Adobe Scan 13 Jun 2024

The Electricity Audit Report for the Bangalore 6 branch, conducted on June 27, 2023, indicates that the branch has a connected load of 35.91 KW and a recent energy consumption of 1570 KWH with a bill amount of Rs 20,408. The audit found no frequent power breakdowns, very rare irregular tripping, and the overall condition of electrical installations is reported as good. Additionally, the branch is equipped with UPS systems, proper earthing, and has no DG set backup.

Uploaded by

Anil Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views

Adobe Scan 13 Jun 2024

The Electricity Audit Report for the Bangalore 6 branch, conducted on June 27, 2023, indicates that the branch has a connected load of 35.91 KW and a recent energy consumption of 1570 KWH with a bill amount of Rs 20,408. The audit found no frequent power breakdowns, very rare irregular tripping, and the overall condition of electrical installations is reported as good. Additionally, the branch is equipped with UPS systems, proper earthing, and has no DG set backup.

Uploaded by

Anil Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

--

ELECTRICITY AUDIT REPORT

Branch : Bangalore 6 Branch Code : 0561


Type of Branch : DO. Year of Opening : 2016
Region : Bangalore Date of Audit : 27-06-2023

1st floor, S.N.P. pl aza , K.R. Puram extensi on, OMR M ain
1 Address of branch/offic e Road, Bangalore - 560036
2 Name of Engineer Nilesh Behare
3 Qualificatio n of Engineer (attach certificate) B.E. Electrical
(a) Digital Clamp Mete r, Sr. No. 22 30 -1323124
Measuring Instrument (b) Digital Earth Tester, Sr. No. 386571
4
(Make and Model) (c) Thermal lmager Fl ir one pro.
(d) -
Is there any power breakdown that results
5 frequently in the branch- If so - is it regular/ Irregular.
irregular?
Opinion of the Branch Manager regarding frequent No Power breakdown .
6
power breakdown /shut down
Is there any irregular tripping that exists in the
7 branch? - If so - is the tripping - frequent/ occasional Very Rarely.
/ very rarely?
8 Building/ Premises establishme nt year. 2015
Whether same wiring/cabli ng used while occupying Same Cabling Used.
9
the space of new cabling done?

A. Meter Details
Description Observation
1 Name of State Electricity Board Bangalore Electricity Supply Company Limited.
2 Type of metering (LT/HT) LT
3 Incoming Supply (Single OR Three Phase) 3 Phase
4 Sanction load (kW) 30 KW
5 Connected load (kW) 35 .91 KW
Latest Energy Consumption of Branch/Office in KWH 1570 KWH
6
and Bill amount in Rs 20,408.
Actual used load of the branch . 3.88 KW
7
Energy Consumptio n of Branch/Office For last 6 Total KWH Total Amount
8 months. Month- KWH & Amounts (Total) 6550 90,144
Average power factor during last quarter 0.98
9
Size Of Incoming S.E. Board Cable/Wires 35 SQMM, Al. cable
10
Condition Of Incoming Cable/ Wires Joints/ Burnt Ok, Good condition .
11
Insulation if any.
Whether Temperatur e of Incoming cable Hot/ Normal.
12
Normal
Whether Cable are loose? /Condition of connector. No loose connection.
13
Whether Utility Supply meter lPh/ 3Ph and its Volt, 3 phase, 440 Volt, 3X240 Volt.
14
Am p Capacit y.
Output wire Size from Utility Meter to Fuse/ MCB/ 35 SQMM connected to 63A, SFU.
15 MCCB/ SFU switch etc.
Output of Meter wires are terminated in Fuse OR Terminated to 63A, SFU, Aluminum lugs used.
MCB OR MCCB OR SFU units with Amp. Capacity of
16 Switchgear & no of poles . Whether
Copper/Alim unium lungs used?
No Of Earth wires with Incoming Utility Supply 2 Nos': 4 SQMM .
17 cable/Wires and their Size in Sqmm/ SWG

.,,,. . ·---,
3 Pole MC CB in M ain DB
35 SQMM . connected to 100A, ,
f FUSE/ MCB/
Size of Cable/Wires in Sq .mm rom ·t h/
Main SwI c
M CCB/ SFU at output of meter to . .
. (S ate switch Is
18 MCB/ MCCB in Branch/Office epar .
. · ted directly In
provided . OR the wires are term1na
Main DB Incomer. Pl. indicate) .• 2 NOS, 4 SQMM .
No of Earth wires connected to main· DB Is it a Utl 1Ity
19 Earth Or Separate Building Earth wire/s . B- N: 236 N- E: 0 .3 Volt
R- N: 237 Y-N : 235
20 Voltage at incoming panel (V) lb : 0 .7 A In : 10.9 A
Ir: 4.9 A ly: 12.1 A
21 current at incoming panel (A)
3.88 KW
22 Total Measured load (kW/kVA)

B. DG Set
DG Set Not Provided .
Whether DG set back up is provided? If YES
1 Whether by Landlord OR SBI Life? Any AMC?
Capacity Of DG set in KVA & Whether single/3 Not Applicable
2
phase?
Whether AMF panel is provided at the DG set OR Not Applicable
3 Manual Changeover switch is provided? Its capacity
& no of poles.
Whether separate earthing provided to Neutral & Not Applicable
4 body of D.G. set and brought with D.G. cable/wires
up to Change-over Switch.
5 DG set Output Voltages Not Applicable
Whether full OR part load put on DG set? Total load Not Applicable
6
on DG
Whether D.G. is operated by the operator Not Applicable
7
appointed by Landlord OR SBI Life?
Whether D.G. set operator is well conversant with Not Applicable
8
operation & electrical safety aspects?
9 Resistance of earth pit/ earth wire in Ohms. Not Applicable

C. UPS & Inverter


1 Total no Of UPS in the branch 2 Nos.
KVA Capacity & Make of UPS. 3 KVA X 2nos, Emerson, 1 Phase.
2 Whether Incoming supply to UPS is 3 phase or 1
Phase
Voltage, AH capacity & make of batteries & their 12V, 65AH, Amaron Quanta, 8 Nos, SMF Type.
3
Quantities (Whether SMF/ Tubular) 12V, 65AH, Amaron Quanta, 12 Nos, SMF Type .
Whether batteries installed in UPS cabinet OR Yes, Separate rack is provided.
4
Separate battery rack is provided?
5 Are battery rack provided with earthing? Yes, Earthing is provided.
UPS & batteries are kept in a separate room Or in Yes, Separate Room is provided
6
Hall?
In case a separate room is provided whether AC or Yes, AC is provided for ventilation but not working
Exhaust fan is provided for ventilation? In case of condition .
7
hall whether proper Exhaust fan provided near UPS
batteries?
Whether battery room is clean? & No waste
Yes, Battery room is clean.
8 papers/files OR other material stored/put over
them? Room is clean?

9
Condition Of Batteries & Total battery voltage as per
quantity & ratin g. Ok, Good condition, 12X8= 96 Volt, 12X12= 144 Volt.
10 UPS Output Voltages (V)
L-N : 230 L-E : 230
11 Load on the UPS output (A) N-E : 0 .3 Volt
0 .SA & 0 .8
Whether iw~'l nput/ Output wires are laid through
12 Conduit Pipe Used .
conduit pipe OR Armored cable used?
/4l}--~<f\
' '-Pt ~
v,\t'~).,'OJ
Wheth ~ ,separate Inverter is provided for Lighting
13
j :if ~~}
14
of bra nch?

.. . •. .
Inverter Ra_ting & batteryjletails.
Yes, Provided.
,~\
Inverter 1.1 KVA- Sukam, Battery- lS0AH,\.: '- ...,.
Tubular Type. ~ ~
,.-{'~
✓t
__.....,,,
'-......J 8 1. "n ':>
.
-

D. Server Rack/ Switch Room Yes, Serv er rack Foun d Locked .


etc kept in locke d
Whe ther Serv er sw itch/ switc hes
1
serve r rack OR in open ?
Yes, Earth ing is Co nn ect ed
2 Whe ther Serv er rack is earth ed ?
red place in hall ? Yes, Prov ided
3 Sepa rate Serv er Room OR in secu Co2 t ype
ed close /reas onab le Yes, locat ed close d near 1 M ete r,
Is Fire extin gu isher locat
4 er/UP S & Type of Extin gu isher?
dista nce from Serv sed.
h prop erly dres sed ? OR Yes, Data cable are prop erly dres
Are CAT5/6 cables to switc
5
hanging?

E. Air- Conditioners
of each type in Spl it - lton - 3Nos , Cass ette AC -
3 t o n - 5 Nos, Sp it - 1.5
Type & Tonn age capa city+ Qua ntity
1 ette/ Pack aged} t on - 2 Nos
Br/O ff. (Win dow / Split / Cass
? Yes, Time r is prov ided
Whe ther time r is prov ided
2 not wo rk ing cond it ion .
SBI LIFE & SBI Life, Unde r AM C But som e AC
AC Units prov ided by Land lord OR
3 r AMC ?
whe ther unde
OR norm al Yes, Meta ll ic s/s is prov ided .
Whe ther Meta llic S/S is prov ided
4
Switc h/So ckets ? .
ided ?/ Need ed if Yes, Volta ge Stab ilizer is prov id1;d
Whe ther Volta ge stabi lizers prov
5 exist s in area?
w ide volta ge fluct uatio n

F. General Parameters
Norm al
Norm al/ Dull/
Whe ther illum inati on of Branch is
1
I Very brigh t?
es? Ok, Good cond it ion .
2 Wha t is cond it ion Of light ing fixtur
.C.B. to indiv idual NO, Not Pasted on DB .
Whe ther load distributi on from M
3 in DB?
circu it is indic ated by char t paste d
Draw ing avail able in Bran ch/ office ? Yes, Avai lable .
4 Is any AS BUIL T
oard not prov ided .
d on D.B. Yes, Pasted on DB & Woo den cupb
Is Electrical Dang er mark stick er paste
is enclosed in a
5 Cover? Or on wood en door if D.B.
wood en cupb oard ?
in wood en Not Appl icabl e
If DB/ Main Switc hgea r is enclosed
prov ided? Are any
6 cupb oard any vent ilatio n louve rs
mate rials dum ped in the cabin et?
e as repo rted Norm al.
No of powe r fa ilures in Bran ch/ Offic
rge? Whe ther
7 by Bran ch/ Offic e Adm in lncha
High?
Incom ing Voltages Norm al/ Low/
g of Bran ch/ Offic e Needed
Whe ther the wirin
Insul ation with MEG GAR Instr ume nt by Not requ ired.
checking of
ition of wirin g
8 taking total shut down (based on cond
main panel,
& it ' s life perio d cond ition 8 years) . For
er DB and Light ing DB.
UPS DB, Raw Pow t.
How man y DB' s are prov ided in Bran
ch office ? 4 Nos, Details attac hed sepa rate shee
9 Com mon ?
Pow er/ Ligh t/ UPS sepa rate UPS or
Give Details Of Inco mer/ Outg oing
Swit ch/ ELCB/ Attac hed sepa rate shee t
( For more Nos attac h
10 MCB / MCCB in each DB
sepa rate sheet)
If ELCB is provided in main / Sub DB
their mA & Amp Attac hed sepa rate shee t.
11
ratings.
Sq .mm Copp er w ire .
Incom ing & Outp ut Switc hgea r ratin
gs for UPS & Inpu t & Outp ut not prov ided, 2.5
12 whet her prop er no & size of earth wires are
connected to DB's
able? Yes, Prov ided .
13 Whe ther Separate Build ing Earth Pit is Avail
as meas ured in 2.8 Ohm .
Resistance of earth pit/ earth w ire
ked at
Ohm s. Wh~ther above Resistance is chec
14 Earth Clam p/
earth pit C?r at 'D.a: earth wires with
Ton g teste r?
3 phase
th.er doub le earth ing Is prov ided for Yes, Doub le Earth ing is prov id ed._
15 Whe . I
DB? ~c.;::..,.
✓ -

t,,v ~~
I.I I SBI0l.ife .,
~
1

~w ~ l
be; -
Total Watts
G. Connected Load Calculation
Watts
Quant ity
24850
-
Equipment's 5+3+2
3600+1150+1700 0
ACs 0
Tube Lights
0 1008
84
12 0
CFL/LED 0
Water Cooler 0 2400
2400 1
UPS 1 2400
2400 1
UPS 2 400
250+150 1+1
Printer/ Scanner 1790
110+90 4+15
Computer/L aptop 1260 \
40 + 500 19+1
Fan+ Other 1800
1800 1
Pantry Equipment 35,908 watts, 35 .91 KW

Total Connected Load: 35,908 watts, 35.91 KW


y LOB, cable
H. Thermograph (Delta T} Readings- Main DB, Raw Power DB , LDB, UPS O/P DB , Emergenc
temperatu re)
joints etc {Delta T criteria is the temperatu re above the temperatu re of ambient air
' Likely Cause of Deviation and
DP Location, Delta T T Image/ Pie (cable T Image/ Pie (Live
Room Temp, cable) Corrective Actions
not Live)
Ambient Temp
s· c Not Applicable 20230627_ 035519 Nil
1. Main DB
AT= 29°C
RT= 22°C

2. AC & RPDB 2.s·c Not Applicable 20230627_ 035614 Nil


AT= 29°C
RT= 22°C
3. UPS DB 2.s·c Not Applicable 20230627_035646 Nil
AT= 29°C
RT= 22°C
4. Light DB 2.5°C Not Applicable 20230627_035725 Nil
AT= 29°C
RT= 22°C

Thermograp hy report will be submitted on later.

~
. F"ire T ram· ·ne./
1 lnsoection Form for Branches/ Offices
Essentials Inform ation
24 Nos
1 Total No of Staff includin g Branch manage r.
Date : 13-3-20 23 Persons presen t : 17 Nos.
Dates of last two emerge ncy evacua tion drill last
2 Date : 7-9-2022 Person' s presen t : 16 Nos.
held and persons presen t
& UPS Yes, Availab le.
Are danger boards availab le at electric al
3
room?
Yes, Dis played .
4 Are fire exits signs installe d at floors?
Yes, Displayed .
Are emerge ncy contact Nos. display ed in English,
5
Hindi & Local language?
Yes, Display ed .
6 Are emerge ncy exit maps display ed at floors?
Yes, Availab le.
Is First Aid Box availab le along with approp riate
7
fillings? ABC Type : 3
BC Type : NA

I
A Type: NA
How many Nos of Each categor y of Fire Type : NA
CO2 Type :2 DCP
8 Extinguishers are availab le in branch / office with
their capacities :
Yes, ISi Marked .
9 Are all the Fire Extingu ishers ISi marked ?
Yes, Visible & Accessible .
Are all the Fire Extingu ishers installe d at visible and
10
accessible places?
Yes, Servicing & refiling done on periodi cally.
Are fire extingu ishers servicin g & refilling done as
11
per require d periodi city?
Yes, they know to operate .
Do the staff membe rs know to operate the fire
12
extingu ishers
Yes Availab le.
Is any Fire Extingu isher Type & Operat ing chart
13
available near Extingu isher/s?
ion
J. Energy and Cost Saving as a Result of the Audit/ Inspect
rectifica tion Nil.
Estimated energy to be saved after
1
of risk factors (if any-in watt/kW )
Estimated cost reducti on/ cost saving as a result Nil.
2 n (if any)
of the audit/in spectio
ation
K. Safety Observations, Hazards and Suggestions for Rectific
n in Last Presen t Status -Rectif ied/ Still pending.
Sr Major Observ ations/ recomm endatio
Audit Report Dated: 3-9-202 2

In UPS, Earthin g wire is not connec ted Rectified .


1

Main DB door earthin g is open Rectified .


2

Sr Current (to include old un-rectified) Major Hazard Suggestion/ Recom menda tion
Observations Rating for rectification.

30mA RCCB is not provide d to Inverte r Output . Averag e 30mA RCCB should be provide d to Inverte r
1 Hazard Output .
Correct rating switchgear should be provided to
Average
Incorrect Switchgear rating provided to ACDB ACDB . (63A- l00mA- 4 pole RCCB)
Hazard
2 {25A-100mA- 4 Pole- RCCB)

UPS room AC should be in working condition for


Average
UPS room AC & Hall AC's not working condition Ventilation and all AC should be in working
Hazard
3 condition .

.
9

L.
nn:1
Overall, Hazard rating of the Branch/ Office, (Extreme/Ultra I Av erage/ Less Hazard - based on th
\w.mlJt ._S
b .
e O sen,at,oas).
Average Hazard .
S 3,1 Ccocu II I

(crt)
'~
Nam!/'-',/~/,. ~eJfov.z_ ~ Name & Signature
Branch Manager

Audit Ag

OSBILife Apne liye . .-.-;fT1'1"1o- N


Ban galore 6 Branch MCB Details.
F- 10: Details of incomer/ outgoing switch/ ELCB / MCB/MCCB IN Each DB .

1. Main Switch : 63A- SFU- 1 Nos.

2. Main DB : lO0A-3 Pole- MCB-lNos.


C63A- 3 pole - MCB- 6 Nos.
C32A-1 Pole - MCB - 2 Nos.
C16A- Single Pole - MCB - 1 Nos .
C40A -3 Pole - MCB -1 Nos.

3. AC & RPDB: l00mA- 25A- 4 pole - RCCB -1 Nos.


C16A- Single Pole - MCB - 4 Nos.
Cl0A- Single pole MCB- 4 Nos.
C25A- Single Pole- MCB- 5 Nos.

4. UPS DB: 100mA-25A - 2 pole -RCCB -1 nos.


Cl6A - Single Pole MCB - 4 Nos.
Cl0A- Single Pole MCB- 4 Nos .

5. Light DB: 30mA- 40A- 2 Pole - RCCB -1 Nos.


C16A- Single Pole - MCB- 3 Nos .
ClOA- Single Pole - MCB- 5 Nos.
6. Inverter: Input & Output: C32A -02 Pole- MCB - 2 Nos.

F- 11: Deta ils of ELCB / RCCB .

1. LDB : 30mA- 40A- 2 Pole- RCCB -lNos

2. UPS DB : 100mA -25A-2 Pole RCCB -1 Nos .

3. AC & RPDB: lO0mA- 25A- 2 Pole- RCCB- 1 Nos.

Energy consumption of 581 Life Bangalore 6 Branch office for last 6 Months.

Month KWH Amount


May - 2023 1570 20408
April- 2023 1620 20402
Mar - 2023 1270 16708
FEB - 2023 770 11504
Jan - 2023 640 10417
Dec-2023 680 10705
Total 6550 90,144