5 Structural Scheme
5 Structural Scheme
CE 01526
STRUCTURAL
SCHEME
INTRODUCTION
Structural scheme means the decision about placement and spacing of
columns, position of main beams, location of secondary beams and
position of expansion and contraction joints giving the maximum
economy and structural efficiency. This scheme is to be decided based
on the architectural scheme and operational use of the building.
1. The column spacing should not be too less to give a congested plan.
It is to be remembered that larger number of columns may even
increase the structural cost. The minimum spacing of columns is
generally taken as 3 .0 m, unless the columns are hidden within the
walls. The maximum spacing is approximately 10 m, leaving
exceptionally larger unobstructed halls.
INTRODUCTION
2. The columns are placed as symmetrically as possible where these
are lying along two mutually perpendicular axes at almost a regular
spacing. The reference lines in one direction are marked by
alphabets while the reference lines in the other direction are
designated by numerals, as shown in Fig. 20.4. In this way, every
column may uniquely be designated by its alphabetic reference
combined with the numeral reference.
INTRODUCTION
3. Primary beams usually run on all columns along the two
perpendicular directions.
4. Secondary beams are sometimes provided such that the slab panels
become sufficiently smaller to get a preferable depth of solid slab
not exceeding about 150 mm. However, in some cases, we may go
up to a depth of 175 to 200 mm.
5. Expansion joints must be provided at a spacing of 30 to 50 m and
preferably at all changes in the geometry of the structure. For
example, in case of L, I or T-shaped building, these are to be
provided at every junction of various arms of the building. These
joints must be accommodated at reasonable locations within the
plan, such as ends of various portions or blocks of the building.
At an expansion joint, the two sides of the building must be fully
divided into separate parts with no connection in between; the only
exception to this may be the foundation. Due to temperature
changes, the structure may expand or contract at these joints. The
building must have separate columns and beams at each side of
joint, as shown in Fig. 20.5.
INTRODUCTION