API 1104 FINAL QATAR-KEY
API 1104 FINAL QATAR-KEY
API 1104 - PRACTICE EXAMINATION- ALLIGN Properly With Code Ref from 46 to 75
Read each question carefully, and select the one best answer. It is very helpful for you
to write down the Section number(s) and page number(s) where you found the
answer.
1. Automatic welding without filler metal additions shall be done using ( 13.1)
a. GTAW
b. OFW
c. the flash butt welding process
d. SMAW
e. none of the above
4. For pipe ends of the same nominal wall thickness, the alignment offset
requirement is:(7.2)
a. not more than 1/4 inch
b. not more than 1/8 inch
c. not more than 1/32 inch
d. If misalignment is larger than 1/16 inch due to dimensional variations, it
shall be equally distributed around the circumference of the pipe.
e. none of the above
Page | 1
6. Lineup clamps shall be used for butt welds in accordance with the
procedure specification. When it is permissible to remove the lineup clamp
before the root bead is completed,:(7.3)
a. The completed part of the bead shall be in approximately equal segments
spaced approximately equally around the circumference of the joint.
b. the completed part of the bead shall be removed and rewelded after
removing the clamp,
c. The completed part of the bead shall be peened before removing the
clamp.
d. the completed part of the bead shall be at least 4 inches long for all pipe
sizes
e. none of the above
7. During welder qualification, when destructively testing pipe with a diameter less
than or equal to 15/16 inches Table 3 note)
a. radiography must be used
b. the entire pipe must be used for bend testing
c. one full-section tensile specimen may be substituted for the root-bend and nick-
break specimens
d. pipe of this diameter may not be destructively tested
e. none of the above
8. When pipe is welded above ground, the working clearance around the pipe at the
weld should be at least:( 7.6)
a. 12 inches
b. 16 inches
c. 20 inches
d. 24 inches
e. 30 inches
10. When automatic or semiautomatic welding is used, which of the following shall be
removed by grinding before welding over them? 7.7 2nd para
a. surface porosity clusters
b. bead starts
c. high points
d. all of the above
e. none of the above
Page | 2
11. Undercutting adjacent to the final bead on the outside of production pipe welds
shall: Table 4
a. not be permitted
b. not be more than 1/32 inch or 12.5% of the pipe wall thickness, whichever is
smaller
c. not be more than 1/8 inch or 6% of the pipe wall thickness, whichever is smaller
d. always be acceptable if the inspector does not see it
e. none of the above
14. Inadequate penetration without high-low (IP) found by NDT shall be unacceptable
when: 9.3.1
a. the aggregate length of IP indications exceeds 3 inches in any continuous 12 inch
length of weld
b. the aggregate length of IP indications exceeds 2 inches in any continuous 12 inch
length of weld
c. the aggregate length of IP indications exceeds 1 inch in any continuous 12 inch
length of weld
d. the aggregate length of IP indications exceeds 1/2 inch in any continuous 12 inch
length of weld
e. the aggregate length of IP indications exceeds 1/4 inch in any continuous 12 inch
length of weld
Page | 3
16. Field bevelling of pipe ends by manual oxygen cutting is acceptable if authorized
by the company, 7.4.2
a. True
b. False
c.this statement is true only if the cutting operator is certified by API
d. this statement is true only if the cutting operator is a certified welder
e. none of the above
17. Any length of internal concavity (IC) found by NDT is acceptable provided:9.3.6
a. the density of the radiographic image of the IC does not exceed that of the
thinnest adjacent base metal
b. the density of the radiographic image of the IC must exceed that of the thinnest
adjacent base metal
c.IC is never acceptable
d. ultrasonic inspection does not reveal the IC
e. none of the above
18. Parallel elongated slag inclusion (ESI) indications separated by approximately the
width of the root bead shall be considered a single indication unless the width of
either of the indications exceeds 1/16inch.-9.3.8.2
a. True
b. False
c.true if no other indications exist
d. true if SMAW was used for the welding
e. none of the above
19. A welding procedure test is being performed on 3 inch schedule 80 pipe (0.300"
wall). What is the total number of specimens required for testing? Table 2
a. 4
b. 6
c. 8
d. 12
e. 16
Page | 4
21. NDT operators may, by API 1304, be required to:8.4.2
a. pass the AWS CWI exam
b. only pass the ASNT Level I exam for all test method interpretations
c.be recertified if any question arises about their ability
d. demonstrate at least two different methods of NDT
e. demonstrate at least three different methods of NDT
22. Which of the following types of defects may be repaired with prior company
authorization?10.1.1 & 1.2
a. cracks in the root
b. cracks in the filler beads
c.excessive undercut
d. root bead porosity
e. a and b above
25. When found by NDT, inadequate penetration due to high-low (IPD) shall be
unacceptable when:9.3.2
a. the length of an individual IPD indication exceeds 1 inch
b. the length of an individual IPD indication exceeds 2 inches
c.the aggregate length of IPD indications exceeds 3 inches in any continuous 12
inch weld length
d. a and c above
e. b and c above
26. Cracks in welds may be repaired provided the following criteria are met:10.1.1
a. the length of the crack is less than 8% of the weld length
b. the crater crack must be ground smooth
c.complete repair procedure has been developed and documented
d. a and c above
e. b and c above
Page | 5
27. For pipe with an outside diameter greater-than or equal to 2 3/8 inches, isolated
slag inclusions (ISI) fount by NDT shall be unacceptable when: 9.3.8.2
a. the aggregate length of ISI indications exceeds 4 inches in any continuous 12
inch weld length
b. the aggregate length of ISI indications exceeds 3 inches in any continuous 12
inch weld length
c. the aggregate length of ISI indications exceeds 2 inches in any continuous 12
inch weld length
d. the aggregate length of ISI indications exceeds 1 inch in any continuous 12 inch
weld length
e. the aggregate length of ISI indications exceeds 1/2 inch in any continuous 12
inch weld length
30. The essential wire dia for API 1104- ASTM Peni is for 20 mm thk object
is-Table 5
a. 0.1 mm
b. 1mm
c. 0.51 mm
d. 2 mm
e. none of the above
31. When selecting butt-weld specimens for a welder qualification test, the specimen
locations may be rotated, provided they are equally spaced around the pipe;
however, specimens shall not include the longitudinal weld. Fig 3 note 1
a. True
b. False
c. the welder may select any location for the samples
d. the inspector may select any location for the samples
e. none of the above
Page | 6
32. API 1104 applies to the welding of pipe and fittings that conform to: 4.2.1
a. API Specification 5L
b. API Specification 620
c. AWS Specification 5.19
d. Applicable ASTM specifications
e. a and d above
33. Essential hole dia for 1 inch object thk is ( No code coverage)
a. 1/32 inch
b. 1/16 inch
c. 3/32 inch
d. 1/8 inch
e. 5/32 inch
36. The only API-approved method for testing a nick-break specimen is breaking it in
a tensile machine.5.6.3.2
a. True
b. False
c. true, but the exposed area of the fracture must be at least 3/4 inch
d. true, but the exposed area of the fracture must be no more than 3/4 inch
e. none of the above
37. If the pipe wall thickness range radiographed is greater than 3/8 inch through 1/2
inch, what is the maximum thickness in inches of the required ISO
penetrameter?Table 6
a. 0.005
b. 0.0075
c. 0.013
d. 0.0125
e. 0.0150
Page | 7
38. The bend test shall be considered acceptable if: 5.6.4.3
a. there are no cracks or other defects
b. the bend sample does not break into several pieces
c. the defects in the weld or fusion zone do not exceed 1/16 inch in any direction
d. the defects in the weld or fusion zone do not exceed 3/32 inch in any direction
e. the defects in the weld or fusion zone do not exceed 1/8 inch or one-half the
nominal wall thickness, whichever is smaller, in any direction.
39. Film or other imaging media shall be processed, handled, and stored so that the
images are interpretable for at least 3 years after they are produced: 11.1.11
a. is required by API 1104
b. generally accepted as the best thing to do
c. a very good thing to do
d. only when requested by the company
e. none of the above
40. A record of certified non destructive testing personnel shall be kept by the
company. Level I and Level II NDT personnel shall be recertified at least every:
8.4.2
a. Year
b. 2 years
c. 3 years
d. 4 years
e. 5 years
41. Automatic welding shall be done using which of the following processes?12.1
a. SAW
b. GMAW
c. GTAW
d. FCAW with or without external shielding
e. all of the above
42. When a radiographic source is centered inside the pipe for exposing a butt
weld:11.1.3.1
a. three exposures are adequate for the radiographic inspection of the completed
weld.
b. two exposures are adequate for the radiographic inspection of the completed
weld.
c. one exposure is adequate for the radiographic inspection of the completed weld
(SWE/SWV).
d. double film must be loaded in the film cassette
e. none of the above
43. Each automatic welding unit and each operator shall be qualified by producing an
acceptable weld using qualified welding procedure.12.6
a. True
b. False
c. automatic welding is not permitted in API 1104
d. b and c above
e. none of the above
Page | 8
44. A welder who successfully completes the qualification in Section 6.3.2 on 8 inch,
schedule 40 pipe (0.322" wall) must be re-qualified if: 6.3.2 a
a. the welding process is changed from SMAW to GMAW
b. the welder changes the welding direction from horizontal left to horizontal right
c. there is a change in filler metal classification from Group 1 or 2 to Group 3
d. the welder welds on 6 inch, schedule 40 (0.280" wall) pipe
e. a and c above
45. For automatic welding, which of the following statements are true?12.1, 12.3.
12.4.2.8
a. flux cored arc welding without external shielding may not be used in automatic
welding
b. qualified procedures for automatic welding need not be recorded
c. the welding position need not be specified as to roll or position welding for
automatic welding
d. all of the above are false
e. none of the above
46. Which of the following represent changes in essential variables for a manual
welding procedure? 5.4.2.2, , 5.4.2.4, 5.4.2.9, 5.4.2.10
a. a change in the pipe material group
b. a change of welding position
c. a change in the vertical direction of welding
d. a change in the shielding gas or a major change in shielding gas flow rate
e. all of the above
APX A
48. Use of this appendix for the evaluation of any or all imperfections,-
Page | 9
49. Rain flow method
a) Heat
b) Stress intensity
c) Environment at the crack tip
d) All
e) none
a) By Reducing Temperature
b) By Increasing Press as pressure may close the crack tip
c) By the use of CP
d) By Doing WFMPT
52. The tensile strength specimen used to qualify the welding procedure------
a) Shall be confirmed by RT
Page | 10
53.Nominal Qualified shielding gas flow rate was 10 cc/Sec. So the acceptable value is
a) 9 cc/sec
b) 11 cc/sec
d) a & b & c
e) it is at Company’s option
b) The Crack tip is placed so that it cross the area of maximum hardness
c) The Crack tip is placed so that it cross the area of minimum hardness
55. If the applied Axial strain =0.0020 and CTOD=0.010” what will be the allowable
surface imperfection size ------
a) 0.1 inch
b) 9mm
c) 0.2 inch
d) No sufficient information
56. In the above case what will be allowable buried imperfection size assuming it does
not exceed the half of wall thk
a) 0.2 inch
b) 18 mm
Page | 11
57. Arc burns that contain cracks visible to the eye or on conventional radiographs
are ----
c) Not acceptable
b) AWS –CWI
c) Owner
d) Company representative
Appendix – B
59. The two primary concerns with welding onto in-service pipelines
c) Burnthrough & HC
Page | 12
60. The conditions for the Hydrogen Cracking are the following except
b) Susceptible microstructure
d) By doing PWHT
Page | 13
64. Which of the following are to be positively identified in the procedure?
d) all
a) None
65. For macro section test specimen, at least one face should be ground to---------------
a) 500 Microns
b)700 grit
66. How much load must be applied when using Vickers indenter?
a) 1 kg
b) 10000 gram
c) 1 Lb
d) 200 gm
a) API 1104
b) ASME Sec V
c) ASTM E 92
d) ASNT – SNT-TC -1A -2011---------------
Page | 14
a) with in 24 hours
b) after 24 hours
d) At ambient temperature
c) With PT on root Pass and each pass until the final pass
a) PT & MT
b) MT & RT
c) MT & UT
d) PT & UT
71. Which of the following aspect that should a welder consider during in-service
welding
72. At the owner’s option , In lieu of making separate specimens for ----------- Test the
remaining portion of------------ test specimens may be prepared for and
submitted
Page | 15
73. In in-service welding procedure qualification test For pipe OD less than or equal
to 4.500in. ------------------welds required.
a) 1
b) 2
c) 3
d) 4
a) 2
b) Atleast 1
c) 1
d) alll
e) none
75. In a welder qualification test for testing longitudinal seam welds how many face
bend specimen is needed for wall thickness 0.7000in.
a) 1
b) 2
c) 4
d) Any of the above
e) None of the above
Page | 16
API 1104 - PRACTICE EXAMINATION
QB – ANSWERS
1 C 18 B 35 A
2 A 19 A 36 B
3 D- 20 D 37 C
4 B- 21 C 38 E
5 C- 22 E 39 A
6 A 23 E 40 C
7 C 24 D 41 E
8 B 25 E 42 C
9 C 26 D 43 A
10 D 27 E 44 E
11 B 28 D 45 D
12 E 29 A 46 E
13 E 30 C 47 C
14 C 31 A 48 D
15 C 32 E 49 A
16 A 33 B 50 D
17 A 34 D 51 C
52 D
Page | 17