12-01-2021 S072 Weekly Site Safety Inspection Report
12-01-2021 S072 Weekly Site Safety Inspection Report
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Arrange to provide
Found workman carrying temporary staircase
bricks to 12 mtr from 8 mtr for bricks shifting
MPH#2, 8 mtr
2 floor by using unsafe access, M/s B&R Civil Civil UC 15/01/2021 and carrying work till closed
to 12 Access.
chances of slip and fall along the completion of
with bricks. winch bucket
installation.
Need to remove
CW pump unwanted materials &
5 Poor house keeping found. M/s B&R Civil Civil UC 15/01/2021 closed
house. maintain good house
keeping .
Need to remove
Hydro Chloride unwanted materials &
6 Poor house keeping found. M/s B&R Civil Civil UC 15/01/2021 closed
building maintain good house
keeping .
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Coal Bunker
Arrange to provide
Unit#2, Ring Ring beam girder scaffolding
4 M/s B&R Mech MECH UC 15/01/2021 railing to the working
Beam Girder platform without hand railing.
platform.
Area.
Unit#2, Coal
Found life line without Arrange to fix the
Bunker K row,
5 clamping at K row 22 mtr M/s B&R Mech MECH UC 15/01/2021 clamp at life line wire
22 mtr adjacent
adjacent to CCR. rope eye end.
to CCR roof.
Arrange to provide
MPH#1, A0 Found hand railing missing at hand railing and
7 Row last working platform and improper M/s B&R Mech MECH UC 15/01/2021 replace the damaged
column. tying of fall arrestor rope. bend tube with safe
fall arrestor rope.
Arrange to provide
Multiple Gas cutting sets usage soap solution bottle
9 Coal Bunker#2. M/s B&R Mech MECH UC 15/01/2021
without soap solution. for each gas cutting
sets.
Arrange to dismantle
Found multiple unwanted
MPH#2, B/C and remove all the
column scaffoldings without
11 Row 13 to 15 M/s B&R Mech MECH UC 15/01/2021 column scaffolding at
platform gratings at work
number column. B/C bay work
completed area.
completed area.
Arrange to dismantle
MPH#2, B Row, 11 A column
and remove the
MPH#2, B row found idle scaffolding and
12 M/s B&R Mech MECH UC 15/01/2021 scaffolding and
11 A column. vertical ladder at work
vertical ladder at
completed area.
work completed area.
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Provide hard
Unit#1 Return No hard barricade or backfill
2 M/sGCCPL CIVIl UC 15/01/2021 barricade or do
cw pipe line done.
backfill.
CW pipe line
Midrail not provided in hard
3 near Cooling M/sGCCPL CIVIl UC 15/01/2021 Provide midrail.
barricade.
Tower #2B
CW pipe line
No side handrails found in Provide side
4 near Cooling M/sGCCPL CIVIl UC 15/01/2021
access/ ramp. handrails.
Tower #1B
Marked SWL on
SWL Not marked on hook and
hook and display
7 AHP Building inspection due date sticker note M/sGCCPL MECH U/C 15/01/2021
inpspection due date
mentioned.
sticker.
Do proper hard
9 AHP Building Improper Hard Barricading. M/sGCCPL CIVIl U/C 15/01/2021
barricading.
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
At Unit#1, generator
Arrange to rectify the
transformer area curing pit area
damaged power
found curing pump power
Unit#1 GT area supply terminal box
2 supply terminal box in damage M/s SIL Civil UC 15/01/2021
curing pit. and provide a safe
condition and substandard
weather protection
damaged weather protection
shed.
cover.
MPH#1, 38 mtr,
At expansion floor opening Arrange to remove all
TG roof to B/C
edge found poor housekeeping the loose material
6 bay expansion Simplex Civil Civil UC 15/01/2021
of multiple loose materials and from the floor
floor joint
steel scrap material. opening edge.
opening.
Condenser
Arrange to install the
Unit#1, Back
Found improper installation of power distribution
9 side to Unit Simplex Civil Civil UC 15/01/2021
power distribution board. box at safe place with
Transformer
proper rubber mat.
area.
Arrange to provide
MPH#1, 38 mtr Found usage of single railing
14 Simplex Civil UC 15/01/2021 double railing hard
B/C bay hard barricading.
barricading.
Control room
Electrical cables found routed Need to route it at
16 near GIS M/s SL Electrical UC 15/01/2021
at unsafe height. standard height.
building
Need to remove
unwanted materials &
Stacking Yard No hard barricade provided for
provide hard
18 near GIS stacking yard. Also poor house M/s Simplex Civil UC 15/01/2021
barricade to
Building keeping found.
demarcate your
stacking yard.
Bunker
Metal Scrap stacked at M/s Simplex Need to remove all
20 Fabrication MECH U/C 15/01/2021
workplace in front of the road. Mech scrap
Yard.
Bunker
Poor Welding cable M/s Simplex Need proper routing
21 Fabrication MECH U/C 15/01/2021
management. Mech of welding cables.
Yard.
Bunker
Metal Scrap kept seens for a M/s Simplex Remove all the metal
22 Fabrication MECH U/C 15/01/2021
along duration at workplace. Mech scrap from the site.
Yard.
Provide safe
Stacker
23 Unsafe access observed. M/s SIL Civil CIVIL U/A 15/01/2021 approach for each
Reclaimer
working platform.
HTG Engineering Private Limited
2*800 MW AP(J)L USCTPP Godda
Weekly Site Safety Inspection Report
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Batching Plant Poor cable dressing found for Cable dressing need
5 M/s PCTL Civil UC 15/01/2021
(Cooling Tower) electrical power cables. to do properly.
Need to stack
Shuttering boards found
materials away from
Cooling stacked over hard barricade
7 M/s PCTL Civil UC 15/01/2021 hard barricade
Tower#1B provided by M/s GCCPL. Its
provided by M/s
damaging hard barricade.
GCCPL.
Near stacking
Unwanted materials found near
8 yard at Cooling M/s PCTL Civil UC 15/01/2021 Need to remove.
work place.
Tower
Need to provide
Stacking Yard Hard barricade not provided standard hard
9 Behind Paharpur properly to demarcate the M/s PCTL Civil UC 15/01/2021 barricade (with white
Office stacking yard. & red painted ms
pipe).
Need to provide
No demarcation found for standard hard
Paharpur Office
10 office . Also many materials M/s PCTL Civil UC 15/01/2021 barricade (with white
side
found scattered near office. & red painted ms
pipe).
Need to display
Drinking water drum not cleaning schedule &
Cooling
13 found at standard height & also M/s PCTL Civil UC 15/01/2021 also place drinking
Tower#1B
no cleaning schedule found. water drum at hight
of minimum 1mt.
Need to provide
Stacking Yard Hard barricade not provided standard hard
14 Behind Paharpur properly to demarcate the M/s PCTL Civil UC 15/01/2021 barricade (with white
Office stacking / fabrication yard. & red painted ms
pipe).
HTG Engineering Private Limited
2*800 MW AP(J)L USCTPP Godda
Weekly Site Safety Inspection Report
Responsible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Responsible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
We instructed to the
Main power supply cable site engg. To
Boiler Unit - were found overlapped segregate those
1 Ground cables and hose pipes
2 with gas cutting set hose M/s PCPIL MECH UC 15/01/2021 closed
floor & 18 separately and trye to
mtr floor pipe and also overlapped make some distance
with welding cables..? with this main supply
cable..?
We instructed to the
Boiler Unit - Provided winch diversion concerned person to
4 1 Ground rope pulley was found run M/s PCPIL MECH UC 15/01/2021 lubricate the rope closed
floor 0 mtr dry pulley and avoid the
dry run of pulley
Instructed to the
Refiilled argon cylinders concerned sup. to avoid
Boiler Unit - the unsafe work
5
were found kept on the M/s PCPIL MECH UC 15/01/2021 closed
1 Ground practice at site and
floor 0 mtr site such in unsafe provide proper cylinder
manner..? safe stacking
immediately
Instructed to the
Boiler Unit - Usable chain pulley block concerned engg. To
6 1 Ground was found laying on the M/s PCPIL MECH UC 15/01/2021 store the CB in suitable closed
and such in safe place
floor 0 mtr ground..? and avoid the
negligence
Instructed to the
Provided flooring mates
site hse &
were found not lock
Boiler Unit - execution person
properly or tie with
9
1 Ground to ensure proper
floor & 62 &
binding wire may risk of M/s PCPIL MECH UC 15/01/2021 closed
locking of floor
69 mtr floor slip & trip and also risk of mates and avoid
man fall from the height if
the mate tie with
binding wire will fail
binding wire
Instructed to the
concerned team
advice to avoid such
Boiler Unit - Using gas cutting sat hose
unsafe practice at site
10
1 Ground pipe were found over M/s PCPIL MECH UC 15/01/2021 and must ensure that closed
floor & 62 lapped with live welding
provided welding
mtr floor cable cable and hose pipe
passing over the
induslually
instructed to the
Boiler Unit - paint box cover Sharp concerned site hse
11
1 Ground team to avoide
floor & 62
edge was found damaged M/s PCPIL MECH UC 15/01/2021 closed
such unsafe work
mtr floor to the LPG hose pipe
practice and
beware from it
Instructed to the
Boiler Unit - Hand made bar 'T' were
concerned engg. To
1 Ground found hanging in the floor
15 M/s PCPIL MECH UC 15/01/2021 remove those loose closed
floor & 62 mate at height in unsafe bar t from the mate
mtr floor manner immediately
immediately
Instructed to the
concerned person
Boiler Unit - to provide two
1 Ground Single footboard using in footboard in each
16 M/s PCPIL MECH UC 15/01/2021 closed
floor & 62 structure scaffolding structure working
mtr floor platform then
allow to the
workmen's for
work
Instructed to the
concerned engg.
And advice to
Poor cable management
separate the hose
Boiler Unit - were found at floor height
17
and live cables
1 62 & 69 And live cable were found M/s PCPIL MECH UC 15/01/2021 closed
mtr floor and provide the
over lapped with gas
insulated cable
cutting hose
hangers to each
cables and avoid
the overlapping
Instructed to the
site hse &
execution person
to remove that all
Boiler Unit - Loose materils were found unwanted loose
1 72 right kept near the floor edge materials from the
23 side, 69 left and floor grading mate M/s PCPIL MECH UC 15/01/2021 structure edge or closed
side mtr such it's high risk of fall floor mates and
floor from the height ..? provide the
material tray and
bring the loose
materials in that
tray only
Instructed to the
No landing platform
site engg. To
provide on structure
avoid such unsafe
Boiler Unit - scaffolding and workmen
24
work practice at
1 69 mtr was found working on M/s PCPIL MECH 15/01/2021 closed
floor site and before
scaffolding pipe may risk
work platform
of fall or slip from the
condition must be
height …?
ensure
We immediately
instructed to the
concern person to
provide the
emergency contact
welding booth and Using no. list with
Site DB door lock was responsible
Boiler Unit - found damaged or open electrician name
36 1 72 ,75. and also main supply M/s PCPIL MECH UC 15/01/2021 and details, also closed
mtr floor cable armed was not displayed the
connected with body gland shock treatment
.May risk of shock..? chart near the
penal or welding
booth and connect
the each penal
with main armed
cable earthing.
Instructed to the
concerned person to
Boiler Unit - remove that all
Unsafe access way found on
37 1 69,62 mtr boiler top structure M/s PCPIL MECH UC 15/01/2021 unsafe and closed
floor nonstandard
footboards from the
structure immediately
HTG Engineering Private Limited
2*800 MW AP(J)L USCTPP Godda
Weekly Site Safety Inspection Report
Responsible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
2
WAREHOU Safety net found in idle UB
MECH UC 15/01/2021 Remove the safety net
SE condition at warehouse Engineering.
ESP
Terminal box not found in UB Need to provide
3 CONTROL MECH UC 15/01/2021
ROOM welding machine Engineering. terminal box.
Arrange to remove
the garbage in
Found poor housekeeping of
Transformer UB immediate basis and
5 garbage and improper stacking MECH UC 15/01/2021
area Unit#1. Engineering. stack all the structural
of structural material.
material in proper
and safe manner.
Arrange to provide
Unit#1, Found multiple bus duct
safe length ladder
Transformer column erected with short UB
6 MECH UC 15/01/2021 with working
bus duct length ladders and improper Engineering.
platform for all the
structure. working platform.
columns.
HTG Engineering Private Limited
2*800 MW AP(J)L USCTPP Godda
Weekly Site Safety Inspection Report
Responsible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Need to shift
Purlins found stacked near M/s Lloyd
1 GIS Building MECH UC 15/01/2021 materials & stack
staging. Insulation
away from staging.
Responsible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Responssible Status of
Sl No. Location Description of the observation Sub-contractor Photographic evidence UA/UC Target Date Corrective action Photo of Corrective action
Dept. observation
Earthine should be
2 DM Plant Loose earthine. M/s JSEC TURBINE U/A 15/01/2021 tight and earth road
should proper grout.
Bunker
Unsafe working plateform, Provide hand rails for
3 Fabrication M/s JSEC MECH U/C 15/01/2021
Side edge without barricad. working platform,
Yard.
Bunker
Flammable waste scattered at Collect and remove
4 Fabrication M/s JSEC MECH U/A 15/01/2021
workplace. from the site.
Yard.