RFP Design Consultancy Services Ntcheu-Tsangano-Neno-Mwanza
RFP Design Consultancy Services Ntcheu-Tsangano-Neno-Mwanza
Roads Authority
For the
Lilongwe 3, MALAWI
2
Part 1 - Section 1 Instructions to Bidders
Table of Contents
3
4
Table of Clauses
A. General..................................................................................................................................... 5
1. Scope of Proposal.................................................................................................................... 5
2. Source of Funds....................................................................................................................... 5
3. Eligible Bidders......................................................................................................................... 5
4. Conflict of Interest..................................................................................................................... 5
C. Preparation of Proposals........................................................................................................ 8
9. Preparation of Proposals.......................................................................................................... 8
E. Evaluation of Proposals....................................................................................................... 12
20. Confidentiality......................................................................................................................... 12
29. Negotiations............................................................................................................................ 14
F. Award of Contract................................................................................................................. 15
30. Award of Contract................................................................................................................... 15
6
Part 1 - Section 1 Instructions to Bidders
1.1 The Procuring Entity indicated in the Bid Data Sheet (BDS) invites technical and financial
proposals for the consulting services described in Section 6, Terms of Reference. The
proposal could form the basis for future negotiations and ultimately a contract between
your firm and the Procuring Entity.
1.2 The procurement reference number and a brief description of the Assignment and its
objectives are given in the BDS.
1.3 The Assignment shall be implemented in accordance with the phasing indicated in the
Terms of Reference. When the Assignment includes several phases, continuation of
services for the next phase shall be subject to satisfactory performance of the previous
phase, as determined by the Procuring Entity.
2. Source of Funds
2.1 The Procuring Entity has an approved budget from public funds towards the cost of the
procurement described in the BDS. The Procuring Entity intends to use these funds to
place a contract for which this Request for Proposals is issued.
2.2 Payments will be made directly by the Procuring Entity and will be subject in all respects to
the terms and conditions of the resulting contract placed by the Procuring Entity.
3. Eligible Bidders
7
Part 1 - Section 1 Instructions to Bidders
4. Conflict of Interest
4.1 The Government of the Republic of Malawi (hereinafter called “the Government”)
requires that Consultants provide professional, objective, and impartial advice and at all
times hold the Procuring Entity’s interests paramount, strictly avoid conflicts with other
assignments or their own corporate interests and act without any consideration for
future work. Without limitation on the generality of the foregoing, Suppliers, and any of
their affiliates, shall be considered to have a conflict of interest and shall not be
recruited, under any of the circumstances set forth below:
(a) A firm that has been engaged by the Procuring Entity to provide goods, works or
services other than consulting services for a project, and any of its affiliates, shall be
disqualified from providing consulting services related to those goods, works or
services. Conversely, a firm hired to provide consulting services for the preparation
or implementation of a project, and any of its affiliates, shall be disqualified from
subsequently providing goods or works or services other than consulting services
resulting from or directly related to the firm’s consulting services for such
preparation or implementation. For the purpose of this paragraph, services other
than consulting services are defined as those leading to a measurable physical
output, for example surveys, exploratory drilling, aerial photography, and satellite
imagery.
(b) A Consultant (including its Personnel and Sub-Consultants) or any of its affiliates
shall not be hired for any assignment that, by its nature, may be in conflict with
another assignment of the Consultant to be executed for the same or for another
Procuring Entity. For example, a Consultant hired to prepare engineering design for
an infrastructure project shall not be engaged to prepare an independent
environmental assessment for the same project, and a Consultant assisting a
Procuring Entity in the privatization of public assets shall not purchase, nor advise
purchasers of, such assets. Similarly, a Consultant hired to prepare Terms of
Reference for an assignment should not be hired for the assignment in question.
(c) A Consultant (including its Personnel and Sub-Consultants) that has a business or
family relationship with a member of the Procuring Entity’s staff who is directly or
indirectly involved in any part of (i) the preparation of the Terms of Reference of the
assignment, (ii) the selection process for such assignment (iii) a member of the
Procuring Entity’s Internal Procurement Committee, or (iv) supervision of the
Contract, may not be awarded a Contract, unless the conflict stemming from this
relationship has been resolved in a manner acceptable to the Government
throughout the procurement process and the execution of the Contract.
4.2 Consultants have an obligation to disclose any situation of actual or potential conflict
that impacts their capacity to serve the best interest of the Procuring Entity, or that may
reasonably be perceived as having this effect. Failure to disclose said situations may
lead to the disqualification of the Consultant or the termination of its Contract.
4.3 No agency or current employees of the Procuring Entity shall work as a Consultant
under their own ministries, departments or agencies. Recruiting former government
employees of the Procuring Entity to work for their former ministries, departments or
agencies is acceptable provided no conflict of interest exists. Bidders should be aware
that existing government employees can only be nominated as personnel in Technical
8
Part 1 - Section 1 Instructions to Bidders
5.1 The Government requires that Procuring Entities, as well as Bidders and Suppliers
under government-financed contracts, observe the highest standard of ethics during the
procurement and execution of such contracts. In pursuance of this policy, the
Government:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) "corrupt practice" means the offering, giving, receiving or soliciting, directly or
indirectly, of anything of value to influence the action of a public official in the
procurement process or in contract execution;
(ii) "fraudulent practice" means a misrepresentation or omission of facts in
order to influence a procurement process or the execution of a contract;
(iii) “collusive practices” means a scheme or arrangement between two or more
Bidders, with or without the knowledge of the Procuring Entity, designed to
establish prices at artificial, noncompetitive levels; and
(iv) “coercive practices” means harming or threatening to harm, directly or
indirectly, persons or their property to influence their participation in a
procurement process, or affect the execution of a contract.
(b) will reject a recommendation for award if it determines that the Bidder recommended
for award has, directly or through an agent, engaged in corrupt, fraudulent, collusive or
coercive practices in competing for the contract in question; and
(c) will debar a Bidder from participation in public procurement for a specified period of
time if it at any time determines that the firm has engaged in corrupt, fraudulent,
collusive or coercive practices in competing for, or in executing, a contract.
B. Request for Proposals Document
6. Sections of Request for Proposals Document
6.1 The Request for Proposals Document consist of Parts 1, 2, and 3, which include all the
Sections indicated below, and should be read in conjunction with any Addenda issued in
accordance with ITB Clause 8.
Part 1 Bidding Procedures
Section 1 Instructions to Bidders (ITB)
9
Part 1 - Section 1 Instructions to Bidders
7.1 Bidders requiring a clarification of the Request for Proposals Document must notify the
Procuring Entity, in writing, not later than fourteen (14) days before the proposal
submission date. Any request for clarification shall be sent to the Procuring Entity’s
address indicated in the BDS. The Procuring Entity shall respond in writing to such
requests, and copies of the response shall be sent to all invited Bidders.
8.1 At any time before the submission of proposals, the Procuring Entity may, for any reason,
whether at its own initiative or in response to a clarification requested by an invited Bidder,
modify the Documents by amendment. The amendment shall be sent in writing to all
invited Bidders and will be binding on them. The Procuring Entity may at its discretion
extend the deadline for the submission of proposals.
C. Preparation of Proposals
9. Preparation of Proposals
9.1 You are requested to submit separate technical and financial proposals.
9.2 In preparing the proposal, you are expected to examine all terms and instructions included
in the Request for Proposals Document. Failure to provide all requested information shall
be at your own risk and may result in rejection of your proposal.
9.3 To obtain first-hand information on the Assignment and on the local conditions, bidders are
encouraged to pay a visit to the Procuring Entity before submitting a proposal and attend a
pre-proposal conference if specified in the BDS. Bidders must fully inform themselves of
local conditions and take them into account in preparing their proposal.
9.4 The Procuring Entity shall provide the inputs specified in the Terms of Reference, assist
the Supplier in obtaining licenses and permits needed to carry out the services, and make
available relevant project data and reports.
9.5 Please note that the costs of preparing the proposal and of negotiating the contract,
including a visit to the Procuring Entity, are not reimbursable as a direct cost of the
Assignment;
9.6 Please note that the Procuring Entity is not bound to accept any of the proposals
10
Part 1 - Section 1 Instructions to Bidders
submitted.
10.1 The proposal, as well as all correspondence and documents relating to the proposal
exchanged by the Bidder and the Procuring Entity, shall be written in English.
10.2 Study reports must be in the Language(s) specified in the Terms of Reference. Working
knowledge of the national language by the firm’s personnel is recommended.
11.1 If a Bidder considers that it does not have all the expertise for the assignment, it may
obtain a full range of expertise by associating with individual consultant(s) or other firms
or entities or by sub-contracting as appropriate.
11.2 Bidders shall not associate with other Bidders invited for this assignment, unless
otherwise specified in the BDS.
11.3 International Bidders for large contracts are encouraged to seek the participation of
national Consultants by entering into a joint venture with, associating with or
subcontracting part of the assignment to national Consultants.
11.4 The same subconsultant may be included in several proposals, subject to any limitations
in the BDS. Any limits on the percentage of the total proposed contract price which may be
subcontracted are stated in the BDS.
12.1 The estimated number of key professional staff-months required for the Assignment is
stated in the BDS. Your proposal should be based on a number of key professional staff-
months substantially in accordance with the above number. Alternatively, for fixed-budget
assignments, the available budget is given in Section 3, Evaluation Criteria and the
Financial Proposal shall not exceed this budget.
12.2 It is desirable that the majority of the key professional staff proposed are permanent
employees of the Bidder or have an extended and stable working relationship with the
Bidder.
12.3 Proposed staff should have experience under conditions similar to those prevailing in the
Republic of Malawi.
12.4 No alternative to key professional staff may be proposed, and only one curriculum vitae
(CV) may be submitted for each position.
13.1 Your technical proposal shall provide the following and any additional information, using
the formats included in Section 4, Bidding Forms:
(a) The Technical Proposal Submission Sheet (Section 4, Form T1);
(b) A brief description of the Bidder’s organisation and an outline of recent experience on
assignments of a similar nature. (Section 4, Form T2). For each assignment, the
outline should indicate, inter alia, the profiles of the staff provided, duration, contract
amount and firm involvement;
11
Part 1 - Section 1 Instructions to Bidders
(c) Any comments or suggestions on the Terms of Reference, including the data, services
and facilities to be provided by the Procuring Entity (Section 4, Form T3);
(d) A description of the approach, methodology and work plan that the Bidder proposes to
execute the services (Section 4, Form T4);
(e) The composition of the proposed staff team, the tasks which would be assigned to
each (Section 4, Form T5);
(f) CVs recently signed by the proposed key professional staff or an authorized manager
in the home office (Section 4, Form T6). Key information should include number of
years with the firm, and degree of responsibility held in various assignments during the
last ten (10) years;
(g) A Staffing Schedule, showing estimates of the total staff input to be provided to carry
out the Assignment (Section 4, Form T7), supported by bar chart diagrams showing
the time proposed for each professional staff member;
(h) A Work Schedule, showing the timing proposed for each activity, which must be
consistent with the methodology and workplan described in the proposal (Section 4,
Form T8); and
(i) Any additional information requested in the BDS.
13.2 The technical proposal shall not include any financial information.
14.1 The financial proposal shall list all costs associated with the assignment, using the
following standard forms contained in Section 4, Bidding Forms:
(a) Financial Proposal Submission Sheet (Section 4, Form F1);
(b) Summary of Proposal (or Activity ) Price (Section 4, Form F2);
(c) Summary of Fees (Section 4, Form F3);
(d) Summary of Reimbursables (Section 4, Form F4); and
(e) Any additional information requested in the BDS.
14.2 The total proposal price shall be broken down into the following cost components using
the appropriate forms:
(a) Fees for staff, indicating rates for home and field work, where appropriate; and
(b) Reimbursable expenditure, such as subsistence, transportation (international and
local for mobilisation and demobilisation), services and equipment (vehicles, office
equipment, furniture, and supplies), printing of documents, surveys etc.
14.3 Where indicated in the BDS, the total proposal price shall be broken down into separate
activities and forms F2 to F4 shall be completed for each activity.
14.4 The financial proposal should clearly estimate, as a separate amount, the local taxes
(including social security), duties, fees, levies, and other charges imposed on the
Consultant and their personnel (other than nationals of or permanent residents in the
Republic of Malawi), unless the BDS specifies otherwise.
14.5 The completed financial proposal forms, adjusted if necessary during evaluation or
negotiation, will be used in any resulting Agreement, to compile the: breakdown of
Contract Price in the case of a Lump Sum contract, which will be used only to
12
Part 1 - Section 1 Instructions to Bidders
15.1 Bidders may express the price of their services in Malawi Kwacha or any freely
convertible currency, unless otherwise indicated in the BDS. Bidders may not use more
than three currencies. The Procuring Entity may require Bidders to state the portion of
their price representing local cost in Malawia Kwacha, if so indicated in the BDS.
16.1 Bidders shall submit one original technical proposal and one original financial proposal
and the number of copies of each indicated in the BDS. Each proposal shall be in a
separate envelope indicating original or copy, as appropriate. All technical proposals shall
be placed in an envelope clearly marked “Technical Proposal,” and the financial
proposals in one marked “Financial Proposal.” The envelope containing the financial
proposal shall also bear a warning “DO NOT OPEN WITH THE TECHNICAL
PROPOSAL”. These two envelopes, in turn, shall be sealed in an outer envelope
bearing the address and information indicated in the BDS. The envelope shall be clearly
marked: “DO NOT OPEN, EXCEPT IN PRESENCE OF THE INTERNAL
PROCUREMENT COMMITTEE.”
16.2 In the event of any discrepancy between the copies of the proposals, the original shall
govern. The original and each copy of the technical and financial proposal shall be
prepared in indelible ink and shall be signed by the authorized Supplier’s representative.
The representative’s authorization shall be confirmed by a written power of attorney
accompanying the proposals, unless otherwise indicated in the BDS. All pages of the
technical proposal shall be initialed by the person or persons signing the proposal.
16.3 The proposal shall contain no interlineation or overwriting except as necessary to correct
errors made by the Bidders themselves. Any such corrections shall be initialed by the
person or persons signing the proposal.
16.4 The completed technical and financial proposals shall be delivered on or before the time
and date stated in the BDS to the address indicated in ITB Sub-Clause 16.1. The
Procuring Entity shall not consider any proposal that arrives after the deadline for
submission of proposal. Any proposal received by the Procuring Entity after the
deadline for submission of proposals shall be declared late, rejected, and returned
unopened to the Bidder.
17.1 The proposals shall be valid for the number of days stated in the BDS from the date of the
deadline for submission. During this period, Bidders shall keep available the professional
staff proposed for the assignment. The Procuring Entity shall make its best effort to
complete negotiations within this period.
13
Part 1 - Section 1 Instructions to Bidders
18.1 A Bidder may withdraw, substitute, or modify its proposal after it has been submitted by
sending a written notice, duly signed by an authorized representative, and shall include
a copy of the authorization in accordance with ITB Sub-Clause 16.2. The corresponding
substitution or modification of the proposal must accompany the respective written
notice. All notices must be:
(a) Submitted in accordance with ITB Clause 16 (except that withdrawals notices do not
require copies), and in addition, the respective envelopes shall be clearly marked
“Withdrawal,” “Substitution,” or “Modification;” and
(b) Received by the Procuring Entity prior to the deadline prescribed for submission of
proposals, in accordance with ITB Sub-Clause 16.5.
18.2 Proposals requested to be withdrawn in accordance with ITB Sub-Clause 18.1 shall be
returned unopened to the Bidders.
18.3 No proposal may be withdrawn, substituted, or modified in the interval between the
deadline for submission of proposals and expiry of the period of proposal validity
specified by the Bidder on the Technical Proposal Submission Sheet or any extension
thereof.
19.1 The Procuring Entity shall conduct the proposal opening in the presence of Bidders’
designated representatives who choose to attend, and at the address, date and time
specified in the BDS.
19.2 First, envelopes marked “WITHDRAWAL” shall be opened and read out and the
envelope with the corresponding proposal shall not be opened, but returned to the
Bidder. Next, envelopes marked “SUBSTITUTION” shall be opened and read out and
exchanged with the corresponding proposal being substituted, and the substituted
proposal shall not be opened, but returned to the Bidder. Envelopes marked
“MODIFICATION” shall be opened and read out with the corresponding proposal. No
proposal withdrawal, substitution or modification shall be permitted unless the
corresponding notice contains a valid authorization to request the withdrawal,
substitution or modification and is read out at proposal opening. Only envelopes that
are opened and read out at proposal opening shall be considered further.
19.3 All other outer envelopes shall be opened one at a time, the technical proposals within
them opened, reading out: the name of the Bidder and any other details as the
Procuring Entity may consider appropriate.
19.4 No proposal shall be rejected at proposal opening except for late proposals, in
accordance with ITB Sub-Clause 16.4. Only proposals that are opened and read out at
the proposal opening shall be considered further.
19.5 The financial proposals shall remain sealed until the time and date notified for the
opening of the financial proposals. Evaluators of technical proposals shall have no
access to the financial proposals until the technical evaluation is concluded and the
result established.
19.6 The Procuring Entity shall prepare a record of the proposal opening that shall include,
14
Part 1 - Section 1 Instructions to Bidders
as a minimum: the name of the Bidder and whether there is a withdrawal, substitution,
or modification. The Bidders’ representatives who are present shall be requested to
sign the record. The omission of a Bidder’s signature on the record shall not invalidate
the contents and effect of the record. A copy of the record shall be distributed to all
Bidders, who formally request a copy.
E. Evaluation of Proposals
20. Confidentiality
20.1 Information relating to the examination, evaluation and comparison of proposals, and
recommendation for contract award, shall not be disclosed to Bidders or any other
persons not officially concerned with such process until information on Contract award
is communicated to all Bidders.
20.2 Any effort by a Bidder to influence the Procuring Entity in the examination, evaluation
and comparison of the proposals or Contract award decisions shall result in the
rejection of its proposal.
21.1 To assist in the examination, evaluation and comparison of the proposals, the Procuring
Entity may, at its discretion, ask any Bidder for a clarification of its proposal. Any
clarification submitted by a Bidder in respect to its proposal, that is not in response to a
request by the Procuring Entity, shall not be considered. The Procuring Entity’s request
for clarification and the response shall be in writing. No change in the prices or
substance of the proposal shall be sought, offered, or permitted, except to confirm the
correction of arithmetic errors discovered by the Procuring Entity in the financial
evaluation of the proposals, in accordance with ITB Clause 27.
23.1 Provided that a proposal is substantially responsive, the Procuring Entity may waive
15
Part 1 - Section 1 Instructions to Bidders
24.1 The Procuring Entity shall examine the proposals to confirm that:
(a) the Bidder meets the eligibility criteria defined in ITB Clause 3;
(b) the proposal has been properly signed;
(c) all documents and information requested in ITB Clause 13 have been provided; and
(d) the proposal is substantially responsive to the requirements of the RFP document.
24.2 The Procuring Entity shall confirm that the following documents and information have
been provided:
(a) Technical Proposal Submission Sheet, including a brief description of the services
offered and the proposal validity period;
(b) Separately sealed financial proposal;
(c) Written confirmation of authorization to commit the Bidder;
(d) Any other documentation as may be required by the Procuring Entity
24.3 If the proposal fails to meet the criteria specified in ITB Sub-Clause 24.1, it shall be
rejected.
25.1 The Procuring Entity shall technically evaluate the proposals on the basis of the
Bidder’s responsiveness to the Terms of Reference, applying the evaluation criteria,
sub-criteria and maximum points specified in Section 3. Each responsive proposal will
be given a technical score. A proposal shall be rejected at this stage if it does not
respond to important aspects of the Terms of Reference or if it fails to achieve any
minimum technical score indicated in Section 3.
25.2 The proposals proceeding to the financial evaluation shall be determined in accordance
with the methodology and criteria specified in Section 3.
26.1 After the technical evaluation is completed, the Procuring Entity shall notify those
Bidders whose proposals will not pass to the financial evaluation, indicating that their
financial proposals will be returned unopened after completing the evaluation process.
The Procuring Entity shall simultaneously notify the Bidder(s) whose proposals will
proceed to the financial evaluation indicating the date and time set for opening the
financial proposal(s). The opening date shall not be sooner than one week after the
16
Part 1 - Section 1 Instructions to Bidders
27.1 The Procuring Entity shall financially evaluate each proposal that has been opened as
stated in ITB Clauses 26.1 and 26.2 above.
27.2 The Procuring Entity will determine whether the financial proposals are complete. In the
case of lump sum contracts, activities and items described in the Technical Proposal but
not priced, shall be assumed to be included in the prices of other activities or items.
27.3 The Procuring Entity will correct any arithmetical errors on the following basis:
(a) if there is a discrepancy between the unit price and the total price that is obtained
by multiplying the unit price and quantity, the unit price shall prevail and the total
price shall be corrected, unless in the opinion of the Procuring Entity there is an
obvious misplacement of the decimal point in the unit price, in which case the
total price as quoted shall govern and the unit price shall be corrected;
(b) if there is an error in a total corresponding to the addition or subtraction of
subtotals, the subtotals shall prevail and the total shall be corrected; and
(c) if there is a discrepancy between words and figures, the amount in words shall
prevail, unless the amount expressed in words is related to an arithmetic error, in
which case the amount in figures shall prevail subject to (a) and (b) above.
If the Bidder that submitted the best evaluated proposal does not accept the correction of
errors, its proposal shall be disqualified.
27.4 Where an activity or line item is quantified in the Financial Proposal differently from the
Technical Proposal no corrections shall be applied to the Financial Proposal in this
respect.
27.5 The Procuring Entity shall convert all proposal prices expressed in various currencies
into the single currency specified in the BDS, using the official selling exchange rate
established by the source 14 calendar days prior to the date of submission of the
proposals, as specified in the BDS.
27.6 The evaluation shall include those taxes, duties, fees, levies, and other charges
imposed under the applicable law; and to be applied to foreign and non-permanent
resident consultants (and to be paid under the contract, unless the consultant is
exempted), and estimated in accordance with ITB Sub-Clause. 14.3, unless otherwise
indicated in the BDS.
28.1 The Procuring Entity shall compare all substantially responsive proposals to determine
the best evaluated proposal, in accordance with the methodology specified in Section 3,
17
Part 1 - Section 1 Instructions to Bidders
Evaluation Criteria.
29. Negotiations
29.1 Prior to the expiry of proposal validity, the Procuring Entity shall notify the successful
bidder in writing and invite it to negotiate the Contract at the location indicated in the BDS.
29.2 The aim is to reach agreement on all points and initial a draft contract by the conclusion of
negotiations.
29.3 Negotiations shall commence with a discussion of the technical proposal, including the
proposed methodology, work plan, staffing and any suggestions to improve the TOR.
Agreement shall then be reached on the final TOR, the staffing, and the staffing and work
schedules, which shall indicate activities, staff, periods in the field and in the home office,
staff months, logistics and reporting. Special attention shall be paid to optimizing the
required outputs from the Supplier within the available budget and to defining clearly the
inputs required from the Procuring Entity to ensure satisfactory implementation of the
Assignment.
29.4 Changes agreed upon shall then be reflected in the financial proposal, using proposed unit
rates. The fee rates will not be subject to negotiation, except in the case of Quality Based
Selection.
29.5 Having selected the lowest evaluated proposal on the basis of, among other things, an
evaluation of proposed key professional staff, the Procuring Entity expects to negotiate a
contract on the basis of the staff named in the proposal. Prior to contract negotiations, the
Procuring Entity shall require assurances that the staff members will be actually available.
The Procuring Entity shall not consider substitutions during contract negotiations except in
cases of unexpected delays in the starting date or incapacity of key professional staff for
reasons of health.
29.6 The negotiations shall be concluded with a review of the draft form of the contract. The
Procuring Entity and the Bidder shall finalise the contract to conclude negotiations. If
negotiations fail, the Procuring Entity shall invite the next ranked Bidder to Contract
negotiations.
F. Award of Contract
30. Award of Contract
30.1 The Procuring Entity shall award the Contract to the Bidder whose proposal has been
determined to be the best evaluated proposal and is substantially responsive to the
Request for Proposals, subject to satisfactory negotiations and provided that such
Bidder has been determined to be eligible in accordance with the provisions of Clause
3.
30.2 Notwithstanding ITB Sub-Clause 30.1, the Procuring Entity reserves the right to accept
or reject any proposal, and to cancel the procurement process and reject all proposals,
at any time prior to the award of Contract, without thereby incurring any liability to the
affected Bidder or bidders or any obligation to inform the affected Bidder or bidders of
the grounds for the Procuring Entity’s action.
30.3 The Bidder whose proposal has been accepted will be notified of the award in writing by
18
Part 1 - Section 1 Instructions to Bidders
the Procuring Entity prior to expiration of the proposal validity period. Following contract
award, the Procuring Entity shall promptly inform the other Bidders that their proposals
have not been selected.
30.4 The Procuring Entity shall publish in the Malawi Government Gazette the results of the
award of contract, as required by the Public Procurement and Disposal of Public Assets
Act 2017.
19
20
Instructions
to Bidders
Data relevant to ITB
(ITB)
reference
A. General
The assignment is: Consultancy Services for the Feasibility Study and
ITB 2.1
Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-
N eno-Mwanza
Road
ITB 7.1 For clarification purposes only, the Procuring Entity’s address is:
Roads Authority
Functional Building
Lilongwe 3
E-mail: [email protected]
C. Preparation of Proposals
Part I - Section 2 Bid Data Sheet
Instructions
to Bidders
Data relevant to ITB
(ITB)
reference
Date:
Venue:
ITB 11.2 International Bidders shall be required to meet the following National
Construction Industry Council (NCIC) regulations:
a. Practice of Construction Services by Foreign Consulting
Firms Regulations 2004.
b. Subcontracting and Joint Ventures by Foreign and Malawian
Construction Firms order 2014.
ITB 13.1 (i) The technical proposal shall include the following additional information:
ITB 14.1 (e) The financial proposal shall include the following additional information:
ITB 14.3 The total proposal price shall be broken down into separate activities.
ITB 15.1 All bid rates and amounts shall be in Malawi Kwacha
ITB 16.1 In addition to the original of the proposal, the number of copies is: Four (4)
22
Part I - Section 2 Bid Data Sheet
Instructions
to Bidders
Data relevant to ITB
(ITB)
reference
Roads Authority
Functional Building
Lilongwe 3, MALAWI
In addition to the address, the outer envelope shall bear the following
information:
ITB 17.1 The proposal validity period shall be One Hundred and Twenty (120)
days.
ITB 19.1 For proposal opening purposes only, the Procuring Entity’s address is:
Roads Authority
Functional Building
23
Part I - Section 2 Bid Data Sheet
Instructions
to Bidders
Data relevant to ITB
(ITB)
reference
Private Bag B346
Lilongwe 3, MALAWI
E. Evaluation of Proposals
ITB 27.5 The currency that shall be used for proposal evaluation and comparison
purposes to convert all proposal prices expressed in various currencies
into a single currency is: Not applicable
ITB 27.6 The evaluation shall include all taxes, duties, fees, levies and other
charges.
ITB 29.1 For negotiations purposes only, the Procuring Entity’s address is:
Roads Authority
Functional Building
Lilongwe 3, MALAWI
24
Part I - Section 3 Evaluation Criteria
19
Part I - Section 3 Evaluation Criteria
This section, read in conjunction with Section 1, Instructions to Bidders and Section 2, Bid
Data Sheet, contains all the factors, methods and criteria that the Procuring Entity shall use
to evaluate a proposal and determine the best evaluated proposal
20
Part I - Section 3 Evaluation Criteria
21
Part I - Section 3 Evaluation Criteria
22
Part I - Section 3 Bid Data Sheet 23
Criteria Maximum
Points
(a) Specific experience of the bidder related to the assignment (A 10
Minimum of five (5) projects of similar nature and complexity)
(b) Adequacy of the proposed work plan and methodology 25
(c) Qualifications and competence of the key staff for the Assignment 60
Criteria, sub-criteria, and point system for the evaluation of the Full Technical Proposals:Points
(i) Specific experience of the Consultant (as a firm) relevant to the Assignment: 10
(ii) Adequacy and quality of the proposed methodology, and work plan in
responding to the Terms of Reference (TORs): 25
a) Technical approach and methodology 12
b) Work plan 8
d) K-4: Hydrologist 6
General Qualifications 1.8
The number of points to be given under each evaluation sub-criteria for (c) qualifications and
competence of the key staff for the assignment are:
Criteria Maximum
24
Part I - Section 3 Evaluation Criteria
Points
(a) General qualifications 30
(b) Adequacy for the assignment (The maximum points of 60 to be split as follows: 60
Number of years in the specific field (maximum of 30 points) and number of
projects carried out during the period (maximum of 30 points)
(c) Experience in the region and language 10
To determine financial scores for each proposal, the lowest priced proposal shall be given a
financial score of 100, and other proposals shall be given a score proportionate to this, by
application of the following formula:
A total score (S) will be determined for each proposal, by combining its technical (St) and
financial (Sf) scores using the following formula and weightings:
Proposals will be ranked and the proposal achieving the highest total score will be
recommended for contract award, subject to satisfactory negotiations.
25
Part I - Section 4 Bidding Forms 26
List of Forms
25
Part I - Section 4 Bidding Forms
Note to Bidders: This Technical Proposal Submission Sheet should be on the letterhead of
the Bidder and should be signed by a person with the proper authority to sign documents
that are binding on the Bidder. It should be included by the Bidder in its technical proposal.
Name Address
26
Part I - Section 4 Bidding Forms
(j) Our Proposal is binding upon us, subject to modifications agreed during any contract
negotiations, and we undertake to negotiate on the basis of the staff proposed in our
proposal;
(k) We understand that this proposal, together with your written acceptance thereof, shall
constitute a binding contract between us, until a formal contract is prepared and
executed;
(l) We understand that you are not bound to accept any proposal that you may receive;
Name: [insert complete name of person signing the proposal]
In the capacity of [insert legal capacity of person signing the proposal]
Signed: [signature of person whose name and capacity are shown above]
Duly authorised to sign the proposal for and on behalf of: [insert complete name of Bidder]
Dated on ____________ day of __________________, _______ [insert date of signing]
27
Part I - Section 4 Bidding Forms
Note to Bidders: The information requested is required in the format provided below and
should be included by the Bidder in its technical proposal.
Bidder’s Experience
[Using the format below, provide information on relevant assignments carried out in
the last five years which best illustrate your experience, where your firm/entity (and
each associate for the assignment) provided services similar to the ones requested
under this assignment. Please provide the name and contact details of the officer
responsible for management by the client for each assignment.]
Names of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions
performed:
1
The minimum staff months to meet the minimum criteria shall be the staff months stated in ITB 12.1
28
Part I - Section 4 Bidding Forms
Bidder’s Name:
Note: A completion certificate from the Client is required to back up each completed service,
or a notice of acceptance letter and latest Invoice from Client for Services in progress above
70% completion.
Note to Bidders: The information requested is required in the format provided below and
should be included by the Bidder in its technical proposal. If none, include form and state
”None”.
29
Part I - Section 4 Bidding Forms
Note to Bidders: The information requested is required in the format provided below and
should be included by the Bidder in its technical proposal.
a) Technical Approach and Methodology. In this chapter you should explain your
understanding of the objectives of the assignment, approach to the services,
methodology for carrying out the activities and obtaining the expected output, and the
degree of detail of such output. You should highlight the problems being addressed
and their importance, and explain the technical approach you would adopt to address
them. You should also explain the methodologies you propose to adopt and highlight
the compatibility of those methodologies with the proposed approach.
b) Work Plan. In this chapter you should propose the main activities of the
assignment, their content and duration, phasing and interrelations, milestones
(including interim approvals by the Procuring Entity), and delivery dates of the
reports. The proposed work plan should be consistent with the technical approach
and methodology, showing understanding of the TOR and ability to translate them
into a feasible working plan. A list of the final documents, including reports, drawings,
and tables to be delivered as final output, should be included here. The work plan
should be consistent with the Work Schedule of Form T8.
c) Organisation and Staffing. In this chapter you should propose the structure and
composition of your team. You should list the main disciplines of the assignment, the
key expert responsible, and proposed technical and support staff.]
It is recommended that the approach, methodology and work plan, inclusive of charts
and diagrams, should be no more than 50 pages.]
30
Part I - Section 4 Bidding Forms
Note to Bidders: The information requested is required in the format provided below and should be included by the Bidder in its technical
proposal.
31
Part I - Section 4 Bidding Forms
Note to Bidders: The information requested is required in the format provided below for each
named member of professional staff and should be included by the Bidder in its technical
proposal.
3. Name of Staff:
4. Date of Birth: Nationality:
5. Education: [indicate college/university and other specialised education, giving names of
institutions, degrees obtained and dates of obtained][*Include copies of all certificates mentioned in
the Curriculum Vitae]
7. Other Training: [indicate other significant training not included under Education]
8. Countries of Work Experience: [list countries of work experience in the last ten years]
9. Languages: [indicate proficiency in each language as good, fair or poor for speaking, reading
and writing]
10. Employment Record: [starting with present position, list every employment held since
graduation, stating dates of employment, employing organisation and positions held]
From: [year] _______ To: [year]
Employer:
Positions held:
27
32
Part I - Section 4 Bidding Forms
13. Certification:
I, the undersigned, certify that to the best of my knowledge and belief, this CV correctly
describes myself, my qualifications, and my experience. I understand that any wilful
misstatement described herein may lead to my disqualification or dismissal, if engaged.
___________________________________________ Date:
33
Part I - Section 4 Bidding Forms
34
Part I - Section 4 Bidding Forms
I, the undersigned, hereby declare that I agree to participate exclusively with the tenderer
<tenderer name> in the above-mentioned service tender procedure. I further declare that I
am able and willing to work for the period(s) foreseen for the position for which my CV has
been included in the event that this tender is successful, namely:
From To
< start of period 1 > < end of period 1 >
< start of period 2 > < end of period 2 >
< etc >
I confirm that I am not engaged in another RA-funded project in a position for which my
services are required during the above periods.
Furthermore, should this tender be successful, I am fully aware that if I am not available at
the expected start date of my services for reasons other than ill-health or force majeure, I
may be subject to exclusion from other tender procedures and contracts funded by the RA
and that the notification of award of contract to the tenderer may be rendered null and void.
Name
Signature
Date
2
To be completed by all key experts
35
Part I - Section 4 Bidding Forms
Note to Bidders: The information requested is required in the format provided below and should be included by the Bidder in its technical
proposal.
Staff input should be counted from the start date of the assignment and indicated in weeks or months, as appropriate. Professional staff should
be indicated individually by name; support staff should be indicated by category e.g. clerical staff. Input should be indicated separately for input
at home and in the field and for foreign and national staff, for the purpose of calculating travel, subsistence etc.
T7 Staffing Schedule
Totals
36
Part I - Section 4 Bidding Forms
Part-time input
Note to Bidders: The information requested is required in the format provided below and should be included by the Bidder in its technical
proposal.
Indicate all main activities of the assignment, including milestones such as submission of reports and other deliverables. For phased
assignments, indicate activities separately for each phase.
T8 Work Schedule
37
Part I - Section 4 Bidding Forms
Note to Bidders: This Financial Proposal Submission Sheet should be on the letterhead of
the Bidder and should be signed by a person with the proper authority to sign documents
that are binding on the Bidder. It should be included by the Bidder in its financial proposal.
Date: [insert date (as day, month and year) of proposal submission]
Procurement Reference No: [insert Procurement Reference number]
To: [insert complete name of Procuring Entity]
We, the undersigned, declare that:
(a) We offer to provide the consulting services for [insert a brief description of the
Services]in conformity with your Request for Proposals and our technical and financial
proposals;
(b) The total price of our proposal is: [insert the total proposal price in words and
figures, indicating the various amounts and the respective currencies], inclusive of
local taxes [amend if local taxes are not required to be included];
(c) Our proposal shall be valid for a period of [specify the number of calendar days] days
from the date fixed for the proposal submission deadline in accordance with the Request
for Proposals, and it shall remain binding upon us, subject to any modifications resulting
from negotiations, and may be accepted at any time before the expiration of that period;
(d) The following commissions, gratuities, or fees have been paid or are to be paid with
respect to the bidding process or execution of the Contract: [insert complete name of
each Recipient, its full address, the reason for which each commission or gratuity
was paid and the amount and currency of each such commission or gratuity. If
none has been paid or is to be paid, indicate “none”];
(e) We understand that you are not bound to accept any proposal that you receive;
Name: [insert complete name of person signing the proposal]
In the capacity of [insert legal capacity of person signing the proposal]
Signed: [signature of person whose name and capacity are shown above]
Duly authorised to sign the proposal for and on behalf of: [insert complete name of Bidder]
Dated on ____________ day of __________________, _______ [insert date of signing]
38
Part I-Section 4 Bidding Forms 39
Note to Bidders: If BDS 14.3 requires the proposal price to be quoted separately for different Activities, complete this form as a “Summary of
Activity Price” for each activity and complete one overall Summary of Proposal Price.
State the currencies under (currency 1), (currency 2) etc. Delete unused columns.
For lump sum contracts, this financial information will be used as a breakdown of contract price in Appendix C of the contract. For unit price
contracts, this financial information will be used as the breakdown of cost estimates in Appendix C of the contract.
1 Fees
2 Direct Costs
6 VAT on Fees
Total
Part I - Section 4 Bidding Forms
40
Part I - Section 4 Bidding Forms
Note to Bidders:. Complete this form for the total proposal or for each activity as indicated in the ITB.
The Bidder should complete a separate form for each currency or add currency columns and show up to three totals. Where required, enter
separate rates for home and field work.
F3 Summary of Fees
State activity name or total proposal:__________________________ Currency:_________
Total
41
Part I - Section 4 Bidding Forms
42
Part I - Section 4 Bidding Forms
Note to Bidders: Bidders may reproduce this form in landscape format, but are responsible for its accurate reproduction. The Bidder should
complete a separate form for each currency or add currency column and show up to three totals. Complete this form for the total proposal or for
each activity as appropriate.
Total
Notes Local transportation costs are not to be included if local transportation is being made available by the Procuring Entity. Similarly, the
project site, office rent/accommodations/clerical assistance costs are not to be included if being made available by the Procuring Entity.
All other costs related to the study not specifically provided for in the financial proposal shall be deemed to have been included in the
other rates.
43
Section 5 Eligible Countries 44
Terms of Reference
Terms of Reference
Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-
Tsangano-Neno-Mwanza Road (S135/T396/T397)
1.0 Background
The policy of the Government of Malawi (GoM) towards the roads sub-sector is to
build, maintain and ensure efficient utilization of the road infrastructure and other
services appropriate to meet the current and future development needs of the
economy. This includes helping the people in the rural areas to gain access to income
generating activities, such as agricultural activities and to social services such as
hospitals, schools etc. by providing reliable and durable roads; thus facilitating the
continued development of the country’s rural areas through increased agricultural
production, the mainstay of the country’s economy.
The Roads Authority intends to apply part of the resources Roads Fund to finance
the Feasibility Study and Detailed Engineering Design for the upgrading of the
Ntcheu-Tsangano-Neno-Mwanza Road (S135/T396/T397) to bitumen standard.
Consultancy services are therefore required to carry out an economic and
environmental feasibility study, social impact assessment, detailed engineering
design and preparation of bidding documents for the upgrading works.
The Ntcheu – Tsangano – Neno – Mwanza Road, is 140 Km long, of which 8.4 Km is
paved and the rest is an earth surface road. The road is in southern part of Malawi and
runs along the south-western border with Mozambique.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
46
Part 2 - Section 6 Terms of Reference
The road traverses through the Rift Valley Scarp Zone linking the Central and
Southern Regions of Malawi and is characterized by hills and mountainous terrain with
very steep slopes. The major crossing is at Lisungwi river.
The road passes not only through medium densely populated villages but also through
some of the fertile areas in the country not open to habitation due to problems of
access during the rainy season on account of slippery road condition.
(i) Investigate and determine the technical and economic feasibility, and the
environmental and social impacts of upgrading the remaining 140 Km of the
Ntcheu-Tsangano-Neno-Mwanza earth road to an all-weather bitumen paved
road.
(ii) Prepare detailed engineering designs based on the findings of the feasibility
study as well as of the preliminary design and to prepare tender documentation
for the upgrading works (national competitive bidding).
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
47
Part 2 - Section 6 Terms of Reference
The services are expected to be performed in line with the Guidelines and Checklists
for this monitoring of Road Design Projects (GCMRDP). In addition the design shall
adopt the principle of ‘Building Back Better’ with respect to climate resilience.in this
respect, the consultant is expected to use the Malawi Guidelines for the Road Sector to
increase its Resilience to the Effects of Climate Change.
The feasibility study shall investigate the economic and social viability for the
upgrading of the existing earth road between Ntcheu-Tsangano-Neno-Mwanza
(S135/T396/T397) roads to Bitumen Surfaced Standard. The Feasibility Study
shall comprise an Economic Feasibility Study, Environmental and Social
Impacts Assessment Study together with Preliminary Engineering Design. The
consultant will also be required to make recommendations of the most viable
option in terms of cost and environmental/social considerations.
The Consultant shall carry out manual classified traffic counts for a
period of seven consecutive days on a minimum of 2 counting stations.
The counts are to include non-motorized traffic and are to be conducted
over an 18-hour period, 04:00-22:00 hours and must include at least
one 24-hour weekday count and one 24-hour weekend count for
purposes of estimating night traffic.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
48
Part 2 - Section 6 Terms of Reference
The consultant shall also count the different traffic vehicle categories for
calculation of the equivalent axle loads.
The counts shall be carried out using the format as per traffic count
form attached as Annex 1.
i. Time
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
49
Part 2 - Section 6 Terms of Reference
Workplaces
Markets
Traffic forecast shall be prepared for a 15/20 year period following opening
of the upgraded road to traffic.
The consultant shall estimate the nature and volume of traffic forecast to
use on the road by analyzing traffic counts, origin-destination studies and
the present volume of freight and passenger movements on the road
under study. The Consultant shall also identify, describe and quantify
existing and potential diverted and generated traffic. On the diverted and
generated traffic, it will be extremely important to consider trends on
recently upgraded roads as this will give a more realistic estimation of such
traffic once the road is opened.
The traffic forecast shall be given at three growth rates namely: low,
medium and high. The consultant shall use these three growth rates in
obtaining the economic internal rate of return (EIRR) of the project. The
consultant shall give his estimate of probability of occurrence of projected
growth rates and his rationale for the probabilities selected.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
50
Part 2 - Section 6 Terms of Reference
ii. The consultant shall identify and quantify Benefits using HDM-4 over
the analysis period. Benefits categories shall include key items
classified under road user effects in the HDM-4 terminology:
VOC savings
iii. It is important to note that the economic analysis shall include the
following cost items:
Construction
Supervision
Maintenance
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
51
Part 2 - Section 6 Terms of Reference
iv. The Consultant shall calculate the NPV, IRR and First Year Rate of
Return including:
VOC savings
v. The consultant shall carry out sensitivity tests for NPV and IRR with
reference to:
The Consultant shall promptly initiate and carry out the surveys of the
project road. Surveys shall use the UTM co-ordinate system and the
ARC-1950 datum consistent with Malawi topographic mapping System.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
52
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
53
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
54
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
55
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
56
Part 2 - Section 6 Terms of Reference
a) Grading
b) Atterbergs Limits;
a) Grading;
b) Atterbergs Limits
e) Bitumen Affinity
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
57
Part 2 - Section 6 Terms of Reference
The catchment areas, run-off factors and design discharge flows shall
be determined for each drainage structure and the corresponding
maximum water level established which shall be the basis for
determining the finished road level (after taking into consideration the
allowable free board and the bridge deck configuration. The flood
return period(s) utilized for the design of culverts and other drainage
structures shall be selected from an engineering and economic
analysis to determine the optimum period for the road and type of
structure from hydrographic data pertinent to the topography and
terrain through which the road is located.
The hydrological and hydraulic analysis shall also take into account
issues of climate resilience by among other issues checking the
sensitivity of the proposed drainage structures to higher flood return
periods than those specified in the design manual.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
58
Part 2 - Section 6 Terms of Reference
The consultant shall determine the design approach for the road (i.e. either
conventional design or LVSR design) based on the estimated design traffic.
This entails that traffic studies shall precede all activities. The recommended
design approach shall be submitted to the client for approval.
The Consultant shall carry out a preliminary design of the road project in
accordance with the relevant design guideline (SATCC Draft Code of Practice
for the Geometric Design of Trunk Roads September 1998 and the pavement
design has to be in line with the SATCC Code of Practice for the Pavement
Design.
The consultant shall, based upon the results of the traffic studies and
projections and the preliminary engineering investigations, discuss and
recommend alternative design options, ascertain the merits and
demerits of each option, evaluate each in terms of the total transport
costs, compare them and select appropriate design standards for the
preferred road as follows:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
59
Part 2 - Section 6 Terms of Reference
side slopes, ditch profile etc. to suit all situations. The cross section shall
have concrete edge beams thoughout the alignment.
A schedule and location of all proposed new road furniture shall also be
compiled.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
60
Part 2 - Section 6 Terms of Reference
The Consultant shall gather basic statistics on the number of road accidents,
the number of deaths, and number of injuries for each kilometre or section of
the route for each of the previous three years. This data will be included, along
with national statistics and trends on road accidents, as an appendix to the
feasibility report. The feasibility report shall include a section on road safety,
indicating typical current problems along the existing route and outlining what
will be done within the project to enhance road safety. If alternative alignments
and standards are considered, the evaluation must cover the road safety
aspects.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
61
Part 2 - Section 6 Terms of Reference
(i) The Consultant shall confirm the computation and definition of the
geometric characteristic of the road along the centerline. Setting out
data shall also be given for points at regular intervals along curves and
the longer tangent alignments. Vertical alignment is to be checked and
defined.
(ii) The construction drawings will clearly define all the relevant setting out
details for all the various elements of the work.
(i) At bridge sites and or other major structures, sub surface conditions shall
be investigated by trenching, hand augering and/or drilling as required
including taking of undisturbed samples and standard penetrometer
tests.
The Consultant shall further detail the preliminary horizontal and vertical
alignment for the upgraded road sections to ensure its compliance with the
standards as stipulated in the SATCC Draft Code of Practice for the Geometric
Design of Trunk Roads. The basis of the detailed geometric design shall be the
agreed preferred route during the preparation of the preliminary engineering
design.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
62
Part 2 - Section 6 Terms of Reference
The optimum pavement design for the new road, in particular under
consideration of availability of construction materials shall be confirmed after
discussions with the Client. For that purpose he consultant shall review the
traffic data collected with regards to traffic composition, occupancy and volume
counts. Forecasts for a life span of 15/20 years (whichever is appropriate) shall
include traffic of normal, generated, diverted traffic as well as future traffic
growth. The traffic forecast shall be given at three growth rates, namely: low;
medium and high. The correct assumptions for the growth rates are extremely
crucial for the pavement design and have to be discussed with the client. The
Consultant shall then use these three accepted growth rates in obtaining the
cumulative equivalent standard axles (ESAs) for the three scenarios. For that
discussion the pavement design shall be verified by comparison with at least
two other internationally accepted methods in order to produce an optimum
design for the project.
All existing data and the results of the field investigation for soils, foundations,
hydrology etc. shall be analyzed and used as the basis for the design of
drainage structures, which shall be supported by detailed hydraulic
computations and foundation designs.
The Consultant shall verify and develop the preliminary designs for bridge and
drainage structures and produce detailed designs in accordance with the draft
Bridge Design Specifications, November 1988, of the Ministry of Works and
Supplies in conjunction with the provisions of BS 5400: Steel, Concrete and
Composite Bridges, Parts 1, 2, 3,4,5,9 and 10 as appropriate and as amended
by the provisions of the relevant UK Department of Transport Memoranda.
Specifications and recommendations for materials and workmanship are given
in Parts 6, 7, 8 and 9.2 of BS 5400. These parts should be read in conjunction
with the SATCC Standard Specifications for Roads and Bridge Works.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
63
Part 2 - Section 6 Terms of Reference
guidance shall be taken from the SATTC Draft Code of Practice for the
Design of Road Bridges and Culverts September 1998. Sections of BS 5400
Part 2 to which this paragraph particularly applies are as follows:
5.4 Temperature
a. Accidents Statistics
The consultant shall make contact with the Department of Road Traffic and
Safety Services and Malawi Police Stations along the project road to obtain
from them such accident statistics as may exist for the project road as well as
details of the main causative factors in accidents and the locations of known
accident black spots. Particular attention should be paid to accidents and
black spots involving non-motorized transport and pedestrians.
The Road Safety Audit shall consider aspects such as inferior road geometry,
poor sight distances, inadequate junctions or provisions for turning, slow
moving traffic, informal trading and in particular any history of accident or
known black spots.
The Consultant shall update the economic assessment prepared under Phase
1, taking into account the latest traffic data and the final estimated construction
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
64
Part 2 - Section 6 Terms of Reference
cost of the detailed design for the project. In the event of the interval between
Phase 1 and Phase 2 of the services being greater than nine months, the traffic
counts referred to earlier shall be repeated.
A bar chart showing the proposed sequencing and duration of the major
activities for the entire construction period.
In preparing this programme, the Consultant shall take into account the climatic
conditions prevailing in the areas concerned.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
65
Part 2 - Section 6 Terms of Reference
The Client will be responsible for all costs which will be incurred
by the graduate engineers during the mentoring period such as
transport and accommodation.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
66
Part 2 - Section 6 Terms of Reference
The client shall identify the area of interest for training and shall
determine the number of staff to be trained.
The Consultant shall provide sufficient resources to carry-out all the services
required under this assignment phase and the input together with minimum
requirements for the key professional staff are as indicated below. All the key
professional staff should have graduate/first degrees as a minimum
qualification. The Consultant will be required to apportion the key professionals’
contingent and inputs to the technical proposal.
Man
Item DESCRIPTION
Month
1 12
TEAM LEADER/ HIGHWAY DESIGN ENGINEER
STRUCTURAL ENGINEER
3
6
4 3
HYDROLOGIST
5 4
CONTRACT DOCUMENT SPECIALIST
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
67
Part 2 - Section 6 Terms of Reference
TRANSPORT ECONOMIST
6
4
ENGINEERING SURVEYOR
8
5
The Consultant's personnel, nominated for this project, shall be suitably qualified and
experienced. As a guide, the following is an indication of the minimum level of training
and experience expected of the key members of the design team:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
68
Part 2 - Section 6 Terms of Reference
preparation of bidding document for road works, and should have undertaken at
least 6 feasibility study and detailed design projects as a Contract Document
Specialist.Demonstrable experience in the use of SATCC standards and
specifications as well as FIDIC Conditions of Contract.
(g) Environmental and Social Expert: with a Bsc. in Environmental Science and
Technology or its equivalent and must have 8 years of working experience, and
should have undertaken at least 5 feasibility study and detailed design projects
as an Environmental and Social Expert.
6.0 Timing
The Consultant shall draw up his own proposal for a time schedule, but shall make due
allowance for time required by the Authority to assess and approve documents submitted by
the Consultant, before subsequent project tasks can be commenced with. The following
schedule is to be used as a guide:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
69
Part 2 - Section 6 Terms of Reference
by RA
The feasibility study phase and the detailed engineering design phases are expected
to be completed not later than forty eight (48) Weeks, including time for comments and
approvals by the Roads Authority and other key stakeholders.
The Consultant shall prepare and submit the following reports and documents, in
English, in an approved format to the Client. The comments of the Client shall be
incorporated in the final version of the reports and documentation.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
70
Part 2 - Section 6 Terms of Reference
Ten (10) hard copies and one (1) soft copy of each of the reports/documents listed
below shall be sent to the Client.
In addition, thirteen (13) sets of the final bidding documents in hard copy and one set in
electronic copy, shall also be provided. Six sets of drawings shall be provided with A1
size drawings and thirteen (13) sets with A3 size drawings.
The Consultant shall submit a draft feasibility study report at the end of 24
weeks from the date of commencement of the study as outlined under Section
7. The following volumes have to be included:
The Draft Economic Feasibility Report should attempt to comment and discuss all
the elements of the entire Economic Feasibility study including the economic
calculations and analysis carried out and showing detailed results of the
economic feasibility under this stage, covering all the required elements
included under Section 4.1.2.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
71
Part 2 - Section 6 Terms of Reference
A draft Preliminary Engineering Design Report covering all the elements included
under Section 4.1. Shall be submitted the report shall include details of the
services carried out and the outcomes of the preliminary design with emphasis on
soils and material investigation results, preliminary designs and cost estimates.
The Report should attempt to comment and discuss all the elements of the entire
Preliminary Design study over and above the preliminary design issues and
processes.
The report shall include the findings of the preliminary designs and cost
estimates, planning requirements of the socio-economic and environment impact
assessments. It shall include an executive summary, summarizing all the findings
and recommendations. This report will be presented including survey data,
drawings, maps, plans and diagrams in A3 size to be included in the Final Report.
The draft Environmental and Social Impact Assessment Report shall be prepared
in accordance with Section 8 of the Guidelines for an Environmental Impact
Assessment of Proposed Road Works which are appended as Appendix No.1 to
these ToR. The report shall also include cost estimates and STD & HIV/AIDs and
other pandemic components. Ten copies of the report shall be submitted for
scrutiny to the Technical Council for the Environment of the Malawi Environment
Protection Authority (MEPA) for approval. This report shall be submitted together
with the draft feasibility study at the end of 24 Weeks from the commencement of
the services.
The draft full or abbreviated Resettlement Action Plan (RAP) shall be prepared in
accordance with Appendix 2 or 3 of these Terms of Reference whichever is
applicable. The RAP should address all typical issues as outlined under
Appendix 5 of these Terms of Reference. This report shall be submitted together
with the draft feasibility study at the end of 24 Weeks from the commencement of
the services.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
72
Part 2 - Section 6 Terms of Reference
After taking into account the Client’s comments on the draft feasibility study
report including the draft Economic Feasibility and Preliminary Design Report,
the Environmental and Social Impact Assessment Statement and the
Resettlement Action Plan, the Consultant shall prepare and submit the final
feasibility study report complete with plans and all documents. This report will be
presented including survey data, soils and material investigation results,
required drawings, maps, plans and diagrams in A3 size. This report shall be
submitted within 2 Weeks of receipt of the Clients comments
Under phase II of the assignment, the Consultant shall submit the following reports;
The consultant shall submit a draft detailed engineering design report including
soil and material investigation and pavement design report complete with cost
estimates and accompanied by a set of the draft bidding documents and all
drawings, maps, plans and diagrams in A1 size. For major structures, the
consultant will submit all the calculations for the design as an appendix to the
report. The bidding documents shall be in accordance with the latest version of
the Roads Authority standard bidding documents. This report has to be
submitted after 42 Weeks from the date of commencement of the study.
After approval of the draft detailed design report, the consultant shall submit
the final report with a set of bidding documents, acceptable to the Client and
the Financiers. The drawings that will form part of the bidding documents shall
be in A1 size as well as reduced to A3 size. Thirteen (13) sets of the final
bidding documents in hard copy and one set in electronic copy (in pdf and
editable format), shall be provided. Also six sets of drawings shall be provided
with A1 size drawings and thirteen (13) sets with A3 size drawings.
This report shall be submitted within 3 Weeks after receipt of the client’s
comments. The consultant will also be required to submit an electronic copy
(USB flash drive) of the Final Detailed Design Report and bidding documents.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
73
Part 2 - Section 6 Terms of Reference
The Client shall provide the consultant with all requested and available data.
The Client will also assist in the facilitation for the co-operation of other government
ministries and agencies, departments and other agencies as required for carrying out
the works and in liaison as necessary for the same purpose. The Client will give the
Consultant assistance to gain access to all information required for the proper conduct
and completion of the studies.
The consultant’s obligations shall include, but not be limited to the following:-
i. The Consultant shall employ well qualified and competent professional staff
at all times in the execution of this study.
ii. The Consultant shall make his own arrangements for all necessary office and
living accommodations, transportation, office and other supplies, computers,
computer software, survey equipment, engineering investigations, materials
testing, printing of reports and drawings etc. in connection with the services to
be provided. All costs have to be included in the Financial Proposal.
iii. Prior to commencement of the actual services, the Consultant shall formulate
a quality management system and procedures for implementation of these
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
74
Part 2 - Section 6 Terms of Reference
The services will be executed on a Lump Sum Contract basis and the payment
schedule shall be as follows: -
10% of the Contract Price shall be paid on submission and acceptance by the
client of the Inception Reports.
30% of the Contract Price shall be paid on submission and acceptance by the
client of the draft Economic Feasibility and Preliminary Design Reports.
10% of the Contract Price shall be paid on submission and acceptance by the
client of the Final Economic Feasibility and Preliminary Design Reports.
30% of the Contract Price shall be paid on submission and acceptance by the
client of the Draft Detailed Design Report.
20% of the Contract Price shall be paid on submission and acceptance by the
client of the Final Detailed Engineering Design Report.
Note: The consultant shall price the additional services under item 4.2.10 separately, and for
these services the payment schedule shall be as follows:
Fifty percent (50%) of the Mentoring Cost shall be paid on submission and
acceptance of the training report at Draft Feasibility study reporting stage.
The other 50% of the Cost shall be paid on submission and acceptance of the
training report at Draft Detailed Design reporting stage.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
75
Part 2 - Section 6 Terms of Reference
A provisional sum, where training is applicable, has been included in the financial
proposal against which all training expenses will be paid on submission of receipts.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
76
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
77
Part 2 - Section 6 Terms of Reference
Name of the Road (Start & End Description) Road No:_________ Date Day Weather GPS Reference
Link. No:
__________ Traffic Count
Survey Location dd / mm / yy Sunny Cloudy S
Station No:________
Zone: Special Feature: Rainy Foggy E
District Name :
Nearest Town ___________
______________ Any other Remarks:
_
Motorized Traffic
Non-Motorized Traffic
Passenger Vehicle Goods Vehicle
Landrovers, Three
Pickups Two Wheeler Mini-Bus Medium Bus Large Bus Light Truck, Medium Truck Heavy Truck Others
Landcruisers, Twin Cab Wheeler Semi-Trailer
Time/ Direction Tractor or Animal Remarks
(Motor ( >16 ≤50 Seats Trucks ≤ 3.0 (ST)/ Full Trailer
Saloon car 4 WD Tricycle (≤ 16 seats) ( >50 Seats ) ( 2-Axle ), ( 3-4 Axle ), Tractor & Bicycle Drawn /
Cycles) ) ton (FT) Count Axle
Trailer Hand Cart
Trucks > 3.0≤ 16 (5,6,…)
LOW BASE HIGH BASE Trucks > 16 tons
ton
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
e.g. Rain,
Market,
Time Dir. Accident,
Procession,
etc
_________
___ To
04 - 05
_________
__ To
_________
____ To
05 - 06
_________
____ To
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
78
Part 2 - Section 6 Terms of Reference
_________
____ To
06 - 07
_________
____ To
_________
____ To
07 - 08
_________
____ To
_________
____ To
08 - 09
_________
____ To
_________
____ To
09 - 10
_________
____ To
_________
____ To
10 - 11
_________
____ To
_________
____ To
11 - 12
_________
____ To
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
79
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
80
Part 2 - Section 6 Terms of Reference
Annex 2 - OD Survey
Date:
Interviewer: To:
CODES
VEHICLE TYPE TRIP PURPOSE LOAD TYPE VEHICLE LOADING ROAD CONDITION
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
81
Part 2 - Section 6 Terms of Reference
Time Reg. No. Vehicle Number Origin Destination Trip Purpose Trip Vehicle Load Road Would
Type of Frequency Loading Type Condition use road
People if
improved
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
82
Part 2 -Section 6 Terms of Reference 83
[NB This item cannot be effectively pursued until the proposed alignment has been determined.
Hence, if there is a Feasibility Study stage involving alignment selection then the item cannot be
commenced until the Feasibility Study has been completed, although Items 10.01 to 10.04 could be
undertaken prior to that milestone]
***
***
Item 10.01 – Prepare Quality Assurance [QA] Plan for Topographic Survey
CONFIRMATION: Submitted:
ACTIVITY:
The DCs [in collusion with their survey sub-contractor, if any] must prepare a QA Plan to describe
how topographic survey will be organised and managed in a realistic way for implementation and
achievement of the project objectives.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
84
Part 2 - Section 6 Terms of Reference
***
The following checklist outlines the expected contents of the QA Plan. Other elements should be
included as appropriate to the specific project.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
85
Part 2 - Section 6 Terms of Reference
Job methodology; including ensuring compliance with requisite accuracy specifications Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
86
Part 2 - Section 6 Terms of Reference
Other considerations:
Relevant: Included:
Relevant: Included:
Relevant: Included:
Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
87
Part 2 - Section 6 Terms of Reference
Relevant: Included:
***
CONFIRMATION: Completed:
RA [and Donor(s), where applicable] comments on Draft QA Plan for Topographic Survey
ACTIVITY:
There should be a defined period in the Services Contract which will commence immediately upon
the submission of the Draft QA Plan for Topographic Survey during which period the RA and
[where applicable] the Donor(s) perform a review of the draft plan and [where considered
necessary] hold discussions with the DCs to clarify any points which require further explanation.
The comments arising from that review will be formally forwarded to the DCs.
***
Item 10.03 – Finalise QA Plan for Topographic Survey
CONFIRMATION: Submitted:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
88
Part 2 - Section 6 Terms of Reference
ACTIVITY:
The DCs will receive the official comments of the RA and Donor(s) [as applicable].
They will finalise and formally submit the QA Plan for Topographic Survey to incorporate the
received comments or modification(s) of same following any subsequent discussion with RA for
the purpose of clarification or debate.
***
Item 10.04 – Implementation of QA Plan for Topographic Survey
CONFIRMATION: Confirmed:
ACTIVITY:
The implementation of the QA Plan for Topographic Survey must be an on-going obligation on the
part of the DCs throughout the topographic survey work. The item can only be ‘signed off’ in the
above ‘Confirmation’ box upon completion of all topographic survey work.
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
89
Part 2 - Section 6 Terms of Reference
CONFIRMATION: Completed:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
90
Part 2 - Section 6 Terms of Reference
ACTIVITY:
The DCs will utilise “state of the art” equipment for all survey and setting out works and to facilitate
the ready transfer of digital survey data to the highway design / digital terrain model software.
The DCs must identify all existing triangulation beacons installed during previous studies [if such
exist], and national survey monuments in the proximity of the project area, and install additional and /
or replace existing damaged triangulation beacons, as necessary, to ensure adequate coverage of
the project area. These must be of robust construction typically comprising steel pins set in concrete
or alternatively set in holes drilled into solid immovable rock. The beacons will be located outside the
area to be occupied by the permanent works, shall be mutually inter-visible, and at spacing and
locations such that all secondary survey and setting out can be carried out from them. The beacons
must be conspicuously marked at the site of each, and location diagrams must be prepared for each.
The network must be linked to the National Survey Grid, and benchmarks to the National
Benchmarks system, where practicable. Where this cannot be practicably achieved a local
triangulation and / or benchmark level system may alternatively be established. However, it is vital
that such a systems be tied-in to carefully chosen, ‘indestructible’, and easily identifiable landmarks.
These basic reference landmarks must not be susceptible to damage or movement by agricultural
activity, erosion, flood, vandalism or any other such reasonably foreseeable threat. There must be a
redundancy in the number of such basic reference landmarks so that, in the unlikely event of one or
more actually being disturbed, there will be sufficient remaining to still enable restoration of the
system. THIS IS VITALLY IMPORTANT.
The accuracy of observations for the x [easting], y [northing] coordinates must be within 10 mm +
1 part per million e.g for 2 points located 5 km apart:
Distance = 5 million mm
Error = 10 + 1 x 5,000,000/1,000,000 = 15 mm
The accuracy for the z coordinate [elevation / reduced level] must be within 5 mm x k [where k is
distance in km between successive beacons] e.g. for two points 5 km apart:
Error tolerance = 5 x 5 = 11 mm
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
91
Part 2 - Section 6 Terms of Reference
CONFIRMATION: Completed:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
92
Part 2 - Section 6 Terms of Reference
ACTIVITY:
The DCs must carry out detailed secondary surveys using “state of the art” equipment. The surveyed
strip width must be sufficient to accommodate all the envisaged design components plus a margin
beyond so that the adjacent terrain configuration can, where relevant, influence the nature of the
nearby works. This is especially important in respect of roadside drainage. As a general indication,
the strip width should be about twice that of the nominal RoW width [but not less than 100m], to allow
for full control of all designed elements within the RoW and also for moderate modifications in
geometric alignment during fine detailing. Good judgment will be required with regard to the actual
selected detailed survey width to reflect degree of complexity of the alignment geometrics, and also
with regard to the need for additional coverage where dictated by special circumstances such as side
roads realignment, frontage [service] roads and other access roads, intersections, slip roads and
interchanges, grading and realignment of watercourses, and structures.
The DCs will record x [easting], y [northing], z [elevation] coordinates of all surface features. A coding
system for all features should have been outlined in the QA plan.
Judgement will be necessary on the frequency of ground points surveyed to create the contour string
lines based on the particular terrain but the intensity must be sufficient to accurately support 1/1000
scale mapping with a 1 metre contour interval for general design and 1/500 scale mapping with a
0.5 metre contour interval in special areas where a larger scale is required for clarity of presentation,
eg for such locations as those outlined in the last sentence of the first paragraph of this ‘Activity’ box.
The actual features captured in the topographic survey work will vary from project to project,
particularly between existing road rehabilitation and new road alignment, and these will require
agreement prior to commencement of the survey work.
The following tabulation provides a comprehensive list of potential features for incorporation into the
Digital Terrain Model [DTM] from which the actual features surveyed should be selected and agreed
as per the requirements of the specific project. In the event of other features special to the project
area, and not listed, they should be added in the blank spaces provided
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
93
Part 2 - Section 6 Terms of Reference
National Survey trigonometric stations, with coordinates and all other details Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
94
Part 2 - Section 6 Terms of Reference
Watercourses [natural rivers, streams], upper edges and bottom profile Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
95
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
96
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
97
Part 2 - Section 6 Terms of Reference
Drainage manhole / catchpit [type], with invert level and size of pipework Relevant: Included:
Railway track, with track profile [all lines] for [say] 50m each side of alignment Relevant: Included:
Buildings [frontage, general, solid-sided, open-sided, type of wall structure, type of Relevant: Included:
roof]
Walls [low 0.1m - 0.5m, > 0.5m / various types] Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
98
Part 2 - Section 6 Terms of Reference
Overhead electricity cables and pole positions, including voltage Relevant: Included:
Water supply chamber cover, including depth to pipe and pipe size Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
99
Part 2 - Section 6 Terms of Reference
Telecommunications chamber , including depth to top and bottom of cables Relevant: Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
100
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
101
Part 2 - Section 6 Terms of Reference
Additional areas of survey at larger scale [see above ‘Activity’ box for this item] related Relevant: Included:
to such special circumstances as:
intersections,
structures.
Other features:
Included:
Included:
Included:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
102
Part 2 - Section 6 Terms of Reference
Included:
Included:
***
Using appropriate road design software cross sections through the proposed road and ground profile
can readily be obtained from the DTM. Hence, for projects where the ToR requires the preparation of a
DTM it will not be necessary to undertake separate field survey to produce cross section information
for the proposed road at specific chainage intervals.
However, for projects where a DTM is not called for, such as a simple road rehabilitation without
geometric realignment, it may be more efficient and economical to undertake a cross section survey at
suitable intervals sufficient to accurately depict the profile of the existing road.
CONFIRMATION: Completed:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
103
Part 2 - Section 6 Terms of Reference
ACTIVITY:
Where a road cross section survey is required as described above the typical cross section
interval would be 20 metres but this may require adjustment from road section to road section
depending on the severity of the existing road geometry or on such matters as extreme
topography, urban areas, junctions, property accesses, nearby structures, specific drainage
improvements etc.
Each cross section of an on-site cross section survey should extend over at least the full width of
the RoW, and also any adjacent ditches or drainage channels [even outside the RoW] should be
captured by the survey so that positive drainage can be designed for the location.
In the event of a project consisting of part new alignment and part simple rehabilitation the on-site
cross section information will be included in the overall DTM.
Where existing roadside utility lines will be affected by a road rehabilitation project then their
details must also be accurately recorded during the on-site cross section survey work, with the
parameters recorded as described in the previous item for the preparation of a DTM.
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
104
Part 2 - Section 6 Terms of Reference
ACTIVITY:
Alignment and RoW staking must be effected using robust markers with high visibility markings
and the physical nature of the markers must be as approved by the RA.
In the case of a road rehabilitation project without realignment the existing RoW may remain
largely unchanged and, accordingly, it may not be necessary to stake out the RoW boundaries.
Where the project requires new RoW boundaries to be established due to realignment of an
existing road or for a new road alignment these must be staked out when their final details have
been determined. This is an essential component in the assessment and evaluation of land
acquisition and compensation. It should be noted that traditionally most roads have had a uniform
RoW width generally related to the class of road involved, which greatly simplifies the process of
staking out the boundaries. However, in some cases the more sophisticated roads of the present
and future, with their attendant special features, such as side roads realignment, frontage [service]
roads and other access roads, complex intersections, slip roads and interchanges, realignment of
watercourses, and complex drainage outfall facilities will commonly require many localised
additional areas beyond the nominal RoW width to accommodate those features.
Whilst the alignment should be staked out at the site as soon as it has been finalised, it is
important not to stake out the RoW boundaries before the final land areas required in each
location have been finally determined since modification and re-staking can cause distress to
project-affected people who are required to lose land and property.
Where involuntary resettlement (physical and/or economic displacement) will arise the alignment
and ROW staking much be coordinated with the resettlement and compensation action planning
process. This is particularly important to avoid opportunistic settlers moving into the area, looking
to benefit from compensation packages.
Concurrently with the staking process the DTM must be updated with any changes in property
features, to facilitate the most accurate subsequent inventory of property loss due to the project.
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
105
Part 2 - Section 6 Terms of Reference
CONFIRMATION: Confirmed:
ACTIVITY:
Checking procedures are vitally important to ensure the overall accuracy and professional standards
of the topographic survey. These must include regular checking of instrument calibration, random
independent checks to validate the three dimensional accuracy of survey points, and site
reconnaissance to provide a visual appreciation of field conditions compared to the survey data.
Whilst this must be an on-going obligation on the part of the DCs throughout the topographic survey
work the item can only be ‘signed off’ in the above ‘Confirmation’ box upon completion of all
topographic survey work.
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
106
Part 2 - Section 6 Terms of Reference
CONFIRMATION: Submitted:
ACTIVITY:
The draft Topographic Survey Report will outline the methodology used by the DCs to carry out the
primary control survey and detailed secondary surveys and must include the following deliverables.
Unedited digital files of all raw survey data for both the Primary Traverse and secondary
surveys together with legible copies of any field books / notes.
Traverse layout drawing(s) and computations.
Correlation with the Malawian topographic Grid System, where appropriate.
The final x, y, z coordinates for all Control Points; point number, easting (x), northing (y),
elevation (z).
Levelling computation sheets.
Monographs for each triangulation beacon comprising a brief description of the location,
numeric photography, and triangulation data.
The complete DTM in electronic format.
Details of equipment calibration.
Staffing of the topographic survey work.
The report and accompanying data must be prepared in a user-friendly manner for ease of
reference subsequently by the construction contractor and construction supervising consultants
during the construction stage.
***
CONFIRMATION: Completed:
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
107
Part 2 - Section 6 Terms of Reference
ACTIVITY:
There should be a defined period in the Services Contract which will commence immediately upon
the submission of the Draft Topographic Survey Report during which period the RA and [where
applicable] the Donor(s) perform a review of the report and [where considered necessary] hold
discussions with the DCs to clarify any points which require further explanation.
The comments arising from that review will be formally forwarded to the DCs.
***
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
108
Part 2 - Section 6 Terms of Reference
CONFIRMATION: Submitted:
ACTIVITY:
The DCs will receive the official comments of the RA and Donor(s) [as applicable].
They will finalise and formally submit the Topographic Survey Report to incorporate the received
comments or modification(s) of same following any subsequent discussion with RA for the
purpose of clarification or debate.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
109
Part 2 - Section 6 Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
110
Part 2 -Section 6 Terms of Reference 111
ANNEX 5
The typical contents of an ESIA Report are presented hereafter. It shall be noted that the
presentation of the report may be adapted depending on the nature and specific
requirements of the project.
Executive Summary
This section shall present in a non-technical language a concise summary of the ESIA Report
with a particular attention on the processes and procedures used, baseline conditions,
alternatives considered, mitigation/enhancement measures, monitoring programme,
consultations with stakeholders, capabilities of environmental and social units and actions to
strengthen those capacities and associated cost implications. This Executive Summary shall
be written in English and a local language, if necessary, for public consultations.
Introduction
The introduction shall indicate the purpose of the ESIA, present an overview of the proposed
project to be assessed as well as the project’s purpose and needs. This section identifies the
project sponsor and the consultant assigned to carry out the ESIA. It shall also briefly mention
the contents of the ESIA Report and the methods adopted to complete the assessment.
This chapter concerns the policy, legal and administrative framework within which the ESIA is
carried out. It presents the relevant environmental and social policies of the country as well as
the national legal requirements and related constraints (e.g. practices that may discriminate or
exclude any stakeholder group) relevant to the project.
The first part of this chapter shall describe the proposed project and its geographic, ecological,
social, economic and temporal context, project location, various project components, capacity,
construction activities, facilities, staffing, working conditions, availability and source of raw
materials, production methods, products, schedule of works, land tenure, land use system,
potential beneficiaries, affected groups (directly and indirectly) and offsite investments that
may be required.
This section shall determine and characterise the anticipated liquid, solid and gaseous
discharges from the processes as well as the sources of nuisance such as noise, odours,
visual nuisances, etc. It shall indicate the need for any resettlement plan or vulnerable groups’
development plan. It shall at least include a map showing the project location and area of
influence.
The project justification should be based on combined economic, environmental and social
assessments. To this end, this chapter shall describe the current situation in the sector, explain
the problems or the needs to be satisfied by the project and present the constraints associated
with the project implementation.
This chapter shall first determine the limits of the study area that shall be defined in order to
encompass all project direct and indirect impacts. The description and analysis of the physical,
biological and human conditions shall be addressed. Relevant environmental and social issues
within this area, including any changes anticipated before project implementation shall also be
described.
Within the human environment, key issues that shall be considered include population
characteristics and trends, revenue disparities, gender differences, health problems, natural
resource access and ownership, land use patterns and civil society organisation level. For
further information on typical issues to consider in an ESIA, refer to
Annex 9.
It shall also address the interrelations between the environmental and social components and
the importance (value) that the society and local populations attach to these components, in
order to identify the environmental and social components of high value or presenting a
particular interest. Particular attention shall be given to the rare, threatened, sensitive or
valorised environmental and social components.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
112
Part 2 - Section 6 Terms of Reference
The information presented shall be relevant to decisions about project location, design,
operations as well as environmental and social management. Maps, figures and tables shall
be included in this chapter to better illustrate the various environmental and social
components.
Project Alternatives
This part of the ESIA Report consists an analysis of various feasible alternatives of the
project including the "without project" option. It normally comprises two sections. The first
section identifies and describes the potential feasible alternatives that would allow reaching
the project objectives. The second section presents a comparison of the potential
alternatives on the basis of technical, economic, environmental and social criteria as well as
of public views and concerns.
The alternative comparison shall address the proposed project site, technology, design and
operation in terms of their potential environmental and social impacts and the feasibility of
mitigating these impacts. For each of the alternatives, the environmental and social impacts
shall be quantified as much as possible including their economic values where feasible. The
selected alternative shall be the most environmentally and socially sustainable taking into
account the technical and economical feasibility.
This chapter presents a detailed analysis of beneficial and adverse impacts of various
components of the selected project alternative on the physical, biological and human (social,
cultural and economic) environments. The methodology of assessment, based on a rigorous
scientific method, shall be first presented. Then all environmental and social, direct and
indirect, short and long-term, temporary and permanent impacts shall be described and
assessed, indicating their importance levels and their probability of occurrence. The
importance levels may be assessed on the basis of the nature, extent, intensity and duration
of the impact, as well as on the sensitivity of the concerned environmental and social
components and perceptions of the public. Irreversible or unavoidable impacts shall be
clearly identified. Cumulative effects shall also be addressed taking into account other
projects or actions planned in the study area.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
113
Part 2 - Section 6 Terms of Reference
performance. Roles and responsibilities to implement measures shall be clearly defined. The
cost of the measures shall be estimated, including the cost for environmental and social
capacity building and gender mainstreaming, if necessary. Residual impacts shall be
presented.
Whenever relevant, this chapter shall describe the security measures and propose a
preliminary contingency plan for the construction and operation phases of the project (possible
contingency situations, major actions to properly react to accidents, responsibilities and means
of communications).
For projects that may cause major technological accidents whose consequences may exceed
the project site, the ESIA shall include an analysis of the technological accident risk:
identification of hazard and potential consequences, estimation of the consequences’
magnitude and frequency and risk estimation and evaluation.
The first section of this chapter shall describe the surveillance measures aimed at ensuring
that the proposed mitigation and enhancement measures are effectively implemented during
the implementation phase. The second section concerns the environmental and social
monitoring activities designed to measure and evaluate the project impacts on some key
environmental and social components of concern and to implement remedial measures, if
necessary. Indicators, roles and responsibilities shall be clearly defined. The cost of the
programme shall be estimated, including the cost for environmental and social capacity
building, if necessary.
Public Consultations
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
114
Part 2 - Section 6 Terms of Reference
This chapter shall summarise the actions undertaken to consult the groups affected by the
project as well as other concerned key stakeholders including Civil Society Organisations. The
detailed record of the consultation meetings shall be presented in annex to the ESIA Report.
Conclusion
The Conclusion shall specify the environmental and social acceptability of the project, taking
into account the impacts and measures identified during the assessment process. It shall also
identify any other conditions or external requirements for ensuring the success of the project.
Annexes
i. List of the professionals and organizations having contributed to the preparation of the
ESIA Report.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
115
Part 2 - Section 6 Terms of Reference
Annex 6
OUTLINE OF A TYPICAL FULL RESETTLEMENT ACTION PLAN
2. Potential Impacts
3. Organizational Responsibility
The institutional arrangements within the executing agency and provision of adequate
resources to the executing agency should be discussed and all inter-agency
coordination should be described. The capacity and commitment of the executing
agency to carry out the resettlement plan should also be evaluated. If necessary,
strengthening of the executing agency should be considered and the steps that will
be taken, together with a timetable and budget, should be described at the project
preparation phase. There should be considerable scope for involving the local people
and Non-Governmental Organizations (NGOs) in planning, implementing and
monitoring resettlement.
4. Community Participation
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
116
Part 2 - Section 6 Terms of Reference
Consultations with host communities and local governments and arrangements for
prompt tendering of any payments due to the hosts for land or other assets should be
provided to resettlers. Arrangements for addressing any conflict that may arise
between the resettlers and host communities should also be made.
Appropriate measures should be taken to augment public services (e.g. education, water,
health and production) in host communities to make them comparable to services provided
to resettlers.
6. Socio-economic Studies
(a) A population census covering current occupants of the affected area including
the description of the production systems, household organization, baseline
information on livelihoods and standards of living of the displaced population.
(d) Description of land tenure systems including common property and non-title
based land ownership or allocation system recognized locally and related
issues.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
117
Part 2 - Section 6 Terms of Reference
(b) Laws and regulations relating to the agencies responsible for implementing
resettlement activities.
8. Institutional Framework
9. Eligibility
Definition of displaced persons and criteria for determining their eligibility for
compensation and other resettlement assistance including relevant cut-off dates.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
118
Part 2 - Section 6 Terms of Reference
(a) Institutional and technical arrangements for identifying and preparing relocation
sites for which a combination of productive potential, locational advantages and
other factors are at least comparable to the ancillary resources.
(b) Procedures for physical relocation under the project including timetables for site
preparation and transfer.
(c) Any measures to prevent influx of ineligible persons at the selected sites.
resettlers.
Plans to provide or finance housing, infrastructure (e.g. roads, water supply, etc) and
social services (schools, health services), plans to ensure comparable services to
host populations and any necessary site development.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
119
Part 2 - Section 6 Terms of Reference
Tables indicating breakdown of cost estimates for all resettlement activities including
allowances for inflation and other contingencies, timetable for expenditures, sources
of funds and arrangements for timely flow of funds.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
120
Part 2 - Section 6 Terms of Reference
Annex 7
1. A census survey of the expected size of the displaced persons, their socio-economic
status including the value of their assets and other sources of livelihood should be
carried out
2. Definition of displaced persons and criteria for determining their eligibility for
compensation and other resettlement assistance including relevant cut-off dates.
3. The displaced people and the host population should be consulted about acceptable
project alternatives and should be informed about project’s potential impacts on
them.
6. The schedules, budget and sources of funds should be agreed upon with the
executing agency.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
121
Part 2 - Section 6 Terms of Reference
Annex 8
An Environmental and Social Management Plan (ESMP) shall follow the Environmental
Impact Assessments Guidelines (1997).
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
122
Part 2 - Section 6 Terms of Reference
Annex 9
Environmental and Social Impact Assessment studies shall address key crosscutting issues
in accordance with the Environmental Management Act, national legislation and policies as
well as Roads Authority Environmental and Social Management Guidelines in the Road
Sector. For donor funded projects, the consultant shall review donor’s policies and guidelines
on Environmental and Social safeguards. While assessment contents depend on the nature
and scope of the project, plan or program, there are typical environmental and social
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
123
Part 2 - Section 6 Terms of Reference
components in the human and natural environments that shall be considered. The following
components may not require to be thoroughly analyzed in ESIA studies, but their importance
and significance in relation to the nature and scope of the considered project, plan or
program shall at least be assessed.
1. Human environment
The components to consider in the human environment include the elements and
characteristics of the social, cultural and economic environments as well as
infrastructures and services and land use patterns in the project area and its zone of
influence.
2 Social Environment
2.1 Population
Demographic trends (fertility, birth and mortality rates, growth, forecast, etc.) and
pressures/problems associated with demographic trends.
Characteristics of poor people and other vulnerable groups: who they are, where
they live, employability level, economic activities, access to productive factors,
etc.
2.2 Gender
Gender perspective in legal and policy framework (marriage codes and law,
inheritance laws, property law, labour law, immigration laws, education and
health policy, agricultural and rural development policy, economic policy with
regard to gender budgeting; etc).
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
124
Part 2 - Section 6 Terms of Reference
2.3 Health
HIV/AIDS epidemiological situation, especially among the 15-24 and 25-34 years’
age groups.
Injuries and violent assaults, particularly against women, youth, elderly and other
vulnerable groups.
Health and safety at work (work related injuries, contamination associated with
pesticide or fertilizer use, existing control programmes and regulations, etc).
Composition and size of the Civil Society Organizations (local, regional, national
and international CSOs active in the study area): community-based
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
125
Part 2 - Section 6 Terms of Reference
Capacities in the environmental and social sectors (including local, regional and
national institutions involved in the study area).
Local and regional political and administrative structures (traditional and modern)
and their interrelations.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
126
Part 2 - Section 6 Terms of Reference
Major economic activities at the local and regional levels and growth trends.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
127
Part 2 - Section 6 Terms of Reference
Water supply: facilities (open wells, distribution systems, etc), ratio per capita,
water quality, affordability, etc.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
128
Part 2 -Section 6 Terms of Reference 129
Table of Clauses
A. General Provisions............................................................................................................. 105
1. Definitions............................................................................................................................. 105
5. Language.............................................................................................................................. 107
6. Notices................................................................................................................................. 107
7. Location................................................................................................................................ 107
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
130
Part 3 - Section 7 General Conditions of Contract
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
131
Part 3 - Section 7 General Conditions of Contract
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
132
Part 3 - Section 7 General Conditions of Contract
1. Definitions
1.1 Unless the context otherwise requires, the following terms whenever used in this
Contract have the following meanings:
“Contract” means the Agreement entered into between the Parties and includes the
Contract Documents.
“Contract Documents” means the documents listed in GCC 2.1, including all
attachments, appendices, and all documents incorporated by reference therein, and
shall include any amendments thereto.
“Contract Price” means the sum stated in the Agreement representing the maximum,
total or estimated amount payable for the provision of the Services.
“Days” are calendar days; “months” are calendar months.
“Eligible Countries” means the countries and territories eligible as listed in the SCC.
“GCC” means these General Conditions of Contract.
“Government” means the Government of the Republic of Malawi.
"Member", in case the Supplier consists of a joint venture of more than one entity,
means any of these entities; "Members" means any of these entities, and "Member in
charge" means the entity specified in the SCC to act on their behalf in exercising all the
Suppliers’ rights and obligations towards the Procuring Entity under this Contract.
"Party" means the Procuring Entity or Supplier, as the case may be, and "Parties"
means both of them.
“Personnel” means persons engaged by the Supplier or by any Sub-consultant as
employees and assigned to the performance of the Services or any part thereof;
“Foreign Personnel” means such persons who at the time of being so engaged had
their domicile outside the Republic of Malawi; “Local Personnel” means such persons
who at the time of being so engaged had their domicile inside the Republic of Malawi;
and “Key Personnel” means those Personnel that are regarded by the Supplier as
essential to the successful completion of the Services and related tasks.
“Procuring Entity” means the Roads Authority of Malawi, purchasing the Services, as
specified in the Agreement, hereinafter called “the Client”.
“SCC” means the Special Conditions of Contract.
“Services” means the consultancy services to be performed by the Supplier as
described in the contract.
“Supplier” means the natural person, private or government entity, or a combination of
the above, whose proposal to perform the Contract has been accepted by the Procuring
Entity and is named as such in the Agreement, and includes the legal successors or
permitted assigns of the Supplier, hereinafter called “the Consultant”.
“Sub-consultant” means any natural person, private or government entity, or a
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
133
Part 3 - Section 7 General Conditions of Contract
combination of the above, including its legal successors or permitted assigns, to whom
any part of the Services to be provided is subcontracted by the Supplier.
“Time-Based contract” means a contract under which the Services are provided on the
basis of fixed fee rates and payments are made on the basis of time actually spent.
2. Corrupt Practices
2.1 It is the Government’s policy to require that Procuring Entities, as well as Bidders and
Consultants under Government financed contracts, observe the highest standards of
ethics during the procurement and execution of such contracts. In pursuit of this policy,
the Government:
(a) defines, for the purposes of this provision, the terms set forth below as follows:
(i) "corrupt practice" means the offering, giving, receiving or
soliciting, directly or indirectly, of anything of value to influence the
action of a public official in the procurement process or in contract
execution;
(ii) "fraudulent practice" means a misrepresentation or omission of
facts in order to influence a procurement process or the execution
of a contract;
(iii) “collusive practices” means a scheme or arrangement between
two or more Bidders, with or without the knowledge of the
Procuring Entity, designed to establish prices at artificial,
noncompetitive levels; and
(iv) “coercive practices” means harming or threatening to harm,
directly or indirectly, persons or their property to influence their
participation in a procurement process, or affect the execution of
a contract.
(b) will debar a Bidder from participation in public procurement for a specified period of
time if it at any time determines that the firm has engaged in corrupt, fraudulent,
collusive or coercive practices in competing for, or in executing, a contract.
2.2 In pursuit of the policy defined in GCC Clause 2.1, the Procuring Entity may terminate a
Contract in accordance with GCC Clause 16 if it at any time determines that corrupt,
fraudulent, collusive or coercive practices were engaged in by representatives of the
Procuring Entity or of a Consultant, during the procurement or the execution of that
contract.
3. Contract Documents
3.1 The documents forming the Contract shall be interpreted in the following order of
priority:
(a) Contract Agreement, including all appendices;
(b) Special Conditions of Contract;
(c) General Conditions of Contract; and
(d) Terms of Reference
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
134
Part 3 - Section 7 General Conditions of Contract
(e) any other document listed in the SCC as forming part of the Contract.
3.2 All documents forming the Contract are intended to be correlative, complementary, and
mutually explanatory.
3.3 No amendment, modification or other variation of the Contract shall be valid unless a
Modification to Contract is made in writing, is dated, expressly refers to the Contract,
and is signed by a duly authorised representative of each party thereto.
3.4 If any provision or condition of the Contract is prohibited or rendered invalid or
unenforceable, such prohibition, invalidity or unenforceability shall not affect the validity
or enforceability of any other provisions and conditions of the Contract.
3.5 Any action required or permitted to be taken, and any document required or permitted
to be executed, under the Contract by the Client or the Consultant may be taken or
executed by the authorised representatives specified in the SCC.
3.6 The Contract constitutes the entire agreement between the Client and the Consultant
and supersedes all communications, negotiations and agreements (whether written or
oral) of parties with respect thereto made prior to the date of Contract. No agent or
representative of either Party has authority to make, and the Parties shall not be bound
by or be liable for, any statement, representation, promise or agreement not set forth
herein.
4.1 This Contract, its meaning and interpretation, and the relation between the Parties shall
be governed by the laws of the Republic of Malawi, unless otherwise specified in the
SCC.
5. Language
5.1 This Contract has been executed in English, which shall be the binding and controlling
language for all matters relating to the meaning or interpretation of this Contract, unless
otherwise specified in the SCC.
6. Notices
6.1 Any notice, request, or consent made pursuant to this Contract shall be in writing and
shall be deemed to have been made when delivered to an authorised representative of
the Party at the address specified in the SCC.
7. Location
7.1 The Services shall be performed at such locations as are specified in the Terms of
Reference and, where the location of a particular task is not so specified, at such
locations, whether in the Republic of Malawi or elsewhere, as the Client may approve.
8. Authorised Representatives
8.1 Any action required or permitted to be taken, and any document required or permitted
to be executed, under this Contract by the Client or the Consultant may be taken or
executed by the authorised representatives specified in the SCC.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
135
Part 3 - Section 7 General Conditions of Contract
9.1 Unless otherwise specified in the SCC, the Consultant, Sub-consultants, and their
Personnel shall pay such taxes, duties, fees, and other impositions as may be levied
under the law of the Republic of Malawi, the amount of which is deemed to have been
included in the Contract Price.
10. Eligibility
10.1 The Consultant and its Subconsultants shall have the nationality of an eligible country. A
Consultant or Subconsultant shall be deemed to have the nationality of a country if it is
a citizen or constituted, incorporated, or registered, and operates in conformity with the
provisions of the laws of that country.
10.2 The Consultant and its Sub-consultants shall provide Personnel who shall be citizens of
eligible countries.
11.1 This Contract shall come into effect on the date the Contract is signed by both parties or
such other later date as may be stated in the SCC.
12.1 The Consultant shall begin carrying out the Services thirty (30) days after the date the
Contract becomes effective, or at such other date as may be specified in the SCC.
13.1 Unless terminated earlier pursuant to Clause 16, this Contract shall terminate at the end
of such time period after the Effective Date as is specified in the SCC.
14. Modification
14.1 Modification of the terms and conditions of this Contract, including any modification of
the scope of the Services or of the Contract Price, may only be made by written
agreement between the Parties.
Definition
15.1 For the purposes of this Contract, “Force Majeure” means an event which is beyond the
reasonable control of a Party and which makes a Party’s performance of its obligations
under the Contract impossible or so impractical as to be considered impossible under
the circumstances.
No Breach of Contract
15.2 The failure of a Party to fulfill any of its obligations under the contract shall not be
considered to be a breach of, or default under, this Contract insofar as such inability
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
136
Part 3 - Section 7 General Conditions of Contract
arises from an event of Force Majeure, provided that the Party affected by such an
event (a) has taken all reasonable precautions, due care and reasonable alternative
measures in order to carry out the terms and conditions of this Contract, and (b) has
informed the other Party as soon as possible about the occurrence of such an event.
Extension of Time
15.3 Any period specified within the Contract by which a Party is required to complete any
action or task, if as a result of Force Majeure, shall be extended for a period equal to
the time during which the Party was unable to perform the action or task.
Payments
15.4 During the period of their inability to perform the Services as a result of an event of
Force Majeure, the Consultant shall be entitled to continue to be paid under the terms
of this Contract, as well as to be reimbursed for additional costs reasonably and
necessarily incurred by it during such period for the purposes of the Services and in
reactivating the Service after the end of such period.
16. Termination
By the Client
16.1 The Client may terminate this Contract, by not less than thirty (30) days’ written notice
of termination to the Consultant, to be given after the occurrence of any of the events
specified in paragraphs (a) through (e) of this Clause 16.1 and sixty (60) days’ in the
case of the event referred to in (f):
(a) if the Consultant does not remedy a failure in the performance of its obligations under
the Contract, within thirty (30) days after being notified or within any further period as
the Client may have subsequently approved in writing;
(b) if the Consultant become insolvent or bankrupt;
(c) the Consultant fails to comply with any final decision reached as a result of dispute
settlement proceedings pursuant to GCC Clause 35;
(d) the Consultant, in the judgement of the Client, has engaged in corrupt, fraudulent,
collusive or coercive practices in competing for or in executing the Contract;
(e) if, as the result of Force Majeure, the Consultant is unable to perform a material
portion of the Services for a period of not less than sixty (60) days; or
(f) if the Client, in its sole discretion, decides to terminate the Contract.
By the Consultant
16.2 The Consultant may terminate this Contract, by not less than thirty (30) days’ written
notice to the Client, such notice to be given after the occurrence of any of the events
specified in paragraphs (a) to (d) of this Clause 16.2:
(a) If the Client fails to pay any monies due to the Consultant pursuant to this Contract and
not subject to dispute pursuant to Clause 7 within forty-five (45) days after receiving
written notice from the Consultant that such payment is overdue;
(b) If the Client is in material breach of its obligations pursuant to the Contract and has not
remedied the same within forty-five days (or such longer period as the Consultant may
have subsequently approved in writing) following the receipt by the Client of the
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
137
Part 3 - Section 7 General Conditions of Contract
17. General
17.1 The Consultant shall perform the Services and carry out its obligations with all due
diligence, efficiency, and economy, in accordance with generally accepted professional
techniques and practices, and shall observe sound management practices, and employ
appropriate advanced technology and safe methods. The Consultant shall always act,
in respect of any matter relating to this Contract or to the Services, as a faithful adviser
to the Client, and shall at all times support and safeguard the Client’s legitimate
interests in any dealings with Sub-consultants or third parties.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
138
Part 3 - Section 7 General Conditions of Contract
19.1 The Client and the Consultant shall keep confidential and shall not without the written
consent of the other party hereto, divulge to any third party any reports or data, or other
information furnished directly or indirectly by the other party hereto in connection with
the Contract, whether such information has been furnished prior to, during or following
completion or termination of the Contract. Notwithstanding the above, the Consultant
may furnish to its Sub-consultant such documents, data, and other information it
receives from the Client to the extent required for the Sub-consultant to perform its work
under the Contract, in which event the Consultant shall obtain from such Sub-consultant
an undertaking of confidentiality similar to that imposed on the Consultant under the
Contract.
20.1 The Consultant shall take out and maintain, and shall cause any Sub-consultants to
take out and maintain, at its (or the Sub-consultants’, as the case may be) own cost but
on terms and conditions approved by the Client, insurance against the risks, and for the
coverage, as shall be specified in the SCC.
20.2 The Consultant, at the Client’s request, shall provide evidence to the Client showing
that such insurance has been taken out and maintained and that the current premiums
have been paid.
21.1 The Consultant shall obtain the Client's prior approval in writing before taking any of the
following actions :
(a) entering into a subcontract for the performance of any part of the Services;
(b) appointing such members of the of the personnel not listed by name in the Contract;
and
(c) any other action that may be specified in the SCC.
22. Reporting Obligations
22.1 The Consultant shall submit to the Client the reports and documents specified in the
Terms of Reference in the form, in the numbers, and within the periods set forth in the
said Terms of Reference.
23.1 All plans, drawings, specifications, designs, reports, and other documents and software
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
139
Part 3 - Section 7 General Conditions of Contract
submitted by the Consultant in accordance with the Contract shall become and remain
the property of the Client, and the Consultant shall, not later than upon termination or
expiration of this Contract, deliver all such documents and software to the Client,
together with a detailed inventory thereof. The Consultant may retain a copy of such
documents and software. Restrictions about the future use of these documents, if any,
shall be specified in the SCC.
D. Consultant’s Personnel
24.1 The titles, agreed job descriptions, minimum qualifications, and estimated periods of
engagement in the carrying out of the Services of the Consultant’s Key Personnel are
described in the Contract. The Key Personnel and Sub-consultants listed by title as well
as by name in Contract are hereby approved by the Client.
25.1 Except as the Client may otherwise agree, no changes shall be made in the Key
Personnel. If, for any reason beyond the reasonable control of the Consultant, it
becomes necessary to replace any of the Key Personnel, the Consultant shall provide
as a replacement a person of equivalent or better qualifications.
25.2 If the Client finds that any of the Personnel have (i) committed serious misconduct or
have been charged with having committed a criminal action, or (ii) have reasonable
cause to be dissatisfied with the performance of any of the Personnel, then the
Consultant shall, at the Client’s written request specifying the grounds therefor, provide
as a replacement a person with qualifications and experience acceptable to the Client.
25.3 The Consultant shall have no claim for additional costs arising out of or incidental to any
removal and/or replacement of Personnel.
26.1 Unless otherwise specified in the SCC, the Client shall use its best efforts to ensure that
the Government shall:
(a) Provide the Consultant, Sub-Consultants and Personnel with work permits and such
other documents as shall be necessary to enable the Consultant, Sub-Consultants or
Personnel to perform the Services.
(b) Arrange for the Personnel and, if appropriate, their eligible dependents to be provided
promptly with all necessary entry and exit visas, residence permits, exchange permits
and any other documents required for their stay in the Republic of Malawi.
(c) Facilitate prompt clearance through customs of any property required for the Services
and of the personal effects of the Personnel and their eligible dependents.
(d) Issue to officials, agents and representatives of the Government all such instructions
as may be necessary or appropriate for the prompt and effective implementation of the
Services.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
140
Part 3 - Section 7 General Conditions of Contract
(e) Provide assistance to the Consultant’s international personnel and, where applicable
international Sub-Consultants employed by the Consultant, to obtain registration or
obtain any permit to practice their profession in the Republic of Malawi.
(f) Grant to the Consultant, any Sub-Consultants and the Personnel of either of them the
privilege, pursuant to the laws of the Republic of Malawi, of bringing into the Republic
of Malawi reasonable amounts of foreign currency for the purposes of the Services or
for the personal use of the Personnel and their dependents and of withdrawing any
such amounts as may be earned therein by the Personnel in the execution of the
Services.
(g) Provide to the Consultant, Sub-Consultants and Personnel any such other assistance
as may be specified in the SCC.
27. Change in Laws
27.1 Unless otherwise specified in the Contract, if after the date of the Request for
Proposals, any law, regulation, ordinance, order or bylaw having the force of law is
enacted, promulgated, abrogated, or changed in the Republic of Malawi (which shall be
deemed to include any change in interpretation or application by the competent
authorities) that subsequently affects the period for completion of the Services and/or
the Contract Price, then such time period and/or Contract Price shall be
correspondingly increased or decreased, to the extent that the Consultant has thereby
been affected in the performance of any of its obligations under the Contract.
Notwithstanding the foregoing, such additional or reduced cost shall not be separately
paid or credited if the same has already been accounted for by a contract modification
or a price adjustment.
28.1 The Client shall make available to the Consultant the Services and Facilities listed in
the Contract.
29.1 The Contract Price shall be expressed as a specific amount or amounts in the
Agreement representing the estimated amount for a Time-Based contract.
29.2 Payments shall be made in the currency or currencies of the contract price, unless
otherwise specified in the SCC.
29.3 In consideration of the Services performed by the Consultant under the Contract, the
Client shall make to the Consultant such payments in such manner as is provided by
the Contract.
30. Payment
30.1 The Contract Price shall be an estimated amount, based on the Breakdown of Cost
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
141
Part 3 - Section 7 General Conditions of Contract
30.7 A final payment shall be made against submission by the Consultant of a final
statement, identified as such and approved by the Client. The final statement shall be
deemed approved by the Client ninety calendar days after receipt by the Client unless
the Client, within this period, gives written notice to the Consultant specifying in detail
deficiencies in the Services, the deliverables or the final statement.
30.8 Any amount which the Client has paid or caused to be paid which is in excess of the
amounts actually payable in accordance with the provisions of the Contract, shall be
reimbursed by the Consultant to the Client within thirty days after receipt by the
Consultant of a notice thereof. Any such claim by the Client for reimbursement must be
made within twelve months after receipt by the Client of a final statement approved by
the Client.
31.1 All payments under the Contract shall be made in accordance with the payment
schedule specified in the SCC.
31.2 Unless otherwise stated in the SCC, where any payment is made in advance of any
deliverables as an advance payment, the payment shall be made against the provision
by the Consultant of a bank guarantee for the same amount, and shall be valid for the
period stated in the SCC.
31.3 Should the advance payment guarantee cease to be valid and the Consultant fails to re-
validate it, a deduction equal to the amount of the advance payment may be made by
the Client from future payments due to the Consultant under the contract.
31.4 If a Contract is terminated for any reason, the guarantee securing the advance may be
invoked in order to recover the balance of the advance still owed by the Consultant.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
142
Part 3 - Section 7 General Conditions of Contract
32.1 Unless otherwise specified in the SCC, payments shall be made by the Client, no later
than sixty days after submission of a request for payment by the Consultant.
32.2 The Consultant’s request for payment shall be made to the Client in writing,
accompanied by invoices and supporting documents. The supporting documentation
required shall be as specified in the SCC.
32.3 The Client shall notify the Consultant of the inadmissibility of a request for payment due
to an error, discrepancy, omission or any other reason so that the Parties may resolve
such error, discrepancy, omission or other fault and agree a solution to enable payment
of the corrected request for payment. The Client shall not unreasonably withhold
payment of any undisputed portion of a request for payment. Should any discrepancy
be found to exist between actual payment made and costs authorised to be incurred by
the Consultant, the Client may add or subtract the difference from any subsequent
payments.
32.4 If the Client has delayed payments beyond fifteen (15) days after the due date stated in
the SCC, interest shall be paid to the Consultant for each day of delay at the rate stated
in the SCC.
33.1 Prices charged by the Consultant for the Services performed under the Contract shall
not vary from the prices quoted in the Contract, with the exception of any price
adjustments authorised in the SCC.
G. Settlement of Disputes
34.1 The Parties shall use their best efforts to settle amicably all disputes arising out of or in
connection with this Contract or its interpretation.
35.1 Any dispute between the Parties as to matters arising pursuant to this Contract that
cannot be settled amicably within thirty (30) days after receipt by one Party of the other
Party’s request for such amicable settlement may be submitted by either Party for
settlement in accordance with the laws of the Republic of Malawi.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
143
Part 3 - Section 8 Special Conditions of Contract 144
GCC 1.1 The Procurement Reference Number for the contract is: RA/CON/CR/UN-
MN/UP/2024-25/34
GCC 1.1 The Eligible Countries are those described in Section 5 of the Request for
Proposals document.
The documents forming the contract shall be interpreted in the following order
of priority:
Agreement
Notice of Acceptance
Terms of Reference
Roads Authority
Functional Building
Lilongwe 3
E mail: [email protected]
Town/City: (Insert)
Country: (Insert)
Telephone: ………………………………
Email:………………………………………
for the Roads Authority Eng. Ammiel Champiti, Chief Executive Officer
GCC 13.1 The period for expiration of the contract is: 12 months after the Commencement
Date.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
146
Part 3 - Section 8 Special Conditions of Contract
If the Consultant does not perform the Services in accordance with the Contract
and the agreed Work Program for a period of thirty (30) days. In this case the
Client shall give at least thirty (30) calendar days’ written notice of termination to
the Consultant.
If the Consultant does not perform the Services in accordance with the Contract
and the agreed Work Program then a deduction of 0.1% of the Lumpsum
Contract Price per delayed calendar day shall apply. The maximum deduction
shall be 3% of the lump sum contract price.
GCC The following activities are prohibited: N/A
18.3(b)
GCC 22.1 Failure to submit reports whether at intermediate stages or overall in relation to
the time periods specified in the Terms of Reference shall result to imposition of
liquidated damages equal to 1/1000th (one thousandth) of the value of the
consultant’s contract for the relevant phase payable per day of delay up to a
maximum of 15% (fifteen percent) of the consultant’s contract price.
GCC 23.1 The future use of documents is restricted as follows: the document shall not be
used for the purposes unrelated to the contract without the prior written
approval of the Client
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
147
Part 3 - Section 8 Special Conditions of Contract
GCC 31.1 The services will be executed on a Lump Sum Contract basis and the payment
schedule shall be as follows: -
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
148
Part 3 - Section 8 Special Conditions of Contract
GCC 31.2 An Advance Payment Guarantee shall be required in the format of the example
given in Section 9, Contract Forms, or similar approved in advance by the
Client.
The period of validity of the Advance Payment Guarantee shall be: 12 months
GCC 32.2 The following documentation shall be required to support requests for payment:
- Inception Report
- Draft Economic Feasibility and Preliminary Design Reports.
- Final Economic Feasibility and Preliminary Design Reports
- Draft Detailed Design Report.
- Final Detailed Engineering Design Report
- Training Reports
- Receipts
GCC 32.4 Interest shall be paid on late payments at the rate of:
Prime lending rate of the Reserve Bank of Malawi plus 1% or if not available the
Inter Bank Offered Rate and shall be calculated at simple rate.
Consultancy Services for the Feasibility Study and Detailed Engineering Design for the Upgrading of Ntcheu-Tsangano-Neno-Mwanza (S135/T396/T397) Road
149
Part 3 - Section 9 Contract Forms 150
Agreement 115
Advance Payment Security 117
151
Part 3: Section 9. Contract Forms
Contract Agreement
This Agreement is made the…………. day of the month of ……………………… between
The Government of Malawi acting through the Roads Authority of Private Bag B346,
Lilongwe 3 (the “Client ”) and ……………………………………….. of
…………………………………………………… (the “Consultant” ).
WHEREAS
(a) the Client has requested the Consultant to provide certain consultancy services
(hereinafter called the “Services”) as defined herein and attached to this Contract;
(b) the Consultant having represented to the Client that it has the required professional
skills, personnel and technical resources, has agreed to provide the Services on the
terms and conditions set forth in this Contract;
1. The documents forming the Contract shall be in the order of priority and stated
below as follows:
Agreement
Notice of Acceptance
Minutes of Contract Negotiations
Special Conditions of Contract (SCC)
General Conditions of Contract (GCC)
Terms of Reference
Technical Proposal with Standard Forms T4, T5, T6
Financial Proposal with Standard Forms F2, F3, F4
2. The mutual rights and obligations of the Client and the Consultant shall be as set forth
in the Contract, in particular:
(a) The Consultant shall carry out the Services in accordance with the provisions
of the Contract; and
(b) the Client shall pay the Consultant the Contract Price of
_____________________________________________________________
_____________________________________________________________
____________________________ (MWK____________________) or such
other sum as may become payable under the provisions of the Contract, at
the times and in the manner prescribed by the Contract.
152
Part 3: Section 9. Contract Forms
IN WITNESS WHEREOF, the Parties hereto have caused this Contract to be signed in their
respective names as of the day and year first above written.
Witnessed by:
______________________________________________________________
Name:
____________________________________________________________________
Position:
__________________________________________________________________
Witnessed by:
______________________________________________________________
Name:
____________________________________________________________________
153
Part 3: Section 9. Contract Forms
Note to Bidders: The Advance Payment Security should be on the letterhead of the issuing
Financial Institution and should be signed by a person with the proper authority to sign
documents that are binding on the Financial Institution.
Signed: [signature of person whose name and capacity are shown above]
Duly authorised to sign the Security for and on behalf of: [insert complete name of the
Financial Institution]
Dated on ____________ day of __________________, _______ [insert date of signing]
154