INSTITUTE OF MUSIC LANGUAGES AND POLYTECHNIC
STUDIES
UBT434/2024/T/C/M/0044
DECLARATION
I TABI STEPHEN declare that the work embodied in this report is my original work to the best of my
knowledge and it has never been submitted for any academic award in any academic institution.
TABI STEPHEN
UBT434/2024/T/C/M/0044
Sign……………………………….. Date…………………………
(i)
UBT434/2024/T/C/M/0044
APPROVAL
This report has been presented for a review with approval of my supervisor and field supervisor
Field Supervisor;
Mr. KASULE COSMAS
Signature…………………………………
Date………………………………………
INSTITUTE SUPERVISOR;
Mr. LUKANGA JULIUS
Signature ………………………………….
Date…………………………………………..
HEAD OF TRAININGS;
MR KASULE COSMAS
Signature......................................
Date............................................
(ii)
UBT434/2024/T/C/M/0044
ABSTRACT
This project involves a combination of subjects’ knowledge, process skills and transferable abilities.
Learners have to apply classroom knowledge and skills proactively in a real-life context for an
extended period of time. Each learner will be required to run a real life project outside classroom
time. At the end of every academic year a learner should have a visible real life project on the ground
to be authenticated by UBTEB and the major activities carried out in the field included installation of
both electrical and solar components such as security lights, repair of solar batteries, carrying out
conduit work on buildings, making earthing and installation of solar systems on buildings
(iii)
UBT434/2024/T/C/M/0044
ACKWOLEDGEMENT
I extend my thanks to my parents and my field supervisor Mr. KASULE COSMAS for training and
grooming me into hard-working man. I highly appreciate my sister Endreo Betty and my brother
Kandaruku Charles for the extra support of paying my tuition till this level. I thank the almighty God
who has granted and helped me to do this work till accomplishment and I continue thanking the
management of Kasule Electricals and Solar Systems Who granted me this opportunity to work with
them from 16th December 2024 to 25th January 2025. I extend my appreciation to my fellow
internees and my field supervisors who have Been guiding me during this time of internship and I also
thank the company for the love and the things they have showed me during the time I have been
working with them.
(iv)
UBT434/2024/T/C/M/0044
CHAPTER ONE
1. INTRODUCTION
This field report shows all the activities we students we engaged in during the internship at Kasule
Electricals and Solar Systems from 16th December 2024 to 25th January 2025. In the supervision of
Mr. KASULE COSMAS
This report is made up of four chapters which consist of the all activities carried out, hazards
faced, risks and precautions. This report also shows how I applied the techniques and principles I
learnt theoretically by analyzing and solving real life challenges.
1.1 AREA SCOPE
Kasule Electricals and Solar Systems has been my area scope and it is located on in Nyendo
Kitovu road in Masaka city.
1.1.2 TIME SCOPE
Internship at has been for six weeks and it began on 16th December 2024 to 25th January 2025.
1.2. BACKGROUND OF THE FIELD ATTACHMENT
The main reason of doing this field attachment is link theoretical work to practical work thus over
coming real life challenges. The purpose of involving the students into the field attachment is to
help them to build their thinking capacity hence overcoming and solving the daily challenges in
work.
1.3. OBJECTIVES OF THE FIELD ATTACHMENTS.
To strengthen the relationships between the institutes and the organization hence
enhancing linkages.
To enable me to apply techniques and principles learnt theoretically into solving real life
problems.
To demonstrate my ability of communication both orally and in written information in a
manner that reflects professional working skills
To develop students in understanding of work ethics, interpersonal relationships at work,
employment demand, responsibilities and opportunities
UBT434/2024/T/C/M/0044
CHAPTER TWO
2.1. COMPANY BACKGROUND
Kasule Electricals and Solar System is a private company and its incorporation date is 8th August
2018 and it is located in Nyendo. It specializes in domestic and industrial installation in both Solar
and Electrical Supply.
2.2.1 COMPANY MISSION
To constantly deliver value by constantly achieving standard operation and solar installation
excellence, conducting our business in a safe.
2.2.2 COMPANY VISION.
To be the top performing and most admired engineering, procurement and construction of choice
in Masaka.
2.2.3 COMPANY OBJECTIVES
To provide professional and standard electrical services to various sectors of the economy by
focusing on how best we meet our customer requirements and ensure safety in all we do.
2.3.1 KASULE ELECTRICALS AND SOLAR SYSTEMS HEALTH AND SAFETY POLICY
The management takes responsibilities below;
Carry out risk assessments and review them when necessary.
Issue and enforce proper use of PPE.
Safety meeting should be mandatory and regular when called for.
Make adequate provision and arrangement for welfare facilities at work.
Monitor safety performance to maintain the greed of standards.
Mandatory report of accidents / incidents /near miss should be done immediately.
No frictional relationship that will be allowed between co-workers.
Tools and vehicles should always be inspected before commencement of their respective
work Facilities for the welfare of workers to maintain health and safety.
Information, instruction, training and supervision that is reasonably to ensure that each
worker is free from injury and risks to health.
A commitment to consult and co-operate with workers in all matters relating to health and
safety in the workplace
UBT434/2024/T/C/M/0044
7
CHAPTER THREE
3.1 ACTIVITIES CARRIED OUT IN FIELD, CHALLENGES FACED, RISKS AND PRECAUTIONS
As a student I was working as a trainee in the organization under the supervision of Mr.
Kasule Cosmas and correspondence assistants called Mr. John. And in among the activities we
carried out under their supervision included the following.
3.1.1. OFFLOADING MATERIALS
Offloading of materials was so tiresome since it incurred moving the materials from the car to
the company store.
3.1.2. MATERIALS INCLUDED
Solar modules
Solar batteries
Cables
Switch and sockets
Inverter
Change over switch
The evidence 3.1 attached below shows me offloading materials
Figures above showing me offloading materials
UBT434/2024/T/C/M/0044
3.1.3 CHALLENGES FACED
o Distance to reach the store also challenged me
o I got Cuts and wounds on my hands since we were using sharp objects.
o The materials were so heavy more soothe batteries
o The work was so tiresome
o The work was so dusty and dirty
3.2. MOUNTING OF SOLAR PANELS
This work includes placing them on racks.
3.2.1TOOLS USED TO MOUNT SOLAR PANELS.
Digital meter
Phase taster
Pier
3.2.2. FUNCTIONS OF THE ABOVE STATED TOOLS
Digital meter
To measure current and voltage produced by the solar module
Phase taster
To taste phase.
Pier
To cut cables and to twist cables.
3.2.3. CHALLENGES FACED
a) I got wounds and cuts when cutting cables
b) I got difficult in moving mounting solar modules since they were heavy and delicate.
c) Accidents like falling from the ladder to the ground
d) Challenged by tying cables on a cable tie.
UBT434/2024/T/C/M/0044
9
THE FIGURE BELOW SHOWS PANELS MOUNTED ON RACKS
3.3 MOUNTING OF GRID FELICITY SOLAR INVERTERS
During mounting of the felicity solar inverters we connected them in parallel connection in order
to balance the power and to strength wattage.
3.3.1 THE FOLLOWING ARE THE TOOLS WE USED TO MOUNT FELICITY SOLAR INVERTERS
Connecter
Pliers
Electrician knife
Phase taster
Network cables
Concrete nails
3.3.2 FUNCTIONS OF EACH TOOL STATED ABOVE
CONNECTOR
To connector different cables at the joint
To insulate cables to avoid live to connect with neutral cable
PLIER
• Used to cut cables.
• Used to twist cables.
• Used to remove sheath on the cable.
ELECTRICIAN KNIFE
To remove sheath on the cables
PHASE TASTER
To taste phase
UBT434/2024/T/C/M/0044
CONCRETE NAILS
To fix inverters on wall
3.3.3 CHALLENGES FACED
Tiresome
Making loose connection
Cuts and wounds
3.3.4 THE FIGURE BELOW SHOW ME MOUNTING GROWATT INVERTERS ON WAL
UBT434/2024/T/C/M/0044
11
3.4.1 INSTALLING CHANGE OVER SWITCH
3.4.2 Tools used
• Phase tester
• Pliers
• Connecters
3.4.3 HOW THE ABOVE TOOLS WHERE USED
PHASE TESTER
Was used to fasten of lights and supply cables in connectors
To taste phase
PLIER
To me remove sheath on the cable
To twist cables
3.4.4 Challenges faced
a. The work was so tiresome
b. Challenged by connecting power form the panels and power of hydro
c. Materials got used up which longed the work
d. Makin loose connections
e. Challenged by using applier to remove sheath on a cable
The evidence in form of a figure 3.2 below shows a changeover switch.
UBT434/2024/T/C/M/0044
3.5 CONDUIT WORK AND INSTALLATION ON BUILDING
This site incurred us to move to Kalangala in Maboga village
3.5.1 I FACED A LOT OF CHALLENGES TOWARDS THE SITES AND ON THE SITES IN AMONG THE
CHALLENGES I FACED INCLUDED
The work was so tiresome.
Walking long distances to the site location
Challenged by fixing metallic mold boxes in the wall without nails but with only cement
mixture
Tower clipping cables.
Cables termination and making cable joint.
Digging earthing pit since the area was to rocky
3.5.2 TOOLS USED INCLUDED
-Spade - Pliers
-Trowel -pickaxe
-Hammer - Phase taster
-Hoe -Chisel
BELOW ARE THE FINGERS 3.3 AND 3.4SHOWING ME TRYING TO REPLACE METALLIC METER BOX
IN THE WALL AND THE ACTIVITIES CARRIED OUT.
UBT434/2024/T/C/M/0044
13
3.6 INSTALLING ACCESSORIES
Accessories are components that cater for the work of appliances.
3.6.1 These included;
Circuit breakers
Socket outlets
Isolators
Switches
Evidence in form of figures 3.5andbelow show us installing switch
3.6.2 CHALLENGES FACED
I was challenged by installing 2way 3gang switch
Materials got used up which longed the work to the following day
UBT434/2024/T/C/M/0044
3.7 MOUNTING SOLAR MODULE ON ROOF
The follow are the photos showing me mounting solar module on roof.
3.7.1 CHALLENGES FACED
Making loose connection
Tiresome since we worked for long time
Stomach due to late eating which resulted into sickness thus missing some days of work.
INSTALLATION OF SOLAR BATTERIES
We installed batteries in series to increase voltage
1.8 HAZARDS FACED IN FIELD INCLUDED THE FOLLOWING.
1) SHARP TOOLS.These are tools which has sharp edges and these included;
Chisel
Nossal plier
Cutters
Drilling machines
Phase taster
UBT434/2024/T/C/M/0044
15
Pickaxe
Hammer
2) HEAVY TOOLS
The tools included;
Hoes
pickaxes
chisel
3) digital multmeter
4) phase tester
5) Screw driver
6) Electrician knife
3.9. RISKS FACED WHEN CARRYINGOUT ACTIVITIES IN FIELD
Are unexpected dangers that take place on our body when we are in field and these included;
Cuts and wounds since we were dealing with sharp objects
Electric shock since we were dealing with live circuits
Falling from ladders since the wooden ladders were so weak
Road accidents since the training involved moving long distances to the sites
Sickness since we were working in too much sunshine
Body pain due to pit digging
Making short circuits due to lose connections
Drilling big holes for lights
Falling
Broking glasses of the module
UBT434/2024/T/C/M/0044
3.10 PRECAUTIONS TO THE RISKS FACED IN THE FIELD
Putting on helmets in order to overcome the risks of head shock
Putting on gloves in order to overcome the risks of getting cuts and wounds
Putting on overalls in order to overcome the risks of cuts on body
Putting on safety shoes in order to overcome the risks of injuries on legs
Working under guides of field supervisors to overcome the risk of short circuit
Wearing personal protective equipment’s when dealing with live circuit
Using phase taster before dealing with any circuit
Switch off the supply when installing accessories to overcome the risk of electric shock
To use appropriate tools to overcome the risk of making lose connections which can result
into short circuits.
3.11. The figure below shows me putting on some of the safety measures I have
UBT434/2024/T/C/M/0044
18
CONCLUSIONS AND RECOMMENDATIONS
4.1 CONCLUSIONS
Kasule Electrical and solar system service ltd has played a very big role in helping me and my
fellow students in intern through teaching us and showing us the real life in electrical installation.
That is to say challenges in electrical installation, different wiring systems, site planning and
counting materials which are good for the installation thus enabling us to put in practice what we
have study at school.
4.2 RECOMMENDATIONS
4.2.1. To kasule Electrical and solar system service ltd. The board of kasule Electrical and solar
system should increase on the number of partner organization in order to widen on its market
since sometimes we have been not working due to few domestic jobs available to support
internees in domestic installation, repair and maintenance. The organization should also take a
step in awarding certificates to the internees as a way of proving their skills. The organization
should also give assistance to facilitate trainees during internship.
4.2.2. To the institute. The students should be given enough time to do internship and also visit
other institutes so as to widen their knowledge. Students should as well be given supervision from
the institutes so as to bridge the gap between the organization and the institute to enhance
cooperation. Students should as well be given enough time to write reports so as to enable them
write down all their field experiences.
4.2.3. The student. The students should keep maximum discipline when there are at work and
they should show respect each other
UBT434/2024/T/C/M/0044
REFERENCES
I refer you or more information about kasule cosmas my intership www.leesonssolar.com
I aslo refer you to Mr. kasule Cosmas who taught me how to carry out installation of accessories
and he has been my field supervisor for more information contact him on 0703254277.
I also refer you to Mr. John who has been working with Mr. kasule for more information contact
him on 0709786672
UBT434/2024/T/C/M/0044
APPENDICES
15
UBT434/2024/T/C/M/0044