Final Rate For NH-105 - Package-2
Final Rate For NH-105 - Package-2
(b) Loading & unloading form quarry to Mirzachauki wagon Rs. 89.9 371.3
(c) Loading & unloading form Mirzachauki wagon to Darbhanga wagon Rs. 89.9 371.3
(c) Loading & unloading Darbhanga wagon to site Rs. 89.9 371.3
Total Rs. 269.7 1113.9
(b) Loading & unloading form quarry to Sheikhpura wagon Rs. 89.9
(c) Loading & unloading form Sheikhpura wagon to Darbhanga wagon Rs. 89.9
(c) Loading & unloading Darbhanga wagon to site Rs. 89.9
Total Rs. 269.7
Stone chips /agg Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/ pipe Sand Steel Cement
Finished
Sl. No. Cl No. Item SOR Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
Girth from 300 mm to 600 mm
1 2.01 A (i) 419.70 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 419.70
2.01 A Girth from 600 mm to 900 mm
2 602.00 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 602.00
(ii)
2.01 A Girth from 900 mm to 1800 mm
3 1168.80 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 1168.80
(iii)
2.01 A Girth above 1800 mm
4 2291.60 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 2291.60
(iv)
Girth from 300 mm to 600 mm
5 2.01 B (i) 477.70 477.70
2.01 B Girth from 600 mm to 900 mm
6 639.10 639.10
(ii)
2.01 B Girth from 900 mm to 1800 mm
7 767.80 767.80
(iii)
2.01 B Girth above 1800 mm
8 953.70 953.70
(iv)
Clearing and Grubbing Road Land by
9 2.03 (i) A Mechanical Means - In area of light jungle 139578.00 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 139578.00
Stone chips /agg Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/ pipe Sand Steel Cement
Finished
Sl. No. Cl No. Item SOR Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
Excavation for Structures
18 3.13 (i) Ordinary soil 77.90 77.90
B. Mechanical Means (Depth upto 3 m)
Construction of Embankment with
19 3.16 174.90 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 174.90
Material obtained from Borrowpits
Construction of Embankment with
20 3.17 Material Deposited from Roadway Cutting 87.20 0.000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 87.20
28 5.01 A (i) Prime Coat over WMM 45.00 0.000 0.00 0.000 0.00 0.0000 0.00 0.0007 1384.50 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 45.97
29 5.02 (i) Tack Coat on Bitumeneous Surface 13.50 0.000 0.00 0.000 0.00 0.0000 0.00 0.0002 1384.50 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 13.78
Tack Coat on Granular Surface treated
30 5.02 (ii) 16.60 0.000 0.00 0.000 0.00 0.0000 0.00 0.0003 1384.50 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 17.02
with Primer
Dense Graded Bituminous Macadam
31 5.04 B 9302.00 1.441 1908.00 0.1039 1384.50 0.0441 123.42 12201.33
Grading - II
32 5.05 B Bituminous Concrete Grading - II 10594.40 1.459 1908.00 1592.99 0.1274 1384.50 0.0000 0.00 0.0446 123.42 0.000 0.00 0.0000 0.00 0.000 0.00 13560.06
With reinforcing elements of synthetic
33 7.5 (i) B 289.40 289.40
geogrids
34 7.5 (ii) Facing elements of RCC 1548.70 0.1620 1908.00 0.0810 2689.58 0.0070 569.70 0.0760 569.70 2122.94
35 8.01 (i) PCC M15 for Kerb Base 146.20 0.029 1908.00 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.015 2689.58 0.0000 0.00 0.009 569.70 245.65
36 8.01 (ii) PCC M20 for Kerb cast in situ 181.30 0.032 1908.00 0.016 2689.58 0.012 569.70 290.73
37 8.04 Retro-Refecltorised
38 (ii) 90 cm equilateral triangle 6206.80 0.110 1908.00 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.055 2689.58 0.0000 0.00 0.049 569.70 6591.98
39 (viii) 60 cm circular 5477.20 0.110 1908.00 0.000 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.055 2689.58 0.0000 0.00 0.049 569.70 5862.38
40 (x) 80 mm x 60 mm rectangular 7590.70 0.110 1908.00 0.000 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.055 2689.58 0.0000 0.00 0.049 569.70 7975.88
41 (xv) 90 cm high octagon 9639.80 0.110 1908.00 0.000 1592.99 0.00 0.00 0.00 0.055 2689.58 0.00 0.049 569.70 10024.98
Direction and Place Identification signs
42 8.05 13832.00 0.122 1908.00 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.061 2689.58 0.0000 0.00 0.055 569.70 14259.98
upto 0.9 sqm size board
Stone chips /agg Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/ pipe Sand Steel Cement
Finished
Sl. No. Cl No. Item SOR Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
Painting Two Coats on New Concrete
44 8.08 100.60 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 100.60
Surfaces
45 8.09 Printing On Steel Surface 88.40 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 88.40
Road Marking with Hot Applied
46 8.13 680.10 0.000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.000 0.00 680.10
Thermoplastic Compound
47 8.14 (i) 5th KM Post (precast) 3806.10 0.353 1908.00 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.176 2689.58 0.00368 569.70 0.108 569.70 5016.16
48 8.14 (ii) Oridinary KM Post (precast) 2170.90 0.242 1908.00 1592.99 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.121 2689.58 0.0019 569.70 0.074 569.70 3002.53
49 8.14 (iii) Hectometer stone (precast) 656.00 0.043 1908.00 0.022 2689.58 0.0020 569.70 0.013 569.70 804.83
Stone chips /agg Stone Metal Bitumen Bitumen Emulsion Lime/Filler/soil/ pipe Sand Steel Cement
Finished
Sl. No. Cl No. Item SOR Rate
Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
44 12.40 TMT Bar 70272.20 0.00 0.00 0.00 1908.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.422 569.70 70512.61
Mixed Seal Surface (MSS) 228.00 0.0270 0.00 0.0019 1384.50 230.63
61 13.3 plastering 137.60 0.0151 2689.58 0.0073 569.70 182.45
13.5 E
62 RCC M 20 957.90 0.9000 1908.00 0.4500 2689.58 0.3473 569.70 4083.28
(p) Case-
63 13.1 Brick Masonry 6647.20 500.00 0.86 0.2240 2689.58 0.1613 569.70 7772.40
64 508 Premix Surfacing 245.00 0.03 0.00 0.0022 1384.50 248.04
65 509 Seal Coat 70.00 0.01 0.00 0.0010 1384.50 71.36
37 12.3 Sand Pile 809.00 0.1963 149.58 838.36
MULTIPLYING FACTOR FOR ROAD ITEMS = 1.111
Stone metal or Brick Stone Boulder Aggregate / Stone chips Bitumen Sand Steel Cement Structural Steel
Sl. Finished
Cl No. Item SOR Rate
No. Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
1 12.01 B (i) Excavation for Structures 100.40 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 100.40
2 12.01 B (ii) Depth 3m to 6m 111.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 111.00
3 12.01 B (iii) Depth upto 6m 124.10 124.10
4 12.03 Sand filling in foundation 265.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 1.2000 149.58 0.0000 0.00 0.0000 0.00 0.0000 0.00 444.50
4 12.05 Brick masonry work (1:3) 6786.80 500.00 0.86 0.2688 2689.58 0.0967 569.70 7995.71
5 12.08 A (I) PCC M15 4345.00 0.0000 0.00 0.0000 0.00 0.900 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.2750 569.70 0.0000 0.00 7429.18
6 12.08 B PCC M20 4848.60 0.0000 0.00 0.0000 0.00 0.900 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.3440 569.70 0.0000 0.00 7972.09
6 12.08 G RCC M30 5351.60 0.0000 0.00 0.0000 0.00 0.900 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.4067 569.70 0.0000 0.00 8510.81
7 12.22 Steel Liner 103192.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 2689.58 0.0000 0.00 0.0000 0.00 1.0500 569.70 103790.19
8 12.25 Board Cast in Situ RCC M35 (Dia 1200m) 13948.60 0.0000 0.00 0.0000 0.00 1.0586 1908.00 0.0000 0.00 0.5293 2689.58 0.0000 0.00 0.4964 569.70 0.0000 0.00 17674.80
9 12.40 (C) (i) RCC Pile Cap M30 5222.90 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.4067 569.70 0.0000 0.00 8382.11
10 12.41 Levelling Course Pile Cap M15 4177.90 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.2750 569.70 0.0000 0.00 7262.08
11 12.42 HYSD Bar 69813.70 0.0000 0.00 0.0000 0.00 0.0000 1908.00 0.0000 0.00 0.0000 0.00 1.0500 569.70 0.0000 0.00 0.0000 0.00 70411.89
12 13.01 Brick masonry work (1:3) 6647.20 500.0000 0.86 0.2520 2689.58 0.1224 569.70 7825.56
13 13.03 Plastering with cement mortar (1:3 ) 137.60 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0151 2689.58 0.0000 0.00 0.0073 569.70 0.0000 0.00 182.45
14 13.05 A (p) PCC Grade M15 Height upto 5 M 4595.70 0.9000 1908.00 0.4500 2689.58 0.2750 569.70 7679.88
15 13.05 B (p) PCC Grade M20 Height upto 5 M 5128.30 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.3440 569.70 0.0000 0.00 8251.79
16 13.05 E (p) RCC Grade M20 Height upto 5 M 5126.30 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.3472 569.70 0.0000 0.00 8251.61
13.5 E
31 RCC M20 (SUBSTRUCTURE)-5-10 M 5312.70 0.0000 0.00 0.0000 0.00 0.0000 1908.00 0.0000 0.00 0.066 2689.58 0.0000 0.00 0.1250 569.70 0.0000 0.00 5560.42
(q)Case II
11 13.05 F (p) RCC Substructure M25 Height 5M 5613.86 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.4032 569.70 0.0000 0.00 8771.07
33 13.05 F (q) RCC Substructure M25 Height 5M-10M 5797.60 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.4032 569.70 0.0000 0.00 8954.81
34 13.05 F (r) RCC Substructure M25 Height above10M 6073.20 0.9000 1908.00 0.450 2689.58 0.4032 569.70 9230.41
19 13.05 H (p) RCC M35 Height 5M 5804.80 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.4220 569.70 0.0000 0.00 8972.72
20 13.05 I (p) RCC M40 Height 5M 5946.80 0.9000 1908.00 0.450 2689.58 0.4220 569.70 9114.72
21 13.06 HYSD Bar 70043.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 1.0500 569.70 0.0000 0.00 0.0000 0.00 70641.19
22 13.08 Weep Hole 153.80 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0018 2689.58 0.0000 0.00 0.0009 569.70 0.0000 0.00 159.02
Back Filling In Abutment, Wing Wall,
23 13.09 A 805.50 0.0000 0.00 0.0000 0.00 1.2000 1908.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 3095.10
Return Wall by Granular Material
Back Filling In Abutment, Wing Wall,
24 13.09 B 1465.90 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.200 149.58 0.0000 0.00 0.0000 0.00 0.0000 0.00 1645.40
Return Wall by Sandy Material
25 13.10 Filter Media 1579.40 0.0000 0.00 0.0000 0.00 1.2000 1908.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 3869.00
26 13.16 Elastomeric Bearing 0.90 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.90
27 13.18 POT-PTFE bearing 211.50 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 211.50
MULTIPLYING FACTOR FOR ROAD ITEMS = 1.111
Stone metal or Brick Stone Boulder Aggregate / Stone chips Bitumen Sand Steel Cement Structural Steel
Sl. Finished
Cl No. Item SOR Rate
No. Carriage Carriage Carriage Carriage Carriage Carriage Carriage Carriage Rate
Quantity Quantity Quantity Quantity Quantity Quantity Quantity Quantity
Cost Cost Cost Cost Cost Cost Cost Cost
14.01 (B) (i)
28 RCC M25 Superstructure (height 5m) 6059.90 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.4032 569.70 0.0000 0.00 9217.11
(p)
14.01 (C) (i)
29 RCC M30 Solid Slab Height 5M 6110.50 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.4067 569.70 0.0000 0.00 9269.71
(p)
14.01 (C) (ii)
30 RCC M30 T-Beam Height 5M 6365.20 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.4500 2689.58 0.0000 0.00 0.4067 569.70 0.0000 0.00 9524.41
(p)
31 14.01 (E) RCC M40 solid slab super-structure 6316.00 0.9000 1908.00 0.4500 2689.58 0.4300 569.70 9488.48
14.01. (F)
32 PSC Grade M45 T-Beam Height upto 5.0 m 6518.40 0.9000 1908.00 0.4500 2689.58 0.4300 569.70 9690.88
(ii) (p)
33 14.02 Supplying, Fitting, Fixing TMT Bar 70272.20 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 1.0500 569.70 0.0000 0.00 0.0000 0.00 70870.39
34 14.03 High tensile steel wires/strands 155737.10 0.3316 569.70 1.0212 569.70 156507.79
Cement concrete wearing coat M-30
35 14.04 10444.10 0.9000 1908.00 0.4500 2689.58 0.0788 569.70 0.4067 569.70 13648.15
grade
36 14.05 Mastic Asphalt(FOR CD WORKS) 464.50 0.0000 0.00 0.0000 0.00 0.0135 1908.00 0.00283 1384.50 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 494.18
37 14.06 Precast RCC Railing 1808.30 0.0000 0.00 0.0000 0.00 0.0767 1908.00 0.0000 0.00 0.038 2689.58 0.0180 569.70 0.0347 569.70 0.0000 0.00 2087.95
38 14.08 Mild steel railing 3832.20 0.0429 569.70 3856.63
39 14.09 Drainage Spout 5936.90 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0040 569.70 5939.18
40 14.10 PCC M15 Grade Levelling Course 4177.90 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.2750 569.70 0.0000 0.00 7262.08
41 14.11 RCC Approach Slab 8762.30 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0500 569.70 0.4067 569.70 0.0000 0.00 11949.99
42 14.16 Painting on concrete surface 130.90 130.90
43 14.17 Filler joint
Providing & fixing 2 mm thick corrugated
44 14.17 (i) 3401.00 3401.00
copper plate in expansion joint
Providing & fixing 20 mm thick
45 14.17 (ii) compressible fibre board in expansion 467.30 467.30
joint
Providing and fixing in position 20 mm
46 14.17 (iii) 181.70 181.70
thick premoulded joint filler
Providing and filling joint sealing
47 14.17 (iv) 35.50 35.50
compound
48 14.21 Strip Seal Expansion Joint 14496.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 14496.00
49 16.04 A laying Pitching on slopes 1674.30 1.2000 2752.20 4976.94
Filter Media at edge of GSB Drainage
50 16.05 1850.00 0.0000 0.00 0.0000 0.00 1.2000 1908.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 4139.60
Layer
51 16.08 (A) Laying Flooring by Rubble stone 4344.40 1.2000 2752.20 0.1397 2689.58 0.0678 569.70 8061.28
Laying Flooring with cement concrete
52 16.08 (B) 5836.64 0.0000 0.00 0.0000 0.00 1.1970 1908.00 0.0000 0.00 0.599 2689.58 0.0000 0.00 0.3658 569.70 0.0000 0.00 9938.59
blocks
53 16.10 (B) Curtain Wall (M20) 4345.00 0.0000 0.00 0.0000 0.00 0.9000 1908.00 0.0000 0.00 0.450 2689.58 0.0000 0.00 0.3440 569.70 0.0000 0.00 7468.49
54 16.11 Flexible Apron 1766.00 1.2000 2752.20 0.2997 1908.00 0.290 2689.58 0.1594 569.70 6509.91
55 14.26 Structural Steel for Super structure 134186.70 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 0.0000 0.00 1.0500 569.70 134784.89
56 14.15 B Crash Barrier for Bridge (height 1100 mm) 3858.40 0.00 0.00 0.00 0.00 0.268 1908.00 0.1341 2689.58 0.0268 569.70 0.1281 569.70 0.00 0.00 4819.07