0% found this document useful (0 votes)
31 views20 pages

Bannockburn ST 2 - Preliminaries Specification Rev A

Uploaded by

Mheanne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views20 pages

Bannockburn ST 2 - Preliminaries Specification Rev A

Uploaded by

Mheanne
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

Nardi Holdings

Bannockburn Central – Stage 2

Preliminaries Specification

June 2024 (Rev A)


Preliminaries Specification P.i

Contents

1. General 1
1.1 Scope of Works 1
1.2 Contractor to inform itself 1
1.3 Inspections 1
1.4 Information supplied by the Principal 2
1.5 Documents 2
1.6 Obvious Minor Work 2
1.7 Contractor’s Documents 2
1.8 Adequate Supervision 2
2. Administration 3
2.1 Meetings 3
2.2 Reporting 4
2.3 Requests for Information during Design and Construction 5
2.4 Programming 5
2.5 Independent OHS 6
2.6 Authority Approval Requirements 6
2.7 Coordination, Authorities & Utility Liaison 6
2.8 By Laws, Fees & Notices 6
2.9 Structural Certification 6
2.10 Awards 7
2.11 Site Agreement 7
2.12 Industrial Relations 7
2.13 Guarantees 7
2.14 Days of Work 7
2.15 Direction of Labour, Coordination & Superintendence 7
2.16 Taxation Schedule / Depreciable Items 7
2.17 On Site Documents 7
2.18 Australian Standards & Codes 8
2.19 Tests 8
2.20 Quality Assurance 8
2.21 Document Management Systems 8

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification P.ii

3. Site 8
3.1 Site Conditions 8
3.2 Dilapidation Report 8
3.3 Surveys & Setting Out 9
3.4 Temporary Services 9
3.5 Existing Services 9
3.6 Services shutdowns effecting Adjoining Owners, Occupiers or Tenants 10
3.7 Site Accommodation 10
3.8 Attendance on & facilities for Subcontractors 10
3.9 Site Access & On-Site Parking 11
3.10 Construction Loads 11
3.11 Tools, Plant & Equipment 11
3.12 Liaison with Neighbours and Tenants 11
3.13 Security 11
3.14 Removal of Construction Materials 12
3.15 Environmental & Traffic Management 12
4. Site Control 12
4.1 Working Area & Control of Site Activities 12
4.2 Access, Protection & Fencing 12
4.3 Cranes, Scaffold, Hoists, etc. 13
4.4 Plant Hire and Small Tools 13
4.5 Sundry Expenses 13
4.6 Maintenance 13
4.7 Vermin Control 13
4.8 Dust, Noise & Nuisance Control 13
4.9 Pollution 14
4.10 Cleaning & Rubbish Removal 14
4.11 Protection of Flora & Landscaping 14
4.12 Advertising & Signage 14
4.13 Explosives 14
4.14 Welding 14
4.15 Salvaged Materials 15
4.16 Protective Apparel 15
5. Completion 15
5.1 Spare Materials 15

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification P.iii

5.2 Training of Operations staff 15


5.3 As Built documentation 15
5.4 Operating & Maintenance manuals 16
5.5 Other information required prior to Practical Completion 16

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

1. General
1.1 Scope of Works
The Works shall comprise work as specified in the contract documents.

The Contractor shall familiarise themselves with all aspects of the project, including design and construction,
site conditions, access/loading, program requirements and authority approvals & requirements and make due
allowance for all required items in accordance with the Contract documentation. Adequate supervision must
be maintained by the Contractor for the duration of the works.

The Contractor acknowledges that the contract and tendering conditions and the contract documents provide
a description of the works sufficient to enable the Contractor to carry out its obligations notwithstanding any
omission, discrepancy, or inadequacy in these documents.

The Contractor assumes the risks of all increased costs, losses and expenses arising out of any omission,
discrepancy or inadequacy in the contract documents and will not be entitled to any extension of time or
adjustment to the contract sum in respect of any variation in the works to the extent that such variation
remedies any omission, discrepancy, or inadequacy.

1.2 Contractor to inform itself


The Contractor shall be deemed to have:

a) examined all the information made available to them by the Principal for the purpose of tendering
including the drawings, specification, schedules, conditions of tendering, contract and the like;

b) examined all information relevant to the risks, contingencies and other circumstances which could affect
the price, and which is obtainable by making reasonable enquiries;

c) examined the site and its surroundings;

d) informed itself of all relevant physical conditions upon and below the surface of the site;

e) visited the site to ascertain all site conditions, conditions of access, the state of any structures thereon
and services and their effect on the costs of carrying out the works. The Contract Price shall be deemed
to include all such costs. No claim for additional costs will be considered on the grounds of the Site
Conditions;

f) informed itself as far as practicable of the nature of the work and materials necessary for the execution of
the work under the Contract, the means of access to the facilities at the Site, and transport facilities for
deliveries to the Site;

g) informed itself to the availability of labour and the accommodation required; and

h) satisfied itself that they have examined all documentation and carried out all necessary investigations
relating to the integrity of the existing structure and it’s as-built condition.

Failure by the Contractor to do all or any of the things under this Section will not relieve them of their liability to
perform all their obligations under the Contract.

1.3 Inspections
Contractors shall inspect the site and shall make arrangements for inspection through the Project Manager. It
is the Contractors obligation to confirm existing conditions, levels and the locations of existing services.
Contractors shall allow for all work involved including removal of obstructions in the way of the work and allow
any consequential make good.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

1.4 Information supplied by the Principal


The information made available by the Principal may not completely show the full extent of the existing Site
conditions. The Principal is not responsible for any interpretations, deductions or conclusions made by the
Contractor from the information made available, and the Contractor shall accept full responsibility for any such
interpretations, deductions or conclusions.

For any discrepancies, the more expensive or stringent of the alternatives shall be deemed included in the
contract sum.

It is noted that the documents supplied by the Principal are not designed as trade packages, but a set of
Contract Documents to be read as a whole.

1.5 Documents
a) Drawings & Specifications

The Contractor and any intended Sub-Contractor shall check all relevant dimensions on-site before submitting
the Tender. In no circumstances shall dimensions be scaled off drawings. No claims for additional costs
arising from the Contractor’s failure to obtain measurements and other information on site will be allowed.

b) Shop Drawings

Contractors shall allow for the preparation of all necessary shop drawings required by the projects Consulting
Engineer. Sufficient detail must be given to permit a full appraisal of all parts of the installation and their
relation to the building structure.

1.6 Obvious Minor Work


If either the Drawings or Specifications omit particulars of minor work which nevertheless is clearly to be
inferred or is necessary for the proper execution and completion of the Works, then such minor work shall be
executed by the Contractor as part of the execution of the Works and at no extra cost to the Principal.

1.7 Contractor’s Documents


Where the Contract requires the Contractor to supply documents such as shop drawings, technical schedules
or other written information, the Contractor must supply sufficient copies for retention by each interested party
including the Project Manager.

Within the timeframe stipulated in the Contract, the Project Manager shall advise as to the suitability or
otherwise of the documents. This advice shall not constitute an instruction under the Contract, nor shall it
relieve the Contractor from responsibility for the Contractor's errors or omissions or compliance with the
requirements of the Contract.

If a document is rejected, the Contractor is to submit a new or amended document.

Documents shall be supplied in sufficient time for examination, and revision, if necessary, to occur before they
are required for use.

1.8 Adequate Supervision


1.8.1 Design Management

The Contractor shall provide constant and competent co-ordination and management of its duties under the
requirements of the Contract.

The Contractor shall provide not less than the following requirements:

a) A Construction / Project Director who shall be responsible for the overall management of the project for
the duration of the design and construction of the works.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

b) A Project Manager dedicated to the project for the duration of the works that shall have a technical ability
and field experience commensurate with the scale and nature of the Works for progressing the works
during this time.

c) A Design Manager dedicated to the project during the design period that shall have a technical ability and
field experience commensurate with the scale and nature of the Works for progressing the works during
this time.

d) Such additional resources required to ensure the objectives and deliverables of the design phase are
achieved.

1.8.2 Construction

The Contractor shall provide constant and competent direction, co-ordination, and superintendence of all
trades in all phases and parts of the Works so as to comply with the required standards of the Contract.

The Contractor shall provide not less than the following requirements:

a) A Construction / Project Director who shall be responsible for the overall management of the Works and
the compliance with the terms of this Contract.

b) A Project Manager - who shall be employed during the construction period and thereafter as necessary
who shall have a technical ability and field experience commensurate with the scale and nature of the
Works.

c) Site Manager - who shall be employed full-time on Site during the construction period and thereafter as
necessary who shall have a technical ability and field experience commensurate with the scale and
nature of the Works. The Site Manager shall be available for a period of one month after the issue of the
Certificate of Practical Completion of the last Separable Portion or until such time as all the identified
completion items have been completed.

d) Such additional site management, foremen, sub-foremen, leading hands and first aid attendants as are
necessary for the satisfactory carrying out and completion of the Works and compliance with all OH&S
requirements.

e) Clerical and administrative staff for the effective and efficient support of the supervisory staff.

Note:
• The names and relevant details of experience of the personnel detailed above are to be provided to the
Project Manager for acceptance prior to the execution of the Contract.
• Any intended changes in such personnel during the construction of the Works shall be immediately
advised 14 days before in writing to the Project Manager for prior written approval.
• The Contractor is to allow for necessary supervisory staff and industrial relations and safety personnel to
be in attendance during any necessary after hours works post-handover and as required for the duration of
the Works.

2. Administration
2.1 Meetings
Throughout the duration of the Contract, the Contractor is to arrange meetings, as required by the Project
Manager with appropriate consultants, subcontractors, and the Project Manager and, unless otherwise
directed by the Project Manager, keep minutes of such meetings.

Within two working days after each meeting, the Contractor is to issue a draft of the minutes, for approval by
the Project Manager, prior to formal issue to the Project team.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

The inclusion in the minutes of any oral instruction given by the Project Manager or Principal shall not be
taken to be a written instruction or direction under the Contract notwithstanding confirmation of the minutes at
a subsequent meeting.

At the first design and site meeting the Contractor is to submit to the Project Manager the names and
telephone numbers of all responsible persons who may be contacted after hours during the course of the
Contract.

2.1.1 Design Meetings

At award, the Contractor assumes responsibility to attend, contribute to and lead the design team, design
coordination and subcontractor meetings. The Contractor will be the lead coordination consultant and be
responsible for design, design coordination, buildability, value engineering, cost management and fulfilling
Principals requirements of the development.

The Contractor is expected to liaise closely with the Project Manager, working in a collaborative manner to
achieve the objectives of the design period efficiently and effectively. The Contractor will keep minutes of all
such meetings.

2.1.2 Site & Coordination Meetings

Throughout the construction period, the Contractor is to arrange regular meetings (as required by the Project
Manager) with appropriate sub-contractors, the Architect and consultants, and Project Manager and keep
minutes of such meetings and distribute copies to the parties present within two working days after each
meeting.

2.1.3 Monthly Project Control Group Meetings

The Project Control Group (‘PCG’) meeting will be the formal forum to determine policies, strategies and
discuss significant issues in relation to approvals and other requirements, design, construction, the Site and
Site access, progress and programming, costs and budget, tenancy management, staging of the works,
operational requirements, consents required from the Principal or the Superintendent, safety, quality control,
environmental matters, industrial relations, contractual matters and administrative matters.

The PCG Meeting shall be held monthly, or such other interval as reasonably required by the Principal or
Project Manager and notified to the Contractor.

2.1.4 Tenant Meetings

Throughout the design and construction period the Contractor is to arrange any required meetings with the
Tenant, the consultant team, Project Manager, and keep minutes of such meetings and distribute copies to the
parties present within two working days of each meeting, in order to satisfy the requirements of the Tenant
Brief and Agreement for Lease, and to ensure the documentation and works proceed in line with the program
for works.

2.2 Reporting
2.2.1 Construction PCG Reports

The Contractor, as required by the Project Manager, shall submit monthly construction PCG Reports at least 7
days prior to the scheduled PCG meeting.

The Project Manager / Principal is to agree any specific details of these reports.

2.2.2 Time Lapse

The Contractor must supply, maintain, and remove on completion a time lapse camera on-site to show and
record the Contractors' on-site construction work. The location of the camera is to be agreed with the Project
Manager and located to record relevant on-site works throughout the Contract duration. The Contractor must
provide regular still photographs from the camera as part of their monthly reporting and provide a time lapse
video of all recorded on-site works within 30 days of Practical Completion.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

2.3 Requests for Information during Design and Construction


The Contractor may issue requests for information (RFI) to the Project Manager during the Project. It is the
Contractor’s responsibility to coordinate and consolidate all queries from its suppliers and subcontractors and
determine whether there is a genuine need to issue an RFI.

Generally, the Contractor is to allow in the construction program the following response times:
• Five (5) working days for additional information or clarification of items on the documents, and for approval
of Contractor sample submissions; and
• Fourteen (14) working days for review of shop drawings, alternative products or methods of constructions
to those specified.

2.4 Programming
2.4.1 Design & Construction Program Requirements

The Contractor shall supply a detailed program including all design, documentation, procurement, and
construction activities. The program shall include:
• A project calendar clearly denoting which days are workdays, allowing for restrictions on working time and
contingencies for which the Contractor is responsible. This shall include but not be limited to Sundays,
holidays, Christmas close-down, union designated and other days off.
• Activities which represent the entire scope of the works, including but not limited to;
» Completion of design;

» Completion of Building Permit deliverables;

» Commencement and completion of construction (Practical Completion);

» Satisfaction of the staging requirements of the project;

» Satisfaction of any Authority approval requirements;

» Order dates, supply lead times and installation dates for substations and other Authority installed items;

» Commencement and completion dates for external works;


» The time allowed for testing and commissioning of major items of plant or equipment;

» The preparation of and approval process for all required shop drawings and sample submissions;

» The date for Substantial Completion and handover of each tenancy for their fitout and stocking
activities;

» The inter-relationships between activities;

» The estimated duration of all activities;

» The calculation of the total float of each activity and therefore the sequence of activities which
constitutes the critical path or paths;

The program shall comply in all other respects with the requirements of the Contract.

A revised program may be requested if the Project Manager considers the current program cannot be adhered
to or it is not in accordance with the requirements of the Contract. Within five (5) working days of such a
request, the Contractor shall submit an updated program incorporating changes in methods, times, or
sequence of activities, and showing the planned progress towards the Date for Practical Completion, to the
same detail as specified for the original program.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

2.4.2 Counting of Days

For the purposes of this Contract and Works, unless otherwise noted, working days for programming and
extension of time purposes shall be all days except RDO’s, Saturdays, Sundays and Public Holidays, and a
working week shall be five (5) days.

For all other matters, including notices, time limits, etc., days shall be calendar days.

2.5 Independent OHS


The Contractor shall commission an independent safety auditor to undertake quarterly audits of the
implementation and effectiveness of the Safety and Health Management System implemented for the Works,
with such audits to include, but not be limited to:

» a Site safety plan;

» completed induction sheets;

» a risk analysis of the Works, and it’s scope;

» safety requirements to be placed upon sub-contractors;

» documentation relating to the management of sub-contractors on Site;

» completed inspection sheets;

» completed plant checklists

The Contractor must provide a copy of the auditor’s report to the Principal and comply with corrective action
recommended by the auditor within a reasonable period and to a reasonable standard.

2.6 Authority Approval Requirements


The Contractor shall pay all fees associated with the works including long service leave levy payments,
footpath crossing fees, damage deposits, hoarding erection fees, inspection fees, application fees and the like.

The Contractor shall ensure that the requirements of all authorities are complied with during the carrying out of
the Works, and the Contractor shall be responsible for all consequent costs, fees or bonds required as a result
of such compliance.

2.7 Coordination, Authorities & Utility Liaison


The Contractor shall review and include all costs for preliminaries, overheads, profit, and builders work in
connection with all coordination, authorities, and utility works.

2.8 By Laws, Fees & Notices


Unless the Contract otherwise provides, the Contractor shall be responsible for the connection of all water,
drainage, sewerage, stormwater, phones, electricity and other services and shall apply for all relevant permits
and pay all fees (with the only exception of Headworks Contribution Fees) and charges levied by the relevant
authority.

2.9 Structural Certification


All structural works must be certified by an independent structural engineer to the satisfaction of the relevant
authority. The contractor is responsible for completion of any structural design and having the design
computations prepared for certification.

All structural design must meet the provision of relevant Australian Standards and requirements of statutory
authorities.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

2.10 Awards
The Contractor shall observe all awards and pay all claims in respect of salaries and allowances, fares and
travelling time, holiday pay, long service leave, pay roll tax, insurance of workmen's tools, protective clothing
and all other Statutory Authority requirements relating to the employment of labour in accordance with their
own enterprise bargaining agreement.

2.11 Site Agreement


The Contractor shall be responsible to agree with the parties the employment conditions, which shall apply in
respect of the Works. All costs associated with the agreement shall be included in the Contractor’s price.

2.12 Industrial Relations


The Contractor is to manage and be fully responsible for all aspects of industrial relations for the execution of
the Works. The Contractor acknowledges that it has allowed in the Contract Sum for all costs and expenses of
complying with all industrial and relevant enterprise bargaining and project agreements (including any
changes during the performance of the Contract). The Contractor must keep the Principal fully and promptly
informed of industrial relations problems or issues that affect or are likely to affect the execution of the Works.

2.13 Guarantees
Unless otherwise specified or agreed, warranties, or guarantees specified in the Contract shall name the
Principal as warrantee and shall be furnished by the Warrantor direct to the Principal.

2.14 Days of Work


All demolition, excavation and building work in connection with the Works must only be carried out within the
times stipulated in the Contract and/or by the Planning Permit conditions of consent.

2.15 Direction of Labour, Coordination & Superintendence


The Contractor shall provide constant and competent direction, coordination, and superintendence of all work
and of all trades and services in all phases and parts of the Works. This must be provided at all times when
there is construction activity occurring on the Site.

The Contractor is to take responsibility for the suitability of all workers and Subcontractors working on Site,
provide a Site induction with regular updates as required, set reasonable standards of conduct, investigate
complaints about their behaviour and take appropriate action including removal from Site if so warranted.

2.16 Taxation Schedule / Depreciable Items


The Contractor must provide the relevant details to the Projects Quantity Surveyor to enable the preparation of
a schedule of depreciation items and replacement cost schedules.

2.17 On Site Documents


In addition to the documents referred to in the Contract, the Contractor shall keep at the Site in good order, a
full set of certified documents or any other document identified by any Authority, which shall be kept in a
secure place and which shall not be made available for general use on the Site but which together with the
documents referred to in the Contract shall be made available for use only by the Contractor’s employees
supervising the works as referred to in the Contract, and the Project Manager.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

2.18 Australian Standards & Codes


Where the Contract requires compliance with a standard or code, unless otherwise specified, that standard or
code shall be the one current at the closing date for tenders, except for the Building Code of Australia, which
shall be the one current at the Date of Practical Completion.

2.19 Tests
Any testing required to be by an independent authority shall be carried out by an authority registered with the
National Association of Testing Authorities Australia (NATA) to perform the specified testing.

2.20 Quality Assurance


All the Works under the Contract shall be executed in accordance with a quality assurance system that
conforms to all requirements of the ISO/AS 9000 series of standards.

2.21 Document Management Systems


A document management system (Aconex or equal approved) shall be adopted for the project and the
Contractor shall cause subcontractors and consultants to use the system. All written communication shall be
through the approved document management system, unless directed otherwise by the Project Manager.

The Contractor shall allow for the cost of the document management system in their contract sum.

3. Site
3.1 Site Conditions
The Contractor shall be responsible for investigating the site and for making all reasonable enquiries into the
risk, contingencies and circumstances relating to the works. Without limiting the generality of the foregoing,
the Contractor must ascertain the means of access to and physical conditions of the Site as well as access to
adjoining properties.

The Contractor will assume all risk and responsibility associated with the condition of the site and any damage
to the existing site and adjoining properties resulting from the works.

All works on the site must be carried out in the least disruptive manner to ensure continuity of normal business
at all times. The Contractor will be responsible for liaison where required to ensure neighbouring building
owners / authorities / tenants are kept informed at all times and do not suffer disruption.

The Contractor will be responsible for the staging of works to ensure minimized disruption to the ongoing
operation of the existing surrounding properties and roadways, including but not limited to, the provision of
hoardings, temporary services, and temporary loading arrangements as and when required.

The Contractor will be responsible for resequencing of work hours, security, and any other requirements
deemed necessary by those impacted by the works.

The Contractor is to carry out their own investigations in relation to existing conditions and services on site.

3.2 Dilapidation Report


The Contractor shall, prior to commencement of the works, undertake a video and photographic dilapidation
survey to record all existing conditions of the site, adjacent buildings, footpaths, roadways, etc. The
dilapidation report must be submitted to the Project Manager prior to the commencement of any works on site.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

Any damage to property both public and private, including buildings, services, roads, footways, paving,
fencing, passing or parked vehicles and any other property disturbed or injured shall be reinstated or made
good by the Contractor without cost to the Principal.

Reinstatement shall include spreading of topsoil, re-grassing, replacing trees, paths, kerbs, potholes, road
paving or any other item damaged or destroyed.

The Contractor shall make itself aware of all existing services within all areas of the Works. Any services
damaged by the Contractor shall be made good at the Contractors cost.

3.3 Surveys & Setting Out


The Contractor is responsible for checking and verifying all dimensions and levels on the Site and the location
of existing services on and adjacent to any area of the Works before commencing any work on the Site.

The Contractor is responsible for setting out the whole of the works and for providing the sub-contractors with
sufficient data and detailed instructions to enable them to properly carry out their Contract work.

A final identification survey must be provided certifying the position of improvements on the Site, the distance
of improvements to boundaries, compliance with relevant authorisations and locations of any easements.

Any encroachments or non-compliances revealed by any such survey must promptly be remedied by the
Contractor at its cost.

As soon as practicable, and prior to Practical Completion, the Contractor shall, at its cost, furnish the Principal
with surveys by a Registered Surveyor confirming:

a) The Works have been constructed within the boundaries and providing the title dimensions;

b) Any required survey to satisfy the Planning Permit conditions of consent;

Any encroachments or non-compliances revealed by any such survey must promptly be remedied by the
Contractor at its cost.

The measuring tool for the NLA / GLAR shall be the PCA Method for the Measurement of Buildings 1997
version published by the Property Council of Australia.

3.4 Temporary Services


The Contractor must provide and maintain all temporary services necessary for the execution of the work
under the Contract and to ensure continuity of service for any existing operational area of the Works.

The Contractor must install meters, valves, substations, and switchboards, in accordance with the
requirements of the Relevant Authorities and pay all charges in connection with the installation and use of
such temporary services.

All temporary services must be made available to sub-contractors.

On completion, the Contractor must disconnect temporary services, clear away all traces and undertake make
good works.

3.5 Existing Services


The Contractor shall notify the Project Manager of any connection, disconnection or interference with existing
services. Where existing services obstruct the Works, or if damaged in the course of performing the work
under the Contract, these services shall be dealt with as follows:

• If the service is to be continued: repair, divert, relocate as required;


• If the service is to be abandoned: cut and seal or disconnect and make safe as required.

Where the Contractor damages an existing service for any reason whatsoever, the Contractor shall bear all
costs and any delays for repairing or disconnecting the service.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

3.6 Services shutdowns effecting Adjoining Owners, Occupiers or Tenants


The Contractor shall plan the sequence of construction to ensure that owners, occupiers and tenants of other
premises supplied with services supplied from the Site have full and uninterrupted use of all building services
at all times. Where shutdowns of any services are essential, these shall be performed outside of normal
working hours and at times and in a manner agreed with any owners, occupiers and tenants of other premises
supplied with services supplied from the Site. The Contractor shall ensure that any service shutdown does not
result in damage or loss to owners, occupiers and tenants of other premises supplied with services supplied
from the Site.

3.7 Site Accommodation


The Contractor shall provide all necessary accommodations for its operations. None of the existing amenities
on Site will be available for the Contractor’s use. The location on Site of the Contractor’s accommodations
shall be as agreed with the Project Manager, and failing agreement as directed by the Project Manager.

a) Meeting Room: The Contractor shall make available the use of a site shed for the purpose of
convening site construction meetings.

b) Materials Storage: The Contractor shall provide and maintain weatherproof and dry storage for
materials subject to weather damage.

c) Sanitary Accommodation and Amenities: The Contractor shall provide messing facilities, change
rooms, sanitary accommodation and washing facilities for use by all workpeople employed on the
Works as required by Authorities or relevant Awards. Such sanitary accommodation shall be suitably
enclosed and connected to the sewer, if possible, and have proper flushing arrangements and be
maintained in a clean condition. Sanitary accommodation and amenities shall be cleaned daily or at
more frequent intervals if necessary.

d) Subcontractors’ sheds: Any sheds erected by Subcontractors shall conform to the appropriate
requirements of this Clause.

e) The Contractor shall provide first aid facilities for the use of all workpeople employed on the Works and
the Site. A fully provisioned first aid cabinet and such other lifesaving and safety equipment as
deemed necessary or as may be required by relevant Statutes, Authorities and Awards shall be
maintained at all times by the Contractor.

f) Shopfitters/Other Contractors. The Contractor shall make available site amenities, including lunchroom,
change rooms, sanitary facilities and first aid for all other contractors and shopfitters involved with the
Development.

3.8 Attendance on & facilities for Subcontractors


The Contractor shall allow for and shall provide general attendance on all subcontractors and the expression
“general attendance” unless otherwise described shall mean the Contractor shall without charge provide to
those subcontractors all reasonable facilities.

a) The Contractor shall provide its subcontractors with necessary programming information and shall
ensure the proper integration of the programming of their sub-contract works into the Contract
Program.

b) The Contractor shall provide the required inductions daily to enable all subcontractors and Shopfitters
to work on the site.

c) All subcontractors shall be allowed by the Contractor full access to those parts of the Site necessary to
perform their specified works during normal working days and hours, or otherwise by specific
arrangement with the Contractor.

d) The Contractor shall make available to all Subcontractors and Shopfitters free of charge, facilities as
follows:

• water;

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

• power;

• temporary lighting (permanent light fittings shall not be used);

• hoisting and lifting, and any other materials handling equipment;

• scaffolding - costs & responsibilities as agreed between Contractor and subcontractor;

• chutes and space for demolished or discarded materials including the provision of bins or skips and
regular removal from Site of waste materials; and

• fire protection - the Contractor shall be responsible for fire protection on the Site during construction
of the Works.

3.9 Site Access & On-Site Parking


The Contractor shall be responsible for all vehicles and equipment entering and exiting the Site and pay
particular attention to pedestrian access and safety at these entrances. The Contractor shall promptly make
good any damage caused to any roads, pavements or structures damaged by its own and/or its
subcontractor’s vehicles and equipment.

No construction or subcontractor vehicles are permitted to use the operational shopping car park for car
parking purposes.

3.10 Construction Loads


The Contractor shall ensure no excessive loads are put on any parts of the structure during the works.

The Contractor shall ensure expert advice is provided by its structural engineer to determine safe loads for the
various parts of the structure. The Contractor shall provide temporary supports as necessary to safely
distribute construction loads. The Contractor is responsible for all required engineering and certification costs
of propping temporary construction plant.

3.11 Tools, Plant & Equipment


The Contractor shall allow for all costs associated with providing scaffolding, cranage, hoisting, gantries, tools,
and any other equipment necessary for the execution of the works.

3.12 Liaison with Neighbours and Tenants


The Contractor is responsible for obtaining all necessary approvals from affected parties and adjoining
neighbours. The proposed communication strategy is to be agreed with the Principal.

3.13 Security
The Contractor, its workers and subcontractors shall abide by any direction given to it in relation to the
Principal’s security requirements for the Site and in particular any direction given by the Principal’s security
guards.

The Contractor shall from the commencement of, and throughout the period of execution of the Works up to
Practical Completion of the last Separable Portion take all proper and adequate precautions to prevent access
by unauthorised persons to the Site to prevent all thefts and vandalism. It shall be the Contractors
responsibility for the security of the site and materials delivered once building works have commenced until
Practical Completion is achieved.

The Contractor shall on completion of works for the day, make secure the site to prevent access of
unauthorized persons. Where openings have been formed on external walls these shall be secured by means
of steel shutters fixed to the inside face of walls.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

3.14 Removal of Construction Materials


Prior to Practical Completion the Contractor shall remove all plant, equipment, temporary offices, and
structures and disconnect temporary services including sanitary conveniences, mess rooms, sheds, hoarding,
protective covers, and coatings and the like, unless otherwise instructed.

3.15 Environmental & Traffic Management


The Contractor is required to prepare and implement an environmental management plan and traffic
management plan that is specific to the Site and the Works.

4. Site Control
4.1 Working Area & Control of Site Activities
The Contractor is to allow to provide and maintain all hoardings, chain wire mesh barricades, gates, and other
temporary structures, to give adequate protection to the public or other persons legally on the site or in the
vicinity of the works, including any areas of storage, unloading or hoisting material, and provide any necessary
night lighting. The Contractor shall ensure all marketing signage and hoardings are maintained to a standard
acceptable to the Principal. Any damage to marketing signage shall be promptly rectified by the contractor, at
the contractors cost.

4.2 Access, Protection & Fencing


The Contractor shall be aware of the security requirements of owners & occupiers of adjacent sites and
always comply with such requirements.

The Contractor must at all times:

a) Do everything necessary to ensure the safety and freedom from injury, damage or interference of all of
the adjacent public or private lands, properties, ways, services and all other adjacent real or personal
property whatsoever and of persons at any time in the vicinity of the Site, and in particular and without
affecting the generality of the foregoing, carry out and provide such forms of support, shielding, fencing
and other protective and precautionary measures as may be necessary for any of these purposes.

b) Protect all work and materials and make good all damage done to such work and materials until Practical
Completion.

c) Provide protection as soon as a surface is finished or upon arrival of materials or as required and
maintain adequate protection throughout the course of the Works until Practical Completion.

d) Erect hoardings, gantries, etc. in accordance with the requirements of the relevant authorities and the
Principal and as required for the duration of the construction period.

e) Provide necessary temporary covers, railings, signs, access, supports, as necessary and to the area
affected by the Works in accordance with the requirements of all relevant authorities.

f) Install lockable access gates as necessary and/or as required.

g) Erect and maintain hoardings and other protection in a safe manner.

h) Replace any damaged or vandalised hoardings or fencing as soon as practicable.

i) Install lighting, warning signs and all protection necessary for public safety.

j) Provide temporary traffic management as required for the carrying out and completion of the works,
including applying for, obtaining and paying for all required authority approvals and/or requirements, to
ensure safe access, pedestrian movements, loading and construction of the works.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

k) Prevent nuisance to the Principal, the owners or occupiers of properties adjacent to the Site and to the
public generally.

l) The Contractor shall provide protection to the public during the Works ensuring all walls and floors are
smooth, free of trip hazards, protruding nails, screws, rivets and other dangerous items.

4.3 Cranes, Scaffold, Hoists, etc.


The Contractor shall include the cost for the supply, installation, operation and removal of access equipment
required for the construction of the Works.

The Contractor shall include the cost for the supply, installation, maintenance and removal of all scaffolding
including external, internal, mobile, scissor lifts, safety rails, lift barricades, crane lifting bays, protection gantry
and swing for the construction of the works.

The Contractor shall include the cost for the supply, operation and removal of all materials hoists, fork lifts,
concrete pumps, permanent lifts and cartage for the construction of the Works.

4.4 Plant Hire and Small Tools


The Contractor shall include the cost for the supply, operation and removal of all necessary plant hire and
small tools for the construction of the works.

4.5 Sundry Expenses


The Contractor shall include the cost of all sundry expenses including but not limited to stationery, petty cash,
site photos, couriers, plan prints, photocopying and postage.

4.6 Maintenance
The site shall be maintained in a neat and orderly condition at all times during the currency of the Contract and
shall be progressively cleaned up and debris and excess material removed progressively from time to time as
necessary to the satisfaction of the Project Manager.

The Contractor shall ensure that the site is well drained and protected from flooding and, where necessary to
facilitate the progress of the works, shall provide temporary roads and/or paved access to assist the
movement of vehicles, plant, and personnel.

4.7 Vermin Control


The site shall be kept clean and suitable provision made for disposal of food scraps, etc. It shall be the
Contractor's responsibility to take all precautions necessary to prevent infestation by vermin and insects.

4.8 Dust, Noise & Nuisance Control


The Contractor shall take all possible precautions to avoid any nuisance and/or trespass to adjacent occupied
areas including but not limited to nuisance and/or trespass from dust, debris, noise, obstruction, water and/or
vibration by workmen (including those of Subcontractors) or from any other cause.

Without limiting the foregoing requirements of this clause, the Contractor shall erect screens and/or take other
preventative measures to prevent damage and shall arrange the programming of the execution of the Works
so as to prevent nuisance and trespass so far as possible. The Contractor shall provide an action plan if
excessive dust, noise nuisance is required. The Contractor shall use best endeavours to ensure that the
Works utilise best practice methods for noise suppression.

Noisy equipment shall be fitted with efficient silencers where practicable, or housed in suitably acoustically
treated enclosures so that the noise generated will be effectively dampened to a level which is not offensive to
persons on or adjacent to the site and which does not impact amenity of the Site.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

4.9 Pollution
The Contractor shall take all reasonable precautions necessary to prevent the discharge of mud, dust, water,
fumes, smoke, rubbish, and other pollutants from the site to any adjacent areas or through the existing
stormwater drainage system. The Contractor will be responsible for the rectification of any activities causing
pollution.

4.10 Cleaning & Rubbish Removal


The Contractor at all times shall keep the Site and the Works clean and tidy including all pipework, ventilation
ducts and similar areas.

The Contractor shall provide covered receptacles for rubbish, garbage and food scraps and shall have these
emptied at regular intervals as necessary. Rubbish, garbage, and food scraps shall not be left lying about the
Site and the Works. As much as practicable, all waste from the Site should be separated for ease of
recycling.

The Contractor shall take adequate measures to ensure the clean and orderly performance of the execution of
the Works. The Contractor shall make provisions for progressive sweeping and clean up, and the daily
removal of rubbish, debris, surplus materials and the like, including those of every subcontractor and for the
tidy disposal, stacking and storing of materials.

The Contractor shall make available adequate skip bins for its sub-contractors and other contractors.

The Contractor shall undertake a final detailed clean of the Site and the Works prior to Practical Completion.

4.11 Protection of Flora & Landscaping


The Contractor shall ensure that existing flora and landscaping on and around the Site in areas that are not
designated by the documents to be the subject of new landscaping work, is not damaged, disturbed, or
interfered with.

The Contractor shall repair and make good any damage caused.

4.12 Advertising & Signage


Unless specifically approved by the principal, advertising by the Contractor, subcontractors and trades shall
not be permitted on any part of the site and/or the works at any time during the currency of the Contract.

4.13 Explosives
Where it is necessary to use explosives, explosive powered tools or the like, the Contractor and all sub-
contractors shall comply with all By-Laws, Regulations, Acts, Orders and Standards governing their use and
storage.

The Contractor and/or sub-contractors shall be held strictly responsible for and shall settle, at their own
expense, any claims for damage or injury resulting from the use of such items.

4.14 Welding
Prior to any hot work being carried out the Contractor must obtain a” Hot Works permit” for issue to the Project
Manager for these works.

All hot work must be carried out in compliance with AS1674-1980.

The Contractor shall provide welding blankets, screens and fire extinguisher as required and directed by the
Project Manager.

Hot work includes any oxy-cutting, welding, gas soldering or flame heating.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

4.15 Salvaged Materials


Materials salvaged from the works other than that specified to be retained by the Project Manager shall
become the property of the Contractor.

Any such materials shall be removed from the site.

4.16 Protective Apparel


The Contractor shall ensure that the necessary protective apparel is worn by all trades working on the Site so
as to comply with the requirements of all relevant statutes, authorities, awards and the Principal’s
requirements. The Contractor shall make available all necessary protective apparel to any person visiting the
Site without such clothing and equipment.

5. Completion
5.1 Spare Materials
The Contractor must manage, co-ordinate and document the provision of spares as required by the Contract.
The Contractor must:

a) provide a schedule of spares which includes a photograph or image of the spares, the quantity
provided, the location where used on the Site and allocate a unique number to each spare; and

b) ensure spares are individually and securely packaged with a label that includes the unique number,
nature and quantity included and the location on the Site where used.

The Contractor shall allow prior to Practical Completion to supply additional materials and to place in a secure
area within the site as instructed by the Project Manager.

5.2 Training of Operations staff


The contractor shall provide, prior to Practical Completion, information, and training to operations staff on all
aspects of the new works including but not limited to:

• Lighting control system


• Electrical and mechanical system
• Security system
• Any other installations requiring training

5.3 As Built documentation


Not less than 10 days prior to issue of Practical Completion the Contractor shall provide as-built drawings for
all services and structural components of the Works. The drawings are to comply with the requirements of the
AS1100 series of Standards unless otherwise instructed and are to be provided in hard copy (3 copies) as well
as electronic format (2 copies).

Draft as-built drawings for all services and structural components are to be provided to the Project Manager at
least one (1) month prior to Practical Completion for each Separable Portion for review and approval. The as-
built drawings will need to be amended as applicable until they are approved by the Project Manager as
complying with all requirements of the Contract.

This clause should be read in conjunction with the requirements of other Contract documents.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)


Preliminaries Specification

5.4 Operating & Maintenance manuals


Not less than 10 days prior to issue of Practical Completion for each Separable Portion, the Contractor shall
provide operating and maintenance manuals, associated technical data and drawings necessary for the
efficient operation and maintenance of installations included in the Works.

The manuals are to include but not be limited to the following:

a) a general description of the installation;

b) a description of the systems with a separate description of each system;

c) start and stop procedures, and operational procedures;

d) identification of equipment suppliers/manufacturers, incl names, addresses & telephone numbers;

e) equipment details;

f) maintenance requirements both preventative and breakdown;

g) manufacturers’ handbooks;

h) performance data sheets and spare parts indexes; and

i) wiring diagrams and the like as applicable.

Provide three (3) copies and one (1) electronic copy of all operating and maintenance manuals, and where
possible in a standard format, bound and having A4 size pages.

All operating and maintenance manuals shall be submitted to the Project Manager in draft form for review and
approval at least one (1) month prior to Practical Completion for each Separable Portion. The manuals will
need to be amended as applicable until they are approved by the Project Manager as complying with all
requirements of the Contract.

This clause should be read in conjunction with the requirements of other Contract documents.

5.5 Other information required prior to Practical Completion


Not less than 10 days prior to the issue of Practical Completion, the Contractor shall provide:

a) A schedule of subcontractors and suppliers, name and address of the company, responsible officer
and company contact details and the work or product they were responsible for.

b) A schedule of Authorities detailing approval dates and reference or licence numbers.

c) A schedule of guarantees and warranties and relevant expiry dates with cross reference to the
specification.

d) A schedule of all maintenance contact details.

Nardi Holdings – Bannockburn Central – Stage 2 June 2024 (Rev A)

You might also like