Erbil Power System
Erbil Power System
For
By converting the system voltage level, the expensive and long-lasting applications like a
power transformer connects a power system's
generators and transmission lines, as well as the power transmission system, costs and lifetime
transmission and distribution systems. Two are also crucial. The choice of a transmission
categories—two winding and three winding
transformers with tap changers—are available line cable is made after taking Equation 3.12
for system study. Nine parameters are
necessary to model transformers in MATLAB, into account. The system interface for
including the nominal voltages at the primary simulating the transmission line cable is shown
and secondary sides (V1, V2), the rated power
(S), the operation frequency (f), the connection in Figure 3.10 below.
setup, the short circuit voltage, the copper
¿=S ÷ (√ 3∗V −i)
losses, the no load current, and the no load
power losses. Where the line current, whose SI unit is A, is
3.3 Modelling of overhead lines and represented as Li, the line to line voltage,V , is
cables presented as Vi−i , and the apparent
power, VA , is represented by S.
International standards and recommendations
whether a transmission line cross section exists: IEEE-14 and 30 bus systems are from
To begin with, taking safety into account, the MATPOWER [38], respectively. Table 1 contains
selected transmission line must be able to an overview of power generating units,
transmit at any rate the maximum current that transmission lines, and load buses.
can flow at the nominal operating state. Table 1: bus systems for IEEE-14 and 30
Additionally, the decision needs to be available
S.No IEEE-14 IEEE-30 10-11 18 0.89 4th
5 0.9363 4th
Table 2: IEEE-14 Bus System with index 11 0.906 5th
values of lines. 12 0.8904 6th
line branch Lmn at Rank 7 0.8687 7th
Maximum 13 0.8355 8th
loading 10 0.8173 9th
point
4-7 8 0.998 1st PSO is used to determine the best rating for
nd
4-9 9 0.993 2 these devices after identifying potential
rd
7-9 15 0.97 3 locations for TCSC and SVC. Table 4 displays the
One of the largest issues in the majority of
ideal rating of FACTS devices and how they
developing nations is T&D losses in lines.
affect power loss.Because SVC can efficiently Technical losses from heating in the lines and
unmetered losses from theft are among the
manage VAr in the system, as shown in Figure 2, losses. Some Distribution Companies (DISCOs)
they can significantly enhance the voltage of in the Pakistan grid have distribution losses of
greater exceeding 30% [5]. There has been
the entire power system. The voltages prior to some improvement in the energy deficit during
FACTS range from 0.95 to 1.05, however they the last few years with the construction of
10,000 MW of producing capacity. However,
typically dip below 1 p.u. However, the voltage because of significant overloading, transmission
profile is nearly steady above 1 p.u. when the lines began to operate at their maximum
loading point [46]. The overall transmission and
SVC and TCSC are installed. distribution losses for the Pakistan grid from
Figure 3 demonstrates that the addition of 2015 to 2020 are shown in Figure 5 [10].
voltage profile of the IEEE-30 bus system. The majority of developing nations lack
appropriate planning for their electrical
Therefore, the overall voltage profile of the systems, but even then, putting those plans into
network can be significantly improved by action can be difficult. Modeling the operations
and parts of the generation, transmission, and
installing SVCs with the best ratings at the distribution systems is essential for long-term
network's weakest points. planning. For the planning and study of power
systems, there are numerous commercial
software programs available. MATPOWER has
Figure 3: Bus voltages prior to and been utilized to model and analyze the
electrical network in this research project
following the placement of FACTS (IEEE-30 Bus [21].The study has been applied to Pakistan's
System) projected national gird for the year 2025 as well
as its current national gird (for the year 2018).
3.2 Practical grid for Erbil The National Transmission and Dispatch
Company's power system planning division has
The suggested approach of placing and sizing assisted with the research (NTDC). NTDC is in
FACTS devices optimally is evaluated on charge of overseeing the transmission network
standard IEEE systems before being that connects Power Generation Units with
implemented on countries such as Pakistan’s Load Centers dispersed across the nation. The
national grid. Figure provides a summary of the NTDC disclosed all the research's findings,
electric grid's electricity deficit from 2013 to including its actual plans for grid development.
2017. Figure 5; Transmission and distribution
Figure 4: Demand, supply and deficit for losses in a grid.
electricity between 2013 and 2017.
In the current national grid architecture, there increase to 42,000 MW.The main factor driving
are 1930 load buses, 277 producing buses, and the high demand was air conditioning.
4147 overhead transmission lines. The current In the projected national grid for 2025, load is
electric grid experienced a total active power expected to be around 41,000 MW, while
power loss of 9951 MVAr. The base voltage and MW. The grid system model has 10,110
base power of the national network are 500 kV transmission lines, 6007 load buses, 797
and 100 MVA, respectively, and are expressed generator buses, and 2961 generator
in terms of per-unit data. The T&D network in buses.Table 7 provides a summary of the
Pakistan consists of six voltage levels: 500, 220, electrical elements of the Pakistani national grid
132, 66, 33, and 11 kV, of which the high that were utilized in this investigation.
and 132 kV) is owned and operated by NTDC Table 7: network-grid summary current
(DISCOs).
Table 6: Bus details of the grid. method-based AC load flow analysis. The power
277 GENCOs were connected to the NTDC significant active and reactive power losses,
transmission network in 2018 according to the according to load flow findings. Modern tools
modeling data, and it is anticipated that like FACTS are therefore absolutely necessary
amounts of nuclear, wind, and solar PV facilities The best places to install the TCSC are found to
are also included in the nation's energy mix. On be weak lines throughout the entire system.
July 11, 2018, the peak load for 2018 was FACTS can therefore be applied to clusters with
findings, a group of seven lines indicated in will cause nearby buses and lines to be
dramatically reduce power losses. Total active FACTS to determine the savings. While OC with
power losses in the network model for 2018 FACTS is the total of the capital cost of FACTS
were 853.67 MW before FACTS devices were and the cost associated with real power loss, OC
installed, however they were reduced to 792.12 without FACTS is the cost associated with active
MW after their placement. Moreover, the power loss.Real power transfer as a result of
reactive power loss in the 2018 model was FACTS placement is added before calculating
decreased from 9951.2 MVAr to 9283.86 MVAr. the cost of real power loss after FACTS
reactive power losses have decreased by about The inclusion of FACTS devices will prevent total
6.21% and 6.71%, respectively. Figure 7 power losses of 61 MW and 96 MW, or around
illustrates the national grid model for the year 6% of the overall loss, in the current grid model
2025, which has also seen similar and the predicted grid model, respectively.As a
Figure 7: power loss change after analysis and the payback period, energy savings
A thorough financial analysis is conducted, in Pakistan) were taken into account. Figure 8
including a comparison of the national grid's displays the operating costs, FACTS costs, and
Operation Cost (OC) before and after the net savings for each scenario both before and
of FACTS deployment are VAR compensation before to the deployment of FACTS from OC
and voltage profile enhancement.Improved post-FACTS placement yields the total net save.
voltage profiles lead to lower network losses After FACTS are sized and placed in the ideal
and, as a result, increased real power flow.The location, the OC is greatly reduced.The payback
additional real power transmission has been period assessed for both the current national
taken into account while calculating the cost- grid and the projected national grid is less than
benefit analysis and payback period for the a year, demonstrating the project's financial
10. The typical operating voltage range at any respectively, are linked with buses B1 and B4.
bus is 0.95 to 1.05 p.u [36]. Prior to the The capacity of six and four producing units,
introduction of FACTS, the voltage profile is respectively, make up the combined total of S1
typically unstable but becomes more stable and S2. 250 MW and 100 MW of load L1 and L3
later. The voltages ranged from 0.779 p.u. to linked to B1 and B4, respectively. Similarly,
1.526 p.u. in the voltage profile of buses for the 50MW and 2200MW of load L2 and L4 are
grid model 2018 with a standard deviation of connected to L21 and L22, respectively.
0.081. Six SVCs are inserted, bringing down the According to Fig. 6-7, SSSC is linked in series
value of to 0.06. Depending on the available between B1 and B2. L1, L21, L22, and L3 are
budget, placing more SVCs could result in transmission lines with lengths of 280 km, 150
Table 11 provides an overview of the planning SSSC is a device connected between buses B1
issue that has been resolved for FACTS devices and B2 that belongs to the series family of
in both the current 2018 and anticipated 2025 FACTS devices. Here, the transmission line L1's
models. active power flow can be improved by the SSSC
injecting a maximum of 10% compensating
Table 11: Planning model summary for voltage. As seen in Fig. 8, when the SSSC is not
present and forecast model. in use, the Vinj is zero. When it is in use, the
power flow are seen in Fig. 9 for various SSSC controller for 500kV grid station that has
Improvement in active power flow was 17.18% A thorough planning model is offered for
at 0.1 p.u. in (Bisht et al., 2020). Similar to this, enhancing the national grid's performance by
Fig. 9's depiction of the range in P's positioning FACTS devices for both the existing
improvement from 2% to 10% (Green Line). It is scenario and the anticipated scenario. First,
evident that the proposed model increased the analysis using line stability and voltage collapse
active power by 15MW over the prior control proximity indices is done to determine the best
(Bisht et al., 2020). The increase in current flow sites for FACTS devices. Weak lines and
and decrease in inductive losses brought on by potential TCSC installation locations are those
the SSSC's virtual capacitance are the causes of with Lmn index values that are near to
placement of FACTS. A thorough financial study voltages. High voltage transmission networks
has been done, accounting for operational costs employ SVCs. These electrical appliances are
both before and after the placement of FACTS used to deliver quick-reacting reactive power to
as well as the payback period. Policymakers in improve voltage profile, power factor
developing nations will use the information correction, and power system stability. SVCs are
offered in this paper as a roadmap to improve placed primarily for two purposes:
the performance of their national grids under i. Enhancing and regulating the
to incorporate the power system's small-signal ii. modifying the industrial loads' power
and sized to fulfill both tiny signal stability and SVCs are typically utilized in transmission
the goals attained in this work. networks to increase grid voltages. When a
node where the SVC is linked, and Vn is the θ for the impedance angle, and δ for the angle
voltage of the bus at node n . difference between buses.
FACTS devices regulate several transmission The VCPI index is used to arrange SVCs in the
network parameters including voltage, current, best possible locations. The index aids in
and impedance while taking into consideration identifying the busses in a transmission system
the power transmission lines' capacity for that are unstable. All buses' VCPI indices are
transfer. But if any of these devices are used calculated; those with indices close to 1.0 are
effectively through ideal positioning and regarded as weak. These buses are therefore
sensible sizing, their full potential can be potential sites for the installation of SVCs.
realized. For the system's ideal placement of Maximum power transfer via line is the basis for
the FACTS, which are covered in the next VCPI, which is characterized as:
The stability index ( Lmn) of the transmission SVC sizes for each chosen location in an effort
line, which can be used to identify weak to reduce the overall cost of system operating.
transmission lines, is where TCSC is placed. A
Mathematical derivations
transmission line that is more unstable is one
whose Lmn index value is closer to 1.0 than The major goal of determining the FACTS rating
one whose Lmn index value is farther from 1.0. that is best is to reduce both the active power
Equation can be used to determine Lmn index loss costs and the FACTS installation expenses.
Lmn=4 XQr [Vs sin(θ−δ)]2 numerically (12). PSO modifies the ratings of
Where X stands for the line impedance, Qr for FACTS devices with each iteration; as a result,
the reactive power demand of the transmission active power loss is estimated with each
Figure 4: Demand, supply and deficit for
iteration and multiplied by the price of electrical
electricity between 2013 and 2017.
energy. The cost of electrical energy per unit
One of the largest issues in the majority of
[43] and the total active power losses of the developing nations is T&D losses in lines.
Technical losses from heating in the lines and
complete system (PL) for the entire year (365
unmetered losses from theft are among the
24) are compounded to get "0.09$". The losses. Some Distribution Companies (DISCOs)
in the Pakistan grid have distribution losses of
Newton Raphson power flow method is used in greater exceeding 30% [5]. There has been
MATPOWER to compute active power losses in some improvement in the energy deficit during
the last few years with the construction of
each iteration of PSO in order to reduce this 10,000 MW of producing capacity. However,
value. The following is the overall objective because of significant overloading, transmission
lines began to operate at their maximum
function: loading point [46]. The overall transmission and
min [CPL+ CFACTS] distribution losses for the Pakistan grid from
2015 to 2020 are shown in Figure 5 [10].
Where CPL, or the cost of active power loss, is
determined as
The majority of developing nations lack
O 1=(x 1 , x 2) appropriate planning for their electrical
and is a function of active power loss that must systems, but even then, putting those plans into
action can be difficult. Modeling the operations
be kept to a minimum. The conductance of line and parts of the generation, transmission, and
k is Gk. The sending and receiving buses' distribution systems is essential for long-term
planning. For the planning and study of power
respective voltage amplitudes are Vi and Vj. systems, there are numerous commercial
Phase difference between ith and jth bus is software programs available. MATPOWER has
been utilized to model and analyze the
represented by ij. Here, the arrays of dependent electrical network in this research project
variables (x1) and control variables (x2) are [21].The study has been applied to Pakistan's
projected national gird for the year 2025 as well
shown. as its current national grid (for the year 2018).
The National Transmission and Dispatch
Practical grid for Erbil Company's power system planning division has
assisted with the research (NTDC). NTDC is in
The suggested approach of placing and sizing charge of overseeing the transmission network
FACTS devices optimally is evaluated on that connects Power Generation Units with
standard IEEE systems before being Load Centers dispersed across the nation. The
implemented on countries such as Pakistan’s NTDC disclosed all the research's findings,
national grid. Figure provides a summary of the including its actual plans for grid development.
electric grid's electricity deficit from 2013 to
2017.
Figure 5; Transmission and distribution electrical elements of the Pakistani national grid
losses in a grid. that were utilized in this investigation.
In the current national grid architecture, there Table 7: network-grid summary current
are 1930 load buses, 277 producing buses, and and forecast.
4147 overhead transmission lines. The current
electric grid experienced a total active power
loss of 853 MW while experiencing a reactive MATPOWER is used to do the Newton Raphson
power loss of 9951 MVAr. The base voltage and method-based AC load flow analysis. The power
base power of the national network are 500 kV system is weak and susceptible, with extremely
and 100 MVA, respectively, and are expressed significant active and reactive power losses,
in terms of per-unit data. The T&D network in according to load flow findings. Modern tools
Pakistan consists of six voltage levels: 500, 220, like FACTS are therefore absolutely necessary
132, 66, 33, and 11 kV, of which the high for the system.
voltage transmission network (500 kV, 220 kV,
and 132 kV) is owned and operated by NTDC 5.1 Discussions
and the balance by the Distribution Companies
(DISCOs). SSSC is a device connected between buses B1
and B2 that belongs to the series family of
FACTS devices. Here, the transmission line L1's
Table 6: Bus details of the grid. active power flow can be improved by the SSSC
injecting a maximum of 10% compensating
voltage. As seen in Fig. 8, when the SSSC is not
277 GENCOs were connected to the NTDC in use, the Vinj is zero. When it is in use, the
transmission network in 2018 according to the SSSC needs 0.2 seconds to fully inject 0.1 p.u. of
modeling data, and it is anticipated that compensating voltage.It should be noted that
number will rise to 797 generating stations by the compensating voltage's amplitude is
the year 2025. The majority of these power inversely proportional to the DC link voltage.
plants are thermal and hydroelectric, but small The active power flow in L1 increases to 765
amounts of nuclear, wind, and solar PV facilities MW after correction (0.1 p.u.). That is a growth
are also included in the nation's energy mix. On of 19.53 %. Similar improvements in active
July 11, 2018, the peak load for 2018 was power flow are seen in Fig. 9 for various
21,483.6 MW, and by 2025, it is expected to compensating voltages (2% to 10%).
increase to 42,000 MW.The main factor driving Improvement in active power flow was 17.18%
the high demand was air conditioning. at 0.1 p.u. in (43). Similar to this, Fig. 9's
depiction of the range in P's improvement from
In the projected national grid for 2025, load is 2% to 10%. It is evident that the proposed
expected to be around 41,000 MW, while model increased the active power by 15MW
generation is expected to be around 42,000 over the prior control (21). The increase in
MW. The grid system model has 10,110 current flow and decrease in inductive losses
transmission lines, 6007 load buses, 797 brought on by the SSSC's virtual capacitance are
generator buses, and 2961 generator the causes of this improvement.
buses.Table 7 provides a summary of the
5.2 Conclusion into the system also reduces active and reactive
power losses on the line.
The IEEE 14 bus test system assesses Using 48 pulses and a 3-level NPC-based VSC, a
STATCOM's effectiveness in reducing power new SSSC control for 500kV grid stations is
losses and boosting system voltage stability designed in this study. SSSC is used to look at a
limitations. The outcomes show how the device steady state power transfer problem. Buses B1
controller simultaneously reduces power losses and B2 were connected by SSSC, which
and improves the voltage profile of the system. improved the transfer of 125 MW of active
The IEEE 14 bus transmission technology was electricity through L1. The importance of this
initially modeled in. model for 500kV grid station will be
Standard load on the transmission system was demonstrated through a thorough comparison
done using MATLAB/Simulink. At that time, the with or without SSSC. Additionally, this
system was simulated using the Newton- approach successfully accomplishes important
Raphson load flow program to conduct a power objectives including the prevention of
flow study. Before STATCOM was added to the malfunctioning, a reduction in line losses, cost
system, quantities of the voltage magnitude effectiveness, and simplicity. Results from
profile and active and reactive power losses MATLAB/Simulink 2017(a) support the new
were seen to have an impact on the system's SSSC controller for 500kV grid station that has
voltage stability and power transfer at steady- been proposed.
state operating conditions. To obtain the A thorough planning model is offered for
voltage profile and active and reactive power enhancing the national grid's performance by
losses in the system, STATCOM constructed in positioning FACTS devices for both the existing
MATLAB/Simulink was introduced into the scenario and the anticipated scenario. First,
system. The power flow analysis was carried out analysis using line stability and voltage collapse
once more on the system. The maximum proximity indices is done to determine the best
loading factor was raised once more, this time sites for FACTS devices. Weak lines and
in increments of 10% up to 40%. To determine potential TCSC installation locations are those
the effects of the device on the system with Lmn index values that are near to unity.
quantities, the obtained data were compared. Similar to this, candidates for SVC placement
When STATCOM was added to the system at are buses with VCPI values near to unity. The
normal load, the active and reactive power ideal sizes of these devices have been
losses were reduced by 17.63% and 24.78%, established using PSO after the candidate
respectively. It was noted that there was a locations for FACTS devices have been
sufficient improvement in the voltage profile identified. The outcomes demonstrate that an
and power transfer on the transmission line. optimized strategy substantially lowers power
The active and reactive power losses were system losses. Using eight TCSCs and six SVCs,
significantly decreased, it was found when the the active power losses in the Pakistani national
results obtained for all scenarios for load grid model for 2018 are decreased by 6.21%,
increases in steps of 10% to 40% before and while the reactive losses are decreased by
after the insertion of STATCOM were compared. 6.71%.Depending on the budget, more FATCS
The results show that STATCOM effectively devices can be installed to further limit the
improves voltage stability and reduces active losses. The voltage profiles for both the current
and reactive power losses at the load bus and grid and the projected grid are been improved.
the lines connecting the buses of the system. The standard deviation of bus voltages for the
Therefore, STATCOM effectively improves current model is 0.08 before the placement of
voltage profiles and reduces power loss when FACTS and improves to 0.064 after the
linked to the system. Incorporating STATCOM placement of FACTS. A thorough financial study
has been done, accounting for operational costs
both before and after the placement of FACTS A STATCOM is typically implemented to assist
as well as the payback period. Policymakers in
electrical networks that frequently have poor
developing nations will use the information
offered in this paper as a roadmap to improve voltage management and poor power factor.
the performance of their national grids under
Voltage stability is STATCOM's primary
the projected and present-day scenarios. The
objective function will eventually be expanded application. A voltage source converter (VSC)-
to incorporate the power system's small-signal
based device, a reactor serves as the voltage
stability. As a result, FACTS will be positioned
and sized to fulfill both tiny signal stability and source in a STATCOM. A STATCOM has very
the goals attained in this work.
little active power capabilities because the