5906G - GL - M - SP - 3013 - 00 - Specification For Centrifugal Compressors

Uploaded by

tomela3612
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
82 views20 pages

5906G - GL - M - SP - 3013 - 00 - Specification For Centrifugal Compressors

Uploaded by

tomela3612
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 20

TEKNICA (UK) LTD

WAHA OIL COMPANY


FAREGH FIELD DEVELOPMENT PHASE 2
WAHA/5906G
DOCUMENT TITLE:

SPECIFICATION FOR CENTRIFUGAL COMPRESSORS

DOCUMENT NUMBER:

5906G-GL-M-SP-3013 00

(Amendments / Supplements to API 617)

C2 29.11.01 Client Approval W Khoshaba D White W Khoshaba D White J Funnell K Hashad


C1 14.11.01 Client Approval W Khoshaba D White W Khoshaba D White J Funnell
B1 09.08.01 Client Comments W Khoshaba D White W Khoshaba J Funnell J Funnell
A1 11.07.01 IDC W Khoshaba D White W Khoshaba D White
Rev Date Issued for Originator Checked Lead Eng Project Eng PM Approval Waha
Approval

CONTENTS PAGE NO.

Page 1 of 20
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 2 of 20
1

SECTION 1 - GENERAL 3
1.0 SCOPE OF SPECIFICATION 3
1.1 Scope 3
1.3 Conflicting requirements 3
1.4 Definition of Terms 3
1.5 Referenced Publications 4
2.0 SECTION 2 – BASIC DESIGN 5
2.1 General 5
2.2 Casings 6
2.3 Interstage Diaphragms and Inlet Guide Vanes 7
2.4 Casing Connections 7
2.6 Rotating Elements 8
2.7 Bearings and Bearing Housings 8
2.8 Shaft Seals 8
2.9 Dynamics 9
2.10 Lube Oil and Seal Oil Systems 10
2.11 Materials 11
3.0 SECTION 3 – ACCESSORIES 11
3.1 Drivers 11
3.2 Couplings and Guards 12
3.3 Mounting Plates 12
3.4 Controls and Instrumentation 13
3.5 Piping and Appurtenances 15
4.0 SECTION 4 – INSPECTION, TESTING and PREPARATION for SHIPMENT 15
4.1 General 15
4.1 Inspection 15
4.2 Testing 16
4.4 Preparation for Shipment 19
5.0 SECTION 5 – VENDOR’S DATA 19
5.1 General 19
APPENDICES to API 617 20
APPENDIX A - Typical Data Sheets 20

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 3 of 20
1

SECTION 1 - GENERAL

The API 617 clause / paragraph numbering system has been used
throughout this specification for ease of reference

1.0 SCOPE OF SPECIFICATION


1.1 Scope
1.1.1 [Add]
This specification applies to centrifugal compressor units in oil/gas production
and petroleum product services, and is based on API Specification 617, Sixth
Edition, February 1995.

1.1.2 [Add]
This specification gives the minimum requirements, for the design, material
selection, inspection and preparation for shipment for skid mounted
centrifugal compressors. The requirements for documentation are presented
in the enquiry/purchase requisition and the Vendor Document Requirement
Schedule (VDRS) therein.

1.1.3 [Add]
Clauses and Paragraphs in API 617 not mentioned in this specification are
also applicable.

1.1.4 [Add]
Deviations from the requirements of this specification are not permitted
without prior written approval of the Client.

1.3 Conflicting requirements


[Replace with]
In the event of any conflict between this specification and requisitions, the
individual data sheets or other referenced data, the individual data sheet shall
govern.

1.4 Definition of Terms


1.4.24 [New]
The commercial terms are used in this specification are defined as follows:

CODE CODE is defined as the applicable Design Code

CLIENT CLIENT is defined as Waha Oil Company. CLIENT is the


company to whom all materials and equipment will be delivered
and is the end user of such materials and equipment.

PURCHASER PURCHASER is the company appointed by Waha Oil Company


to place the purchase order for the material or equipment on
Waha Oil Company’s behalf.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 4 of 20
1

ENGINEER ENGINEER is defined as Teknica (UK) Ltd. ENGINEER is the


engineering consultant appointed by Waha Oil Company to
produce the engineering design for the Project, and to prepare
technical requisitions, associated engineering deliverables and
purchase documentation.

ENGINEER is authorised to review and approve all VENDOR


document submissions required in PURCHASER Purchase
Conditions.

Correspondence on all technical issues shall be addressed by the


ENGINEER. Where the term CLIENT or PURCHASER appears
in the following document in relation to any technical issue this
shall be interpreted to mean ENGINEER acting on CLIENT’s
behalf.

VENDOR VENDOR is defined as the company engaged in a purchase


contract with PURCHASER, for the supply of materials or
equipment. During the Bidding or Tender stage VENDOR shall
be referred to as BIDDER.

SUB-VENDOR SUB-VENDOR is defined as a company awarded a sub-order by


VENDOR for part of the work awarded to the VENDOR. Note that
SUB-VENDORs are subject to CLIENT approval.

INSPECTION INSPECTION AUTHORITY is defined as the organisation that


AUTHORITY verifies that the material or equipment supplied by the VENDOR
has been designed, constructed, inspected, and tested in strict
accordance with the requirements of the applicable design code.

INSPECTOR INSPECTOR is defined as a qualified individual representing the


CLIENT or PURCHASER who verifies that the material or
equipment supplied by the VENDOR has been designed,
constructed, inspected, tested, and packed in strict accordance
with the requirements of this specification and all other Purchase
Order requirements.

SHALL The word “Shall” denotes that the requirement is mandatory.

SHOULD The word “Should” denotes that the requirements is highly


recommended but is not mandatory.

1.5 Referenced Publications


Add reference to the following Specifications;

5906G-GL-M-SP-3001 00 Unfired Pressure Vessels


5906G-GL-M-SP-3005 00 Specification for Shell & Tube Heat
Exchangers
5906G-GL-M-SP-3006 00 Design & Fabrication of Air Cooled Heat
Exchangers.
5906G-GL-M-SP-3009 00 Centrifugal Pumps (API 610)
5906G-GL-M-SP-3011 00 Positive Displacement Pumps–Rotary

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 5 of 20
1

(API 676)
5906G-GL-M-SP-3014 00 Combustion Gas Turbines (API 616)
5906G-GL-M-SP-3015 00 Shop Assembled Equipment Packages
5906G-GL-M-SP-3017 00 Specification for Lubrication, Shaft-sealing and
Control Oil Systems for Rotating Equipment
(API 614)
5906G-G-M-SP-3020 00 Piping Fabrication, Testing & Inspection and
Pressure Vessel Testing
5906G-GL-M-SP-3021 00 Painting and Coating
5906G-GL-L -SP-4001 00 General Piping Materials Class A5 to M5
5906G-GL-E-SP-5009 00 Specification for Electrical Equipment for
Package Units
5906G-GL-E-SP-5010 00 Specification for Low Voltage Electric Motors
5906G-GL-J-SP-6003 00 Specification for Instruments Supplied with
Packaged Equipment
5906G-GL-G-GE-7000 00 Equipment General Design Criteria
5906G-DC-1004 Earthing Lugs Standards

DRAFT No 001 Waha Drafting Requirements for


Contractor/Vendor
DRAFT No 002 Waha Drafting Requirements for
Vendor/Manufacturer
DRAFT No 003 Waha Civil, Electrical, Flow and Instrument
Symbol Legends and Abbreviations

[Add] Data Sheets


The technical data supplied for the equipment is provided on the data sheets,
which form part of the requisition.

The Vendor shall complete the data sheets and submit them with his
proposal. Prior to shipment, the Vendor shall submit a complete set of “as
built” data sheets.

2.0 SECTION 2 – BASIC DESIGN


2.1 General
2.1.1 [Replace]
Replace “20” years with “25” years and also replace “at least 3 years” with “at
least 4 years”.

[Add]
Compressor shall be supplied by a qualified Vendor with manufacturing
experience of similar equipment type as that of the proposed machine. The
qualified Vendor must have manufactured at least two compressors of
comparable speed, power rating and design pressures and temperatures for
gases of similar characteristics to the specified gas and shall have
satisfactory track record for at least two years field operation.

In addition, the machine shall be designed for safe, continuous, unattended


operation for the specified duties.

2.1.4 [Add]
The Vendor shall clearly illustrate the projected performance on a head-flow
5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 6 of 20
1

graph with speed lines, efficiency lines and surge limit. The head-flow graph
shall cover all speeds between 105% of the design and the minimum
continuous speed of the driver. The operating point of each of the off-design
conditions shall be plotted by the Vendor.
In applications where compressors will operate in parallel the minimum head
rise from the rated point to the predicted surge shall be 8 percent and the
head difference for the same flow shall not exceed 2 percent.

2.1.5 [Replace with]

Refer to Project Specification 5906G-GL-G-GE-7000 00 for the relevant


design data.

2.1.6 Replace the word ‘purchaser’ in the first sentence with ‘Client and purchaser’.

2.1.7 [Add]
The barrel compressor inner casing (diaphragms) shall be of a horizontally
split design. The head cover retention system or the barrel compressor shall
be of shear ring type design.
Vendor shall provide a suitable hydraulic bundle puller and cradle (special
tools) to allow safe rotor withdrawal and prevent damage to casing / inner
parts.

2.1.10 [Replace with] The maximum noise level shall not exceed 85 dBA at 3 feet
from the perimeter of the skid.

2.1.11 Liquid injection is not required.

2.1.14 Delete the bullet and delete ‘when specified’.

2.1.15 [Replace with]

All electrical equipment and components shall be suitable for the area
classification specified on the data sheets and shall comply with the
referenced project specification 5906G-GL-E-SP-5009 00 and 5906G-GL-E-
SP-5010 00.

2.1.17 Delete ‘when specified’ and add that compressor shall be suitable for site
operation on air or nitrogen. This is to allow mechanical testing of the
compressor on site.
Replace ‘purchaser’ with ‘Client and purchaser’.

2.1.19 [New]
When electric motor drivers are equipped with `fast' transfer facilities, the
compressor train shall be capable of withstanding momentary high torque
overloads equal to four times motor nameplate rating. The suitability of this
rating shall be confirmed by Purchaser after final electrical system
characteristics are defined.

In addition, for synchronous motor drives, the compressor train shall also be
capable of withstanding the peak oscillatory torque values predicted by the
system transient torsional analysis of the motor starting.

2.2 Casings
5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 7 of 20
1

2.2.8 Ductile (nodular) iron casings are not acceptable.

2.2.9 [Add]
Castings shall be radially split for gases of molecular weight less than 15, or
when the maximum allowable working pressure exceeds 550 psig.

2.2.10 [Add]
Lifting lugs shall be provided for lifting the top half of the casing for
horizontally split compressors.
Radially split casings shall also be provided with lifting lugs.

2.2.16.3 [Add]
Casing joint bolting and main process connections shall be designed to suit
tensioning by hydraulic equipment.

2.3 Interstage Diaphragms and Inlet Guide Vanes


2.3.1 Delete the bullet.

2.3.5 Diaphragm cooling is not acceptable.

2.3.6 [New]
If the side stream flow exceeds 15% of the total flow to the impeller, the
entrance passage shall minimise the disturbances at the impeller eye. In this
case the standard spaced diaphragm section is not acceptable. Use of extra
spacing between the impellers is an acceptable method for introducing a side
stream.

2.4 Casing Connections

2.4.2 Main Process Connections

2.4.2.1 Delete the bullet.

2.4.2.3 Delete the bullet and add:


Where a Vendor has no previous satisfactory experience of providing flanges
to paragraph 2.4.2.2 requirements, then mating flanges, studs, nuts, gaskets
and suitable reducers (to accommodate the next larger ANSI piping size)
shall be provided. The reducer shall be fully welded to the mating flange.

2.4.3 Auxiliary Connections

2.4.3.2 [Add]
Individual drain connections shall be provided for horizontally split casing
compressors. Each drain connection shall be piped to skid edge and be
terminated with a suitable isolation valve. Angled valves are not acceptable.

2.4.3.5 [Replace with]


Where flanged connections are impracticable, for oil or flammable gas 1 inch
or larger connection shall be full penetration butt weld. Socket weld
connections are not acceptable.

2.4.3.6 [Replace with]

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 8 of 20
1

Pipe nipples shall not exceed 6 inches (150 mm) in length. Pipe nipples of
schedule 160 for 1 inch and smaller and a minimum of schedule 80 for 1½
inch and larger and be provided with a weld neck flange.

2.5 External Forces and Moments.

2.5.1 [Replace with]


The allowable nozzle loads shall be in accordance with the following table:

Nozzle Flange Rating 150# 300# 600# 900# 1500# 2500#


Times NEMA SM 23 2 3 4 6 8 10

2.6 Rotating Elements


2.6.2 [Add]
Shaft ends shall be tapered and be suitable for hydraulically mounted
couplings. Vendor shall provide the required hydraulic equipment for this
purpose.

2.6.7 Delete ‘riveted’ from the second sentence.

2.6.8 Delete the word ‘and riveted’.

2.6.9 Cast impellers are not acceptable.

2.6.16 [Add]
Sizing of the balancing drum shall be such that a positive load is maintained
on the active side of the thrust bearing for all operating and upset conditions.

2.7 Bearings and Bearing Housings


2.7.1 General

2.7.1.2 Delete ‘Unless otherwise specified’.


[Add]
Dual Resistance Temperature Detectors (RTD) shall be provided for each
journal bearing.
Thrust bearing shall be fitted with two, dual RTDs on each side.

2.7.4 Bearing Housings

2.7.4.8 [New]
Adequate space shall be provided between the casing and the bearing
housing to allow fitting of an earthing brush, should this become necessary. A
design and drawing shall be provided for such an arrangement.

2.8 Shaft Seals


2.8.1 [Add]
The use of unidirectional self acting dry gas seal is the preferred option for
centrifugal compressors, provided that Vendor has satisfactory field
experience for similar applications.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 9 of 20
1

Where self acting dry gas seals are technically not feasible for the proposed
duty, the Vendor, in consultation with the seal manufacturer, shall design the
system with a view to converting the arrangement, at a future date, to accept
dry gas seal system without the need for any site machining.

Where both Dry Gas Sealing and conventional Seal Oil Sealing
arrangements are feasible, the Vendor, as Bidder, shall provide Option Prices
for both arrangements. Together with the option prices, Bidder shall state his
recommended Seal arrangement, clearly stating the advantages and benefits
of his preferred arrangement.

Vendor, as Bidder, shall provide a separate price and technical specification,


for the supply of a suitable skid-mounted nitrogen generation package
(Pressure Swing Absorber (PSA) type or equivalent) to provide nitrogen for
the dry gas seals. This price shall appear as a separate line item on the
Bidder’s pricing summary.

2.8.2 Delete the bullet and delete ‘when specified’.

2.8.3 Delete the bullet and add:


The preferred seal type shall be as per project specification 5906G-GL-M-SP-
3017 00, Chapter 4, figure 4A – 2 (tandem type with an intermediate
labyrinth seal). Floating carbon bushes shall also be provided at the shaft exit
from the casing.

2.8.3.2[Add]
Gas leakage from static compressor shall be prevented when mechanical
contact type seals are provided.

2.8.4 [Add]
For low temperature services, provisions shall be made to maintain the
sealing oil above its pour point temperature at the inner seal and drain
connection.

2.8.7 Delete the bullet and ‘Unless otherwise specified’ and add:
When buffer gas injection is required, the Vendor shall provide the complete
buffer gas control system and also advise the flow rates requirements.

2.8.8 Delete the bullet and ‘’When specified’. The Vendor shall provide all the
necessary control system requirements to prevent the ingress of air and
moisture for all operating conditions including start up and shut down.

2.9 Dynamics

2.9.1 Critical Speeds

2.9.1.4 [Add] Where the calculated amplification factor is less than 2.5, this shall be
verified by the residual unbalance testing, as per Clause 2.9.3.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 10 of 20
1

2.9.1.6 Delete ‘unless the resonances are critically damped’ from this clause.

2.9.2 Lateral Analysis

2.9.2.2 [Add]
The Vendor shall provide details of all the assumptions made for the
excitations and damping, including film stiffness used for damped unbalance
response analysis.

2.9.2.5 (e)[Add]
Sub-synchronous resonances at 52% or below of the normal rated speed
shall be avoided. Where such requirement cannot be met, the Vendor shall
perform a rotor stability analysis at rated speed for a constant speed train and
from the minimum speed to 125% of rated speed for a variable speed train.

2.9.4 Torsional Analysis

2.9.4.3 Delete the word ‘preferably’ from the first sentence for constant speed motor
drives. For variable drives, where such requirement may not be avoidable,
the Vendor shall prove that system will not be subject to adverse effects.

2.9.5 Delete ‘when specified’.

2.9.4.6 [Add]
The acceptance criteria will be subject to Vendor demonstration that the
transient events in the motor will have no adverse effect, when considering
the following:
- Start-up of the motor
- 2 phase terminal short circuits
- Asynchronous run-up on synchronous motors
- pulse operation of a variable speed motor
- Out-of-synchronous reconnection of the supply after a transient power
failure.

The above analyses will be subject to purchaser’s approval.

2.9.5 Vibration and Balancing

2.9.5.5 [Add]
‘A’ values given is to include the run-out.
The casing or bearing housing maximum allowable vibration velocity levels in
any plane shall not be more than 0.125 in/s (rms).

2.10 Lube Oil and Seal Oil Systems

2.10.3 [Add]
Self acting dry gas seals shall be used (tandem with intermediate labyrinth)
as the preferred option.
Seal oil system may be used provided the Vendor has no proven field
experience with dry gas seals for the proposed application.

The lube oil and seal oil system may be combined provided the gas being
handled in not corrosive, toxic, or have higher percentage of heavy
5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 11 of 20
1

hydrocarbons (molecular weight of 40 plus). Adequate decontamination and


degassing facilities shall be provided for the inner drain oil before it can be
returned to the oil reservoir.
Where separate oil systems are used, adequate separation space shall be
provided between the seal and bearing housing to eliminate the possibility of
cross contamination.

2.10.5 [Replace with]


The pressurised oil system shall comply with the requirements of project
specification, 5906G-GL-M-SP-3017 00.

2.11 Materials

2.11.1 General

2.11.1.1[Add]
Alternative materials of construction may be offered by the Vendor, if in his
experience the alternative materials are superior to those specified.

2.11.1.7 [Replace the first sentence with]


Material for compressors for gas containing hydrogen sulphide (25 vppm or
more) shall comply with the requirements of NACE MR 0175 (latest edition).

2.11.1.9 [Add] Overlays are acceptable subject to prior written approval on Client.

2.11.1.15 [Replace first sentence with]


The bolting material for pressure containing parts shall be ASTM A193 grade
B7 and nuts shall conform to ASTM 194 grade 2H as a minimum.

2.11.2 Pressure – Containing Parts

2.11.2.10 Delete the bullet and ‘When specified’.

2.11.5 Impellers

2.11.5.3[Add]
Any new impeller design shall be overspeed tested to 120% of the aximum
continuous speed. After the overspeed test, the impeller shall be examined
and any permanent deformation will be a cause for rejection.

3.0 SECTION 3 – ACCESSORIES


3.1 Drivers
3.1.3 [Add]
The driver shall be suitable for starting the compressor with casing
pressurised to settle out pressure or suction pressure, in addition to being
able to start on Nitrogen gas. In the latter case, the Vendor shall advise the
limitation on the pressure ratio and the maximum allowable temperature rise.

Variable speed drivers shall be suitable for all operating conditions and speed
range specified up to 105% of the rated speed.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 12 of 20
1

3.1.5 Delete this clause and replace by:


Electric motors shall be in accordance with project specification 5906G-GL-E-
SP-5010 00.requirements.

3.1.7 Delete this clause and replace by:


Gas turbine drivers shall conform to project specification 5906G-GL-M-SP-
3014 00 requirements.

3.1.8 Delete this clause and replace by:


Gearboxes shall be to API 613 and AGMA 420 and AGMA 421. Gearbox
rating shall be based on the potential power rating of the driver. Epicyclic
gearboxes are not acceptable.
Vendor shall provide a completed set of API data sheets for the proposed
gearbox.

3.2 Couplings and Guards

3.2.1 Delete ‘Unless otherwise specified’.


The coupling guards shall be of non-sparking type.

3.2.2 [Add]
Coupling shall be of dry non-lubricated spacer type in accordance with API
671 specification. Spacer length shall be suitable to allow withdrawal of the
bearing shell or seal cartridges without removing the gearbox or the
compressor.
Main coupling shall be of taper bore design to suit the shaft and be arranged
for hydraulic mounting and removal.

3.3 Mounting Plates

3.3.1 General

3.3.1.1 [Replace with]


A common baseplate shall be provided to accommodate the train. The
baseplate shall be extended to accept the rotor withdrawal cradle, where
applicable.

3.3.1.2 In clauses 3.3.1.2.1 through 3.3.1.2.10 the term ‘mounting plate’ is to be


replaced with ‘baseplate’.

3.3.1.2.9 Delete the bullet. Non-shrink epoxy grout will be used.

3.3.2 Baseplate

3.3.2.1 Delete ‘When specified’.

3.3.2.2 Delete ‘When specified’.

3.3.2.4 [Add]
The deflection during the lifting of the assembled package shall not exceed
1:1200.

3.3.2.6 Delete ‘When specified’.


5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 13 of 20
1

3.3.2.9 The oil reservoir shall be separate from the baseplate.

3.4 Controls and Instrumentation

3.4.1 General

3.4.1.1 Delete the bullet. Delete ‘When specified by purchaser’ from the second
sentence.

3.4.1.2 [Replace]
Instrumentation and installation shall be in accordance with project
specifications, 5906G-GL-J-SP-6003 00. Instrumentation requirements shall
conform to 5906G-GL-M-SP-3017 00.

3.4.2 Control Systems

3.4.2.1 Delete the bullet. Delete the third and fourth sentences.
The control system will be based on a digital electronic system, with
automatic and manual facilities and remote interface capability.

3.4.2.2 Delete the bullet and ‘When specified’ and add:

The Vendor shall provide the Anti-Surge and Load-Sharing controllers


including the configuration and software required. These systems shall be of
proven design.
The surge control system shall be invariant to process gas characteristics.
Vendor shall also provide the recycle valve of low noise type, with linear
characteristics with full stroke timing of less than one second.
Vendor shall carry out a stability analysis for the anti-surge control system,
where machines are operating in parallel and / or with variable speed drives.

3.4.2.3 Delete the bullet.

3.4.2.4 Delete the bullet.

3.4.3 Instrument and Control Panels

3.4.3.1 Delete ‘When specified’.


The panel shall be in accordance with project specification 5906G-GL-J-SP-
6003 00 requirements.
The panel shall be of free standing type and located off the skid in the
Package Control Cubicle.

3.4.3.2 [Add]
All interconnecting cables, trays and supports from the Package Control
Cubicle and the skid(s) shall be provided and installed by the Vendor.
Connections shall be accomplished through junction boxes at either end.
Cabling shall be in accordance with specification, 5906G-GL-E-SP-5009 00.

3.4.4 Instrumentation
5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 14 of 20
1

3.4.4.1 General
Delete “When specified”.

3.4.4.2.1 [Add]
Mercury filled temperature gauges are not acceptable.
Temperature gauges shall be in accordance with project specification 5906G-
GL-J-SP-6003 00.

3.4.4.5 Delete the words ‘When specified’ from the third sentence. Pressure gauges
shall be in accordance with project specification 5906G-GL-J-SP-6003 00.

3.4.6 Electrical Systems

3.4.6.2 Delete the bullet and the second sentence. Amend the referenced paragraph
number at the end of first sentence to read “2.1.15” instead of ‘2.1.14’.

3.4.6.3 [Add]
Electrical cabling shall be segregated from all the Instrument wiring to avoid
any interferences with latter signals.

3.4.6.6 Delete the bullet and “When specified” from the second sentence.

3.4.6.7 [Add]
Wiring and cabling shall be in accordance with project specifications 5906G-
GL-J-SP-6003 00 and 5906G-GL-E-SP-5009 00.

3.4.6.8 [Replace with]


Refer to project specification 5906G-GL-E-SP-5009 00 for requirements.

3.4.7 Vibration, Position and Bearing Temperature Detectors

3.4.7.1 [Add]
• Two 90° apart radial probes are required for each bearing.
• A key phaser for each shaft system is required.

3.4.7.2 Delete the bullet and ‘When specified’.

3.4.7.3 Delete the bullet. Resistance Temperature Detector (RTD) shall be provided.
Refer to Project Specification 5906G-GL-J-SP-6003 00 for details.

3.4.7.4 Delete the bullet and ‘When specified’.

3.4.7.5 Delete the bullet and “When specified”. The casing vibration probes for the
gearbox and the gas turbine driver are required in addition to the radial
probes (3.4.7.1).

3.4.7.6 Delete the bullet and “When specified”.

3.4.7.7 [New]
Seals shall be installed at the entry of each probe to eliminate possibility of
any leakages.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 15 of 20
1

3.5 Piping and Appurtenances

3.5.1 General

3.5.1.1 [Replace]
All auxiliary piping shall be in accordance with project specification 5906G-
GL-M-SP-3017 00 requirements.

3.5.1.2 [Add] to item (f):


The balance gas line shall be fitted with orifice plate flanges, with upstream
and downstream connections to a differential pressure transmitter for
measuring flow.

3.5.1.6 Delete the bullet. Replace the word ‘Buffer’ with ‘Buffer and Separation’.

3.5.2 Instrument Piping

Instrument piping shall be in accordance with project specifications


5906GGL-M-SP-3017 00and 5906G-GL-J-SP-6003 00 requirements.

4.0 SECTION 4 – INSPECTION, TESTING and PREPARATION for SHIPMENT

4.1 General

4.1.1 [Add]
Client reserves the right to assign a third party inspector to attend / observe /
witness any or all the inspection and testing activities at Vendors’ or his sub-
Vendor’s shop.
Inspection and testing shall comply with this specification, data sheets and
the agreed Procedures and Quality Control Plan issued with the Purchase
Order.

4.1.4 Delete the bullet. Refer to purchase requisition and attachments for the
extent of Client’s participation in the inspection and testing.

4.1.6 Delete the bullet and ‘When specified’.

4.18 [New]
Any approval given by the purchaser’s inspector(s) and/or Inspection
Authority do not relieve the Vendor of any responsibility regarding
guarantees, workmanship or compliance with this specification and the
relevant codes.

4.1 Inspection

4.2.1 General

4.2.1.1 [Replace the first sentence with]


Vendor shall retain the data listed below for 10 years and make it available
for examination by Client or his representative upon request. The data shall
be offered to the Client after 5 years.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 16 of 20
1

4.2.1.3 Delete the bullet and the words ‘The purchaser will specify the following’, and
replace with; Vendor shall provide relevant test procedures for approval for
the following applications:

4.2.1.5 Delete the bullet and ‘When specified’.

4.2.1.5 Delete the bullet and ‘When specified’.

4.2 Testing

4.3.1 General

4.3.1.1 Replace the Clause with]


Equipment shall be tested in accordance with this specification.
Where Capital spare parts have been purchased, they shall be subjected to
the same tests as per the main parts.

4.3.2 Hydrostatic Test

4.3.2.2 Replace ’30 minutes’ with ’60 minutes’.

4.3.2.3 Replace ’50 parts per million’ with ’30 parts per million’.

4.3.3 Impeller Overspeed Test


Replace ‘’duration of 1 minute’ with ‘duration of 3 minutes’.

4.3.4 Mechanical Running Test

4.3.4.1.8 Delete the second sentence.

4.3.4.1.9[Add]
Vendor test report shall include a hard copy of frequency spectrum analysis
for each channel of vibration.

4.3.4.1.10[Add]
Immediately before the test run, the shaft run out shall be measured at each
probe vibration location.

4.3.4.2.4 Amend the first sentence to read ‘The inner and outer seal oil leakage shall
be measured at each seal.’

4.3.4.2.5 Delete the bullet and ‘When specified’.

4.3.4.3.1 Delete the last sentence and replace with:


The measured unfiltered vibration levels shall not exceed the limits of clause
2.9.5.5 of this specification.

4.3.4.3.2[Add]
Vendor test report shall include copies of sweep plots (frequency versus
displacement) when operating at the minimum, rated and maximum
continuous speeds.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 17 of 20
1

4.3.4.3.3 Delete the bullet. Delete ‘When specified’ from the third sentence.

4.3.4.3.6 Delete the bullet and “When specified”.

4.3.4.3.7 Delete the bullet and “When specified”.

4.3.4.4.1 Delete the second sentence and replace with:


Only Oil Film type seals shall be removed for inspection after a satisfactory
test run.

4.3.5 Assembled Compressor Gas Leakage Test

4.3.5.3 Delete the bullet ‘When specified’.


[Add] The test shall be carried out after the post-test inspection (4.3.6.8).

4.3.6 Optional Tests

The required optional tests will be specified on the data sheets.

4.3.6.1 Performance Test

This test is required to be carried out on one unit of identical machines.


However for units required for parallel operation, Vendor shall guarantee
satisfactory operation can be achieved with equal / unequal load sharing
mode. This requirement is also applicable to spare rotor.

4.3.6.1.1[Add]
No correction for Reynolds number variation shall be made.

For a variable speed machine, five test points (including the surge point) shall
also be taken at maximum continuous speed and the minimum operating
speed.

4.3.6.1.3 [Replace with]


For variable speed compressors, a speed other than the ‘normal’ speed may
be used –if necessary- to achieve the required performance. In this case the
maximum continuous speed and trip speed margins shall be maintained and
in accordance with Figure 1 of API 617, Sixth Edition February 1995.

4.3.6.1.4 Replace the ‘107%’ quoted in the clause with ‘104%’ of the guaranteed
value.

4.3.6.1.5 Delete this clause and refer to clause 4.3.6.1 of this specification.

4.3.6.1.6 Delete the bullet.

4.3.6.1.7 [New]
Contract seals shall be used during the performance test.

4.3.6.1.8[New]
For compressors fitted with self acting dry gas seals, the following
parameters shall be measured during the performance test:

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 18 of 20
1

• Dynamic seal leakage, at normal speed and the maximum continuous


speed.
• Static leakage before and after the test.
• Buffer gas and Separation gas flow rates.

The leakage and flow rates shall be corrected to site operating condition, if
necessary.

4.3.6.1.9[New]
Vendor performance procedure shall state all the flows and any correction
factors for internal losses, balance losses and any other losses that should
be considered.
The procedure will be subject to Client’s and purchaser’s approval.

4.3.6.2 Complete Unit Test

A compete unit test is required during the Mechanical Running Test of each
package. These tests are in addition to individual equipment tests when
specified on the data sheets.
Delete ‘When specified’ from the third sentence.

4.3.6.5 Helium Test

Helium test is required for compressor handling gases of molecular weight of


15 or less.

4.3.6.6 Sound Level Test

[Replace] Sound pressure level measurements shall be performed for all the
equipment.
The Noise levels shall not exceed 85 dBA at 3 feet from the skid edge.

4.3.6.7 Auxiliary Equipment Test

[Add]
Self Acting Dry Gas Seals shall be tested, generally to API Appendix I, at full
speed and pressure at seal Manufacturer’s works.
The seal Manufacturer shall submit a test procedure for Client’s and
Engineer’s approval.
As a minimum, the following points shall be addressed / verified during these
tests.

• Overspeed test as per clause 4.3.3.


• Static seal leakage pressure tests, from atmospheric to maximum
sealing pressure when cold and hot (simulated shutdown with full
pressure).
• Verify dynamic seal faces lift off minimum rotating speed.
• Dynamic leakage flow rates measurements at the maximum
continuous speed.
• Measurement of leakage rates at trip speed for 3 minutes period.
• Post-test strip down and inspection.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor


WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 19 of 20
1

4.3.6.8 Post-Test Inspection of Compressor Internals

This inspection is required after completion the mechanical test of the


machine (including the spare rotor) and performance test.

4.3.6.9 Full Pressure / Full Load / Full Speed Tests

The above tests will be carried out on site.


Full details shall be developed jointly by the Client / Owner and the Vendor.
The Vendor shall be responsible for the complete package until the unit has
been accepted by the Client / Owner.

4.3.6.10 Spare Parts Test

Spare compressor rotor and spare gear rotors shall be mechanically tested
as per the main component tests.

4.4 Preparation for Shipment

4.4.1 Replace “type of shipment specified” with “ sea worthy shipment” in the first
sentence and replace ‘six’ months with ‘eighteen’ months in the third
sentence, unless specified otherwise in the requisition.

4.4.3 Replace the words ‘…released by the purchaser’ with ‘…after inspector notify
the Purchaser of his release and the Purchaser’s release note for equipment
for shipment ’.

4.4.3.1 Painting and coating shall be in accordance with project specification 5906G-
GL-M-SP-3021. Vendor may offer his standard painting and preservation
systems for the proposed equipment for Client’s review and approval.

4.4.3.2 [Add]
The proposed system shall be approved by Client.

4.4.3.4 [Add]
The proposed system shall be approved by Client.

4.4.3.10 [Replace with]


The spare rotor shall be supplied in a metal container which is fully nitrogen
blanketed and complete with pressure regulator, pressure gauge and
moisture sight glass.
The system shall be suitable for site storage for at least 4 years.

4.4.3.11 Delete the bullet and ‘When specified’.

5.0 SECTION 5 – VENDOR’S DATA


5.1 General
5.1.1 [Substitution]
All documentation shall be submitted as detailed in the relevant section of the
compressor requisition and the Vendor Document Requirement Schedule
(VDRS).
5906G_GL_M_SP_3013_00 for Centrifugal Compressor
WAHA OIL COMPANY
FAREGH FIELD DEVELOPMENT PHASE 2
TITLE SPECIFICATION FOR CENTRIFUGAL REV DATE PAGE NO.
COMPRESSORS (API 617)
DOCUMENT 5906G-GL-M-SP-3013 00 C2 29.11.0 20 of 20
1

5.2.2 Drawings

5.2.2.1 [Add]

Drafting standards shall be in accordance with Waha Oil Company , Drafting


Requirements for Contractor/Vendor Specification No. DRAFT 001 and
Vendor/Manufacturer Specification No DRAFT 002 and to Waha Civil,
Electrical, Flow and Instrument Symbol Legends and Abbreviations, DRAFT
No 003.

5.2.5 Options

Delete “When specified”.

5.3 Contract Data

5.3.3.1.5 Delete the bullet and ‘when specified’.

5.3.4 Delete the bullet.

APPENDICES to API 617

APPENDIX A - Typical Data Sheets

Delete and use Client’s data sheet included in the Material Requisition.

5906G_GL_M_SP_3013_00 for Centrifugal Compressor