A EARTHW ORK
A.1.1 In all type of soils up to 3 m depth M3 91,584.79 150.00 13,737,719
A.2.1 For each additional lift of 3 m over initial lift of 3 m M3 9,158.48 160.00 1,465,357
A.2.2 For each additional lead of 500 m over initial lead of 1500 m M3 36,633.92 150.00 5,495,088
A.6.1.1 Filling in Plinth, Trenches etc. w ith surplus excavated stuff. M3 48,909.14 150.00 7,336,370
B CEMENT CONCRETE AND ALLI ED W ORK
B.1.3.1.a M-25 Concrete w ith local stone aggregates M3 9.50 750.00 7,125 only casting w ark
B.1.3.1.b M-30 Concrete w ith local stone aggregates M3 4,135.59 750 3,101,691 only casting w ark
B.3 Supplying and Placing stone plums M3 646.00 750 484,500
C FORMW ORK, S HUTTERI NG, CENTERI NG, CAS I NG AND S TAGI NG
C.1.1 For plain surface Upto + / -0.00 M (-6.0m—0.00m) M2 29,701.78 280 8,316,498 only leveling w ark
C.1.2 For Curved/ Circular surface Upto + / -0.00 M M2 1,020.68 280 285,790
C.2 P&F Finished formw ork/ Shuttering For Plain surface
C.2.1 0.00 M to 10.0 M M2 1,089.27 280 304,996
D REI NFORCEMENT W ORK
D.1.2 Fab. & fixing HYSD Bars ( FE-500) MT 369.06 7,500.00 2,767,923
R ROADS
Laying in position at all locations controlled fly ash concrete for
R.1 M3 10,771.00 750 8,078,250 only casting w ark
truck parking yard w ith M35
R.2 Cast-in-situ kerb stone Rmt 17,683.59 210 3,713,553
R.3 ( *) Pouring and laying in position plain cement concrete M3 108.02 750 81,011
R.4 Supplying, providing and laying 100mm thick compacted Moorum M3 2,160.30 2,100.00 4,536,630 w ith material
R.5.a Providing and laying w ater bound macadam as subbase M3 2,275.25 2800 6,370,700 w ith material
R.5.b Rubble Soling
Ro a d A
R.5.b.1 Base:Graded Crushed Stone 25cm CBR>45% M3 9,375.33 3600 33,751,193 w ith material
R.5.b.2 Cushion:Stone Dust 15 cm M3 6,250.22 1550 w ith material
Ro a d B
R.5.b.3 Base:Graded Crushed Stone 20cm CBR>45% M3 4,437.34 3600 15,974,410 w ith material
R.5.b.4 Cushion:Stone Dust 15 cm M3 2,958.22 1850 5,472,714
Ro a d C
R.5.b.5 Sandiness Wearing Layer 3CM M3 341.29 1650 563,124
Base:Graded Macadam 20 CM For Filling Bed Excavated Subgrade
R.5.b.6 M3 3,412.88 2800 9,556,050
Is Not Required
Side Walk
R.5.b.7 Lime Soil 12: 88( Part By Weight) 15 CM M3 324.05 1750 567,079
Providing all types of equipment & labour for site grading w ork
R.10 Sqm 59,845.25 75 4,488,394
( Cutting/ filling avarage 150mm thickness)
Unloading materials & taking care of marerials supplied by ACC &
UNL MT 359.01 1200 430,815
SINOMA
To t a l b a s ic Am o u n t I N R 1 3 6 ,8 8 6 ,9 7 9
Contractor Signature Page 1 of 1