JAFURAH COGENERATION POWER PROJECT
JCP JOB SAFETY ANALYSIS
Contractor / Specific Date of Risk
SINOHYDRO
Subcontractor Location Assessment
Duration of
Work Discipline Civil No. of Works
Work
Activity Plumbing Works (pipe installation & fitting work)
Risk Assessment Risk level A Risk Level B Risk Level C Risk Level D Risk Level E
Standard 16 – 25 10- 15 5- 9 3-4 1-2
Likelihood x Severity Unacceptable Severe Risk Through review required Acceptable Level Acceptable Level
Review and Approval
Subcon Permit Signature Signature Signature Signature
Subcon Dept Subcon Site Subcon HSE
Reciever /
Head Manager Manager
Supervisor
Name Name Name Name
RISK RISK
Work Activity Hazard Factor & Control Measure & Detailed
GRADE
GRADE
No.
information Environmental impactJAFURAH
L S COGENERATION
T POWER
management Plan PROJECT
In Charge
Correction Date
L S T
JCP JOB All
SAFETY ANALYSIS
personnel have attended the project
Safety Orientation and relevant safety
awareness training prior to site mobilization.
The field supervisor or foreman shall be a
certified permit receiver and to coordinate
for permit approval to Doosan const. &
safety team.
The field supervisor shall perform a daily
tool box talk addressing the site hazard and
Non-compliance to project
discussing risk control to all crew member
procedure & permit system
Everyone must know the emergency
Unawareness of emergency
assembly point and emergency contact
procedures
numbers to be posted at work area.
Area Assessment Permit
1 & Preparation
Incompetent Personnel 2 2 4 D
Ensure that competency of all personnel is Supervisor
2 1 2 E
verified prior perform the operation and
Uninspected use of
ensure that the operators are having the
equipment and tools.
valid third-party certification with them.
All equipment & tools shall be declared
upon entry of project gate and be
coordinated with Doosan Safety team for
inspection and approval
Heavy equipment shall have safety function
device, fire extinguisher and first aid kit in
place.
Homemade tools are not allowed to be use
in the project.
Use of leather or cut resistance hand
gloves to eliminated or prevent hand injury
for handling sharp objects.
Sharp edges Where an object requires two or more
employees to handle it, one employee
Carrying of heavy items should give the direction for lifting and
lowering the object in unison.
2 Manual Handling Repetitive lifting 2 3 6 C Work Crew 2 2 4 D
Never attempt to lift beyond your capacity
Lifting and carrying on (20 Kg). If in doubt test the objects’ weight
uneven and / or slippery before handling it: if it appears too heavy or
ground conditions bulky, obtain a mechanical lifting aid.
The work area shall be in good condition
and free from slips. Ensure clear access is
available.
Use proper tools for the job.
Never use handmade tools.
Ensure that the hand tools are inspected
and color coded as per the project
Defective Hand tools procedure.
Lifting and carrying heavy Wherever possible, a reduction in the