nov_2015_design
nov_2015_design
It
in to be analyzed for uniformly distributed moving load. For maximum reaction at the
right support, what is the total beam length (m) which should be subjected to the moving
load?
a) 10 b) 4 c) 8 d) 6
Situation 1 – Refer the Figure SAM 10.06- A barge shown in diagram carries the
following loads:
W1 = 290 kn/m
W2 = 580 kn/m
Dimensions are:
L1 = L3 = 3m
L2 = 6m
2. Find the total length, L (m) so that the upward …….. and the barge remains
horizontal.
a) 21 b) 18 c) 15 d) 24
3. If shear is zero at 5 m from the left end, what is the upward pressure in kn/m?
a) 192 b) 58 c) 174 d) 96
4. If the upward pressure is 145 kN/m, what is the resuting moment First point of zero
shear?
The spiral column shown is to be designed to carry a safe ultimate load of 2900 kN.
5. Using a steel ratio Pg of 0.025 relative to the gross concrete area, what should be the
minimum column diameter (mm)?
6. The column diameter is 600 mm and the ratio of steel reinforcement the gross
concrete area, Pg = 0.02 . Find the required minimum diameter (mm) of the main
reinforcement.
a) 21 b) 34 c) 32 d) 25
7. What is the design axial strength of the column given the following
L1 = 125 mm ; L2 = 65 mm
8. Based on the gross area of the diagonal, calculate the allowable tensile load, P (kN)
10. Based on block shear in the gusset plate along the perimeter of the welds, calculate
the allowable tensile load, P (kN).
Points A and B represent the stresses on the X face and on the Y face, respectively, of
an element in plane stress.
a) 100 b) 19 c) 50 d) 20
a) 70 b) 25 c) 105 d) 50
a) 40 b) 25 c) 19 d) 30
An open ended thin walled cylinder is subjected to an internal pressure, p and an axial
force, F resulting to the stresses as shown in the corresponding Mohr’s circle.
a) 90 b) 60 c) 110 d) 40
Situation 6 – Refer to Figure SMM 10.01
The wall bracket shown consists of an eyebar AC, and a horizontal strut BC. The
eyebar and the strut are of hollow rectangular tubes with outside dimensions of 38 mm x
76 mm and with wall thickness of 3mm. Their modulus of elasticity is 73 GPa.
Given:
L= 1.5 m
ϴ = 30o
17. What weight W (kN) can be safely applied so that the normal stress is the eyebar
does not exceed 50 MPa?
18. What weight W (kN) can be safely applied so as not to exceed the allowable strain
in the eyebar of 0.002mm/mm?
20. Given :
P1 = 1200 kN
P2 = 800 kN
b = 10 m
c = 2m
20. Find the minimum dimension a (m), such that the resulting soil pressure shall be
uniform.
a) 8 b) 16 c) 4 d) 12
21. Given :
P1 = 1200 kN
P2 = 1200 kN
a= 3 m b=6m c=3m
22. Given:
P1 = 1200 kN
P2 = 1200 kN
a=3m
b=6m
c=3m
Locate the point of inflection from the left end of the footing.
Given:
23. What is the slenderness ratio of the column? Assume that column end are pinned.
a) 16 b) 13 c) 20 d) 4
24. If the required steel ratio is 1.71, find the corresponding numberof mm diameter bars
required.
a) 8 b) 10 c) 6 d) 12
25. Find the number of 32 mm diameter bars required at ultimate design load strength,
U = 1.2 D + 1.6 L.
a) 10 b) 12 c) 8 d) 6
Situation 9 – A simply supported girder spans 10 m. It carries two (2) beams, each at
3.5 m from the supports. The concentrated load from each beam is 70 kN.
Given:
Beam Properties
bf = 260 mm Iy = 49 x 10 -6 mm -4
26. Which of the following gives the maximum bending stress (MPa)?
27. Which of the following gives the maximum web shear stress (MPa)?
28. Which of the following gives the maximum horizontal shear stress (MPa) at the
neutral axis?
Given : Loads
P1 = 1.5 kN
P2 = 0
P3 = 0
F = 1.0 kN
Dimensions
H= 3 m
S1 = S2 = 3m
S3 = S4 = 2.25 m
Situation 11- A girder spans 9 m on simple supports. It carries two (2) beams, each
inducing equal concentrated load, P, at third points of the span.
Given:
Girder Properties
A= 12500 mm2
d = 465 mm
bf = 193 mm
tf= 19 mm
tw = 11 mm
Iy = 23 x 106 mm4
32. Based on the flexural capacity of the girder, what is the maximum load, P (kN)?
33. Which of the following gives the maximum load, P (kN) based on shear capacity of
the girder?
34. To strengthen the girder, two (2) cover plates are added, one at the top and the
other at the bottom flange. The cover plates are 16 mm thick and the concentrated load
P= 180 kN. Which of the following gives the required width of the cover plates based on
bending stress?
The lap splice for a tension member requires 9- 20 mm diameter A307 bolts.
Given:
Plate thickness, t = 12 mm
S1 = 38 mm S2 = 76 mm S3 = 50 mm
Calculate the allowable tensile load, P (kN) under the following condition:
Given:
B x h = 300 mm x 400 mm
T = 100 mm
H= 2.8 mm
L = 6.0 m
38. What is the spacing of reinforcement (mm) required for the moment at the interior
beam support BE?
39. What is the spacing of reinforcement (mm) for the positive moment at the span
bounded by B-E-F-C as prescribed by design codes?
40. What is the maximum spacing (mm) of 10 mm diameter bars prescribed by design
codes?
a) 78 b) 65 c) 156 d) 33
a) 198 b) 78 c) 156 d) 99
43. What upward force (kN) is to be applied at the free end to prevent the beam from
deflecting?
a) 63 b) 95 c) 189 d) 150
Situation 15 – The basic data for proportioning trial batches for normal weight concrete
with an average with an compressive strength of 35 MPa at 28 days are as follows:
Slump = 75 mm to 100 mm
Entrapped air = 1%
44. What is the total solid volume of water, cement, coarse aggregate and entrapped
air, if the dry weight of coarse aggregate is 10.1 kN/m3?
A rigid bar AB is hinged at A and is supported by rod CD at C. The rod is pin connected
at D. The bar carries a load, W at its free end, B.
Given:
W = 80 kN
H=2m
L1 = 1.8 m
L2 = 1.2 m
Rod diameter , d = 36 mm
Es = 200 GPa
47. What is the displacement (mm) of the loaded end , B of the bar?
48. Determine the tensile stress (MPa) induced in the rod CD by the 80 kN load.
49. If the allowable stress in rod CD is 124 MPa, what weight W (kN) can be safely
applied?
Situation 17 – A trial batch for normal weight concrete with an average 28 th day
compressive strength of 42 MPa is to be proportioned based on the following:
Slump = 50 mm to 100 mm
50. What is the required dry rodded weight (kN) of coarse aggregate?
a) 16 b) 27 c) 20 d) 10
51. Find the approximate combined weight (kN) of cement and water.
Situation 18 – Refer to Fig. SAM 10.04 – A reinforced concrete floor consists of beams
with width, b= 400 mm and depth of 500 mm below the 100 mm thick slab.
Given:
S = 3m
L1 = L2 = 7.5 m
EI value is constant throughout the beam. The column at E and at H are deleted, thus
girder BEHK supports beam GHI at H and beam DEF at E. Assume that all spans are
loaded. Based on tributary area of the beams,
53. Calculate the ultimate uniformly distributed load (kN/m) at beam GHI.
54. Calculate the maximum shear Vu (kN) in beam GHI. Assume fixed supports at G
and at I.
a) 122 b) 81 c) 41 d) 182
55. Calculate the maximum positive moment, Mu (kN/m) in span GH. Assume fixed
supports at G and at I.
Situation 19 – Light gage cold- formed steel channels used as purlins are simply
supported on roof trusses 6 m apart.
Given:
Roof Slope = 1V : 4H
Properties of C Purlins:
C 200 mm x 76 mm
Assume that all loads pass through the centroid of the C section. For D + L + W, a one
third increase in allowable stresses is allowed.
56. What is the safe purlin spacing (m) due to D + L if sag rods are not used?
57. What is the maximum spacing of purlins (m) due to loads, D, L and W at the leeward
side?
58. How much is the safe spacing of purlins (m) due to loads D + L + W at the windward
side?
a) b) 1.0 c) 0.7 d) 1.2
The signage is subjected to a wind pressure of 1.6 kPa. Considering wind force acting
at the signage only, determine the following forces at the base of the pole:
Given:
W= 36 kN/m
L1 = 8 m
L2 = 8 m
a) 3 b) 0 c) 2 d) 1
63. Due to w, the resulting reaction at B = 288 kN. What is the maximum shear (kN) at
span AB?
a) 72 b) 144 c) 288 d) 36
Given : S= 2.4 m
L1 = L2 = L3 = 7.5m
LL = 3.6 kPa
Given : x1 = 8 m x2= 4 m H= 9m
70. What is the biggest load, W (kN), that can be lifted if the maximum tensile force in
the cable AC is 50 kN and the mast weighs 8 kN?
Given:
Dimensions, L1 = L2 = 6 m
S= 2.5 m
a) 144 b) 72 c) 81 d) 128
73. If beam GH is subjected to a positive span moment, Mu = 164 kN-m find the number
of 20 mm diameter bars required.
a) 6 b) 3 c) 4 d) 5
The flooring of a warehouse is made up of double-tee joints (DT) as shown. The joists
are simply supported on a span of 7.5 m and are pre-tensioned with one tendon in each
stem with an initial force of 745 kN each, located at 75 mm above the bottom fiber.
75. Compute the resulting (MPa) at the bottom fibers of the DT at midspan due to the
service loads and prestress force.
76. What additional superimposed load (kPa) can the DT carry such that the resulting
tensile stress at the bottom fibers at midspan is zero?
Given:
P1 = 1.5 kN F = 1.0 kN H= 3m
P2 = 0 S1 = S2 = 3.0 m
P3 = 0 S3 = S4 = 2.25m
Given:
80. What is the nominal axial load strength of the colmn, Pn (kN)?
81. Find the nominal shear capacity of the section, Vux (kN)
82. Calculate the nominal shear capacity of the section, Vuy (kN)
Given:
S = 1.5 m
H = 3.0 m
P1 = 13.0 kN
P2 = 6.5 kN
84. In addition to the given wind load, a vertical load of 27.5 kN is applied at joint D.
Determine the resulting vertical reaction at support B (kN)
85. What is the stress (kN) in the vertical web member CD if a vertical of 27.5 kN is
applied at joint D?
Given:
Depth, d = 305 mm
Flange thickness, tf = 12 mm
Loads: (MALABO)
Situation 30- A hollow circular pole 3 m high is fixed at the base. It is 6mm thick and its
outside diameter is 300mm. The pole is subjected to a torque and a lateral force at the
free end.
Given:
Torque, T = 25 kN-m
Lateral Force, N = 3 kN
89. What is the maximum shear stress (MPa) at the outside surface of the pole due to
the torque, T?
91. Find the maximum flexural stress (MPa) at the base of the pole due to the lateral
force.
92. To prevent beam deflection at the free end, what force P(kN) is needed at that
point?
93. What force P (kN) should be applied at mid length of the beam for displacement at
the free end?
a) 120 c) 160
94. The reduce the deflection at the free end to 19mm, how much force is needed to be
applied at that point?
Given:
b= 350 mm
h1= 100 mm
h2= 500 mm
Lateral ties, = 12 mm
a) 25 b) 28 c) 53 d) 38
96. Which of the following gives the nominal shear strength (kN) provided by the
concrete?
97. Which of the following gives the nominal shear strength (kN) of the section if the
lateral ties are spaced at 125 mm on center?
An 6m high retaining wall is subjected to lateral earth pressure increasing from zero at
the top to 138 kPa at the base. Flexural rigidity. EI = 4.5 x 10 14 N-mm2. Analyze per
meter length of wall.
98. Which of the following gives the moment (kN-m) at the base of the cantilever
retaining wall?
99. To prevent excessive deflection at the free end, the wall is braced at the top. Find
the force (kN) exerted at the propped end of the wall so that the resulting deflection is
zero.
100. When the wall is propped at the top, what is the resulting moment (kN-m) at the
base?