Technical Details
1. Design:
I. System Voltage:
II. SOLAR Array
a) SOLAR Array Capacity (Wp):
b) Capacity of each SOLAR Module (Wp): Total No of SOLAR Modules:
c) Manufacturer Name:
d) Brand/Model:
e) No of SOLAR Modules in a string (x):
f) No of Parallel Strings (y):
g) Design Calculations (Mathematical calculation/ Simulation / Performance Curve):
h) Catalogues:
i) RETS Certificates:
j) Agreement with principal manufacturer:
III. Pump
a) Pump Type:
Submersible: Surface:
If Surface,
Suction head (m): Delivery head(m): Total Head(m):
b) Manufacturer Name:
c) Brand/Model:
d) Pump Capacity (HP):
e) Design calculations for Pump selection and sizing (Mathematical calculation/ Simulation / Performance Curve):
f) Catalogues:
Page 1 of 65
g) IEC certificate/Test report:
h) Controller:
a. Rating (amp/watt):
b. Manufacturer name:
c. Model/Brand:
i) Agreement with principal manufacturer:
IV. Cable
a) Manufacturer Name:
b) Brand :
c) Cross sectional area ( sqm):
d) Cable Length (SOLAR array to Pump):
e) Maximum Voltage Drop between PV Modules and Pump (shall be <=3%):
f) Cables shall be PVC insulated, weather resistant and suitable for a wide temperature range (Yes/No):
g) UV Resistant (yes/No):
V. Protection System
a. Air Termination System:
i. Length of the Air terminal rod above the PV array: …….m
ii.Diameter of the air terminal rod...........mm
iii. Material of air terminal rod: Aluminum / copper / copper bonded.
iv. Comply with IEC 62305
v.Technical datasheet of Air termination system
b. Down Conductor:
i. Cross sectional area of Down Conductor..........mm2
ii.Material of Down conductor: Copper / Aluminum / GI/ Copper bonded
iii. Comply with IEC 62305
iv. Technical datasheet of Down Conductor
c. Earthing:
Page 2 of 65
i. Length of the earth electrode:.........m
ii.Diameter of the rod :….mm
iii. Comply with IEC 62305
iv. Technical datasheet of Earthing system
d. Surge Protector:
i. SPD is DC Type
ii.SPD of Type 2
iii. Manufacturer Name:
iv. Brand /Model:
v.Comply with IEC 61643-31:2018
vi. Technical Datasheet
e. Lighting Arrester:
1 set of Lighting arrester,
wire having down conductor size: 25mm width x 3 mm thickness copper strip.
LPS height: Minimum 10 meters
VII. Mounting Structure
a) Mounting structure material (shall be of aluminum or steel angles and channels with properly galvanized):
b) Mounting structure shall be non-corrosive (Yes/No):
c) Tilt angle:
d) Orientation of SOLAR panel:
e) Foundation type for mounting structure:
f) Clearance between ground level and bottom edge of PV modules (shall be >0.5m):
g) Fasteners used for fixing structure shall be non-corrosive (Yes/No):
The design of above-mentioned components should be supplied with mathematical calculation sheets, performance curves, single line diagrams and all
other relevant document
Page 3 of 65
Annex-2: Format for Price Schedule (Bill of Quantities)
Design, Supply, Delivery, Installation, Testing and Commissioning, R&M training, After-sale services of Solar water lifting System
Bidders can make necessary changes in Quantity, size, ratings, and specification of the equipment by providing justification for doing so and provided that the Works will meet
the requirements set out in the Scope of Works, the Specification, and the Drawings. The changes made by bidders will be accepted if it is found to be more cost effective with
enhanced quality
The prices in the Bill of Quantities shall be inclusive of all things necessary to meet the requirements set out in the Scope of Works, the Specification, and the Drawings.
Where an item of work, equipment or material required is not specifically listed in the Bill of Quantities description given below the Bidder shall include it within the most
appropriate item or add a further item to the Bill of Quantities as most appropriate.
Name of Assignment: Solar Powered Water Lift System for Gavar Valley Lions Park
Location: Baijnath Rural Municipality-01, Banke
Site Information:
Head in mt 125
Water demand in liter/day 25,000 Ltr/day
Elec. cable length in mt 130
Complete Solar Pumping System
Unit Price, Rs. Item Total, Rs.
S. N. Item Description Qty VAT Free
VAT Free Item VAT-able Item VAT-able Item
Item
1 PV Array Poly or Mono/ Mono perk
Crystalline Solar array. Minimum
each PV Module of capacity
325Wp, having minimum 5kWp -
efficiency of 21%. With minimum
capacity of 5kWp
(RETS Passed)
Page 4 of 65
2 Submersible pump All body Stainless steel AC Solar
Pump of minimum capacity 2.5KW
with inbuilt MPPT Charge
Controller and dry running sensor
capable to lift average annual 1
discharge of 25m3/day at a head of
125 meters
(RETS Passed)
(IEC 62253 certified)
3 Inverter Supply of & Installation of Inverter
of 5KVA specification with all
1
complete accessories
(RETS Passed)
4 Grounding and Grounding System with DC and AC
Protection System surge protector, 1 set of DC MCB, 1
set of AC MCB, 2 set of Earthing
1
Electrode 2m length, 2 set of
Backfill chemical, wire, junction
box etc.
5 Lighting Arrester 1 set of Lighting arrester, wire
having down conductor size:
25mm width x 3 mm thickness 1
copper strip.
Page 5 of 65
7 Armored Cable Armored Copper Cable 3 Core 6sq.
mm. 130
8 Installation Installation Materials including
Materials weatherproof junction box, DC
MCB, termination kits, submersible 1
cable, pvc conduit, and other
accessories.
9 Transportation Installation, Transportation, Testing
Installation, Testing and Commissioning 1
and Commissioning
10 After Sales Service After Sales Services with 2 site
1
visits
Total
Certified that:
1. The above rates are in accordance with the specifications & various terms & conditions mentioned in the tender document. (*
Please attach breakdown of cost of individual components, but the figure quoted in this page is considered for evaluation)
2. The unit price shall include all custom duties and taxes, transportation cost to the final destination and insurance cost including
all incidental cost whatsoever.
Notes:
In case of discrepancy between unit price and total, the unit price shall prevail.
In case of discrepancy between amount in figure and words, the amount in words shall prevail.
Bidder needs to provide break down cost of each component in separate page
Name……………………………………….
Duly authorized to sign the Bid for and on behalf of …………………….
In the capacity of…………………….
Signed………………………………………. Date………………………….
Page 6 of 65
Annex-3: Technical Specification
The purpose of the Technical Specifications (TS) is to define the technical characteristics of the goods
and related services that are required to be procured for the installation. The TS, as a part of the
schedule of requirements, constitute a contract document and are, therefore, a part specification of
all the indicated equipment of power generation and distribution system including performance
curve, power and energy curve, test certificates, warranty assurance certificate, international
standard that the proposed goods comply with.
Where the contract includes design by the Contractor the Contractor shall be responsible for the
detailed specification of the Works which shall, as a minimum, conform to the standards specified in
the TS.
1. Solar Photovoltaic (PV) Module
General Description
The proposed SOLAR PV Modules for the site must comply with the following standards and
technical specifications.
Manufacturer's experience in
2 manufacturing PV modules: Minimum
10 years
Page 7 of 65
Specifications Offered Reference Document
S.N. Specifications Required
with Compliance (Specify Document)
A letter provided by principal PV module
manufacturer in their letter head stating
the warranty period for their PV module.
Product Workmanship Warranty: ≥ 10
years
12 Performance Guarantee:
first year: ≥ 97% of STC power
10 year: ≥ 90% of STC Power
25 years: ≥ 80% of STC Power
linear warranty ≤ 0.8% per year from
year 2 and onwards
International Certification:
IEC 61215:2005 2nd Edition or
IEC 61215-1:2016 and IEC 61215-2:2016
for Terrestrial photovoltaic (PV) modules
- Design qualification and type approval
14 – Part 1: Test requirements and Part 2:
Test Procedures.
IEC 61730 for PV module safety
qualification, IEC 62804 for detection of
potential induced degradation (PID)
The test certificates must be provided.
18 Number of Module
Page 8 of 65
Specifications Offered Reference Document
S.N. Specifications Required
with Compliance (Specify Document)
Design Calculations (Mathematical
21 calculation/ Simulation / Performance
Curve):
Rafter: Minimum
40mmx80mmx2mm Rectangular tube
Purlins:
3 Minimum 40mmx80mmx2mm Rectangular tube
or
Angles: Minimum 50mmx50mmx5mm
Page 9 of 65
Specifications Reference Document
S.N. Specifications Required Offered with
Compliance (Specify Document)
placement. There must be a minimum of 25mm
uniform spacing between the modules.
3) Solar PV Pump
A SOLAR motor pump set shall be designed for daily demand of 24.77 m3 per day for a head of
125 meter (Suction Head 10 m and delivery head 115 m). The motor-pump system should have
low operating costs and high efficiency at rated head and discharge. It is recommended that all
parts of the pump and the motor of the submersible pumps should be made of corrosion-
resistant stainless steel with a minimum grade of AISI 304 or higher. Other technical minimum
requirements are mentioned below in the table below:
Page 10 of 65
Reference
Specifications Document
S.N. Specifications Required Offered with
Compliance (Specify
Document)
3 Name of Manufacturer
4 Brand/model of Pump
Page 11 of 65
Reference
Specifications Document
S.N. Specifications Required Offered with
Compliance (Specify
Document)
or quality assurance certification from national or
international laboratory/institutions.
4) Pump Controller/Inverter:
The total required pumping inverter capacity must be at least …. kVA. The Pump Controller/ Inverter
shall comply with the following standards and technical specifications.
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
1 Manufacturer Name/Brand/Model:
Manufacturer's experience in manufacturing
2
inverters: Minimum 3 years
The manufacturer shall have:
3
ISO 9001, ISO 14001 Certificates
Warranty: Manufacturing warranty of minimum
4 3 years from inverter manufacturer in their letter
head signed and stamped
Inverter type: built-in electronics with MPPT
5
(Maximum Power Point Tracking) function.
6 Rated Power: …. kVA
Surge Handling Capacity: The surge capacity shall
7
be at least 150% for 3 sec
8 Peak Efficiency: Minimum 95%
Inverter efficiency: The efficiency when operating
loads at power levels within 40% to 90% of the
9 rated load must be greater than 90%. The bidder
must submit the efficiency curve of the inverter
to justify operational efficiency
Total Harmonic Distortion
10
(THD) < 5%
Page 12 of 65
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
11 Protection class: IP54 or above
Operating Temperature: Minimum range of -20⁰C
12
to +50⁰C
RETS Certification or Quality certificate validation
13
by AEPC or third party assigned by AEPC
If the separate MPPT charge controller is used
14 with inverter, both must be from the same
manufacturer
The Bidder must submit the technical datasheet
14
of the Pump Controller/inverter
5) DC Combiner Box
DC combiner box refers to the box where the PV modules/ strings are collected, and cables
are routed towards SOLAR Pump Controller. The DC combiner box shall comply with
following standards and technical specifications.
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
Page 13 of 65
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
The cables and accessories shall comply with the following standards and technical specifications.
1. Manufacturer Name
2. Brand Name
Page 14 of 65
Specifications Reference Document
S.N. Specifications Required Offered with
Compliance (Specify Document)
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
Page 16 of 65
Specifications Reference
S.N. Specifications Required Offered with Document
Compliance (Specify Document)
The Switches/Circuit
11 Breakers/Disconnectors/Fuses used must
comply with IEC 60947 Part 1, 2 & 3: All parts
Page 17 of 65
such tests any part is not found as per the specified technical parameters, the Employer will take