MTB- TGC-ANL-ELE-
Document No:
ITP-0014
Revision 00
PROJECT NAME: Power and Data Connection Provision to Retail PODS and
Carpet Replacements Central Processor (CP) Seating Areas in Terminal A Page Page 1 of 2
Rebus Projects Managements LLC
INSPECTION & TEST PLAN
Installation of Wiring Devices & Accessories
Inspection and Acceptance
Test /Inspection Criteria and Report
No. Activity Description Reference Documents Frequency Main
Requirements Subcontractor Engineer Reference No.
Contractor
Compliance with
requirements of relevant
Material Approval of Wiring As per Abu Dhabi International Prior to start to work
1. project Specification H H H MAR Approval
Airport Specification, Section on site
Devices Material Approval Request
262726
ADCD Regulation
Compliance with the project
As per ADIA Specification,
specifications Section 262726
Approval of Electrical Shop Drawing
2. Manufacturer As per ADIA Specification, H H H
System Shop Drawings Section 013300 Prior to start to work Approvals
Recommendation Approved for Construction on site
ADCD Regulation Drawing
Make / Brand Material
Model & Type As per ADIA Specification,
Wiring Devices delivered to Inspection
3. Material Inspection Request Section 262726 H H H
site Approved Method Statement Material Approval Request For each lot Request Forms.
Storage and Handling Supplier Delivery Note (MIR)
Section
Work Inspection
Request forms &
Mock Up Installation for As per ADIA Specification,
4. Approved Shopdrawing Section 262726 Clause 3 Mock Up Installation H H H Check List.
Wiring devices
Approved Method Statement
WIR
ELE-FM-0007
Legend: S- Surveillance Inspection W- Witness Inspection Point H- Mandatory Hold Point for Inspection R - Record Review
MTB- TGC-ANL-ELE-
Document No:
ITP-0014
Revision 00
PROJECT NAME: Power and Data Connection Provision to Retail PODS and
Carpet Replacements Central Processor (CP) Seating Areas in Terminal A Page Page 2 of 2
Rebus Projects Managements LLC
INSPECTION & TEST PLAN
Installation of Wiring Devices & Accessories
Inspection and Acceptance
Test /Inspection Criteria and Report
No. Activity Description Reference Documents Frequency Main
Requirements Subcontractor Engineer Reference No.
Contractor
Work Inspection
Request forms &
As per ADIA Specification,
Check all Installations of
5. Approved Shop Drawing Section 262726 Clause 3 H H S Check List.
Wiring Devices
Approved Method Statement Every Installation
WIR
FM-0007