Facility Layout & Location Guide

The document discusses factors affecting facility location, including market proximity, availability of utilities, and labor supply. It outlines methods for single and multi-facility location optimization, such as the MINISUM approach and the North-West corner method for transportation problems. Additionally, it covers facility layout design techniques like CRAFT and ALDEP, detailing their procedures and data requirements.

Uploaded by

Chintu Chaniyara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views57 pages

Facility Layout & Location Guide

The document discusses factors affecting facility location, including market proximity, availability of utilities, and labor supply. It outlines methods for single and multi-facility location optimization, such as the MINISUM approach and the North-West corner method for transportation problems. Additionally, it covers facility layout design techniques like CRAFT and ALDEP, detailing their procedures and data requirements.

Uploaded by

Chintu Chaniyara
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 57

FACILITY LAYOUT AND

LOCATION

C O M P I L E D B Y:
P R O F. A . M . G O H I L
INSTITUTE OF TECHNOLOGY
NIRMA UNIVERSITY
Factors affecting facility location

 Market proximity
 Proximity to Raw Materials
 Availability of land
 Availability of Utilities
 Labour supply and Unionization
 National taxes
 Legal restrictions
 Stability of demand
 Modes of transportations
 Security
Single Facility Location - MINISUM
Single Facility Location - MINISUM

Rectilinear distance measure Euclidean distance measure


Manhattan distance
Right-angle distance
Rectangular distance
Single Facility Location - MINISUM
Single Facility Location - MINISUM

 There are 6 existing plants which have a material


movement relationship with a new plant. The existing
plants have locations of (300,400), (500,800),
(1000,700), (900,200), (300,750) and (1200,500).
The number of tons of materials transported per year
from the new plant to various existing plants are 500,
900, 400, 900, 800 and 1600, respectively.
Determine the optimum location for the new plant
such that the distance moved in transporting the
materials to the existing facilities is minimized.
Single Facility Location - MINISUM

X=900
Single Facility Location - MINISUM

X=900
Y=500
Multi-facility Location – Transportation Problem
Multi-facility Location – Transportation Problem
Multi-facility Location – Transportation Problem

Balanced Transportation Problem


Multi-facility Location – Transportation Problem

Unbalanced Transportation Problem – Total Supply exceeds Total demand


Multi-facility Location – Transportation Problem

Unbalanced Transportation Problem – Total demand exceeds Total supply


North-West corner method

 A company has three plants A, B and C which supply a product to six


major distribution centres 1, 2, 3, 4, 5, and 6. The table below gives the
transportation costs per unit, the annual plant capacities and the
forecast of the demands at various centres.
 Formulate a transportation model and thus determine how the products
should be supplied from the plants to the distribution centres as per
North-West corner method.
North-West corner method
North-West corner method
North-West corner method
North-West corner method
North-West corner method
FACILITY LAYOUT

C O M P I L E D B Y:
P R O F. A . M . G O H I L
INSTITUTE OF TECHNOLOGY
NIRMA UNIVERSITY

9/20/2024 8:50:27 AM
CONTENT

 Computerized Relative Allocation of Facilities


Techniques (CRAFT)
 Automated Layout Design Program (ALDEP)

9/20/2024 8:50:27 AM
Overview of plant layout problem

 How plant layout problem arise?


 Communication for effective plant layout.
 ‘Satisfactory solution’ using ‘component approach’
 Objectives
 Constraints

9/20/2024 8:50:27 AM
• Input Data and Activities
• Assembly chart
• Bill of materials
• Operation process chart

Systematic layout planning procedure 9/20/2024 8:50:27 AM


Horizontal flow pattern

Factors affecting
flow pattern

9/20/2024 8:50:27 AM
Vertical flow pattern

9/20/2024 8:50:27 AM
Types of layout

9/20/2024 8:50:27 AM
Activity relationship analysis

9/20/2024 8:50:27 AM
Activity relationship diagram

9/20/2024 8:50:27 AM
CRAFT

 Developed by Armour and Buffa


 Improvement type algorithm
 Minimizes – transportation cost

9/20/2024 8:50:27 AM
CRAFT Procedure

1. Inputs
1. Number of departments
2. Number of interchangeable departments
3. Initial layout
4. Cost matrix
5. Flow matrix
6. Area of departments
2. Compute centroids of departments in present layout
3. Form distance matrix using the centroids
4. Compute total handling cost of the present layout
5. Find all the pair wise interchanges of departments based
on ‘common border’ or ‘equal area’

9/20/2024 8:50:27 AM
CRAFT Procedure

6. Find the pair with minimum handling cost


7. Is the cost less than the total cost of present layout? If
yes, goto step 8. If not, goto step 11.
8. Interchange the selected pair of departments. Call this as
NEW LAYOUT. Compute centroids, distance matrix and
total cost.
9. Is the cost of new layout less than the cost of present
layout? If yes go to step 10. If not, go to step 11.
10. New layout is considered as PRESENT LAYOUT. Goto
step 5.
11. Print the present layout as FINAL LAYOUT
12. Stop

9/20/2024 8:50:27 AM
CRAFT

6 4

4 A B

4 C D

4 6
•Number of departments
•Number of interchangeable departments
•Initial layout
9/20/2024 8:50:27 AM
CRAFT

To
A B C D

A - 1 1 1
B 1 - 1 1
From

C 1 1 - 1
D 1 1 1 -
•Cost matrix

9/20/2024 8:50:27 AM
CRAFT

To

A B C D

A - 1 1 3

B 2 - 2 1
From

C 0 2 - 2

D 1 4 3 -

•Flow matrix

9/20/2024 8:50:27 AM
CRAFT

6 4 Centroid
X Y
4 A B A 3 6
4 C D B 8 6
C 2 2
4 6 D 7 2

•Centroid

9/20/2024 8:50:27 AM
CRAFT

Centroid
X Y •Rectilinear distance measure
•Di = |X-Xi|+ |Y-Yi|
A 3 6
B 8 6 To
C 2 2 A B C D
D 7 2 A - 5 5 8
From B 5 - 10 5
C 5 10 - 5
D 8 5 5 -
•Distance matrix

9/20/2024 8:50:27 AM
CRAFT

To To
A B C D A B C D
A - 1 1 1 A - 1 1 3
From

B 1 - 1 1

From
B 2 - 2 1
C 1 1 - 1 C 0 2 - 2
D 1 1 1 - D 1 4 3 -
•Cost matrix •Flow matrix
To To
A B C D A B C D
A - 5 5 8 A - 5 5 24
142
From

B 5 - 10 5
From
B 10 - 20 5
C 5 10 - 5 C 0 20 - 10
D 8 5 5 - D 8 20 15 -
•Distance matrix •Total cost matrix
9/20/2024 8:50:27 AM
CRAFT

6 4 Pair Remark
A&B Common Boarder
4 A B A&C Common Boarder
A&D Equal Area
4 C D
B&C Equal Area
B&D Common Boarder
4 6
C&D Common Boarder

•Pair wise interchange

9/20/2024 8:50:27 AM
CRAFT

4 6

4 B A
4 C D

4 6
•A & B interchange

9/20/2024 8:50:27 AM
CRAFT

Centroid
X Y To
A 7 6 A B C D
B 2 6 A - 1 1 1 CM

From
B 1 - 1 1
C 2 2 C 1 1 - 1
D 7 2 D 1 1 1 -

To To
A B C D A B C D
A - 5 9 12 A - 1 1 3
FM
From

From
B 10 - 8 9 B 2 - 2 1
C 0 8 - 10 C 0 2 - 2
D 4 36 15 - D 1 4 3 -

To
TCM A B C D
126 A - 5 9 4
From

B 5 - 4 9
C 9 4 - 5 DM
D 4 9 5 -

9/20/2024 8:50:27 AM
ALDEP

 Automated Layout Design Program


 Construction type algorithm
 Data required
 Total number of departments
 Area of each department
 Length and width of layout
 Closeness ratings of various pairs of departments
 Minimum department preference (MDP) value
 Sweep width
 Number of iterations to be performed
 Fixed area if any

9/20/2024 8:50:27 AM
ALDEP

Department Area sq m No. of square


1 16000 40
2 24000 60
3 10000 25 Number of
4 20000 50 department
5 16000 40 1 Sq. = 400 sq m
6 12000 30
98000 245

L 18
W 14
Total 252
9/20/2024 8:50:27 AM
Facility Layout Design

 Automated Layout Design Program(ALDEP)


 Construction type algorithm
 Data required
 Total number of departments
 Area of each department
 Length and width of layout
 Closeness ratings of various pairs of departments
 Minimum department preference (MDP) value
 Sweep width
 Number of iterations to be performed
 Fixed area if any

9/20/2024 8:50:27 AM
ALDEP

Department Area sq m No. of square


1 16000 40
2 24000 60
3 10000 25 Number of
4 20000 50 department
5 16000 40 1 Sq. = 400 sq m
6 12000 30
98000 245

L 18
W 14
Total 252
9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1
2
3
4
5
6
7
8
9
10
11
12
13
14

9/20/2024 8:50:27 AM
ALDEP

To
1 2 3 4 5 6
1 - A O E I E
2 A - U E A I
From

3 O U - I U O
4 E E I - I E
5 I A U I - A
6 E I O E A -

Relationship chart

9/20/2024 8:50:27 AM
ALDEP

Closeness Notation Value


Absolutely necessary A 64
Essentially important E 16
Important I 4
Ordinary closeness OK O 1
Unimportant U 0
Not desirable X -1024
Closeness rating

Minimum department preference value MDP = 4


Sweep width =2
Location of fixed department = Nil
9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 4 4
2 4 4
3 4 4
4 4 4 4 4
5 4 4 4 4
6 4 4 4 4
7 4 4 4 4
8 4 4 4 4
9 4 4 4 4
10 4 4 4 4
11 4 4 4 4
12 4 4 4 4
13 4 4 4 4
14 4 4 4 4
9/20/2024 8:50:27 AM
ALDEP

To
1 2 3 4 5 6
1 - A O E I E
2 A - U E A I
From

3 O U - I U O
4 E E I - I E
5 I A U I - A
6 E I O E A -

List A = { Nil}
List B = {1, 2, 3, 5, 6 }

9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 4 4 1 1 1 1
2 4 4 1 1 1 1
3 4 4 1 1 1 1
4 4 4 4 4 1 1
5 4 4 4 4 1 1
6 4 4 4 4 1 1
7 4 4 4 4 1 1
8 4 4 4 4 1 1
9 4 4 4 4 1 1
10 4 4 4 4 1 1
11 4 4 4 4 1 1
12 4 4 4 4 1 1 1 1
13 4 4 4 4 1 1 1 1
14 4 4 4 4 1 1 1 1
9/20/2024 8:50:27 AM
ALDEP

To
1 2 3 4 5 6
1 - A O E I E
2 A - U E A I
From

3 O U - I U O
4 E E I - I E
5 I A U I - A
6 E I O E A -

List A = { 3}
List B = {2, 5, 6}

9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 4 4 1 1 1 1 2 2 2 2
2 4 4 1 1 1 1 2 2 2 2
3 4 4 1 1 1 1 2 2 2 2
4 4 4 4 4 1 1 2 2 2 2
5 4 4 4 4 1 1 2 2 2 2
6 4 4 4 4 1 1 2 2 2 2
7 4 4 4 4 1 1 2 2 2 2
8 4 4 4 4 1 1 2 2 2 2
9 4 4 4 4 1 1 2 2 2 2
10 4 4 4 4 1 1 2 2 2 2 2 2
11 4 4 4 4 1 1 2 2 2 2 2 2
12 4 4 4 4 1 1 1 1 2 2 2 2
13 4 4 4 4 1 1 1 1 2 2 2 2
14 4 4 4 4 1 1 1 1 2 2 2 2
9/20/2024 8:50:27 AM
ALDEP

To
1 2 3 4 5 6
1 - A O E I E
2 A - U E A I
From

3 O U - I U O
4 E E I - I E
5 I A U I - A
6 E I O E A -

List A = { 3}
List B = {5,6}

9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 4 4 1 1 1 1 2 2 2 2 5 5 5 5
2 4 4 1 1 1 1 2 2 2 2 5 5 5 5
3 4 4 1 1 1 1 2 2 2 2 5 5 5 5
4 4 4 4 4 1 1 2 2 2 2 5 5 5 5
5 4 4 4 4 1 1 2 2 2 2 5 5 5 5
6 4 4 4 4 1 1 2 2 2 2 5 5 5 5
7 4 4 4 4 1 1 2 2 2 2 5 5 5 5
8 4 4 4 4 1 1 2 2 2 2 5 5 5 5
9 4 4 4 4 1 1 2 2 2 2 5 5 5 5
10 4 4 4 4 1 1 2 2 2 2 2 2 5 5
11 4 4 4 4 1 1 2 2 2 2 2 2 5 5
12 4 4 4 4 1 1 1 1 2 2 2 2
13 4 4 4 4 1 1 1 1 2 2 2 2
14 4 4 4 4 1 1 1 1 2 2 2 2
9/20/2024 8:50:27 AM
ALDEP

To
1 2 3 4 5 6
1 - A O E I E
2 A - U E A I
From

3 O U - I U O
4 E E I - I E
5 I A U I - A
6 E I O E A -

List A = { 3}
List B = {6}

9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
1 4 4 1 1 1 1 2 2 2 2 5 5 5 5 3 3 3 3
2 4 4 1 1 1 1 2 2 2 2 5 5 5 5 3 3 3 3
3 4 4 1 1 1 1 2 2 2 2 5 5 5 5 6 6 3 3
4 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
5 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
6 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
7 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
8 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
9 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
10 4 4 4 4 1 1 2 2 2 2 2 2 5 5 6 6 3 3
11 4 4 4 4 1 1 2 2 2 2 2 2 5 5 6 6 3 0
12 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
13 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
14 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
9/20/2024 8:50:27 AM
ALDEP

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 Neighbour
Rel. Rel.
Grade Value
1 4 4 1 1 1 1 2 2 2 2 5 5 5 5 3 3 3 3
4-1 E 16
2 4 4 1 1 1 1 2 2 2 2 5 5 5 5 3 3 3 3
1-2 A 64
3 4 4 1 1 1 1 2 2 2 2 5 5 5 5 6 6 3 3 2-5 A 64
4 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3 2-6 I 4
5 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3 5-6 A 64
5-3 U 0
6 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3
6-3 O 1
7 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3 SCORE 213
8 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3 Two-way
426
9 4 4 4 4 1 1 2 2 2 2 5 5 5 5 6 6 3 3 Rel. Score

10 4 4 4 4 1 1 2 2 2 2 2 2 5 5 6 6 3 3
11 4 4 4 4 1 1 2 2 2 2 2 2 5 5 6 6 3 0
12 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
13 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
14 4 4 4 4 1 1 1 1 2 2 2 2 6 6 6 6 0 0
9/20/2024 8:50:27 AM