SC U 29 2021
SC U 29 2021
Notification
The 19th July, 2021
Chapter — I General
1.2 These Regulations shall come into force from the date of publication in the Official
Gazette of Haryana.
1.3 These Regulations shall extend to the whole of the State of Haryana.
a) “Act” means the Electricity Act, 2003 (36 of 2003) and subsequent
amendments thereof;
f) “Consumer” means any person who is supplied with electricity for his own
use by a licensee or the Government or by any other person engaged in the
business of supplying electricity to the public under the Act or any other law
for the time being in force and includes any person whose premises are for the
time being connected for the purpose of receiving electricity with the works of
distribution licensee, the Government or such other person, as the case may
be;
h) “Contract demand” means the maximum demand kilovolt ampere (kVA) (within a
consumer’s sanctioned load) agreed to be supplied by the licensee and indicated in
the agreement executed between the licensee and the consumer. In case contract
demand is not mentioned in the agreement, the sanctioned load or connected load
as mentioned shall be considered;
j) “Electricity Supply Code” means the Electricity Supply Code specified by the
Commission under Section 50 of the Act and subsequent amendments/ re-
enactments thereof;
l) “Financial year” or “year” means the period beginning from first day of April in a
calendar year and ending with the thirty first day of the March of the next year;
u) “Obligated entity” means the entity mandated by the Commission under Clause
(e) of Subsection (1) of Section 86 of the Act to fulfil the Renewable Purchase
Obligation (RPO) and identified under the Haryana Electricity Regulatory
Commission (Terms and Conditions for determination of Tariff from Renewable
Energy Sources, Renewable Purchase Obligation and Renewable Energy Certificate)
Regulations, 2017 and subsequent amendments/re-enactments thereof;
v) “Premises” means rooftops or/and any area on the land, building or infrastructure
or part or combination thereof in respect of which a separate meter or metering
arrangements have been made by the licensee for supply of electricity to the
consumer;
w) “Prosumer” means a person who is consumer of electricity from the grid and may
also inject electricity into the grid for distribution licensee, using same point of
supply.
y) “Rooftop solar system” or “rooftop solar grid interactive system” means the
solar photovoltaic system installed in any part of a premises of an eligible consumer
located within the area of distribution licensee that uses solar irradiation for its
direct conversion into electricity;
aa) “Sanctioned load” means the load in kW (kilowatt), kVA (kilovolt ampere) or BHP
(Break Horse Power), agreed to be supplied by the licensee to the consumer;
ab) “Settlement period” means the period beginning from the first of April in a
calendar year and ending with the thirty first of March of the next year, i.e., same
as financial year;
Provided that the first settlement period for a newly commissioned roof top solar
system will be from the date of commissioning to March of next year.
(ac) “Solar meter” means a unidirectional energy meter installed as an integral part of
the net metering system at the point at which electricity generated by Solar Photo
Voltaic (SPV) system, is delivered to the main panel of an eligible consumer;
(ad) “Tariff order” in respect of a distribution licensee means the ARR/Tariff Order
issued by the Commission under section 62 of the Act for that distribution licensee
for the relevant year indicating the retail supply rates to be charged by the
distribution licensee from various categories of consumers for supply of electrical
energy and for other services;
(ae) “Third party owner” means a developer who installs, maintains and operates the
solar energy generation system on a rooftop but does not own the rooftop and enters
into a lease / commercial agreement with the rooftop owner, in such case of net
metering /gross metering arrangement owned by third party, the eligible consumer
only shall enter into an agreement with the Licensee.
Provided that any arrangement/contract between eligible consumers and third
party shall be confined to the agreeing/contracting parties and shall in no way
create any encumbrance whatsoever for the distribution licensee; Distribution
Licensee shall deal only with the eligible consumer only for all intents and purposes
under these Regulations.
2.2. All other words and expressions used in these Regulations although not specifically
defined herein above, but defined in the Act, shall have the same meaning as assigned
to them in the Act.
2.3. All other words and expressions used herein but not specifically defined in these
Regulations or in the Act but defined under any law passed by the Parliament/State
Legislation applicable to the electricity industry in the State shall have the meaning
assigned to them in such law.
Chapter — II
3.1. These Regulations shall apply to all the distribution licensee(s) and the eligible
Consumers/Prosumers of electricity of distribution licensees within the State of
Haryana.
3.2. The eligible consumer may install the rooftop solar system under net
metering/gross metering arrangement which:
3.3. The rooftop solar grid interactive system installed in a premises by an eligible
consumer of distribution licensee may be self-owned or third party owned under
RESCO model.
3.5. The facility of Net metering shall not be available to the consumer drawing power
under Open Access mechanism.
3.6. These Regulations do not preclude the right of any person or state authorities to
undertake rooftop solar projects of capacity above the limit of sanctioned
load/contracted demand through alternative mechanism i.e. other than
net/gross metering arrangement.
3.7. In case a person is applying to the distribution licensee(s) for new electricity
connection along with rooftop solar system under net metering/gross metering,
the distribution licensee(s) shall grant the connection subject to technical
feasibility and admissibility of installation of applied capacity of Roof Top Solar
System as per these regulations. The refusal of the said application shall only be
with a Speaking Order.
3.8. A rooftop solar grid interactive system that has not received technical feasibility
approval at the time of notification of these Regulations shall be required to be
set up under the provision of these Regulations.
4. General Principles:
4.1. The distribution licensee shall allow the eligible consumers, the facilities of net
metering/gross metering, in its area of supply on a non-discriminatory and first
come first served basis.
4.2. Any eligible consumer, who intends to discontinue net metering/gross metering
arrangement with the distribution licensee shall be allowed, subject to a written
notice to the distribution licensee made at least two months in advance. Any excess
energy generation remaining unadjusted as on the date of termination of the
agreement shall lapse and the same shall not be eligible for any payment or
adjustment.
Provided that the consumer shall be eligible to install rooftop solar system of
capacity as specified in these regulations.
Provided that the eligible consumer availing gross metering arrangement under
these Regulations shall not be allowed to apply for net metering arrangement
within the same premises
Provided that the eligible consumer availing net metering arrangement under
these Regulations shall not be allowed to apply for gross metering arrangement
within the same premises
Provided that the entire power generated from roof top installation shall be
injected into the distribution system of the Licensee at the interconnection point
if the eligible consumer opts for gross metering.
Provided further that in case of multiple applications from consumers fed through
a transformer for participation in the scheme, the connectivity with the rooftop
solar PV system shall be allowed on first come first serve basis.
5.3. The maximum rated capacity of rooftop solar system, to be installed by any
eligible consumer in his premises, shall not exceed its connected load/sanctioned
load in case of Low-Tension connection and contract demand in case of High-
Tension connection.
Provided that net metering to the consumer shall be allowed for the loads up to
500 kW or up to sanctioned load/contracted demand, whichever is lower and in
case of gross metering for the loads up to sanctioned load/contracted demand of the
eligible consumer.
Provided further that minimum rated capacity of rooftop solar system that can
be set up under net metering/gross metering arrangement shall not be less than
1 kW.
Provided also that a variation in the rated capacity of the system within a range
of five percent shall be allowed with reference to the capacity caps given above
Provided also that distribution licensee shall accept SPV Power as per useful life
of SPV System.
Chapter — III
In House Roof Top Solar Monitoring Mechanism
6.1. Every distribution licensee shall put in place in-House Roof Top Solar Monitoring
Mechanism, within one month from the date of notification of these Regulations
6.2. The guidelines for Constitution and functions of such in house Monitoring
Mechanism shall be as per the details attached at relevant Annexure of these
Regulations.
Chapter — IV
Interconnection with the Grid — Technical Standards and Safety Aspect
7.1. The voltage level for interconnection with the grid shall be as specified in the
Haryana Electricity Supply Code or the voltage level at which an eligible consumer
has been given supply by the distribution licensee. The cost of evacuation system
and interconnection of roof top solar PV system with the distribution system shall
be borne by the eligible consumer.
7.2. The interconnection of the rooftop solar system with the network of the distribution
licensee shall conform to the technical standards for connectivity of distributed
generation resources specified under the CEA (Technical Standards for Connectivity
of the Distributed Generation Resources) Regulations, 2013, and subsequent
amendments thereof.
7.3. The interconnection of the rooftop solar system with the distribution system of the
licensee shall also conform to the relevant provisions of the CEA (Measures Relating
to Safety and Electric Supply), Regulations, 2010, as amended from time to time.
7.4. The eligible consumer shall be responsible for safe operation, maintenance and
rectification of any defect of the rooftop solar system up to the point of net meter
or gross meter, beyond which the responsibility of safe operation, maintenance and
rectification of any defect in the system, including the net meter, shall be that of
the distribution licensee.
7.5. The distribution licensee shall have the right to disconnect the rooftop solar
system at anytime in the event of threat/damage from such rooftop solar system
to its distribution system to prevent any accident or damage, without any
notice.
The distribution licensee may call upon the consumer to rectify the defect within
a reasonable time.
7.6. The rooftop solar system must be capable of detecting an unintended islanding
condition. The system must have anti-islanding protection to prevent any
feeding of power into the grid, in case of failure of supply or grid failure. Applicable
IEC/IEEE technical standards shall be followed to test islanding prevention
measure for grid connected PV inverters.
7.7. The rooftop solar system must fulfill the technical requirements for grid
interconnection with the network of the distribution licensee and it shall be
separately grounded/earthed.
7.8. Any alternate source of supply shall be restricted to the consumer’s network and
the consumer shall be responsible to undertake adequate safety measures to
prevent battery power/diesel generator power/backup power extending to grid
on failure of distribution licensee’s grid supply.
7.9. Every rooftop solar system shall be equipped with automatic synchronization
device.
Provided that the rooftop solar system using inverter shall not be required to
have separate synchronizing device, if the same is inherently built into the
inverter.
7.10. The inverter shall have the features of filtering out harmonics and other
distortions before injecting the energy into the system of the distribution licensee.
The Total Voltage Harmonic Distortion (THD) shall be within the limits specified
in the Indian Electricity Grid Code (IEGC)/IEEE technical standards.
8. Technical Standards:
All technical and operational aspects of rooftop solar system shall conform to the
standard specified in the following Regulations/Codes, wherever applicable, as
amended from time to time:
a. The HERC (Haryana Grid Code) Regulations, 2009
g. The CEA (Measures relating to Safety and Electric Supply) Regulations, 2010;
and
9.1. The third party owned rooftop solar PV net metering or gross metering model may
consist of the developer or intermediaries leasing out solar PV system to
interested rooftop owners. The owner of the premises shall provide the rooftop and
engage a turnkey installer to design and install the system. The installers may
also offer integrated service of leasing, commissioning and maintenance of Solar
PV system to owners and guaranteeing standards of performance.
9.2. In the third party owned solar PV system, based on net metering, the electricity
generated from such plants/system shall be used to meet the eligible consumer’s
internal electricity needs up to the capacity allowed under the Regulations and
the excess generation shall be fed into the Grid (network of licensee) on Net
Metering basis, whereas, in case of gross metering, all the generation shall be fed
into the Grid (network of licensee) at the interconnection point.
9.3. The developer shall continue to be the owner of equipment in third party owned
system, to qualify for claiming depreciation on capital cost for the solar PV system
with associated direct tax benefits, if any.
Chapter — V
Metering, Energy Accounting, and Settlement
10. Metering
10.1. The metering system shall be as per CEA (Installation and Operation of Meters)
Regulations, 2006, as amended from time to time.
10.3. The net metering equipment (Bi-directional meters), the Solar meter and Gross
meter (unidirectional) shall be installed as per CEA Regulations and maintained
by the distribution licensee.
Provided that the eligible consumer may procure net meter/solar meter/gross
meter as per the technical specification of the distribution licensee and present
the same to the distribution licensee for testing and installation as per provisions
of the Electricity Supply Code. The location of the meter shall be as per CEA
Metering Regulations.
Provided further that for all rooftop solar systems of capacity 20 kW and above,
net meter, solar meter as well as gross meter shall be Automated Meter Reading
(AMR).
Provided also that a check meter shall be mandatory for roof top solar PV system
of rated capacity more than 50 kWp by the eligible consumer at his cost.
Provided also that in case the eligible consumer is under the ambit of TOD Tariff,
the meter compliant of recording time of day consumption/ generation shall be
installed.
10.4. The provisions of meter rentals shall be governed as per the Schedule of General
and Miscellaneous charges for Distribution and Transmission licensee, 2019 as
amended from time to time.
10.5. It shall be the distribution licensee’s responsibility to satisfy itself regarding the
accuracy of the meter(s) before it is installed and the distribution licensee shall
ensure that the meters have been duly tested and accordingly certified before
Installation.
10.6. In case of multiple rooftop solar plant within a premise, the Net Meter, Solar Meter
and Gross Meter shall be installed at such locations in the premises or outside
the premises of the eligible consumer or person as would enable easy and
unhindered access to the distribution licensee’s representative for meter reading.
10.7. The installed meters shall be jointly inspected and sealed by the distribution
licensee in the presence of the consumer as per the procedure laid down in HERC
Electricity Supply Code 2014 as amended time to time.
10.8. The meter reading taken by the distribution licensee shall form the basis of billing
and commercial settlement.
11.1. Energy Accounting: The energy accounting and settlement procedure for
consumers installing and operating rooftop solar system under net
metering/gross metering arrangement shall be as per the following procedure:
iii. Quantum of net electricity that has been billed for payment by the eligible
consumer;
c) In case the electricity injected by the rooftop solar system exceeds the
electricity consumed during the billing period, such excess injected electricity
shall be carried forward to the next billing period as electricity credit and may
be utilized in the following billing periods but within the same settlement
period;
d) In case the electricity supplied by the distribution licensee during any billing
period exceeds the electricity injected in the grid by the eligible consumer’s
rooftop solar system, the distribution licensee shall raise invoice for the net
electricity consumption after taking into account any electricity credit balance
remaining from the previous billing periods;
e) In case the eligible customer is under the ambit of time of day tariff, as
determined by the Commission, the electricity consumption in any time block
(e.g., peak hours, off-peak hours, etc.) shall be first compensated with the
electricity injection in the same time block. Any excess injection over
consumption in any time block in a billing cycle shall be carried forward to
the corresponding time block in the subsequent month for adjustment
purpose against energy supply at the lowest applicable Tariff across all the
slots.
f) The excess injected electricity measured in kilowatt hour (kWh) shall only be
utilized to offset the consumption measured in kWh and shall not be utilized
to compensate any other fee and charges imposed by the distribution licensee;
11.2. In case, consumer is being billed on kVAh reading basis, then kVAh shall be
computed for billing purpose as under:
i. Net Consumption (in kWh) = kWh (Import) - kWh (Export)
ii. Net Consumption (in kVAh) = Net Consumption (in kWh) divided by the
power factor maintained by the consumer during corresponding billing
period.
11.3. Regardless of availability of electricity credits with the eligible consumer during
any billing period, the consumer will continue to pay applicable charges such
as fixed/demand charges, Government levy, etc.
11.5. The distribution licensee shall continue to accept the solar power from the
rooftop solar system installed by the consumers as per these Regulations as
amended from time to time unless the solar power generator ceases to be a
consumer of the licensee or the rooftop solar system is abandoned earlier.
11.6. In case, an eligible consumer leaves the system, such consumer’s unused credits
for excess energy generated shall lapse and shall not be paid-for or adjusted in
any other manner by the distribution licensee.
ii. The case of rooftop solar PV system under gross metering arrangement, the
Licensee shall undertake energy accounting and settlement with the eligible
consumer only who is also the signatory of the interconnection agreement
with the Licensee.
iii. The energy accounting and settlement procedure for eligible consumers
installing and operating rooftop solar PV system under gross metering
arrangement shall be as per the following procedure:
a. For each billing period, the Licensee shall show the quantum of electricity
(in kWh) injected by the rooftop solar PV system installed at the premises of
the eligible consumer in the billing period.
b. The Distribution Licensee shall reimburse the eligible consumer for the
quantum of injected electricity by the rooftop solar PV system during the
billing period by way of ‘Solar Injection Compensation’.
Provided that the energy drawl by such eligible consumer/ prosumer and
energy injected by them under gross metering arrangement shall be
considered as two separate transaction and the payables for energy drawn
by the prosumer shall not be set off against his receivable for export of power
to the distribution licensee.
Provided further that for each unit (kWh) of energy generated and injected
into the grid by eligible consumer/prosumer shall be paid by the DISCOMs
at Rs. 3.11/- per kWh. The said rate has been determined by the
Commission for the solar power projects setup/ to be setup in Haryana
under PM Kusum Scheme wherein the cost of land/lease rental and higher
O & M expenses are included. Further in the tariff discovered for solar
energy through competitive bidding is continuously below Rs 3/- per unit.
Nonetheless, given the high cost of land in Haryana including its limited
availability, rooftop solar system can only drive the solarization in Haryana.
Hence, the tariff shall be Rs. 3.11/- per unit for five year without any
escalation despite market asymmetry. The Commission may revise/re-
determine the tariff after a period of five year from the notification of these
Regulations.
Provided that such delayed payment surcharge shall also be payable to the
eligible consumer in the same manner as per procedure specified for the
consumer of the Licensee in the HERC (Electricity Supply Code) Regulations
2014 and subsequent amendments thereof;
vi. The Distribution Licensee shall be responsible for billing of the electricity
injected by the rooftop solar PV system into the distribution system. The bills
prepared by the distribution license shall necessarily include the following:
Provided also that Licensee shall reimburse the eligible consumer of the solar
rooftop system, within the due date of the electricity bill of the consumer in
whose premises the rooftop solar PV system has been installed.
13.2. The distribution licensee shall undertake necessary action and replace the
meter as specified in the HERC (Electricity Supply Code) Regulations, 2014,
and amendments thereof.
13.3. During the period the meter remained deed or defective, the distribution
licensee may consider the energy generated by the rooftop solar for the solar
energy generation benefits by considering 19% CUF.
Provided that the defective meter shall be replaced within the prescribed time
period as mandated under HERC Supply Code Regulations, 2014 as amended
from time to time.
CHAPTER — VI
Application Process, Procedure, and Fee
a) The eligible consumer (applicant) may either apply online on the distribution
licensee website and/or HAREDA website (Format 1) or submit the application
in the prescribed form in the concerned subdivision. The application shall be
accompanied with non-refundable processing fee of Rs. One thousand.
e) The applicant shall remove all identified deficiencies within a period of 15 days
from the receipt of intimation (Format 2(a)) and intimate the distribution
licensee about the resolution of deficiencies (Format 2(b)) through email/post.
Provided that the DISCOM shall assess the resolution of deficiencies and
provide Letter of Approval (LoA) (Format 2) to the applicant upon satisfaction.
In case deficiencies are not removed in the said period, the application shall
stand cancelled.
f) In case the proposal is not found technically feasible, the same shall be
intimated to the applicant vide Format 2(c) within 22 days from the issuance
of the acknowledgement of application.
a) The applicant shall install rooftop solar system within 180 days from the receipt
of LoA (Format 2), as per the Standards/Codes specified under these
Regulations.
b) The aforesaid duration of 180 days is the maximum permissible time allowed
to the applicant for installation of rooftop solar, unless an extension is sought
in writing and allowed by the distribution licensee. However, in case no
extension is sought/allowed, the LoA shall become null and void. Further time
period covered under forced majeure conditions shall be dealt accordingly.
However, the applicant shall be at liberty to complete the installation process
before this period and approach the distribution licensee to initiate subsequent
steps.
14.4. Signing of Agreement
a) The applicant shall submit duly filled and signed net metering/gross metering
agreement using Format 3 to the distribution licensee(s) within 30 days of the
date of issuance of LoA.
b) The agreement shall be then signed by the distribution licensee within three
days of receipt of duly filled net metering/gross metering agreement from the
applicant
a) In case the applicant intends to procure meter from the distribution licensee,
the applicant shall submit the Intimation Form (Format 4) along with an
appropriate procurement fee to the distribution licensee. This shall be
intimated to the distribution licensee at least 30 days prior to the expected
date of submission of Work Completion Report (Format 5).
b) In case the applicant intends to procure meter on its own, the applicant shall
submit the procured meter along with a safety certificate and request form for
testing of meter (Format 4(a)) to the distribution licensee/test centers approved
by the distribution licensee, at least 30 days prior to the expected date of
submission of Work Completion Report (Format 5).
Provided that the consumer shall procure meter from the empaneled vendor
of the Distribution Licensee.
Provided that in case the Work Completion Report is not satisfactory, the
applicant shall resolve the discrepancies within seven days of receiving
the intimation from the appropriate authority, and resubmit the Work
Completion Report.
iii. The distribution licensee shall synchronize the system with the
distribution grid post verification of the Work Completion Report, install
meters, issue letter of synchronization, and Date of Commissioning (COD)
(Format 7) to the applicant.
i. The applicant shall submit the Work Completion Report (Format 5) to the
distribution licensee. In case the consumer is availing subsidy, the work
completion report is also to be shared with DISCOM.
ii. The distribution licensee shall undertake system inspection and safety
checks, as per applicable practices, within seven days of submission of
work completion report and undertake system synchronization.
iii. Provided that in case the Work Completion Report is not satisfactory, the
applicant shall resolve the discrepancies within seven days of receiving
the intimation from the appropriate authority, and resubmit the Work
Completion Report.
iv. The distribution licensee shall synchronize the system with the
distribution grid post verification of the Work Completion Report, install
meters, issue letter of synchronization, and Date of Commissioning (COD)
(Format 7) to the applicant.
DISCOM shall develop process for delivery of CFA to the applicable consumer
as per provisions of guidelines of MNRE with regard to installation of grid
connected roof top solar system in-vogue within three months of notification
of these Regulations, if the same is not put in place earlier and the applicable
consumer may approach it to avail CFA accordingly.
Chapter- VII
Other Provisions
Chapter- VIII
Miscellaneous
Sd/-
Secretary
Haryana Electricity Regulatory Commission
Annexure
c) Representative from the state nodal agency (SNA) (Project Officer) shall facilitate the
Technical and Process Committee on subsidy related and allied matters.
1.2. The officers of Monitoring Mechanism shall meet at least once in a month to take up the
functions assigned to it.
1.3. Functions
b) Appraise utility field officials about the changes in Policy and Regulatory provisions.
c) Develop web-based application system for ease in application filing, monitoring, and
tracking of the same.
d) Assist the billing department to incorporate adequate changes in its billing procedures
and develop online billing mechanism, if it does not exist already.
e) Form Technical and Process Committee to facilitate adequate framework for large
scale deployment of rooftop solar in the State.
g) Assist senior management and utility field officers to ease rooftop solar deployment.
iv. Total number of eligible consumers’ interconnections at the end of previous quarter;
vi. Total kWh received by the eligible consumer from the distribution licensee by month
and by quarter;
vii. Total kWh of solar energy generated by the eligible consumer by month and by
quarter;
viii. Total kWh delivered by the eligible consumer to the distribution licensee as per the
billing cycle and by quarter;
To
Date:
I / we herewith apply for a renewable energy Net/ Gross metering connection at the existing
service connection for RTSPV system. The details are provided below.
Address
5. Telephone number
6. Email Address
Details of the Existing Connection
7. Sanctioned Load/ Contracted
Demand (kW/ kVA/ HP)
8. Existing Connectivity Voltage
(Single Phase LT/ Three Phase
LT/ Three Phase HT)
S. No. Particulars Details of the Applicant
Details of the Proposed System
9. Capacity of RTSPV system
proposed to be connected (kW
Certification
I hereby state that the information provided above is best and true to my knowledge.
Place:
Note:
Only the person who has the service agreement with the appropriate DISCOM can avail the
RTSPV metering connection. If the agreement is not in the name of the Applicant, then the
Applicant must undertake Change of Tenancy with the appropriate DISCOM before
applying for metering connection.
Related Instructions and Terms & Conditions for Submission of Format 1
Instructions:
1. The filled-in application along with the necessary documents shall be submitted to concerned
Division office, DISCOM.
2. The application fees (non-refundable) of INR shall be payable in Cash / DD / Online
(NEFT/RTGS) / adjusted in the bill.
3. It is recommended that the Applicant select a system installer to install the RTSPV System
who is an empanelled contractor with Ministry of New and Renewable Energy (MNRE), Govt.
of India and/ or State Nodal Agency (SNA). The list of the same is available on the website of
MNRE and SNA
4. For RTSPV system size of more than ---------- kWp (as per the State’s regulations), the
inspecting officer of the Electrical Inspectorate, State Government shall inspect and issue a
Safety Certificate for commissioning.
5. For RTSPV system size of less than ---------------- kWp, the consumer will submit a safety
certificate issued by chartered engineers circulated vide circular no. , or any other
authority or self-certified, as per the regulations of the respective State.
1. The premise must have easy access for inspection, metering and other necessary checks.
2. The Applicant should be the owner of the property or an authorized person of the owner
organization or third party, as the case may be. If the property is in the name of the Company,
Trust, Co-operatives / partnership firms, then authorization shall be assigned to a person for
correspondence, paperwork, execution of various agreements, etc. The board / management
of the organization must authorize such person. In case of partnership firms, the authorized
signatory must be one of the partners, to whom written consent has been given by the other
partners.
3. The suggestive format for authorization certificate can be downloaded from the website or
from Consumer Information manual. This authorization certificate must be submitted to the
DISCOM office at the time of submitting the interconnection agreement signed by the
authorized person.
4. Application is not transferable.
5. DISCOM shall not be held responsible for any legal disputes between the Applicant and
RTSPV installer arising out of the contract.
6. The proposed capacity of the RTSPV system shall be in-line with the provisions of the
appropriate supply code and Regulations of HERC, as amended from time to time, for
permitting consumer connections.
Format 1(a)
Authorization Certificate
(To be submitted by the Applicant, in case applicable)
(For the application registered for installation of renewable energy system under net/ gross
metering program on behalf of a Trust / Committee / Housing Society etc.)
Date:
Pin:
wish to participate in the on-going net/gross metering plan for installation of RTSPV system
initiated by DISCOM and we accept all the terms and conditions mentioned in the application form
and any other formats laid down by DISCOM for this purpose.
Name of Officer
Signature
Seal
(Designation of Officer)
(To be specified at the time of signing)
(Acknowledgement Form will be a system generated mail and SMS. This will be issued immediately
once the Applicant has filled his/ her application online. The acknowledgement email/ SMS will contain
the information listed out above).
Format A
Technical Feasibility Report
(To be filled by Sub Divisional Engineer, DISCOM)
I hereby certify that the above said RTSPV System is technically feasible/ not feasible/ feasible with --
capacity.
Signature
Name of Authorized Person and Designation
Name of the DISCOM
Date
Format 2
Letter of Approval (LoA) for Consumer with respect to the Application for Net/ Gross Metering
and Grid Connectivity of Grid Connected Rooftop Solar PV System
(To be filled by the DISCOM)
Date
To
(Applicant’s name)
(Consumer No.)
With reference to above-mentioned Application number, after the technical feasibility (Format A
attached), approval is provided for installing RTSPV system of kW in your premises.
Following are the terms and conditions for installing the system:
1. It is recommended that you select an empanelled system installer of your choice to install the
RTSPV system. A list of empanelled installers of grid-connect PV systems by MNRE (Ministry
of New and Renewable Energy, Government of India) / DISCOM is available.
2. All components of RTSPV system must comply with applicable BIS/IEC standards. Please find
attached a list of standards to be complied with attached with this approval letter.
3. You must submit the copy of Manufacturers Test Certificates for all components for having
complied with relevant BIS/IEC standards of the selected model along with work completion
report.
4. In case of any changes required at your premises due to this proposed installation, these shall
be performed by you at your own cost.
5. The grid connectivity of the system shall be in accordance with the HERC applicable
Regulations any amendments thereof from time to time and shall confirm to requirements of
State Government’s Solar Policy.
6. In case the Applicant desires to purchase the Net/ Gross meter on its own (with prior permission
from DISCOM), the same shall be purchased from DISCOM approved vendors (as per
DISCOMs approved technical specifications). These meters shall be successfully tested from
DISCOM or their authorized laboratory. The DISCOM shall fix this meter on receiving system
test and safety certificate from CEI/EI (only applicable to RTSPV systems of more than xx kW/
kVA in size) during synchronization. For system size less than xx kWp/ kVA, the consumer
needs to submit safety certificate issued by a chartered engineer, or any other certificate,
applicable as per the State’s Regulations.
7. All the safety measures and standards of the installed system must comply with requirements
as stated in CEA/HERC Regulations and all standards referred to in those Regulations.
8. Please submit the following documents after installation of RTSPV system:
a. Inspection Report by Chief Electrical Inspector/ Electrical Inspector, State Government,
safety certificate issued by Chartered Engineer, as applicable;
b. Work Completion Report in provided format;
c. Test Certificate of Net/ Gross meter from DISCOM approved laboratory, if applicable;
d. Copy of signed Net/ Gross Metering Interconnection Agreement.
This approval is valid for 180 days from the date of issuance of letter and the RTSPV system is to be
commissioned within this period, failing which the approval will stand cancelled.
You may download all technical specifications, standards and other requirements of the solar rooftop
system from (link to website of documents download)
Signature of Officer
Date
Stamp
Format 2(a)
Intimation on deficiency scrutinized in the Application
(To be filled by DISCOM)
To
This is to inform you that we have received your above-mentioned Application and after the technical
feasibility of the RTSPV system (Format A attached), DISCOM have found that the Application is not
complete, because of the under-mentioned reason:
Please complete the above query within 15 days of receipt of this letter. In case you have not completed
the formality within the given period, your Application shall stand cancelled and paid fees, if any, shall
not be refunded.
Furthermore, it is found that due to above-mentioned constrains it is not feasible for the DISCOM to
provide connectivity at all/ up to the applied capacity (tick appropriate). However, the connectivity is
feasible for a reduced capacity of kW.
Signature of Officer
Date
Stamp
Format 2(b)
Response of Applicant for Removal of Deficiencies as intimated after the technical feasibility
(To be filled by Applicant)
To
Date:
With reference to the DISCOM’s letter (Form 2(a)), dated , regarding the
intimation on deficiencies found in the Application/ operational constraints to provide connectivity at the
applied capacity.
The Applicant will exercise the following option (tick the appropriate choice):
2. I accept the connectivity at reduced capacity as intimated by the DISCOM vide letter dated and
request the DISCOM to process the case.
3. I withdraw my Application.
Application Number:
Format 2(c)
Intimation for Non-Feasibility and Termination of the Application
(To be filled by DISCOM)
To
Date
This is to inform you that we have received your above-mentioned Application and after the
technical feasibility of the RTSPV system (Format A attached), DISCOM have found that the
Application is not feasible at this stage due to the following reasons:
The Application hereby stands terminated and the Application Fee shall be refunded within 7 days
from the date of issuance of this letter.
Signature of Officer
Date
Stamp
Format 3
Inter-connection agreement (Net/ Gross Metering Arrangement)
Between DISCOM and Applicant
AND
Distribution Licensee (herein after called as Licensee) and having its registered
office at (address) as
second party of the agreement.
Whereas, the eligible consumer has taken the responsibility to set up or facilitate the requisite
Photovoltaic system and injection system into the Licensee’s grid.
And whereas, the Licensee has verified the application and agrees to benefit the eligible consumer for
the electricity generated and as per conditions of this agreement and net/ gross metering Regulations.
1. Eligibility
1.1 Eligible consumer agrees that the standards and conditions of his Photovoltaic system meet the
norms for being integrated into grid/distribution system and that he shall maintain the system
accordingly for the duration of this agreement.
1.2 Eligible consumer agrees that for connection of his Photovoltaic system to Licensee’s distribution
system, he shall be bound by requirements of state Distribution Code/supply code and/or Licensee’s
conditionsof service and such connection shall not affect the performance of the grid with specified
reliability,security and quality as per the Central Electricity Authority (Grid Standard) Regulations
2010 as amended from time to time.
2.1 Eligible consumer agrees that the interconnection of the rooftop solar system with the network of
the licensee shall be made as per the technical standards for connectivity of distributed generation
resources specified under the Central Electricity Authority (Technical Standards for Connectivity of
the Distributed Generation Resources) Regulations, 2013 and subsequent amendments thereof.
2.2 Eligible consumer agrees that he has installed or will install, prior to connection of Photovoltaic
system to Licensee’s distribution system, an isolation device (both automatic and inbuilt within
inverter and external manual relays) and agrees for the Licensee to have access to and operation
of this, if required, for repair and maintenance of the distribution system.
2.3 Eligible consumer agrees that in case of a power outage on Licensee’s system, photovoltaic system
will shut down, unless special transfer and isolating capabilities have been installed on photovoltaic
system.
2.4 Eligible consumer agrees that Licensee will specify the interface/inter- connection point and
metering point.
2.5 Eligible consumer agrees to furnish all the data such as voltage, frequency, breaker, isolator position
in his system, as and when required by the Licensee. He may also try to provide facilities for online
transfer of the real time operational data.
3. Safety
3.1 Eligible consumer shall comply with the Central Electricity Authority (Measures Relating to Safety
and Electricity Supply) Regulations 2010.
3.2 Eligible consumer agrees that the design, installation, maintenance and operation of the photovoltaic
system are performed in a manner conducive to the safety of the photovoltaic system as well as the
Licensee’s distribution system.
3.3 Due to Licensee’s obligation to maintain a safe and reliable distribution system, eligible consumer
agrees that if it is determined by Licensee that eligible consumer’s photovoltaic system either causes
damage to and/or produces adverse effects affecting other distribution systems’ consumers or
Licensee’s assets, eligible consumer will have to disconnect photovoltaic system immediately from
the distribution system upon direction from the Licensee and correct the problem at his own expense
prior to a re-connection.
4.1 The eligible consumer agrees to obtain all the necessary approvals and clearances (environmental
and grid connected related) before connecting the photovoltaic system to the distribution system.
5.1 Licensee shall have access to metering equipment and disconnecting devices of photovoltaic
system, both automatic and manual, at all times.
5.2 In emergency or outage situation, where there is no access to the disconnecting devices, both
automatic and manual, such as a switch or breaker, Licensee may disconnect service to the
premises.
6. Liabilities
6.1 Eligible consumer and Licensee will indemnify each other for damages or adverse effects from either
party’s negligence or intentional misconduct in the connection and operation of photovoltaic system
or Licensee’s distribution system.
6.2 Licensee and eligible consumer will not be liable to each other for any loss of profits or revenues,
business interruption losses, loss of contract or loss of goodwill, or for indirect, consequential,
incidental or special damages, including, but not limited to, punitive or exemplary damages, whether
any of the said liability, loss or damages arise in contract, or otherwise.
6.3 Licensee shall not be liable for delivery or realization by eligible consumer for any fiscal or other
incentive provided by the central government.
7. Commercial Settlement
7.1 All the commercial settlement under this agreement shall follow the HERC applicable Net/ Gross
Metering Regulations.
8. Connection Costs
8.1 The eligible consumer shall bear all costs related to setting up of photovoltaic system including
metering and interconnection costs. The eligible consumer agrees to pay the actual cost of
modifications and upgrades to the distribution facilities required to connect photovoltaic system in
case it is required.
8.2 Costs of all interconnection equipment including the isolators, and meters. are also to be borne by
the eligible consumer.
9. Termination
9.1 The eligible consumer can terminate the agreement at any time by giving 30 days prior written notice
to the Licensee.
9.2 Licensee may terminate the agreement with 30 days prior written notice, if eligible consumer
breaches any term of this agreement and does not remedy the breach within 30 days of receiving
written notice from the Licensee of the breach.
9.3 Eligible consumer, upon termination of this agreement, shall disconnect forthwith the photovoltaic
system from Licensee’s distribution system.
To,
(Concerned Authority)
(Name of the DISCOM)
(Date)
Ref: Application No. dated
Dear Sir,
With reference to above- mentioned Application number and receiving the Letter of Approval after the
technical feasibility, I/we intend to install KWp of RTSPV system vide letter No dated
. In this regards, I/we request DISCOM to provide a meter of class for RTSPV
installation. The meter shall be as per the Net/ Gross metering clause in Solar Rooftop Policy/Guidelines...
I/We agree to pay fee of INR - as mentioned in DISCOM website via online mode/DD
/ cheque .
Name of Consumer/Sign
1. Net/Gross meter of class is available/ not available (tick (✔) appropriate) with DISCOM.
2. Appropriate meter will be sent by DISCOM test lab and shall be dispatched on the day of final
check and synchronization of RTSPV system with the DISCOM’s grid.
3. The DISCOM will issue test certificate to consumer prior to final checks and synchronization of the
system. The Consumer has to submit test certificate along with Work Completion Report
Signature of Officer
Date
Stamp
Note: -
a) Applicant must bring a copy of Letter of Approval.
b) In case meter is not available with DISCOM it can be procured from external agency
c) If meter is procured from outside agency, a letter intimating Meter No., Class and other
specifications described as per CEA regulations, - shall be submitted to the DISCOM.
Format 4(a)
Request for Meter Testing
(To be filled by Applicant)
Date:
To
(Concerned Authority)
(Name of the DISCOM)
Dear Sir,
With reference to above-mentioned Application number and receiving the Letter of Approval after the
technical feasibility, I/we intend to install KWp of RTSPV system vide letter No dated
. In this regards, I/we have procured the meter from ------------------- --.
As per the clause of meter testing of Solar Rooftop Policy/Guidelines, I
request DISCOM to kindly test meter of specification --------------------------------------------------- --.
I/We agree to pay fee of INR as mentioned by the DISCOM for testing of meter through online
mode/ DD / cheque .
Name of Consumer/Signature
Application number
Format 4(b)
Intimation regarding Completion of Testing of Meter for Installation with RTSPV System
(To be filled by DISCOM)
Date
Dear Sir,
With reference to the above-mentioned Application number and your letter dated ,
regarding testing of meter, hereby inform you that your meter with specification
is tested. The same will be installed after the synchronization check of the
system.
Signature of Officer
Date
Stamp
Format 5
Work Completion Report
(To be submitted by the Applicant)
To,
Dear Sir,
4. No. of Modules
5. Total Capacity (kWp)
6. Date of Installation
42. Capacity
45. CT Ratio
Date: Date:
Enclosures:
To
Date:
This is in reference to your Application number , it is hereby inform you that this office has
received your work completion report for the installed RTSPV system. Subsequent to that Grid
Synchronization Check of the RTSPV system (Format B attached) installed on the roof of your premises
, was done.
After incorporating the above-mentioned queries, please inform within 15 days from the receipt of this
letter. In case the revised report will not be submitted in the given period, your application shall be
cancelled and paid fees, if any, shall not be refunded.
Signature of Officer
Stamp
Enclosure: Format B
Format B
Guidelines for pre-commissioning check before and after connecting the RTSPV system with
DISCOM Network and steps for maintenance of network where such connectivity exists
(For DISCOMs internal purpose only)
To,
(Name of the Applicant)
(Consumer No)
Date
Dear Sir
Signature of Officer
Stamp
Annexure 1
Solar Rooftop Photovoltaic Systems Application Register
(To be filled by DISCOM and maintained at sub-division level)
Chief
Electrical
Sanc Inspector/
Proposed DT
tion Electrical Commissioni
Application RTSPV Detail Registration
Load/ Techn Inspector ng Approval
System s Date of Date of
S Cons Contr ical Approval Wait
Project Agreeme Commissi
Name of umer act Feasi (if Rem
N Consumer Num Dem
Capacity
bility
nt with oning list
(kWp) the applicable) &Synchro arks
o ber and Repor Rank
Name of DISCOM nize
(kW/ t
the Avail
kVA/ Nu Nu
Num Applicant able Num Dat
Date HP) Date mb mbe Date
ber Capa ber e
er r
city
( (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13) (14 (15) (16) (17) (18) (19)
1 )
)
1
2
3
4
5
6
7
8
9
1
0