Itp-Bjp-Cpfc-Qc-Pip-001-Inspection Test Plan For Piping
Itp-Bjp-Cpfc-Qc-Pip-001-Inspection Test Plan For Piping
REVISION CONTROL
B 11/12/2024 ITP-BJP-CPFC-QC-PIP-001
C 18/12/2024 ITP-BJP-CPFC-QC-PIP-001
D 24/12/2024 ITP-BJP-CPFC-QC-PIP-001
E 02/01/2025 ITP-BJP-CPFC-QC-PIP-001
INSPECTION TEST PLAN
PIPING FABRICATION AND
INSTALLATION
Rev. No : E Page 3
List Contents
1. GENERAL ........................................................................................................................................................... 4
2. SCOPE ................................................................................................................................................................ 4
3. DEFINITION ....................................................................................................................................................... 4
4. LEGEND of RESPONSIBILITY ............................................................................................................................... 4
5. INSPECTION and TEST PLAN for PIPING ............................................................................................................ 4
6. ATTACHMENT ................................................................................................................................................... 4
INSPECTION TEST PLAN
PIPING FABRICATION AND
INSTALLATION
Rev. No : E Page 4
1. GENERAL
The purpose of this Inspection Test Plan (ITP) is to ensure that piping fabrication and installation meet
project specifications, codes, and quality standards. It defines inspection stages, testing requirements,
and critical hold points to verify compliance, prevent defects, and ensure the piping system’s safety,
functionality, and reliability.
2. SCOPE
This Inspection Test Plan (ITP) applies to piping fabrication and installation, covering material verification,
welding, NDT, painting, and final installation. It defines inspection activities, responsibilities, and
acceptance criteria to ensure compliance with project requirements and standards.
3. DEFINITION
- Company (CPY)
- Contractor (CONT)
- TPI
- MIGAS
4. LEGEND of RESPONSIBILITY
The Legend of inspection responsibility for each party stated in ITP Table shall be following:
I : Inspection / Test Record to be submitted only for information and no need approval
H : Hold point where indicated in ISOG, TPI, MIGAS columns are defined as critical steps in
the installation and testing process. The Project Team cannot proceed to the next work
activity until the inspection, measurement, or test has been witnessed and approved by
the attending parties.
2. Test Package
ITR
3. Packing Manufacture Spec QA
DISPATCH &
10 4. Lifiting Company Spec P/I SW/W SW R
DOCUMENTATION Dosier/MDR/MC
5. Transportation Arrangement Package
6. Quality Record
CENTRAL PROCESSING FACILITY CONSTRUCTION
Note : SW = Shop Weld FW = Field Weld BW = Butt Weld FT=Fillet Weld RT = Radiography Test PT = Penetrant Test
Prepared by, Checked By, / Witness By, Riviewed By, Riviewed By,
PT BJP PT. HBP PT. INDOSINO TPI (Third Party Inspection)
If Aplicable
Joint MATERIAL
Welder
No. Sheet Spool No. WPS NO. Filler Metal RESULT NDT Dia. Remarks
I.D
No. Type General Identifier Specification Size Heat No. Sch. / Thk Class
Total :
Note : SW=Shop Weld FW = Field Weld BW = Butt Weld FT=Fillet Weld RT = Radiography Test PT = Penetrant Test
Excessive Reinforcement
Incomplete Penetration
Misalignment / Hi-Lo
No. Joint
Tungsten Inclusions
Incomplete fusion
Film Identification Location
Root Concavity
Burn Through
Slag Inclusions
Welder Stamp
SKETCHS
INSPECTION REPORT
WELDING REPAIR
Location : Report No. : ITR-PIP-FBR-Q05
Line No. : Date Repair :
ISO Drawing No. : Page No. :
WELDING DATA
WPS Welded No. : Joint No. :
Welder Code Who Produced The : Date :
Defect : RT Report No. :
Repair Data
WPS Welded No. : Joint No. :
Welder ID :
Defect Excavation Position :
Defect
0
14 Type of Defect :
7
Size of Defect :
Circumferential
:
Position
Note :
Removal of Defect
Remarks :
WELD JOINT AFTER REPAIRED ARE :
VISUALLY ACCEPTABLE
RT ACCEPTABLE
Client : Date :
Project : Page :
Location : Report No. : ITR-PIP-FBR-Q08
P & ID. NO :
Yes N/A
RECORDING INST. / PRESSURE GAUGE : CHECK CALIBRATION
Yes N/A
ATTACHED : HYDRO AND TEMPERATURE CHART
Remarks :
PT. BJP PT. HBP PT. ISOG TPI (Third Party Inspection)