Excel Dashboard Delay Analysis Report
Excel Dashboard Delay Analysis Report
Planned Updated
Items Delay Jan-20 Jun-20 Dec-20 Jun-21 Dec-21 Jun-22 Dec-22 Jun-23 Dec-23
Finish Finish
SCHEDULE DATA
1160
1154
1150
ANALYSIS 1140
1130
1120
PLANNED START 1110
01-Jan-20
1100
1094
ACTUAL START 1090
01-Jan-20 1080
30-Dec-22 1060
Original Updated
Duration Duration
EXPECTED FINISH
28-Feb-23 Original Duration
1094 Days
Project Overall Is Under a Updated Duration
Total of 60 Days Delay 1154 Days
OVERALL PROGRESS UPDATE
20 350
18
300
16
14 250
12
200
10
150
8
6 100
4
50
2
0 0
Millions
Monthly Planned Value Monthly Earned Value
Accumulated Planned Value Accumulated Earned Value
SCHEDULE
PERFORMANCE INDEX
SPI = 0.92
The Project Is Behind of The Target
Delays 5%
Justifications 37%
% Actual Time
% Progress
WORK PACKAGES
UPDATE
Package % %
Description Planned Actual
PROJECT
Concrete Works 91% 88%
Block Works 55% 47% OVERALL
35%
Finishing Works 23% 17%
Mechanical Works 54% 52%
Electrical Works 50% 47%
Metal Works 53% 49% PLANNED
Doors, Window 14% 14%
32%
Conveying System 18% 18%
Special Finishing 0% 0%
Equipment 0% 0%
Wood Works 0% 0% Actual
Infrastructure 56% 42%
External Works 33% 32%
BEAUTIFUL BUILDING
PROJECT