R44 Earthworks
R44 Earthworks
QA SPECIFICATION R44
EARTHWORKS
NOTICE
This document is a Transport for NSW QA Specification. It has been developed for use with transport
infrastructure contracts let by Transport for NSW or by local councils in NSW. It is not suitable for
any other purpose and must not be used for any other purpose or in any other context.
Copyright in this document belongs to Transport for NSW.
REVISION REGISTER
ii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 4/Rev 0 4.4 Previously clause 4.3.
(cont’d) 4.5 Previously clause 4.4.
4.6 New clause titled “Pre-splitting or Line
Drilling”; previously part of clause 4.5.2.
4.7 Previously clause 4.5; previous sub-clauses
4.5.1 to 4.5.3 correspondingly renumbered.
4.7.1 Clarification added that cost of Building
Condition inspection to be responsibility of
contractor if no pay item provided in G36.
4.7.2 Previously clause 4.5.2.
Heading re-titled “Pre-splitting or Line
Drilling Prior to Blasting”.
5.1 Clause reorganised and reworded.
5.2 Previously clause 5.1.1.
Table title inserted for table of layer
thickness and material properties in earth fill
embankments.
5.2.1 Previously clause 5.1.1.1.
Fig 7 amended.
Material property requirements for fill at spill
through abutment changed.
Maximum layer thickness increased to 300
mm.
5.3 Previously clause 5.1.2; previous sub-clauses
5.1.2.1 to 5.1.2.5 correspondingly
renumbered.
5.3.2 Maximum dimension of rockfill material
reduced to 300 mm.
Table title inserted for table of rock fill
material properties.
5.3.3 Table title inserted for table of capping layer
material properties.
5.4 Previously clause 5.2.
Embankment batter tolerances now shown in
new Table 8.
5.5 Previously clause 5.3.
Restriction on placing rock facing higher
than 1.5m below Designed Finish Level
deleted.
Superfluous statement on provision of
drainage layer deleted.
iii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 4/Rev 0 5.6 Previously clause 5.4.
(cont’d)
Fill adjacent to structures explicitly referred
to as “Select Fill”.
7.4 Characteristic deflection formula moved to
this clause from Annexure.
Annex A Notes to Tender Documenter (within boxed
text) amended.
Annex A1 Table on survey requirements amended.
Annex A2 Previously Annex A4.
Topsoil requirements moved to this Annex
from previous Annex 3.
Material properties for earth fill at spill
through abutments amended.
Annex A3 Previously Annex A7; retitled “Foundation
Treatment”.
Thickness requirement added for Type E5
Foundation Treatment “Drainage Layer”.
Annex A4 Combining previous Annex A3 and A6, and
retitled.
Annex A6 Previously Annex A2.
Annex B Pay Item P2: clarification to parts (a), (c) and
(g); previous part (i) on placing and
compaction of verge material deleted.
Annex L Previous clause 8 transferred to this
Annexure.
Ed 4/Rev 1 Global “OEH” changed to “EPA”. GM, IC 15.04.13
1.4 Definition of “Designed Floor Level”
changed.
2.7.3 Names of government departments updated.
2.8.2 Maximum size of UZF other than SMZ
material fixed at 100 mm, regardless of
whether safety barriers, etc are to be
installed.
2.8.5 New clause on spilled through bridge
abutment fill material added.
3.2 Minor editing of Hold Point.
3.2.5, 3.4.5 Superfluous statement that drainage layer
material must not contain clay fines or silt
deleted.
3.2.5 Table 2 reworded.
3.3 Requirement for terraces to coincide with
natural discontinuities deleted.
iv
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
3.4.5 Statement on placing of geotextile around
drainage layer moved from item (d) to within
item (c).
3.5.2 Plan view for Fig 6(b) added.
5.2.1 Clause on spilled through bridge abutment
fill material requirements replaced by
reference to clause 2.8.5.
5.3.2 Rock fill material property requirements
moved to Table 6.
5.3.3 Apparent inconsistency for capping layer
material property requirements clarified.
Rock fill material property requirements
moved to Table 7.
5.5 Requirement for graded filter layer deleted.
Statement regarding wave action, etc deleted.
7.5.1 Table 12 on level tolerances reworded.
7.5.2 Clause reworded to clarify intent.
Annex A2.2 Item descriptions changed to improve clarity.
Column titled “Test Condition” deleted and
replaced by footnote.
Footnotes reworded and rearranged.
Annex A4 Reinstated item for deduction for level
nonconformity where overlying layer is not
part of Contract.
Annex A6 Statement on vp amended.
footnote (1)
Ed 5/Rev 0 Global Clauses rearranged and reworded to improve GM, CPS 18.09.14
clarity.
References to G35 and G39 deleted.
Term “compaction routine” replaced with
“compaction procedure”.
1.1 Heading title changed to “Scope”. Individual
clauses edited.
1.2 Heading title changed to “Earthworks
Process”.
1.4 Definitions of:
• “Bridging layer”, “Site won material”,
“Steel furnace slag” added;
• “Imported material”, “Spoil”, “Structural
Treatment”, “Unsuitable material”,
“Upper Zone of Formation”, “Working
Platform” amended;
• “Limit of Works” deleted.
v
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 1.5 Headings added to form new sub-clauses
(cont’d) 1.5.1 and 1.5.2. Earthworks Plan
requirements edited for clarity.
1.6.2 Previous clauses 1.6.2 and 1.6.3 on survey
reworded and combined together under
clause 1.6.2.
2.1, 2.2 Individual sub-clauses rearranged between
the two clauses.
Last paragraph of clause 2.2 (repeat of clause
1.5.1 item (d)) deleted.
2.3.2 Maximum height of topsoil stockpiles
reduced to 2 m.
2.4 Headings added to form new sub-clauses
2.4.1 to 2.4.5.
2.5.1 “Limit of Works” replaced by “Site”.
Period of notice to Principal before use of
spoil locations outside the Site changed from
“7 days” to “5 working days”.
2.5.2 Clarification on payment for contaminated
material added.
2.6 Clauses rearranged and rewritten to improve
clarity.
2.7.1, 2.7.2 Requirements applicable only to specified
borrow areas moved from clause 2.7.1
“General” to clause 2.7.2 “Nominated
Borrow Areas”.
2.7.3 POEO Act added as a statutory requirement
for compliance.
Lead time for submission of copies of
approvals and consents to Principal before
commencing work at contractor arranged
borrow areas changed from “10 days” to “5
working days”.
Statement added that material brought on to
site from contractor arranged borrow areas
must comply with conditions attached to
EPA resource recovery exemptions.
2.8 Heading title expanded to include spill
through abutment zone material.
2.8.1 Heading added to form new sub-clause 2.8.1.
Subsequent sub-clauses renumbered.
2.8.2 Previously sub-clause 2.8.1.
Clause reworded to delete option of
mandating Upper Zone Material etc, to be
imported.
vi
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 2.8.2 Statement added to prohibit use of steel
(cont’d) furnace slag aggregates in UZF, verges and
spill through bridge abutment zones.
2.8.3 New sub-clause titled “Sampling and
Testing”, combining existing requirements
on sampling and testing of material in
stockpiles with that from sub-clauses 6.1.2
and 6.2.
Subsequent sub-clauses renumbered.
2.8.5.1 Statement on modification of Selected
Material reworded to clarify the intent.
2.8.6 CBR values for conformity for verge material
in stockpiles changed to characteristic values.
3.2 Clarification note added on damage caused to
foundation by earthworks plant after
foundation treatment.
3.2 Individual clauses for each of the treatment
types rewritten to improve clarity.
Statement added that foundation treatment
required in medians if so specified in Annex
A6.
Applicable Pay Item for each type of
treatment added.
3.2.2 Figure 3(b) – dimension arrow changed to
between top of bridging layer and underside
of SMZ. Clause changed to suit.
Statement added that Principal may require
trial section for bridging layer.
Pay Item reference changed.
3.2.5 Minimum distance between top of Type E5
drainage layer and underside of SMZ added.
Dimension arrow and accompanying note for
the same added to Figure 3(e).
Use of steel furnace slag aggregates in
drainage layer prohibited.
Specified strength class and filtration class of
geotextile changed to “complying with R63”.
3.2.6 New Type E6 earth fill embankment
foundation treatment added.
“Other Treatments” now clause 3.2.7.
3.3 Heading title changed to indicate more
clearly scope of clause.
vii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 3.4 Clarification on level for excavation, whether
(cont’d) Designed Floor Level or Foundation Level.
Statement added that samples for CBR and
PI tests may be obtained from test pits prior
to reaching required excavation level.
3.4 Statement added that foundation treatment
required in medians if so specified in Annex
A6.
3.4.1 to 3.4.5 Individual clauses for each of the treatment
types rewritten to improve clarity.
Applicable Pay Item for each type of
treatment added.
3.4.1 Maximum depth of ripping in Type C1
treatment limited to 400 mm added.
Figure 5(a) – “Foundation Level” deleted
(not relevant).
3.4.2 Statement added to determine CBR and PI
values of material in cutting floor for Type
C2 treatment only where directed by the
Principal.
Requirement in Type C2 treatment to “loosen
and recompact” floor of cutting changed to
“compact with not less than 6 passes of
vibrating roller”.
3.4.5 Specified strength class and filtration class of
geotextile changed to “meeting the
requirements of R63”.
Use of steel furnace slag aggregates in
drainage layer prohibited.
3.5.2 Statement added that cut/fill transition
treatment required in medians if so specified
in Annex A6.
Figure 6(b) – extent of shallow embankment
corrected.
4.1 Individual clauses rearranged. Headings
added to form new sub-clauses 4.1.1 to 4.1.3,
incorporating the contents of previous clause
4.2.
Subsequent clauses renumbered.
4.3 Text in Table 3 reworded to improve clarity.
Footnote added that bench widths must not
be less than that shown on Drawings.
4.5 Headings added to form new sub-clauses
4.5.1 and 4.5.3.
viii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 4.5.1 Requirement that line drilling boreholes must
(cont’d) be straight, parallel and in designed plane of
batter added.
4.5.3 Clause moved here from previous clause
4.7.2.
Statement added that burden blasting must
not damage batter face.
4.6.1 Statement added that Hold Point in G36 for
submission of Vibration and Airblast
Management Sub-Plan and Building
Condition Inspection Reports applies.
Process held in Hold Point changed to “start
of each blast”. Submission details amended.
4.6.1 Notification of blasting extended to include
“any other relevant parties”.
Clarification of payment for Building
Condition Reports added.
4.6.3, 4.6.4 Clauses on control of airblast and ground
vibration previously located at back of
specification moved to follow immediately
clause 4.6.2.
4.6.3 Requirement to comply with criteria in
Australian and New Zealand Environment
and Conservation Council (ANZECC) to
minimise annoyance due to blasting deleted
(duplicate clause in G36).
Statement that verification of compliance
with ANZECC criteria to be in accordance
with AS 2187.2 Appendix J, moved to G36.
“recognised testing facility” changed to
“NATA accredited testing facility or
manufacturer’s facility approved by the
Principal”.
4.6.3, 4.6.4 Monitoring to be carried out by NATA
accredited personnel deleted, as NATA does
not accredit personnel.
4.6.6 Simplified version of equation added as
alternative.
5.1 Individual clauses rearranged. Headings
added to form new sub-clauses 5.1.1 to 5.1.3.
5.2 Individual clauses rearranged. Headings
added to form new sub-clauses 5.2.1 and
5.2.2. Previous clause 5.2.1 becomes 5.2.3.
5.2.3 Figure 7: dimension of bench width and
notes to figure added.
ix
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
5.3 Individual clauses rearranged; headings
added to form new sub-clauses or replace
existing sub-clauses.
Ed 5/Rev 0 5.3 Previous sub-clause 5.3.4 on minimum
(cont’d) thickness of Select Fill within rock fill
embankments moved to B30 and R11.
5.3.2 Requirement added for geotextile to be
placed over foundation area prior to placing
rock fill where shown on Drawings or
directed by the Principal.
5.3.2 Requirement to hand place rock around
columns or retaining wall moved here from
sub-clause 5.2.3 (previously sub-clause
5.2.1).
5.3.4 Heading title changed.
Thickness requirement for rock capping layer
moved to Annex A4.
Table 7 – Percentage passing 19.0 mm sieve
limits increased to “0 – 15%”.
Requirement for geotextile as separation
between rock capping layer and overlying
earth fill added.
Minimum distance between top of capping
layer and bottom of SMZ decreased to
400 mm and 800 mm.
5.3.5 Previous sub-clause deleted, and
requirements moved to sub-clauses 5.3.2 and
5.3.4 and B30.
5.4 Heading title changed. Text in Table 8
reworded to improve clarity.
5.5 Individual clauses rearranged. Headings
added to form new sub-clauses 5.5.1 to 5.5.4.
5.5.3 Requirement for geotextile as separation
between earth fill and rock facing added.
5.6 Heading title changed.
Select Fill against structures to be in
accordance with the Drawings in the first
instance, otherwise to be in accordance with
B30, R11 and R58/R59 as appropriate.
“Bridge structures” replaced by “retaining
walls and bridge abutments”.
Previous clause 5.6.2 for treatment at
weepholes moved to B30 and R11.
6.1.1 Statement added that UZF layer required in
medians if so specified in Annex A6.
x
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 6.1.2 Requirement for Selected Material to be
(cont’d) stockpiled and tested moved to clause 2.8.3.
Previous Table 10 on sampling frequency for
stockpiled Selected Material moved to Annex
L.
7.2, 7.3, 7.4 Heading titles changed to more accurately
reflect the content.
7.3 New clause titled “Sampling and Testing for
Compaction Conformity”, incorporating parts
of previous sub-clauses 7.2.1 and 7.2.2.
Headings added to form sub-clauses 7.3.1 to
7.3.7.
7.3.3 Clause on applicable test methods for field
density rewritten to clarify requirements.
7.4 New clause titled “Earth Fill Compaction
Conformity Criteria” incorporating parts of
previous sub-clauses 7.2.1 and 7.2.3.
Table 10 location details amended to clarify
requirements.
7.5 Previously clause 7.3; title changed to “Rock
Fill Placing Conformity”.
7.6 Previously clause 7.4 “Deflection Testing”.
7.6.1 Clarified that proof rolling to be carried out
only when directed.
7.6.2 Deflection testing by Benkelman Beam may
be delayed due to adverse weather condition
added.
7.7 Previously clause 7.5 “Level Control”.
7.7.1 Level tolerances in Table 11 changed.
7.7.2 Clarified volume to which deduction for out
of tolerance is applied.
Annex A Notes to guide Tender Documenter
differentiated from notes to clarify details in
table.
Annex A1 Table edited. Survey of surface after placing
of imported material added to table.
Annex A2.1 Table edited.
Annex A2.2 Table column heading titles changed.
CBR requirement for Selected Material and
verge material increased to allow for change
from minimum value to characteristic value.
PI lower limit of 6 added for spill through
bridge abutment fill material at waterway
crossings.
xi
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 Annex A2.2 Note (4) to table amended to clarify
(cont’d) application rate requirement for binder.
Annex A3 Minimum distance from top of bridging layer
to underside of SMZ increased to 900 mm.
Tolerances added to thickness of bridging
layer.
Minimum distance from top of drainage layer
to underside of SMZ added.
Minimum distance and thicknesses
associated with Treatment Type E6 added.
Annex A4 Thickness of rock capping layer added.
Annex A6 New annexure for specifying whether
foundation treatments/structural treatments
required in medians
Previous Annex 6 on blasting now becomes
Annex 7.
Annex B Statement added that rates must include cost
of testing, where not paid under Primary
Testing.
Pay item descriptions changed to improve
clarity.
Pay item P1.1 – clarification added that
payment for placing of topsoil for
revegetation purposes is made under R178.
Pay item P1.2 – note added that if bank
volume cannot be measured, the Principal
will determine conversion factor for loose
volumes.
Pay item P2 “General Earthworks (Cut/Fill)”
- method of determining excavation volume
reworded to improve clarity;
- scope clarified.
Pay item P3 – inclusions and exclusions in
rate amended.
Pay item P5 – “Limit of Works area”
changed to “Site”.
Pay item P6 – notes added that if bank
volume cannot be measured, the Principal
will determine conversion factor for loose
volumes, and rate must include cost of
classification of waste material.
Pay item P7 – individual sub-pay item
descriptions changed to improve clarity.
xii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Ed 5/Rev 0 Annex B Previous pay item P7.1 (for both Types E1
(cont’d) and C1) separated into pay items P7.1 (for
Type E1) and P7.2 (for Type C1).
Previous pay item P7.2 (for Type E2) now
becomes pay item P7.3. Unit of
measurement for pay item P7.3(b) for
imported material changed from “tonnes” to
“cubic metres”. Rate to allow for extra
material required due to penetration into
underlying surface. Clarification added that
geotextile is paid under P7.5(a).
New pay item P7.4 (for Type C2) added.
Unit of measurement for pay item P7.4(b) for
imported material changed from “tonnes” to
“cubic metres”.
Previous pay item P7.4 (for both Types E5
and C5) separated into pay items P7.6 (for
Type E5) and P7.7 (for Type C5). Unit of
measurement for pay item P7.3(b) for
imported material changed from “tonnes” to
“cubic metres”. Rate to allow for extra
material required due to penetration into
underlying surface. Clarification added that
geotextile is paid under P7.5(a).
New pay item P7.8 for Type E6 added.
Annex C1 Descriptions in Schedule of Hold Points
amended.
Annex C3 Schedule of Identified Records items
amended.
Annex L Title expanded to include “work activities”.
Individual items within table rearranged to
more closely reflect work sequence.
Table L.2 moved here from previous clause
6.1.2.
Annex M Referenced documents updated.
Ed 5/Rev 1 Global References to “Roads and Maritime DCS 22.06.20
Services” or “RMS” changed to “Transport
for NSW” or “TfNSW” respectively.
Ed 6/Rev 0 Global Clauses rearranged and reworded to improve A/CEI 28.06.23
clarity. Some clause rearrangement and DK
rewording without changing the intent or
meaning are not recorded in this register.
1.2, 1.3, 1.4 Previous clauses 1.2, 1.3 and 1.4 rearranged
to be in same order as other specs. Clauses
and Figures re-numbered accordingly.
1.3 Definitions reworded.
xiii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
1.5.1 (n) Procedures to protect buried structures, utility
services infrastructure and culverts from
construction traffic added to Earthworks Plan
requirements.
1.6 Sub-clauses 1.6.1 and 1.6.2 order rearranged.
1.6.2 Clause amended to require marking on
ground the location and extent of cuttings,
embankments and drainage layers.
1.8 New clause on protection of environment,
incorporating requirement relocated from
Clause 1.7.
2 Individual clauses under this clause
rearranged in different order.
2.1 Clause title changed. Previous first two
paragraphs, which are superfluous, deleted.
2.4 Headings added to form new sub-clauses
2.4.1 to 2.4.3.
2.4.2 Requirement to carry out pre-construction
land condition assessment of stockpile areas
added.
2.6.4 Statements on payment for removal of
unsuitable material, and replacement with
conforming material, added.
2.8.1 Drainage layers added to areas where use of
steel furnace slag aggregates is prohibited.
2.8.3 Clause title changed.
2.8.5.1 Site won Selected Material requirements
updated to harmonise with revised spec 3071.
Reference to Note (5) in Annex A2.2 added.
2.8.7 References to Type ST2 material deleted;
Type ST1 material becomes simply Type ST
material.
2.9 New clause on other earthworks materials,
cross referencing requirements in other
clauses.
3 Clauses rearranged, with clauses relating to
“cutting” shown before clauses relating to
“embankment”. Clauses and Figures
re-numbered accordingly.
3.2 Exception to requirement to carry out CBR
and PI tests for foundations of cuttings added
for Treatment Type C5.
3.2.3 Treatment Type C3 “working platform”
separated into Types C3(I) and C3(II),
comprising insitu stabilised and plant mixed
stabilised respectively.
xiv
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
3.2.4 Geogrid conformity requirements to R67
clarified.
3.3.2 Reminder added that capping layer on top of
Treatment Type E2 “rock fill bridging layer”
required if bridging layer is overlain by earth
fill.
3.3.3 Treatment Type E3 “working platform”
separated into Types E3(I) and E3(II),
comprising insitu stabilised and plant mixed
stabilised respectively.
3.3.4 Geogrid conformity requirements to R67
clarified.
3.3.6 Maximum rock particle size clarified.
Pay Item reference added for Treatment Type
E6, consistent with the wording for other
Treatment Types.
3.4 Fig. 5 – required depth of terrace changed to
a range.
4.1.2 Previous statement under this clause number
moved to sub-clause 2.8.2. Clause title
changed.
Previous 1st paragraph of sub-clause 4.1.3
moved here and reworded. Remaining
clauses moved elsewhere.
4.2 Clause title changed.
Clause edited to remove superfluous
wording.
Requirement to clean bench surface at top of
batter deleted, as meaning is unclear.
4.3 Clause title changed.
Previous first two paragraphs and table on
cutting batter tolerances moved to under
Clause 7.8.
4.4 Headings added to form new sub-clauses
4.4.1 to 4.4.3.
4.5.2 Note added to Table R44.3.
4.6 Headings added to form new sub-clauses
4.6.2 and 4.6.3. Subsequent sub-clauses
re-numbered.
4.6.1 New title for vibration and airblast sub-plan
added.
4.6.4 Video recording of blasting event required as
part of blasting records.
4.6.5, 4.6.6 Wording harmonised between the two sub-
clauses.
xv
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
5.1 Heading added to form new sub-clause 5.1.4.
5.1.2 Heading title changed.
5.1.3 Reminder to carry out survey before and after
placing imported fill material added.
5.2.1 Previous 2nd paragraph incorporated within
definition of earth fill material under Clause
1.3.
Previous Table 5 on maximum layer
thickness and grading of earth fill, replaced
by descriptive requirements.
5.2.2 Statement added that Principal may
authorised increase in layer thickness to
500 mm.
Clauses relevant to earth fill placing moved
here from previous Clauses 5.2.1, 7.1 and
5.1.3.
5.2.3 Clause title changed.
Fig.7 – detail of zone immediately adjacent
to bridge abutment amended.
Requirement to stockpile Type ST and test
for conformity before use, deleted as this is
inconsistent with Clause 2.8.3.
5.4 Previous Clause 5.4 on embankment batter
tolerances moved to under Clause 7.8.
Subsequent clauses re-numbered accordingly.
7.1 Previous Clause 7.1 moved to Clause 5.2.2.
Subsequent clauses re-numbered accordingly.
Headings added to form new sub-clauses
7.1.1 and 7.1.3. Previous sub-clause 7.3.5
moved here to become sub-clause 7.1.2.
7.2.1 Previously sub-clause 7.3.2, with clause title
changed.
7.2.2 Previously sub-clause 7.3.3, incorporating
parts of previous sub-clauses 7.3.1, 7.3.3 and
7.3.4, with clause title changed.
Requirement to select sample locations in
accordance with spec Q added.
7.2.3 Previously sub-clause 7.3.6 on relative
compaction determination.
7.2.4 Previously Clause 7.4 on compaction
conformity.
7.3 Previously sub-clause 7.3.7 on repair of test
holes.
xvi
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
7.4 Previously Clause 7.5 on rock fill placing.
Headings added to form new sub-clauses
7.4.1 to 7.4.3.
Witness Point and Hold Point – requirements
clarified.
7.5, 7.6 Previous clause on deflection testing now
split into Clause 7.5 (on proof rolling) and
Clause 7.6 (on Benkelman Beam testing).
7.5 Clause title changed. Headings added to
form new sub-clauses 7.5.2 and 7.5.3.
7.5.1, 7.5.2 Proof rolling requirements clarified.
7.6 Headings added to form new sub-clauses
7.6.1 to 7.6.5.
7.6.1 Requirement to conform to grid sampling
pattern in T199, and other requirements,
added.
Permissible time delay in carrying out
Benkelman Beam testing clarified.
7.6.3 Minimum width of Lot changed from “a
single carriageway” to “a single lane”.
7.6.4 Equation for calculating characteristic
deflection deleted, as equation is given in
referenced T199.
7.6.5 Conformity requirements changed.
7.7 Clause title changed.
7.8.1 New sub-clause on cutting batter dimension
tolerances, incorporating parts of previous
(sub-)clauses 4.1.3, 4.3 and 5.4.
7.8.2 Previously Clause 5.4.
7.9.1 Part of previous (sub-)clauses 4.3 and 4.1.3,
and Clause 5.4 moved here and modified.
7.9.2 Parts of previous Clause 5.4 moved here and
modified.
7.9.3 Previously sub-clause 7.7.3, on batter surface
tolerances in medians, now made applicable
to all batter surfaces.
Annex A1 New item on survey of surface of existing
ground where topsoil not required to be
removed, added.
Previous separate items on survey before,
and after, removal of unsuitable material
combined into one item.
Previous separate items on survey before,
and after, placing imported material
combined into one item.
xvii
Ed/Rev Clause Authorised
Description of Revision Date
Number Number By
Annex A2.1 New item for spill through bridge abutment
zone added.
Annex A2.2 Type ST2 material deleted; Type ST1
material becomes Type ST material.
Table notes order rearranged.
Notes 1, 2 and 5 requirements clarified.
Annex A3 Items added for specifying Treatment Types
C3(II) and E3(II).
Annex A4 Item added for specifying Benkelman Beam
deflection testing at top of verge.
Note 1 added to table.
Annex A5 Guidance notes within boxed text added.
Annex A7 Terminology made consistent with main text.
Annex B Pay Item P1.2 – pay item clarified to apply
only to non-contaminated topsoil; EPA waste
classification added to part of rate.
Pay Item P2 – individual clauses rearranged,
and reworded; development and verification
of compaction procedure for rock fill added
as a cost item.
Pay Item R44P3 – replacement of unsuitable
material deleted, as it is not relevant.
Pay Item R44P7.4 – rate to allow for capping
layer over rock fill bridging layer added.
Annex C1 & Schedule of Hold Points and Witness Points
C2 updated.
Annex C3 Schedule of Identified Records updated.
Annex D Planning Documents added.
Annex L Table L.1 – some items in table rearranged
and reworded.
Testing frequency for rock fill and rock
capping material changed.
Annex M Referenced documents updated.
xviii
QA S PECIFICATION R44
EARTHWORKS
Copyright – Transport for NSW
TS 02158.1
IC-QA-R44
VERSION FOR:
DATE:
CONTENTS
CLAUSE PAGE
FOREWORD ............................................................................................................................................. III
TfNSW Copyright and Use of this Document ............................................................................. iii
Revisions to Previous Version ..................................................................................................... iii
Project Specific Changes ............................................................................................................. iii
1 GENERAL ........................................................................................................................................ 1
1.1 Scope .............................................................................................................................. 1
1.2 Structure of Specification ............................................................................................... 1
1.3 Definitions ...................................................................................................................... 2
1.4 Earthworks Process ........................................................................................................ 6
1.5 Earthworks Plan.............................................................................................................. 8
1.6 Surveying........................................................................................................................ 9
1.7 Protection of Earthworks .............................................................................................. 10
1.8 Protection of Environment ........................................................................................... 10
2 MATERIALS .................................................................................................................................. 10
2.1 Contractor’s Responsibility .......................................................................................... 10
2.2 Materials Management ................................................................................................. 11
2.3 Borrow Areas................................................................................................................ 11
2.4 Stockpile Areas............................................................................................................. 12
2.5 Topsoil .......................................................................................................................... 12
2.6 Unsuitable Material ...................................................................................................... 13
2.7 Spoil.............................................................................................................................. 15
2.8 Upper Zone, Verge and Spill Through Bridge Abutment Fill Material ....................... 15
2.9 Other Earthworks Materials.......................................................................................... 18
3 FOUNDATIONS .............................................................................................................................. 18
3.1 General ......................................................................................................................... 18
3.2 Foundation Treatments Within Cuttings ...................................................................... 19
3.3 Foundation Treatments Under Embankments .............................................................. 24
3.4 Foundation Treatment for Hillside Embankments – Terracing .................................... 30
3.5 Shallow Embankment and Cut/Fill Transition Zone .................................................... 31
4 CUTTINGS ..................................................................................................................................... 33
4.1 General ......................................................................................................................... 33
4.2 Cleaning of Cutting Batters and Inspection .................................................................. 33
4.3 Over-excavation and Actions Required ........................................................................ 34
4.4 Benching in Cuttings .................................................................................................... 34
4.5 Line Drilling or Pre-splitting ........................................................................................ 35
4.6 Blasting ......................................................................................................................... 36
5 EMBANKMENTS ............................................................................................................................ 39
5.1 General ......................................................................................................................... 39
5.2 Earth Fill Embankments ............................................................................................... 40
5.3 Rock Fill Embankments ............................................................................................... 41
5.4 Rock Facing to Embankments ...................................................................................... 43
5.5 Select Fill Adjacent to Structures ................................................................................. 44
Ed 6 / Rev 0 i
R44 Earthworks
ANNEXURE R44/C – SCHEDULES OF HOLD POINTS, WITNESS POINTS AND IDENTIFIED RECORDS...... 73
C1 Schedule of Hold Points .............................................................................................. 73
C2 Schedule of Witness Points.......................................................................................... 73
C3 Schedule of Identified Records .................................................................................... 74
ANNEXURE R44/L – WORK ACTIVITIES, TEST METHODS, MINIMUM FREQUENCY OF TESTING AND
ACCEPTANCE CRITERIA............................................................................................................... 75
ii Ed 6 / Rev 0
Earthworks R44
FOREWORD
This document should be read with all the documents forming the Contract.
This copy is not a controlled document. Observe the Notice that appears on the first page of the copy
controlled by TfNSW. A full copy of the latest version of the document is available on the Transport
Standards Portal https://standards.transport.nsw.gov.au/.
All revisions to the previous version (other than minor editorial and project specific changes) are
indicated by a vertical line in the margin as shown here, except when it is a new edition and the text
has been extensively rewritten.
(a) Text which is additional to the base document and which is included in the Specification is
shown in bold italics e.g. Additional Text.
(b) Text which has been deleted from the base document and which is not included in the
Specification is shown struck out e.g. Deleted Text.
Ed 6 / Rev 0 iii
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
EARTHWORKS
1 GENERAL
1.1 SCOPE
This specification sets out the requirements for earthworks for roadworks, which aims to create a
stable formation suitable for a pavement to be constructed upon, using materials from within the Site
or, if suitable materials are not available from within the Site, using suitable materials from outside the
Site.
The earthwork formation is constructed by the controlled excavation, selection and placement of the
materials, and the use of Foundation Treatments and Structural Treatments, to achieve the best
possible support for the road pavement.
Earthworks is carried out in conjunction with other works such as surface and subsurface drainage and
environmental control measures.
The schedules in Annexure R44/C list the HOLD POINTS and WITNESS POINTS that must be
observed. Refer to Specification TfNSW Q for the definitions of HOLD POINTS and WITNESS
POINTS.
The records listed in Annexure R44/C are Identified Records for the purposes of TfNSW Q
Annexure Q/E.
The PROJECT QUALITY PLAN must include each of the documents and requirements listed in
Annexure R44/D and must be implemented.
Ed 6 / Rev 0 1
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The Inspection and Test Plan must nominate the proposed testing frequency to verify conformity of
the item, which must not be less than the frequency specified in Annexure R44/L. Where a minimum
frequency is not specified, nominate an appropriate frequency. Frequency of testing must also
conform to the requirements of TfNSW Q.
Unless otherwise specified, the applicable issue of a referenced document, other than an TfNSW
Specification, is the issue current at the date one week before the closing date for tenders, or where no
issue is current at that date, the most recent issue.
Standards, specifications and test methods are referred to in abbreviated form (e.g. AS 1234). For
convenience, the full titles are given in Annexure R44/M.
1.3 DEFINITIONS
The terms “you” and “your” mean “the Contractor” and “the Contractor’s” respectively.
Borrow area An area (either within or outside the Site), other than cuttings and specified
excavations, from which material may be excavated for use in the Works.
Bridging layer A layer located at the foundation of an embankment constructed from granular earth
fill material or rock fill material with strong mechanical interlock. The purpose of
the bridging layer is to provide a stable platform upon which a conforming
earthworks layer can be constructed.
Capping layer A layer of graded rock material, placed over rock fill (including rock fill in bridging
layers) as a transition layer between rock fill layers and the overlying earth fill
layers in an embankment.
Cutting An earth or rock excavation within the Site that is made below an existing surface to
create the road formation.
Cut/Fill An area of special formation treatment where the road formation transitions from a
Transition cutting to an embankment, as shown in Figure R44.6(b), and described in
Zone Clause 3.5.2.
Designed Floor The level of excavation in a cutting at the underside of the Selected Material Zone.
Level
Drainage layer A layer located at the foundation of a cutting or an embankment, constructed of free
draining material with grading as specified in Clauses 3.2.5 and 3.3.5. The purpose
of the drainage layer is to provide a pathway for the free drainage of excess water
away from the foundations of cuttings or embankments. The drainage layer is
usually wrapped in geotextile to prevent its contamination or blockage over time
from adjacent fine grained material.
2 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Earth fill Material composed of fine and coarse particles, which when placed and compacted
produces a dense embankment deriving its stability from the packing of the fine
particles around the coarser material.
Embankment An earth fill or rock fill structure above an existing and/or excavated surface to
create the formation.
Floor of cutting The trimmed base of the cutting excavation, at either the level of the Designed Floor
Level or the Foundation Level, depending on the type of Foundation Treatment.
Formation The earthworks structure including all Foundation and Structural Treatments on
which the road pavement will be constructed.
Foundation The level from which the formation is constructed. This is the level achieved after
Level excavation is undertaken for Foundation Treatments.
Foundation A special layer or treatment zone at the base of a formation for the purpose of
Treatment reinforcing, strengthening or draining the foundation.
General fill Material placed as fill in embankments for other than Foundation or Structural
Treatments.
Imported Material obtained from sources other than that generated by excavation in cuttings
material and other specified excavations within the Site.
Joint survey A survey carried out in the presence of, or in conjunction with, the Principal’s
surveyor. Refer also to Specification TfNSW G71.
Rock fill Material composed of hard, sound, durable rock with only a small amount of fine
particles which, when placed and compacted produces an embankment deriving its
stability from the mechanical interlock of the coarser particles, rather than from the
packing of the fine particles around the coarser material.
Roller pass Compactive effort of a single movement (or pass) of the roller over all areas of the
Lot nominated in the PROJECT QUALITY PLAN.
Select Fill Fill material of specified quality placed against or adjacent to structures (refer to
Clause 5.5). This material is different from Selected Material (see below).
Selected Material placed in the Selected Material Zone of the quality specified in
Material Clause 2.8.5 and Annexure R44/A2.2.
Selected The top part of the Upper Zone of Formation consisting of Selected Material, as
Material Zone shown in Figures R44.1(a) and R44.1(b).
Shallow A part of an embankment where the height from the Stripped Surface Level to the
Embankment Top of Formation is less than the height specified in Annexure R44/A4.
Site won Material that is obtained from excavations within the Site.
material
Spoil Material from excavations under the Contract which is surplus to that required to
complete the Works, and/or material from excavations under the Contract whose
quality renders it unacceptable for incorporation in the Works. Spoil includes
contaminated material which needs to be disposed of outside the Site.
Ed 6 / Rev 0 3
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Steel furnace Material that is a waste by-product from the production of steel using the Basic
slag Oxygen Steel (BOS) or Electric Arc Furnace (EAF) processes. Steel furnace slag
does not include any bag house dust or air pollution control residues.
Structural A special layer or zone within the upper part of the formation for the purpose of
Treatment strengthening the upper part of the formation.
Upper Zone of The top part of the formation composed of materials of a specified higher quality, as
Formation shown in Figures R44.1(a) and R44.1(b). In cuttings, the Upper Zone of Formation
comprises only the Selected Material Zone. In embankments, the Upper Zone of
Formation comprises two components, with the top component as the Selected
Material Zone. The thickness and quality of the materials for the Upper Zone of
Formation are specified in Annexure R44/A4 and R44/A2.2 respectively.
Upper Zone Material of specified quality used in the Upper Zone of Formation.
material
Verge material Material placed in the zone adjacent to the edge of the pavement which is subjected
to occasional traffic from vehicles leaving the pavement, of the quality specified in
Annexure R44/A2.2.
4 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 5
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Reference Description
Clause 1 General
Prepare and submit for consideration an EARTHWORKS PLAN and PROJECT
QUALITY PLAN. Set out the earthworks by survey, and carry out surveys for process
control and determining quantities. Protect earthworks by providing effective drainage.
Protect the environment by installing and maintaining erosion and sedimentation control
measures.
Clause 2 Materials
Manage the use of materials from within the Site and stockpile areas; remove topsoil and
place in stockpiles; remove, replace or treat any unsuitable material; dispose of spoil;
and borrow and import materials as required.
Clause 3 Foundations
Prepare and treat the floors of cuttings, embankments and cut/fill transitions, including
the use of bridging layers, working platforms, geotextiles/geogrids and drainage layers as
Foundation Treatments.
Clause 4 Cuttings
Excavate cuttings to the specified dimensions and batter surface tolerances, including
providing benches and drainage. Use blasting of rock where required and permitted.
Clause 5 Embankments
Place and compact suitable earth fill or rock fill material to the specified dimensions and
batter surface tolerances, including use of geotextiles/geogrids, rock capping and rock
facing, and Select Fill against structures.
Clause 6 Structural Treatments
Place and compact material of the specified quality for the Upper Zone of Formation
(including Selected Material Zone) and verges, or provide other geotechnical treatments
as required.
Clause 7 Additional Conformity Requirements
Complete the earthworks to the specified quality and tolerances. Undertake all
inspection and testing necessary to demonstrate that the quality requirements of this
Specification are achieved.
6 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Cut
or
DFL: Designed Floor Level
Fill
FdnL: Foundation Level
Cutting Embankment
Embankment
Cut/Fill Transition
Construction
Clause 3.5.2
Clause 5
Structural
Treatments
Clause 6
Conformity
Requirements
Clause 7
Pavement
construction
Note (b)
Ed 6 / Rev 0 7
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The EARTHWORKS PLAN must address all requirements and constraints imposed by the
specifications, the physical conditions at the Site and your proposed methods of working. The
EARTHWORKS PLAN must include details of the following:
(a) All excavations required for the Works, including: cuttings, foundation treatments, Shallow
Embankments, cut/fill transitions, terracing and trenches (such as that for drainage pipes or
utility conduits).
(b) The types, locations and quantities of all materials required for the Works or to be disposed of
as spoil, including: foundation treatment materials, earth fill, rock fill and spill through bridge
abutment fill material, rock for capping layers and rock facing, Upper Zone material (including
Selected Material and that at Shallow Embankments and cut/fill transitions), verge material,
Select Fill, topsoil, unsuitable material, non-contaminated spoil, contaminated spoil and
imported materials.
(c) The locations and quantities of all materials to be sourced from within the Site, and the staging
and excavation sequence that ensures that each of the material types listed in item (b) above is
available when needed. Locations and quantities must be cross-referenced to the excavations
listed under item (a) above.
(d) A mass haul diagram and/or table detailing the types and quantities of each type of material to
be excavated from each cutting or borrow area, and the locations within the Site for placement
of the materials.
(e) Preliminary assessment of stockpiling requirements and the quantities that can be placed in the
nominated stockpile areas, and any additional potential stockpile areas required (refer to
Clause 2.4).
(f) Preliminary identification of zones of potentially unsuitable material, and their management for
re-incorporation and/or disposal (refer to Clause 2.6).
(g) Details of the processes for winning, sorting, isolating, processing, blending and placement of
the materials listed under item (b) above, to meet the requirements of this specification,
including maximum particle dimension, grading, durability and other soil properties.
(h) Procedures for procuring and managing materials from borrow areas, or as imported materials
where applicable (refer to Clauses 2.3 and 2.8).
(i) Where applicable, procedures for the control and incorporation of potentially deleterious
materials such as acid sulfate rock and high swelling clays in zoned embankments.
(j) Procedures for the treatment of foundations in cuttings and under embankments (refer to
Clause 3).
(k) Procedures to ensure that the specified moisture content and compaction have been achieved
over the full depth of each layer and that the specified layer thickness is not exceeded (refer to
Clauses 5, 6 and 7).
(l) Procedures for protection of earthworks and dealing with over-wet materials and over-dry
materials (refer to Clause 1.7).
8 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
(m) Procedures to prevent damage to structures from hammering or ripping during rock excavation,
from compaction using vibrating plant, or from blasting.
(n) Procedures to protect buried structures, culverts and utility services infrastructure during
earthworks placing and from construction traffic as required by Specifications TfNSW R11 and
TfNSW G7.
Notwithstanding the staged submission provisions of TfNSW Q, provide the EARTHWORKS PLAN
in its entirety with the first stage submission of the PROJECT QUALITY PLAN.
1.6 SURVEYING
1.6.1 Surveys – General
Carry out all surveys shown as required in Annexure R44/A1 in accordance with Specification
TfNSW G71. Where so specified in Annexure R44/A1 or directed by the Principal, carry out the
survey as a joint survey.
Obtain the surface levels at sufficient positions when carrying out surveys for the purpose of
calculation of earthworks quantities for payment, or for process control or conformity verification.
Where a “Model File” is shown as required in Annexure R44/A1, include with the Survey Report an
electronic file of the survey data which is in a format suitable for creating accurate models using
standard TfNSW CADD software.
Set out the earthworks prior to commencement of construction by marking on the ground, using pegs
and signs, the location and extent of all cuttings and embankments including cut/fill transitions and
drainage layers as detailed on the Drawings. Install batter profiles, or provide alternative means, to
indicate the slope of embankments or cuttings.
When setting out, take into account any formation widening necessary to accommodate the design
requirements.
Ed 6 / Rev 0 9
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Where this specification refers to dimensions or setting out relevant to the underside of the Selected
Material Zone, and the Drawings do not provide for a Selected Material Zone, adopt the dimensions
for setting out relevant to the underside of the pavement.
(a) Provide and maintain measures for drainage of the working areas without scouring from the
surface run-off. Do not allow water to pond in the working areas resulting in wetting up of the
existing pavement or formation or foundation material, except where ponding is off the
formation and forms part of a planned erosion and sedimentation control system.
(b) When rain is likely, or when no work is planned for the following day in a particular area being
worked, take precautions to minimise any ingress of water into the earthworks material. Seal
off ripped material remaining in cuttings, and material placed on embankments, using a smooth
drum roller.
(c) Should earthworks material become over-wet (i.e. above the specified moisture content for
compaction), replace and/or dry out the material at your own cost (refer also to Clauses 2.6.5
and 7.1.3).
(d) Do not allow earthworks material in embankments to dry out to the point where excessive
shrinkage occurs, and the surface is pulverised by traffic generating excessive dust.
2 MATERIALS
(a) any of the assumptions you made in relation to the nature and types of the materials as
encountered in excavations or imported, and the bulking and compaction characteristics of all
such materials which are incorporated in the Works;
(b) determining suitable sources of material and any processing needed to satisfy the quality
requirements;
(c) the design, and the cost of construction and/or maintenance of all tracks, roads, haul roads, pads
and other earthworks structures required for the proper execution of the Works.
10 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Unless otherwise specified, do not import material for use in the Works until all material meeting the
specified requirements which are available from cuttings within the Site has been placed, or has been
allocated to be placed, in the formation.
If you cause a deficiency of material suitable for use in embankment construction or materials meeting
other specified requirements, by electing not to use acceptable material from excavations in the
embankments or by constructing embankments with dimensions other than those shown on the
Drawings or authorised in accordance with Clause 5.4, make good that deficiency at your own cost
using material meeting the specified requirements.
Include details of the method of selection and quality control of materials obtained from borrow areas
in the EARTHWORKS PLAN (refer to item (h) in Clause 1.5.1).
For borrow areas shown on the Drawings or nominated in Annexure R44/A2.1, carry out site
preparation in accordance with Clause 2.5.1 of this specification and TfNSW G40.
The top of the batter from the resulting excavation of the borrow areas must not be closer than 3 m to
any existing or proposed fence line, road reserve boundary or edge of excavation or embankment. The
slope of cutting batters at such borrow areas must conform to that specified in Annexure R44/A2.1.
At Completion, leave the borrow areas in a tidy and safe condition and meeting the requirements of
TfNSW G36. Unless otherwise approved by the Principal, carry out restoration of borrow areas in
accordance with TfNSW R178.
For borrow areas arranged by you, obtain any permits required for entry on to the land and for
payment of any royalty for such borrow material.
Comply with all statutory requirements including the Environmental Planning and Assessment Act
1979 (NSW) and Protection of the Environment Operations Act 1997 (NSW), and any requirements of
local Councils, landowners and other relevant stakeholders.
Provide copies of all approvals and consents to the Principal at least five working days prior to
commencing work at these borrow areas.
Any material which you bring from borrow areas to the Site must comply with the conditions attached
to the EPA resource recovery exemptions, as applicable.
You are responsible for all costs involved in opening up, maintaining and restoring any borrow areas
which are arranged by you.
Ed 6 / Rev 0 11
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Locate your stockpiles at the areas nominated on the Drawings or specifications. Where no such areas
are nominated, or if you propose to locate your stockpiles in areas other than those nominated, submit
your proposal with details of the maximum dimensions of the proposed stockpiles, for concurrence by
the Principal at least 10 working days before stockpiling is due to commence.
Obtain all the necessary approvals and consents, including environmental approvals, and provide
copies of them to the Principal.
The Principal will consider requests for new stockpiles areas only if all stockpile areas nominated on
the Drawings or Specifications have already been allocated for full use.
2.4.2 Setting Up
Prior to using the areas, carry out a pre-construction land condition assessment of the area as specified
in TfNSW G36.
Set up the stockpiles in a manner that minimises any damage to natural vegetation and trees, maintains
the existing surface drainage and allows access to the stockpiles for carting away at any time.
Carry out any clearing and grubbing for the stockpile areas in accordance with Specification
TfNSW G40. Comply with the requirements in TfNSW G38 for placing and managing stockpiles.
2.4.3 Restoration
Following completion of the Works, carry out restoration of the stockpile areas in accordance with
TfNSW R178.
2.5 TOPSOIL
2.5.1 Removal of Topsoil
Commence removal of topsoil after completion of clearing and grubbing, and removal of the cleared
materials on that section of the Works.
Do not remove topsoil in locations where a bridging layer is to be constructed in accordance with
Clause 3.3.2, unless directed otherwise by the Principal.
Where so specified in Annexure R44/A2.1 or where directed by the Principal, after removal of the
topsoil:
(a) stockpile the topsoil within the Site separately from other materials and clear of the Works for
use in revegetation, or
(b) stockpile the topsoil as a windrow longitudinally and adjacent to the toe of embankment batter,
or
(c) dispose of the topsoil as spoil outside the Site in accordance with Clause 2.7.1; or
(d) if the topsoil has been identified as contaminated material, dispose of the topsoil as spoil in
accordance with Clause 2.7.2.
12 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Before commencing stockpiling of topsoil, carry out a survey of the existing surface at each stockpile
area in accordance with Clause 1.6.1, to be able to later determine the volumes of topsoil placed at the
location.
After removing the topsoil, carry out a survey of the resulting surface in accordance with Clause 1.6.1
to be able to later determine the volume of excavation for general earthworks, and the volume of
unsuitable material.
HOLD POINT
Process Held: Any works which will alter the ground surface as surveyed.
Submission Details: Survey Report of existing surface levels, and notification that the set out
specified in Clause 1.6.2, including set out of the extent of the Cut/Fill
Transition Zone as specified in Clause 3.5.2, have been carried out, at least
three working days prior.
Release of Hold Point: The Principal will consider the submitted documents, inspect the surfaces
and set out, and may direct further action prior to authorising the release of
the Hold Point. Further action may include altering the limits of the Cut/Fill
Transition Zone.
Upon reaching the Designed Floor Level or Foundation Level of cuttings, or after stripping of the
topsoil covering each embankment foundation, hold any subsequent earthworks processes (refer to
Hold Points in Clauses 3.2 and 3.3) to allow inspection of the foundation.
Where unsuitable material (as defined in Clause 1.3) is found, excavate such unsuitable material to the
extent directed by the Principal.
Ed 6 / Rev 0 13
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
HOLD POINT
Process Held: Replacement of each Lot of unsuitable material.
Submission Details: Notification that unsuitable material has been removed as directed.
Release of Hold Point: The Principal will inspect the excavation and may direct removal of further
material as unsuitable material prior to authorising the release of the Hold
Point.
Notify the Principal promptly of any areas of the foundation, or any layer within the formation, that rut
excessively, yield or show signs of distress or instability.
Replace any material that has been removed as unsuitable material with either:
(a) suitable material conforming to Clause 5.2.1; or
(b) if directed, with foundation treatments in accordance with Clause 3 or as shown on the
Drawings.
Use any material that has been removed as unsuitable by placing it in embankments in accordance
with Clause 5, unless directed to dispose of the material as spoil in accordance with Clause 2.7.
Remove from the Site any contaminated materials that cannot be treated and re-used within the Works
or stockpiled at the Site, and dispose of such material in accordance with Clause 2.7 of this
specification and TfNSW G36.
Before and after removal of unsuitable material, carry out a survey (if specified as required in
Annexure R44/A1) in accordance with Clause 1.6.1 to determine the volume of unsuitable material
removed.
Alternatively, the Principal may agree to determination of volume by manual measurement (with a
tape measure or other means) and calculation.
Payment for the removal of unsuitable material, and its subsequent processing and use or disposal
within the Site, will be made under Pay Item R44P4. Payment for placing and compaction of
conforming material to replace the unsuitable material removed will be paid under Pay Item R44P2
(site won material) or Pay Item R44P3 (imported material).
If you allow any material to become unsuitable because of your inappropriate construction activities,
all costs associated with reworking or replacing such unsuitable material will be borne by you.
14 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
2.7 SPOIL
2.7.1 Non-contaminated Materials
Dispose of spoil comprising non-contaminated material in the manner and at the locations authorised
or agreed to by the Principal, by any of the following means, as appropriate:
(a) forming flatter batter slopes on embankments; or
(b) widening embankments uniformly; or
(c) stockpiling within the Site; or
(d) disposal at an approved location outside the Site.
Use up all available areas within the Site for disposal by the above means, before proposing alternative
locations.
Construction of flatter batters (item (a) above) or wider embankments (item (b) above) must be carried
out in accordance with Clause 5 for embankment construction.
If you propose to use spoil disposal locations outside the Site, obtain all the necessary approvals and
consents, including environmental approvals, and provide copies of them to the Principal at least five
working days prior to commencing the disposal of material at these locations.
Payment for disposal of spoil comprising non-contaminated material within the Site is to be included
in the rates generally. Payment for disposal of spoil comprising non-contaminated material at an
approved location outside the Site will be made under Pay Item R44P6 or Pay Item R44P1.2.
Manage, stockpile and/or remove from the Site contaminated materials in accordance with
TfNSW G36. If disposal methods and locations are not specified, determine the method(s) and
location(s) for disposal of the contaminated material.
Notify the Principal at least 24 hours prior to excavation of the contaminated material, and removal of
any contaminated material from the Site, and provide details of the proposed method and location of
disposal.
Payment for excavation and stockpiling of contaminated material at the Site will be made under
Pay Item R44P1.2 or Pay Item R44P2; or where the contaminated material is contained within
unsuitable material, under Pay Item R44P4.
Additional payment will be made under Pay Item R44P8 for the identification, treatment, classification
in accordance with EPA Waste Classification Guidelines and disposal of the contaminated material at
locations legally authorised to accept the contaminated material.
Treatment and disposal of material contaminated by your operations will be at your own cost.
2.8 UPPER ZONE, VERGE AND SPILL THROUGH BRIDGE ABUTMENT FILL
MATERIAL
2.8.1 General
Material placed in the Upper Zone of Formation, verges, and spill through bridge abutment zones
(refer to Clause 5.2.3) must conform to the requirements of Clauses 2.8.4 to 2.8.7.
Ed 6 / Rev 0 15
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Do not use steel furnace slag aggregates in the Upper Zone of Formation, verges, spill through bridge
abutment zones, and cutting and embankment drainage layers.
Obtain Upper Zone material, verge material and spill through bridge abutment fill (Type ST) material
of the specified quality in the first instance from cuttings or borrow areas within the Site.
Loosen and process the excavated materials from cuttings as required to meet the specified
requirements before their incorporation in the Works.
Where these materials are not available from cuttings or borrow areas within the Site or in insufficient
quantities, obtain them as imported material from the sources nominated in Annexure R44/A2.1,
unless otherwise approved by the Principal (refer also to Clause 2.2).
Where the source of imported material is not nominated in Annexure R44/A2.1, obtain them from
legally operating quarries or recycling facilities or other sources acceptable to the Principal. Provide
the Principal with details of the proposed source locations, quantities to be supplied and their material
properties before the imported material is delivered to the Site (refer also to Clauses 6.1.1 and 6.2, and
associated Hold Points).
Prior to placement of Selected Material, verge material and Type ST material, place the material in
stockpiles and test it for conformity with the requirements of Clauses 2.8.5, 2.8.6 and 2.8.7
respectively and Annexure R44/A2.2. Each Lot of stockpiled material must not exceed 4,000 tonnes
in mass.
Sample and test the material at the frequency specified in Table R44/L.2, and calculate the
characteristic value (Q) of the CBR for each Lot in accordance with TfNSW Q. For the purpose of
this calculation, report the individual CBR values to the nearest 1% and the characteristic value (Q) to
the nearest 0.1%.
Before placing the material in the Works, establish the response of the material to pre-treatment and
adopt an appropriate pre-treatment regime for subsequent conformity testing.
For those materials which may be susceptible to breakdown or weathering, pre-treat samples of the
material by crushing to size, subjecting to repeated compaction in accordance with Test Method
TfNSW T102 or artificial weathering in accordance with Test Method TfNSW T103 (refer to
Annexure R44 A2.2).
Material for use in the Upper Zone of Formation, other than Selected Material Zone, must:
(a) have a CBR value conforming to Annexure R44/A2.2, for the fraction passing 19.0 mm
AS sieve;
(b) have a Plasticity Index (PI) value conforming to Annexure R44/A2.2;
(c) (i) have a maximum particle dimension no greater than 100 mm;
(ii) have greater than 50% passing the 19.0 mm AS sieve.
16 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Material imported for the Upper Zone of Formation, other than Selected Material Zone, must be
from the sources and of the quality specified in Annexures R44/A2.1 and R44/A2.2
respectively, or approved by the Principal.
Clause 2.8.4.1 item (c) for site won material also applies to the imported material.
If the site won Selected Material conforms to the specified requirements for the lower layer of
the Selected Material Zone, but has a CBR value that is less than that specified for the upper
layer of the Selected Material Zone, you may modify the Selected Material by mixing it with
hydrated lime, or other binders approved by the Principal, to make it conforming to the specified
requirements of the upper layer. (Refer also to Note (5) of the table in Annexure R44/A2.2.)
Material imported for the Selected Material Zone must conform to TfNSW 3071.
Material for use in the verges must meet the following requirements:
(a) have a characteristic CBR value conforming to Annexure R44/A2.2, for the fraction
passing 19.0 mm AS sieve;
(b) have a PI value conforming to Annexure R44/A2.2;
(c) (i) have a maximum particle dimension no greater than 53 mm;
(ii) have greater than 50% passing the 19.0 mm AS sieve.
Material imported for the verges must meet the grading requirements of TfNSW 3071 for
Selected Material and must:
(a) have a characteristic CBR value conforming to Annexure R44/A2.2, for the fraction
passing 19.0 mm AS sieve;
(b) have a PI value conforming to Annexure R44/A2.2.
Ed 6 / Rev 0 17
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
2.9.1 General
Obtain fill material for embankment construction in the first instance from cuttings within the Site.
Where authorised by the Principal, the site won fill material may be supplemented with borrowed or
imported material in accordance with Clause 2.3.
Fill material for embankment construction must be free of tree stumps, roots and refuse.
Loosen and process the excavated materials from cuttings as required to meet the specified
requirements before their incorporation in the Works.
If surplus excavated material from other works under the Contract (such as that from trenching for
drainage pipes or utility conduits) is used in the construction of embankments or backfilling of
trenches, such material must also conform to the specified requirements.
Material for foundation treatment Types C5 and E5, Drainage Layer, must conform to the properties
specified in Table R44.2 in Clause 3.2.5 (and cross referenced in Clause 3.3.5).
Earth fill and rock fill material must also conform to the requirements of Clauses 5.2.1 and 5.3.1
respectively.
Rock capping and rock facing material must conform to the requirements of Clauses 5.3.4 and 5.4.2
respectively.
3 FOUNDATIONS
3.1 GENERAL
Carry out foundation treatments for:
(a) Cuttings: after excavation to the Designed Floor Level, or Foundation Level as appropriate, and
removal of unsuitable material;
18 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Taking into account the site conditions such as traffic, access, environmental/climatic conditions and
insitu materials, select your equipment and techniques and use them in such a manner that minimises
surface heaving or other foundation damage during preparation of the foundation and construction of
overlying layers.
Construct other features (such as trench and foundation drains in accordance with Specification
TfNSW R33) in conjunction with the foundation treatments, as shown on the Drawings, or as directed
or authorised by the Principal.
Remove and replace any unsuitable material in accordance with the Clause 2.6.
Prior to carrying out any foundation treatments within cuttings (except for Treatment Type C5), carry
out tests to determine the CBR and PI values of the material in the floor of the cutting, using the Test
Methods specified in Annexure R44/A2.2, and present the floor for inspection by the Principal.
You may obtain samples for the CBR and PI tests from test pits prior to completion of excavation to
the required floor level of the cutting.
HOLD POINT
Process Held: Treatment of each Lot of floors of cuttings.
Release of Hold Point: The Principal will consider the submitted documents, inspect the floor of the
cutting and may direct further action prior to authorising the release of the
Hold Point.
Further action may include the removal of unsuitable material in accordance
with Clause 2.6; installation of trench drains in accordance with
TfNSW R33, foundation treatments in accordance with this Clause, or
changes to the area to be excavated.
The following types of treatments for foundations within cuttings are depicted in Figures R44.3(a) to
R44.3(d) or described under Clause 3.2.4:
Ed 6 / Rev 0 19
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Where so specified in Annexure R44/A6, extend the foundation treatment into the medians.
Where the CBR and PI values of the material at the Designed Floor Level conform to the requirements
of Annexure R44/A2.2, carry out Foundation Treatment Type C1 involving loosening and
recompaction of the underlying material.
Where the CBR of the material at the Designed Floor Level is less than, or where the PI is greater
than, the requirements nominated in Annexure R44/A2.2, remove or modify the material to the
appropriate depth in accordance with the directed foundation treatment (i.e. Foundation Treatment
Types C2 to C5).
Maintain the floor of the cutting in its conforming condition until you have completed the subsurface
drainage and commenced backfilling and construction of Upper Zone of Formation (which, in
Cuttings, comprise only the Selected Material Zone). You will bear the cost of any additional
treatment required as a result of damage to the foundations that is caused, or allowed to occur, by you.
Unless shown otherwise on the Drawings or specified or directed or authorised by the Principal, carry
out a Type C1 treatment to the floors of cuttings as follows:
(a) After excavation to the Designed Floor Level, trim the surface to within the tolerances specified
in Clause 7.7.1;
(b) Remove and replace any unsuitable material present in accordance with Clause 2.6;
(c) Loosen the material below the floor of the cutting by ripping to a depth of between 300 mm to
400 mm for the width of the Selected Material Zone as shown on the Drawings, or the width of
the pavement layers plus one metre on each side (whichever width is the greater). The
maximum particle dimension in the loosened material must not exceed 100 mm;
(d) Adjust the moisture content of the loosened material as required and recompact it to conform to
the relative compaction level specified in Clause 7.2;
(e) After recompaction, trim the floor of the cutting to the Designed Floor Level and within the
tolerances specified in Clause 7.7.
As part of the trimming operation, prepare the surface in accordance with Test Method
TfNSW T199, for deflection monitoring as required under Clauses 7.5 and 7.6.
20 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Payment for the Type C1 treatment will be made under Pay Item R44P7.1. Do not include the volume
that is loosened (and recompacted) for the Type C1 treatment when measuring the total excavation
volume under general earthworks, for payment under Pay Item R44P2.
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type C2 treatment to the floors of the cuttings as follows:
(a) After excavation to the Foundation Level which is parallel to, and at a depth below the Designed
Floor Level equal to the required thickness of backfill, trim the floor of the cutting to within the
tolerances specified in Clause 7.7;
Determine the CBR and PI values of the material in the floor of the cutting by the Test Methods
specified in Annexure R44/A2.2;
(b) Remove and replace any unsuitable material present in accordance with Clause 2.6;
(c) Compact the material exposed at the floor of the cutting with not less than six passes of a
vibrating roller;
(d) Place backfill material conforming to the requirements of Clause 2.8.4 and Annexure R44/A2.2,
and compact to the relevant requirement specified in Table R44.7 under Clause 7.2;
(e) Trim the compacted backfill to the Designed Floor Level and within the tolerances specified in
Clause 7.7.
Ed 6 / Rev 0 21
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Include the volume that is excavated between the Designed Floor Level and the Foundation Level for
the Type C2 treatment when measuring the total excavation volume under general earthworks, for
payment under Pay Item R44P2.
Payment for the backfilling under item (d) of this Clause will be made under Pay Item R44P7.3.
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type C3 treatment to the floors of the cuttings by either the C3(I) or C3(II) method, as follows. Use
the latter method where so specified in Annexure R44/A3.
Payment for the stabilisation will be made under the appropriate Pay Items in TfNSW R50, and
payment for imported material will be made under Pay Item R44P3.
Include the volume that is excavated between the Designed Floor Level and the Foundation Level for
the Type C3(II) treatment when measuring the total excavation volume under general earthworks, for
payment under Pay Item R44P2.
Where shown on the Drawings or specified or directed or authorised by the Principal, after excavation
to Designed Floor Level, carry out a Type C4 treatment to the floor of the cutting by placing a layer
(or multiple layers) of geotextile and/or geogrid over the floor of the cutting.
22 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The geotextile and geogrid must conform to Specifications TfNSW R63 and TfNSW R67 (short term
design strength only) respectively. Place the geotextile and geogrid in conformity to TfNSW R63 and
TfNSW R67 respectively.
Payment for the geotextile and geogrid used in the Works will be made under Pay Item R44P7.5.
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type C5 treatment to the floors of the cuttings as follows:
(a) After excavation to the Foundation Level which is parallel to, and at a depth below the Designed
Floor Level equal to the required thickness of the drainage layer, trim the floor of the cutting to
within the tolerances specified in Table R44.8 under Clause 7.7 and to the same crossfall as the
pavement above to ensure that drainage within the cutting can occur;
Where the horizontal alignment of the road is in crossfall transition, provide a minimum 1%
crossfall at the floor of the cutting;
Provide end outlet/drainage treatment as shown on the Drawings, or directed by the Principal.
(b) Remove and replace all unsuitable material present in accordance with Clause 2.6;
(c) Compact the material exposed at the floor of the cutting with not less than six passes of a
vibrating roller;
(d) Prior to placing the drainage layer, place a geotextile conforming to TfNSW R63, over the floor
of the cutting, except where the cutting is in rock;
(e) Place and spread the drainage layer material over the geotextile, to a minimum layer thickness
of 300 mm, avoiding segregation and contamination with foreign material.
The drainage layer material must conform to the properties specified in Table R44.2. Do not
use steel furnace slag aggregates in the drainage layer.
Property Requirement
Maximum particle dimension 125 mm
Percentage passing:
19.0 mm AS sieve 0 – 15%
1.18 mm AS sieve 0 – 5%
75 µm AS sieve < 0.5% (1)
Percentage of +19.0 mm fraction with Is(50) less than
the specified value in Annexure R44/A2.2 10% (max)
Wet/Dry Strength Variation Annexure R44/A2.2
Note:
(1)
Test only where directed.
(f) Adjust the grading of the drainage layer material as necessary to within the limits specified in
Table R44.2 to ensure that it provides a stable foundation for compaction of the overlying
Selected Material Zone.
(g) Compact the drainage layer using the nominated compaction procedure developed in accordance
with Clause 7.4.2. After compaction, the upper surface of the drainage layer must be within the
tolerances specified in Table R44.8.
Ed 6 / Rev 0 23
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
(h) Place a geotextile of the same type as that specified in item (d) above over the top of the
drainage layer.
Payment for the drainage layer will be made under Pay Item R44P7.6. Include the volume that is
excavated for the Type C5 treatment when measuring the total excavation volume under general
earthworks, for payment under Pay Item R44P2. Payment for the geotextile will be made under Pay
Item R44P7.5(a).
Other foundation treatments may be adopted as shown on the Drawings or as directed or agreed to by
the Principal.
24 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
HOLD POINT
Process Held: Treatment of each Lot of embankment foundation.
Release of Hold Point: The Principal will consider the submitted documents, inspect the prepared
embankment foundation area, and may direct further action prior to
authorising the release of the Hold Point.
Further action may include removal of unsuitable material in accordance
with Clause 2.6, or treatment in accordance with Clause 3.3.
The following types of treatments for foundations under embankments are depicted in
Figures R44.4(a) to R44.4(e) or described under Clause 3.3.6:
• Type E1 – Loosen and Recompact;
• Type E2 – Bridging Layer;
• Type E3 – Working Platform;
• Type E4 – Geotextile/Geogrid Layer(s);
• Type E5 – Drainage Layer;
• Type E6 – Earth Fill Foundation Treatment.
Where so specified in Annexure R44/A6, extend the foundation treatment into the medians.
Carry out Type E1 treatment for all embankment foundations, unless shown otherwise on the
Drawings or directed or authorised by the Principal to carry out other types of treatment.
Maintain the embankment foundation after treatment in its conforming condition until you have
commenced embankment construction. You will bear the cost of any additional foundation treatment
required as a result of damage to the foundations that is caused, or allowed to occur, by you.
Damage in this context includes that arising from using the treated foundation area by earthworks
plant for purposes other than the construction of the embankment over the foundation treatment.
Ed 6 / Rev 0 25
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Unless shown otherwise on the Drawings or specified or directed or authorised by the Principal, carry
out a Type E1 treatment to the embankment foundation as follows:
(a) Remove and replace any unsuitable material present in accordance with Clause 2.6;
(b) Loosen the material in the foundation area by ripping to a depth of between 300 mm to 400 mm;
(c) Carry out any terracing as required by Clause 3.4;
(d) Adjust the moisture content of the loosened material as required and recompact it to conform to
the relative compaction level specified in Clause 7.2.
Payment for the Type E1 treatment will be made under Pay Item R44P7.2. Do not include the volume
that is loosened (and recompacted) for the Type E1 treatment when measuring the total excavation
volume under general earthworks, for payment under Pay Item R44P2.
Where shown on the Drawings or specified or directed or authorised by the Principal where you can
demonstrate that it is impracticable to achieve the degree of compaction specified for the foundation in
Clause 7.2, carry out a Type E2 treatment by constructing a bridging layer over the embankment
foundation area.
The distance from the top of the bridging layer to the underside of the Selected Material Zone must not
be less than that specified in Annexure R44/A3.
You may construct the bridging layer using either earth fill or rock fill material. Whichever material is
used, the bridging layer must provide a stable platform upon which a conforming earthworks layer can
be constructed.
Earth fill used must conform to the requirements of Clause 5.2.1, and in addition must consist of
granular material with strong mechanical interlock and low sensitivity to moisture. Rockfill used must
conform to the requirements of Clause 5.3.1.
If specified or directed by the Principal, prior to placing the bridging layer, place a geotextile
conforming to TfNSW R63 over the embankment foundation area.
Place the bridging layer material by end-dumping and spreading it in a single layer of sufficient
thickness to allow the passage of earthmoving equipment over the bridging layer with minimal surface
26 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
heaving. The compaction requirements of Clause 7.4 for rock fill placing do not apply to the bridging
layer.
The thickness of the bridging layer when completed must conform to that specified in
Annexure R44/A3.
The Principal may require the construction of a trial section of the bridging layer prior to authorising
placement of the bridging layer in other areas.
Where the bridging layer is constructed from rock fill material, and the bridging layer is to be overlain
by earth fill, place a rock capping layer, including geotextile, immediately above the rock fill in
accordance with Clause 5.3.4 unless approved otherwise by the Principal.
Payment for the bridging layer will be made under Pay Item R44P7.4. Payment for the geotextile will
be made under Pay Item R44P7.5(a).
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type E3 treatment to the embankment foundation by either the E3(I) or E3(II) method, as follows.
Use the latter method where so specified in Annexure R44/A3.
Ed 6 / Rev 0 27
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Payment for the stabilisation will be made under the appropriate Pay Items in TfNSW R50, and
payment for imported material will be made under Pay Item R44P3.
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type E4 treatment to the embankment foundation by placing a layer (or multiple layers) of geotextile
and/or geogrid over the foundation area.
The geotextile and geogrid must conform to TfNSW R63 and TfNSW R67 (short term design strength
only) respectively. Place the geotextile and geogrid in conformity to TfNSW R63 and TfNSW R67
respectively.
Foundation Level
Geotextile / Geogrid Topsoil
(one or more layers) (removed or
overlain by Geotextile)
Payment for the geotextile and geogrid used in the Works will be made under Pay Item R44P7.5.
Where shown on the Drawings or specified or directed or authorised by the Principal, carry out a
Type E5 treatment to the embankment foundation by constructing a drainage layer consisting of a rock
layer enclosed by geotextile.
The distance between the top of the drainage layer and the underside of the Selected Material Zone
must not be less than that specified in Annexure R44/A3.
28 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Where shown on the Drawings or specified or directed or authorised by the Principal, remove the
topsoil layer.
Shape and trim the foundation beneath the drainage layer, to ensure that the drainage layer after
placing can drain properly. Maintain a clear drainage path through the layer, particularly at the outer
edges of the embankment, and provide outlet/drainage treatment at the ends as shown on the
Drawings, or directed by the Principal.
Place a geotextile conforming to TfNSW R63 over the embankment foundation area.
Place and spread the drainage layer material over the geotextile, avoiding segregation and
contamination with foreign material.
The drainage layer material must conform to the properties specified in Table R44.2 under
Clause 3.2.5. Do not use steel furnace slag aggregates in the drainage layer.
Adjust the grading of the drainage layer material as necessary to within the limits specified in
Table R44.2 to ensure that it provides a stable foundation for compaction of the overlying
embankment.
Compact the drainage layer using the nominated compaction procedure developed in accordance with
Clause 7.4.2.
Place a geotextile of the same type as that specified above over the drainage layer, before placing the
embankment fill.
The thickness of the drainage layer when completed must conform to that specified in
Annexure R44/A3.
Geotextile Topsoil
(removed or overlain
by Drainage Layer)
Payment for the drainage layer will be made under Pay Item R44P7.7. Payment for the geotextile used
in the Works will be made under Pay Item R44P7.5(a).
Where shown on the Drawings or specified or directed or authorised by the Principal where you can
demonstrate that it is impractical to achieve the degree of compaction specified for the foundation in
Clause 7.2, carry out a Type E6 treatment by placing an earth fill layer over the embankment
foundation area.
Ed 6 / Rev 0 29
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The distance from the top of this earth fill layer to the underside of the Selected Material Zone must
not be less than that specified in Annexure R44/A3.
The material for this earth fill layer must conform to the requirements for earth fill in Clause 5.2,
except that the maximum particle dimension of rock must not be greater than 200 mm. The moisture
content must be within the limits specified in Annexure R44/A5.
Place the material such that the top 300 mm of the layer is compacted to the relevant relative
compaction specified in Table R44.7 under Clause 7.2.
The thickness of the earth fill layer when completed must conform to that specified in
Annexure R44/A3.
After placing, the Principal may require you to carry out proof rolling of each Lot in accordance with
Clause 7.5. If proof rolling shows that this earth fill layer exhibits excessive deflection, or if
subsequent layers cannot be compacted to meet the specified requirements for earth fill, remove the
layer placed for this Foundation Treatment and treat the foundation as re-determined by the Principal.
The Principal may require the construction of a trial section of the earth fill foundation treatment layer
prior to authorising the construction of the earth fill foundation treatment layer in other areas.
Payment for the earth fill foundation treatment layer will be made under Pay Item R44P7.8.
Adopt other foundation treatments as shown on the Drawings or as directed or agreed to by the
Principal.
Such horizontal terraces are not required for slopes flatter than 10H:1V.
Cut each successive terrace step to the depths shown in Figure R44.5. Cut the terraces progressively
as you construct the embankment.
Depth of terrace:
• for slope steeper than 4H:1V 600 to 900 mm
• for slope from 10H:1V to 4H:1V 300 to 600 mm
Inspect the floor of each terrace in accordance with Clause 2.6 to check for any unsuitable material.
Unless directed otherwise by the Principal, incorporate the material thus excavated in embankments in
accordance with Clause 5, or dispose of it as spoil in accordance with Clause 2.7.
30 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Do not include the volume of material removed in terracing when measuring the total excavation
volume under general earthworks, for payment under Pay Item R44P2.
Where the height of the embankment from the Stripped Surface Level to Top of Formation is less than
the Shallow Embankment height specified in Annexure R44/A4, carry out further excavation of the
area to a depth below the Stripped Surface Level necessary to achieve that height, unless otherwise
shown on the Drawings or directed by the Principal.
You may propose to the Principal a height that is less than the specified Shallow Embankment height,
to reduce the depth of excavation required. The Principal may approve this reduced height if you can
verify by testing, that CBR and PI values at your proposed higher Foundation Level conform to that
specified in Annexure R44/A2.2.
Observe the Hold Point in Clause 3.3 and carry out embankment foundation treatment(s) in
accordance with Clause 3.3, before placing the overlying formation.
When the height of the embankment conforms to the specified Shallow Embankment height, then the
thickness of the Upper Zone of Formation will conform to that specified in Annexure R44/A4
corresponding to “Shallow Embankment”, unless the Principal has approved a reduced height as
mentioned above. (The entire formation from Foundation Level to Top of Formation will thus
comprise solely of the Upper Zone of Formation.)
Include the volume of material excavated to achieve the Shallow Embankment height when measuring
the total excavation volume under general earthworks, for payment under Pay Item R44P2.
Within the Cut/Fill Transition Zone, following excavation to the Designed Floor Level, carry out
further excavation, parallel to the cutting floor, to a depth below the Designed Floor Level necessary
to achieve the minimum thickness specified for the Upper Zone of Formation corresponding to
“Cut/Fill Transition Zone” in Annexure R44/A4, as shown in Figure R44.6(b).
Ed 6 / Rev 0 31
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
10 m (4)
Extent of additional
Intersection
excavation into cutting
line
Plan View
Notes:
(1) Within this zone, which is outside the Cut/Fill Transition Zone and within the cutting, the thickness of the Upper Zone of
Embankment height, further excavation to achieve the Shallow Embankment height is necessary. This excavation extends
into the cutting for a further 10 m as part of the Cut/Fill Transition Zone.
The thickness of the Upper Zone of Formation will be that corresponding to “Cut/Fill Transition Zone” in
Annexure R44/A4.
(3) Within this zone, where the height from the Stripped Surface Level to the Top of Formation is greater than the Shallow
Embankment height, no further excavation below the Stripped Surface Level, other than terracing, is necessary. The
thickness of the Upper Zone of Formation will be that corresponding to “Embankment” in Annexure R44/A4. The fill
below the Upper Zone of Formation may be General Fill.
(4) The 10 m is measured perpendicular to the line resulting from the intersection of the plane of the Designed Floor Level
This additional excavation must extend into the cutting for a distance of 10 m from the line resulting
from the intersection of the plane of the Designed Floor Level with the plane of the stripped surface, as
shown in Figure R44.6(b). The 10 m distance is measured perpendicular to the line of intersection
between the two planes.
Where so specified in Annexure R44/A6, extend the cut/fill transition treatment into the medians. Do
not extend this cut/fill transition treatment into the cutting batter.
Within this transition zone, the requirements of Clause 3.5.1 for Shallow Embankment apply.
Include the volume of material excavated when measuring the total excavation volume under general
earthworks, for payment under Pay Item R44P2.
32 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ensure that the excavation is free-draining by either sloping toward the nearest exit of the cutting at a
minimum grade of 1%, or installing a subsurface drain at the lower end of the excavation unless
otherwise shown on the Drawings or directed by the Principal. Installation, and payment, of the
subsurface drains will be in accordance with TfNSW R33.
4 CUTTINGS
4.1 GENERAL
4.1.1 Scope
The batter slopes in cuttings shown on the Drawings may be re-determined by the Principal, following
an inspection and investigation during excavation (refer to Clause 4.2).
Remove by hand or machine any loose or unstable blocks which are too large to be removed by other
means, unless otherwise directed by the Principal.
Clean the surfaces of cutting batters in rock with slopes of 1H:1V or steeper using compressed air. Do
not use water jets or air-water jets for cleaning unless specifically approved by the Principal for
specific areas.
Immediately following completion of excavation in rock to the level of each bench, remove all loose
rock and soil material and clean the rock surfaces to sufficiently expose the batter surface, and
particularly the joints, to allow the Principal their assess their condition and likely effect on the
stability of the batter.
Ed 6 / Rev 0 33
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
HOLD POINT
Process Held: Excavation below bench level for slopes of 1H:1V or steeper.
Submission Details: Presentation of cleaned batter and bench/floor surfaces for geotechnical
inspection.
Release of Hold Point: The Principal will inspect the cleaned surfaces and may direct further action
prior to authorising the release of the Hold Point.
Further action may include additional cleaning (if the condition of the faces
cannot, in the opinion of the Principal, be adequately assessed), and
stabilisation works, prior to or concurrent with any further work within the
cutting.
Following inspection, the Principal may direct additional stabilisation works, including changes to the
batter slope.
For batters steeper than 1H:1V, if any section of the batter up to a height of 3 m above the toe of batter
has been over-excavated beyond the tolerance limit specified, the Principal may direct you to re-form
the batter to the average batter slope using randomly mortared stone or other treatments. Where the
former is directed, the stone used must be similar to the sound rock in the cutting and the mortar used
must be coloured to match the colour of the rock.
Alternatively, you may propose a minor change in the general slope of the batter for your convenience.
If the Principal approves such a change, it will not be regarded as a re-determination of the batter slope
under Clause 4.1.2, and no additional payment will be made. If your proposal is not approved, restore
the batter to the specified slope and stability, to the satisfaction of Principal.
Construct benches at cutting batters as shown on the Drawings to provide geotechnical stability,
provide drainage and erosion control, and allow access for maintenance purposes. Notwithstanding
the tolerances permitted under Clause 7.8, bench widths must not be less than those shown on the
Drawings.
Clean the surface of benches in rock cuttings, using compressed air, to allow inspection of the bench
and assessment of its stability, unless otherwise directed by the Principal.
34 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The floor of the bench must not vary from levels shown on the Drawings by more than the tolerances
specified in Clause 7.7, but the bench must have a crossfall to drain water away from the cut face
located immediately below the bench. Provide and maintain longitudinal drainage to prevent ponding
of water on the benches.
Construct the bench drains, where shown on the Drawings, progressively as each batter face is
completed. Payment for this work will be made in accordance with TfNSW R11.
4.4.3 Maintenance
Maintain and regularly clean the benches of any loose materials throughout the Contract period. The
cost of such maintenance and cleaning of benches is to be included in the rates generally.
4.5.1 General
Use line drilling or pre-splitting to produce a uniform and neat batter surface after excavation. The
boreholes used in line drilling or pre-splitting must be straight, parallel and in the designed plane of
the batter.
You may propose an alternative method of excavation and preparation of the cut face so as to produce
a result equivalent to that produced from line drilling or pre-splitting. Approval to such alternative
methods will be granted at the absolute discretion of the Principal, who may require you to carry out a
trial section using the proposed method to demonstrate its suitability.
When carrying out line drilling or pre-splitting, do not exceed the centre-to-centre spacing of the drill
holes shown in Table R44.3.
Table R44.3 – Hole Diameter and Spacing for Line Drilling or Pre-splitting
Cutting Batter Treatment Hole Diameter (mm) Maximum Hole Spacing (1) (mm)
Line Drilling Up to 51 150
Line Drilling 51 – 76 250
Pre-splitting 38 – 51 450 (2)
Pre-splitting 51 – 64 750 (2)
Pre-splitting 76 – 89 900 (2)
Notes:
(1)
Spacing measured centre-to-centre.
(2)
Reduce the maximum hole spacing as necessary to produce a uniform and neat batter surface after
excavation.
Prior to commencing blasting (refer to Clause 4.6) for excavation with batter slope of 1H:1V or
steeper, carry out line drilling or pre-splitting to the designed batter profile at the hole spacings shown
Ed 6 / Rev 0 35
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
in Table R44.3, so as to produce a uniform and neat batter surface after excavation which is acceptable
to the Principal.
4.6 BLASTING
Clause 4.6 applies only where blasting is permitted under the Contract, as indicated in
Annexure R44/A7. Burden blasting must not damage the batter face.
4.6.1 General
Comply with the requirements of TfNSW G36 for ground vibration and airblast.
The Hold Point in TfNSW G36 for the submission of the Noise and Vibration Management Sub Plan
(previously Vibration and Airblast Management Sub-Plan) and the Building Condition Inspection
Reports applies prior to the commencement of blasting. Include in the Noise and Vibration
Management Sub-Plan a detailed procedure to be followed in the event of a misfire of the charges.
Comply with all Government regulations relating to transport, storage, handling and the use of
explosives and AS 2187.1 and AS 2187.2. Comply also with the requirements of external agencies
including, but not limited to, the NSW Environment Protection Authority (EPA) and SafeWork NSW,
and demonstrate compliance.
Prior to commencement of any blasting activities, obtain all necessary approvals and licences from the
appropriate authorities.
Prior to the start of each blast, submit to the Principal details of the following:
(a) proposed blasting design, and estimated airblast overpressure (noise) and peak particle velocity
(ground vibration) at sensitive locations;
(b) measures to limit noise and ensure that vibration from blasting does not adversely affect nearby
structures.
HOLD POINT
Process Held: Start of each blast.
Submission Details: Proposed blasting design, estimated airblast overpressure and peak particle
velocity at sensitive locations, and measures to limit noise and ensure that
vibration from blasting does not adversely affect nearby structures, at least
24 hours prior.
Release of Hold Point: The Principal will consider the submitted documents prior to authorising the
release of the Hold Point.
If you revise the blasting design, re-submit details of the revised blasting design, and the above Hold
Point again applies.
Confine your blasting operations to the weekdays of Mondays to Fridays but excluding public
holidays, between the hours of 9:00 am and 3:00 pm, unless otherwise approved by the Principal.
36 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
During blasting operations, take precautions relating to the safety of persons and animals. Close any
roads likely to be affected by the blasting to traffic and erect the appropriate signs in accordance with
Specification TfNSW G10. Establish a standard warning procedure such as that given in the National
Association of Australian State Road Authorities (NAASRA) Explosives in Roadworks Users Guide
1982 and implement the procedure at all times.
Implement and maintain a community liaison program during blasting activities to keep the
community in the vicinity of the Works informed of any such activities. Provide information on
expected levels of vibration or airblast.
For each blast, notify in writing all residents within a radius of 1 km from the location of the proposed
blasting, and any other relevant parties, before blasting commences. Include in the notification the
likely times, frequency and duration of blasting and precautions being taken to ensure that damage to
property will not result.
Do not detonate a blast prior to the time that has been announced for that blast, unless otherwise
approved by the Principal.
Monitor and report the building(s) condition during the blasting operations. If no Pay Item has been
provided in TfNSW G36 for the Building Condition Inspection Reports, all costs associated with the
inspections and reports will be borne by you.
Maintain accurate records of each blast including the details listed below:
(a) date, identification number and time of blast;
(b) location, number and diameter of blast holes loaded;
(c) depth of each drill hole loaded;
(d) inclination of drill holes;
(e) burden(s) and spacing(s);
(f) types and amounts of explosives used;
(g) maximum instantaneous charge;
(h) Initiation Plan;
(i) length and type of stemming in each blast hole;
(j) ground vibration and noise levels at measuring locations.
These details must be written down at the time when the holes are loaded and not afterwards, and the
records must be signed by the shotfirer. Provide a copy of the records to the Principal on the same day
as the blast.
Perform also a high definition video recording of the blasting event, covering the period between at
least 5 seconds before the blast to 30 seconds after. Record the video at a minimum of 120 frames per
second and a minimum resolution of 720p. Retain the video recording as an Identified Record.
Ed 6 / Rev 0 37
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Clause 4.6.5 will apply only where a noise sensitive location exists which will be impacted by the
blasting.
Carry out monitoring of airblast from blasting operations to verify that the limits specified in
Annexure R44/A7 are not exceeded at any noise sensitive location. The equipment for this monitoring
must be sited at the perimeter of the noise sensitive location at the point closest to the maximum
charge.
The monitoring equipment used must be calibrated annually by a NATA accredited testing facility or
manufacturer’s facility approved by the Principal.
Report all monitoring readings on test certificates, indicating clearly whether they are in conformity to
the requirements of this Specification. Provide a copy of the test certificate to the Principal.
In the event that the measured airblast exceeds the specified limits, suspend further blasting work and
take additional measures to ensure that, for any future blast, the limiting airblast is not exceeded. Do
not resume any blasting until details of the additional measures have been provided to the Principal.
Clause 4.6.6 will apply only where a vibration sensitive location exists which will be impacted by the
blasting.
Carry out monitoring of ground vibrations from blasting operations to verify that the limits specified in
Annexure R44/A7 are not exceeded at any vibration sensitive location. The equipment for this
monitoring must be sited at the perimeter of the structure or building at the point closest to the
maximum charge.
The measurement process for determining verification of compliance with the specified criteria must
be in accordance with AS 2187.2.
The monitoring equipment used must be calibrated annually by a NATA accredited testing facility or
manufacturer’s facility approved by the Principal.
Report all monitoring readings on test certificates, indicating clearly whether they are in conformity to
the requirements of this Specification. Provide a copy of the test certificate to the Principal.
To minimise the risk of peak particle velocity limits being exceeded, develop a blasting site
relationship between peak particle velocity, distance and blasting charge.
For the first blast, set up monitors at not less than five points, at varying distances away from the
blasting site. The maximum instantaneous charge for the first blast must not exceed that calculated
from the following formula:
2
D
MIC = 0.5 −0 . 625
p. p. v.
1140
or
38 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
p.p.v. 1.25
MIC = 0.5 D2 � �
1140
For subsequent blasts, you may adjust the charge weight and other aspects of the blast design,
provided that you undertake further ground vibration monitoring and re-determine the blasting site
relationship to demonstrate that charge weight limits are not exceeded. Make the graphs available to
the Principal, if so requested.
5 EMBANKMENTS
5.1 GENERAL
5.1.1 Scope
Program and manage the Works as detailed in the EARTHWORKS PLAN (refer to Clauses 1.5 and
2.2) such that material of the quality specified in Clause 2.8 for the Upper Zone of Formation, verge
and spill through bridge abutment zone is available when required.
Prior to placement, process those materials which do not meet the requirements of Clauses 5.2 and 5.3
to achieve conformity. Select the methods of excavation, transport, depositing and spreading of the
fill material so that the placed material in any Lot is homogeneous.
Carry out embankment construction (other than for foundation treatments as specified in Clause 3,
Upper Zones of Formation and verges) in accordance with the requirements of either Clause 5.2 or 5.3,
as applicable.
Before and after placing any imported fill material, carry out a survey (if so required) of the surfaces in
accordance with Clause 1.6.1 to determine the compacted volume of imported fill material placed in
the Works.
Ed 6 / Rev 0 39
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Place fill material for embankment construction in layers parallel to the grade line. When placing
additional material against existing embankment batters, conform to the hillside terracing requirements
specified in Clause 3.4.
Promptly remove any loose material on the batters as the work progresses.
When placing embankment layers, use suitable equipment and methods to avoid surface heaving or
other damage to the foundations and underlying embankment layers.
The batter slopes shown on the Drawings may be re-determined by the Principal, depending on the
earthworks materials available for use.
Earth fill is material other than that conforming to rock fill requirements (refer also to the definition
for earth fill in Clause 1.3).
Earth fill material must have a grading of greater than 60% passing the 37.5 mm AS sieve, and a
maximum particle dimension of rock no greater than two thirds the compacted layer thickness.
If the material does not meet these requirements, before using, break down further the material and/or
blend it with material of finer grading. You may obtain additional finer material from other places
within the Site or by a change in the method of winning and processing the material.
Unless otherwise approved, place earth fill in layers of not less than 100 mm and not more than
300 mm in thickness when compacted. Where more than 25% by volume of the earth fill consists
of rock with any dimension larger than 150 mm, the Principal may authorise an increase in the
compacted layer thickness to 500 mm.
Distribute any rock material evenly throughout the layer to prevent the formation of voids and to
produce a dense, compact embankment. Trim each layer of material placed prior to and during
compaction.
Compact all layers of material placed in the Works uniformly over the full area, and full depth of the
layer to achieve the relative compaction specified in Clause 7.2 before placing the next layer.
Complete the compaction promptly to ensure that the moisture content remains conforming and
uniform, and to minimise the possibility of rain damage.
Include in the EARTHWORKS PLAN details of the procedure to verify that the specified compaction
has been achieved over the full depth of each layer, and that the specified layer thickness has not been
exceeded (refer to item (k) in Clause 1.5.1).
At spill through bridge abutments, place Type ST material conforming to Clause 2.8.7 within the zone
shown in Figure R44.7.
40 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The limits of the zone are detailed as follows. At one end, it forms the exposed sloping part of the
spill through embankment. At the other end, at the top, it extends a distance of 2h from the rear face
of the bridge abutment headstock; at the bottom at embankment foundation level, it extends a distance
of h/2 from this rear face.
(For the purpose of this Clause, the height “h” is the distance between the soffit of the headstock and
the embankment foundation level. Where excavation is required for foundation improvement, the
height “h” is measured to the base of the excavation.)
2h
Notes: h /2
(1)
Dashed line above indicates location of batter behind
abutment and extent of fill complying with Clause 5.2.3, if Natural Ground Level
abutment fill is placed prior to that for adjoining embankment.
(2)
Select Fill placed adjacent to bridge abutment – refer to
Clause 5.5.
(3)
Provide a minimum 0.75 m wide bench for access and
working area during bridge bearing maintenance, unless
shown otherwise on the Drawings.
Place the fill material in layers not exceeding 300 mm in thickness when compacted, and compact to
the relevant requirement specified in Table R44.7 under Clause 7.2.
Rock fill is material composed of hard, sound, durable rock with only a small amount of fine particles
(refer also to the definition for rockfill in Clause 1.3).
Material for rock fill must conform to the properties specified in Table R44.4. The constituent
particles must be of uniform strength and soundness.
Ed 6 / Rev 0 41
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Property Requirement
Maximum particle dimension 300 mm
Percentage passing:
100 mm AS sieve 0 – 20%
19.0 mm AS sieve 0 – 10%
1.18 mm AS sieve 0 – 5%
Percentage of +100 mm fraction with
Is(50) < Annexure R44/A2.2 specified value 10% (max)
Wet/Dry Strength Variation Annexure R44/A2.2
To produce site won rock fill material meeting the grading and rock strength specified, you may need
to adjust your working methods, including screening and (where necessary) secondary processing,
during excavation of cuttings.
Where the site won material does not meet the requirements for rock fill, break down the material
further into finer particles, or have additional fines incorporated, for use as earth fill in accordance
with Clause 5.2.1.
Nominate to the Principal the proposed areas of rock fill. Unless shown otherwise on the Drawings,
do not place rock fill in areas where earth fill has previously been placed.
Shape and treat the foundations under rock fill to maintain drainage and to ensure that erosion of the
foundation will not occur. Where shown on the Drawings or directed by the Principal, place a
geotextile conforming to TfNSW R63 over the foundation area prior to placing the rock fill.
Place the rock fill material in layers not exceeding 550 mm in thickness when compacted, and place
and spread the material in such manner as to avoid segregation and contamination with foreign
material.
Do not dump rock against the columns or retaining walls but build it up evenly by hand placing around
or against such structures.
Compact the rock fill using the nominated compaction procedure, developed in accordance with
Clause 7.4.2.
If you elect to place earth fill in some or all of the nominated rock fill locations, and a surplus of rock,
capable of being processed for use as rock fill, is later found to exist, then treat the surplus by:
(a) processing the material for use as earth fill; or
(b) removing the earth fill, and replacing it with the surplus rock as rock fill, at your own cost.
42 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Place a rock capping layer, composed of graded rock fill conforming to the properties specified in
Table R44.5, with a completed thickness as specified in Annexure R44/A4, immediately above the
completed rock fill embankment.
Property Requirement
Maximum particle dimension 150 mm
Percentage passing:
19.0 mm AS sieve 0 – 15%
1.18 mm AS sieve 0 – 5%
Percentage of +19.0 mm fraction with
Is(50) < Annexure R44/A2.2 specified value 10% (max)
Wet/Dry Strength Variation Annexure R44/A2.2
Place and spread the capping layer material in such manner as to avoid segregation and contamination
with foreign material. Compact the capping layer using the nominated compaction procedure,
developed in accordance with Clause 7.4.2.
Place a geotextile conforming to TfNSW R63 as separation between the rock capping layer and any
overlying layer of earth fill.
Do not place the rock capping layer within 400 mm of the underside of the Selected Material Zone.
Increase this minimum distance to 800 mm, where safety barrier posts, subsurface drainage or services
are to be installed.
Where shown on the Drawings, provide a rock facing of clean, hard, durable rock over embankment
batters (including embankments at bridge structures).
Program and manage the Works such that sufficient hard and durable rock of the specified dimensions
is available when required.
You may elect, with the approval of the Principal, to place surplus rock conforming to the
requirements in Clause 5.4.2 as rock facing on embankment batters which are not shown on the
Drawings to have rock facing.
Rock used for rock facing must have a minimum dimension of 500 mm, with Point Load Strength
Index (Is(50)) as determined by Test Method TfNSW T223, and Wet/Dry Strength Variation meeting
the respective requirements specified in Annexure R44/A2.2.
Ed 6 / Rev 0 43
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Build up the rock facing in layers just ahead of each layer of fill. Place the rock oriented such that the
face with its least dimension is vertical, and mechanical interlock between the larger stones occurs.
Provide a geotextile conforming to TfNSW R63 as separation between the earth fill material and the
rock facing.
Fill the space between larger rocks in the rock facing and adjacent fill material with progressively
smaller rocks to form a graded filter which prevents the leaching out of fines from the fill material but
which does not overfill the voids between larger rocks, or cause the larger rocks to lose contact with
one another.
Remove any excess of fine material surrounding any rock placed within the rock facing by removing
the rock, removing the excess fine material and re-placing the rock.
Exercise extreme caution whilst placing the rock facing. Where embankment material is placed in the
formation above other roads in use, place the outer rock layer in such a manner as to prevent spillage
down the batter. Implement measures to prevent any rock being dislodged and allowed to roll down
on to any adjacent roadway or track in use.
5.4.4 Payment
Payment for the rock facing will be made under Pay Item R44P2. Payment for the geotextile will be
made under Pay Item R44P7.5(a).
5.5.1 General
Place Select Fill adjacent to structures to the details shown on the Drawings.
Where such details are not shown on the Drawings, place Select Fill adjacent to structures in
accordance with Clauses 5.5.2 to 5.5.4.
Outside of the zones of Select Fill material, place fill in accordance with Clauses 5.2 and 6.1.
Place Select Fill adjacent to retaining walls and bridge abutments of the material type and to the extent
required in accordance with Specification TfNSW B30.
Place Select Fill adjacent to culverts and other drainage structures of the material type and to the
extent required in accordance with TfNSW R11.
Place fill for reinforced soil walls of the material type and to the extent required in accordance with
Specification TfNSW R58 or TfNSW R59 as applicable.
44 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
6 STRUCTURAL TREATMENTS
Construct the Upper Zone of Formation, including the Selected Material Zone (see Figures R44.1(a),
R44.1(b), R44.6(a) and R44.6(b)), to the thickness specified in Annexure R44/A4, using materials
conforming to the requirements specified in Clause 2.8.
Unless otherwise specified, do not import material for the Works until all material of suitable quality
available from cuttings within the Site has been placed or has been allocated to be placed in the
formation.
HOLD POINT
Process Held: Delivery of site won and imported material for Upper Zone of Formation.
Submission Details: Proposed source locations, quantities and types of material, and verification
of conformity. If imported, verification that all possible sources of the
material within the Site have been exhausted or allocated for placing.
Release of Hold Point: The Principal will consider the submitted details and may inspect the source
and stockpiles of material prior to authorising the release of the Hold Point.
Before placing any imported Upper Zone Material (including Selected Material), carry out a survey (if
so required) of the existing surface in accordance with Clause 1.6.1 to be able to later determine the
compacted volume of imported Selected Material placed in the Works.
When placing the material, conform to the moisture content and compaction requirements in Clause 7.
Where so specified in Annexure R44/A6, extend the Upper Zone of Formation layer into the medians.
Construct a Selected Material Zone (see Figures R44.1(a), R44.1(b), R44.6(a) and R44.6(b)) to the
thickness specified in Annexure R44/A4, using materials conforming to the requirements specified in
Clause 2.8.5.
Where so specified in Annexure R44/A2.1, the material placed in the upper layer of the Selected
Material Zone at any particular location must be from the same source, produced using the same
process and exhibit similar properties prior to any modification which may be required, as that placed
in the lower layer, at that same location.
Ed 6 / Rev 0 45
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
HOLD POINT
Process Held: Placement of each Lot of Selected Material Zone.
Submission Details: Test reports verifying conformity of each Lot of stockpiled material for use
in Selected Material Zone.
Release of Hold Point: The Principal will consider the submitted documents prior to authorising the
release of the Hold Point.
Place and compact materials for the Selected Material Zone in layers of compacted thickness not
exceeding 150 mm, unless specified otherwise in Annexure R44/A4.
The placed Selected Material Zone must be homogeneous and free from patches containing segregated
stone or excess fines. If the placement method used is considered to result in excessive breakdown of
the material, the Principal can request additional testing to verify conformity with the requirements of
Clause 2.8.5 and Annexure R44/A2.2 following placement of each Lot.
Trim the Selected Material Zone to meet the level tolerances specified in Clause 7.7.1. As part of the
trimming operation, prepare the surface in accordance with TfNSW T199 for deflection monitoring as
required in Clause 7.6.
HOLD POINT
Process Held: Covering of each Lot of Selected Material Zone.
Submission Details: Verification of conformity of each Lot of Selected Material Zone placed,
with relevant test and survey reports.
Release of Hold Point: The Principal will consider the submitted documents prior to authorising the
release of the Hold Point.
6.2 VERGES
Construct verges as shown on the Drawings, using material conforming to the requirements specified
in Clause 2.8.
Unless otherwise specified, do not import material for the Works until all material of suitable quality
available from cuttings within the Site has been placed or has been allocated to be placed in the
formation.
HOLD POINT
Process Held: Delivery of site won and imported material for the verges.
Submission Details: Proposed source locations, quantities and type of material, and verification
of conformity. If imported, verification that all possible sources of the
material within the Site have been exhausted or allocated for placing.
Release of Hold Point: The Principal will consider the submitted details and may inspect the source
and stockpiles of material prior to authorising the release of the Hold Point.
46 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Before placing any verge material (and not just imported verge material), carry out a survey of the
existing surface in accordance with Clause 1.6.1 to be able to later determine the compacted volume of
verge material placed in the Works.
When placing the material, conform to the moisture content and compaction requirements specified in
Clause 7.
Place and compact the verge in layers of compacted thickness as specified in Annexure R44/A4. You
may compact adjacent to a concrete pavement not earlier than 10 days after concrete placement, or
immediately after completion of joint sealing, whichever is the later.
The placed verges must be homogeneous and free from patches containing segregated stone or excess
fines.
Trim the verge to meet the level tolerances specified in Clause 7.7.1.
7 CONFORMITY REQUIREMENTS
Maintain the moisture content of earth fill, at the time of compaction, to within the range specified in
Annexure R44/A5 at all locations within the Lot. Adjust the moisture content as required to enable the
specified compaction to be achieved.
Include a procedure for monitoring and adjusting of moisture content in the EARTHWORKS PLAN
(refer to item (k) in Clause 1.5.1).
Determine field moisture content in accordance with Test Methods TfNSW T120, TfNSW T121 or
TfNSW T180. Only use TfNSW T121 and TfNSW T180 where results have previously been checked
against those of TfNSW T120 for the range of materials being compacted, using Test Method
TfNSW T2105.
Do not compact material that has been placed with a moisture content greater than that specified
in Annexure R44/A5, or has become wetted up after placement, until it has dried out to the
extent that the moisture content is within the specified range. To assist with drying, you may
use aeration or, where approved by the Principal, hydrated lime or quicklime complying with
Specification TfNSW 3211, at your own cost.
Ed 6 / Rev 0 47
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Alternatively, you may remove the wet material to a stockpile site for drying out and later use as
fill material. Any cost of removal to stockpile, for drying out and later use, is to be included in
the rates generally.
If there is insufficient moisture in the material for it to be compacted as specified, add the
required amount of water. Apply the added water uniformly and mix it thoroughly with the
material until a homogeneous mixture is obtained. The cost of such wetting of the material will
be borne by you.
7.2 COMPACTION
7.2.1 Lot Definition
A Lot must comprise only areas of work that are essentially homogeneous. This occurs when material
origin and properties, moisture content during compaction, compaction technique, response to
compaction, state of underlying materials and general appearance, are substantially alike.
Exclude from the Lot areas which fail to meet these conditions, and test such areas separately as one or
more additional Lots.
Include in the PROJECT QUALITY PLAN procedures for identification and inspection of Lots for
homogeneity in accordance with TfNSW Q.
Select the sample locations in accordance with TfNSW Q. Provide a smooth surface at each sampling
location for the purpose of obtaining samples.
At each sample location selected for determination of relative compaction, carry out a field density test
and obtain a sample for laboratory testing to determine the maximum density and field moisture
content.
Carry out field (insitu) density tests in accordance with either Test Methods TfNSW T173 using a
nuclear gauge, TfNSW T119 using the sand replacement method or TfNSW T165 using the fixed
volume extractive method. The test methods used must conform to that specified in Table R44.6.
48 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Table R44.6 – Applicable Test Methods for Determining Field Density and Relative Compaction
Unless otherwise specified, do not use TfNSW T173 (nuclear gauge) for insitu density tests if the layer
thickness exceeds 300 mm.
Conduct all tests within a particular Lot using only a single Test Method. Do not combine results from
different Test Methods in a statistical calculation to assess conformity of a particular Lot.
Irrespective of the Test Method used to determine the insitu density, determine also the proportion and
density of oversize material retained on the 37.5 mm AS sieve in the sample, for adjustment of the
laboratory maximum density, in accordance with the procedure described in Test Method
TfNSW T105 Appendix A Part A.5.
Determine the laboratory maximum density using Test Methods TfNSW T111, TfNSW T112,
TfNSW T162, TfNSW T164 or TfNSW T166, as appropriate.
Determine by calculation the minimum (lower limit) characteristic value of relative compaction in
accordance with TfNSW Q. Round off the individual relative compaction value, and the characteristic
relative compaction value, to the nearest 0.1%.
7.2.4 Conformity
Conformity of a Lot is achieved if the calculated minimum characteristic value of relative compaction
of that Lot is not less than the corresponding specified value in Table R44.7.
Ed 6 / Rev 0 49
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Minimum Characteristic
Lot Location Value of Relative
Compaction
(a) Earth mounds.
90.0%
Spoil stockpiles.
(b) (i) Each layer of material replacing unsuitable material under embankments.
95.0%
(ii) Foundation treatments under embankments (except Type E2 and Type E5).
(c) Each layer of material replacing unsuitable material in cuttings.
98.0%
Foundation treatments in cuttings.
(d) (i) Each layer of material placed in formation up to underside of Selected Material
Zone, including that in Shallow Embankments and Cut/Fill Transition Zone.
98.0%
(ii) Each layer of material in verges, or within medians up to level at which topsoil is
placed.
(e) Each layer of material placed in spill through bridge abutment zone. 100.0%
(f) Each layer of material placed in Selected Material Zone. 102.0%
(g) Other areas not specifically mentioned herein. 98.0%
Where conformity of Lot is not achieved, either re-work the Lot, or re-check the Lot for homogeneity
and/or re-determine the Lot boundaries, and subsequently re-nominate the Lot (or parts thereof) for
further compaction testing.
Detail in the PROJECT QUALITY PLAN the method of repairing the test holes.
7.4.1 General
Conformity of rock fill placing is based on compliance with your nominated compaction procedure,
developed and verified in accordance with Clause 7.4.2 and proof rolling in accordance with
Clause 7.5.
All costs associated with the development and verification of the compaction procedure, and the
utilisation of the nominated compaction procedure on rock fill layers, is to be included in the rate for
general earthworks, for payment under Pay Item R44P2.
Through construction and testing of some trial sections, develop a compaction procedure using
parameters such as material characteristics including grading, blending and moisture conditioning,
layer thickness and rolling procedure.
The compaction procedure must include the use of at least one vibrating roller. If the procedure
includes insitu modification (e.g. with a grid roller or similar), then determine the grading of the
material after rolling and compaction.
50 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The length of a trial section must not exceed 50 m, and the width must be greater than or equal to two
times the maximum roller drum width. Do not select areas as trial sections that are within 1.5 m of the
underside of the Selected Material Zone.
Verify the compaction procedure by using results from two separate trial sections which are not
contiguous or constructed concurrently.
WITNESS POINT
Process to be Witnessed: Construction of each trial section of rock fill.
Submission Details: Notification of the location, date and time of the trial section construction,
with details of your compaction procedure, including:
(a) material(s) to be used and their specification(s), including any moisture
conditioning prior to and during rolling;
(b) plant type(s) and their specification(s);
(c) number of roller passes;
(d) maximum and minimum roller speed and frequency of vibration;
at least three working days prior.
If the trial section is for verification of the procedure carried out on previous
trial section(s), submit also:
(i) test results of all previous trial section(s);
(ii) in-process testing regime and proof of embankment stability, with no
remaining internal settlement of the previous trial section(s).
HOLD POINT
Process Held: Construction of remaining sections of rock fill.
Submission Details: Verification of conformity of previous trial sections, including test results
and survey reports, and details of nominated compaction procedure.
Release of Hold Point: The Principal will consider the submitted documents, prior to authorising the
release of the Hold Point.
Where in-process testing of the placed rock fill using the nominated compaction procedure reveals
nonconforming results, cease all placing and compaction, and re-develop the procedure using new trial
sections in accordance with the above, or break down and/or sort rock material to achieve an earth fill
in accordance with Clause 5.2.
The above Hold Point applies to the re-developed procedure prior to recommencement of placement
and compaction operations.
Ed 6 / Rev 0 51
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
All Lots within the Selected Material Zone (whether in cuttings, embankments, shallow embankments
or cut/fill transitions) and all Lots in an embankment must be capable of withstanding proof rolling to
verify their stability.
Carry out proof rolling in accordance with Test Method TfNSW T198.
Unless otherwise specified, proof roll each layer within three days of compaction testing and moisture
conformity testing.
The moisture content of the compacted material being proof rolled must be within the range specified
in Annexure R44/A5.
Carry out proof rolling on all Lots within the Selected Material Zone and within 1.5 m below the
underside of the Selected Material Zone.
Where directed by the Principal, carry out proof rolling on all embankment Lots which are deeper than
1.5 m from the underside of the Selected Material Zone.
The proof rolling pattern must cover the full width and length of each Lot.
WITNESS POINT
Process to be Witnessed: Proof rolling of surface of any Lot.
Submission Details: Notification of the location, date and time of the proof rolling, and providing
verification that the subject layer or surface conforms in all respects except
for proof rolling, at least one working day prior.
7.5.3 Conformity
The surfaces when proof rolled must not exhibit visible deformation, rutting, or yielding and/or show
signs of distress or instability.
7.6.1 General
Carry out deflection testing using the Benkelman Beam in accordance with TfNSW T199.
When carrying out deflection testing by Benkelman Beam, conform to the grid sampling pattern
specified in TfNSW T199, and maximising the number of sampling points that can be accommodated
within the Lot. Where a minimum of 12 points cannot be obtained using this grid sampling pattern,
use a random pattern of at least 12 points over the Lot.
Unless otherwise specified, carry out deflection testing by Benkelman Beam within three days of
testing the Lot for compaction and moisture conformity. Except for reasons due to wet weather
conditions, any results of deflection testing which have been carried out later than three days after
compaction conformity testing will not be accepted.
52 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Carry out deflection testing by Benkelman Beam on the following areas, where so specified in
Annexure R44/A4:
(a) underside of the Selected Material Zone, except where a drainage layer lies immediately below
the Selected Material Zone, e.g. in Treatment Type C5;
(b) top of the Selected Material Zone.
Where a Selected Material Zone is not part of the Works, carry out deflection testing of the formation
at the level of the underside of pavement.
For the purpose of deflection testing with the Benkelman Beam, a Lot must consist of a continuous
length of formation and of at least a single lane width that is generally homogeneous with respect to
material and appearance. Mark the boundaries of each Lot such that they are clearly identifiable in the
field.
WITNESS POINT
Process to be Witnessed: Benkelman Beam testing of surface.
Submission Details: Notification of the location, date and time of the Benkelman Beam testing,
and providing results of any previous proof rolling, at least one working day
prior.
Determine the maximum deflection for each sampling point within the Lot, and their standard
deviation and coefficient of variation for each Lot, in accordance with TfNSW T199. Calculate the
maximum (upper limit) characteristic deflection (CD) for each Lot in accordance with T199.
7.6.5 Conformity
The Lot is conforming if the maximum (upper limit) characteristic deflection (CD) does not exceed the
value specified in Annexure R44/A4, and either the standard deviation does not exceed 0.2 mm or the
coefficient of variation does not exceed 25%.
HOLD POINT
Process Held: Placing each Lot of Selected Material Zone, or each Lot of pavement where
there is no Selected Material Zone.
Submission Details: Deflection test results, Survey Report of the finished surface and verification
of conformity of each Lot tested, at least three working days prior.
Release of Hold Point: The Principal will consider the submitted documents, and may direct further
action prior to authorising the release of the Hold Point.
Where conformity of Lot is not achieved, either re-work the Lot, or re-check the Lot for homogeneity
and/or re-determine the Lot boundaries, and subsequently re-nominate the Lot (or parts thereof) for
further deflection testing.
Ed 6 / Rev 0 53
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The finished surface levels of the various surfaces must conform to the tolerances specified in
Table R44.8.
Location Tolerance
(a) Designed Floor Level in cutting before foundation treatment:
(i) Type C1 - Loosen and recompact +10 mm / –40 mm
(ii) Type C3(I) - Working platform - stabilisation of insitu material +10 mm / –40 mm
(iii) Type C4 - Geotextile and geogrids +0 mm / –40 mm
(b) Foundation Level in cutting before foundation treatment:
(i) Type C2 - Excavation and backfill +10 mm / –40 mm
(ii) Type C3(II) - Working platform - imported stabilised material +10 mm / –40 mm
(iv) Type C5 - Drainage layer in:
- rock cutting +10 mm / –150 mm
- other than rock cutting +10 mm / –40 mm
(c) Foundation Level at Shallow Embankment and Cut/Fill Transition Zone +50 mm / –150 mm
(d) Floor of benches in cutting +50 mm / –50 mm
(e) Top of formation at underside of Selected Material Zone:
(i) where underlying layer is a drainage layer in a cutting +20 mm / –40 mm
(ii) all other cases +0 mm / –40 mm
(f) Top of lower layer of Selected Material Zone +10 mm / –40 mm
(g) Top of upper 150 mm layer of Selected Material Zone, or top of formation +0 mm / –20 mm
where there is no Selected Material Zone
(h) Surface of verges +0 mm / –20 mm
Note: Refer to Clause 1.3 and Figures R44.1(a) and R44.1(b) for definitions of “Designed Floor Level” and
“Foundation Level”.
7.7.2 Acceptance of Areas Below Level Tolerances (Where Overlying Pavement is Not
Part of Contract)
Where the overlying pavement is not part of the Contract, and the finished surface level of the top of
the Selected Material Zone is not higher than the upper limit of the tolerance specified in Table R44.8
(+0 mm), but is lower than the lower limit of the tolerance (–20 mm), the work may be accepted by the
Principal, under the following conditions:
(a) Deductions applied at the rate shown in Annexure R44/A4 for the volume that is outside the
lower limit of tolerance (–20 mm);
(b) Acceptance by the Principal of your method for determining the volume referred to in item (a)
above by survey and calculation, and the calculated volumes.
Notwithstanding the construction tolerances mentioned above, slope the surface of the medians so as
not to pond water.
54 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
7.8 DIMENSIONS
7.8.1 Cutting Batters
Batters in cuttings will generally require progressive flattening towards the bottom end of the cutting
owing to the presence of less stable material.
Completed batters in cuttings must conform to that shown on the Drawings, unless otherwise
authorised or re-determined by the Principal, and within the tolerances specified in Table R44.9.
Tolerance (mm)
Location
Slope 1H:1V or flatter Steeper than 1H:1V
At level of toe of batter +0 / –150 +0 / –200
Between level of toe of batter and 2 m above toe of
interpolate interpolate
batter
2 m above toe of batter and beyond +300 / –300 +300 / –600
Notes:
(1)
Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are measured
perpendicular to the plane of the slope.
(2)
Bench widths must not be less than those shown on the Drawings.
Round off the top edges of cutting batters to the dimensions shown on the Drawings unless otherwise
directed.
Completed batters of embankments must conform to that shown on the Drawings, unless otherwise
authorised or re-determined by the Principal, and within the tolerances shown in Table R44.10.
Tolerance (mm)
Location
Slope 1H:1V or flatter Steeper than 1H:1V
At level of top of formation/underside of pavement +0 / –150 +0 / –150
Between top of formation and 1 m below top of
+150 / –150 +150 / –150
formation
Beyond 1 m below top of formation +300 / –300 +300 / –300
Note:
(1)
Plus (+) is towards the roadway and minus (–) is away from the roadway. Tolerances are measured
perpendicular to the plane of the slope.
Notwithstanding the above, the edge of the formation at the level of the underside of the pavement
must not be nearer to the roadway than that shown on the Drawings.
Ed 6 / Rev 0 55
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Batter surfaces must not have undulations in the general plane of the batter outside of the tolerance
specified in Clause 7.9.3, and must be free of rills running down the face of the batter, except those
resulting from pre-splitting or line drilling boreholes (refer to Clause 4.5).
Treat the face of the batter where such treatment is shown on the Drawings.
Batter surfaces must not have undulations in the general plane of the batter outside of the tolerance
specified in Clause 7.9.3, and must be free of rills running down the face of the batter.
Undulations in the general plane of the batter must conform to the following tolerances:
(a) For a horizontal distance of up to 2 m from the edge of the shoulder (except areas where verges
are required), no point on the completed batter may vary from the specified slope line by more
than 35 mm when measured at right angles to the slope line;
(b) At distances greater than 2 m horizontally from the edge of the shoulder, no point on the
completed batter may vary from the specified slope line by more than 75 mm when measured at
right angles to the slope line.
56 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
A1 SURVEY
Refer to Clause 1.6.
Carry out the surveys listed in the table below. Where so specified, the survey must be carried out as a
joint survey in accordance with TfNSW G71.
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure R44/A1)
Delete whichever of the “Yes / No” options shown below that is not applicable.
Review the default values shown below for “Joint Survey”, and amend if appropriate. Prior to
completing the table, consult TfNSW Survey Section whether TfNSW survey resources are available
for undertaking the joint surveys shown in the table below.
Requirements
Joint Model
Clause Area To Be Surveyed
Survey File (1)
2.5.1 Surface of existing ground before commencing construction of Yes Yes / No
bridging layer where topsoil is not required to be removed
2.5.2 Surface at each topsoil stockpile location before commencing Yes Yes / No
stockpiling
2.5.3 Surface after stripping of topsoil Yes Yes / No
2.6.4 Surface before and after removal of unsuitable material Yes Yes / No
3.2, 7.7.1 Floor of cutting before placing material for foundation No Yes / No
treatment or formation
5.1.3, 6.1.1 Surface before and after placing imported material Yes Yes / No
6.1.2 Surface before placing Selected Material No Yes / No
6.2 Surface before placing verge material No Yes / No
7.7.1 Top of finished formation No Yes / No
7.8, 7.9 Completed batter in cutting and embankment prior to No Yes / No
topsoiling, vegetation or other treatments
Note:
(1)
If this requirement is “Yes”, the survey report must include an electronic file in a format suitable for creating
accurate models using standard TfNSW CADD software.
Ed 6 / Rev 0 57
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
A2 MATERIALS
A2.1 Sources
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure R44/A2)
Complete the table below by filling in the required details, and deleting whichever of the “Yes / No”
options shown below that is not applicable.
Where borrow areas or sources of imported material are to be specified, insert in the table below their
locations.
58 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
A2.2 Properties
Pre-treatment
Clause Material Type Criteria Test Method (1, 2)
Ed 6 / Rev 0 59
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
(4) When calculating CBR characteristic value, report values calculated to the nearest 1%.
(5) Refer to Clause 2.8.5.1.
If the site won Selected Material conforms to the specified requirements for the lower layer of the Selected Material Zone,
but has a CBR value less than that specified for the upper layer of the Selected Material Zone, the Contractor may
modify the Selected Material by mixing it with hydrated lime, or other binders approved by the Principal, to make it
conforming to the specified requirements of the upper layer.
The modified material must have a UCS of less than 1.5 MPa, when tested in accordance with TfNSW T131 using 7 days
accelerated curing, but must otherwise conform to the specified requirements of the upper layer.
If using hydrated lime as the binder, a suggested application rate is 1 to 2% by mass, but the Contractor must by
laboratory trials determine the appropriate application rate to be used. Do not use binders which are prone to give rise to
rapid or uneven strength gain or excessive shrinkage.
A3 FOUNDATION TREATMENT
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure R44/A3)
Complete the table below by filling in the required details, and deleting whichever of the “Yes / No /
NA” options shown below that is not applicable.
Review the default values shown below and amend if appropriate, taking into account the geotechnical
and the pavement design details for the project.
60 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure R44/A4)
Complete the table below by filling in the required details, and deleting whichever of the “Yes / No”
options shown below that is not applicable.
Review the default values shown below and amend if appropriate, taking into account the geotechnical
and the pavement design details for the project.
A5 MOISTURE CONTENT
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after customising Annexure A5)
Complete the table below by filling in the required details.
Ed 6 / Rev 0 61
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Review the default value of 60% – 90% moisture range shown below.
This default value of moisture range will generally provide a satisfactory result required for attaining
the specified compaction, but may be adjusted to reflect the material types and likely environmental
moisture conditions.
For clay soils in wet conditions, it may be preferable to raise the 90% limit and/or specify placement
in the core of fill embankments. For granular non-cohesive soils, it may be preferable to lower both
percentages.
Notes:
(1)
Material types above are project specific.
(2)
“Moisture Range” is expressed as the ratio of Field Moisture Content to Optimum Moisture Content at
standard compactive effort and is reported to the nearest 1%.
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after completing Annexure A6)
State in the table below any foundation treatment and/or structural treatment required in the medians
between carriageways.
If any foundation treatment is required in the median areas, insert the treatment type required (e.g.
Types C1 to C5, and E1 to E6) in the middle column.
For cut/fill transition treatment or structural treatment in medians, delete whichever of “Yes / No”
options that is not applicable.
A7 BLASTING
Refer to Clause 4.6.
62 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 63
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Where no specific pay items are provided for a particular item of work, the costs associated with that
item of work are to be included in the rates and prices generally for the Work Under the Contract.
Unless specified otherwise, a lump sum price for any of these items will not be accepted.
The rates include the cost of testing where such costs are not paid under Primary Testing.
The unit of measurement is the “cubic metre”, measured on the stockpile of topsoil, removed
and stockpiled in accordance with Clause 2.5. The volume is determined by survey or manual
measurement and hand calculation.
The rate is an average rate to cover the cost of removal, loading, handling, transporting and
stockpiling of all non-contaminated topsoil within the Site.
Payment for placing of topsoil for revegetation purposes is made under the relevant pay item in
TfNSW R178.
Pay Item R44P1.2 - Removal and Disposal Outside Site of Topsoil (Bank Volumes)
The unit of measurement is the “cubic metre”, measured as bank volume of excavation of
topsoil removed and disposed of outside the Site in accordance with Clause 2.5.1 items (c) and
(d). The volume is determined by survey or manual measurement and hand calculation.
The rate is an average rate to cover the cost of classification in accordance with EPA Waste
Classification Guidelines, removal, loading, handling, transporting and disposal outside the Site
of the topsoil, including tipping fees and any other disposal costs.
Where the topsoil is contaminated material and is treated and disposed of outside the Site in
accordance with Clause 2.7.2, payment is made under Pay Item R44P8.
The unit of measurement is the “cubic metre”, measured as bank volume of excavation.
64 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
or
(ii) the Foundation Level for Treatment Types C2, C3(II) and C5, and Shallow Embankments
and Cut/Fill Transition Zones.
before the removal of unsuitable material.
When measuring the total excavation volume for payment, do not include the volumes arising from:
(a) removal of unsuitable material which is paid under Pay Item R44P4;
(b) level or batter tolerances;
(c) material removed in hillside terracing (refer to Clause 3.4);
(d) excavations for drainage works (other than that for table drains and gutters) and utility
adjustment works, which is paid under TfNSW R11 and TfNSW G7 respectively.
The rate is an average rate to cover excavation in all types of material, processing of the excavated
material for use as fill material, placing and compaction of the fill material in embankments, or
disposal of surplus excavated material in other than embankments within the Site.
Ed 6 / Rev 0 65
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
(ii) additional cost for supply and placing of site won and imported material for Foundation
Treatment Types C2, E2, C5, E5, and E6 is paid under Pay Items R44P7.3, R44P7.4, R44P7.6,
R44P7.7 and R44P7.8 respectively;
(iii) additional cost for Foundation Treatment Types C3 and E3, involving stabilisation of insitu
material and imported stabilised material, is paid under the relevant pay items in TfNSW R50,
and Pay Item R44P3;
(iv) cost for supply and placing of imported or borrowed general fill material and Upper Zone
materials (other than Selected Material and verge material) is paid under Pay Item R44P3;
(v) additional cost for placing site won Selected Material and verge material is paid under Pay Items
R44P5.1 and R44P5.3 respectively, while the cost for supply and placing of imported Selected
Material and verge material is paid under Pay Item R44P5.2 and R44P5.4 respectively;
(vi) additional cost of disposal outside the Site of non-contaminated spoil is paid under Pay
Item R44P6;
(vii) additional cost for identification, treatment and disposal of contaminated material is paid under
Pay Item R44P8;
(viii) additional cost for placing of material in reinforced soil block is paid as an “extra over” under
TfNSW R58/R59;
(ix) cost for placing of site won Select Fill adjacent to structures is paid under the relevant pay items
in TfNSW B30, R11 and R58/R59 as applicable;
(x) payment for incorporation into embankments of surplus material from other works under the
Contract, is made under the relevant pay items in the associated specifications for those other
works.
Pay Item R44P3 - Imported or Borrowed Material (other than Selected Material,
Verge Material and Foundation Treatment Material)
The unit of measurement is the “cubic metre” of compacted volume of imported or borrowed material,
measured in place. The volume is determined by calculation from the Drawings or by survey.
The volume for payment includes imported or borrowed material for Foundation Treatment
Types C3(II) and E3(II). Stabilisation of the imported or borrowed material is paid under the relevant
pay item in TfNSW R50.
The volume for payment excludes imported or borrowed material for the following:
(a) Foundation Treatment Types C2, E2, C5 and E5 which are paid under Pay Items R44P7.3(b),
R44P7.4(b), R44P7.6(b) and R44P7.7(b) respectively;
(b) Selected Material and verge material, which are paid under Pay Items R44P5.2 and R44P5.4
respectively;
(c) Select Fill adjacent to structures, which is paid under the relevant pay items in TfNSW B30,
R11 and R58/R59 as applicable.
Payment will not be made for imported material used in embankment widening which have not been
authorised by the Principal, or wasted by you.
The rate covers all costs associated with supply, haulage, placing, compaction, and trimming of
imported or borrowed material placed in the formation, including any necessary pre-treatment such as
breaking down or blending material or drying out material containing excess moisture.
It also includes all costs associated with the opening up of the borrow area, excavation of material
from the borrow area, maintenance of the borrow area, and restoration of the borrow area.
66 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
This Pay Item refers only to unsuitable material as defined in Clause 1.3 and described in Clause 2.6.
The unit of measurement is the “cubic metre”, measured as bank volume of excavation. The quantity
is a Provisional quantity.
If the bank volume of excavation cannot be measured, the Principal will determine the conversion
factors to be applied to the loose volumes measured in haulage plant or in stockpile volumes in order
to calculate the bank volume of excavation for payment.
The rate covers all costs associated with the excavation of unsuitable material, temporary stockpiling,
drying out, haulage, compaction or other activity required under Clause 2.6 for the incorporation of
unsuitable material in embankments or all activities required for disposal within the Site in accordance
with Clause 2.7.1.
Placing and compaction of conforming material to replace the unsuitable material removed is paid
under Pay Item R44P2 if using site won material, or under Pay Item R44P3 if imported or borrowed
material is authorised for this purpose by the Principal.
Where the Principal directs that non-contaminated unsuitable material be disposed of outside the Site,
additional payment will be made under Pay Item R44P6.
Where the unsuitable material is contaminated material and requires identification, classification,
treatment and disposal outside the Site, additional payment will be made under Pay Item R44P8.
When the schedule of quantities under Pay Item R44P4 provides for ranges of provisional quantities,
the rates are applied successively, but not cumulatively, as the volume of unsuitable material increases
from one provisional quantity range to the next higher range.
Each rate is applied for all unsuitable material removed within each quantity range, irrespective of the
nature of the material removed.
The unit of measurement is the “cubic metre” of compacted volume of the Selected Material Zone and
verge.
For the purpose of determining the volume, the width, depth and length are taken as those shown on
the Drawings, and no account is taken of the allowable placement tolerances. Where additional areas
are directed by the Principal, the volume is determined by survey or manual measurement, and
calculation.
The rates cover all costs associated with the identification, winning (for site won material) or
purchasing (for imported material), processing (including blending or modification to meet the CBR
and PI requirements), stockpiling (including double handling to suit your construction staging),
haulage, placing, compaction and trimming of material in the Selected Material Zone and verge.
Where modification of the material is required for purposes other than only to meet specified CBR
requirements (refer to Clause 2.8.5.1), payment for the work is made under the relevant pay item in
TfNSW R50.
Ed 6 / Rev 0 67
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Where the material is obtained from excavations within the Site, the rate is an “extra over” rate
to cover any additional cost over and above those allowed for under Pay Item R44P2.
Where the material is imported (from outside the Site), the rate covers all relevant costs as stated
above (including the cost of any modification required to conform to TfNSW 3071).
Where the material is obtained from excavations within the Site, the rate is an “extra over” rate
to cover any additional cost over and above those costs allowed for under Pay Item R44P2.
Where the material is imported (from outside the Site), the rate covers all relevant costs as stated
above (including the cost of any modification required to conform to TfNSW 3071).
Pay Item R44P6 – Disposal Outside Site of Non-contaminated Spoil (other than Topsoil)
The unit of measurement is the “cubic metre”, measured as bank volume of excavation.
If the bank volume of excavation cannot be measured, the Principal will determine the conversion
factors to be applied to the loose volumes measured in haulage plant or in stockpiles in order to
calculate the bank volume of excavation for payment.
The rate is an average rate to cover all additional costs associated with the disposal outside the Site of
all types of non-contaminated material, except for topsoil. The rate includes the cost of classification
in accordance with EPA Waste Classification Guidelines.
Payment under this Pay Item R44P6 is additional to payment(s) made under R44P2 or R44P4.
Payment for disposal of non-contaminated topsoil outside the Site is made under Pay Item R44P1.2.
The quantity is determined by survey or manual measurement, and calculation. The quantity
measured excludes quantities resulting from over-excavation and changes to suit your
construction method.
The rate is an average rate to cover the cost of trimming the excavated floor of cutting,
loosening the floor of cutting, adjusting the moisture content, processing the material to achieve
the specified quality requirements, recompaction and trimming the surface after compaction.
68 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The quantity is determined by survey or manual measurement, and calculation. The quantity
measured excludes quantities resulting from over-clearing or over-excavation and changes to
suit your construction method.
The rate is an average rate to cover the cost of loosening the embankment foundation, terracing,
adjusting the moisture content, processing the material to achieve the specified quality
requirements, recompaction and trimming the surface after compaction.
The unit of measurement is the “cubic metre” of compacted volume, measured in place.
The quantity is determined by calculation using the measured area and specified thickness. The
quantity measured excludes quantities resulting from excess widening of the layer, wastage,
local depressions, settlement or changes to suit your construction method.
The rate covers all costs associated with the identification, selection, winning, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of site won material in
the backfill layer, over and above those costs allowed for under Pay Item R44P2.
The rate covers all costs associated with the identification, purchasing, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of imported material in
the backfill layer.
The unit of measurement is the “cubic metre” of compacted volume, measured in place.
The quantity is determined by survey or manual measurement, and calculation. The quantity
measured excludes quantities resulting from excess widening of the bridging layer, wastage and
changes to suit your construction method.
The rate allows for any bridging layer material that penetrates or settles below the level of the
underlying natural surface or stripped surface, and allows for a capping layer where a rock fill
bridging layer is overlain by earth fill.
Pay Item R44P7.4(a) – Treatment Type E2 – Bridging Layer – Site Won Material
The rate covers all costs associated with the identification, selection, winning, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage and placing of site won material in the bridging layer, over
and above those costs allowed for under Pay Item R44P2.
Ed 6 / Rev 0 69
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The rate covers all costs associated with the identification, purchasing, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage and placing of imported material in the bridging layer.
Pay Item R44P7.5 – Treatment Type C4 and Type E4 – Geotextile and Geogrid
The unit of measurement is the “square metre” of each type of geotextile or geogrid installed.
The quantity of geotextile or geogrid is determined using the width and length measured in
place. The quantity measured excludes the additional areas in the laps required to provide a
continuous length or width of geotextile or geogrid.
The rate covers all costs associated with the supply and placing of geotextile and geogrids in
earthworks, including use in rock fill, rock facing, rock capping and foundation treatments.
The unit of measurement is the “cubic metre” of compacted volume, measured in place.
The quantity is determined by calculation using the specified thickness and measured area. The
quantity measured excludes quantities resulting from excess widening of the layer, wastage,
local depressions, settlement, or changes to suit your construction method.
The rate allows for any drainage layer material that penetrates or settles below the level of the
underlying natural surface or stripped surface.
Pay Item R44P7.6(a) – Treatment Type C5 – Drainage Layer – Site Won Material
The rate covers all costs associated with the identification, selection, winning, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of site won material in
the drainage layer, over and above those costs allowed for under Pay Item R44P2.
The rate covers all costs associated with the identification, purchasing, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of imported material in
the drainage layer.
Excavation to Foundation Level for the drainage layer is paid for under Pay Item R44P2.
70 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
The unit of measurement is the “cubic metre” of compacted volume, measured in place.
The quantity is determined by calculation using the specified thickness and measured area. The
quantity measured excludes quantities resulting from excess widening of the layer, wastage,
local depressions, settlement, or changes to suit your construction method.
The rate allows for any drainage layer material that penetrates or settles below the level of the
underlying natural surface or stripped surface.
Pay Item R44P7.7(a) – Treatment Type E5 – Drainage Layer – Site Won Material
The rate covers all costs associated with the identification, selection, winning, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of site won material in
the drainage layer, over and above those costs allowed for under Pay Item R44P2.
The rate covers all costs associated with the identification, purchasing, processing
(including breaking down), stockpiling (including double handling to suit your
construction staging), haulage, placing, compaction and trimming of imported material in
the drainage layer.
Pay Item R44P7.8 – Treatment Type E6 – Earth Fill Foundation Treatment Layer
The unit of measurement is the “cubic metre” of compacted volume, measured in place.
The quantity is determined by survey or manual measurement, and calculation. The quantity
measured excludes changes to the design quantities resulting from excess widening of the earth
fill foundation treatment layer, wastage and changes to suit your construction method.
The rate covers all costs associated with the identification, selection, winning, processing
(including breaking down), stockpiling (including double handling to suit your construction
staging), haulage, placing, compacting and trimming of site won material in the earth fill
foundation treatment layer, over and above those costs allowed for under Pay Item R44P2.
The rate allows for any earth fill foundation treatment material that penetrates or settles below
the level of the underlying natural surface or stripped surface.
Ed 6 / Rev 0 71
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Pay Item R44P8 – Identification, Treatment and Disposal Outside Site of Contaminated
Material
NOTES TO TENDER DOCUMENTER: (Delete this boxed text after customising Pay Item R44P8)
Use Pay Item R44P8.1 where the presence of specific types of contaminated materials has been
identified during site investigation. Provide separate sub-Pay Items R44P8.1(a), R44P8.1(b), etc for
each type of identified contaminated material, together with descriptions of the contaminated material.
Use Pay Item R44P8.2 for any potential contaminated material which has not been identified at time
of tender.
The rate covers the additional costs of identification, classification in accordance with EPA Waste
Classification Guidelines, treatment, loading, haulage and disposal of contaminated material at
locations legally authorised to accept the contaminated material, whether the contaminated material is
topsoil, general fill or unsuitable material.
Payment under this Pay Item R44P8 is additional to payment made under Pay Items R44P1.2 or
R44P6 as applicable.
The quantity is determined using weighbridge dockets or invoices issued by the disposal
facility.
Payment will be made for the costs of the activities required by Clause 2.7.2 for any
contaminated material other than those provided in Pay Item R44P8.1 plus the provisional sum
margin added in accordance with Clause 55.4 of the General Conditions of Contract.
72 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Clause Description
G71 Notification of joint survey.
2.5.3, G71 Submission of Survey Report, and presentation of set out.
2.6.1 Presentation of area where unsuitable material has been removed, prior to backfilling.
3.2 Presentation of each Lot of floor of cutting, and submission of CBR and PI test results of
material in floor of cutting, if required.
3.3 Presentation of each Lot of embankment foundation after removal of topsoil, and
submission of CBR and PI test results of material in foundation, if required.
4.2 Presentation of cleaned cutting batter and bench/floor surfaces for geotechnical
inspection.
4.6.1, G36 Submission of Vibration and Airblast Management Sub-Plan and Building Condition
Inspection Reports.
4.6.2 Submission of blasting details for each blast.
6.1.1 Submission of details of Upper Zone materials (including Selected Material) to be
delivered. If imported, verification that all possible sources of material within the Site
have been exhausted or allocated for placing.
6.1.2 Submission of verification of conformity of stockpiled Selected Material.
6.1.2 Submission of verification of conformity of each Lot of Selected Material Zone placed,
with test and survey reports.
6.2 Submission of details of verge material to be delivered. If imported, verification that all
possible sources of material within the Site have been exhausted or allocated for placing.
7.4.2 Submission of verification of conformity of trial sections of rock fill carried out, and
details of nominated compaction procedure for remaining sections of rock fill.
7.6.5 Submission of deflection test results, Survey Report and verification of conformity of
each Lot tested.
Clause Description
7.4.2 Construction of each trial section of rock fill.
7.5.2 Proof rolling of surface of any Lot.
7.6.3 Benkelman Beam testing of Selected Material Zone.
Ed 6 / Rev 0 73
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
The following documents are a summary of documents that must be included in the PROJECT
QUALITY PLAN. Review the requirements of this Specification and other contract documents to
determine any additional documentation requirements.
74 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 75
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
8. SPOIL 2.7
8.1 Non-contaminated Materials 2.7.1
Each location
Obtain authorisation for disposal within Site 2.7.1 Authorised
within Site
Evidence of
Each location
Obtain authorisation for disposal outside Site 2.7.1 approvals,
outside Site
authorised
8.2 Contaminated Materials 2.7.2
Each source or
Submit method of and location for disposal 2.7.2 Submission G36
location
[Additional details to be inserted by Project Manager as
appropriate]
10. CUTTINGS 4
10.1 Preparation of Cutting Area
Remove topsoil and survey stripped surface -
refer item 7.1 of this table
10.2 Excavation 4.1
Loosen and break down material to meet requirements for
2.8.2, 2.9.1 Inspection
use as:
- Earth fill 5.2.1 5.2.1
- Rock fill 5.3.1 Table R44.4
- Drainage layer 3.2.5, 3.3.5 Table R44.2
- Bridging layer 3.3.2 3.3.2
- Rock capping layer 5.3.4 Table R44.5
- Rock facing 5.4.2 5.4.2
- Spill through bridge abutment fill (Type ST) material 2.8.7, 5.2.3 2.8.7
- Upper Zone Material other than Selected Material 2.8.4, 6.1.1 2.8.4
- Selected Material 2.8.5, 6.1.2 2.8.5
- Verge material 2.8.6, 6.2 2.8.6
5.5, B30, B30, R11,
- Select Fill adjacent to structures
R11, R58/R59 R58/R59
10.3 Cutting Batters 4.2
Table R44.9,
Conform to batter dimension and surface tolerances 7.8.1, 7.9.1 Survey Each batter
7.9.3
76 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 77
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
78 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 79
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
80 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 81
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
14. EMBANKMENTS 5
14.1 General Fill Material other than Type ST material 2.9, 5.2, 5.3
Conform to earth fill material properties: 5.2
No tree
- Free from tree stumps, roots and refuse 2.9.1 Inspection Each Lot
stumps, etc
Inspection,
- Maximum particle dimension 5.2.1 T280 if Each Lot Table R44.5
required
- Grading 5.2.1 T201 Each Lot Table R44.5
Conform to rock fill material properties: 5.3
Inspection,
- Maximum particle dimension 5.3.1 T280 if Each Lot Table R44.4
required
- Grading 5.3.1 T201 500 m3 Table R44.4
Annex Annex
- Point Load Strength Index of +100 mm fraction 5.3.1 10 per 50 m3
R44/A2.2 R44/A2.2
Annex Annex
- Wet/Dry Strength Variation 5.3.1 Each source
R44/A2.2 R44/A2.2
Conform to rock capping layer material properties: 5.3.4
Inspection,
- Maximum particle dimension 5.3.4 T280 if Each Lot Table R44.5
required
- Grading 5.3.4 T201 500 m3 Table 44.5
Annex
- Point Load Strength Index of +19 mm fraction 5.3.4 T223 10 per 50 m3
R44/A2.2
Annex
- Wet/Dry Strength Variation 5.3.4 T215 Each source
R44/A2.2
14.2 Earth Fill Embankment Construction 5.2
Place earth fill for embankment construction: 5.2.2
- Layer thickness 5.2.2 Measure Each Lot 5.2.2
- Lot homogeneity 7.2.1 Inspection Each Lot 7.2.1
T120, T121,
- Moisture content 7.1 Q Annex R44/A5
T180
T105, T111,
- Relative compaction 7.2 T119, T162, Q Table R44.7
T166, T173
14.3 Spill Through Bridge Abutment Fill (Type ST)
2.8.7
Material
Conform to Type ST material properties:
Annex Annex
- CBR 2.8.7 Each Lot
R44/A2.2 R44/A2.2
82 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 83
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
84 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
Ed 6 / Rev 0 85
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Total Mass of Lot Represented (tonnes) 1 – 500 501 – 1,000 1,001 – 2,000 2,001 – 4,000
Minimum Number of Samples per Lot 2 3 4 5
86 Ed 6 / Rev 0
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
Earthworks R44
TfNSW Specifications
Ed 6 / Rev 0 87
(TfNSW COPYRIGHT AND USE OF THIS DOCUMENT - Refer to the Foreword after the Table of Contents)
R44 Earthworks
Australian Standards
Other References
88 Ed 6 / Rev 0