool level (HNWL) to impound this
storage shall be at 1628.50 masl.
Contour Contour Contour Incremental Cumulative
Depth
Elevation Area Area Volume Volume
m ha (sq. m) (m) (cu. m) (cu. m)
1,601.00 0.361 3,611.90 0.00 - 0.00
1,602.00 0.645 6,448.93 1.00 5,030.42 5,030.42
1,603.00 0.871 8,710.56 2.00 7,579.75 12,610.16
1,604.00 1.193 11,928.86 3.00 10,319.71 22,929.87
1,605.00 1.408 14,080.27 4.00 13,004.57 35,934.44
1,606.00 1.640 16,402.64 5.00 15,241.46 51,175.89
1,607.00 1.902 19,020.00 6.00 17,711.32 68,887.21
1,608.00 2.200 22,002.71 7.00 20,511.36 89,398.57
1,609.00 2.616 26,161.80 8.00 24,082.26 113,480.82
1,610.00 3.246 32,459.91 9.00 29,310.85 142,791.67
1,611.00 3.876 38,758.01 10.00 35,608.96 178,400.63
1,612.00 4.611 46,114.42 11.00 42,436.22 220,836.85
1,613.00 5.345 53,450.91 12.00 49,782.67 270,619.51
1,614.00 6.199 61,994.11 13.00 57,722.51 328,342.02
1,615.00 7.068 70,676.22 14.00 66,335.17 394,677.19
1,616.00 7.841 78,409.08 15.00 74,542.65 469,219.84
1,617.00 8.616 86,162.09 16.00 82,285.59 551,505.42
1,618.00 9.374 93,740.45 17.00 89,951.27 641,456.69
1,619.00 10.083 100,832.21 18.00 97,286.33 738,743.02
After the normal water level is fixed as explained above the total dam height is determined as follows:
H= HNWL + Hd + Fb
Sufficient free board is provided to accommodate wave height, wave run up, wind set up above the
maximum water level and a provision for settlement.
The effective fetch length of the Aegen Micro dam reservoir was calculated from the relevant
topographic map. Accordingly, the effective fetch lengths for the maximum reservoir water level
were found to be 650m at 32.50 m dam height.
II. Wind Speed (V)
The maximum wind speed for the Aegen Micro Dam site, based on a Hydrology report is 2.13m/s.
But, the Ethiopian Building Code Standard and the National Atlas of Ethiopia shows that the western
and southern parts of the country have a wind speed (V10) for the highest mountain tops that never
exceeds 15 knots (equal to 30 m/s or 108 km/h). Wind velocity over land (U) in km/h taken as two
third of maximum wind velocity = 0.67 x 108 = 72.36 km/h or 20 m/s. Hence the basic wind speed
for the purpose of estimating significant wave height in the reservoir has been considered as 72
km/hour or 20.0 m/sec.
g Hs g Fe
0.47
= 0.0026
V
2 2
V
Where:
Fe - Effective fetch, in m
g Ts g Fe
0.28
= 0.45
V
2
V
Ho = 1.67*0.041 = 0.069m
H0
Steepness ratio = =0.069/1.012 = 0.068 for normal free board, 0.052 for minimum free board
Ls
Figure 1 is used to determine the relative run-up R/H0, whose value depends on the upstream slope of
the dam. An upstream slope of 1V:2H was assumed in this case, and the steepness ratio H0/Ls ≈ 0.1
(>0.06) for normal freeboard. Accordingly, R/H0 for a rough surface is taken to be 0.58 for normal
freeboards.
The river bed elevation is 1597.0 m. The maximum reservoir elevation is 1629.50 m for the 32m high
dam. Hence, the average depth of reservoir is:
Where:
Where:
R – wave run-up, in m
S – wind set-up, in m
Thus, the total height of the dam is the maximum of the two relations
A 7.0 m top width of the earth dam is determined to account roadway requirement, its ability to keep
the phreatic line well within the dam body, accommodate the 3.0 m minimum top width of the clay
core and practicability of construction.
A minimum of 1:2.5 (V:H) upstream and 1:2.2 at top and 1:2.5 bottom of downstream slopes of the
dam are chosen depending on the type of the embankment material, foundation conditions, the height
of the dam, and many other factors and the dam is homogenous. The stability of these slopes has been
checked by using computer software GEOSLOPE.
The hand dug trial pits along the dam axis reveal that bed rock may be found at an depth of 3m. The
cut off trench is to be provided throughout the length of the foundation. Its dimensions are fixed as
follows.
Bottom width = 4.0 m
Side slope = 1:1
The thickness of the strip drain should be sufficient to convey the maximum quantity of seepage
estimated to come through the dam.
Where : Discharge, q = 6.75×10-8 m3/s/m * 362 m length of dam = 2.41x10-5 m3/s/m (from seepage
analysis by SEEP/W software). Permeability of filter, k = 2.10 x 10-3 m/s (assumed).
A = t × 1 = t; i = 1.
t = 3.25mm
However, from construction practical considerations and to account for leakage through cracks in
core of the dam and safety of the core, it is proposed to provide a 1.0 m thick horizontal filter.
The amount of seepage loss per unit width of the dam q is estimated using the SEEP W analysis. The
seepage loss at the toe drain is 6.7 x 10-8 m3/s.
Where, q = Seepage volume per unit length (m3/sec/m) = 6.71x 10-8 m3/s/m =
L = average length of dam (355.0m)
However, since the reservoir is a monocycle and water depth in the dam is supposed to deplete/vary
continually throughout the year and the seepage is proportional to the upstream head and the above
estimated seepage loss shall be considered in the reservoir planning/water balance.
G = 100 h2
Cot
Where, h = maximum wave height (0.58m)
= Angle the upstream slope makes with the horizontal (Cot =3.0)
G = 100 (0.58)2 = 11.213 kg
3.0
Thickness of riprap in cm is computed as
t = 10.93G, =10.93*11.213
= 36.6 cm
The riprap thickness should be 50% more than the estimated linear average rock size. Therefore, t =
1.5 x 36.6 = 0.549 m
Thus from 38cm to 55 cm thick hand placed riprap shall be provided especially on the upper-most
surface of upstream slope.
Since the shell material is relatively pervious, there is no as such sudden draw down incidence
expected due to the nature of the reservoir operation. However, this may be supplemented by
provision of sandy gravel material under the hand placed riprap.
Surface stabilization of downstream slope and the prevention of soil from rain drop erosion shall be
accomplished by the establishment of grass. A depth of 20 cm of good quality organic top soil
overlying the embankment is sufficient to sustain grass growth. This shall be found from the clearing
work of the dam site and borrow areas. The cross section of the dam design is shown in Figure 8
4.10.1 General
One of the basic requirements for design of embankment dams is to ensure safety against internal
erosion, piping and development of excessive pore pressures in the dam. Seepage and slope stability
were carried out on the design of the homogeneous earth fill dam using the Slope-W and Seep-W
programs from Geo-slope international, 2014. These analyses were conducted on preliminary designs
and the results of these analyses have been used to refine the final design of the dam section. The U/s
slope section of the dam is 1:2.5 and the d/s slope selected is continues with two benches starting
from 1:2.2 u/s at the tope and 1:2.5 at the bottom respectively. The section is checked to ensure that it
satisfies the following checks are carried out safety criteria.
i. The downstream slope is checked for the stability during steady seepage conditions at reservoir
full condition and
ii. The upstream slope is checked for the stability during sudden drawdown conditions.
The slope stability investigation was carried out using the Slope/W computer program based on the
limit equilibrium method and the Morgenstern-Price method was used to obtain the factors of safety.
This particular method has been adopted because, unlike Fellenius or Bishop’s or Janbu’s methods,
the Morgenstern-Price method satisfies both the force and moment equilibrium conditions. Spencer’s
method also satisfies both moment and force equilibriums and gives factors of safety values very
close to those obtained by the Morgenstern-Price method.
The pore water pressures developed within the body of the dam and in the foundation under steady
state seepage has been initially estimated with the help of the SEEP/W software. These pore pressures
in terms of head have been incorporated in the slope stability analysis.
The worst condition under which the downstream slope should be stable is during steady seepage, at
full reservoir level. For the downstream slope of the earth dam, the most critical condition occurs
when the reservoir is full and steady seepage condition has been established because a well-defined
phreatic line is formed at this stage. The stability of downstream slope is checked under this critical
condition and the analysis result is shown in table 4-2 below. To minimize the effects of steady
seepage on the downstream slope for homogeneous dam, a horizontal filter is provided.
For the upstream slope of the earth dam, the critical condition occurs when the reservoir is suddenly
emptied (sudden drawdown condition). To minimize the effects of sudden drawdown, a shell material
which is more permeable than that of the core is provided at the upstream side. However, sudden
drawdown may not be as such expected problem due to the nature of the reservoir operation. The
reservoir evacuation time is over 30 days and this will cause an average drawdown of 0.316 m/day
which is well below the sudden draw down condition.
The Upstream slope stability has been checked under this critical condition and result is shown in
section 4.10.6.2. In both u/s and d/s slope stability analysis,
F.S = CΣ LI + Σ (Wi Cos I - UGLI) tan φ
Σ Wi Sin I
Where: WI = Weight of the slice (Wi = bi h)
= sat in saturated condition
bi = Width of the slice
h = average height of the slice (read from graph)
Li = arc length of the slice
Uw = pore water pressure developed ( wh)
I = the angle that the slice makes with horizontal
C = unit cohesion of the soil
φ = angle of internal friction
Slope stability analysis is done under the above-mentioned critical cases and the results as calculated
using the geo-slope 2018 R2 software are summarized in the table below: Since the software
considers several possible slip circles and the parameters are taken from lab results, the result has
considered dependable. Results of the long term, seismic and rapid drawdown loading cases are
presented in the following Figures
i) Results of the steady-state seepage analysis
Figure 11: Results of D/s Slope Stability Analysis for Steady-state Seepage (long term) Loading Condition
Figure 12: Results of U/s Slope Stability Analysis for Rapid Drawdown Loading Condition
Figure 13: Results of D/s Slope Stability Analysis for Short Term Loading (During Construction)
Figure 14: Results of U/s Slope Stability Analysis for Short Term Loading (During Construction)
4.10.6.2 Summary of Results
Table 9 Factor of Safety Analysis Result Summary
Slip Slope Safety factor
S.No. Condition Conclusion
Slope used
Compute Allowable
1. Steady State Seepage D/S 1:2.2 & 1.52
d* 1.50 Safe
1:2.5
2. Sudden drawdown U/S 1:2.5 1.36 1.3 Safe
Upstr
4. Steady State Seepage U/S 1:2.5 2.13 1.5 Safe
eam
5. Short Term Loading – D/S 1:2.2 & 1.51 1.0 Safe
During Construction Down 1:2.5
6 Short Term Loading – U/S
strea 1:2 1.55 1.25 Safe
During Construction
m
* As computed by Morgenstern-Price
Upstr
4.10.6.3 Conclusion eam
Down
Based on the stability analyses results, the stable slopes for the proposed earth fill dam are upstream
strea
slope of 1V:2.5H and downstream slope of 1V:1.2.2H and 1V:1.2.5H.
m
4.11 Diversion During Construction
The Aegen Micro earth dam construction expected to be completed in dry season. Before the start of
rainy season, the height of the dam is expected to be completed. Therefore, provision of diversion
structure is required as the stream is perennial and there is rainy season flow during dam fill work. If
the dam construction takes more time than expected and unexpected rain happens, the flow to be
handled by pass over the fill which will be at the riverbed section after key trench completion. The
right and the left part of the dam fill work will be done primarily then the river bed section will be
done finally. Due to the river is perennial outlet canal is used as diversion during construction and
river course during rainy season.
5. SPILLWAY DESIGN
Aegen dam being an earth dam, provision of spillway of sufficient capacity is essential for the safety of the
dam. The spillway capacity needs to be sufficient such that it contains the inflow design flood within the
storage space above the full retention level of the reservoir and prevents the dam to be overtopped in the event
of occurrence of design flood. Normally, the releases from the reservoir would be so regulated that the water
level comes close to MDDL at the end of dry season and the excess flow during rainy season gets absorbed in
the live storage. Still, the chances of occurrence of a major flood cannot be ruled out when water level in the
reservoir is close to FSL. Hence, it is required that spillway of adequate capacity be provided such that even
in the event of design flood impinging at such time when reservoir is at full retention level, there should be no
occasion for the resulting flood lift to be so high that the dam gets overtopped.
In addition to the provision of sufficient discharging capacity of the spillway, the hydraulic design of
spillway must be adequate to dissipate the energy associated with water corresponding to the
difference in head pond level of the reservoir and the tail water level downstream of the spillway
structure.
Selection of inflow design flood to determine the spillway capacity plays an important role in safety
and economy of dam and spillway structures. It relates to the risk that would arise on failure of dam
due to overtopping. Selection of IDF for Aegen Micro Dam project has been guided by USACE and
ETCOLD. The USACE guidelines for selecting of spillway design flood recommended by classifying
dams by height, volume impounded, and hazard potentials in the downstream areas in the event of
dam failure.For Aegen Micro- dam, which falls under Intermediate dam size and hazard category of
Low and class B project and its designed flood, is estimated by 100 years return period. Therefore,
the design flood for sizing the spillway will be 100 years return period was adopted but the design
will be ensured by the 500 years Return period design flood as it will not cause damage to the
spillway structures or the dam.
A design flood for spillway design of 500 years return period was considered and the estimated flood
of 49m3/s was used for spillway dimension design.
Flood routing studies for estimating the flood lift and the routed discharge over the spillway have
been made for different lengths of spillway crest. The objective of the study has been to optimize the
spillway crest length so that a balance is achieved between incremental cost of earth fill dam and the
spillway structure. Table 5.1 presents the results of reservoir flood routing by adopting different
lengths of spillway crest, the spillway crest being set at FRL of El 1608.0m.
Table 10:Aegen Micro- Reservoir Flood Routing Results for Various Special Events
Initial Routing Max.
Dam Flood Max. Inflow Spillway Spillway Elevation
Elevation at Outflow
Height, Event, Discharge, Length, Head (m)
NWL, Discharge,
m Years m3/s m (m)
Masl m3/s
24 500 1628.50 53.7 20 1.02 49 1629.50
Generally, for passing an inflow flood discharge of 53.7 m3/s and an outflow flood discharge of
49m3/s, with spillway crest at FRL, a crest length of 20m would be a proper choice.
5.4 Location
Location of the spillway is mainly governed by the feasibility of finding an economic layout and by
the consideration that it should not interfere with layout or performance of other permanent structures
of the project. Thus, the topography, geology and layout of other structures have been the main
considerations in locating the spillway structure on right bank of the river.
The spillway section starts from the right abutment of the dam. The axis of spillway control structure
is in line with axis of dam. The co-ordinates of point SP1 lying at the intersection of spillway axis and
centerline are Easting 314790.19, Northing 934986.4
Selected scheme of Aegen spillway structure comprise an approach channel leading the water to the
control structure, a control structure and an inclined chute terminating into a stilling basin. Energy
dissipation will be by means of hydraulic jump forming in the stilling basin. After the dissipation of
energy in stilling basin, the flows over spillway structure will be conveyed back to the river through
an outlet channel.
The function of the approach channel is to draw water from the reservoir and convey it to the control
structure. The guiding considerations in selecting the layout and design of approach channel are that
the entrance velocity shall be limited and channel curvatures and transitions are shaped so as to obtain
uniformity of flow over the spillway crest.
The approach velocity and depth below crest level have important influence on the discharge over the
overflow crest. A greater approach depth with the accompanying reduction in approach velocity
results in a larger discharge coefficient. Taking all factors into consideration, the bed of approach
channel is planned at El 1619.17 m.
The selected scheme has two parts. The first part of the approach channel has 90m length of
trapezoidal earth channel. The second part has 10m length of rectangular masonry & concrete lined
channel. The approach channel provides for guide walls perpendicular to the axis of control structure.
So, the total length of the approach channel is 90 m. The width of approach channel is 40.0 m and the
top of the guide walls has been kept at El 1610.16, 0.5m above the MWL.
Guided by the results of flood routing studies, the design parameters of spillway have been selected
corresponding to effective crest length of 40m and corresponding maximum outflow discharge of
189.81 m3/s. Ungated spillway control structure is recommended for releasing surplus water. For
reasons of eradicate negative pressure an Overflow Ogee control structure is chosen.
Chute section of spillway structure starts from the end of ogee profile and extends up to the start of
stilling basin. The layout is selected to effect economy by reducing the quantity of required
excavation. Discharge passes from the spillway control structure to the chute section in a supercritical
state. In order to avoid the formation of a hydraulic jump in between the crest and the stilling basin,
the layout of the chute section needs to be so selected that the flow remains in the supercritical stage
throughout the length of the chute part.
Stilling basin is the terminal structure of spillway. It is planned and designed for dissipation of energy
of flow by means of a hydraulic jump. The flow enters the stilling basin in a supercritical state. It
meets the subcritical flow in stilling basin, resulting in formation of a hydraulic jump. After
dissipation of the energy, the flow exits the stilling basin and joins the exit/outlet channel.
Outlet channel conveys the flow coming out of the stilling basin to the Aegen River. As per design
scheme of the project, the stilling basin is located 140m far from the control structure and 60m far
from the river.
For reasons of eradicate negative pressure an Overflow Ogee control structure is chosen. The ogee
shape is made to conform to the profile of the lower surface of nappe of a ventilated jet
issuing from a sharp crested weir when the head over the weir is the design head. At design
head the water flowing over the crest remains in contact with the surface of the spillway. The
pressure at the spillway surface will be atmospheric for the design head.
Design Parameters
• From the hydrology report, the design flood Qd is 53.7 m3/s
• From water balance calculations to impound the required storage the normal pool level
(NPL) shall be at 1628.50 masl.
• Dam crest level is at 1631.0m after adding sufficient freeboard for all relevant
considerations.
hf = n2V2L/R4/3 = 0.01 m
x 0.00 0.25 0.50 0.75 1.00 1.25 1.50 1.75 2.00 2.10
y 0.00 -0.02 -0.09 -0.19 -0.32 -0.49 -0.69 -0.91 -1.17 -1.29
Elevation 1608.00 1607.98 1607.91 1607.81 1607.68 1607.51 1607.31 1607.09 1606.83 1606.71
As per USBR, the upstream quadrant of the crest should conform to the quadrant of ellipse defined as
the following graphs:
For the above reason a paved channel of 140.00 m is provided with a bed slope 1/5 from 0-140m that
can keep the flow in supercritical condition until the velocity is low enough to be carried by an
earthen channel. (For details, please see the water surface profile computation table below).
1 2 3 4 5 6 7 8 9 10 16 17 19 20
0 1626.50 0.0007 0.85 2.9 0.42 1627.77 17.0 21.7 0.8 1627.8 1.0 1627.3 1628.2
5 1628.50 0.90 2.7 0.38 1629.78 18.0 21.8 0.8 1629.8 0.9 1629.4 1630.3
10 1628.50 0.88 2.8 0.40 1629.77 17.6 21.8 0.8 1629.8 0.9 1629.4 1630.2
15 1628.49 0.86 2.8 0.41 1629.77 17.2 21.7 0.8 1629.8 1.0 1629.4 1630.2
20 1628.49 0.84 2.9 0.43 1629.76 16.8 21.7 0.8 1629.8 1.0 1629.3 1630.2
25 1628.49 0.82 3.0 0.45 1629.76 16.4 21.6 0.8 1630.8 1.1 1629.3 1630.2
30 1628.48 0.80 3.1 0.48 1629.76 16.0 21.6 0.7 1629.8 1.1 1629.3 1630.1
35 1628.48 0.78 3.1 0.50 1629.76 15.6 21.6 0.7 1629.8 1.1 1629.3 1630.1
40 1628.48 0.76 3.2 0.53 1629.77 15.2 21.5 0.7 1629.8 1.2 1629.2 1630.1
45 1626.81 0.33 0.74 3.3 0.56 1628.11 14.8 21.5 0.7 1628.1 1.2 1627.6 1628.4
50 1625.14 0.70 3.5 0.63 1626.47 13.9 21.4 0.6 1626.5 1.4 1625.8 1626.7
55 1623.48 0.66 3.7 0.71 1624.85 13.1 21.3 0.6 1624.9 1.5 1624.1 1625.0
60 1621.81 0.62 4.0 0.81 1623.24 12.3 21.2 0.6 1624.3 1.6 1622.4 1623.3
65 1620.15 0.58 4.3 0.93 1621.65 11.5 21.2 0.5 1623.7 1.8 1620.7 1621.6
70 1618.48 0.54 4.6 1.07 1620.08 10.7 21.1 0.5 1623.1 2.0 1619.0 1619.9
75 1616.81 0.50 4.9 1.25 1618.56 9.9 21.0 0.5 1622.6 2.2 1617.3 1618.2
80 1615.15 0.46 5.4 1.48 1617.08 9.1 20.9 0.4 1622.1 2.5 1615.6 1616.5
85 1613.48 0.42 5.9 1.78 1615.67 8.3 20.8 0.4 1621.8 2.9 1613.9 1614.8
90 1611.82 0.38 6.5 2.18 1614.37 7.5 20.8 0.4 1621.5 3.4 1612.2 1613.1
95 1610.15 0.34 7.3 2.73 1613.21 6.7 20.7 0.3 1621.4 4.0 1610.5 1611.4
100 1608.48 0.33 7.4 2.81 1611.62 6.6 20.7 0.3 1620.8 4.1 1608.8 1609.8
105 1607.58 0.20 0.32 7.7 2.99 1610.88 6.4 20.6 0.3 1621.1 4.3 1607.9 1608.9
110 1606.67 0.31 8.0 3.23 1610.20 6.2 20.6 0.3 1621.5 4.6 1607.0 1607.9
115 1605.76 0.30 8.2 3.45 1609.50 6.0 20.6 0.3 1621.8 4.8 1606.1 1607.0
120 1604.85 0.30 8.2 3.40 1608.55 6.0 20.6 0.3 1621.8 4.8 1605.1 1606.1
125 1603.94 0.29 8.5 3.69 1607.92 5.8 20.6 0.3 1622.2 5.1 1604.2 1605.2
130 1603.03 0.28 8.9 4.02 1607.32 5.5 20.6 0.3 1622.7 5.4 1603.3 1604.3
135 1602.12 0.26 9.3 4.39 1606.78 5.3 20.5 0.3 1623.2 5.8 1602.4 1603.4
140 1601.21 0.25 9.7 4.82 1606.28 5.0 20.5 0.2 1623.8 6.2 1601.5 1602.5
145 1600.96 0.05 0.52 4.7 1.13 1602.62 10.4 21.0 0.5 1620.9 2.1 1601.5 1602.4
150 1600.71 0.51 4.8 1.18 1602.40 10.2 21.0 0.5 1621.5 2.1 1601.2 1602.1
155 1600.46 0.50 4.9 1.23 1602.19 10.0 21.0 0.5 1622.2 2.2 1601.0 1601.9
160 1600.22 0.48 5.1 1.31 1602.01 9.7 21.0 0.5 1623.1 2.3 1600.7 1601.6
165 1598.55 0.20 0.47 5.2 1.37 1600.39 9.4 20.9 0.5 1622.5 2.4 1599.0 1599.9
170 1596.88 0.44 5.6 1.58 1598.91 8.8 20.9 0.4 1622.0 2.7 1597.3 1598.2
175 1595.22 0.43 5.7 1.67 1597.32 8.6 20.9 0.4 1621.4 2.8 1595.6 1596.6
180 1593.55 0.42 5.9 1.77 1595.74 8.3 20.8 0.4 1620.8 2.9 1594.0 1594.9
185 1591.89 0.40 6.1 1.87 1594.16 8.1 20.8 0.4 1620.3 3.0 1592.3 1593.2
The design parameters for calculating the critical slope of the chute by Manning formula are:
The critical water depth with in the chute can be calculated by the next formula;
q = Q/L = 2.45m3/s/m
The slope of the chute should be steeper than 2 % in order to attain supercritical flow in the chute.
From the water surface computations, we can see that at chainage 0 +185.0 m the velocity of flow is
9.46 m/sec and the Froude number is 2.73 which is below 4.5. This shows that there is no much
energy left that requires a special energy dissipating structure. However, a stilling basin is
recommended for length of 8 m concrete lined channel.
When the water is coming from the steeper slope of the chute before reaching the earth channel which
leads it to the natural river a stilling basin is provide for a length 6*d 2 = 14 (take 15.0 m). Since the
Froude number of the pre-jump is less than 4.5, a true hydraulic jump does not fully develop. Stilling
basins that accommodate these flows are the least effective in providing satisfactory dissipation.
Hence, a concrete lined floor for a length of 6*d2 is provided.
Y2=
Y1
2
1+ 8 F - 1=0.68/2[√1+8*2.73 -1]
2
1
2
Y2(d2= 2.29 m
After the energy is dissipates through the stilling basin the water flows into an exit channel. The
design of the exit channel is carried out below.
A trapezoidal type of section of 1:1 side slope is selected in cut, for this type of channel the cross
section area is given by:
A = bd + md2
= 20*0.5+1*0.6^2
P = B + 2d 1 + m2 =20+2*0.5*(√1+12)
Then, Q = 1 A R2/3 S ½
n
Assuming a channel bed slope of S0 = 0.024 and n = 0.020 for Rocky channel,
Solving the above equation by trial and error gives a flow depth d = 0.6m, as a result the velocity of
the flow through the channel can be found from the discharge Q = 49 m3/s and cross section area A =
9.04 m2
Then, the velocity becomes,
V = Q = 5.46 m/s
A
The velocity of the channel is indeed higher for earth channel. Hence, it is recommended to add a
hand placed stone riprap. The stone riprap should be both in the floor and side bank underlain by 15.0
cm sand gravel.
Because of average width of Aegen stream channel is small and to protect the command area from the
flood-related problems during spilling of the flood; the stream should be trained by enlarging the
channel width. When analyzing the flood discharge by the tail water rating curve (see the table and
figure below) the river channel requires expanding the channel width. Average Slope of the stream is
2.48%.
The intended river channel section has been designed using standard Manning’s formula and proposed
as unlined, open trapezoidal section with side slope of 1H : 1V. In order to maintain the flood flow
from the d/s toe of the dam to the end of the command area, it is desirable to keep the waterway
opening at least 40m at the bottom and 43.0m at the top of the channel. Flow depth of the channel is
estimated 1.50m and 0.30m additional depth (free board) is provided to prevent overtopping of the
banks due to waves in the water surface.
6.2 Location
The out let is located on the left side of the river at a distance of 96.0m along the dam axis, from the
left abutment.
The out let pipe bed level elevation at the intersection point of the pipe axis with the dam axis is fixed
to be 1610 m amsl.
The dead storage level is fixed by keeping a 50-year useful life without dragging operation. The gate
is located at the downstream end to ease of operation.
The major components of the outlet work are; an inlet box (intake) submerged in the upstream
reservoir with trash rack over it and on the side wall as well, steel conduits of diameter 0.7 m, 6.0 m
long each, provided to carry the discharge from the inlet box to downstream, at the end of which two
butterfly valves are provided. A plunge basin is also provided at the downstream end to dissipate the
excess energy so that the main canal is safe from erosion. The basin will have two outlets where the
one is for the main canal while the remaining one is for downstream release during rainy season.
Since the gate is provided at the dawn stream end of the pipes, the portion up stream of the gate is
considered to be flow regime under pressure. The outlet is designed to carry 0.55 m3/sec.
The head losses considered for the design of the outlet were trash rock losses (ht), entrance losses (he),
gate or value losses (hg) friction losses (hf) and exit losses (hv). Other losses were assumed to be not
relevant to this scale of outlet.
The head ‘hL’ as measured from the reservoir surface (NPL, 1628.50 masl) to the effective position of
the hydraulic grade line at the outlet is given by;
hL= ht + he+ hg + hv +hf + V2/2g ............. (1)
Since the outlet pipe diameter is constant (i.e.0.60 m) throughout its lengths and assuming the get to
be operated fully opened the cross-sectional area of the pipe is constant. Hence the velocity is
assumed to be constant throughout the pipe length.
For a maximum discharge Q max =0.55 m3/sec. And pipe diameter D=0.60m. the cross-sectional area
will be,
A= πD2/4 ............. (2)
= π (0.6)2
4
= 0.283 m2
V= Q ............. (3)
A
= 1.95m/sec.
The pipe length from inlet to outlet is 140.0 m. Since each pipe length is 6 m, and a total of 24 pipes
can be taken. Each loss was computed as under.
The head loss due to friction along the conduit was computed by the Darcy-Weisbach formula
(According to USBR Small Dam, for flow in large pipes, the Darcy-Weisbach formula is most often
used to determine the energy losses from frictional resistances of the conduit) which is given by
hf = (f *L)/D (V2/2g) ............ (4)
The value of the friction factor f is determined by its relation with manning “n” by
The maximum and minimum value of n for a steel pipe with welded joints is 0.012 and 0.008. The
average value i.e. 0.01 is taken for design purpose.
f av = 185* (0.01)2 / (1.97)1/3 = 0.015 For the assumed pipe diameter of 0.60 m;
(i.e. 2.3ft...)
Similarly
f min = 0.009
f max = 0.021
2
an an
K t av = 1.45 - 0.45 - .................. (7)
ag ag
V2
_ ht = 0.915
2g
htmax=0.915*0.19 = 0.177m
The minimum trash rack loss coefficient is taken as zero and the maximum loss value is considered
k t avg = 0.608
Using equation (6)
2
v
havg = k t avg x * .......... ........(8 )
2g = 0.117 m.
hmin=0.045m
Entrance Loss
1 = 0.266
k emax = ( 2
- 1)
0.79
2
v
h g = Kg ( )
2g ...........................................(11)
The minimum, average and maximum valves loss coefficient kg for a butterfly valve were assumed to
be 0.10, 0.15 and 0.2 respectively hence, from equation (9)
h g min = 0.019 m.
hg avg = 0.029 m
hg max = 0.039 m.
Bend loss
Bend losses are given by hb = Kb (V2) ............................... (12)
2g
The value of the loss coefficient, Kb, for 900 bends is taken as 0.9. Therefore, hb = 0.9*v2/2g = 0.174 m
Exit loss
Exit losses are given by he = Kv (V2) ............................... (13)
2g
Since the release form pressure conduit freely discharges, the velocity head loss coefficient k v is taken as 1.0
Therefore, hg = v2/2g = 0.193 m
Table 14: Summery computation of loss coefficients and head losses
Loss Considerations
S. No. Loss type & Coefficient head
symbol head loss Coefficient head Coefficient
Minimum loss
(m) average loss (m) maximum
(m)
1 Friction, hf 0.009 0.29 0.015 0.46 0.021 0.66
2 Trash rack, ht 0.235 0.045 0.608 0.117 0.915 0.177
3 Entrance loss, he 0.087 0.017 0.111 0.021 0.266 0.051
4 Value loss, hv 0.10 0.019 0.15 0.029 0.2 0.039
5 Bend loss, hb 0.9 0.174 0.9 0.174 0.9 0.174
6 Exit loss, hex 1.0 0.193 1.0 0.193 1.0 0.193
Total loss hL 0.74 0.99 1.29
Heff = H - h
Where H, is the total head i.e. the difference in head between the upstream normal water level (NPL=
1608.0) and the downstream centre line of the pipe is (1591) is 17.0 m.
Therefore, the net available head to cause flow in the three conditions will be
Q = A 2g.H eff
..................................... (13)
Substituting the maximum and minimum net effective head in equation (13) give the average,
maximum and minimum discharges as follows;
Qav = A 2gHeff
Q av = 5.01 m3/Sec., Qmax = 5.05 m3/sec and Q min = 4.96m3/sec > 0.55 m 3/sec; this is ok for reservoir
full condition, since the minimum discharging capacity of the outlet (Qmin) is much greater than the
discharge required during the peak demand, it is ok.
For low reservoir levels, the minimum net head required to get the design discharge of 0.55 m3/sec is
computed as follows:
= 0.19 m
This is too small from the max head loss. This shows that there will be short of head to get the 0.55
m3/sec discharge at very low reservoir level if we fix maximum main canal beginning bed level at
elevation 1609.95m amsl. In other words, there must be a minimum of 0.22 m and a maximum of
0.41 m head above the outlet level to get the maximum discharge. This situation will be a problem if
the lowest reservoir level and the maximum irrigation demand occur simultaneously. But the
proposed maximum main canal beginning bed level is 1609.80m amsl this is lower than the
calculated maximum main canal bed level hence the design head is safe and there will not be
expected head problem.
It has been empirically proven that the dam body compaction around circular pipe has always been
less than the required density & as a result leakage is likely to happen. One of the techniques to be
applied is the use of Filter material along Pipe which easily pass the seepage.
Plunge basins type terminal structure were chosen to dissipate energy as flow issue from a
downstream control value and the jet discharges in to the air and plunges down wards in to a pool
of water.
According to USBR recommendation the total basin depth was made about one-fifth (1/5) of the
difference in elevation between maximum reservoir water surface and maximum tail water levels.
=6.50 m
But this value seems uneconomical for such a maximum discharge of 5.05 m3/sec; therefore,
about 50% of it is adapted, i.e., 1.85 m. The basin length will be 5 times of the actual basin depth,
i.e., 10m. Therefore, the bottom width of the plunge basin can be made 2D i.e., 1.2 m.
The Intake tower is designed as a rectangular hollow section stem uniform size throughout the
height, made out of reinforced concrete structure. The typical tower height taken is 20.1m high
and the stem cross section is 3.90mx2.6m m. Figure 1.1 below shows the plan and vertical section
of the intake tower. The tower has 2 gates at the bottom of stem to control water supply for
irrigation. In case the reservoir is full, or in case of flood and the stem is empty, for the case of
maintenance period for example, the uplift of water on the stem is at the maximum value. To
introduce a factor of safety drilled anchor rods are used to attach the structure to the foundation to
balance the uplift force together with the self-weight of the stem and to control the possibility of
overturning of the stem in case of an earthquake event. The external tower wall facing the
pedestrian bridge side supports the bridge girder. The access bridge is aligned to parallel to the
dam axis in order that access is possible from right or left side of the dam from the site
topographic convenience point view and to avoid the complication between the interaction of the
bridge support foundations with the dam body and irrigation outlet instead of access is made
across dam axis or along the alignment of the irrigation outlet for accessing the bridge right from
the dam crest.
Design of intake tower is based on linear elastic response spectra modal techniques. The tower
has a 0.3m thick concrete slab at the top and a heavy 1.0 m thick slab at its base. The unit weight
of concrete considered is equal 24 KN/m.
The tower is located in seismic zone. The peak ground accelerations for the MDE (Maximum
Design Earthquake) are 0.1g. Dynamic forces were calculated using SAP-2000 software.
Figure 15: Intake tower and Access Bridge Plan and Longitudinal Section
Design provisions outlined here are applicable to structures with capacities well below the
balanced point of the axial-force bending-moment interaction curve (Figure 3). Since the vertical
load in towers is generally the result of self-weight, which is not very large, most intake towers
will have capacities well below the balanced point.
The basic seismic design of the reinforced concrete intake towers should follow the following steps:
(7) Check ultimate-state failure modes and redo shear design if necessary:
Tower will fail in bending. Since the bending is a ductile failure mode, the design is OK if the
ductility requirement is met and the shear strength is not exceeded.
Tower will fail in shear. Since the shear is a brittle failure, the failure under shear should be
avoided. This is done by increasing shear strength of the tower by redoing shear design with φ =
0.60.
2. Material Properties
The materials used for the design are summarized here in below
3. Section Properties
In order to perform a design, the overall dimensions of the structure should be known. In most
cases geometry of the tower is known prior to the design process. Figure-4 shows dimensions of
the bottom section of the tower, where the largest bending moment, shear, and axial forces occur.
The critical section can also be determined on the basis of the demand-capacity ratios, if
approximate capacities of the sections are known
The computed moment and force demands after application of load factors should be less than or
equal to the factored uni-axial nominal capacities:
Where Ag is the gross sectional area and fc’ is the concrete compression strength, the bending
taken as 0.60.
From the national earth quake zoning provided by Ethiopian building code of standard the
maximum anticipated earth quake Coefficient is 0.1 for recurrence interval of 100 years.
Accordingly, the design is done based on the design procedure outlined by USACE guideline
referred as operating Basis Earthquake (OBE) design for peak ground acceleration of 0.1 and for
Maximum Design earth quake (MDE) for recurrence interval of 1000 years peak ground
acceleration coefficient, which is projected to be equal to 0.2.
7. DAM INSTRUMENTATION
7.1 Dam Control Instrumentation
For the systematic control of the performance of the dam, both during construction and operation, the
following instrumentation has been investigated and measurements of the types stated below will be
taken as outlined in detail in the operation and maintenance manual.
Monuments will be used for the measurement of vertical and horizontal displacements. Theses
monuments will be located at selected points on the dam crest.
The vertical and horizontal displacements of the dam shall be periodically controlled by the help of
surveying instruments which have preferably high degree of accuracy.
The vertical and horizontal spacing of the monuments will be according to the following coordinates
(see Layout Map). Permanent bench marks located outside the influence of the dam and reservoir will
serve as the main reference points from which all surveying works for the control of vertical and
horizontal displacements commence.
For the measurements of pore water pressure open stand pipe piezometers are recommended due to
economical and practical aspects. The location of the pipes should be in such points where pore water
pressure is assumed to be critical. The arrangements of the piezometers are shown in Layout Map.
Non recording rain gauge has to be installed at the Dam site for the measurements of daily rainfall. In
order to obtain continuous data, it is advisable to install self –recording rain gauge.
The Reservoir Water Levels will be measured by means of staff gauges installed on the walls of the
intake tower and on the banks of the reservoir where observation and maintenance could be useful in
observing the flood magnitude.
Reservoir sedimentation can be measured using sounding line capable of measuring the depth of water
in the reservoir, so as to be able to obtain the elevation reached by the sediment deposition. Sampling of
the water turbidity in the reservoir shall be carried out by conventional hydrometric methods.
The quantity of water to be released into the irrigations water supply system can be measured by
installing water meters (V-notch weirs). Downstream release could also be measured by the same
device. For future information conventional reservoir operation planning is included in the operation
and maintenance manual.
In the regular operation of reservoir constant surveillance of the dam must be carried out using
appropriate personnel, necessary equipment and facilities. The Surveillance of the dam shall be ensured
by a responsible technician who will be in charge of the supervision crew. The crew consist of crew
leader (qualified technician), assistant technicians, skilled laborers, guard officer and assistants.
The technician, the guard officer, and their assistants, if any shall reside in the immediate vicinity of the
dam, in a well-furnished living quarter and nearby office rooms. The office should have telephone and
radio communication facility or either of them to be in close contact with local and regional office
which would be responsible for operation and maintenance works of the dam.
The regional/zonal office shall appoint an engineer or an assistant engineer in charge of the operation,
inspection and maintenance of the dam. He will probably reside in the zonal capital, but shall make
regular inspection of the dam according to defined scheduled of inspection and when the need each
period.
The inspection by the engineer or assistant engineer shall be at least four times a year during the regular
operation of the reservoir. Inspection should be scheduled during period of high and low water to
observe conditions peculiar to each period.
Special inspection should be scheduled when there is reason to believe that significant damage has
occurred or may develop, such as after any unusual occurrence, like earth quakes, sustained periods of
heavy rains, heavy flood events etc.
During the initial filling of the reservoir inspection shall be conducted daily or in day time so that
utmost information could be acquired.
Roads and pathways which are in good condition shall be ensured between the living quarter office
rooms and different parts of the dam, such as intake tower, crest of the dam, downstream berms,
spillway, outlet part of conduit.
In relation to hydrologic and meteorological data utilized for this particular study and design
purpose, those global datasets shall be verified by site specific information. Even though current
land use and cover global data and long duration (30 years) precipitation datasets have been
utilized, undertaking site condition analysis maximizes the accuracy for estimates made on flood
and flows together with sediment load. Hence documents to be submitted in the near future will
incorporate such site-specific study and data analysis results.
From conducted seepage analysis through dam body and subsurface formation, the estimated
loss due to seepage was found to be 3.36 m3/day or (0.04l/s) per meter length of the dam. This
may change depending on utilized borrow area material property variability. Therefore, it is
essential to check the assumed soil property in the design is compatible to the existing condition
during construction.
• For better performance and sustainable service of the project, regular inspection and
maintenance is highly required.
• Farmers training on how to operate and maintain the project as a whole and utilization of
available land water resources has a paramount importance.
• The irrigation hours per day and per week should be flexible based on the demand
• Detail supervision, follow up and decision making on compatibility of actually observed
and utilized design parameters is so critical and basic necessity during the construction.
• The Dam has been evaluated against all the causes of failure and found safe specially,
Piping, Overtopping, Settlement / liquification and Stability against different loading
conditions
• Sedimentation is the main cause for shortening the service life of this project. As a result,
a due attention shall be given for soil and water conservation practice in the catchment
area.
• The design is compatible if and only if the dam is constructed with the same quarry site
and material property unless the design should be revised when the material property is
changed.
REFERENCES
• Cedergren, H. R., (1977). Seepage, Drainage and Flow Nets, 2nd ed., Wiley, New York.
• FEMA, (2011), Filters for Embankment Dams, Best Practices for Design and
Construction, U.S Department of Homeland Security, USA.
• Geo-slope International, Ltd., Canada (2009). Dynamic Modelling with QUAKE/W,
QUAKE/W Engineering Workbook.
• Jibson, R.W. (2011). Methods for assessing the stability of slopes during earthquakes—
A retrospective: Engineering Geology, v. 122, p. 43-50.
• Novak, P., Moffat, A.I.B., Nalluri, C., and Narayanan, R., 2007. Hydraulic Structures, 4th
ed., Taylor & Francis, London
• U.S Army Corps of Engineer manual EM-1110-2-6053
• USBR (2014). Design Standards No. 13 Embankment Dams, Chapter 7: Riprap Slope
Protection Phase 4 (Final)
• USBR (1987). Design of Small dams, A water Resources Technical publication, 3rd
edition’
9. BILL OF QUANTITY
Table 16: Bill of Quantity
Revised Amount
Bill. No. Description
(ETH Birr)
1 General Provisions
2.1.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 116.34 20.44 2,377.72
2.1.2.3 Mass concrete fill on floor slab (100mm) C-15. m2 91.4 323.58 29,574.92
Supply and fix 8mm thick chip wood internal wall cover.
2.1.3.4 m2 150 1,023.53 153,529.53
Price shall include 4 x 5 cm wooden buttons
2.1.4.6 Supply and fix CIS windows size 1x1.2m No 8 748.16 5,985.31
2.1.4.7 Supply and fix CIS doors size 1.0x2.10m No 8 1,939.81 15,518.49
2.1.5 Finishing
2.1.5.1 Floor screed in cement mortar 20 mm thick (1:3 mortar) m2 73.12 315.03 23,034.96
2.2.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 36.48 20.44 745.57
2.2.2.3 Mass concrete fill on floor slab (100mm), C-15 m2 33.3 323.58 10,775.11
2.2.4.5 Supply and fix CIS windows size 1x1.2m No 2.00 748.16 1,496.33
2.2.4.6 Supply and fix CIS doors size 1.0x2.10m No 3.00 1,939.81 5,819.43
2.2.5 Finishing
2.2.5.1 Floor screed in cement mortar 20 mm thick, (1:3 mortar) m2 32.83 315.03 10,343.05
2.3.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 24.00 20.44 490.50
2.3.2.3 Mass concrete fill on floor slab (150mm) for shower, C-15 m3 1.20 3,235.77 3,882.92
2.3.4.5 Supply and fix CIS doors size 1.0x2.10m No 6.00 1,939.81 11,638.87
2.4.1.1 Clearing of site to remove top soil to a depth of 200 mm m2 38.40 20.44 784.81
2.4.2.3 Mass concrete fill on floor slab (100mm), C-10 m2 57.60 323.58 18,638.02
2.4.4.5 Supply and fix CIS windows size 1x1.2m No 2.00 748.16 1,496.33
2.4.4.6 Supply and fix CIS doors size 1.0x2.10m No 2.00 1,939.81 3,879.62
2.4.5 Finishing
2.4.5.1 Floor screed in cement mortar 20 mm thick, (1:3 mortar) m2 52.50 315.03 16,539.05
3.1 Earthwork
Clearing the dam site from bushes, stones etc and top soil
3.1.1 m2 42,501.45 20.44 868,729.64
removal, 20 cm and including disposal
3.1.2 Trench excavation in soft rock and disposal m3 2,428.05 269.47 654,286.23
3.1.3 Trench excavation in hard rock and including disposal m3 1,214.02 381.74 463,441.62
5.1 Earthwork
Clearing the spillway site from bushes, stones etc and top
5.1.1 m2 8,627.42 20.44 176,344.46
soil removal, 20 cm and disposal
5.4.3 Supply and place gravel surrounding the perforated pipe m3 30 330.00 9,900.00
5.5 Miscellaneous
5.5.1 Supply and fix 250 mm PVC water-stops m 405 628.00 254,340.00
5.5.2 Resin bonded cork filler (20 mm thick) m2 121.50 950.00 115,425.00
6.2 Backfilling
Backfilling with native excavated material obtained from
6.2.1 m3 19.70 66.76 1,315.12
foundation excavation.
Backfilling with selected material imported from borrow
6.2.2 m3 15.76 99.96 1,575.31
area.
Subtotal 6.2 2,890.42
6.5 Formwork
6.6.1 200mm thick Hollow Concrete Block Work m2 23.65 500.00 11,825.00
6.7 Miscellaneous
6.8.1.2.2 Cut, bend and tie Reinforcement Bar Kg 9,780.64 114.81 1,122,915.01
6.8.1.2.4 Concrete Fluting of Concrete surface at Clay Core Zone m2 416.91 300.00 125,073.05
6.8.2.2 Cut, bend and tie Reinforcement Bar Kg 485.90 114.81 55,786.18
6.9.1.1 PN 10, DN ---- Butter fly Gate Valve No. 2 235,000.00 470,000.00
6.9.1.4 Spindle and geer Box system for Gate Valve Operation No. 2 500,000.00 1,000,000.00
6.9.2.1 Flanged peddled PN16 DCI pipe DN 1000 No. 1 50,000.00 50,000.00
6.9.2.2 Flanged peddled PN16 22.50 DCI Bend DN 1000 No. 1 75,000.00 75,000.00
1000X1000 mm flow Control Slide gate including all
6.9.2.3 No. 1 800,000.00 800,000.00
accessories
600X600 mm flow Control Slide gate including all
6.9.2.4 No. 1 500,000.00 500,000.00
accessories
7.1.3 Spreading & compaction for camber formation m2 18,000.00 20.00 360,000.00