IPC-1 For Print
IPC-1 For Print
GRAND SUMMARY
Total (Birr)
Item No Description
Contract Previous Month This Month Cumulative
1 LOT-B T-4 Condominium 4,336,528.35 1,680,338.56 1,680,338.56
R.N Description Unit Contract amount Previous Amount Current Amount To date Amount
A. Sub Structure
Ite
m Contract Previous Contract Previous Current To date Amount
No Description Unit UNIT PRICE QTY qty Current qty Todate qty Amount (Birr) Amount (Birr) Amount (Birr)
A. SUB STRUCTURE
Site clearing and removing of the top 200mm thick soil. It shall include m2 50.00 185.00 102.80 102.80 9,250.00 0.00 5,140.00 5,140.00
cutting & uprooting of trees on the site (1m away from building on
every side)
1.2 m3 200.00 36.00 104.06 104.06 7,200.00 0.00 20,812.00 20,812.00
Bulk Excavation to reduced level
1.3
Trench Excavation at three side of the building to depth of 0.5m below m3 300.00 37.80 23.98 23.98 11,340.00 0.00 7,193.25 7,193.25
NGL
1.4
Demolish 4cm thick existing cement screed, Terrazzo tile and ceramic m2 150.00 767.50 695.44 695.44 115,125.00 0.00 104,315.90 104,315.90
inside the building
1.5 m 2
150.00 221.56 134.01 134.01 33,234.00 0.00 20,101.53 20,101.53
Demolish damaged surface of rendered and plasterd HCB wall
1.6
Select material from quarry site well compacted at 30cm thickness m3 350.00 29.70 0.00 0.00 10,395.00 0.00 - -
under lean concrete
1.7 Cart away surplus excavated material to a distance not exceeding
m3 100.00 407.52 103.34 103.34 40,752.00 0.00 10,333.53 10,333.53
5kms.
B-SUPER STRUCTURE
4. CONCRETE WORK
4.1
a) For correction works for visible unfinished parts of stair cases thread m3 3,200.00 2.00 - 6,400.00 - - -
and risers
b) Dia 10 reinforcement bar kg 71.34 197.44 97.73 97.73 14,085.37 - 6,972.26 6,972.26
4.3
Provide, cut and fix in position sawn zigba wood or steel formwork - - - - -
which ever appropriate.
b) at one side of each door and any other necessary part of the m2 600.00 221.56 122.71 122.71 132,936.00 - 73,627.32 73,627.32
building
TOTAL CARRIED TO SUMMARY ...... 157,199.32 - 76,127.18 76,127.18
6-METAL WORK
6.1
Terrazzo tiles flooring to kichen and verandah, stair and landing and m2 320.00 154.98 0.00 49,593.60 - - -
including cement mortar backing 1:3 with joint grouted in cement
Color and the entire work shall be as per the Engineers approval.
11.3
100mm high 20mm thick Terrazzo skirting stuck to wall a cement
mortar backing 1:3 with joint grouted in cement Color and the entire ml 80.00 250.86 0.00 20,068.80 - - -
work shall be as per the Engineers approval.
11.4
300X200X4mm white Ceramic wall tiles stuck to wall for Bathroom and
Toilet with cement mortar backing and 2mm jonts to be grouted in m2 705.00 300.00 0.00 211,500.00 - - -
white cement.
11.5 Terazzo tread size 30X110mm. Price shall include mortar bed. m2 345.00 19.80 0.00 6,831.00 - - -
11.6 Terazzo riser size 15X110mm. Price shall include mortar bed. m2 345.00 9.90 0.00 3,415.50 - - -
11.7
300X200X4mm white Ceramic flooring stuck to wall for Bathroom and
Toilet with cement mortar backing and 2mm jonts to be grouted in m2 650.00 75.00 0.00 48,750.00 - - -
white cement.
TOTAL CARRIED TO SUMMARY ...... 430,475.70 - 99,164.52 99,164.52
Supply and install Ø 50mm PVC Waste Water drainge pipe in horizontal
branches and vertical stacks of approved quality with all fittings, m1 100.00 232.50 0.00 23,250.00 - - -
bends, Y's,Ts,,etc.,reducers and increasing pieces and all other
incidential works thereto, joints made tight with adhesive fluides
horizontal pipes laid to 2%,
14.1.2 Ditto items 1.1 but Ø110mm m1 150.00 182.00 0.00 27,300.00 - - -
14.1.3 Supply and Construct of 30cm dia concrete pipe for intra compound
m1 200.00 20.00 0.00 4,000.00 - - -
drainage works connecting to septic tank
14.2 Sanitary And Cold Water Installation 0.00 - - - -
14.2.1
Supply and lay approved quality storm water Ø75mm PVC down pipes
according to where shown on the drawing, with all necessary m1 105.00 320.00 0.00 33,600.00 - - -
connecting pieces and plastic straps to fix to walls.
14.2.2
Supply & install Ø50 vent caps made of rigid PVC to be connected to
the roof terminal of vent pipes complete with the necessary sealing No 200.00 8.00 0.00 1,600.00 - - -
gaskets & accessories
14.3 COLD WATER Supply 0.00 - - - -
14.3.1
Supply and install Ø 15mm Galvanized steel pipes for intrnal cold
water distribution to sanitary fixtures, complete with accessories m1 201.00 390.00 0.00 78,390.00 - - -
including elbows, unions, T's, reducers, etc. of approved quality and all
ather incidential works therto of approved qualitiy
14.3.2 Ditto items 2.1 but Ø 20mm m1 250.00 56.00 0.00 14,000.00 - - -
14.3.3
m1 305.00 200.00 0.00 61,000.00 - - -
Ditto items 2.1 but Ø 25mm
14.3.4
Supply & fix Ø15mm Gate valve complete with unions, elastic water PCS 100.00 60.00 0.00 6,000.00 - - -
proofing, hand wheels and all accessories thereto, of approved quality.
14.3.5
Suppl & fix approved quality water meter Ø15mm with Gate valves PCS 2,500.00 15.00 0.00 37,500.00 - - -
before water meter as shown on the drawings.
14.4 Supply of complete set of Fixturtures 0.00 - - - -
14.4.1
Supply & install of Tabor(Italy) ceramics Hand wash basins made of
white vitreous Tabor(Ital), with chrome plated cold water mixer, No 7,000.00 15.00 0.00 105,000.00 - - -
complete with plug. Chrome plated chain and P -smell trap of size
500X400mm
14.4.2
Supply & install of Turkish type wash down water closets with flush No 9,500.00 15.00 0.00 142,500.00 - - -
cistern and all necessary accessories
14.4.3
Supply & install of shower tray made of enameled cast iron with slip No 1,500.00 15.00 0.00 22,500.00 - - -
resistant base, and complete with approved quality flexible shower
head, mixing faucer, and P-smell trap of size 700X700X170mm
Supply & fix of Awassa Ceramics tiolet paper holde with chrome plated No 500.00 15.00 0.00 7,500.00 - - -
brass wall flanged roll with chrome plated fastening screws
14.4.6 Supply & fix of Complete soap holder made of white vitreuos
No 500.00 15.00 0.00 7,500.00 - - -
Tabor/Italy) ceramics with all necessary accessories
14.4.7
Supply & fix towel hanger made of tubular metal roller, including No 400.00 15.00 0.00 6,000.00 - - -
fastening screws and all accessories
14.4.8
Supply of best quality floor drain with all its accessaries of 100* No 510.00 15.00 0.00 7,650.00 - - -
100mm
a)Flush fixed single pole switch; 10A/ 250V no 140.00 42.0 0.0 5,880.00 - - -
b)Flush fixed two way switch; 10A/ 250V no 200.00 120.0 0.0 24,000.00 - - -
15.3 SOCKET OUTLETS POINTS 0.0 - - - -
15.3.
1
a)Flush mounted socket outlet fed through PVC insulated conductor of pcs 200.00 108.0 0.0 21,600.00 - - -
3x2.5 mm2 in thermoplatic conduit of diam 16mm for recessed
installation including junction boxes with covers all complete
15.3.
2 b)Flush mounted socket outlet fed through PVC insulated conductor of
3x4 mm2 in thermoplatic conduit of diam 25mm for '' Injera'' including pcs 200.00 35.0 0.0 7,000.00 - - -
junction boxes with covers all complete
15.4 TELEPHONE AND TV OUT LET AND ACCESSORIES 0.0 - - - -
15.4.
1 Telephone points only conduits of 19 mm minimum diameter , pcs 430.00 30.0 0.0 12,900.00 - - -
including junction boxes with covers , and pulling guy wires, all as per
ETC requirement
14.4. TV outlet TV cable and conduites of 19mm dia. Including pulling guy
2 wires for TV cables pcs 300.00 30.0 0.0 9,000.00 - - -
15.5. PVC insulated power cable size of 3x6 mm from KWhm to MDB all
2 complete in thermoplastic conduit 35mm dia ml 300.00 250.0 0.0 75,000.00 - - -
A. SUB STRUCTURE
1.7 Cart Away surplus excavated and
Demolished material to the distance 1.5km
away from the site
1. EARTH WORK
1.1 Site Clearing 102.80 from item no. 1.1
0.20 20.56 m3
1 25.70 28.30 from item no. 1.2
4.00 23.98 from item no. 1.3
102.80 m2
27.82 from item no. 1.4
2.68 from item no. 1.5
1.2 Bulk excavation upto 60cm depth
103.34
from reduced level m3
1 25.7
2.00 2. Masonry Work
0.60 28.30 m3 2.1 70 cm thick basaltic or
L=4.60+17.40+5.80=27.80m
1 27.8 equivalent
H=0.70m roughly dressed stone
masonry below NGL, bedded and
jointed in cement mortar 1:3
1 73.86 0.70 Waverage= (0.70+0.80)/2=0.75m
1.60 0.75 14.60 m3
0.30 75.76 m3
2.2 Ditto item 2.1 but for
L=4.60+17.40+5.80=27.80m
104.06 m3 1 27.8 exposed part above NGL, bedded
H=0.90m
and jointed in cement mortar 1:3.
1.3 Trench excavation at three side of
the building
0.90 Waverage= (0.50+0.70)/2=0.60m
L=4.60+17.40+5.80=27.80m
15.01
1 27.8 H=0.70+0.05=0.75m 0.60 m3
Waverage=
0.75 (0.50+0.80)/2=0.65+0.25*2=1.15m
1.15 23.98 m3 2.3 Apply pointing to exposed
1 27.8 part of stone masonry wall above
0.90 ground level in cement mortar
1.4 Demolish 4cm thick existing
1:3
cement screed, Terrazzo tile and
Ceramic inside the building. 25.02
550.91 Cement Screed m2
72.81 Terazzo tile from Kitchin and Landing
43.99 Ceramic floor Tile 3. Concrete Work
27.72 Terazzo Thread and Riser 3.1 5cm thick lean concrete C-5,
1 27.8 150 kg/cement/m
* Under masonry wallof concrete.
3
695.44 m2 0.90
25.02 m2
Contarctor Supervisor
______________________ _____________________
TAKE OFF SHEET page 18
Finishing Work of Existing T4-B Block
1.80
1 3.50 3 1 Axis 1&2 (C&D) Gr,1st & 2nd floor(10cm HCB)
2.5 2.60 14.04
0.4 2 1 4.00 Axis D (2&3) 1st & 2nd floor
3.50 m3 0.90 7.20
1 1 3.20 Axis A&B (4&5) 2nd floor
4.2 Provide cut and fix in position
reinforcement bar for lintel beam and
in any necessary places ordered by
engineer 2.40 7.68
22 0.70 a) Diam 6mm plain bar 2 1 0.80 Axis B&C (4&5) 1st & 2nd floor
9.00 2.70 4.32
0.222 2 1 1.50 Axis B (1&2) 1st floor
30.77 kg 2.70 8.10
b) Diam 10 reinforcement bar 1 1 2.10 Axis A&B (3&4) 1st floor
22 1.80 2.70 5.67
4.00 2 1 1.80 Axis 4&5 (B&C) Gr &1st floor(10cm HCB)
0.617 2.70 9.72
97.73 kg 1 1 0.80 Axis A&B (4&5) 1st floor
2.70 2.16
4.3 Provide, cut and fix in position
4.00
sawn zigba formwork 1 1 Axis D (4&5) 1st floor
a) To Lintel beam and Top tie beam 0.90 3.60
22 5.20 1 1 1.80 Axis 5&6 (C&D) 1st floor(10cm HCB)
0.20 2.70 4.86
22.88 m2 1 1 1.50 Axis B (5&6) 1st floor
2.70 4.05
5. Block work 8.69 2nd floor above lintel
5.1 HCB wall of 20x20x40cm strength 122.71 m2
a) above lintels of door and window
2 3 1.70 1st & 2nd floor (Axis C B/n 2 & 5)
0.40
4.08 m2
1 12 0.6 7.22 2nd floor above lintel
11.30
Contarctor Supervisor
______________________ _____________________
TAKE OFF SHEET page 18
Finishing Work of Existing T4-B Block
139.20 -3 11.928
1 2.80 6.14
4.50 -54.204 ddt
0.00
Edges of windows
0.00 m2 2 57.12
7.2 Supply and fix G-28 galvanized flat 0.15
metal sheet gutter as per the detailed
drawing.
2 25.00 17.14
13.00
12.00 m2 for
3.00 Err:522 m2 for three
singlefloors
floor of normal wall
100.00 ml Err:522
Contarctor Supervisor
TAKE OFF SHEET page 18
Finishing Work of Existing T4-B Block
1 2.51 landing
1.31
3.29
54 1.10
0.30
17.82 m2
Contarctor Supervisor
______________________ _____________________
Bar Schedual
Project: Construction of MHM Room, WP, Soak AP, HWF, Incinerator & S.Tank
Ba
No.of No.of Total
Lengt Total Dia
r Location Bar Shape Dia Membe No.of Length
bar r Bars h (M) (M) 6mm
No.
Contractor:__________________________
l
Date:_______________
19.6
27.79
19
5
Site Engineer:_____________________