CIVIL WORKS
GOVERNMENT OF GUJARAT
ROAD & BUILDING DEPARTMENT
Superintending Engineer
Surat (R&B) circle
Surat
Index
Sr No Section Description Page No
10 Section -9 Drawings 91
(ITB)
Table of Clauses
1. Scope of Bid
1.1 The Employer (Named in Appendix to ITB) invites bids for the Construction of works (as
defined in these documents and referred to as ‘the works”) detailed in the table given in
IFB. The bidders may submit bids for any or all of the works detailed in the table given in
IFB.
1.2 The successful bidder will be expected to complete the works by the intended completion
date specified in the Contract data.
1.3 Throughout these bidding documents, the terms ‘bid’ and ‘tender’ and their derivatives
(bidder/ tenderer, bid / tender, bidding/ tendering, etc.) are synonymous.
2. Source of Funds
2.1 The expenditure on this project will be met from the budget of Govt. of Gujarat / Govt. of
India for centrally sponsored projects.
3. Eligible Bidders
4.1 All bidders shall provide in Section 2, Forms of Bid and Qualification Information, a
preliminary description of the proposed work method and schedule, including drawings
and charts, as necessary. The proposed methodology should include a program of
construction backed with equipment planning and deployment duly supported with broad
calculations and quality assurance procedures proposed to be adopted justifying their
capability of execution and completion of work as per technical specifications, within
stipulated period of completion.
4.2 Deleted
4.3 Deleted
4.4 Deleted
#4.5 QUALIFICATION CRITERIA:
(Applicable for the works which require Post Qualification)
4.5.1 Qualification will be based on Applicant’s meeting all the following minimum pass/ fail criteria
regarding the Applicant’s general and particular experience, personnel and equipment
capabilities and financial positions, as demonstrated by the applicant’s responses in the forms
attached to the letter of application ( specified requirement for joint ventures are given under
para 4.6 below ) Subcontractors experience and resources shall not be taken in to account in
determining the applicants compliance with the qualifying criteria
Following enhancement factors will be used for the costs of works executed and the
financial figure to a common base value for works completed in India.
Applicant should indicate actual figures of costs and amount for the works
executed by them without accounting for the above-mentioned factors.
In case the financial figures and value of completed works are in foreign currency
the above enhanced multiplying factors will not be applied. Instead, the current market
exchange rate (State Bank of India BC Selling rate as on the last date of submission of the
bid) will be applied for the purpose of conversion of the amount in foreign currency into
India rupees.
(a) Achieved a minimum annual financial turnover (defined as billing for works in
progress and completed in all classes of civil engineering construction works only)
in any one year, over the last five years of the annual value of contract / contracts
applied for.
The works may have been executed by the applicant as prime contractor or as
a member of a joint venture or as a nominated sub-contractor. As subcontractor, he
should have acquired the experience of execution of all major items of works under
the proposed contract. In case a project has been executed by a joint venture, weight
towards experience of the project would be given to each joint venture in proportion
to their financial participation in the joint venture.
For these, a certificate from the employers shall be submitted along with the
application incorporating clearly the name of the work, contract value, billing
amount, date of commencement of works, satisfactory performance of the contractor
and any other relevant information.
The bidders should, however, undertake their own studies and furnish with their
bid, a detailed construction planning and methodology supported with layout and
necessary drawings and calculations to allow the employer to review their proposals. The
numbers, types and capacities of each plant/equipment shall be shown in the proposals
along with the cycle time for each operation for the given production capacity to match
the requirements.
The Applicant should give undertaking that he has access to, or has available, liquid assets
(aggregate of working capital, cash in hand and uncommitted bank guarantees) and / or
credit facilities up to 25 percent of the value of the contract / contracts applied.
4.5.7. The audited balance sheets for the last five years should be submitted, which must
demonstrate the soundness of the applicant’s financial position, showing long – term
profitability including an estimated financial projection for the next two years If
necessary, the employer will make inquiries with the applicant’s bankers.
4.5.9. Disqualification
Even though the applicants meet the above criteria, they are subject to be disqualified if
they have:
Made misleading or false representation in the forms, statements submitted, and / or
Record of poor performance such as abandoning the work, rescinding of contract for
which the reasons are attributable to the non – performance of the contractor; consistent
history of litigation awarded against the applicant or financial failure due to bankruptcy.
The rescinding of contract of a joint venture on account of reasons other than non –
performance, such as Most Experienced partner of joint venture pulling out, court
directions leading to breaking up of a joint venture before the start of work, which are not
attributable to the poor performance of the contractor will, however, not affect the
qualification of the individual partners.
(i) The lead partner shall meet not less than 50 percent of all criteria given in para 4.5.3
& 4.5.6 above. The joint venture must collectively satisfy the criteria of para 4.5.3 &
4.5.6 above. The experience of the other joint venture partners shall be considered if
it is not less than 30 percent of the qualifying criteria in para 4.5.3 & 4.5.6 above.
(ii) Individually each member must satisfy the requirements of para 4.5.7 & 4.5.8 above.
(b) Bid shall be signed so as to legally bind all partners, jointly and severally, and shall be
submitted with a copy of the joint venture agreement providing the joint and several
liabilities with respect to the contract.
4.6.2. Qualification of a joint venture does not necessarily qualify any of its partners
individually or as a partner in any other joint venture. In case dissolution of a joint
venture, each one of the constituent firms may qualify if they meet all the qualification
requirements, subject to the written approval of the Employer.
Applicants who meet the minimum qualification criteria will be qualified only if their
available bid capacity at the expected time of bidding is more than the total estimated cost
of the works. The available bid capacity will be calculated as under:
A = Maximum value of work executed in any one year during the last five years (updated
to the price level of the year indicated in appendix) taking into account the
completed as well as works in Progress.
B = Value at current price level of the existing commitments and ongoing works to be
completed during the next (period of completion of work for which bids are
invited); and
N = Number of years prescribed for completion of the works for which the bids are
invited.
Note :- In Case of joint venture, the available bid capacity will be applied for each
partner to the extent of his proposed participation in the execution of the
work.
4.8 Even though the bidders meet the above qualifying criteria, they are subject to be
disqualified if they have:
5.1. Each bidder shall submit only one bid for one package. A bidder who submits or participates
in more than one bid (other than as a subcontractor or in cases of alternatives that have
been permitted or requested) will cause all the proposals with the bidder’s participation to
be disqualified.
6. Cost of Bidding
6.1. The bidder shall bear all costs associated with the preparation and submission of his Bid,
and the Employer will in no case be responsible and liable for those costs.
7. Site Visit
7.1. The Bidder, at the Bidder’s own responsibility and risk is encouraged to visit and examine
the Site of work and its surrounding and obtain all information that may be necessary for
preparing the Bid and entering into a contract for construction of the Works.
The costs of visiting the site shall be at the Bidder’s own expense.
8.2. Volumes I, II, III and IV are available online and documents to be furnished by the bidder
in compliance to section 2 will be prepared by him and furnished as Volume- V in two
parts (refer clause 12).
8.3. The bidder is expected to examine carefully all instructions, conditions of contract,
contract data, forms, terms, technical specifications, bill of quantities, forms, Annexes and
drawings in the Bid Document. Failure to comply with the requirements of Bid
Documents shall be at the bidder’s own risk. Pursuant to clause 26 hereof, bids which
are not substantially responsive to the requirements of the Bid Documents shall be
rejected.
9.1 A prospective bidder requiring any clarification of the bidding documents may notify
the Employer in writing or through E-mail at the Employer’s address indicated in the
invitation to bid. The Employer will respond to any request for clarification which he
received earlier than 15 days prior to the deadline for submission of bids. Employer’s
response will be published on website including a description of the enquiry but without
identifying its source.
9.2.1. The bidder or his official representative is invited to attend a pre-bid meeting which will
take place at the address, venue, time and date as indicated in the appendix.
9.2.3. The bidder shall be required to submit any questions in writing or e-mail to reach the
Employer not later than 03 days before the meeting.
9.2.4 Minutes of the meeting, including the question raised (Without identifying the source of
enquiry) and the responses given will be published without delay on the tender website
i.e. www.nprocure.com. Any modification of the bidding documents listed in sub-
Clause 8.1 which may become necessary as a result of the pre-bid meeting shall be
made by the Employer exclusively through the issue of an Addendum pursuant to
Clause 10 and not through the minutes of the pre-bid meeting.
9.2.5. Non-attendance at the pre-bid meeting will not be a cause for disqualification of a bidder.
10.1 Before the deadline for submission of bids, the Employer may modify the bidding
documents by issuing addenda.
10.2. Any addendum thus issued shall be part of the bidding documents. The Employer will
assume no responsibility for the same.
10.3. To give prospective bidders reasonable time in which to take an addendum into account
in preparing their bids, the Employer may, at his discretion, extend as necessary the
deadline for submission of bids, in accordance with Sub-Clause 20.2 below.
11.1 All documents relating to the bid shall be in the English language.
12.1. The bid be submitted by the bidder as Volume V of the bid document (refer Clause 8.1)
shall be in two separate parts:
(v) Undertaking that the bid shall remain valid for the period specified in Clause 15.1
12.2. The Bidder shall submit the details / information pertaining to each part i.e.
technical as well as financial and must be submitted online only.
12.3. Following documents will be deemed to be part of the bid.
13.1 The Contract shall be for the whole works as described in Sub-Clause 1.1, based on the
priced Bill of Quantities submitted by the Bidder.
13.2 The bidder shall fill in rates and prices and line item total (both in figures and words) for
all items of the Works described in the Bill of Quantities along with total bid price
13.3 All duties, taxes, and other levies inclusive GST payable by the contractor under the
contract, or for any other cause shall be included in the rates, prices and total Bid Price
submitted by the Bidder. (GST will be inclusive)
13.4 Deleted
13.5 The rates and prices quoted by the bidder are subject to adjustment during the
performance of the Contract in accordance with the provisions of Clause 47 of the
Condition of Contract (Irrespective of the time limit and Bid Amount)
14.1 The unit rates and the prices quoted by the bidder shall be entirely in Indian Rupees. All
payments shall be made in Indian Rupees.
15.1 Bids shall remain valid for a period of not less than 120 days after the deadline date forbid
submission specified in Clause 20.
15.2 In exceptional circumstances, prior to expiry of the original time limit, the Employer may
request that the bidders may extend the period of validity for a specified period. A bidder
may refuse the request without forfeiting his bid security. A bidder agreeing to the request
will not be required or permitted to modify his bid, but will be required to extend the
validity of his security for a period of the extension, and in compliance with Clause 16 in
all respects.
16.1. The Bidder shall furnish, as part of his Bid, a Bid security in the amount as shown in
column 4 of the table of IFB for this particular work. This Bid security shall be in favor of
Employer as named in Appendix and may be in one of the following forms;
a. Bank Guarantee from any scheduled Indian bank, in the format given in Volume
III. (Bank Guarantee is applicable only for Bid Estimated Amount of 01 Crore
and above) and Bank Guarantee of Schedule and Private Banks shall be
considered as per GoG Finance Department’s Circular No. FD/MSM/e-
file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their latest amendment.
b. Fixed Deposit Receipt issued by any Scheduled Indian Bank or a foreign Bank
approved by the Reserve Bank of India.
OR
# A Valid Bid Security / EMD Exemption Certificate issued by
(1) Road & Building Department or
(2) Narmada Water Resources, Water Supply and Kalpsar Department of Govt of
Gujarat. Exemption Certificate is applicable only when Registration
Certificate of Appropriate Class and Category of Approved Contractors is
required as eligible criteria of bidder.
16.3. Any bid not accompanied by an acceptable Bid Security and not secured as indicated in
Sub-Clauses 16.1 and 16.2 above shall be rejected by the Employer as non-responsive.
16.4. The Bid Security of unsuccessful bidders will be returned within 28 days of the end of
the bid validity period specified in Sub-Clause 15.1
16.5 The Bid Security of the successful bidder will be discharged when the bidder has signed
the Agreement and furnished the required Performance Security.
(a) If the Bidder withdraws the bid after Bid opening during the period of Bid validity.
(b) If the Bidder does not accept the correction of the Bid Price, if any or
(c) In the case of a successful Bidders, if the Bidder fails the specified time limit to
(i) Sign the Agreement; or
(ii) Furnish the requirement Performance Security.
(d) #If found necessary, the bidder will be intimated for negotiation, He will be
intimated maximum three times within the validity period for negotiation, If
contractor does not respond in time, his Bid Security (EMD) will be forfeited and
his tender will be rejected. Punitive action will be taken on such contractors. (As
per GoG R&B Dept’s Gr. No. S/22/2017/6369/D, Dt.08/06/2018)
17.1. Bidders shall submit offers that fully comply with the requirements of the bidding
documents, including the conditions of contract (including mobilization advance or time
for completion), basic technical design as indicated in the drawing and specifications.
Conditional offers or alternative offers will not be considered further in the process of
tender evaluation.
18.1. The Bidder shall prepare documents comprising the bid as described in Clause 12 of these
Instructions to bidder as the “Technical Bid “and “Financial Bid” in separate parts to be
uploaded.
19. Deleted
20.1. Complete Bids must be received online by the Employer at the tender website specified
above not later than the date indicated in appendix.
20.2. The Employer may extend the deadline for submission of bids by issuing an amendment
in accordance with Clause 10, in which case all right and obligation of the Employer and
the bidders previously subject to the original deadline will then be subject to the new
deadline.
21. Deleted
22.1. Bidders may modify or withdraw their bids online before the deadline prescribed in
Clause 20 or pursuant to Clause 23.
22.2 Deleted
22.3. No bid shall be modified or withdrawn after the deadline for submission of Bid.
22.4. Withdrawal or modification of a bid between the deadline for submission of bids and the
expiration of the original period of bid validity specified in Clause 15.1 above or as
extended pursuant to Clause 15.2 may result in the forfeiture of the Bid security pursuant
to Clause 16.
23.1 The Employer will open all the Bids received including modifications made pursuant to
Clause 22, in the presence of the Bidders or their representatives who choose to attend at
time, date and the place specified in Appendix in the manner specified in Clauses 20 and
23.3, In the event of the specified date of Bid opening being declared a holiday for the
Employer, the Bids will be opened at the appointed time and location on the next working
day.
23.2. Deleted.
23.3. The “Technical Bid” shall be opened. The amount, form and validity of the bid security
furnished with each bid will be announced. If the bid security furnished does not conform
to the amount and validity period as specified in the invitation for bid (ref. Column 4 and
paragraph 3), and has not been furnished in the form specified in Clause 16, the technical
bid will not be opened.
23.4. (i) Subject to confirmation of the bid security by the issuing Bank, the bids accompanied
with valid bid security will be taken up for evaluation with respect to the
Qualification information and other information furnished in part I of the bid
pursuant to Clause 12.1.
(ii) If required, the bidder will be asked in writing to clarify his Qualification
Documents with respect to any required clarification.
(iii) The bidders will respond in not more than 7 days of issue of the clarification letter.
(iv) Immediately (usually within 3 or 4 days), on receipt of these clarification the
Evaluation Committee will finalize the list of responsive bidders whose financial
bids are eligible for consideration.
23.5. Deleted
23.6 At the time of opening of “Financial Bid”, the names of the bidders were found
responsive in accordance with Clause 23.4(iv) will be announced. The bids of only these
bidders will be opened. The responsive Bidders’ names, the Bid prices, the total amount
of each bid, any discount and such other details as the Employer may consider
appropriate, will be announced by the Employer at the opening.
23.7 the time of opening of “Financial Bid”, the names of the bidders were found responsive in
accordance with Clause 23.4(iv) will be announced. The bids of only these bidders will
be opened. The responsive Bidders’ names, the Bid prices, the total amount of each bid,
any discount, and such other details as the Employer may consider appropriate, will be
announced by the Employer at the opening.
23.8 In case bids are invited for more than one package, the order for opening of the “Financial
Bid” shall be in order of Estimated amount of Bids from highest to lowest.
23.9 The Employer shall prepare minutes of the Bid opening, including the information
disclosed to those present in accordance with Sub-Clause 23.6.
25.1. To assist in the examination, evaluation, and comparison of Bids, the Employer may, at
his discretion, ask any Bidder for clarification of his Bid, including breakdowns of unit
rates. The request for clarification and the response shall be in writing or by e- mail, but
no change in the price or substances of the Bid shall be sought, offered, or permitted
except as required to confirm the correction of arithmetic errors discovered by the
Employer in the evaluation of the Bids.
25.2 Subject to sub-clause 25.1, no Bidder shall contact the Employer on any matter relating to
his Bid opening to the contract is awarded. If the Bidder wishes to bring additional
information to the notice of the Employer, it should do so in writing.
25.3. Any effort by the Bidder to influence the Employer in the Employer's bid evaluation, bid
comparison or contract award decision may result in the rejection of the Bidders’ bid.
26.1 During the detail evaluation of "Technical Bid", the Employer will determine whether
each Bid (a) meets the eligibility criteria defined in Clause 3 and 4; (b) has been properly
signed; (c) is accompanied by the required securities and; (d) is substantially responsive to
the requirements of the Bidding document. During the detailed evaluation of the
“Financial Bid”, the responsiveness of the bids will be further determined with respect to
the remaining bid conditions, i.e., priced bill of quantities, technical specifications, and
drawings.
26.2 A substantially responsive “Financial Bid” is one which confirms all the terms, conditions
and specifications of bidding documents, without material deviation or reservation. A
material deviation or reservation is one (a) which affects in any substantial way the scope,
quality, or performance of the Works; (b) which limits in any substantial way, inconsistent
with the Bidding documents, the Employer’s rights or the Bidder’s obligations under the
Contract; or (c) whose rectification would affect unfairly the competitive position of other
Bidders presenting substantially responsive Bids.
26.3 If a “Financial Bid” is not substantially responsive, it will be rejected by the Employer,
and may not subsequently be made responsive by correction or withdrawal of the non-
conforming deviation or reservation.
27. Deleted
28. Deleted
29.1. The Employer will evaluate and compare only the Bids determined to be substantially
responsive in accordance with Sub-Clause 26.2.
29.2. Deleted.
Sign. of the Contractor Sign. of the Executive Engineer 20
29.3. The Employer reserves the right to accept or reject any variation or deviation. Variation
and deviations and other factors, which are in excess of the requirements of the Bidding
documents or otherwise result in unsolicited benefits for the Employer, shall not be taken
in to account in Bid evaluation.
29.4. The estimated effect of the price adjustment conditions under Clause 47 of the Conditions
of Contact, during the period of implementation of the Contract, will not be taken in to
account in Bid evaluation.
29.5. If the Bid of the successful Bidder is seriously unbalanced in relation to the Engineer’s
estimate of the cost of work to be performed under the contract the Employer may require
the Bidder to produce detailed consistency of those prices with the construction methods
and schedule proposed. After evaluation of the price analyses, the Employer may require
that the amount of the performance security set forth in Clause 34 be increased at the
expense of the successful /bidder to a level sufficient to protect the Employer against
financial loss in the event of default of the successful Bidder under the Contract.
29.6. A bid which contains several items in the bill of Quantities which are unrealistically
priced low and which cannot be substantiated satisfactorily by the bidder may be rejected
as non-responsive.
30. Deleted
31.1. Subject to Clause 32, the Employer will award the contract to the Bidder whose Bid has
been determined.
(i) to be substantially responsive to the Bidding documents and who has offered the
lowest evaluated Bid Price; and
(ii) to be within the available bid capacity adjusted to account for his bid price which
is the lowest evaluation in any of the packages opened earlier than the one
consideration.
In no case, the contract shall be awarded to any bidder whose available bid
capacity is less than the evaluated bid price, even if the said bid is the lowest evaluated
bid. The contract will in such cases be awarded to the next lowest bidder at his evaluation
bid price.
32. Employer’s Right to Accept any Bid and to Reject any or all Bids
32.1. Notwithstanding Clause 31, the Employer reserves the right to accept or reject any Bid,
and to cancel the Bidding process and reject all Bids, at any time prior to the award of
contract, without thereby incurring any liability to the affected bidder or Bidder or any
obligation to inform the affected Bidder or Bidders of the grounds for the Employer’s
action.
33.1. The Bidder whose Bid has been accepted will be notified of the award by the Employer
prior to expiration of the Bid validity period by cable, telex or facsimile confirmed by
registered letter. This letter (hereinafter and in the condition of contract called the “Letter
of Acceptance”) will state the sum that the Employer will pay the Contractor in
consideration of the execution, completion, and maintenance of the Works by the
Contractor as prescribed by the Contract (hereinafter and in the Contract called the
“Contract Price”).
33.2 The notification of award will constitute the formation of the contract, subject only to the
furnishing of a performance security in accordance with the provisions of Clause.
33.3. The Agreement will incorporate all agreements between the Employer and the successful
Bidder. It will be signed by the Employer and to the successful Bidder, within 28 days
following the notification of award along with the Letter of Acceptance. Within 21 days of
receipt, the successful Bidder will sign the Agreement and deliver it to the Employer.
33.4. Upon the furnishing by the successful Bidder of the Performance Security, the Employer
will promptly notify the other Bidders that their Bids have been unsuccessful.
34.1. (A) Within 10 (Ten) days of receipt of Letter of Acceptance, the successful Bidder shall
furnish to the Employer an irrevocable and unconditional guarantee from a Bank in
the form set forth in Section 8 (the “Performance Security”) for an amount equal to
5% (five percent) of its Contract Price. In case of bids mentioned below, the
successful Bidder, along with the Performance Security,
(a) If the Contract Price offered by the Selected Bidder is lower than 10% but
upto 20% of the Estimated Project Cost, then the Additional Performance
Security shall be calculated @ 20% of the difference in the (i) Estimated
Project Cost (as mentioned in Bid Document) - Minus 10% of the Estimated
Project Cost and (ii) Contract Price offered by the selected Bidder.
(b) If the Contract Price offered by the Selected Bidder is lower than 20% of the
Estimated Project Cost, then the Additional Performance Security shall be
calculated @ 30% of the difference in the (i) Estimated Project Cost (as
mentioned in Bid Document) - Minus 10% of the Estimated Project Cost and
(ii) Contract Price offered by the selected Bidder.
(c) This Additional Performance Security shall be treated as part of the
Performance Security.
(B) The Performance Security shall be valid beyond 60(sixty) days of the Defects
Liability Period and the Additional Performance Security shall be valid beyond 28
(twenty-eight) days of Project Completion Date.
34.2. If the performance security is provided by the successful Bidder in the form of a Bank
Guarantee, it shall be issued either (a) at the Bidder’s option, by a
Nationalized/Scheduled Indian bank or (b) by a foreign bank located in India and
acceptable to the Employer. As per GoG Finance Department’s Circular No.
FD/MSM/e-file/4/2023/0057/D.M.O. Date 21/04/2023 or as per their latest amendment.
34.3. Failure of the successful Bidder to comply with the requirement of Sub-Clause 34.1
shall constitute sufficient grounds for cancellation of the award and forfeiture of the Bid
Security.
35.1 The Employer will provide an Advance payment on the Contract Price as stipulated in
the Conditions of Contract, subject to maximum amount, as stated in the Contract Data.
36. Deleted
37.1 The Employer will reject a proposal if it determines that the Bidder recommended for
award has engaged in corrupt or fraudulent practices in completing for the contract in
question and will declare the firm ineligible, either indefinitely or for a stated period of
time, to be awarded a contract with National Highways Authority of India/ State PWD
and any other agencies, if it at any time determines that the firm has engaged in corrupt
or fraudulent practices in completing for the contractor, or in execution.
37.2 Furthermore, Bidders shall be aware of the provision stated in Sub- Clause 59.2 of the
Conditions of Contract.
The contractors shall also give a list of machineries in his possession and which they propose to
use on the work.
In case the contractor or partner of the contractor firm is a Civil Graduate Engineer,
Employment of a separate Engineer will not be necessary provided that the Engineer partner
himself attends the execution of the work on the site.
Within 15 days of issue of work-order the Contractor will have to furnish to the Deputy
Executive Engineer-in-charge of the work the Name, Qualifications, copy of marksheet,
Colour Photograph and the appointment order issued such engineers engaged for this
contract work. If 15 days after issue of work order such designated Site Engineers do not
resume or do not remain present on site of work, the recovery at the rate of Rs.15,000-00
per month per Engineer will be made from the bills/deposit/dues of the contractor. Such
recovery shall be non-refundable.
The information to be filled in by the Bidder in the following pages will be used for the
purpose of post qualification as provided for in Clause 4 of the Instruction to Bidders. This
information will not be incorporated in the Contract.
Place of registration
(Attach)
15.2.1 Work performed as prime contractor, work performed in the past as a nominated sub-
contractor will also be considered the sub-contract involved execution of all main items of
work described in the bid documents, provided further that all other qualification criteria
are satisfied (in the same name) on works of a similar nature over the last five years** and
in current year before the submission of the bid.
Project Name of Description Contract Value of Date of Stipulated Actual date Remark
Name the of work No. contract issue period of of explaining
Employer (Rs. of completion completion* reasons for
Crore) work Delay & work
order Completed
1.4 Information on Bid Capacity (works for which bids have been submitted and works which
are yet to be completed) as on the date of this bid.
1.5 Availability of key items of Contractors Equipment for carrying out the works (Ref.
Clause 4.5.5). The Bidder should list all the information requested below.
Attach copies of certificates on possession of valid license for executing water supply/
sanitary work/ building electrification works.
1.9 Evidence of access to financial resources to meet the qualification requirements: cash in
hand, lines of credit, etc. List them below and attach copied documents.
1.10 Name, address, and telephone, telex, and fax numbers of the Bidders bankers who may
provide references if contacted by the Employer.
1.12. Statement of compliance under the requirements of Sub Clause 3.2 of the instruction to
Bidders. (Name of Consultant engaged for project preparations is *................................ )
1.13 Proposed work method and schedule. The Bidder should attach descriptions, drawings and
charts as necessary to comply with the requirements of the Bidding documents. (Refer
ITB Clause 4.1)
1.14 Programme
2. Deleted
3. Additional Requirements
3.1 Bidders should provide any additional information required to fulfill the
requirements of Clause 4 of the Instructions to the Bidders, if applicable.
(i) Affidavit
(ii) Undertaking
BANK CERTIFICATE
(Signature)
Name of Bank
of the Bank
1. I, the undersigned, do hereby certify that all the statements made in the required
attachments are true and correct.
2. The undersigned also hereby certifies that neither our firm M/s.
have not abandoned any work of
Government of Gujarat/Government of India/any Board or Corporation under
Government of Gujarat/Government of India nor any contract awarded to us for such
works have been rescinded, during last five years prior to the date of this bid.
3. The undersigned hereby authorize(s) and request (s) any bank, person, firm or
corporation to furnish pertinent information deemed necessary and requested by the
Department to verify this statement or regarding any (our) competence and general
reputation.
4. The Undersigned understands and agrees that further qualifying information may be
requested, and agrees to furnish any such information at the request of the Department/
Project implementing agency.
Title of Officer
Name of Firm
Date
Title of officer
Name of firm
DATE
A. GENERAL.
1. Definitions
1.1 Terms which are defined in the Contract Data are not also defined in the Conditions of
Contract but keep their defined meaning.
Bill of Quantities means the priced and completed Bill of Quantities forming
part of the Bid
The Completion Date is the date of completion of the Works as certified by the
Engineer in accordance with Sub Clause 55.1
The Contract is the contract between the Employer and Contractor to execute,
complete and maintain the Works till the completion of Defects Liability Period. It
consists of the documents listed in Clause 2.3 below.
The Contract data defines the documents and other information which comprise
the Contract.
The Contractor is a person or corporate body whose Bid to carry out the Work
has been accepted by the Employer.
The Contract Price is the price stated in the Letter of Acceptance and thereafter
as adjusted in accordance with the provisions of the Contract.
The Defects Liability Period is the period named in the Contract Data and
calculated from the Completion Date.
The Employer is the party who will employ the Contractor to carry out the
Works.
The Engineer is the person named in the Contract Data (or any other competent
person appointed and notified to the contractor to act in replacement of the Engineer)
who is responsible for supervising the Contractor, administering the Contract, certifying
payments due to the Contractor, issuing and valuing Variations to the Contract,
awarding extensions of time, and valuing the Compensations Events.
The Initial Contract Price is the Contract Price listed in the Employer’s Letter
of Acceptance.
The Start Date is given in the Contract Data. It is the date when the Contractor
shall commence execution of the works. It does not necessarily coincide with any of the
Site Possession Dates.
A Variation is an instruction given by the Engineer, which varies the Works. The
Works are what the Contract requires the Contractor to construct, install,
and turn over to the Employer, as defined in the Contract Data.
2. Interpretation
2.1 In interpreting these Conditions of Contract, singular also means plural, male also
means female or neuter and the other way around. Heading have no significance.
Words have their normal meaning under the language of the Contract unless
specifically defined. The Engineer will provide instructions clarifying queries
about Conditions of Contract.
2.3 The documents forming the Contract shall be interpreted in the following order of
priority
(1) Agreement
(2) Letter of Acceptance, notice to proceed with works
(3) Contractor’s Bid
3.1 The language of the Contract and the law governing the Contract are stated in the
Contract Data.
4. Engineers Decisions
4.1 Except where otherwise specifically stated, the Engineer will decide contractual
matters between the Employer and the Contractor in the role representing the
Employer.
5. Delegation
5.1 The Engineer may delegate any of his duties and responsibilities to other people
after notifying the Contractor and may cancel any delegation after notifying the
Contractor.
6. Communications
6.1 Communications between parties which are referred to in the conditions are
effective only when in writing. A notice shall be effective only when it is delivered
(in terms of Indian Contract Act).
7. Sub-Contracting
7.1 The Contractor may subcontract any portion of work, up to a limit specified in
contract data, with the approval of the engineer but may not assign the Contract
without the approval of the Employer in writing. Subcontracting shall not alter the
Contractor’s obligations. Sub-contracting of supply or specific items of work is
not allowed.
7.2 The sub-contractor must be registered in appropriate class and category for the part
of work to be subcontracted.
8. Other Contractors
8.1 The Contractor shall cooperate and share the Site with other contractors, public
authorities, utilities and the Employer between the dates given in the Schedule of
other Contractor. The Contractors shall as refer to in the Contract Data, also
provide facilities and services for them as described in the Schedule. The
employer may modify the schedule of other contractors and shall notify the
contractor of any such modifications.
10.1 The Employer carries the risk which these Contract states are Employer’s risks,
and the Contractor carries the risks which these Contracts states are Contractors
risk.
11. Employer’s Risks
11.1 The employer is responsible for the excepted risks which are (a) in so far as they
directly affect the execution of the Works, the risks of war, hostilities, invasion, act
of foreign enemies, rebellion, revolution, insurrection or military or usurped
power, civil war, riot commotion or disorder (unless restricted to the Contractor’s
employees), and contamination from any nuclear fuel or nuclear waste or
radioactive toxic explosive.
13. Insurance
13.1 The Contractor shall provide, in the joint names of the Employer and the
Contractor, insurance cover from the Start date to the end of the Defects Liability
Period, in the amounts and deductibles stated in the Contract data for the
following events which are due to the Contractor’s risks:
13.5 Both parties shall comply with any conditions of the insurance policies.
16.1 The Contractor shall construct and install the works in accordance with the
specification and Drawings.
18.1 The Contractor shall submit Specifications and Drawings showing the proposed
Temporary works to the Engineer, who is to approve them if they comply with the
Specifications and drawings.
18.3 The Engineer’s approval shall not alter the contractor responsibility for design of
the Temporary works.
18.4 The Contractor shall obtain approval of third parties to the design of the
Temporary works where required.
18.5 All Drawings prepared by the Contractors for the execution of the temporary or
permanent work are subject to prior approval by the Engineer before their use.
19. Safety
19.1 The Contractor shall be responsible for the safety of all activities on the Site.
23. Instructions
23.1 The Contractor shall carry out all instructions of the Engineer pertaining to works
which comply with the applicable laws where the site is located.
23.2 The Contractor shall permit the Employer to inspect the Contractor’s accounts
and records relating to the performance of the Contractor and to have them audited
by auditors appointed by the Employer, if so required by the Employer.
24. Disputes
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the decision was
wrongly taken, the decision shall be referred to #Superintending Engineer, Surat
(R&B) circle, Surat (Higher Authority)within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the matter for
conciliation within 15 days from the decision given by the #Superintending
Engineer.
24.2
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer, Surat (R&B) circle, Surat both the
parties have to refer to the Chief Engineer concern for the conciliation
process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with
the decision of the #Superintending Engineer, both the parties have to refer to
the #Secretary, Roads & Building Department, Government of Gujarat for
the conciliation process.
26. Deleted
27.1 Within the time stated in the Contract Data the Contractor shall submit to the
Engineer for approval a Programme showing the general methods, arrangements
orders, and timing for all the activities in the works along with monthly cash flow
forecast.
27.2 An update of the Programme shall be a programme showing the actual progress
achieved on each activity and the effect of the progress achieved on the timing of
the remaining work including any changes to the sequence of the activities.
27.3 The Contractor shall submit to the Engineer, for approval an updated programme
at intervals no longer than the period stated in the Contract data. If the Contractor
does not submit an updated programme within this period, the Engineer may
withhold the amount stated in the Contract data from the next payment after the
date on which the overdue programme has been submitted.
27.4 The Engineer’s approval of the programme shall not alter the Contractor’s
obligations. The Contractor may revise the programme and submit it to the
Engineer again at any time. A revised programme is to show the effect of
Variations and Compensations events.
28.1 The Engineer shall extend the Intended Completion Date if a compensation Event
occurs or a Variation is issued which makes it impossible for completion to be
achieved by the Intended Completion Date without the Contractor taking steps to
accelerate the remaining work and which would cause the Contractor to incur
additional cost.
28.2 The Engineer shall decide whether and by how much to extend the Intended
Completion Date within 35 days of the Contractor asking the Engineer for a
decision upon the effect of a compensation event or Variation and submitting full
supporting information. If the Contractor has failed to give early warning of a
delay or has failed to cooperate in dealing with a delay, the delay by this failure
shall not be considered in assessing the new Intended Completion Date.
28.3 The Engineer shall within 14 days of receiving full justification from the
contractor for extension of Intended Completion Date refer to the Employer his
decision. The employer shall in not more than 21 days communicate to the
engineer the acceptance or otherwise of the Engineer’s decision. If the employer
fails to give his acceptance, the Engineer shall not grant the extension and the
contractor may refer the matter under Clause 24.1
29. Deleted
31.2 The Engineer shall record the business of management meetings and is to provide
copies of his record to those attending the meeting and to the Employer. The
responsibility of the parties for actions to be taken is to be decided by the Engineer
either at the management meeting or after the management meeting and stated in
writing to all who attended the meeting.
32.1 The Contractor is to warn the Engineer at the earliest opportunity of specific likely
future events or circumstances that may adversely affect the quality of the work,
increase the Contract price or delay the execution of works. The Engineer may
require the contractor to provide an estimate of the expected effect of the future
event or circumstance on the contract price and completion date. The estimate is to
be provided by the Contractor as soon as reasonably possible.
32.2 The Contractor shall cooperate with the Engineer in making and considering
proposals for how the effect of such an event or circumstance can be avoided or
reduced by anyone involved in the work and in carrying out any resulting
instruction of the Engineer.
33.1 : Defect liability period : The contractor shall be responsible to make good and
remedy at his own expense any defect which may develop or may be noticed
before the period mentioned hereunder from the certified date of completion. The
Engineer in charge shall give the contractor a notice in writing about the defects
and the contractor shall make good the same within 15 days of receipt of the
notice. In the case of failure on the part of the contractor, the Engineer- in-charge
may rectify or remove or re-execute the work at the risk & cost of the contractor.
The Engineer-in-charge shall be entitled to appropriate the whole or any part of the
amount of security deposit towards the expenses, if any, Incurred by him in
rectification, removal or re-execution. The Defects Liability period shall be as
under….
(a) For all works costing up to Rs. 50,000 (amount put to tender), the period shall be 3
Months from the certified date of completion.
(b) For all works costing more than Rs. 50,000 and up to Rs. 1 crore (amount put
tender), the period shall be 12 (Twelve) months from the certified date of
completion or one monsoon, whichever is later.
(c) For major projects costing more than Rs. 1 crore, the period shall be 36 Months
from the certified date of completion which should include three monsoons.
(d) For original building works the defect liability period will be 4 years or elapse of 4
monsoon period following date of possession of building taken over by user
agency following the certified date of completion, whichever is later.
For the purpose of deciding the monsoon period, the 30th September shall be
treated as the last date.
(1) The flakiness and elongation index (combined) for coarse aggregates under no
circumstances shall exceed the allowable limit set forth in the relevant clause
for the material in question.
(2) 2% of the amount eligible for the payment of bituminous items shall be
withheld till the miscellaneous items like earthwork in embankment / cutting
for side shoulders, side gutters, kilometer / indicator / guard stones, sign boards
etc. are completed in all respect by the contractor. After completion of the
miscellaneous items, the above said 2% withheld amount shall be released.
(Govt. of Gujarat's G.R. No.: TNC-10-2013-3(Part-3)/C, Dtd. 13/12/2013).
(3) Videography for the surface under Maintenance Guarantee is to be done as per
Govt. letter No.: SSR/10/2015-16/26/C, Dtd. 26/11/15 for the work costing
more than Rs. 5.00 Crore.
(4) Setting up of adequate laboratory & deployment of quality engineers.
The contractor shall have to set up the laboratory with adequate equipment.
Till the setting up of adequate laboratory is completed & reported of this to the
engineer (subject to due verification by engineer’s representative) by
contractor in writing, Rs.2,00,000/- shall be withheld. The qualified quality
Engineer shall be deployed exclusively for this contract by the contractors. If
quality Engineer is not deployed by contractor within one month after the date
of work order, the amount equivalent to Rs.20,000 per month shall be
recovered till the actual deployment of quality engineer. The amount so
recovered towards the deployment of quality engineers shall not be refunded.
(5) Asphalt work will have to be cross checked as per G.R. No.:
RGN/60/2006/35/C, dtd.31/05/07 before final bill is paid.
(6) Maintenance during Construction Period
During the Construction Period, the Contractor shall maintain, at his own risk
and cost, the existing lane(s) of the road so that the traffic worthiness and
safety thereof are at no time materially inferior as compared to their condition
10 (ten) days prior to the date of the Agreement, and shall undertake the
necessary repair and maintenance works for this purpose; provided that the
Contractor may, at his cost, interrupt and divert the flow of traffic if such
interruption and diversion is necessary for the efficient progress of works and
conforms to Good Industry Practice; provided
34.1 If the engineer instructs the Contractor to carry out a test not specified in the
Specification to check whether any work has a Defect and the test shows that it
does, the Contractor shall pay for the test and any samples. If there is no defect the
test shall be a Compensation Event.
34.2 #1% of the amount of work done should be deducted from R.A. Bill of the
contractor for testing the quality of material workmanship, irrespective of actual
charges.
34.3 Agency has to establish testing laboratory on site for the various test to be carried
out in the work for this purpose agency shall construct a pukka laboratory building
with all facility on site at location specified by the engineer in charge.
35.1 The engineer shall give notice to the Contractor of any defects before the end of
the defects Liability Period, which begins at Completion and is defined in the
contract data. The Defects Liability Period shall be extended for as long as Defects
remain to be corrected.
35.2 Every time notice of a Defect is given, the Contractor shall correct the notified
defect within the length of time specified by the Engineer’s notice.
36. Uncorrected Defects
36.1 If the Contractor has not corrected a defect within the time specified in the
Engineer’s notice, the Engineer will assess the cost of having the Defect corrected,
and the Contractor will pay this amount.
37.1 The bill of Quantities shall contain items for the constructions, installation,
testing and commissioning work to be done by the Contractor.
37.2 The bill of Quantities is used to calculate the Contract price. The Contractor is paid
for the quantity of the work done at the rate in the Bill of Quantities for each item.
38.1 The Engineer shall have power to make any alterations in or addition to the
original specifications , drawings, designs and instructions that may appear to him
to be necessary or advisable during the progress of the work and the contractor
shall be bound to carry out the work in accordance with any instruction in this
connection which may be given to him in writing signed by the Engineer and such
alteration shall not invalidate the contract and any additional work which the
contractor may be directed to do in the manner above specified as part of the work
shall be carried out by the contractor on the same conditions in all respects on
which he agreed to do the main work and at the same rate as are specified in the
tender for the main work.
Except that when the quantity of any item exceeds the quantity as in the tender by
more than 130%, the contractor will be paid for the quantity in excess of 130%, at
the rate entered in the SOR of the year during which the excess in quantity is first
executed.
39. Variations
40.1 If the additional or altered work includes any class of work for which no rate is
specified in this contract, then such class of work shall be carried out as under.
(i) At the rate derived from the item within the contract which is comparable to the
one involving additional or altered class of work; where there are more than one
comparable items, the item of the contract which is nearest in comparison with
regard to class or classes of the work involved shall be selected and the decision of
the Superintending Engineer as to the nearest comparable item shall be final and
binding on the contractor.
(ii)If the rate cannot be derived in accordance with (i) above, such class of works shall
be carried out at the rate entered in the Schedule of Rates of the division
(iii) If it is not possible to arrive at the rate from (i) and (ii) above, such class of work
shall be carried out at the rate decided by the competent authorities on the basis of
detailed rate analysis after hearing the contractor before a Committee of two
Superintending Engineers stationed at the same place or the nearest place.
40.2 If the additional or altered work, for which no rate is entered in the “Schedule of
Rates” of the Division is ordered to be carried out before the rate is agreed upon,
then the contractor shall within seven days of the date of receipt by him of the
order to carry out the work, inform the Engineer-in-charge of the rate, which it is
his intention to charge for such class of work and if the Engineer in charge does
not agree to this rates, he shall by notice in writing be at liberty to cancel his order
to carry out such class of work and arrange to carry it out in such manner as he
may consider it advisable, provided always that if the contractor shall commence
work or incur any expenditure in regard thereof before the rates shall have been
determined as lastly herein before mentioned, then in such cases he shall only be
entitled to be paid in respect of the work carried out or expenditure incurred by
him prior to the date of the determination of the rate as aforesaid according to such
rate or rates as shall be fixed by the Engineer-in-charge. In the event of the dispute,
the decision of the Superintending Engineer of the Circle shall be final.
Where, however, the work is to be executed according to the designs,
drawings and specifications recommended by the contractor and accepted by the
competent authority, the alternation above referred to shall be within the scope of
such designs, drawings and specifications appended to the tenders.
The time limit for the completion of the work shall be extended in the
proportion that the increase in the cost occasioned by alterations bears to the cost
of the original work and the certificate of the Engineer-in-charge as to such
proportion shall be final and conclusive.
41.1 When the programme is updated, the contractor is to provide the engineer with an
updated cash flow forecast.
42.1 The Contractor shall submit to the Engineer monthly statements of the estimated
value of the work completed less the cumulative amount certified previously.
42.2 The Engineer shall check the Contractor’s monthly statement within 14 days and
certify the amount to be paid to the Contractor after taking in to account any credit
or debit for the month in question in respect of materials for the works in the
relevant amounts and under conditions set forth in sub-clause
32.3 of the Contract Data (secured Advance).
42.4 The value of work executed shall comprise the value of the quantities of the items
in the Bill of Quantities completed.
42.5 The value of work executed shall include the valuation of variations and
compensation events.
42.6 The Engineer may exclude any item certified in a previous certificate or reduce the
proportion of any item previously certified in any certificate in the light of later
information
43. Payments
43.1 Payments shall be adjusted for deductions for advance payments, retention, other
recoveries in terms of the contract and taxes at source, as applicable under the law.
The Employer shall pay the Contractor the amounts certified by the Engineer
within 28 days of the date of each certificate.
43.2 Payment of GST (prevailing rates) on the amount payable under the contract to the
Contractor will be made by the Employer. Hence, it is the responsibility of the
contractor to pay the GST inclusive to the concerned Authority.
43.3 Items of the works for which no rate or price has been entered in will not be paid
by the Employer and shall be deemed covered by other rates and prices in the
Contract.
44.1 The following are compensation Events unless they are caused by the Contractor:
(a) The Employer does not give access to a part of the Site by the site
Possession date stated in Contract data to the Contractor
44.2 In case of compensation event occurs and it prevents the work being completed
beyond the Intended Completion Date then Authority will approve EOT with
eligible contractual price escalation.
45.1 The rates quoted by the Contractor must be inclusive of all taxes prevailing on due
date of bid submission except GST. However, any subsequent changes in the tax
structure by Government after due date of bid submission will be compensated (+/-
) on availability or submission of actual documentation. Contractor will have to
intimate Engineer regarding changes occurred in the tax structure after bid
submission. If the contractor fails to provide such information and if any financial
obligation may arise due to change in tax structure, same will be recovered from
the contractor.
45.2 GST will be paid separately on the bills. Hence, it is the responsibility of the
contractor to pay the GST to the concerned Authority.
46. Currencies.
46.1 All payment shall be made in Indian Rupees.
47.1 Contract price shall be adjusted for increase or decrease in rates and price of
labour, materials, fuels and lubricants in accordance with the following principles
and procedures and as per formula given in the contract data:
(a) The price adjustment shall apply for the work done from the start date given in
the contract data up to end of the initial intended completion date or extensions
granted by the Engineer and shall not apply to the work carried out beyond the
stipulated time for reasons attributable to the contractor.
(b) The price adjustment shall be determined during each month from the formula
given in the contract data.
(c) Following expressions and meanings during to the work done during each
month
R = Total value of work done during the month. It would include the amount
of secured advance granted, if any, during the month less the amount of
secured advance recovered, if any during the month. It will exclude value for
works executed under variations for which price adjustment will be worked
separately based on the terms mutually agreed.
47.2 To the extent that full compensation for any rise or fall in costs to the contractor is
not covered by the provisions of this or other clause in the contract, the unit rates
and prices included in the contract shall be deemed to include amounts to cover the
contingency of such other rise or fall in costs.
48. Retention
48.1 The Employer shall retain from each payment due to Contractor the proportion
stated in the Contract Data until Completion of the whole of the Works.
48.3 On completion of the whole works, the contractor may substitute retention money
with an “on demand” Bank guarantee.
49.1 The Contractor shall pay liquidated damages to the Employer at the rate per day
stated in the Contract Data for each day that the Completion Date is later than the
Intended Completion Date (for the whole works or the milestone as stated in the
contract data). The total amount of liquidated damages shall not exceed the amount
defined in the Contract Data. The Employer may deduct liquidated damages from
payment due to the Contractor. Payment of liquidated damages does not affect the
Contractor’s liabilities.
49.2 If the Intended Completion Date is extended after liquidated damages have been
paid, the Engineer shall correct any overpayment of liquidated damages by the
Contractor by adjusting the next payment certificate. The Contractor shall not be
entitled for any interest on the over payment calculated from the date of payment
to the date of repayment.
49.3 If the contractor fails to comply with the time for completion as stipulated in the
tender, then the contractor shall pay to the employer the relevant sum stated in the
Contract Data as Liquidated damages for such default and not as penalty for
everyday or part of day which shall elapse between relevant time for completion
and the date stated in the taking over certificate of the whole of the works on the
relevant section, subject to the limit stated in the contract data.
The employer may, without prejudice to any other method of recovery
deduct the amount of such damages from any monies due or to become due to the
contractor. The payment or deduction of such damages shall not relieve
49.4 If, before the Time for Completion of the whole of the Works or, if applicable any
Section, a Taking Over Certificate has been issued for any part of the Works or of
a Section, the liquidated damages for delay in completion of the remainder of the
Works or of that Section shall, for any period of delay after the date stated in such
Taking-Over-Certificate, and in the absence of alternative provisions in the
Contract, be reduced in the proportion which the value of the part so certified bears
to the value of the whole of the Works or Section, as applicable. The provisions of
this Sub-clause shall only apply to the rate of liquidated damages and shall not
affect the limit thereof.
50 Bonus
50.1 If the contractor achieves completion of the whole of the works prior to the
intended Completion Date prescribed in Contract Data the Employer shall pay to
the contractor a sum stated in Contract Data as bonus for every completed month
but subjected to maximum amount as stated in Contract Data; which shall
elapse between the date of completion of all items of works as stipulated in the
contract, including variations ordered by the Engineer and the time prescribed in
Clause 17.
50.2 Bonus shall be paid only to works amounting to above INR 5 crore with time limit
of the works is equal or more than 6 months. The bonus would be paid as under
51.1 The Employer shall make advance payment (not to be paid less than two
installments except in special circumstances for which the reason to be Recorded
in writing) to the Contractor of the amounts stated in the Contract Date by the date
stated in the Contract Date, against provision by the Contactor of an Unconditional
Bank Guarantee in a form and by a bank acceptable to the Employer in amounts
and currencies equal to be at least 110% of the advance payment. The guarantee
shall remain effective until the
51.2 The Contractor is to use the advance payment only to pay for Equipment, plant
and Mobilization expenses required specifically for execution of the Works. The
Contractor shall demonstrate that advance payment has been used in this way by
supplying copies of invoices or other documents to the engineer.
51.3 The advance payment shall be repaid by deduction proportionate amount from
payments otherwise due to the Contractor, following the schedule of completed
percentages of the Works on a payment basis. No account shall be taken of the
advance payment or its repayment in assessing valuations of work done,
variations, price adjustments, Compensation Events, or Liquidated damages.
51.4 Deleted
52. Securities
52.1 The performance Security (including additional security for unbalanced bids) shall
be provided to the Employer no later than the date specified in the Letter of
Acceptance and shall be issued in an amount and form and by a bank or surety
acceptable to the Employer, and denominated in Indian Rupees. The performance
Security shall be valid until a date 60 days from the date of expiry of Defects
Liability Period and the additional security for unbalanced bids shall be valid until
a date 28 days from the date of issue of the certificate of completion.
53. Deleted
55. Completion
55.1 The Contractor shall request the Engineer to issue a Certificate of Completion of
the works and the Engineer will do so upon deciding that the work is completed.
56.1 The Employer shall take over the Site and the Works within seven days of the
Engineer issuing a certificate of Completion.
57.1 The Contractor shall supply to the Engineer a detailed final account of the total
amount that the Contractor considers payable as full and final settlement of all
claims under the Contract for items before the end of the Defects Liability Period.
The Engineer shall issue a Defect Liability Certificate and certify any final
payment that is due to the Contractor within 56 days of receiving the Contractor's
account if it is correct and complete. If it is not, the Engineer shall issue within 56
days a schedule that states the scope of the corrections or additions that are
necessary. If the Final Account is still unsatisfactory after it has been resubmitted,
the Engineer shall decide on the amount payable to the Contractor and issue a
payment certificate, within 56 days of receiving the Contractor’s revised account.
57.2 If reversal in characteristic of tender (L1 becoming L2) on account of excesses and
savings in final account is observed, the Engineer/Employer shall be at liberty to
restrict the final payment of BOQ items to the lowest amount evaluated of the bids
considering the final quantities and the rates quoted including the rebates if any.
Payment of variation items shall however be made at the rates approved by the
Employer, within 90 days from the physical completion of work.
58.1 If “as built” drawings and/or operating and maintenance manuals are required, the
Contractor shall supply them by the dates stated in the Contract data.
58.2 If the Contractor does not supply the Drawings and/or manuals by the dates stated
in the Contract data, or they do not receive the Engineer’s approval, the Engineer
shall withhold the amount stated in the Contract Data from payments due to the
Contractor.
59. Termination
59.1 The Employer or the Contractor may terminate the Contract if the other party
causes a fundamental breach of the Contract.
1. The contractor stops work for 28 days when no stoppage of work is shown on
the current programme and the stoppage has not been authorized by the
Engineer
2. The Engineer instructs the Contractor to delay the progress of the Works and
the instructions is not withdrawn within 28 days;
7. The Contractor has delayed the completion of works by the number of days for
which the maximum amount of liquidated damages can be paid as defined in
the Contract data; and
For the purpose of this paragraph: “corrupt practice” means the offering,
giving, receiving or soliciting of anything of value to influence the action of a
public official in the procurement process or in contract execution. “Fraudulent
practice” means a misrepresentation of facts in order to influence a procurement
process or the execution of a contract to the detriment of the borrower, and
includes collusive practice among Bidders (prior to or after bid submission)
designed to establish bid prices at artificial non-competitive levels and to deprive
the Borrower of the benefits of free and open competition.
59.3 When either party to the Contract gives notice of a breach of contract to the
Engineer for a cause other than those listed under Sub Clause 59.2 above, the
Engineer shall decide whether the breach is fundamental or not.
59.4 Notwithstanding the above, the employer may terminate the Contract for
convenience.
61. Property
61.1 All materials on the Site, Plant Equipments, Temporary Works and Works are
deemed to be property of the Employer, if the Contract is terminated because of a
Contractor’s default.
62.1 If the Contract is frustrated by the outbreak of war of by any other event entirely
outside the control of either the Employer or the Contractor the Engineer shall
certify that the Contract has been frustrated. The Contractor shall make the Site
safe and stop work as quickly as possible after receiving this certificate and shall
be paid for all work carried out before receiving it and for any work carried out
afterwards to which commitment was made.
63. LABOUR
The Contractor shall, unless otherwise provided in the Contract, make his
own arrangements for the engagement of all staff and labour, local or other, and
for their payment of housing, feeding and transport.
During continuance of the contact, the Contractor and his sub- contractor
shall abide at all times by all existing labour enactments and rules made
thereunder, regulations, notification and bye laws of the State or central
Government or local authority and any other labour law (including rules),
regulations, bye laws that may be passed or notifications that may be issued under
any labour law in future either by the State or the Central Government or the local
authority. Salient features of some of the major labour laws that are applicable to
the construction industry are given below. The Contractor shall keep the Employer
indemnified in case any action is taken against the Employer by the competent
authority on account of contravention of any of the provisions of any Act or rules
made thereunder, regulations or notifications including amendments. If the
Employer is caused to pay or reimburse, such amounts as may be necessary to
cause or observe, or for observance of the provisions stipulated in the
notifications/bye laws/Acts/Rules/regulations including amendments, if any, on the
part of the Contractor, the Engineer/employer shall have the right to deduct any
money due to the Contractor including his amount of performance security. The
Employer/Engineer shall also have the right to recover from the Contractor any
sum required or estimated to be required for making good the loss or damage
suffered by the Employer.
The employees of the Contractor and the Sub-Contractor in no case shall be
treated as the employees of the Employer at any point to time.
A) Workmen Compensation Act 1923 :- The Act provides for compensation in case of
injury by accident arising out of and during the course of employment.
B) Payment of Gratuity Act. 1972 :- Gratuity is payable to an employee under the Act
on satisfaction of certain conditions on separation if an employee has completed 5
years service or more on death, the rate of 15 days wages for every completed year of
service. The Act is applicable to all establishments employing 10 or more employees.
C) Employees P.F. and Miscellaneous Provision Act 1952:- The Act Provides for
monthly contributions by the employer plus workers @ 10% or 8.33% The benefits
payable under the Act are :
D) Maternity Benefit Act 1951 :- The Act provides for leave and some other benefits to
women employees in case of confinement or miscarriage etc.
E) Contract Labour (Regulation & Abolition) Act 1970 : The Act provides for certain
welfare measures to be provided by the Contractor to contract labour and in case the
Contractor fails to provide, the same are required to be provided, by the Principal
Employer by Law. The principal Employer is required to take Certificate of
Registration and the Contractor is required to take license from the designated Officer.
The Act is applicable to the establishments or Contractor of Principal Employer, if
they employ 20 or more contract labour.
F) Minimum Wages Act 1948 :- The Employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the Act, if the
employment is a scheduled employment. Construction of Building, Roads, Runways
are scheduled employment.
G) Payments of wages Act 1936:- It lays down as to by what date the wages are to be
paid, when it will be paid and what deductions can be made from the wages of the
workers.
H) Equal remunerations Act 1979 :- The Act provides for payment of equal wages for
work of equal nature to Male and Female workers and for not making discrimination
against female employees in the matter of transfer, training and promotions etc.
J) Industrial Disputes Act 1947 :- The Act lays down the machinery and procedure for
resolutions of Industrial disputes, in what situations a strike or lock-out becomes
illegal and what are the requirements for laying off or retrenching the employees or
closing down the establishment.
L) Trade Unions Act 1926:- The Act lays the procedure for registration of trade unions
of workmen and employers. The Trade Unions registered under the Act have given
certain immunities from civil and criminal liabilities.
M) Child Labour (Prohibition & Regulation Act 1986 :- The Act prohibits
employment of children below 14 years of age in certain occupations and process and
provides for regulation of employment of children in all other occupations and
processes. Employment of Child labour is prohibited in Building and Construction
Industry.
Q) Royalty charges-The contractor shall pay the royalty to the competent authority as
per rule. The royalty charges paid shall be borne by the contractor and shall not be
reimbursed by the Employer.
R) Following Pollution control Acts and amendments made thereof from time to
time shall be applicable.
24.1 If the Contractor is of the view that a decision taken by the Engineer was either
outside the authority given to the Engineer by the Contract or that the decision was
wrongly taken, the decision shall be referred to #Superintending Engineer, Surat
(R&B) circle, surat (Higher Authority) within 14 days of the notification of the
Engineer's decision. If the issue is not resolved, any party can refer the matter for
conciliation within 15 days from the decision given by the #Superintending
Engineer.
24.2
(a) For the work up to Rs.100 Cr., if any of the parties is not satisfied with the
decision of the #Superintending Engineer, both the parties have to refer to the
#Chief Engineer concerned for the conciliation process.
(b) For the work more than Rs.100 Cr., if any of the parties is not satisfied with
the decision of the Superintending Engineer, both parties have to refer to the
#Secretary, Roads & Building Department, Government of Gujarat for the
conciliation process.
If the dispute is not resolved through the conciliation process, contractor
may refer the dispute to Gujarat Public Works Contract Dispute Arbitration
Tribunal. If the Contractor fails to refer a claim / dispute to the Higher
Authority within 14 days of the notification of the Engineer's decision, the
Contractor shall not be entitled to any additional payment/claim if he doesn’t
follow the above sequence in stipulated time. However, during such period, he
would not stop the work in any case.
5. The Intended Completion Date for the whole of the works is [CL.1.1,17&2]
9 Months after start of work with the following milestones:
Milestone dates: [CL.2.2& 49.1]
Physical works to be completed Period from the start date
Milestone 1 i.e. 25 % 68 Days
Milestone 2 i.e. 50 % 135 Days
Milestone 3 i.e. 75 % 203 Days
Milestone 4 i.e. 100% 270 Days
6. The Site is located at………………………………………….. [CL.1.1]
7. The name and identification number of the Contract is: [CL.1.1]
8. The works consist of RS.57,93,772.44…with items as per B.O.Q. The [CL.1.1]
works shall, inter alia, include the following, as Specified, or as directed:
11. The law which applies to the Contract is the law of Union of India [CL.3.1]
16. The minimum insurance cover for physical property, injury and death is [CL13]
Rs. 5 lakhs per occurrence with the number of occurrences limited to four.
After each occurrence, the contractor will pay an additional premium
necessary to make insurance valid for four occurrences always.
Vs= Increase or decrease in the cost of work during the month under consideration
due to changes in the rates for steel
So= The all India wholesale price index for steel (Mild Steel - Long Products
Rebars) on 28 days preceding the date of opening of Bids as published by the
Office of the Economic Adviser, Department for Promotion of Industry
and Internal Trade, Ministry of Commerce & Industry.
Si= The all India average wholesale price index for steel (Mild Steel - Long
Products Rebars) for the month under consideration as published by Office
of the Economic Adviser, Department for Promotion of Industry and
Internal Trade, Ministry of Commerce & Industry.
Note : For the application of this clause, the index of Mild Steel- Long
products Rebars has been chosen to represent the steel group.
(iv) Price adjustment for increase in the cost of bitumen shall be paid in
accordance with the following formula
Bo = The official retail price of bitumen at the IOC depot at the nearest
center on the day 28 days prior to the scheduled date of opening of
technical bid.
Bi = The official retail price of bitumen of IOC depot at the nearest center
for the 15th day of the month under consideration.
(v) Price adjustment for increase or decrease in cost of POL (fuel and
lubricant) shall be paid in accordance with the following formula
Fo = The official retail price of High Speed Diesel (HSD) at the existing
consumer pumps of IOC at the nearest centre on the day 28 prior to the
date of opening of Bids.
Note: For the application of this clause, the price of High-Speed diesel Oil has
been chosen to represent the fuel and lubricants group.
(vi) Price adjustment for increase or decrease in the cost of plant and
Machinery spare procured by the Contractor shall be paid in accordance
with the following formula
Vp= Increase or decrease in the cost of work during the month under
consideration due to changes in rates for plant and machinery spares
Note: For the application of this clause, index of Heavy Machinery and parts has
been chosen to represent the Plant and Machinery Spares group
(vii) Price adjustment for increase or decrease in cost of local materials other
than cement, steel, bitumen and POL procured by the contractor shall be
paid in accordance with the following formula
Mi= The All India wholesale price index (all commodities) for the month
under consideration as published by the Office of the Economic Adviser,
Department for Promotion of Industry and Internal Trade, Ministry
of Commerce & Industry.
The following percentage will govern the price adjustment for the
entire contract:
1. Labour -Pl 26.13 %
2. Cement – Pc 16.09%
3. Steel - Ps 29.83%
4. Bitumen – Pb 4.16%
5. POL – Pf 7.30%
6. Plant & Machinery Spares Pp 2.83%
7. Other Materials – Pm 13.66 %
--------------
Total 100 %
--------------
25. The proportion of payments retained (retention money) shall be 6% {CL. 48}
from each bill subject to a maximum of 5% of final contract price.
28. Amount of Bonus for early completion Amount of bonus for early
completion of work shall be given as
per CL.50 of Section-3
29. Maximum limit of bonus for early 5 percent of the Contract {CL. 50}
Completion of work Price
30. The amount of the advance payment are: {CL. 51 & 52}
ii Equipment 90% for new and 50% of After equipment is brought to site
depreciated value for old (provided the Engineer is satisfied
equipment. Total amount That the equipment is required for
will be subject to a performance of the contract) and on
maximum of 5% of the submission of unconditional Bank
Contract Price Guarantee for
amount of advance
(The advance payment will be paid to the Contractor no later than 28 days after
fulfillment of the above conditions).
31. Repayment of advance payment for mobilization and equipment {CL. 51.3}
The advance loan shall be repaid with percentage deduction from the interim payments
certified by the Engineer under the Contract. Deduction shall commence in the next
Interim Payment Certificate following that in which the
-------------------------------------------------------------------------------------------------------------
------------------------------------------------------------------------------------------------------------
-------------------------------------------------------------------------------------------------------------
BID
To :
Address :
1. We offer to execute the Works described above and remedy any defects therein in
conformity with the conditions of Contract, specification, drawings, Bill of Quantities and
Addenda for the sum (s) of
( --------------------------------------------------------------------------------------------------------- )
3. We agree to abide by this Bid for the period of 120 Days from the date fixed for receiving
the same, and it shall remain binding upon it and may be accepted at any time before the
expiration of that period.
4. Unless and until a formal Agreement is prepared and executed this Bid, together with
your written acceptance thereof, shall constitute a binding contract between us.
5. We understand that you are not bound to accept the lowest or any tender you may receive.
-------------
Witness
Address
Occupation
Preamble
1. The bill of Quantities shall be read in conjunction with the Instructions to Bidder,
Conditions of Contract, Technical Specifications and Drawings.
2. The quantities given in the Bill of Quantities are estimated and provisional, and are
given to provide a common basis for bidding. The basis of payment will be the actual
quantities of work ordered and carried out, as measured by the Contractor and verified
by the Engineer and valued at the rates and prices tendered in the priced Bill of
Quantities, where applicable, and otherwise at such rates and prices as the Engineer
may fix within the terms of the Contract.
3. The rates and prices tendered in the priced Bill of Quantities shall, except in so far as
it is otherwise provided under the Contract, include all constructional plant, layout,
supervision, materials, erection, maintenance, insurance, profit, taxes and duties,
together with all general risks, liabilities and obligations set out or implied in the
Contract.
5. A rate or prices shall be entered against each item in the Bill Quantities, whether
quantities are stated or not. The cost of Items against which Contractor has failed to
enter a rate or price shall be deemed to be covered by other rates and prices entered in
the Bill of Quantities (in case of Item rate contract).
6. The whole cost of complying with the provisions of the Contract shall be included in
the items provided in the priced Bill of Quantities, and where no Items are provided
the cost shall be deemed to be distributed among the rates and prices entered for the
related items of Work.
7. General direction and descriptions of work and materials are not necessarily repeated
or summarized in the Bill of Quantities. References to the relevant sections of the
contract documentation shall be made before entering rates or prices against each item
in the Bill of Quantities.
9. Errors will be corrected by the Employer for any arithmetic errors pursuant to
Clause 29 of the Instructions to Bidder.
10. Rock is defined as all materials which, in the opinion of the Engineer, required
blasting, or the use of metal wedges and sledgehammers, or the use of compressed air
drilling for its removal, and which cannot be extracted by ripping with a tractor of at
least 150 kw with a single rear mounted heavy duty ripper.
I/We am/are willing to carry out the work at …..................... % above/below percent (Should
be written in figures and words) of the estimated rate mentioned above. Amount of my /our tender
works out as under.
SEALED with the Common Seal of the said Bank this ---------------------- day of --------- 20
(1) If after Bid opening the Bidder withdraws his bid during the period of Bid validity
specified in the Form of Bid;
Or
(2) If the Bidder has been notified of the acceptance of his bid by the Employer
during the period of Bid Validity:
C. does not accept the correction of the Bid Price pursuant to Clause 27
(Correction of Errors)
* The Bidder should insert the amount of the guarantee in words and figures
denominated in Indian Rupees. This figure should be the same as shown in Clause
16.1(Bid Security) of the Instructions to Bidders.
**45 days after the end of the validity period of the Bid. Date should be inserted by
the Employer before the Bidding documents are issued.
TO,
- ------------------------------------------------------------------- (Name of Employer)
- -------------------------------------------------------------------- (Address of Employer)
-------------------------------------------------------------------
AND WHEREAS it has been stipulated by you in the said Contract that the
Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligation in accordance with the
Contract.
AND WHEREAS we have agreed to give the Contractors such a bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you
on behalf of the Contractor, up to a total of ------------------------------------------
(amount of guarantee)* -------------------------------- (in words), such sum being payable in
types and proportions of currencies in which the Contract prices is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument, any
sum or sums within the limits of ---------------------------------------- (amount of guarantee)
as aforesaid without your needing to prove or to show grounds or reasons for your demand
for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the contractor
before presenting is with the demand.
We further agree that no change or addition to or other modification of the terms of the
Contract to of the Works to be performed thereunder or of any of the Contract documents
which may be made between your and the Contractor shall in any way release us from any
liability under this guarantee, and we hereby waive notice of any such charge, addition or
modifications.
This guarantee shall be valid until 60 days from the date of expiring of the Defect
Liabilities period.
of Bank -----------------------------------------------
Address ------------------------------------------------
Date ---------------------------------------------------
*An amount shall be inserted by the Guarantor, representing the percentage the Contract
price specified in the Contract denominated in Indian Rupees.
TO,
- ------------------------------------------------------------------- (Name of Employer)
- -------------------------------------------------------------------- (Address of Employer)
-------------------------------------------------------------------
AND WHEREAS it has been stipulated by you in the said Contract that the
Contractor shall furnish you with a Bank Guarantee by a recognized bank for the sum
specified therein as security for compliance with his obligation in accordance with the
Contract.
AND WHEREAS we have agreed to give the Contractors such a bank Guarantee:
NOW THEREFORE we hereby affirm that we are the Guarantor and responsible to you
on behalf of the Contractor, up to a total of ------------------------------------------
(amount of guarantee)--------------------------------- (in words), such sum being payable in
types and proportions of currencies in which the Contract prices is payable, and we
undertake to pay you, upon your first written demand and without cavil or argument, any
sum or sums within the limits of ---------------------------------------- (amount of guarantee)
as aforesaid without your needing to prove or to show grounds or reasons for your demand
for the sum specified therein.
We hereby waive the necessity of your demanding the said debt from the contractor
before presenting is with the demand
We further agree that no change or addition to or other modification of the terms of the
Contract to of the Works to be performed thereunder or of any of the Contract documents
which may be made between your and the Contractor shall in any way release us from any
liability under this guarantee, and we hereby waive notice of any such charge, addition or
modifications.
This guarantee shall be valid until 28 days from the project completion date.
of Bank -----------------------------------------------
Address ------------------------------------------------
Date ---------------------------------------------------
TO,
- ---------------------------------------------------------------------------------(Address of Employer)
Gentlemen:
We further agree that no change or addition to or other modifications of the terms of the
Contractor or Works to be performed thereunder or of any of the Contract documents
which may be made between --------------------------------- (name of Employer) and the
Contractor, shall in any way release us from any liability under this guarantee, and we
hereby waive notice of any such change, addition or modifications.
This guarantee shall remain valid and in full effect from the date of the advance
payment under the Contract until -------------------------------------- (name of employer)
receives full repayment of the same amount from the contractor.
YOUR’S TRULY
* An amount shall be inserted by that Bank or Financial Institution representing the amount of
the Advance Payment, and denominated in Indian Rupees.
(date)
To,
(Name and address of the Contractor)
Dear Sirs,
Yours Faithfully
* Delete “Corrected and” or and modified if only one of these actions applies. Delete as corrected
and modified in accordance with the Instructions to Bidders, if corrections or modifications
have not been affected.
- ------------------------------- (date)
To,
Dear Sirs,
Pursuant to your furnishing the requisite security in ITB Clause 34.1 and
signing of the Contract for the construction of
You are hereby instructed to proceed with the execution of the said works in accordance
with the contract documents.
Yours faithfully
Name and identification number of contract (hereinafter called “the works”) and the
employer has accepted the Bid by the Contractor for the execution and completion of such
works and the remedying of any defects therein, at a cost of Rs.
1. In this Agreement, words and expression shall have the same meanings as are
respectively assigned to them in the conditions of contract hereinafter referred to and
they shall be deemed to form and be read construed as part of this Agreement.
4. The Following documents shall be deemed to form and be ready and construed as part
of this Agreement viz
i) letter of Acceptance
ii ) Notice to proceed with the works:
iii ) Contractor’s Bid
iv ) Conditions of contract: General and Special
In the presence of
Title of officer
Name of firm
DATE
Title of officer
Name of firm
DATE