Mini Project Dashrath
Mini Project Dashrath
ON
SUBMITTED IN PARTIAL
FULFILLMENT OF THE
OF
SESSION 2023-24
SUBMITTED BY SUBMITTED TO
St. Wilfred’s Institute of Engineering and Technology, Near Balaji Mandir, Gegal,
Ajmer
ACNOWLEDGEMENT
We take this opportunity to express our immense gratitude and to thank all those
who have helped us in accomplishing this seminar
We would like to begin thanking our H.O.D. Mr. Chetan Kumar Who has always
motivated us to work hard.
We would like to thank our sir Mr. Shaitan singh rawat who oversaw the Seminar
work right from its inspection to its completion and showed a great amount of
patience. Listened to the problems wefaced and constantly encouraged us. Thank
you sir, we could not have completed this seminar without your help.
We also wish to thank all teaching and non-teaching staff and parents who have
been supportive to us during the process of completing this seminar we also thank
our friends for giving us valuable suggestions.
To the people above and all the other people who have done their bit in helping us thanks to all.
Parul Phulwariya
CONTENTS
TOPICS
ACKNOWLEDGEME
NT i ABSTRACT
CONTENTS
LIST OF FIGURES
CHAPTER – 1 INTRODUCTION 1
General
Regulations Types of
Buildings
Organisation of the
project Summary
Introduction
Specific
studies
Summary
Introductio
Methodolo
gy
Types of surveys to be
a building Summary
Introducti
on
Observati
ons
Summary
CHAPTER – 5 CONCLUSIONS
Summary
Conclucio
ns
REFERENCES
LISTOF FIGURES
Isolated
Footing
Stepped
Footing
Eccentric
Footing
Combined
Footing Matt
Footing
Fly-ash Brick
wall Columns
Beams
simply supported
beam Cantilever
Beam
Fixed Beam
Over Hanging
Beam
Continuous
Beam Slab
ABSTRACT
The main aim of our project is to complete a construction of g+9 building &
to ensure that the structure is safe against all possible loading conditions
and to full fill the function for which they have built. Safety requirements
must be met so that the structure is able to serve its purpose with the
maintain cost. Detailed planning of the structure usually comes from several
studies made by town planners, investors, users, architects and other
engineers. On that, a structural engineer has the main influence on the
overall structural design and an architect is involved in aesthetic details. For
the design of the structure, the dead load, live loads, seismic and wind load
are considered.
CHAPTER – 1 INTRODUCTION
GENERAL
The basics needs of human existences are food, clothing’s & shelter. From
times immemorial man has been making efforts in improving their standard
of living. The point of his efforts has been to provide an economic and
efficient shelter. The possession of shelter besides being a basic, used, gives
a feeling of security, responsibility and shown the social status of man.
Engineer has to keep in mind the municipal conditions, building bye laws,
environment capacity, water supply, sewage arrangement, provision of
future, aeration, ventilation etc., in suggestion a particular type of plan.
PURPOSE OF BUILDING
GROUP-B EDUCATIONALBUILDINGS
GROUP-C INSTITUTIONALBULIDINGS
GROUP-E BUSINESSBUILDINGS
GROUP-G INDUSTRIALBUILDINGS
The whole report is organized by divided into five chapters including this
introduction part as chapter 1, chapter 2 gives a basic idea about the review
of the literature.
Chapter 5 makes a conclusion of the project by giving some limitations and applications
SUMMARY
In this project we have discussed about the construction of g+9 building
using building by laws and the rules that are to be followed by each and
every individual for the construction of high rise building in a particular
area.
CHAPTER – 2 LITERATURE REVIEW
INTRODUCTION
To better understand the terms used throughout this paper, a brief overview
is presented of some of the terms not frequently used in the area of
structural engineering. Newly developed design management tools or
systems are not readily available. This research was conducted based on the
available design tools and various studies on these constructions were
carried out by engineersare mentioned below.
SPECIFIC STUDIES
SUMMARY
In this chapter we discussed about the research work carried out by various
persons through their journals regarding construction of g+2 building.
CHAPTER– 3 METHODOLOGY
INTRODUCTION
COARSE AGGREGATES
Coarse aggregate for the works should be river gravel or crushed stone .It
should be hard, strong, dense, durable, clean, and free from dust, clay or
loamy admixtures or quarry refuse or vegetable matter. The pieces of
aggregates should be cubical, or rounded shaped and should have granular
or crystalline or smooth (but not glossy) non-powdery surfaces.
good Whitish
=>bad quality
FINE AGGREGATE
Grading of natural sand or crushed stone i.e. fine aggregates shall be such
that not more than 5 percent shall exceed 5 mm in size, not more than 10%
shall IS sieve No. 150 not less than 45% or more than 85%shall pass IS sieve
No. 1.18 mm and not less than 25% or more than 60% shall pass IS sieve No.
600micron.
REINFORCEM
ENT
used to make stirrups plinth beam. Reinforcement should be free from oil,
grease and rust because they reduce the bond strength between concrete
and reinforcement. The concrete is strengthened by steel reinforcement and
the resultant composite mass is known as reinforced cement concrete (RCC).
2.Distribution Reinforcement
(Longer Span). Main
Reinforcement
Footings which are provided under each column independently are called
as Isolated footings. They are usually square, rectangular or circular in
section. Footing is laid on PCC. Before laying PCC,
termite control liquid is sprayed on top face of PCC to restrict the termites to
damage the footing. Isolated footings are provided where the soil bearing
capacity is generally high and it comprises of a thick slab which may be flat
or stepped or sloped.
Shoe footing is the half cut-out from the original footing and it has a shape of
shoe. They are constructed on property boundary, where there is no provision
of setback area. It is constructed at the corner of the plot when the exterior
column is close to the boundary or property line and hence there is no scope
to project footing much beyond the column face.. Column is provided or
loaded at the edges of shoe footing. Shoe footings are constructed when the
soil bearing
capacity is 24KN/m2 Figure 3.3 Eccentric Footing COMBINED FOOTING A
footing which has more than one column is called as combined footing. This
kind of footing is adopted when there is a limited space. Due to lack of space
we cannot cast individual footing, Therefore footings are combined in one
footing. Figure 3.4 Combined Footing
RAFT OR MATT FOOTING When the column loads are heavy or when the safe
bearing capacity of soil is very low, The required footing area become very
large. As mentioned this footing is in shallow foundation. So in order to
spread the load over large area with less depth then we have to increase the
footing area. If we increase footing area the footings are overlapped each
other, instead of providing each footing on each column all columns are
placed in common footing. A raft foundation is a solid reinforced concrete
slab covering entire area beneath the structure and supporting all the
columns. Such foundation due to its own rigidity minimizes differential
settlements. It is provided in a places like seashore area, coastal area where
the water table is very high and soil bearing capacity is very weak. When
number of column in more than one row, provided with a combined footing,
the footing is called mat or raft foundation.
PILE FOUNDATION
BEAMS
Beam is the horizontal structure of the building which resists between the
slab and the columns. A beam can transmit the load which comes from the
slab transfer it to the columns. Beams are made up of different materials like
timber, steel, concrete. A beam is a structural element that primarily resists
loads applied laterally to the beam axis. Its mode of deflection is primarily by
bending. The loads applied to the beam results in reaction forces at the
beam’s support points. A
beam is a structural element that primarily resist. The loads carried by
beam are transferred to columns, walls, girders, which then transfer the
force to adjacent structural compression member and eventually to the
ground.
Figure 3.8
Beams TYPES
OF BEAMS
A simply supported beam is a type of beam that has pinned support at one
end roller support at the other end. Depending on the load applied. It
undergoes shearing and bending. It is the one of the simplest structural
element. It is abeam which is supported or rest upon two members either
beam or column. In actual practice no beam rest freely on supports.
Supported Beam
CANTILEVER BEAM
The deflection is maximum at the mid span of the beam when the load is
acting symmetrically on the cantilever beam. The slope is maximum at the
free end of the beam when the load is acts symmetrically on the cantilever
beam.
FIXED BEAM
A beam that is supported at both ends. It allows neither vertical movement
nor rotation at the supports. A fixed beam is a beam which is built in such a
way that their end slopes remain zero.
A beam with both ends fixed is statically indeterminate to 3rd degree, and
any structural analysis method applicable on statically indeterminate beams
can be used to calculate the fixed end.
OVERHANGING BEAM
It is the beam that has its one or both ends stretching out past its supports.
It can have any number of supports. In other words, it is a beam when a
cantilever portion is hanging out of a simply support beam.
Beam CONTINUOUS
BEAM
Beam SLABS
The Floor System of a Structure can be of different forms such as solid slab,
ribbed Slab or Precast Units. Concrete Slabs behave primarily as flexural
members and the design is similar to that of beams of 1M width.
SLABS ONE
WAY SLAB
A Slab which is supported on two opposite edges only is called as slabs spanning in one
direction
or one way slab. If the slab is supported on all four edges and the ratio of
longer span to shorter span (ly/lx) is greater than 2, practically the slab
spans across the shorter span. Such slabs are also designed as one way
slabs. One way slabs bends in one direction.
When the slabs are supported on all the four edges and the ratio of longer
span to the shorter span (ly/lx) is less than or equal to 2, the slabs are likely
to bend along the two spans and such slabs are called as two way slabs.
FLOORING This is the surface on which we do most of our activities. Floorings
is laid over the filling of the plinth and on subsequent floors. Flooring can be
done with different materials, but care must be given that the ground below
the floor is well compacted. Flooring is done to prevent dampness from rising
to the top and to have a firm platform that can be kept hygienic and clean.
STAIRS
3.5 SUMMARY
In this chapter we have discussed about the general item of works that are
to be carried out for the construction of a building. These are the works that
are done according to the layouts that are to be satisfied by the client
requirements.
CHAPTER – 4 STUDY INTERPRETATION
INTRODUCTION
This part describes about the meaning or discussion of results obtained by
conducting the tests during the study or doing of the project.
OBSERVATIONS
DURING THIS MINI PROJECT AT SITE WE HAVE OBSERVED THE FOLLOWING
THEY ARE AS FOLLOWS:
installation.
Observed the plastering stages interior and exterior. First coat is of 1:6
ratio and later second coat is laid using 1:3 ratio
Water proofing course used is Dr. FIXIT used 100 ml for 50kgs of
STRENGTH OF CONCRETE
Objective
The testing machine may be of any reliable type, of sufficient capacity for
the tests and capable of applying the load at the specified rate. The
permissible error shall be not greater than ± 2 percent of the maximum load.
10086-1982. Procedure
1. Place the prepared concrete mix in the steel cube mould for casting. 2.
Once it sets, After 24 hours remove the concrete cube from the mould. 3.
Keep the test specimens submerged underwater for stipulated time. 4. As
mentioned the specimen must be kept in water for 7 or 14 or 28 days and
for every 7 days the water is changed. 5. Ensure that concrete specimen
must be well dried before placing it on the UTM. 6. Weight of samples is
noted in order to proceed with testing and it must not be less than 8.1Kg. 7.
Testing specimens are placed in the space between bearing surfaces. 8. Care
must be taken to prevent the existence of any loose material or grit on the
metal plates of machine or specimen block. 9. The concrete cubes are placed
on bearing plate and aligned properly with the center of thrust in the testing
machine plates. 10. The loading must be applied axially on specimen without
any shock and increased. 11. Due to the constant application of load, the
specimen starts cracking at a point & final breakdown of the specimen must
be noted. Results of cube test Average Compressive strength at 7 days =
N/mm² The average Compressive strength at 28 days
= N/mm² FIELD DRY DENSITY OF SOIL BY CORE CUTTER
METHOD
2.Steel rammer
3.Steel dolly
4.Balance
5.Steel rule
6.Spade or pickaxe
7.Straight edge
8.Knife
at field Procedure
1.Determine the internal diameter and height of the core cutter to the nearest 0.25mm.
3.Expose a small area of the soil to be tested. Level the surface, about 300mm square in
area.
4.Place the dolley over the top of the core cutter and press the core cutter
into the soil mass using the rammer. Stop the pressing when about 15mm
of the dolley protrudes above the soil surface.
5.Remove the soil surrounding the core cutter, and take out the core
cutter. Soil soil would project from the lower end of the cutter.
6.Remove the dolley. Trim the tip and bottom surface of the core
cutter carefully using a straight edge.
7.Weigh the core cutter filled with the soil to the nearest gram (M2).
8.Remove the core of the soil from the cutter. Take a representative
sample for the water content determination.
content. SUMMARY
In this chapter we have discussed about the work that we observed during
the construction of g+2 building at R&B DEPARTMENT.
CHAPTER – 5 CONCLUSIONS
SUMMARY
We can conclude that there is difference between the theoretical and
practical work done. As the scope of understanding will be much more when
practical work is done. As we get more knowledge in such a situation where
we have great experience doing the practical work.
Here we observed that works going on in the site which gives us different
experience of process of, we are moved with different types of people. And
we observed footings, plinth beams, columns, beams and slabs. We
observed different types of drawings of beams, columns, slabs, footings,
plinth beams, stair case, brickwork etc.
CONCLUSIONS
Whatever may be the construction, the process followed is same.
We came to know that the structure is constructed after certain soil tests
are done to know whether this land is suitable for construction are not.
ANNEXURE-I
SAFETY DEFINATION
When working with such equipment, you need to be extra cautious to see
there is no wear and tear in the machine.
Equipment’s)
SAFETY HELMET: It is used for avoiding head injury to head while working in
site. It protects head from falling objects.
FIRST AID BOX: First aid box is used to carry emergency treatment equipment’s.
SAFETY GOGGLES: Used for protection from dust particles, flying chips and
the Impact of fragments.
PROTECTIVE GLOVES: They are used for protecting our hands from
damage and accidents while working with hands.
SAFETY BELT: It is used to wear to the employers to save them who works
at heights and hazardous locations.
SAFETY SHOES: They are used to wear to foots to save our foots from
injuries, damages and accidents caused by stepping on objects and slips.
FIRE BLANKET: It is used to cover our body while working in fire works and
during fire accidents.
These are the people who helped us to finish our mini project
CEMENT CONCRETE
In its simplest form, concrete is a mixture of paste and aggregates. The paste,
composed of Portland cement and water, coats the surface of the fine and coarse
aggregates. Through a chemical reaction called hydration, the paste hardens and
gains strength to form the rock-like mass known as concrete.
Within this process lies the key to a remarkable trait of concrete: it's plastic and
malleable when newly mixed, strong and durable when hardened
Concrete's durability, strength and relatively low cost make it the backbone of
buildings and infrastructure worldwide—houses, schools and hospitals as well as
airports, bridges, highways and rail systems. The most-produced material on Earth
will only be more in demand as, for example, developing nations become
increasingly urban, extreme weather events necessitate more durable building
materials and the price of other infrastructure materials continues to rise.
Even construction professionals sometimes incorrectly use the terms cement and
concrete interchangeably. Cement is actually an ingredient of concrete. It is the fine
powder that, when mixed with water, sand, and gravel or crushed stone (fine and
coarse aggregate), forms the rock-like mass known as concrete.
The Forms of Concrete
Concrete is produced in four basic forms, each with unique applications and properties
1.Ready-mixed concrete, far the most common form, accounts for nearly three-
fourths of all concrete. It's batched at local plants for delivery in the familiar trucks
with revolving drums.
2.Precast concrete products are cast in a factory setting. These products benefit
from tight quality control achievable at a production plant. Precast products range
from concrete bricks and paving stones to bridge girders, structural components,
and wall panels. Concrete masonry another type of manufactured concrete, may be
best known for its conventional 8-by-8-by-16-inch block Today's masonry units can
be molded into a wealth of shapes, configurations, colors, and textures to serve an
infinite spectrum of building applications and architectural needs.
3.Cement-based materials represent products that defy the label of "concrete," yet
share many of its qualities. Conventional materials in this category include mortar,
grout, and terrazzo. soil-cement and roller-compacted concrete —"cousins" of
concrete—are used for pavements and dams. Other products in this category
include flowable fill and cement-treated bases.
Test for compressive strength is carried out either on cube or cylinder. Various
standard codes recommends concrete cylinder or concrete cube as the standard
specimen for the test.
This concrete is poured in the mould and tempered properly so as not to have any
voids. After 24 hours these moulds are removed and test specimens are put in
water for curing. The top surface of these specimen should be made even and
smooth. This is done by putting cement paste and spreading smoothly on whole
area of specimen.
This concrete is poured in the mould and tempered properly so as not to have any
voids. After 24 hours these moulds are removed and test specimens are put in
water for curing. The top surface of these specimen should be made even and
smooth. This is done by putting cement paste and spreading smoothly on whole
area of specimen.
Precautions for Tests
The water for curing should be tested every 7 days and the temperature of water must be at
27+-20C.
BIBLIOGRAPHY
References:
1. Theory of Structures by ramamrutham for literature review on
Code Books
S 456-2000 code book for design of beams,
columns and slabs2.SP-16 for design of
columns.