0% found this document useful (0 votes)
23 views54 pages

Interim Amendments to Public Works Contracts

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views54 pages

Interim Amendments to Public Works Contracts

Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 54

Interim Amendments to the Public Works

Contracts
GCCC Information Sessions - June 2015
Part 1
Summary and review of the public
works contracts
• Summary of the development and
implementation of the public works contract
• Fixed price, lump-sum contracts
• Issues impacting on the successful
performance of the public works contract
• Review process
• Review conclusion
Summary of the development and implementation
of the public works contract
Key Driver: Considerable cost overruns in works projects,
Government Decision 2004

Requirement: Greater cost certainty, better value for money and more
efficient delivery of projects

Solution adopted: Fixed price, lump-sum contracts introduced in 2007

Implemented by: Transferring risk to main contractor to achieve cost and


time certainty

Expected Outcome: Increased contract sum in return for price certainty


Fixed price, lump-sum contracts
• Risk Transfer
• Notification requirements or ‘conditions
precedent’ to any claim
Issues impacting on the successful performance
of the public works contracts
• Competitive tendering environment
 Very low prices bid by contractors and consultants
alike;
 Review of the performance of contracts challenging
as a result
• Dispute resolution mechanisms
 Notification requirements trigger early engagement
in formal dispute procedures
 No wider application from having engaged in dispute
procedures
Review Process
• Invitations to stakeholders to make submissions –
December 2013
• On-line questionnaire launched in May 2014
• Review of submissions
• Report to GCCC on submissions
• Response to review presented to GCCC
• Submission to Minister for Public Expenditure &
Reform
Review Conclusion
• Report published 11 December 2014 on
http://constructionprocurement.gov.ie/category/news/
• 4 interim recommendations -
 Change to status of the Bill of Quantities
 Direct engagement of key specialist works
contractors
 MEAT award for contracts above €2m
 Overhaul the dispute resolution mechanisms in the
contracts
• Medium-term strategy to be developed
interim amendments
Interim Amendments – Constraints
• Tight budgetary conditions;
• Key objectives in 2004 Reform still valid;
• Substantial capital programme to deliver;
• Imperative is to provide a means to deliver this
programme efficiently with the best possible
quality outcome and ensure all available money is
directed to this end.
Interim Amendments – Objectives
1. To rebalance the risk currently transferred in
recognition of changed circumstances;
2. To reduce the potential for costly disputes;
3. To provide greater detail on the tendered price;
Interim Amendments – Timeline
• Engagement with key stakeholders virtually
complete;
• Paper setting out details of amendments
published April 2015;
• Final meeting with stakeholders after conclusion
of these sessions;
• Provisional deadline Q2 – Q3 2015;
• Transitional arrangements.
Amendment 1 – Status of the Bill of Quantities
Objectives 1 & 2
• Bill of Quantities to become the primary
reference for tender purposes on Employer-
designed projects;
• Omissions from the Bill will not limit the scope
but will result in a Change Order;
• Items included in the Bill but not required in the
other Works Requirements will result in a Change
Order that will reduce the Contract Sum;
• Errors related to quantity will result in an
adjustment to the Contract Sum – up or down.
Amendment 2 – Direct tendering to specialists
Objectives 1, 2 & 3
• To be used where the extent of specialist works
on projects exceeds 15% of the total contract
value;
• Provides greater insight into pricing of these
elements;
• Reduces the extent of the Contract Sum for which
the main contractor has responsibility;
• Reduces the tendering burden on the specialist
sector.
Amendment 3 – MEAT award for projects >€2m
Objective 3
• Adopt quality MEAT criteria that are directly
related to the project outcomes;
• Greater visibility of the price bid in the tender;
• Increased quality of completed project;
• Guidance required – may be delivered later than
3 other amendments.
Amendment 4 – overhaul ADR in the PWCs
Objective 2
• Provide alternatives to the costly procedures
currently provided for in the contracts;
• Provisions for dispute avoidance to be
strengthened;
• Dispute escalation measures prior to formal
procedures;
• Nominated Conciliator on contracts in excess of
€10m.
medium-term strategy
Medium-term Strategy – Imperatives
• Broader review of the procurement of public
works;
• Including developments such as:
– New procurement directives - eProcurement;
– Building Regulations – BC(A)R, CIRI;
– Building Information Modelling (BIM);
Medium-term Strategy – Key Topics
• Risk management;
• Encouraging co-operative behavior;
• Performance evaluation;
• Alternative forms of contract;
Summary
Contract Administration – Public Works Contracts
Contract Administration
• Responsibility of both parties
– Employer’s Representative on behalf of the Employer
– Contractor’s Representative on behalf of the Contractor

• For the efficient running of the contract to deliver


the final product.
– Clause 4 – Management provides the instruments for efficient contract
administration
– Clause 8 – Quality, testing and Defects
– Clause 11 – Payment
Clause 4 - Management
• Clause 4.1 – Co-operation [PW-CF1 to 5]
– Drafted to encourage the parties to support co-operative behavior for
the benefit of the project
• Negotiated agreements,
• Efficient order and timing of information delivery,
• Minimising effects of delay

– Either party may request clarifications, consultations, workshops, etc


– Clause 4.1.2(1):
• “negotiation of agreements provided for in the contract”
– Clause 4.1.4:
• “The parties may agree to consult or communicate, without prejudice.”

Question: Has Clause 4.1.2(1) and 4.1.4 always allowed for the Project Boards?
Clause 4 - Management
• Clause 4.9 – Programme [PW-CF1 to 4]
– Produced to assist both parties to adequately resource the project.
– Minimum standard presentation required of the Contractor
• Required Instructions
• Procurement, manufacture, delivery, installation, construction, testing,
commissioning, trial operation, sequence and timing of inspections and
tests.
• Resources on site & resources for each task
– Contractor’s Responsibility to provide this information
– Clause 4.9.3 –Employer can withhold 15% of payment.
Question: Do Contractors provide this level of information?
Question; Do Employer’s Representatives seek this level of information?
Question; Do Employers withhold payment where a Contractor fails to submit a revised
programme?
Clause 4 - Management
• Clause 4.10 – Progress Reports [PW-CF1 to 4]
– Progress report to include;
• Detailed description of progress against the current programme.
• Details of Contractor’s personnel
– resources as per programme
• Details of when instructions are to be given
– Clause 4.11
• Details of anything that might have an adverse effect on execution of the
Works, the steps the Contract is taking or proposes to reduce those
risks…
– Clause 4.1.2 (6) – “Efforts by the Contractor to minimize delay and Compensation events
and their effects”

Question: Should the progress report format mirror the programme format?
Question: Do Contractors provide this level of information?
Question; Do Employer’s Representatives seek this level of information?
Clause 8 – Quality, Testing and Defects
• Clause 8.5 – Defects [PW-CF1 to 5]

– Clause 8.5.1 – The ER may direct the Contractor to search for a defect..

– Clause 8.5.2 – The ER may direct the Contractor to remove, demolish,


reconstruct or not to deliver a Works Item with a defect

– Project administration tool to ensure quality standards throughout the


project and reduce defects lists at Substantial Completion
Clause 11 - Payment
• Clause 11.1.1 [PW-CF1 to 5] - “the Contractor shall give a statement to the
Employer’s Representative showing all of the following
– The progress of the Works”
Question: Should the statement be linked to the Progress Report Clause 4.10?

• Clause 11.1.2 [PW-CF1 to 5] - “The instalment of the Contract Sum that the
Contractor shall be entitled to be paid on an interim basis shall be
– The Contract value of the Works properly executed by the Contractor …”
Question: Do interim payments take account of Defect Directions – Clause 8.5.2?
Interim Amendment 1
Change to status of the Bill of Quantities
WHY USE A BQ?
PRINCIPLES –
 All tenderers base their price on carrying out the same extent of work
 The tender process is expedited
 The Employer benefits from cost advice during the tender process
 Both Contractor and Employer have confidence in the adequacy of the tender price
accepted
 The document format facilitates valuation of ‘work in progress’ and any changes
that may arise
A comprehensive BQ will:
 Contribute to comprehensive design development
 Allow tenderers have confidence in the BQ they are pricing
 Reduce the incidence of Contractors pursuing recovery of dubious extras as
compensation for omissions from tender prices.

29
BQs SINCE PWC INTRODUCTION
 Intention of PWC adoption
 Works Requirements to fully define the scope
 Pricing Document to fully quantify the extent
 Risk of discrepancies between WR and Pricing Document to be minor and
risk of errors transferred to Contractor where reasonable – if there is
confidence in accuracy of document.

 What has happened


 Works Requirements still not fully defined
 Risk of errors in BQ commonly transferred to Contractor, regardless of risk
of discrepancies between it and the Works Requirements
 Facility to transfer BQ risk to Contractor reducing Design Teams / QS
members focus on accurate BQ (contributed to by downward fee pressure)
 Loss of confidence in BQ accuracy by Contractors - tenderers
commissioning independent checks to assist in pricing strategy – costs and
time pressure for tenderers
 Disputes

30
CORE OBJECTIVES OF AMENDMENT
 To enhance the level of information provided as part of
the tender documents for ‘Employer-Designed’ contracts.

 To provide greater visibility of the price tendered.

 To rebalance the level of risk currently being transferred


under the Public Works Contracts conditions

31
HOW WILL CHANGES AFFECT BILLS OF
QUANTITIES (AND QSs)
DIRECT
 BQ primary reference document for the price of the work and its
calculation
 BQ status restored to what it was under GDLA ‘yellow form’ with
respect to pricing of the work – drawings and spec still to take
precedence for construction
 Discrepancies between BQ and Works Requirements to be
Compensation Events – price can go up or down as appropriate.
 Detailed consideration of risk allocation before finalisation of Works
Requirements and BQ – ground conditions, utilities, archaeology

INDIRECT
 QS role – importance of contribution to Design Team increased -
highlight to Design Team any information believed to be outstanding.

32
WHAT IS NOT PROPOSED
 BQ will not determine the scope of the work or how it is to be done –
role of Works Requirements

 QS will not fill in the gaps in the Works Requirements prepared by the
designers – if deficits noted by QS then clarification / further design
required

 QS not to design Work

 No reintroduction of Provisional Sums / Quantities in PW Contracts

 No BQ requirement for PW CF6 (Short Form) – to remain as ‘drawings


and spec’ – use CF5 (Minor Works) if BQ required for small project

33
PRINCIPAL PWC AMENDMENTS WITH
REFERENCE TO BQs
 Employer takes risk of errors in BQ – errors and omissions dealt with by
way of Change Order (as in GDLA ‘82 ‘yellow’ form)
 More options for risk allocation between Employer & Contractor
 New option for specialist subcontract work to be tendered directly by
Employer – either before the Main Contract tender or before Main
Contract award - alternative to ‘novation’.
 BQ will contain ‘Reserved Sums’ to allow estimated (or actual) Specialist’s
amounts to be included in submitted tenders.
 Only in exceptional circumstances will contractors be required to appoint
a Specialist beyond the Starting Date and only following an application by
the Employer to the GCCC where a modified form of contract will apply;
 ‘Reserved Sums’ will be swapped for Specialist tender amounts prior to
completion of MEAT process.
 Amounts for Specialists will be identified in Payment Certs and Specialists
informed directly by ER of what is included for them

34
RISK ALLOCATION

 New flexibility in Schedule Part 1K to allocate risks – ground conditions,


utilities, archaeology.

 Risk assessment / allocation to be determined AT LATEST during


preparation of tender documents - may affect feasibility decision

 Principle – If no basis of assessment for the risk by the Contractor


then Employer retains it

 BQ must include items to allow Contractor price risks transferred to him.

 Scope changes arising from occurrence of Contractor risks do not result


in remeasurement of the work affected.

35
METHODS OF MEASUREMENT - ARM
ARM STEERING GROUP CONSULTED – amendments, or a revised document,
to be issued by SCSI/CIF to co-ordinate with updated PWC content.

ARM compliance needed to ensure consistency within individual documents


and across different tenders.

No ad-hoc ARM amendments to be allowed – bad experiences with QS


practitioners adopting global measurement of work items to reduce their costs /
condense Pricing Document / accelerate tender issue.

ARM4 Supplement 2 for Mech and Elec services to be adopted as a


minimum (full ARM4 at Employer discretion) – ARM4 Supplement 2 (drafted
by CIF / SCSI) to provide less demanding set of measurement Rules for services
than full ARM – delivers standard presentation and pricing format for services
content.
ARM use requires buy-in from Services consultant - show the work needed on the
Drawings, provide comprehensive Specs, do not rely on capacity of tenderers to
interpret intentions of Consultant.

36
METHODS OF MEASUREMENT - ARM
 ARM4 Supplement 1 – to be updated because
 Does not provide for specialist contractor appointment mechanism
envisaged by PWC revision – inclusion of allowances in tender
documents for such work, profit mark-up on it, special attendance
requirements

 Rules for some ARM Workgroups do not match current industry


practice – e.g. prefabricated timber roofs where ARM requires detailed
measurement of trusses, plates, bracing, shoes, brackets, etc. More
widespread adoption of Contractor Design solution not envisaged in
ARM.

 Post-BC(A)R environment re design / assigned certifier certs, etc. not


envisaged

37
METHODS OF MEASUREMENT -
ENGINEERING
 CESMM – CESMM3 to continue is use pending drafting of required
amendments to make CESMM4 compliant with PWC provisions.
 Amendments to CESMM3 published in GCCC Guidance 1.5 (Appendix
D2) to be reviewed to comply with revisions to PWC provision.

 MMRB – NRA currently revising MMRB document and final version will
comply with revised PWC provisions.

38
CHALLENGES - EMPLOYERS AND DESIGN TEAMS

 Better assessment of the risks to transfer and to retain – Beware of risk


averse Design Teams / Employers and ‘risk ignoring’ Contractors . Asses potential
for risk, consequences if it arises, mitigation opportunities, design alternatives.
Only transfer a risk to Contractor where he is in position to assess and price it.
 ‘Employer Design’ – misnomer? Conditions of Contract titled ‘Employer
Design’ and 'Design Build’. Post BC(A)R recognition that Employer Design is not
always the case – Designers do the elements they have the knowledge to detail and
Contractor and Specialists do the rest. Works Requirements to clarify who is
designing. If Contractor/Specialist doing it the BQ must include associated duties –
i.e. provision of ancillary certs
 Longer tender preparation duration – more comprehensive tender
documents will take longer or more resources. Set realistic programmes and fees.
 Higher fees on some projects – if more work then higher fees a possibility!
Contracting Authorities’ preference for reasonable fees and good service.

 Payback - less disputes, better delivery and money spent on construction


rather than Dispute Resolution
39
CHALLENGES - DESIGN TEAMS AND QS PRACTICES

 Buy-in to fully designing the work and bringing user confidence


and relevance back to the Bills of Quantities
 QS asking for more information is not doing so to embarrass Design Team members. If
QS forced into assumptions then the Contractor will have same problem – may turn into
opportunity for claim.
 Comprehensive BQ cannot be produced in very short time at the end of the design
period. Design Team programmes should allow a a realistic duration - QS agreeing to
unreasonable programmes doing themselves and the Employer a disservice
 Access to contractor tender lists for Public work now by open application with objective
assessment – tender documents have to be robust enough to withstand challenges that
may arise after Contract award.

QSs to have confidence in their own knowledge and be aware of


the reliance placed on them by Employers to contribute to
successful project conclusion

40
Interim Amendment 2
Direct engagement of key specialist works contractors
Bill of Quantities as Primary Document

• Introduce BOQ as primary document in suite

– M&E Consultants and contractors in many cases not


familiar with ARM

– Education process will be necessary

– ARM 4, Supplement 2 for period of 18 months


Rules of Measurement

• ARM 4 Supplement 2

– Very basic detail, simple rules


– Main plant items
– Schedules of equipment
– Little or no quantities

• ARM 4
– Full measure
Rules of Measurement

• OPW to provide template spreadsheet

– For Supplement 2

– For Full ARM


Tender of specialists

• Separate tender and subcontract for specialist


works contractors
– Tender of M&E Packages can be either before or at the
same time as main contractor package
– Novation or appointment by Contractor can be
used
– Price Certainty as actual tenders included in Main
contractors price at contract award
– Directly tendering gives greater control over quality
– Reduces the value of the contract for which the main
contractor is bidding directly
Issues relating to Specialist sub-contracts

• Right of refusal to accept specialist (does not


apply to novated Specialists)
– Limited scope of refusal
• Sub-contract conditions – CIF ‘NN’ form to be
referenced in specialist tender;
• Requirement in conditions of main contract for a
copy of signed subcontract form to be provided
to Employer;
• Contractor retains full responsibility for
performance of Specialist;
• No direct payment provision for Specialists;
• Payment details provided as part of certification;
• Replacement of specialist
Novation

• Still available for use

– Design
– Advance work
MEAT Assessment

• All projects >€2M assessed using M.E.A.T. with a significant


weighting for Quality

• Useful for M&E packages


– Lifts
– BMS
– Very Large Plant Items

• Considerations
– Design
– Life cycle cost
Interim Amendment 4
Overhaul the dispute resolution mechanisms in the contracts
Key Objectives

• To encourage greater uptake and use of clause 4 of the


contract
• To reduce the number of disputes being referred to the formal
dispute procedures currently prescribed in the contract
• To better manage those disputes that do arise
Present Provisions

• Clause 4.1- Co operation


• Clause 10- Employers Rep. Decides.
• Clause 13.1 – Conciliation
• Recommendation within 42 days – unless otherwise agreed
• Further 42 days to consider – If not rejected then Binding !
• If rejected: Pay money subject to certain provisions
• Clause 13.2 -Arbitration
Proposed Dispute Provisions
Interim Measure No. 4

Dispute Escalation
• Dispute Escalation Procedure –

• High Level Management Group – “Project Board” for Claims


the subject of ER’s determination and in dispute under Cl.
10.5.4 & Cl. 10.5.5 (PW-CF1 to PW-CF5 (>€500k))

• Nominated Conciliator(NC) for contracts >€10m (PW-CF1


to PWCF4).
• NC will be available from beginning of Contract for
disputes . Meeting / hearings at regular intervals.
Future

• CCA 2013- Adjudication - when CCA becomes


operational.
• How will Conciliation provisions sit in the Contract
with the legal entitlement to Adjudicate “at any time”
• Arbitration and / or Courts
• Arbitration – No “case stated” provision, Costly?
Long?
Thank You

You might also like