BMS-20 Plastering and Rendering
BMS-20 Plastering and Rendering
If, despite best endeavours, a conflict should arise between this Method Statement and the Project
Specification the requirements of the latter shall be observed and this document revised, accordingly.
Checked Authorised
Issue Date Prepared
HSE (PSM) Quality (PQM) (Project Manager)
00 DD MMM YY
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 2 of 31
CONTENTS
CONTENTS................................................................................................................................ 2
1.0 SCOPE............................................................................................................................. 5
2.0 RESPONSIBILITIES........................................................................................................ 5
3.0 INTERFACING................................................................................................................. 5
4.0 SEQUENCING..................................................................................................................6
5.0 METHODOLOGY............................................................................................................. 6
5.1 Pre-Works.........................................................................................................................................................6
Preparation of solid surfaces for plastering
Bonding Treatment
Beads Fixation
Lathing
Embedded Items
Control Joints
Submittals
Mix Designs
Alternatives
Mock-Up
5.2 Works...............................................................................................................................................................15
Mixing of Plaster
Plastering Application
Finishing Coats
Inspection
Tolerances
5.3 Post-works.......................................................................................................................................................24
Curing
Cutting and Patching
Cleaning and Protecting
7.0 MATERIALS...................................................................................................................26
10.0 ATTACHMENTS......................................................................................................... 26
Attachment 1: Key to Safety Symbols.......................................................................................................................27
Amendments History
Rev Clause Changes Made
00 Original issue of document
01
02
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 5 of 31
1.0 Scope
This Method Statement covers the application of Cement Plaster works only.
- Any special type of plastering which shall be undertaken by the manufacturer or the subcontractor
and to be discussed in a specific Method Statement.
Note: Emphasis of required safety measures will be inserted throughout, generally in the
following format, pictograms are to be found in Attachment 1:
2.0 Responsibilities
Site Manager:
o In charge of removing any obstacle that may affects the progress of work on site.
Site Engineers:
o Continuous monitoring of all aspects of Plastering works, i.e. substrates preparation before
works, embedded items installation and inspection, fixation of accessories like bead and metal
lathes, indicating locations of control joints and installation of the V-Joints, supervision on mixing
procedures and proportions of ingredients, execution of the mock-up to be approved, plastering
application taking in consideration the specifications of the project, curing for the plaster, post-
works inspection, determination of necessity for repairs, selection and overseeing the
performance of plastering repairs in accordance with prescribed methods and products.
o Liaising with QC Engineers regarding works progression and availability for hold point
inspections.
o Liaising with Mechanical and Electrical Engineers for mechanical and electrical embedded items.
Surveyors:
QC Engineers:
o Ensuring that the Project Inspection Plan (PIP) has been briefed to and is then followed by the
construction team.
o Hold point inspection of plastering works, e.g. dash coat is inspected and cured enough and first
plastering coat can be applied.
QC Technicians:
o Continuous monitoring of and real time reporting to QC Engineers of ongoing plastering works.
o Development and gaining approval of Issued for Construction (IFC) drawings showing the
locations of mechanical/ electrical embedded items and control joints, materials and other
technical submittals and their distribution as required.
< INSERT OTHER JOB TITLES AND ASSOCIATED RESPONSIBILITES AS NECESSARY >
3.0 Interfacing
Site Manager:
o Coordination with Technical Office Manager to ensure timely availability and approval of
materials, design mixes in collaboration with Quality Manager, and IFC drawings.
o Ongoing liaison with Site Engineers concerning the execution progress and obstacles they may
face.
o Liaison with Technical Office Manager for advice required regarding changes, missing
information, clarifications.
Site Engineers:
o Ongoing liaison with Surveyors concerning overall setting out and placing of embedded items.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 7 of 31
QC Engineers:
o Ongoing liaison with Site Engineers concerning plastering works progression and adherence to
stipulated requirements of IFC drawings, method statements, approved materials and PIP.
4.0 Sequencing
Schedule of Areas To be Plastered
Reference Area Covered
5.0 Methodology
5.1 Pre-Works
- In case of presence of any moulds, spores of these moulds must be removed by scrubbing then
hydro blasting.
- Bonding Agent:
a) Bonding agent is applied to substrates to enhance a strong bond between plaster and substrate
and to achieve uniformity of suction.
b) It is recommended in case of low-suction or sealed surfaces.
c) Surface applied to bonding agent must be clean, free from dust, or oils, etc….
d) Bonding agent can be sprayed, rolled or brushed according to the type used and its method of
application indicated by manufacturer.
e) Apply the Bonding Agent to concrete or concrete masonry units after ensuring that it complies
with specifications and after its submittal and approval by the Owner.
f) Steps of application should be tightly followed ( according to manufacturer’s written
instructions ), taking in consideration any important requirements like duration between
application of Bonding Agent and application of first plastering coat in order to get the perfect
bond between the substrate and the plastering coat.
g) Bonding agent can be added to the plaster mix if required and indicated in project
specifications..
h) Bonding agents used and their application method, mixing proportions, etc…. are indicated in
(Table 1 – Bonding Agents) below: <Insert the above required data in the table below>
- Dash Coat:
a) Apply Dash Coat to concrete or concrete masonry units indicated to plastering if Bonding Agent
is not required.
b) Substrate must be dampened before applying the Dash Coat.
c) Dash coat is applied to improve the bond between plaster and the substrate and over come
suction of blocks surface compared to less suction of mortar joints.
d) Dash coat must be consistent in thickness and roughness.
e) Dash coat must have a sharp texture on the substrate.
f) The coat must cover the whole area applied to plastering with no voids.
g) Metal lath must be totally covered with dash coat.
h) Mix of Dash Coat: Ingredients of Design Mix of Dash Coat and its proportions is illustrated in
(Table 4-Mix Design).
Generally, in cement plastering the ratio between cement and sand is:
i) Mix small amounts of the mortar; do not use mortar that is older than 60 mins.
j) Sometimes bonding agent is added to the mix according to project specifications.
k) Dash Coat thickness: Thickness of Dash Coat is illustrated in (Table 5-Thickness of coats).
Generally, Dash Coat thickness = 3 – 6 mm
- Types of accessories (Beads, Control joints, metal lath) commonly used and there locations are
illustrated in (Table 2-Beads) below <Insert any type of accessory used in your project and not
mentioned in the table below>
Angle Beads
a) Designed for 2 or 3 coat application.
Corner Mesh
Metal Lath a) Reinforcement and provides a key for Over any waterproofed
plastering. substrates, contact
6 surfaces between any
b) Prevent cracking at contact surfaces different materials and for
between any two different materials big thickness plaster.
- On fixation:
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 11 of 31
a) It is important to be aware of the relations between structural elements that are indicated to
plastering: Distances between walls and each others, Orthogonality between elements, etc …..
b) Checking that the accessories are fixed in the right place and position (checking level,
plumb, etc…)
1.1.4. Lathing:
- Metal lath is fixed to masonry and concrete substrates, also to metal (by welding) and non-porous
backgrounds to provide a key.
- Used to prevent cracking that may occur at the contact surfaces between any two different
materials. (e.g. Concrete and masonry or two different types of blocks)
- Lathing must be fixed before applying plastering if the substrate is waterproofed.
- Lathing must be used in case of big thickness plastering to act as reinforcement for the plastering
layers.
- Fixation Process: should be fixed per standards, codes and project special requirements:
a) Run the long way of the mesh across supports.
b) Nailed, stapled or hog-tied to the supports.
c) Fixation at centres every 200 mm or less.
d) It should be stretched tightly as much as possible.
e) Don’t stop edges at corners; bend it around for 150 mm al least.
f) Minimum overlap between sheets is about 250 mm.
g) For fixation, use Hand-driven pins (min length= 25 mm) carrying a washer for security, or
flathead concrete nails (min length= 21.5 mm, using a 38 mm nails is preferable) carrying a
washer over the shaft. T-pins or any other devices can be used as an additional holding to the
lath, and they can be fixed between regularly fixed drive-pins or concrete nails.
(Use nails, pins or washers made from galvanized steel only)
h) Types of nails used is according to the metal lath used, refer to the metal lath manufacturer’s
recommendations.
i) Do not use T-pins in fixation alone, it will not support the weight of the metal lath.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 12 of 31
- If there are water pipes, electrical conduits or any other embedded items to be fixed; finish fixation
of these items before starting the first coat of plaster.
- Structurally, control joints are used to control and relieve stresses in the plaster membrane, thereby
reducing the possibilities of cracking and buckling.
- These stresses are found at joints of dissimilar materials or where differential deflection is
anticipated.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 13 of 31
- Stress is caused by expansion and contraction of structure and is usually due to settlement or
varying in climatic conditions.
- Control joints must be installed at locations indicated in approved drawings, if not indicated; install
the joints as follows:
a) Where an expansion or contraction joint occurs in the substrate’s surface with depth extended
through the plaster and reinforcement to the substrate and with width = 3 mm or the same as
substrate’s joint width (the greater of both).
b) When wall area greater than 13 m².
c) When distance between 2 joints is greater than 5.4 m.
d) Between panels, at surface penetrations (Doors, windows, etc…) and at areas of structural
stresses.
- V-joints: or expansion beads are usually manufactured in 13 mm or 19 mm profiles.
- Cut right through the plaster to the substrate at abutments with metal doors, abutments with other
finishes and junctions between different substrates.
- Don’t continue plaster across damp-proof courses.
- A groove or a cut in the plaster can not be considered as a control joint.
1.1.7. Submittals:
- All accessories or materials used in plastering process to be submitted and approved by the owner
before usage.
- Do not proceed with lathing, fixing beads or plastering until all products and finish samples are
approved.
- Material and accessories should be received by a responsible Material Engineer and to be checked
on receive and checked again before usage.
- Mix Design of the mixes used in Dash Coat, First Coat, or Second Coat and its Ingredients,
proportions, etc… are illustrated in (Table 3-Mix Design) below < insert the mixes names used in
your projects and their components in the following table>
- If there is an alternative Design Mix for plastering; to be illustrated in (Table 4-Alt. Mix Designs)
below: <Insert the alternatives for the Mix Design in the table below>
- If there is an alternative type of accessories (beads, lathing, joints, etc….); to be illustrated in (Table
5-Alt. accessories) below: <Insert the alternatives for the Accessories in the table below>
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 15 of 31
1.1.10. Mock-up:
Executing a mock-up exposed to all external factors that may affect plastering
(wind, direct sun light, high temperatures, etc….)
Consider all precautions to keep plastering with the desired quality.
Apply the Dash Coat rate in the mock-up to be approved.
All approved accessories to be fixed precisely in their locations in the mock-up to
measure its performance.
Mix Designs submitted and approved to be applied for first and second coats to test
the workability of these mix designs.
Curing is applied according to project specifications putting the external conditions
in consideration.
The mock-up to be inspected and accepted by QC engineer then by the owner to
approve: Workmanship, Design Mix, Dash coat rate and coat’s textures.
- Curing process for external and internal plastering is illustrated in (Table 10-plaster curing)
5.2 Works
- Select a mix that suits the conditions the plastering is exposed to.
- Measure components of the mix by volume using buckets or boxes (Its better to use a gauging
trowel)
- Ensure successive coats are no richer in binder than the coats to which they are applied.
- Mixing Procedure:
a) Put water in a clean bucket before adding the binder to avoid lumpy mix.
b) Added water to be cold, clean and free from strange materials.
c) Variation in water temperature affects the Setting Time of the cast which will lead to a direct
effect on the strength of plaster.
d) Add plastering materials (Cement, sand, lime…)
e) It’s easier to use a mixer drill instead of manual mixing, manual mixing is not permitted.
f) For mechanical mixing, use Rotary Concrete Mixer
- Mixing time is very important since it affects the strength developed. As mixing time is increased,
strength of the cast increases. However, long mixing time affects other properties adversely (e.g.
porosity)
- Mixing time is based on the properties needed in the cast.
- Mix small amounts of the mortar; do not use mortar that is older than 60 mins.
- Mortar that had been stiffened due to water evaporation can be tempered one time only to restore
the required consistency.
- Mixing time affects Set-Time of the cast, under mixing can lead to separation of plaster from water
prior to set. On other hand, over mixing may decrease the strength of plaster. Therefore, mixing
time must be developed and followed as standards and specifications of the project.
- Ensure of the presence of direct contact between plaster and substrate generally and especially at
Metal Lathing zones. Although lathing is installed, it is important that the plaster membrane adheres
directly to the substrate as fully and securely as possible in addition to the fixation of the metal lath
to the substrate.
- Make dots before applying plaster to be used as a guide to form a flat surface for plaster free from
curves or bends (use spirit level and straight edge to form dots)
- Make screeds by joining the dots horizontally or vertically, lay the plastering material in strips of (7-
10) cm in width and leveled off with the floats to the thickness of the dots. Screeds must have the
same thickness of the dots which is equal to the thickness of the base coat as well. Screeds are used
to fill plaster between them so the entire wall will be flat with no curves and the base coat thickness
is adjusted all over the wall.
- Dots and screeds should be made from the same material of the base coat to avoid removing them
and filling the gabs of the same plaster material after that.
- Press the plaster through the openings of expanded metal lath and wings of beads.
- Scratch-comb each base coat in two directions when it has stiffened.
- Base coat is finished according to the required texture (e.g. Mission Texture. Do not require as much
straightening of the base coat due to absence of plane in the decorative finish coat).
- Base coat must be moist cured in accordance with good industry practice then allowed to dry to
uniform moisture content over the entire wall before application of finish coat.
- Sometimes base coat is built up in more than one coat (Scratch coat + Brown coat) but that is not
necessary over substrates that was applied to dash coat before.
- Plaster base coat must be rodded off to a true flat plane. Even and level with screeds.
- At corners; make internal corners and angles square, finish external corners flush with corner beads
on interior work. Square and true with plaster faces on exterior work.
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 19 of 31
- During plastering works, protect the substrates that had not been plastered yet.
- Number of coats is two coats at least over block walls although it varies according to project
requirements and specifications ( insert no. of coats in your project according to project
requirements) and to be applied over the following surfaces:
(Illustrate substrates indicated to plastering in your project)
- Thickness of coats: Min and Max thickness for each coat is indicated in (Table 6-Thickness of coats)
< Insert thickness of coats according to project requirements>
Dash Coat
1st Coat
2nd Coat
Finish Coat
a) Cold Weather:
Do not use frozen materials.
Do not apply plastering to frozen surfaces or surfaces containing frost.
Do not mix materials or apply cement plaster if temperature is less than 4.4 degrees° C.
(According to ASTM C 962)
b) Hot Weather:
Protect cement plaster from uneven and excessive evaporation during hot, windy and dry
weather.
Moist curing after each coat of cement plaster with water if temperature is more than 24
degrees° C. Moist cure for 48 hours after application of coats.
In hot, or dry, or windy weather, cement plaster should be moistened down and then
covered with polyethylene plastic sheets.
Moist curing is required at the start and the end of work day.
Do not apply plastering if temperature exceeded 26 degrees° C.
- Duration between each coat and its successive is indicated in (Table 7 - Durations between coats)
below: <Insert duration between each coat and the coat following>
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 20 of 31
Dash Coat
1st Coat
2nd Coat
3rd Coat
- Efflorescence Phenomena:
Removing of Efflorescence:
Sources of Efflorescence
- Finish coat is applied after base coat is sufficiently cured (review Table 10-Plaster Curing) and
attained uniformly moisture content or suction over the entire wall.
- It must be applied with suitable thickness and with the desired texture (Float, Dash, etc…) according
to project requirements.
- If the final surface is to be somewhat smooth, plasterers must avoid manipulation for the surface
early to prevent the appearance of hair cracks or migration of fines to the surface.
- Use a finish coat according to the project requirements and specifications.
- Factory –prepared finishing coats must be used according to manufacturer’s instructions.
- Types of finishing coats and their application, properties are illustrated in (Table 8 – Finishing Coats)
<Insert the type of finishing coats used in your project, ingredients and application>
No. of Thickness
Coat Name How to apply
coats (mm)
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 22 of 31
1.1.4. Inspection :
- Before plastering:
a) Substrate:
Ensure that substrate is clean, free from loose materials or any deterioration.
Check verticality and the plane surface of the substrate and ensure that the surface is
free from any deviation or inclination using plump-line and straight-edge.
b) Accessories:
Checking that fixation of the beads and metal lath is executed according to good
industry practice and project’s specifications
Checking that accessories are fixed in the correct positions.
Check that beads are vertical, leveled and free from defects.
ENSURE that the Beads and the final finish coat are on the same plane and no difference
between them.
Check whether delamination occurred or not by knocking on the coat’s surface, if drum
sound is heard, the area should be cut and repaired.
Pull thread all over the whole wall or use a plumb-bob and a straight edge to check if there
is any curvature or bending in the plastered surface.
Ensure that corners are regular and free from any curves using straight edge.
Put the spirit level on the straight edge while checking flatness of plaster.
Ensure that the dimensions of the openings (Doors, windows…) are accurate after applying
plaster and it didn’t change.
For typical floors:
In case of successive openings in the typical floors, pull a vertical thread all over the
openings to check they are vertical and on the same level.
In case of successive openings in the same floor, pull a horizontal thread all over
the openings to check they are horizontal and on the same level
1.1.5. Tolerances:
- Tolerances is indicated in (Table 9 – Tolerances) below: <Insert Tolerance ranges of your project
according to specification>
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 24 of 31
Property Tolerance
Features: Verticality in mm mm
Features: Horizontality in mm mm
Walls: Verticality in mm mm
Walls: Flatness in mm mm
Features: any plastered surface except walls.
Flatness: Measured under a straightedge laid in any direction on a plane surface.
(Table 9-Tolernaces)
- If tolerance ranges are not mentioned in specifications, then the recommended tolerances are:
Property Tolerance
Features: Verticality in 2000 mm 2 mm
Features: Horizontality in 2000 mm 2 mm
Walls: Verticality in 2000 mm 4 mm
Walls: Flatness in 2000 mm 3 mm
Features: any plastered surface except walls.
5.3 Post-works
1.1.6. Curing
- Curing of plastering depends on the mixture used, the coat to which is applied, thickness of coat and
climatic conditions, but generally the following points must be taken in consideration.
- Prevent premature or uneven drying out and protect from sun and wind.
- Using of wetted sackcloth to cover areas indicated to plaster and then cover the sackcloth with
polyethylene sheets to keep it moist for longer time, re-wet sackcloth constantly.
- Duration of curing for each coat is shown in (Table 10-Plaster Curing) below:
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 25 of 31
<Insert Curing processes and curing durations for each plastering coat in your project>
7.0 Materials
Portland cement
Sand
Lime
Bonding Agents
Embedded Items
Sack-cloth
Polyethylene sheets
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 27 of 31
10.0 Attachments
o Key to Safety Symbols
o Risk Assessment
< INSERT PROJECT REF # & TITLE HERE >
METHOD STATEMENT: Ref ??? Rev 00
Plastering Works Date DD MMM YY Page 28 of 31
Use respirators
< INSERT PROJECT REF # & TITLE HERE >
Ref BMS-?? Rev 00
METHOD STATEMENT: Plastering Works
Date DD MMM YY Page 29 of 31
Moving of Unsafe storage of materials in Tech. 3 3 9 Designated areas to be prepared for the cement bags and sand in the working area away from 1 3 3
cement to the working area by blocking accesses.
the working access ways. Gloves and dust masks, goggles, ear muffs and rubber boots to worn to avoid skin and eye irritation
area. Contact with dry cement causing and corrosion.
Preparing of skin, eye and lung irritation. Loose clothes to be avoided, engine guards to be used and only competent trained workers to use the
mortar using Contact with wet cement causing mixer.
cement skin and eye corrosions.
mixers Mixer to be checked prior to use, all cables to be insulated and kept away from wet soil to avoid electric
Noise of the cement mixer shock hazard.
affecting the hearing and causing Cement mixers to be refueled and used in open or well ventilated areas.
tinnitus.
Earthing rods to be used.
Corrosions, entanglement with
rotating drum, engine. Plastic sheets to be used to avoid soil contamination
Electrical shock hazard from bad
wiring, bare wires of the
electrical driven mixer.
Explosions, fumes from the use
of petrol driven mixers.
Ergonomic hazards while manual
handling of cement bags and
sand.
Environmental hazards from
contaminated soil
Application, Ergonomic hazards from poor Plasterers 3 3 9 Job rotation, safe handling and proper body posture to avoid fatigue, muscle and ligament injuries 2 3 6
finishing and body posture and repetitive work Area to be cleaned from all debris, cement waste on daily basis
curing leading to fatigue, muscle and
ligament strains. MSDS to be available with master seal, master cure and other chemicals used, eye wash and suitable
PPE to be worn, spill kits to be provided
Slipping and tripping hazards
from poor housekeeping.
Health hazards from chemicals
< INSERT PROJECT REF # & TITLE HERE >
Ref BMS-?? Rev 00
METHOD STATEMENT: Plastering Works
Date DD MMM YY Page 31 of 31
Working at Overloading, unsafe scaffolding Plasterers 3 4 12 Only competent scaffolder to erect the scaffolding and to make the necessary modifications if needed. 1 4 4
height using erection, moving equipment, Scaffolding to be inspected by competent scaffolding inspector.
scaffolding damaged scaffolding materials
and unsafe use of scaffolding Scaffolding to be green tagged if safe to use.
leading to scaffolding collapse, Equipment and vehicles to be kept away from the scaffolding.
materials and equipment
damage serious injuries and No storage of materials on the scaffolding, no overloading; materials to be kept to minimal.
possible fatalities. No work under the scaffolding to be allowed to avoid falling materials.
Working underneath or around Unsafe scaffolding to be red tagged.
the scaffolding, falling of
materials from the scaffolding Safety harness to be worn when necessary.
leading to injuries such as cuts Cleaning of scaffolding on regular basis to avoid tripping hazard
and bruises.
Poor housekeeping leading to
slips, trips and falls