JSA For LD Line Road Cutting
JSA For LD Line Road Cutting
SAFETY
Rev. 8
15-May-2018
JOB SAFETY ANALYSIS (JSA) FORM
Page 1 of 13
Original JSA Date: 25 Nov 2018 High Risk Activity: NO YES (HSE Rep. required) High Risk Activity Job Step Nos. :
Maruthu Basith Aswin Janarthanan JSA Facilitator Name:
JSA Participants
Name Ralph Abreu
REVALIDATION DATE
(JSA IS VALID FOR 3 MONTHS. REVALIDATION TO BE DONE AFTER 3 MONTHS IF SAME JOB CONTINUOUS OR IF ANY CHANGE IN JOB SCOPE OR JOB CONDITION).
No. DATE NAME SIGNATURE No. DATE NAME SIGNATURE
1 4
2 5
3 6
JSA PRE-CHECKS
YES NO QUESTION
Is the JSA Team sufficient (Area Owners, Job Performers, HSE Rep, Technical, etc.)?
If contractor is involved, contractor participated in JSA?
Is Job Scope clear and well defined?
Visit to the job site has been made?
If a similar activity was performed in past, a copy of previous JSA is available?
Is team aware of any history of incident / near-miss on similar job at Q-Chem? If YES, lesson learned report (LLR) should be reviewed and
attached to JSA?
Are any unique SDS’s required for this job? If YES, SDS’s should be reviewed by JSA Team?
YES QUESTION
The JSA Hazard Checklist is filled and attached with the JSA?
NOTE: If any point ticked “YES” in JSA HAZARD CHECKLIST above, its mitigation shall be mentioned in JSA JOB STEPS below.
JSA - JOB STEPS
JOB STEP JOB STEP DESCRIPTON POTENTIAL HAZARDS REQUIRED MITIGATIONS
1 Vehicle movement only at permitted areas
Access concern/damage to existing Vehicle movement path for adequate ground and
Site preparation and mobilization. facilities overhead clearance
Loading, unloading, shifting of Equipment to move with spotter signal
materials, Generator and other Gas test shall be done prior to vehicle entry and
tools. gas monitoring to continue at work site.
Spark due to vehicle entry. Check vehicle/equipment condition daily prior to
each use.
Keep RLOC certified fire extinguisher with vehicle.
Assign material storage location in field to avoid
blockage of plant operation/maintenance
Blocking of essential area by stored activities/vehicle movement. (Take assistance of
materials operator)
Access should not block to safety or plant
equipment
Proper manual handling techniques shall be
followed with proper body ergonomics.
Avoid twisting or awkward body postures.
Handling heavy loads
Always keep the load close to your body
Maximum lifting for any person shall not exceed 20
kg
Boom truck tilting/collapsing Ensure outriggers are fully extended and the boom
truck should park only on even surface.
Use RLOC certified Boom truck and lifting tackles.
Don’t stand under suspended load.
Barricade and provide barricade tag for the work
area.
Ensure operator have valid 3rdparty certificate for
boom truck operation.
Road Block
Obtain Road Block permit from FSC prior starting
the activity.
Use calibrated surveying machine.
Use of uninspected /calibrated Use appropriate drawings for survey
surveying machine which can cause Survey machine must be inspected and approved
2 Surveying and marking the area improper survey, damage of by RLOC with inspection stickers.
underground pipe /cable (equipment Continuous gas monitoring to be done
damage/personal injury) Obtain PTW prior to start work
Use calibrated scanning instrument
Scanning to identify by Use of uninspected/calibrated scanning Scanning instrument must be inspected and
3
underground utilities instrument. approved by RLOC with inspection stickers.
Continuous gas monitoring to be done
Proper manual handling techniques shall be
followed with proper body ergonomics.
Handling heavy loads
Avoid twisting or awkward body postures.
Always keep the load close to your body
Maximum lifting for any person shall not exceed 20
kg
Lead Worker should identify pinch points in the
Hard Barricading with scaffolding
Pinch points while erecting barricades activity and it should be discussed during TBT
4 pipes around the area to be
Keep body parts away from line of fire.
excavated.
Hard barricade the area and put barricade tags.
Do not park or move any equipment or vehicle near
the edge of the excavation.
Fall of person / materials into excavated
Beware of excavation edges while building hard
area barricade
Hard barriers shall be erect not less than 2 meters
from the edge of the excavation.
5 Cutting of existing Asphalt Personnel injury due to sharp edges Keep away from line of fire.
Pavement and Concrete by using Keep eyes on task.
concrete cutter and Asphalt Wear cut resistant gloves while handling sharp
demolition edges.
Ensure the asphalt cutter having safety guard.
Eye injury due to flying objects while Use face shield with safety glass while using cutting
core cutting machine
blower.
Maximum lifting for any person shall not exceed 20
kg
Use manual handling techniques.
Use of rebar caps for projection from pinch points
Use nail holder while hammering nails
Keep hands away from pinch points
9 Grinding machine, manual chisel Area must be barricaded and only authorized
and cement application. personal should be allowed to enter.
Keep body parts away from rotating parts.
Slips/ trips Secure tools and cables away from work area.
Cables should be laid properly to avoid trips.
Maintain good housekeeping throughout the job.
High noise Use double hearing protection while using grinding
machine
Use adequate PPE.
Use rubber gloves, dust mask (3m 8210)
Skin contact with concrete material Maintain good housekeeping.
SDS must be available at work site
Housekeeping shall be done to ensure work place
Slip / Trip is clear all the time.
All materials shall be removed from site to a safe
area immediately after the work.
10 Housekeeping All the wastes generated must be collected and
Waste accumulation disposed of in the designated collection points on
every day basis.
Use of 3M 8210 dust mask in case of dust
Dust environment
17 34