DANEM ENERGY OIL & GAS FZCO,
DUBAI, UAE
MANUFACTURING RECORD BOOK INDEX
CODE DOCUMENT TITLE PAGE No.
A GENERAL ---
A-1 SIGNED ITP (INSPECTION TESTING PLAN) COMPLETED OF THE
MANUFACTURER, CLIENT/TPI SIGNATURES
A-2 APPROVED/ASBUILT DRAWINGS
B PROCEDURES ---
B-1 WPS, WELD PLAN & WELD MAP
B-2 WELDER QUALIFICATION CERTIFICATES
B-3 POSITIVE MATERIAL IDENTIFICATION PROCEDURE
B-4 NDE PROCEDURE – DYE PENETRANT EXAMINATION
B-5 NDT PERSONNEL CERTIFICATES
B-6 VISUAL EXAMINATION PROCEDURE
B-7 PICKLING & PASSIVATION PROCEDURE
B-8 HYDROTEST PROCEDURE
B-9 WATER FILL TEST PROCEDURE
B-10 SURFACE PREPARATION & PAINTING PROCEDURES
C INSPECTION REPORTS ---
C-1 MATERIAL RECEIVING INSPECTION REPORTS, MATERIAL TRACEABILTY
RECORDS & MTC’s
C-2
WELD VISUAL INSPECTION REPORTS
C-3 WELD SUMMARY
C-4 VISUAL & DIMENSIONAL INSPECTION REPORTS
C-5 DYE PENETRANT EXAMINATION REPORTS
C-6 POSITIVE MATERIAL IDENTIFCATION REPORTS
C-7 WATER FILL TEST REPORTS
C-8 HYDROTEST REPORTS
C-9 WATER ANALYSIS REPORT
C-10 PICKLING & PASSIVATION REPORTS
C-11 COATING REPORTS & PAINT BATCH CERTIFICATES
C-12 CALIBRATION CERTIFICATES
C-13 NAME PLATE PHOTOS
C-14 PHOTO REPORT OF ITEMS BEFORE DELIVERY