WAPCOS LIMITED
(A Government of India Undertaking)
76 C, Sector 18, Gurgaon - 122015, Haryana, INDIA
Tel. +91-124-2397396,
Fax. +91-124-2397392
Email: [email protected]
MAY 2013
CONTENTS
CONTENTS
CHAPTER-1 INTRODUCTION
1.1 GENERAL 1-1
1.2 PROJECT PROFILE 1-1
1.3 LEGAL AND POLICY FRAMEWORK 1-3
1.4 SCOPE OF THE EIA STUDY 1-4
1.5 STAGES IN AN EIA STUDY 1-5
1.6 REGISTRATION WITH QUALITY COUNCIL OF INDIA (QCI)/NABET 1-6
1.7 OUTLINE OF THE REPORT 1-6
i
4.8 CATCHMENT AREA TREATMENT PLAN 4-9
4.9 LOCAL AREA DEVELOPMENT PLAN 4-9
4.10 ENVIRONMENTAL MONITORING PROGRAMME 4-9
CHAPTER-5 HYDROLOGY
5.1 CHENAB RIVER SYSTEMS 5-1
5.2 THE CATCHMENT AND PHYSIOGRAPHIC PARAMETERS 5-2
5.3 HYPSOMETRIC CURVE 5-3
5.4 GAUGE & DISCHARGE 5-7
5.5 STREAM FLOW CHARACTERISTICS 5-8
5.6 WATER AVAILABILITY 5-8
5.7 DESIGN FLOOD 5-9
5.8 RECOMMENDATIONS 5-15
5.9 SEDIMENT DATA AVAILABILITY 5-17
CHAPTER-6 TOPOGRAPHICAL AND GEOLOGICAL ASPECTS
6.1 INTRODUCTION 6-1
6.2 PHYSIOGRAPHY AND DRAINAGE 6-1
6.3 REGIONAL GEOLOGY OF THE AREA 6-2
6.4 STRUCTURE, TECTONICS AND METAMORPHISM 6-4
6.5 TECHTONIC SETUP OF THE PROJECT AREA 6-7
6.6 SEISMO-TECTONICS AND SEISMICITY 6-7
6.7 GEO-TECHNICAL APPRAISAL OF THE COMPONENT STRUCTURES 6-10
ii
8.3 REMOTE SENSING ASSESSMENT OF FLORA 8-2
8.4 METHODOLOGY 8-6
8.5 FINDINGS OF THE FIELD STUDIES 8-7
8.6 LICHENS & FUNGI 8-15
8.7 ECONOMICALLY IMPORTANT PLANT SPEICES 8-17
8.8 RET SPECIES 8-20
8.9 FAUNA 8-20
8.10 AQUATIC ECOLOGY 8-28
8.11 FISH COMPOSITION AND STATUS 8-38
iii
CHAPTER-1
INTRODUCTION
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
CHAPTER-1
INTRODUCTION
1.1 GENERAL
The state of Himachal Pradesh is located in the vicinity of Dhauladhar and Pir Panjal ranges
of Western Himalaya and lies between 32° 22’ 40’’ t o 33° 12’ 40’’ N latitudes and 75° 45’ 55’’
to 79° 04’ 20’’ E longitudes. The state has a geogr aphical area of 55,673 sq km demarcated
into 12 districts, 109 tehsils/sub-tehsils and 57 urban areas with a total population of 60,
77,248 persons as per 2001 Census.
The geographic location and physiography of the state result in varying climatic conditions
and diverse natural ecosystems. The variations in climatic conditions range from lower
tropical regions to cold and alpine conditions in the upper regions. Many areas in the north
and east in Himachal Pradesh are snow-bound and glaciated. These glacial are the source
of many perennial river systems in the state. The prominent rivers rising from these upland
glacial areas are Sutlej, Beas, Parbati and Ravi – all south and southwest flowing rivers. The
perennial availability of water and the conductive geographic terrain have allowed
harnessing of energy from these rivers. The project location map is given in Figure-1.1.
1-1
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
Himachal Pradesh State Electricity Board (HPSEB) in their ranking studies. The Sach Khas
HE project is proposed on river Chenab in Himachal Pradesh between longitudes 76° 25’
30.143” E to 76° 25’ 3.8’’ E and latitudes 32° 57’ 55.123” to N 32° 58’ 7.5’’N. The project
envisages harnessing the hydro-power potential of the river from EL 2219 m to EL 2149 m.
A concrete gravity dam is proposed across the river and underground power house with an
installed capacity of (260+7) MW is proposed immediately downstream of the dam. Out of
this 260 MW is proposed to be generated by the main powerhouse, whereas 2 units of 7MW
each (one acting as standby) are proposed to be installed to utilize the mandatory
environmental releases. The catchment area intercepted at the dam site is 6588 sq. km.
About 3973 sq. km. of the catchment is snow fed.
The nearest rail head is Kalka railway station, which is about 520 km from Project site. The
proposed Sach Khas HEP is at a distance of about 270 km from Bhuntar (Kullu) airport,
which is the nearest airport. The project site is well accessible by three routes ie. First from
Jammu & Kashmir through Kishtwar town; second from Pathankote - Chamba town and third
through Kullu-Manali-Udaipur via Rohtang pass, however the third route is the most
favourable. The project site is located at a distance of about 60 kms downstream from
Udaipur. The projects in cascade development u/s and d/s of Sach Khas Hydro-electric
project is shown Figure-1.2.
Figure- 1.2: Line schematic of hydro projects u/s & d/s of Sach Khas HEP
1-2
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
1-3
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
Consultation process in the form of report detailing the proceedings and video of the entire
event will be submitted to MoEF by HPPCB.
Appraisal: On completion of Public Consultation process, incorporation of suggestions, if
any during the public consultation, final report will be prepared, submitted and presented to
the Expert Appraisal Committee for River Valley and hydroelectric projects at MoEF for final
approval.
1.3.2 State Level Clearances
The Department of Environment & Scientific Technologies, state government of Himachal
Pradesh was set up in April, 2007 with an objective to improve the effectiveness of
environmental management, protect vulnerable ecosystems and enhance sustainability of
development. The Environmental Impact Assessment and monitoring of Environment
Management Plan Report prepared by the Project Proponent is reviewed by the Department
of Environment and Scientific Technologies. A committee constituted by the department with
members from State Pollution Control Board, Forest Department, Fisheries Department, etc.
reviews the EIA reports before Public Consultation as per EIA Notification of September
2006.
Various state departments have also lately issued specific notifications to be taken into
consideration by project developers in Himachal Pradesh. Relevant notifications for
Hydropower projects are briefly described.
Notification on Catchment Area Treatment (CAT) Plan
Department of Forest has issues a notification no. FFE-B-F-(2)-72/2004-Pt-II dated August
03, 2009 setting out the requirements of preparation of CAT plan and defining the minimum
cost of this component as 2.5% of the project cost. It was later modified vide notification no.
FFE-B-F-(2)-72/2004-Pt-II dated September 30, 2009.
Notification on Fisheries
Department of Fisheries has come out with a notification no. Fish-F (5)-1/2008 dated May 2,
2008 specifically for the hydro power projects to specify the compensation to be paid by
developers for various categories of Projects.
1.4 SCOPE OF THE EIA STUDY
The brief scope of EIA study includes:
- Assessment of the existing status of physico-chemical, ecological and socio-economic
aspects of environment
- Identification of potential impacts on various environmental components due to activities
envisaged during construction and operation phases of the proposed Sach-Khas
project.
- Prediction of significant impacts on various aspects of environment.
- Delineation of Environmental Management Plan (EMP) outlining measures to minimize
adverse impacts during construction and operational phases of the proposed project.
1-4
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
Description of Environment: Before the start of the project, it is essential to ascertain the
baseline levels of appropriate environmental parameters which could be significantly
affected by the implementation of the project. The baseline status assessed as a part of
CEIA study involved both field work and review of data collected from secondary sources.
Prediction of Impacts: is essentially a process to forecast the future environmental
conditions of the project area that might be expected to occur as a result of the construction
and operation of the proposed Sach Khas hydroelectric project. An attempt was generally
made to forecast future environmental conditions quantitatively to the extent possible. But for
certain parameters which cannot be quantified, general approach was to discuss such
intangible impacts in quantitative terms so that planners and decision-makers are aware of
their existence as well as their possible implications.
Environmental Management Plan: the approach for formulation of an Environmental
Management Plan (EMP) is to maximize the positive environmental impacts and minimize
the negative ones. The steps suggested include modifications of plans, engineering designs,
construction schedules and techniques, as well as operational and management practices.
After selection of suitable environmental mitigation measures, cost required for
implementation of various management measures was also estimated.
Environmental Monitoring Programme: An Environmental Monitoring Programme for
implementation during project construction and operation phases has been estimated to
oversee the environmental safeguards, to ascertain the agreement between prediction and
1-5
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
reality and to suggest remedial measures not foreseen during the planning stage but arising
during operation and to generate data for further use.
1.6 REGISTRATION WITH QUALITY COUNCIL OF INDIA (QCI)/NABET
WAPCOS Limited is accreditated by QCI/NABET and the Certificate is enclosed as
Annexure-II.
1.7 OUTLINE OF THE REPORT
The document for the Comprehensive EIA study for the proposed Sach Khas hydroelectric
project has been presented in two volumes. Volume-I presents the Environmental Impact
Assessment (EIA) study and Volume-II delineates the Environmental Management Plan.
The present document (Volume - I) outlines the findings of the EIA study for the proposed
Sach Khas hydroelectric project.
The contents of the document are organized as follows:
Chapter-1 The Chapter gives an overview of the need for the project. The policy, legal and
administrative framework for environmental clearance has been summarized. The objectives
and need for EIA study too have been covered.
Chapter-2 gives a brief description of the proposed Sach Khas hydroelectric project.
Chapter-3 gives a brief description of the methodology and schedule to adopt for
construction of the proposed Sach Khas hydroelectric project.
Chapter-4 outlines the methodology adopted for conducting the Comprehensive EIA study
for the proposed Sach Khas hydroelectric project.
Chapter-5 covers the hydrological aspects of the proposed Sach Khas hydroelectric project.
The data was mainly collected from the DPR prepared for the proposed Sach Khas
hydroelectric project.
Chapter-6 covers the geological and seismicity related aspects.
Chapter-7 covers the environmental baseline conditions covering physical aspects of
environment. The baseline study involved both field work and review of existing documents,
which is necessary for identification of data which may already have been collected for other
purposes.
Chapter-8 presents the information on ecological aspects of the Study Area. The study is
based on collection of data from various secondary data sources. As a part of the
Comprehensive EIA study, detailed ecological survey for was conducted for three seasons. The
findings of the survey were analysed and ecological characteristics of the study area have been
described in this Chapter.
Chapter-9 describes the anticipated positive and negative impacts as a result of the
construction and operation of the proposed Sach Khas hydro-power project. It is essentially a
process to forecast the future environmental conditions of the project area that might be
expected to occur as a result of the construction and operation of the proposed project. An
1-6
WAPCOS Limited
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
attempt was generally made to forecast future environmental conditions quantitatively to the
extent possible. But for certain parameters, which cannot be quantified, general approach has
been to discuss such intangible impacts in qualitative terms so that planners and decision-
makers are aware of their existence as well as their possible implications.
1-7
WAPCOS Limited
CHAPTER-2
PROJECT DESCRIPTION
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
CHAPTER-2
PROJECT DESCRIPTION
2.1 INTRODUCTION
The proposed Sach Khas Hydroelectric project is located in the Pangi valley of Chamba
District of Himachal Pradesh. The proposed scheme lies between longitudes 76o 25’ 30.143”
E to 76o 25’ 3.8” E and latitudes 32o 57’ 55.123” N to 32o 58’ 7.5” N.
The river Chenab in project vicinity flows in the northern direction with a slight inclination
towards the east. The Sach Khas hydroelectric project is located near the Shin village (close
to the Cheninala confluence with the Chenab river) with the location of the diversion
structure proposed slightly upstream of the village and the underground powerhouse
structure at the toe of the dam. The project is planned as a dam toe scheme. Head needed
for power generation is envisaged to be harnessed entirely by the diversion structure as the
powerhouse is merely 300m downstream from the dam axis.
As per the information provided by Himachal Pradesh State Electricity Board (HPSEB), a 40
m high (above river bed level) diversion structure is proposed across the river Chenab
located just 2.5 km up-stream of the Mokha Nala confluence, at about 200 m downstream of
the point where the river takes a westward bend, wherein the river bed elevation is 2185m.
The envisaged tail water level upstream of the Saichu Nala confluence is 2150 m.
After confirmation of levels at the site, and after the reconnaissance site visit, it emerged that
a diversion site exists, which is prima-facie suited for a concrete dam of about 77m height
(above the river bed level) located 1.1 km upstream of the Cheninala confluence, a left bank
tributary with Chenab. The river at the site flows through a narrow gorge exposing bedrock
on both the abutments. Adequate straight reach is available downstream of the river bend
where all the head works components can be housed. The live storage of the proposed
diversion scheme is 8.69 Mm3. Since the proposed scheme is a Dam-toe powerhouse, the
need for a headrace tunnel (HRT) has been eliminated. Also it has been proposed to locate
the crest of the sluice spillway sufficiently below the power intakes in the dam body to take
care of bed load depositions and entry of sediments into the intakes. Thus no desilting
chambers are required. Three intakes each leading to 5.8m diameter penstocks have been
planned to be located on three of the right bank non-overflow blocks. Three penstocks off-
taking from the intakes are proposed to direct the flows to an underground powerhouse on
the right bank of the Chenab river housing 3 units of 86.67 MW turbines with a total installed
capacity of 260 MW.
As regards the powerhouse location, it was seen during the reconnaissance visit that the site
originally envisaged by HPSEB for an underground powerhouse is located on the right bank
of the river about 0.5km upstream of its confluence with the Saichunala. However, after
numerous investigations and detailed survey carried out at site, the new powerhouse is
proposed to be located as an underground structure on the right bank of the Chenab River at
a distance of about 200m from the present dam toe and about 850m upstream of the
Cheninala confluence with the Chenab.
2.2 ALTERNATIVES CONSIDERED
Layout 1: (Diversion site as per tender)
As per this alternative, the water of the river Chandra-Bhaga are proposed to be diverted into
a water conductor system for generation of power in an underground powerhouse located
near Sach Khas village. The diversion site is located 2.5km downstream of the confluence of
Mokhanala with the river Chenab. The river bed level at the proposed diversion site is El.
2170.0m, based on the survey data. The FRL envisaged for the scheme was El. 2219m.
A design discharge of 513.75 cumec (including 20% for desanding chamber flushing) is
proposed to be led through the power intake located on the right bank into three feeder
tunnels. Each feeder tunnel leads into a 254m long desanding chamber. The water through
each desanding chamber is let into a link tunnel through a transition placed at right angles to
the desander alignment. The three link tunnels join to form a single a head race tunnel about
4.5km long and 10.0m in diameter, which feed an underground powerhouse located about
500m upstream of the Saichunala confluence with the Chandra-Bhaga River. The allotted
tail water level at the TRT outlet should be El. 2150m which has been revised to 2149m.
Considering an average river slope of 1 in 165, and another 1.5km to Saichu from
Cheninala, the tail water levels 500m upstream of Saichunala are much lower than the
allotted levels at about El.2135m.
This layout was rejected due to following reasons:-
• Gross hydraulic head, in this case, is beyond the allotted levels
• Larger requirement of forest land as surge shaft being on surface would be located
in the forest area
• Construction adits for the head race tunnel and their approaches would be located in
forest area
• Geology in the proposed intake area is not favorable and would require extensive
excavation which would endanger the Killar – Tindi Road
• The Head race tunnel alignment passes through folded rock mass strata which would
make tunneling extremely difficult.
• Very low peaking power, as sufficient live storage would not be available.
In this alternative, the diversion site is proposed to be shifted 850m downstream of the
diversion site as envisaged in Layout 1. The diversion site is located just 300m upstream of
the northward bend that the river takes after the Bakanwalnala confluence with the Chenab
River. The bed level at this location would be at El. 2165.0m.
Shifting the diversion site to this location envisages layout similar to alternative-1. Since
there are no intermediate villages between the two alternative dam sites (Layout 1and
Layout 2), valley being steep, no submergence problems are anticipated. Considering FRL
as 2219m, this will lead to an increase in the dam height by about 10m. However, the
peaking operations of the plant will not possible in this alternative too.
Due to the side intakes, and fragile geology at intake site on the right bank with potential
slide zone at the upstream of intake location, huge excavation for slope stabilization would
be required and the excavations shall extend beyond the present alignment of the SKT road,
which shall need to be realigned above this area and into the forest on Rai Dhank bend.
This was not considered practically feasible in view of the single approach road to the Pangi
Valley. Also for locating desilting chambers, long HRT, etc., large amount of land would be
needed in addition to land for development of the project facility areas.
Alternately, a diversion structure with a powerhouse in the nearby downstream reach can be
considered. This alternative would not result in realization of full head as the head utilized
would reduce considerably from 70m to mere 47m. The tail water levels at this site would be
El. 2172 (as per the survey data) against the allotted levels of El. 2149m. Therefore, this
alternate does not result in optimal utilization of the river potential.
There are two types of arrangements feasible in this location. Prima facie, diversion site is
located 1.3km upstream of the Cheninala confluence with Chenab. The river takes a small
north-east bend and then flows straight north. There is an RCC pillar PH-1 constructed along
the road side, designated as a control point of survey.
This proposal comprises a diversion scheme either with a surface power house or an
underground power house, immediate downstream of the dam. The bed level of the river at
this location is about El. 2146.5m. Foundation rock is available at depths of about 20m. A
92m high dam from the deepest foundation can be envisaged. About 250m downstream of
the dam axis, on the right bank, the hill slopes relatively flat and would provide the terrain for
siting a surface powerhouse, with the power intake from the body of the dam. However, the
tail race channel would be quite long, envisaging a downstream collection basin/surge
chamber, which would result in acquisition of large tact of forest land. The powerhouse being
an open structure, heavy hill cutting and stabilization measures would be needed and extent
of the excavation would necessitate diversion of the existing SKT road which invariably
would also involve larger forest area.
Alternately, an intake along the right bank 30m upstream of the dam axis can also be
constructed, through which 500m long pressure shafts will take the water to the powerhouse
for power generation. But this underground arrangement would warrant a side intake on the
right bank hill, an upstream surge shaft, and a huge underground powerhouse and
transformer cavity. This would involve huge excavation in the intake area where the
excavation would encroach the Sansari-Killad – Tindi road necessitating acquisition of larger
areas in forest again and realignment of the SansariKilarTandi Road. In view of the
disruption/realignment of the SKT road and requirement of large forest areas this scheme is
not considered.
Given the bed level of the river El. 2145 m and probable foundation rock depths at El.
2132m, a dam of about 90m high is envisaged. The hill slopes on the right bank are
relatively flat than the left bank slopes, which permits the housing of the power intakes in the
body of the dam on the right bank, eliminating the side intake which invariably would
endanger and undercut the SKT road in addition to involving larger forest area. The waters
from the river would be taken to the underground powerhouse on the right bank through
three nos. of 5.8m dia steel penstocks, with average length of 300m.
With the intakes in the body of the dam thereby dispensing away the side intake, with the
desilting basin, long HRT, underground transformer hall and shorter, tailrace, the
requirement of forest land shall be significantly less. The SKT road too shall not need to be
realigned.
The last alternative studied is locating a diversion site further 750m downstream of the
above option and 300m upstream of CheniNala confluence with the Chenab. This layout is
schematized on the left bank; as there were visible rock exposure and the river valley is also
relatively narrow than the above. The bed level at this location is at El. 2142.0m, which is 7m
below the allotted levels.
Although, there are no schemes planned across Chenab, immediately below SachKhas,
except the Duggar HEP which is far below. This location is thus avoided as the bed levels
are much below than the allotted levels for the project.
Based on the different layouts detailed above (Refer project layout), the scheme described
at Layout – 4 (diversion site 1100m upstream of CheniNala) is the most suited one, from the
consideration of given levels for the project. Considering favorable geology and rock
exposures, the layout could further be optimized into a simpler model. As the construction
period in each year is extremely limited due to the unpredictable and extreme winter weather
condition reduction in construction period of the project is of utmost importance. This project
layout would eventually bring down the construction period, as major project components,
like desanders, headrace tunnels, surge shafts, etc. have been avoided.
The storage requirement as per the Indus Water Treaty (IWT) is also under this alternative.
No diversion/realignment of existing SKT road is envisaged. Further, it is proposed that
major construction facilities shall be located in the reservoir submergence area bringing in
substantial reduction in requirement of forest land which otherwise would have been
necessary to locate these facilities in addition to forest land required for locating permanent
project components. Thus, huge forest area requirement for locating project components, as
envisaged in other layouts, could be reduced in this alternative.
To take care of the mandatory environmental flows, scheme envisages releasing these
required flows through a surface powerhouse on the left bank housing a 7MW unit. To have
100% redundancy, another unit of 7 MW is also proposed to be installed in the proposed
powerhouse. The additional unit would operate in the contingency of first unit of 7 MW either
under forced or planned outage. This would ensure that the mandatory environmental
release is available continuously even if one unit of 7 MW is out of service. Hence, the
project layout described at alternate – 4 is considered for detailed study in the DPR. A map
showing various alternatives studied is enclosed as Figure-2.1.
At Sach Khas, the proposed dam can be categorized as a small reservoir (as per the gross
storage criteria) and a large dam (as per the hydraulic head criteria of more than 30m).
Since the hydraulic head lies in the large category, the recommended design floods as per
Cl. 3.1.3. of IS 11223 would be a PMF.
• PMF has been calculated as 9047 cumec (as per hydrology studies).
• Minimum available live storage between FRL (2219m) and MDDL (2209.30m) is
8.69 MCM.
• River bed elevation at the proposed dam axis is 2145m.
• Right abutment is characterized by rock scraps at 60o up to EL 2170m followed
by 25 o to35 o slopes upto EL 2190m.
• Left bank rises above the river bed at angle of 45 o to55 o with break in slopes at
EL 2160, 2190 and 2220m.
Keeping in view the above requirements and data, and after an assessment of the
topographic and geological conditions at the proposed site, a concrete gravity dam with a
breast-walled sluice spillway has been adopted as diversion structure. The dam top is
proposed at El. 2222m after accounting for a freeboard of 3m. The structure would thus have
a height of 77m from the deepest bed level. Based on the storage requirements for peaking,
the MDDL has been fixed at El. 2209.30. Five sluices of size 7.5m (width) x 12.3m (height)
have been proposed to pass the PMF with one gate in inoperative condition. The diversion
dam has been conceptualized considering foundation rock strata at a shallow depth of
around 13m below the river bed. Energy dissipation is envisaged by the use of a trajectory
bucket and a suitably located plunge pool. A sluice type gravity dam with foundation resting
over the bed rock is proposed in the present case. Regarding the hydraulics of the structure,
low level sluices with crest placed at 22m above the river bed level are proposed to pass the
design flood of 9047cumec. Energy dissipation shall occur through a trajectory type bucket
dissipater, discharging the excess flow into a pre-formed plunge pool with its center situated
at a distance of about 90m downstream of the sluice lip. It has been planned for the deepest
level of the plunge pool be excavated up to the probable scour depth calculated under the
prevailing discharge and flow conditions.
Since the river bed slope is of the order of 1 in 165, diversion structure will form a reservoir
with an approximate length of 8.3 km at FRL (2219m) and 7.3km at MDDL(2209.30). The
gross storage capacity of the reservoir is estimated as 25.24 Mm3 and the live storage
capacity is envisaged as 8.69Mm3. The reservoir is expected to trap most of the bed load
suspended sediment load thus eliminating the need of desilting chambers. Five low level
sluices with crest at 2167m of size 7.5m width and 12.3m height are proposed for flood
passage. Drawdown flushing of the reservoir shall be carried out through these sluices for
flushing out of the sediment entrapped in the reservoir. Detailed studies on sedimentation
and reservoir flushing can be taken up at detailed planning stage.
Power Intake
Three number of power intakes are proposed to be located in three of the non-overflow
blocks immediately adjacent to the overflow blocks on the right bank to draw a total diversion
discharge of 428.12 cumec. Additional discharge for silt flushing is not planned for due to the
provision of trapping the sediments in the reservoir itself. The invert of intake is proposed at
El. 2196.9 m which is 29.9m above the sluice crest. The proposed invert level satisfies the
criteria for minimum submergence below the MDDL of 2209.30 m to prevent the formation of
vertices. The control arrangement at the inlet is proposed in the form of vertical lift gates with
provision for emergency gate grooves.
Three breast walled type structures are proposed with a bell-mouth inlet transition and with
accelerating velocities from the trash rack location to the mouth of penstocks. Each of the
intakes in turn feeds a 5.8m diameter penstock with a design discharge of 142.707 cumec.
The lengths of the penstock are calculated to 254, 268 and 282meters from the shortest to
the longest respectively.
The trash rack is planned to be located with an inclination of 12 degrees to the dam axis with
the top starting at a distance of 3m from the same. The bottom of the trash rack will rest on a
cantilever portion emerging from the body of the dam. The elevation of floor (trash rack
sitting) is 2193.30 m thus making the total vertical height of the trash rack to be 28.7m. Two
end piers each of width 2.4m and two intermediate piers each of width 1.2m will be provided
to support the trash rack.
Pressure Shaft
Three circular pressure shafts each of diameter 5.8m have been proposed to carry the
design discharge from the intake to the powerhouse. The pressure shafts begin immediately
after the transition near the intake and bend vertically, moving parallel to the downstream
slope of the dam. They lie exposed on the downstream surface of the dam for a short reach
before being underground. They also consist of a compound bend near the toe of the dam
after which the pressure shafts become horizontal and continue on their way to the
powerhouse. There exists yet another horizontal bend in the pressure shafts near the
powerhouse after which the pressure shafts are connected to the Main Inlet Valve. The
lengths of the pressure shaft are calculated to 254, 268 and 282meters from the shortest to
the longest respectively.
The centerline of the pressure shaft at start, after the intake is proposed to be at 2199.80m
and the centerline of the machines in the powerhouse is proposed at 2138.00m, registering
a fall of 61.8m.The pressure shafts are designed such that any need for a surge shaft is
eliminated.
Powerhouse
The underground powerhouse is proposed on the right bank of the river Chenab about 200m
downstream of the toe of the dam. The water from the tailrace tunnel is proposed to
discharge into river Chenab. This site has been considered suitable for underground
powerhouse from geological considerations. The governing tailwater level has been fixed at
EL. 2149m as per the allotted level. The powerhouse is proposed to facilitate the housing of
three units, each of 86.67 MW Francis turbines.
The centerline of the turbine units is proposed at El. 2138.00m after catering to a setting
head of 9.00m below the minimum tailwater level of El. 2147.00m. The erection bay floor
level is proposed at 2151.15m while the generator hall floor level is proposed at El.
2146.15m. The length of the control block is 15m and it is located adjacent to the machine
hall at the left side of the powerhouse cavern. A 35m long service bay is located right side of
the powerhouse cavern. An adit with invert level of El. 2165.40m at the portal is planned on
the right of the powerhouse opening directly into the service bay.
Machine Hall
The internal dimensions of the powerhouse cavern has been proposed as 126m (L) x 23m
(W) x 48.5m (H). The operating floor level is kept at El. 2151.15m. The length of the machine
hall would be 76m. The unit bay is proposed with 21.5 m spacing. The EOT crane beam is
proposed at El. 2163.65m, i.e. 12.5m above the operating floor level.
Each unit is proposed with a draft tube separated by one RCC piers in between. At the draft
tube gate location, the width of each draft tube bay is 11.5m and height is 6.65m. The draft
tube gates are proposed to be operated from a deck in the transformer cavern.
Conductor System
The water conductor system consists of three penstocks of 5.8m diameter located on the
right bank of the river downstream of the dam toe. These convey the water to an
underground powerhouse housing three units each of 86.67 MW, totaling to the installed
capacity of 260 MW. The penstocks are exposed to the surface for a short stretch after they
leave the dam body before going underground again. The length of the penstocks and their
diameter are so designed that the need of a surge shaft is eliminated.
Tailrace Tunnel
The outflow from the end of each of the draft tubes is proposed to be conveyed into
respective tailrace tunnels downstream of the powerhouse. These TRTs then carry the
discharge back into the river Chenab. Each TRT is D shaped and has size of 6.6m x 6.0m.
The invert elevation of the TRTs at the outlet portal is 2145.00.
The centerline of the pressure shaft at start, after the intake is proposed to be at 2202.80m
and the centerline of the machines in the powerhouse is proposed at 2139.45m, registering
a fall of 63.35m. The pressure shaft is designed such that any need for a surge shaft is
eliminated.
Secondary Powerhouse
A surface powerhouse is proposed on the right bank of the river Chenab about 10m
downstream of the toe of the dam. The water from the tailrace tunnel is proposed to
discharge into river Chenab at around the location of the plunge pool of the main dam. The
governing min tailwater level has been fixed at EL. 2145.20m as per the rating curves
developed. The powerhouse is proposed to facilitate the housing of two units, each of 7.0
MW Francis turbines. Out of these two one is proposed to act as a standby unit.
Secondary TRT
The outflow from the end of each of the draft tubes is proposed to be conveyed into
respective tailrace tunnels downstream of the powerhouse. Each TRT is D shaped and has
size of 3m x 3m. After running for a certain distance the unit TRTs merge to form into one.
The larger TRT formed after the unit TRTs merged is proposed to be of D-Shaped with a
size of 3.6m x 3m. The TRT travels with a up slope up to the outlet portal at which it is
proposed that the discharge will occur at a gentle slope of 1 in 300.
The project layout map is enclosed as Figure-2.2.
Length 99.75m,113.13m,132.35m
Design Discharge 142.707 X 3
HFL at TRT outlet El. 2158.0m
Power Generation
90% Dependable year 999.92GWh
50% Dependable Year 1009.44 GWh
Source: DPR
2.6 LAND REQUIREMENT
Land would be acquired on permanent basis for:
• Reservoir
• Dam & Power House,
• Downstream coffer dam and outlet portals of diversion tunnels,
• All muck disposal and borrow areas/ quarries,
• All access roads to the permanent works,
• Explosive magazines and access roads,
• Project site office/Job facilities
The total land required for the project is 125.62, About 118.22 ha is forest land and the
balance land 7.40 ha is private land. The details are given in Table-2.2.
Table-2.2: Land requirement for the project
Sr. No Project Component/ Activity Area (ha)
1 Submergence Area:
a) Forest Land 81.88
b) Non-Forest Land (Private Land) 0.28
Total Area of Submergence 82.16
2 Muck Dumping Area 10.53
3 Quarry 3.03
4 Dam & Power House 9.54
5 Project Site Offices/Job Facilities: 5.25
6 Explosive Magazine 0.23
7 Sub-surface (Underground Works) Area 2.44
8. Approach Roads to explosive magazine, 5.32
Project facilities & Quarry
9. Township & Office (Private land on lease 7.12
basis)
TOTAL 125.62
Source: DPR
The nearest airport is Bhuntar and the nearest rail head is Kiratpur.
The infrastructure works at proposed Sach Khas hydroelectric project would broadly
comprise of:
• Batching Plant
• Crusher Plant
• Stores
• Fabrication Yard
• Workshop
• Formwork & Rebar Yard
• Workman Camp
• Staff Colony
• E&M Workshop
• H&M Workshop
• QA/QC Lab
• Site Office
• Disposal Area
• Borrow Areas/Quarries
• Project Roads leading to all work sites.
Infrastructure works and facilities required for constructing and maintaining the project are
discussed in following sections. The Infrastructure layout plan has been depicted in Figure-
2.4. The land requirements for various infrastructure works covering residential buildings are
given in Table-2.3. The land requirements for permanent and temporary Nonresidential
buildings are given in Table-2.4 and 2.5 respectively.
Figure-2.4: Infrastructure layout plan
The transportation of the material would be done by road transport to the project site. The
main highway from Chandigarh to Project Site has been surveyed to study its suitability to
transport heavy loads to the project site. Road through Rohtang Pass will be opened for
seven months in a year and the same road will be utilized for the transport of construction
material.
Given the sizes of civil components, all the facilities will be cater to one location to have easy
accessibility through all the components.
Since all the work would be highly mechanized, adequate and self-sufficient repair and
service facilities would be set up at the project site. There are absolutely no services or
Facilities of mechanical nature available near the project area. All mechanical repairs and
servicing will be done in house by providing enough space for workshops, maintaining an
adequate inventory and deputing skilled manpower. Close Monitoring of the inventories of
spares, consumables, and other materials would be done to ensure reduced downtime.
Adequate and competent repair staff would be deployed in the field as well as in the shops
to keep the construction fleet in top operational condition.
Every workshop would have partly covered area in addition to open area. Equipment
requiring major overhaul/repairs would normally be parked under cover. The open areas
would provide parking space for the equipment under minor repair. A store to stock the
spares for the equipment, a site office and toilet facilities would be provided under the
covered space. The penstock fabrication yard would be equipped with two plate bending
rolls, a battery of welding and gas cutting sets, hydro-testing and radiography facility, sand-
blasting and painting equipment and sufficient space to stock the raw plates as well as the
finished ferrules awaiting dispatch. An E.O.T crane of 40 MT capacity erected in the yard
would be deployed for handling the ferrules during different stages of fabrication. A separate
mobile crane of 40 MT would be deployed to handle the plates/ferrules in the stock yard. The
fabrication yard would be partly covered to allow welding and other activities to go on
unhindered under the covered area.
Construction Power
Construction power would be available through two sources 3.5MW Chhoo Hydroelectric
Project and through diesel generating sets. It has been planned that 75% of Power will be
available through diesel generating sets and 25% through Choo Hydroelectric Project. The
requirement would have to be met only by installing diesel generating sets. The requirement
of construction power would vary at each individual site depending upon the equipment
deployed.
The set up for aggregate and concrete production for the project would be as below:
Batching Plant of 30 Cum, 60 Cum & 90 Cum and Crusher Plant of 200 TPH will be
deployed to arrange the concrete and aggregate.
To execute the various civil works, roads would be made for linking the work site to other
sites and to job facility areas. They would essentially be unpaved and would be constructed
at a workable gradient so that loaded construction equipment does not have to toil hard to
group slope. An average gradient of 1:15 has been contemplated. These roads would be
connected to the existing roads in the area or to other project roads. The details are given in
Table-2.6.
Table -2.6: Project Road Network
Road Distance Length (km)
Diversion Tunnel to Disposal Area 4.5
Disposal Area to Cofferdam 4.4
Dam to Disposal Area 4.2
Adit to Bottom of Penstock to Disposal Area 4.0
Construction Adit to Top of Power House to Disposal Area 3.7
Main Access Tunnel to Power House to Disposal Area 3.5
Tail Race Tunnel to Disposal Area 3.7
Diversion Tunnel to Batching Plant 1.0
Intake to Batching Plant 2.0
Dam to Batching Plant 1.5
Adit to Bottom of Penstock to Batching Plant 2.0
Construction Adit to Top of Power House to Batching Plant 2.0
Main Access Tunnel to Power House to Batching Plant 1.5
Tail Race Tunnel to Batching Plant 1.5
Source: DPR
Bridges Required
Both permanent and temporary bridges would be constructed to cross the waterways falling
in the alignments of the roads. The details are given in Table-2.7.
It is clear from above table that total 10, 11,750 cubic meters muck requires proper disposal.
Most of the area, identified for dumping is planned on the banks of nearest drainages &
away from River HFL. The identified areas are mostly gradually sloping near river bank. The
drainage side bank of the area will be properly protected and stabilized with Gabions/
Retaining Walls of suitable designed sections.
Source: DPR
About 10.11 Lakh cum. of muck is to be disposed hence capacity of the dumping area is
sufficient to accommodate the muck generated from the project.
It is further elaborated that unused muck would be piled up at an angle of repose at the
proposed dumping sites. For the stabilization of dumped materials various engineering
measures and phyto-remedial measures shall be provided.
Telecommunications
The different work sites, stores, workshop, office, colonies, police station, hospital etc.
should have a reliable telecommunication network, interconnected to the existing
telecommunication network of Himachal Pradesh. An electronic exchange with a minimum
capacity of 50 lines is proposed at the project site during the construction stage. This internal
system should be maintained by Bharat Sanchar Nigam Limited to ensure reliable
connectivity with the rest of the country.
In addition to the above, a wireless VSAT system is also proposed as a standby system for
linking the project site with headquarters, procurement offices and regional offices. After
completion of the project construction, the telecommunication network is proposed to be
maintained to the extent necessary so as to provide a reliable service during plant operation.
hostel/staff hostel complex packaged water treatment plant is proposed to be provided. For
labour/construction colonies, the water sources at nallas and various other small sources will
serve the purpose after providing suitable water treatment.
Explosive Magazines
For completing the project as per the construction programme, it has been estimated that
one explosive magazine, of 20 MT capacity, would be sufficient to meet the requirement.
The area around the building for explosive and detonators would be fenced and have a
strong gate which would be operated by the armed guard only. Adequate protection of the
building against lightening would also be provided as per IS: 2309.The Explosive Rules of
1983 lay down that a safe distance of 345 m should exist from the magazine structure of 30
MT capacity to any railway line or public road. It also specifies that a safe distance of 690 m
should exist from the magazine to any houses, dwellings, factories etc. As per investigations
at site, the requirement of 690 m safe distance can be met.
CHAPTER-3
CONSTRUCTION METHODOLOGY
3.1 GENERAL
The project implementation schedules for construction of a hydroelectric project are drawn
with a view to complete all the works and commission the project in the shortest possible
duration, so that the construction cost in terms of IDC is minimum and the project benefits
are accrued early, Mechanized construction has been planned for all components of the
project to achieve consistent quality with faster progress. Construction activities in different
parts of the project will be so sequenced as to optimize the use of construction equipment
and machinery. Access to the various work sites and all the basic infrastructure facilities will
be provided in advance, before taking up of the main civil structures.
Major assumption considered while making the construction methodology are as below:
Diversion Tunnel
The diversion of the river will be carried out diversion tunnel which is constructed on left
bank side by constructing a coffer dam across the length of the Dam portion.The Diversion
Tunnel will be of 10 m finished diameter, 780m length and bed slope of 1 in 130. The key
features of diversion tunnel are given in Table-3.1.
The type of rocks likely to be encountered on the alignment of Diversion Tunnel is given in
Table-3.2.
Excavation: 1 No., 780m long, 10 m finished diameter, Horse-Shoe shaped diversion tunnel
on the left bank of river Chenab shall be excavated through drilling and blasting by heading
& benching method.
Class II
Excavation in Class II classified in drawing as Good rock will be carried out through drilling &
blasting by heading and benching method. The tunnel excavation will be done by
conventional drill and blast method using hydraulic drill jumbo. Drilling will be done by Two
Boom Drill Jumbo. This will be followed by charging and subsequent blasting of the drilled
face. Excavator of bucket capacity 2.0 Cum and 20 T dumpers will carry out clearing of the
generated muck from blasted face. As the excavation proceeds, rock support system by the
way of rock bolts and shotcrete will be provided in accordance with the approved
construction drawings. Drilling of rock bolts will be carried out with Two Boom Drill Jumbo,
while shotcreting will be done by shotcrete machine.
• Surveying
• Drilling
• Charging of drilled holes
• Blasting
• Defuming
• Mucking
• Scaling/Trimming
• Shotcreting
• Rock bolting
• Drainage holes
Class V
Excavation in Class V as classified in drawing falls under Very poor rock mass conditions.
For this class, if the rock is highly squeezing, less pull will be considered. In addition to that,
permanent steel rib support will be provided in accordance with the approved construction
drawings and technical specifications.
The excavation sequence for Class V
• Surveying
• Drilling
• Charging of drilled holes
• Blasting
• Defuming
• Mucking
• Scaling/Trimming
• Shotcreting
• Rock bolting
• Drainage holes
• Rib erection & backfill concrete
The total duration required to excavate 780 m long diversion tunnel shall be (9 + 2.0 months,
considering benching will follow heading after 100 m and will be done 1 month after the
Heading), 11.0 months. In order to reduce time, diversion tunnel will be excavated from both
the faces, with one set of equipment for each face. Thus, total duration of excavation will be
reduced to 6 months. Portal excavation will take initial 1 months. Thus, the total duration will
be 7 months. For Lining of diversion tunnel, including 2 months of Lining for Inlet and Outlet
Portal is 7 months. Thus, the total duration for Diversion Tunnel excavation and Lining is
14.0 months.
The height of the cofferdam will vary based on the river bed. The central hearting zone will
be formed with colcrete. The top of the hearting zone will be 1m below the top level of the
cofferdam. The Colcrete will be overlaid with M 20 concrete.
3.4 DAM
Excavation
In principle this is indicative method of excavation, which will be developed during
construction stages for exact routing of construction ramps, zones, levels to be tackled.
Excavation requiring no blasting operation shall be executed in accordance with theoretical
cut line defined by cross section on the construction drawing taking into account the nature
of ground. Surfaces shall be perfectly levelled and excavations carried out to ensure final
shape.. Excavations in rock requiring blasting shall be carried out in accordance with
blasting specifications. Blasting shall be performed only by licensed and skilled operators
and under the authority of qualified foreman. All the workers involved in blasting works shall
be well trained. Around the blasting area, before blasting, workers shall check that the
affected area is cleared. All blasting works shall be carried out using controlled blasting
technique to minimise any damage to final profile. The depth and spacing of holes, the
amount of explosives to be used for the hole, the distribution of explosives within one hole
and the numbers and sequence of delay detonators shall be selected in order to obtain the
excavations to the lines and grades as specified in the drawings without any over break,
fracturing and loosening of the rock below or beyond the required excavation lines or level or
causing any damages to the adjacent property or permanent work.
The ground of the excavation area shall be blasted in layers with thickness as required to
meet the specified excavation levels, and the end of holes for blasting the final layers shall
not be drilled closer than 0.3 m to the required final level or line. Any excavation surface for
permanent works after blasting shall exhibit a regular fracture plane between barrels without
back break and with half barrels visible over the major portion of the surface.
The method of pre-splitting will be adopted in areas where it is necessary to keep the sound
rock without any cracks for the structures. Such cracks for the final contour are created by
blasting prior to the rest of the holes for blasting pattern.
Blast pattern shall be accurately set out and holes shall be collared within 50mm of the
required position. Holes, which are over drilled, shall be fully stemmed to the required depth
before charging up takes place. All perimeter holes for surface blasting shall be drilled to a
depth of 1 m below the bottom of any production holes adjacent to perimeter plane.
Controlled perimeter blasting techniques shall be used only and if required to obtain the
excavation faces on permanent works to the lines, grades and levels as specified and on
faces steeper than 1V: 1H.
The material excavated and kept in temporary storage for using later for back filling shall be
well protected, to maintain the material properly regardless of the weather conditions. The
storage area shall be safe with slopes in accordance with angle of internal friction with
materials and with necessary drainage to prevent water flooding during heavy rainfall.
Hydraulic excavators will be used to load the excavated soil / blasted rock into the dumpers,
which will be disposed of to the disposal yard. All the necessary slope protection measures
such as rock anchors, shotcreting wherever necessary will be installed simultaneously going
down with the excavation.
Concreting
In the first phase, concreting of Dam block up to EL 2167.00 m will be completed. In the First
phase, second phase, concreting of piers and breast wall will be done from EL 2167.00m to
EL 2222.00m. In the second stage concreting of power intake block and NOF blocks on the
right bank will be completed. In the third phase concreting of NOF on the left bank will be
completed. At last concreting of bridge will be done. A 8.0 m wide bridge is provided over the
spillway with EL at + 2222.00m. Concreting in dam bays will be done on completion of
excavation work in these portions. For the bottom portion in sluice way bays, where
thickness varies through the longitudinal direction concreting will be done on completion of
excavation work in these portions. For the bottom portions in sluice way bays, where
thickness varies through the longitudinal direction concreting will be done through the Tower
crane. L&T formwork shutters will be mobilized for shutters of 1.50m lift. For installation of
gates, first stage embedded parts are placed while concreting is done.
Green concrete from the batching plant will be transported by 6 Cum Transit Mixers to the
location.
Bridge over the pier will be constructed in-situ by fixing form work from the spillway section.
Necessary embedment will be provided to spillway portion to take care of staging for the
bridge. RCC deck slab of the bridge will be concreted using formwork supported on
temporary brackets fixed to the main beams of the bridge by providing inserts during
concreting of the piers. Kerbs and handrails will be placed on both sides all along the length
of the bridge.
20T capacity dumpers will do the mucking and disposal. As the excavation proceeds, rock
support system by the way of rock bolts and shotcrete will be provided in accordance with
the technical specifications and approved construction drawings. Drilling of rock bolts will be
carried out with two boom drill jumbo, while shotrcreting will be done by shotcrete machine.
Excavation Sequence
• Surveying
• Drilling
• Charging of drilled holes
• Blasting
• Defuming
• Mucking
• Scaling/Trimming
• Rock bolting
• Shotcreting
The salient features of bottom horizontal portion of pressure shaft are given in Table-3.3. A
time of 2 months shall be required for excavation of 220 m long bottom pressure shaft.
Excavation of inclined portion of pressure shaft will be taken up as soon as the bottom
horizontal portion of pressure shaft excavation has been completed.
The pressure shaft initially will be constructed by Alimak raise climbing method from bottom
to top. The shaft shall be excavated full face from the bottom. The drilling can be achieved
by jack hammers for a drill length of 2.4m. The charging also will be done by the Alimak
raise climber platform. The muck generated in each blast shall be collected in the horizontal
pressure shaft tunnel and will be disposed out through adit.
Concreting is planned to be carried out in two fronts. After the completion of excavation in
vertical pressure shaft, the lining of vertical shaft will be done by fixing a structural steel liner
and then concreting the remaining portion left around the steel liner. By using the same front
the lining of horizontal portion will be continued and completed.
Horizontal portion of pressure shaft concreting
Rails will be fixed at the invert level matching the alignment of the excavated pressure shaft.
The trolley platform on rails will be used to transport the liner to the required position in the
pressure shaft by winch arrangement. Structural steel liner of required grade will be
positioned on the trolley by crane. The steel liner will be safely secured to the trolley platform
before movement. After transporting the trolley platform along with the steel liner to the
required position, the steel liner piece will be unsecured from the trolley and rose by means
of jack arrangement to release the trolley and removed. The lowered steel liner is positioned
and aligned by means of precast concrete blocks all around. Concrete will be transported
from the batching plant to the entrance of the underground pressure shaft portal by means of
transit mixers. Concrete shall be transported to the concreting location by pumping through
pipes. After fixing the liner pieces and on completion of the alignment, end shutter (bulk
head) will be fixed leaving space for the future liner to be erected and welding to the existing
liner. On completion of fixing the end shutter, concreting will be carried out around the
respective steel liner portion with the help of suitable concrete pump. Repeat the above
process to progress and complete the structural steel liner installation and concrete
encasing.
The liner ferrule will be shifted to the gantry location by trolley, which will be travelling on the
rails. The gantry is used for lowering the liner ferrule to the desired location. The lowered
steel liner is positioned and aligned by means of precast concrete blocks all around.
Concrete will be transported from the batching plant to the entrance of the underground
pressure shaft portal by means of transit mixers. Concrete shall be transported to the
concreting location by pumping through pipes. After fixing the liner pieces and on completion
of the alignment, end shutter (bulk head) will be fixed leaving space for the future liner to be
erected and welded to the existing liner. On completion of fixing, end shutter concreting will
be carried out around the respective steel liner portion with the help of suitable concrete
pump.
The total duration for Bottom Horizontal Pressure Shaft Concreting of 185 m length shall be
4.5, for 171 m shall be 4months for 157 m shall be 3.5 months considering cycle time of
50m/month. The total duration for Inclined Pressure Shaft Concreting, considering
20m/month, for 80 m shall be 4 months and consecutively for 3 shafts 12 months.
Consider 2 months for Anchor Block Concreting and consecutively for remaining 2 shafts,
total duration will be 6 months.
adit until the erection bay Main Access Tunnel excavation is reached and can be used for
material removal from this elevation. The total excavation for stage 3 is 54080 cum.
Stage 4
Elevation 2152.75 m to 2133 m
From erection bay level the excavation will proceed, benching down, to the level of the TRT
with 1.5-3m, benches and leaving a ramp for mucking from erection bay until the TRT level
is reached and can be used. The total excavation quantity for stage 4 is 32120 cum.
Stage 5
Elevation 2133.00 m to 2125.60 m
In continuation, the excavation of draft tubes and drainage pits will take place. Total
excavation quantity for stage 5 is 10970 cum.
Work will start from service bay and draft tube level of Unit 1, service bay columns will be
completed at the earliest to allow for EOT crane erection; 2 months are foreseen for its
erection. Power House first stage concrete will start after the EOT crane installation. This
crane will be utilized for erection of draft tube lining as well as for concrete and formwork
activities during the entire construction period of the Power House.
Power House second stage construction is controlled by the E&M erection phases. In this
stage concrete placing will commence as soon as the erection of the various components of
the machine is completed and the area is made free from concrete embedment.
Simultaneously slab formwork and pouring for different floors will be carried out to build the
offices and galleries as well as the control room. Architectural works and finishing will be
carried out in parallel to E&M works.
6.0m finished diameter D shaped Diversion Tunnel will be excavated by conventional Drilling
and Blasting Method in Full Face, with pull depending upon the type and class of rock mass
encountered. The salient features of Tail Race Tunnel are given in Table-3.5.
The duration for excavation of Tail Race Tunnel shall be 4.5 Months and Portal Excavation
shall take 3 months. Thus, total duration for excavation shall be 7.5 months.For Tail Race
Tunnel Lining duration of 3 months is expected.
CHAPTER-4
4.1 INTRODUCTION
Standard methodologies of Environment Impact Assessment have been followed for
conducting the CEIA study for the proposed Sach-Khas hydroelectric project. A brief
description of the methodology adopted for conducting the CEIA study for the proposed
Sach-Khas hydroelectric project is outlined in the present chapter. The information
presented in this Chapter has been presented through various primary as well as secondary
sources.
4.2 STUDY AREA
The study area considered for the CEIA study is given as below:
• Submergence area
• Area within 10 km of the periphery of the submergence area
• Area to be acquired for siting of various project appurtenances.
• Area within 10 km of various project appurtenances
• Catchment area intercepted at the barrage site
1
L & T Himachal Hydropower Limited
Table-4.1: Scoping Matrix for EIA study for the proposed Sach-Khas Hydroelectric
Project
Aspects of Environment Likely Impacts
A. Land Environment
Construction phase - Increase in soil erosion from
various construction and quarry
sites
- Pollution by construction spoils
- Acquisition of land for labour
camps/ colonies
- Solid waste generated from labour
camps/colonies
Operation phase - Acquisition of land for various
project appurtenances
- Loss of forest land
due to acquisition of land for
various project appurtenances
B. Water resources & water quality
Construction phase - Impact on water quality of
receiving water body due to
disposal of runoff from construction
Sites carrying high sediment level.
- Degradation of water quality due to
disposal of effluent from labour,
camps/colonies
Operation phase - Modification of hydrologic regime
due to diversion of water for
hydropower generation
C. Aquatic Ecology
Construction phase - Increased pressure on riverine
fisheries as a result of
indiscriminate fishing by the
Immigrant labour population.
- Reduced productivity due to
increase in turbidity levels as a
result of disposed off waste water
from construction sites and labour
Camps/colonies.
Based on the Scoping matrix, the environmental baseline data has been collected. The
project details have been superimposed on environmental baseline conditions to understand
the beneficial and deleterious impacts due to the construction and operation of the proposed
Sach-Khas hydroelectric project.
4.4 DATA COLLECTION
4.4.1 Physico-Chemical Aspects
Primary surveys have been conducted for three seasons namely, monsoon, post-monsoon
and pre-monsoon seasons. The data has been collected for flora, fauna, forest types and
ecological parameters, geological and soil features. During these surveys data and
information was collected on physico-chemical, biological and socio-economic aspects of the
study area. In addition, detailed surveys and studies were also conducted for understanding
bio-diversity in the study area.
As a part of the EIA study, primary data has been collected for three seasons. The details
are given in Table-4.2.
Table-4.2: Details of field studies conducted as a part of CEIA studies
Season Months
Monsoon August 2010
Winter November – December 2010
Summer May-June 2011
Geology
The regional geology around the project area highlighting geology, stratigraphy, etc. has
been covered in the EIA Report, as per the available information in the Detailed Project
Report (DPR) of the project.
Hydrology
Hydrological data for river Chenab as available in the Detailed Project Report was collected
and has been suitably incorporated in the Comprehensive EIA study.
Seismo-tectonics
The regional seismo-tectonics around the project area highlighting seismicity has been
covered in the EIA Report, as per the available information in the Detailed Project Report
(DPR) of the project.
Landuse pattern
Landuse pattern of the study area as well as the catchment area was carried out by standard
methods of analysis of remotely sensed data and followed by ground truth collection and
interpretation of satellite data. For this purpose digital satellite data was procured from
National Remote Sensing Agency, Hyderabad, IRS-P6 LISS-IV. The data was processed
through ERDAS software package available with WAPCOS.
Soil
The soil quality was monitored at various locations in the catchment area. The monitoring
was conducted for three seasons as detailed in Table-4.2. The parameters monitored were:
• pH
• Electrical Conductivity
• Organic Matter
• Sodium
• Available Phosphorus
• Available Potassium
• Available Nitrogen
• Cation Exchange Capacity
• Particle Size Distribution
• Texture
Water Quality
The existing data on water quality has been collected to evaluate river water quality on
upstream and downstream of the project site. The water quality was monitored for various
seasons as listed in Table-4.2. The water samples were collected from the study area and
analyzed for physico-chemical parameters which are listed in Table-4.3.
Table-4.3: Water quality parameters analyzed as a part of the field studies
pH Zinc
Electrical Conductivity Mercury
Total Dissolved Solids Cadmium
Sulphates Magnesium
Chlorides Lead
Nitrates Manganese
Phosphates Cyanides
Sodium Hardness
Potassium DO
Calcium BOD
Copper COD
Iron Oil & grease
Total Coliform Fecal Coliform
The secondary data pertaining to fisheries in river Chenab was collected from Fisheries
Department and through literature review as well. Fishing was done at various sites in the
project area and river stretches both upstream and downstream of the dam site of proposed
Sach Khas hydroelectric project to ascertain the dispersal pattern of fish species.
Identification and measurements of all the fish catch was done and an inventory of the fish
species was also prepared. Various migratory species and the species to be affected due to
conversion of lentic to lotic conditions as a result of commissioning of the proposed project
were also identified.
4.5 SUMMARY OF DATA COLLECTION
The summary of the data collected from various sources is outlined in Table-4.4.
• Provision of facilities in labour camps (Heating, Water Supply, Sanitation & Sewage
Treatment Facilities, Solid Waste Management )
• Provision of free fuel to labour population
• Public health delivery system
• Restoration of quarry sites and landscaping of construction sites
• Disposal of Muck and Reclamation of Muck Disposal Sites
• Management of Impact due to construction of road
• Water pollution control Control of Air Pollution
• Measures for noise control
• Greenbelt development plan
• Energy Conservation measures
• Catchment Area Treatment
• Release of Environmental Flows
• Fisheries Management Plan
The expenditure required for implementation of these management measures has also
been estimated as a part of the EMP study.
4.8 CATCHMENT AREA TREATMENT PLAN
As a part of the CEIA study, a catchment area treatment plan for the catchment area
intercepted at the project site has been formulated. An amount of 2.5% of the project cost
has been earmarked for implementation of CAT Plan. Various sub-watersheds have been
categorized into different erosion categories, as per Silt Yield Index (SYI) method. For high
and very high erosion categories, a catchment area treatment plan comprising of
engineering and biological measures has been formulated.
4.9 LOCAL AREA DEVELOPMENT PLAN
As a part of the CEIA Study, a Local Area Development Plan (LADP) has been formulated
for implementation in study area villages. An amount of 1.5% of the project cost has been
earmarked for implementation of Local Area Development Plan (LADP).
4.10 ENVIRONMENTAL MONITORING PROGRAMME
It is necessary to continue monitoring of certain parameters to verify the adequacy of various
measures outlined in the Environmental Management Plan (EMP) and to assess the
implementation of mitigative measures. An Environmental Monitoring Programme for critical
parameters has been suggested for implementation during project construction and
operation phases. The cost required for implementation of Environmental Monitoring
Programme has also been indicated.
CHAPTER-5
HYDROLOGY
Downstream of Tandi, the Chandrabhaga continues to flow in the north westerly direction
when it meets its first major tributary, Miyar Nala on its right (EL 2590 m) at Udaipur. It is
later joined by Sach Nala on its right which drains a catchment area of 690 sq. km and keeps
flowing in this northerly direction till it is joined by Lujai Nala.
After a short journey from the confluence of Lujai Nala, it enters the Paddar area of Kishtwar
district of Jammu and Kashmir state at EL 1980 m.
About 60% of catchment area at Project site remains perpetually covered by snow and
glaciers and the comparatively high flows between March to June are largely contributed by
snow melting. High discharge in the river between July to September is further compounded
due to monsoon precipitation. The minimum flow occurs during December, January and
February.
Table 5.1 Physiographic Parameters of Sach Khas HEP site and Udaipur G&D site
Sach Khas HEP Site
Total catchment area 6588 sq.km
Snowfed catchment area 3973 sq.km (60.31% of total catchment area)
Longest flow path (L) 218.13 km
Centroidal flow path (Lc) 89.54 km
Equivalent stream slope (S) 8.58 m/km
Udaipur G&D Site
Total catchment area 5910 sq.km
Snowfed catchment area 3860 sq.km (65.31% of total catchment area)
Source: DPR
The hypsometric details of the catchment up to Udaipur G&D site as well as Sach Khas dam
site are given in Figures 5.3 and 5.4 respectively and Tables 5.2 and 5.3 respectively.
The 10 daily discharge data at Sach Khas HEP site for the period 1974-75 to 2009-10 is
enclosed as Annexure-II, The 10 daily discharge data at Sach Khas HEP site for 90%
dependable year is given in Table-5.6.
Table-5.6: 10-daily discharge data at Sach Khas HEP site for 90% dependable year
Month Discharge (m3/s)
June I 339.77
II 525.26
III 510.65
July I 722.12
II 724.46
III 502.94
August I 552.68
II 443.77
III 522.50
September I 396.95
II 274.44
III 223.06
October I 145.25
maximum flood under the complex hydro-meteorological conditions in Sach Khas catchment,
it is desirable to separately analyze the contributions of rain storm and snowmelt and then
synthesize them into flood hydrograph with reference to the most severe combinations of
critical hydrological and meteorological parameters/factors that are reasonably possible in
the region. In the absence of the data pertaining to snowfall and seasonal snow cover area;
it is not possible to estimate the snowmelt contributions during the flood conditions. The
base flow is thus assumed to take into account the snowmelt contribution.
The design flood value has been estimated by adopting the following approaches:
• Probabilistic approach using frequency analysis
• Deterministic approach using Unit Hydrograph analysis
• Transfer from downstream projects using Dicken’s formula
Daily discharge observations at Udaipur had been taken once in a day. The peak discharges
are limited to the above condition, which do not take into consideration the possible peak
discharge occurrences during the daily non-recorded hourly gauge observation. However the
frequency analysis has been carried out with this limitation. As it is quite likely that possible
peaks might have been missed for reasons explained above, the design flood peak arrived
The summary of the flood frequency analysis by the above three distributions is given in
Table-5.10.
A 24-hour clock hour correction of 15% has been applied to 1-day SPS and PMP as
suggested by India Meteorology Department (IMD). The temporal distribution of rainfall for 1-
day is given in Table-5.12 and plotted in Figure-5.6.
Loss Rate
A uniform loss rate of 2 mm/hour has been adopted as suggested by CWC.
Figure-5.8: Design flood hydrograph adopted for Sach Khas hydroelectric project
5.9 SEDIMENT DATA AVAILABILITY
The Silt rate estimated at various sites namely Udaipur, Benzwar and Premnagar Site in
Chenab river basin by CWC are tabulated as in Table-5.18.
Table- 5.18: Details of Silt data
G&D Site C. A. Type of Period River Sediment Source
(Sq.km) Data Rate
(Ha-m/Sq.
km/Yr.)
Udaipur 5910 Daily Jan’03- Chenab 0.0287 Calculated
May’08
Benzwar 10687 Monthly Jun’73- Chenab 0.081 Calculated
May’02
Premnagar 15490 Avg. 1968 to Chenab 0.155 Sept 84
Annual 1976 Feasibility
Report,
Baglihar HEP,
Volume-VI
Source: DPR
It may be concluded from Table-5.18 that annual silt yield increases as we go downstream
of the river. The Sach Khas catchment area is nearly half the catchment area of Benzwar
and one-third that of the Premnagar. Sach Khas site is near the vicinity of Udaipur, but the
data availability at Udaipur is of short period, so annual silt yield is linearly interpolated
between Udaipur and Benzwar after taking account of 20% suspended load (as per standard
BIS practice) as bed load for both the sites. The annual silt yield estimated is 0.0433 ha-
m/sq.km/year.
CHAPTER-6
TOPOGRAPHICAL AND GEOLOGICAL ASPECTS
6.1 INTRODUCTION
The Sach Khas Hydroelectric Project envisages ±90.0 m high concrete gravity dam across
the river Chenab (N 76025’25” E 32058’), about 8 km downstream of Purthi Village in order
to create a reservoir of the capacity of 8.69 MCM between FRL 2219 m and MDDL of
2209.3m. The water will be conducted through the dam to the underground power house
through 300 m long pressure shafts.
In order to utilize the full potential between (EL 2219.0m) and (EL 2149.0m) & keeping in
view the environmental and ecological balance, various schemes i.e. Alternative II,
Alternative III, Alternative III-A and Alternative IV were investigated. Eventually, the present
scheme with a ±90.0 m high concrete gravity dam with underground power house has been
evolved, which is geotechnically feasible and techno economically viable. Various
alternatives considered for the Sach Khas Hydroelectric Project are summarized in Table
6.1.
The following geotechnical mapping and sub-surface investigations have been carried out to
evaluate various alternative layouts.
Bhaga Valley. The altitude of the area varies between 2500m and 6000m with several peaks
projecting over ∆6000m above mean sea level. The Shopu or Trishul peak (∆5222m) marks
the boundary of Himachal Pradesh with that of Jammu and Kashmir. The mountains are
bare along the upper reaches whereas they are forest covered along the lower slopes.
The Chenab river is a major river of the Indus Basin, originating from the Great Himalayan
and Pir Panjal ranges. The river formed by two major tributaries in the upper reaches i.e.
Chandra river and Bhaga river. The Chandra originates from Bara-La Che La whereas
Bhaga takes off from Suraj Tal in the vicinity of the Bara-La Cha La; Bhaga River is further
joined by the Jhankar and the Milang Nala before it joints the Chandra at Tandi to form
Chandrabhaga or Chenab River. Further downstream of its confluence, it is joined by other
significant tributaries namely Shansha Nala near Rashil and Thirot Nala at Thirot, Miyar Nala
at Udaipur, Saichu Nala at Dawag, Ajog, Bakanwal, Kulna Nala, Sach and Chhoo Nala in the
vicinity of Purthi, Dheda Nala, Saichu Nala near Cherry and Lu jai and Sansari Nala
downstream of Killar town. The river in its course traverse through the Lahaul, Pattan and
Pangi Vally of the Himachal Pradesh before entering into Jammu and Kashmir, downstream
of Biana Nallah.
The terrain in the upper reaches of tributaries shows typical glacial landscape characterized
by rugged towering peaks, cirque glaciers and moranic deposits. There are also thick and
extensive alluvial fans. At the higher reaches of the valley, the thickness of colluvium cover
varies from a few meter to 10 meter but in the lower portions it could be even up to ±20 to
30m in a few stretches. These tributaries show sub dendritic to trellis pattern of drainage.
The higher reaches of the slopes on either side of the Chandra Bhaga or Chenab River have
a number of glaciers which forms the perennial source of discharge in tributaries. About 200
glaciers have been identified in the Chenab basin in Himachal Pradesh of which 43 lies on
its southern side in Pir Panjal range and 157 on the northern side. As per Dobhal and Kumar
(1966), the ratio between basin area and glaciated area is 4.22:1.
The valley slopes in the area are characterized by the stretches of unusually abundant
debris. These could have been formed due to the fractured or weathered rocks transported
in abundance by snow, avalanche and landslides to the lower elevations on the banks of the
river.
The rock at and around this stretch of the area are represented by dark grey phyllitic
quartzites and quartzites with thin carbonaceous and pelitic bands. They belong to Haimanta
group of Proterozoic age and the geological succession worked out by Prashara et al (1986-
87) and Prashara (1992) is given in Table-6.2. The Regional Geology is depicted in Figure-
6.1.
Table-6.2: Geological succession of the Area
GROUP AGE FORMATION LITHOLOGY
Haimanta Proterozoic Kunzum La Greenish grey siltstone, shale
& dolomite
Batal Quartzite, phyllite, Carbonaceous
and pyritous.
(It also includes Manjir and Katarigali
Formations)
Lahaul or Chola Thach Garnetiferous schist and quartzite
Rohtang
Gneissic Gufa Granite gneiss, migmatite and
meta sediments
Group
Source: DPR
Haimanta Group of rocks has been divided into Batal and Kunzum- La Formations. In the
south-eastern part of the Lahaul i.e. in the valley of Chenab or Chandra-Bhaga, the Batal
Formation of this group is regarded to be represented by Manjir and Katarigali Formations of
Vaikrita Group of Chamba area. Here Rapa & Gadhoke (1984) mapped two formations i.e.
Bagotu and Dunai which were regarded equivalents of Manjir and Salooni Formations of
Chamba area. Subsequently un-fossiliferous part of Salooni Formation was renamed as
Bharmour Formation and correlated with Katarigali Formation of Jammu & Kashmir. These
formations have not been defined in the rest of Lahaul area except that the pelites
underlying the Tandi Group were correlated with Salooni and conglomerate exposed at
Chobia and Trilokinath with Manjir Formation by Raina and Prashara (1973).
metamorphic evolution of this part of the Himalayan range. It comes out from these previous
works that the Himalayan structures are dominated by SW-directed thrusting and folding.
However, in the Spiti and the Chenab Valley area, early NE-directed verging structures have
also been described. Following these works, four major tectonic events are considered to
explain the tectonic evolution of the Chamba, Zanskar and Lahaul area.
The North Himalayan nappes emplacement is responsible for the main phase of
deformation affecting the sedimentary sequences of the Tethyan Himalaya in the northern
part of the range. The name of Nyimaling-Tsarap nappe was introduced by Steck et al (1993)
for the whole thrust pile of sedimentary rocks located between the Indus Suture Zone to the
north and the Baralacha La to the south. The internal structure of this nappe stack is
characterized by a progressive change in style of deformation. The northern part of the range,
close to the suture zone, corresponds to the root zone of the Nyimaling-Tsarap nappe. In this
region, the deformation is primarily accommodated by ductile shearing and folding. In
contrast, in the frontal part of the nappe, the deformation becomes more and more brittle and
is characterized by the development of imbricate structures.
In the Lahaul and Spiti area, the early NE directed structures of the Shikar Bah nappe (DI)
are overprinted by SW-directed folding. These D3 structures are observed in the central
and southern part of the upper Lahaul, and intensity of deformation increases from NE to
SW, whereas no D3 large scale structures was highlighted in Chenab valley area. This
D3 phase is, on the other hand, responsible for the spectacular SW-directed Kalath fold
in the Kullu Valley (Thoni, 1977). On the, basis of its vergence, its style and its location, this
D3 phase is interpreted as related to the SW-directed folding and thrusting of the High
Himalayan nappe along the Main Central Thrust (e.g. Crystalline nappe; Frank et al; 1977).
This SW-directed nappe is generally formed of the metamorphic core zone of the
Himalayan Orogen. In numerous sections along the range, the crystalline nappe is
separated from the low-grade metamorphic sediments of the Tethyan Himalaya by the
extensional Zanskar Shear Zone (Dezes et al; 1999) considered as a local equivalent of
the south Tibetan Detachment System.
In the central and eastern part of the Himalaya, the metamorphic core zone of the range
corresponds to a 5-40 km thick, NE-dipping monoclonal slab. In contrast, in the
northwestern part of the Himalaya of India, the high-grade metamorphic rocks are
mainly exposed in a more internal part of the orogen. A major characteristic of this
high-grade metamorphic zone in the Zanskar area is the presence of several large-scale
dome structures, cored by Cambro-Ordovician granitic gneisses and/or tertiary migmatites
and leucogranites. This particular setting implies that the exhumation of high-grade rocks in
this part of the range was for a large part controlled by doming. The exhumation of these
rocks back to the surface and the mechanism of dome formation are a complicated and still
debated problem.
The proposed Sach Khas hydroelectric project is situated in between MCT and STDS in broad
tectonic framework of the Tethyan Himalayas and Central Crystalline sequences. In NW
Himalayas the Main Central Thrust is disposed as window and Klippe structures. The Kishtwar
Window is located towards NW of the project area, while Kullu-LargiRampur Window in SE
direction. Towards south in Chamba region, the MCT run more or less parallel to MBT in NW-SE
direction. The Shimla Klippe is significant adjunct to this thrust. Other tectonic element like
MBT and HFT lies further south of MCT while STDS and Zanskar shear zone towards north
of the project area. The some of the important local thrust/fault are Miyar thrust also refer by
some authors (e.g. Thakur, V.C, 2002) as Chenab Normal Fault, Salgaron thrust, Sarchu fault,
Panjal thrust and significant shear zone such as Killar-Miyar shear zone, Kanjhar shear zone
and Zanskar shear zone disposed in the north of the project area.
A review of the published maps suggest that the nearest Tectonic elements such as Miyar and
Salgarom thrust and located more than 50 km away and other fault such as Sundarnagar and
Kistwar faults are located more than 70km away from the Sach Khas project area and no
tectonic implications are foreseen.
deformation style located between the MCT and MBT, the Basement Thrust Front (BTF). It
has also been postulated that the Detachment surface and the MCT and related thrust
surfaces, which are steeper than the detachment surface merge beneath the Great
Himalayan Range.
The most referred conceptual tectonic model of the Himalayan Seismic Belt (HSB), the
seismic zone within the MBT and MCT, suggests that below the Main Central Thrust
(MCT) lies the Basement Thrust Front (BTF), a ramp. The ramp is a geometrical asperity
on the plane of detachment, which accumulates the stress due to collision tectonics in
the Himalaya, and it was suggested that the great earthquakes occurred on the plane of
detachment. The plane of detachment separates the Indian shield and the Himalayan
sedimentary wedge; some authors named it Main Himalayan Thrust (MHT).
The Himalayan Seismic Belt generated several large and great earthquakes based on
which a conceptual tectonic model was envisaged. The Himalayan tectonic model fits
fairly well with the Western Himalayan seismicity to the north of MBT, where earthquakes
occur on the MHT at shallower (<20 km) depth. The four great earthquakes that
occurred to the south of MBT, however, do not fit into this model. It is argued that these
events are not on the MHT, each occurred at a deeper depth in different tectonic
domains.
The upper Chenab valley area encompassing the proposed Sach Khas Hydroelectric
project is located in highly seismic Central Himalayas. Tectonically, the region is located
in Main Himalayan Tectonic Belt bounded by Indus Suture Zone (ISZ) in the north and
Main Boundary Fault—(MBF-1) in south. Most important tectonic plane within this belt is
Main Central Thrust (MCT). However, its position in the area between the rivers Beas and
Chenab has not been clearly demarcated. The other feature of tectonic importance in this
belt is the Vaikrita Thrust. The tectonic zone south of Main Himalayan Belt is Frontal Fold
Belt demarcated in north by MBF1 and in south by Foot Hill Thrust (FHT). The important
tectonic surfaces in this zone include MBF-II, Jwalamukhi Thrust and MBF-III apart from
several transverse faults. From seismotectonic point of view, the project area falls on the
western margin of Kangra Seismic Block of Narula (1991) which is demarcated by Ravi
Tear in west and Sunder Nagar Fault in east. The earthquake catalogue of IMD indicates
that the concentration of magnitude >4<5 earthquakes is maximum in 'the area, being
71% of total recorded events between latitude 32°-3 4°and longitude 75°- 78°. The
catalogue also indicates that after 1964, when worldwide seismic network was
established, a total of 83 earthquakes were recorded up to March, 1995 in the above
mentioned area. The percentage of earthquakes with magnitude >4<5 was 75, those with
magnitude >5<6 were 14% and rest of the events had greater magnitude.
Major earthquakes of the region include Kangra-1905 (M=8); Chamba-1945, 1947, 1950
(M=6.5, 6.2, & 5.5); Dharamshala 1978, 1986 (M= 5 & 5.7) and Kathua-1980 (M=5.3). As
per Zoning Map of India Showing Seismic Zones (IS: 1893-2002 (Part-1)), the project
area lies in Zone-V i.e. highest seismic zone in Western Himalayas. (Refer Figure-6.2 &
6.3). Therefore, it is recommended that suitable seismic coefficient to commensurate with
the seismic status of the area may be evolved based on detailed seismo-tectonic and
seismological studies and incorporated in the design of various appurtenant structures of the
scheme.
POWER HOUSE
The underground power house cavern has been located in the North-South ridge, about
300m downstream of the dam axis. The underground cavern will be located in grey quartzite,
diamictite and phyllitic quartzite bands. The foliation trends N40oW – S40oE with 35o-40o dips
towards SW i.e. downstream.
The proposed power house cavern is likely to encounter fresh and hard quartzite (55% to
60%), diamictite and phyllitic quartzite (30% to 35%) in 80 to 85% reach, phyllite in 10%
reach and sheared and shattered rock mass in 5% reach.
PRESSURE SHAFTS
The water from the reservoir will be carried through three, 5.8m diameter (finished diameter)
and approx. 300m long pressure shafts embedded partly in dam body (EL±2150m) and
partly in the toe of north south trending ridge at an invert level of EL 2140.40m on the right
bank of river Chenab.
The pressure shafts will roughly pass through 45% in quartzite, 25% in diamictite and 30% in
phyllite and phyllitic quartzite rock mass. The rock quality index ‘Q’ probably varies from 7.8
to 3.6 whereas, the shear seams and shattered rock mass may have ‘Q’ values of 1.6 to
<0.5.
DIVERSION TUNNEL
The proposed diversion arrangement consists of a 10m dia. and 780.0m long tunnel and is
located on the left flank of the Chenab River in a North South trending ridge. The inlet portal
of the Diversion Tunnel is located 280m upstream of the Sach Khas dam axis whereas outlet
portal is located 350m downstream of the dam axis.
The diversion tunnel roughly passes through 52% in quartzite, 28% in diamictite and 20% in
phyllitic quartzite and phyllite interbands. The rock quality index ‘Q’ will probably vary from
3.2 to 7.4 for moderately jointed and competent quartzite diamictite; the values for thinly
foliated phyllite and phyllitic quartzite may be of the order of 1.2 to 4.1 whereas soft rock
units, shear seams and shattered zones may have a Q values of 0.15 to 0.04.
COFFER DAM
For construction requirement, two coffer dams, 200m upstream and 290m downstream of
the Sach Khas dam axis have been proposed with top level fixed at EL 2172m and EL
2162m respectively.The grey color, fresh and hard quartzite with phyllitic quartzite and
phyllite interbands are exposed on both the abutments of the upstream Coffer Dams.
The Tail Race Tunnel (Tunnel) in say from power house cavern run in N350W-S350E
direction. The tunnel would negotiate fresh, hard and competent quartzite, diamictite, phyllitic
quartzite and phyllite inter bands in its entire reach.
The TRT will encounter fair to poor rock mass and the ‘Q’-values varying from 6.3 to 1.6 for
the quartzite, phyllitic quartzite and diamictite inter bands. The ‘Q’-values will be 1.1 to <0.1
for the phyllite and sheared rock mass.
CONSTRUCTION ADITS
A 220m long and 8.0m dia. ‘D’ shaped MAT to power house cavern has been planned at an
invert level of 2163.0m with a down grade of 13.9:1, upstream of the Bambal Nala. The MAT
will have a vertical cover of 5-7m in the initial reach to more than 100m in the cavern area.
The MAT will encounter moderately fresh to fresh quartzite and phyllitic quartzite at the
portal with a W=II weathering and stained joints in the initial reaches followed by hard and
fresh grey color quartzite (50%) diamictite (20%), phyllitic quartzite (20%) and phyllite
interbands and shear seams 10%. The general trend of foliation is N550W-S550E with 760 to
800 southwesterly dips.
The Q-values generally varies from 3.4 to 1.6 for the quartzite, phyllitic quartzite & diamictite
and 1.1 to 0.01 for phyllictic and sheared rock mass in the reach between 0m to 80m length.
It is followed by Q= 7.8 to 1.6 for quartzite & diamictite and 3.2 to <0.5 for phyllitic quartzite
and phyllite for the rock mass between 80m to 220m length.
A 200m long construction adit for the excavation of the top of power house cavern has been
planned at an invert level of 2163.0m upstream of the MAT. The adit will subsequently be
used as ventilation tunnel in the power house cavern area.
Hard and fresh quartzite with diamictite, phyllitic quartzite and phyllite interbands are
expected to encounter in the adit. The percentage of rock mass will be of the order of 50%,
20%, 20% and 10% respectively. The general trend of foliation is N550W-S550E with
760southwesterly dips. For the initial 60.0m reach, the rock mass quality index Q generally
varies from 6.4 to 1.6 for quartzite, diamictite & phyllitic quartzite inter bands and 1.1 to <0.1
for phyllitic quartzite & sheared rock mass whereas from 60.0m to 200.0m length of adit Q-
values will be of the order of 7.8 to 1.6 for quartzite & diamictite and 3.2 to <0.5 for phyllitic
quartzite, phyllite and sheared rock mass.
for quartzite & diamictite and 1.1 to <0.1 for weathered phyllitic quartzite, phyllite & sheared
rock mass. The reach between 55m to 155m length is likely to encounter Q-values ranging
from 6.8 to 3.2 for quartzite & diamictite and 1.6 to <0.5 for weathered phyllite & sheared
zone material.
RESERVOIR AREA
A detailed assessment of the reservoir area has been made and in principle, it is qualitative
and is largely based on the observations of geomorphology, vegetation and geology backed
by approximate measurements of the slide features. The 90.0m high, Sach Khas dam with
FRL 2219.0m will have water way of about 8.4km and extend 400m upstream of the Purthi
Bridge.
The topography of the reservoir area comprises of steep slopes along the right and left bank
of the reservoir in a broad ‘U’ shaped valley. The lower elevations comprise glacial drifts,
glacio-fluvial deposits; colluvial / slope wash material, riverine material with exposures of
rocks.
The rock exposed in reservoir area is mainly quartzite with diamictite, quartzite phyllite and
phyllite interbands, trending N300-750W – S300-750E with 400 to 850 south westerly dips. The
rocks are highly folded and crenulated. In addition to the foliation joints, the rock mass is
traversed by four prominent sets of joints i.e. (a) East –West / 200 to 450 northerly southerly
dips (b) North-South/ 500 to 800 Easterly southerly dips (c) N450W-S450E/ 600 to 700
Northerly easterly and (d) N450E-S450W/ 300 to 700 North Westerly dips.
CHAPTER-7
7.1 GENERAL
Before start of any Environmental Impact Assessment study, it is necessary to identify the
baseline levels of relevant environmental parameters which are likely to be affected as a result
of the construction and operation of the proposed project. A similar approach has been adopted
for conducting the CEIA study for the proposed Sach khas hydroelectric Project. A Scoping
Matrix as outlined in Chapter-4 was formulated to identify various issues likely to be affected as
a result of the proposed project. Based on the specific inputs likely to accrue in the proposed
project, aspects to be covered in the EIA study were identified. The other issues as outlined in
the Scoping Matrix were then discarded. Thus, planning of baseline survey commenced with
the shortlisting of impacts and identification of parameters for which the data needs to be
collected. The baseline setting for physico-chemical aspects have been covered in this
Chapter.
7.2 METEOROLOGY
Temperature
Temperature variation in the project area ranges from extreme cold in winter to moderate
temperatures in summer. During winter season, upper reaches of most part of the project
area is covered with snow and temperature remains much below the freezing point
throughout winter season. Cold season precipitation is observed from December to March.
The storms from Iran and Baluchistan side are mainly responsible for heavy snowfall during
winter season in the area. The catchment area is by and large snow bound for about two
months during winter season. For the remaining months, the lower reaches of the drainage
area is free from the snow cover.
For a major part of the year, the basin is under the effect of cold weather systems; viz.
Western Disturbances. The Dhauladhar, the Pir Panjal and the Zanskar ranges of the
Himalayas impart distinct climatological features to the Chenab basin.
Temperature data is not available within the catchment up to Sach Khas. However, daily
maximum and minimum temperature data observed by IMD are available in the downstream
of Sach Khas dam site viz. at Badarwah and Banihal falling in J&K. The data availability is
shown in Table-7.1.
PRECIPITATION CHARACTERISTICS
There are a few raingauge stations in the project catchment maintained by India
Meteorological Department (IMD). The details are given in Table-7.3.
The monthly average rainfalls in the project catchment based on the weights above is
estimated as 798 mm. The monthwise rainfall is given in Table-7.6.
Table-7.6: Monthly average rainfall in the catchment area of Sach Khas HEP
From the above analysis, a few important features of the precipitation pattern emerges –
1. There are two distinct rainfall cycles – one from November to May and the other from
June to October. Rainfall in the winter season is attributed to Western Disturbances
moving from West to East in westerly wind regime that normally prevails over the
Himalayan latitudes. From July to October, the basin is normally under the influence
of southwest monsoons.
2. The amount of rainfall in winter due to Western Disturbances is more than that in
summer due to Monsoon. From the results of the analysis carried out, it comes out
that out of the total annual rainfall, rainfall in the period November to May is 67%
against 33% rainfall in the period June to October. It may be mentioned here that the
flood producing area is however quite diminished in the winter season and therefore,
the extreme flood events are always experienced in the monsoon season.
3. Based on the available data the average annual rainfall in the project catchment is
797.77 mm. It may be mentioned that this not the representative of the catchment, as
most of the catchment area remains snow-covered and snowfall data is not available.
7.3 SOILS
Soil is the product of geological, chemical and biological interactions. The soils in the region
vary according to altitude and climate. The soil in the project area and study area are young
like any other region of Himalayas. The vegetal cover is one of the most important
influencing factors characterizing the soil types in a region. Soil on the slope above 30o, due
to erosion and mass wasting processing, are generally shallow and usually have very thin
surface horizons. Such soils have medium to coarse texture. Residual soils are well
developed on level summits of lesser Himalayas, Sub-soil are deep and heavily textured.
As a part of field studies, soil depth at various locations in the catchment area ranged from
20 to 50 cm. has been collected during summer, post-monsoon and winter seasons and
were analyzed. The sampling stations are shown in Figure- 7.5. The results of the analysis
of soil sampling conducted for Monsoon, winter and pre-monsoon seasons are given in
Tables-7.7 to 7.9 respectively.
0.25 to %w/w 26.2 26.0 27.1 24.2 21.4 27.1 26.2 25.1 27.0 24.4
0.149mm
0.149 %w/w 27.4 24.1 14.2 15.6 18.4 27.8 27.0 25.1 27.1 27.1
to0.088mm
0.088 to %w/w 8.4 9.2 9.1 7.3 11.7 11.9 9.9 7.4 9.6 11.4
0.074mm
0.074 to %w/w 1.2 0.8 1.7 1.8 2.1 1.7 1.3 2.1 1.9 1.5
0.0625mm
0.0625 to %w/w 1.4 0.7 1.8 1.4 1.5 1.5 1.4 2.0 1.5 1.2
0.053mm
<0.053mm %w/w - - - - - - - - - -
Source: Field Studies
Table-7.8: Results of soil sampling analysis of study area (winter season)
Parameter Unit S1 S2 S3 S4 S5 S6 S7 S8 S9 S10
pH - 7.3 7.5 7.6 7.4 7.4 7.1 7.1 7.3 7.0 7.2
Electrical micro 17.0 18.4 25.2 20.2 23.7 16.0 26.2 18.4 20.7 27.1
Conductivity mhos/
cm
Organic % 0.8 0.7 0.8 1.0 1.1 1.5 1.2 1.1 1.2 1.0
Matter
Available kg/ha 10 15 14 12 14 12 14 14 10 13
Phosphorous
(as P2O5)
Available kg/ha 130 160 120 130 120 150 140 110 120 130
Potassium
(as K2O)
Available kg/ha 282 305 312 287 280 340 276 241 310 240
Nitrogen
(as N)
Cation meq/ 11.4 12.0 11.5 12.2 11.2 12.8 11.6 12.0 11.5 11.2
Exchange 100gm
Capacity
Particle Size %w/w
Distribution
>0.25mm %w/w 24.1 25.1 18.4 21.2 23.7 25.1 20.4 21.8 21.5 17.9
0.25 to %w/w 26.2 26.0 27.1 24.2 21.4 27.1 26.2 25.1 27.0 24.4
0.149mm
0.149 %w/w 27.4 24.1 14.2 15.6 18.4 27.8 27.0 25.1 27.1 27.1
to0.088mm
0.088 to %w/w 8.4 9.2 9.1 7.3 11.7 11.9 9.9 7.4 9.6 11.4
0.074mm
0.074 to %w/w 1.2 0.8 1.7 1.8 2.1 1.7 1.3 2.1 1.9 1.5
0.0625mm
0.0625 to %w/w 1.4 0.7 1.8 1.4 1.5 1.5 1.4 2.0 1.5 1.2
0.053mm
<0.053mm %w/w - - - - - - - - - -
Source: Field Studies
0.25 to %w/w 26.2 26.0 27.1 24.2 21.4 27.1 26.2 25.1 27.0 24.4
0.149mm
0.149 %w/w 27.4 24.1 14.2 15.6 18.4 27.8 27.0 25.1 27.1 27.1
to0.088mm
0.088 to %w/w 8.4 9.2 9.1 7.3 11.7 11.9 9.9 7.4 9.6 11.4
0.074mm
0.074 to %w/w 1.2 0.8 1.7 1.8 2.1 1.7 1.3 2.1 1.9 1.5
0.0625mm
0.0625 to %w/w 1.4 0.7 1.8 1.4 1.5 1.5 1.4 2.0 1.5 1.2
0.053mm
<0.053mm %w/w - - - - - - - - - -
Source: Field Studies
The pH of soil at various sites lies within neutral range. The levels of NPK indicate moderate
soil productivity. The CEC levels do not indicate any potential for soil salinization or adverse
impacts on soil productivity
In a hydroelectric project, no significant impact on soil quality is expected barring, soil
pollution at local level due to disposal of construction waste. For amelioration of such
impacts appropriate management measures are recommended.
W1 - At dam site
W2 - 1 km upstream of dam site
W3 - 1 km downstream of dam site
W4 - 3 km downstream of the dam site
W5 - Power house site.
Table-7.13: Drinking water quality standards (Specified by Central Public Health and
Environment Engineering Organisation (CPHEEO)
Characteristics *Acceptable **Cause for
Rejection
Turbidity (units on JTU scale) 2.5 10
Colour (Units on platinum cobalt scale) 5.0 25
Taste and Odour Unobjectionable Unobjectionable
PH 7.0 to 8.5 <6.5 or >9.2
Total Dissolved Solids (mg/l) 500 1500
Total hardness (mg/l) (as CaCO3) 200 600
Chlorides as CD (mg/l) 200 1000
Sulphates (as SO4) 200 400
The total hardness in water samples ranged from 44-51 mg/l and 47 to 57 mg/l in monsoon and
winter season respectively. In summer season, Hardness level ranged from 43 to 50 mg/l. The
low hardness level can be attributed low calcium and magnesium levels, which are responsible
for soft nature of water. The low EC and TDS values indicate the lower concentration of cations
and anions. The concentration of TDS level ranged from 72 to 84 mg/l in various seasons,
which is much lower than the permissible limit of 500 mg/l specified for domestic use (Refer
Table-7.13). This is also reflected by the fact that the concentration of most of the cations and
anions are well within the permissible limit.
The BOD values are well within the permissible limits, which indicate the absence of organic
pollution loading. This is mainly due to the low population density and absence of industries in
the area. The low COD values also indicate the absence of chemical pollution loading in the
area. The marginal quantity of pollution load, which enters river Chenab, gets diluted. In fact,
even for the minimum flow, there is more than adequate water available for dilution. The heavy
metal concentration in the study area is below the permissible limit used for drinking purposes.
Total Coliform count is nil in the study area. It can be concluded that water quality was
observed to be quite good, as various parameters are well below the permissible limit specified
for meeting domestic requirements.
The day time equivalent noise level at various sampling stations ranged from 40.0 to 40.7
dB(A) and 41.5 to 41.6 dB(A) and 42.3 to 43.9 dB(A) in monsoon, winter and summer
seasons respectively. The noise levels were observed to be well within permissible limits
specified for residential area (Refer Table-7.17).
The ambient air quality with respect to the study area around the proposed site forms the
baseline information. The study area represents rural environment. The sources of air
pollution in the region are vehicular traffic, dust arising from unpaved roads and domestic
fuel burning. The prime objective of the baseline air quality study was to establish the
existing ambient air quality of the area. This section describes the identification of sampling
locations, methodology adopted for monitoring, and frequency of sampling.
Three Ambient Air Quality Monitoring (AAQM) locations were selected taking care of above-
mentioned points. The following stations have been monitored:
• Near dam site
• Near power house site
• Village Shin
The location of Ambient Air Quality Monitoring stations are shown in Figure-7.8.
The findings of ambient air quality monitoring in various seasons are given in Table-7.19.
The ambient air quality standards are given in Table-7.20.
Table-7.19: Findings of ambient air quality monitoring in various seasons
Parameter Average (µg/m3) Maximum (µg/m3) Minimum (µg/m3)
Particulate Matter 44.8 – 51.9 49 – 56 42 – 49
less than 10
microns (PM10)
Sulphur dioxide 6.4 – 7.2 7.0 – 7.6 BDL
(SO2)
Nitrogen dioxide 8.7 – 11.8 10.4 – 13.2 7.6 – 8.9
(NO2)
Notes:
• Annual arithmetic mean of minimum 104 measurements in a year at a particular site
taken twice a week 24 hourly at uniform intervals.
• 24 hourly or 08 hourly or 01 hourly monitored values, as applicable, shall be
complied with 98% of the time in a year. 2% of the time, they may exceed the limits
but not on two consecutive days of monitoring.
The SO2 level was Below Detectable Limit BDL) of 6 µg/m3 at some stations covered in
ambient air quality monitoring programme. The SO2 level observed at various sampling
stations was much lower than the permissible limit of 80 µg/m3 for residential and rural areas
are given in Table-7.20.
Observations on NO2 levels
The highest average NO2 values of 11.8 µg/m3 was observed at power house site in winter
season. The highest value of 13.2 µg/m3 too was also observed at the same station in winter
season. The NO2 level observed at various sampling stations was much lower than the
permissible limit of 80 µg/m3 for residential and rural areas are given in Table-7.20.
Although two different approaches to the development of the multi-variate statistics are
used, unsupervised and supervised, their combination gives better results. In the
unsupervised classification, the radiance values of the image data set were submitted to
clustering algorithms that generate statistics until the stopping rule i.e. minimum number of
points per cluster was reached and the minimum distance between clusters and separability
measure was established. Another approach is to 'seed' spectral space with starting points
to establish candidate mean value for clusters, and then iterate the clustering procedure until
minimization criteria is achieved. In the supervised method, training sites with known
properties were used to extract spectral statistics from the image data by interactively
identifying the sites in the imagery. Ground truthing was done for site identification. In the
unsupervised method, identification of the cluster was done after completing the
classification by comparing the spatial distribution of the mapped classes with ground
reference data.
The wide geographic distribution and the range of sites and climates occupied by forests
complicates the understanding of the interaction of forests with solar radiation. Many forests
grow in uneven mountainous terrain. The terrain relief produces large variations in how solar
radiation reaches the forests and produces land form shadows. Terrain relief also generates
large micro-climate variations in temperature, precipitation, and soil properties that produce
large differences in forest composition and activity over elatively small geographic areas.
Vegetation indices are an aid for obtaining accurate results. The DN values of different
bands can be combined mathematically to create output images that can be used
extensively in forest analysis to bring out small differences between vegetation classes.
These mathematical combinations are called indices and if chosen judiciously, they highlight
and enhance differences, which cannot be observed in the display of original color bands.
Indices also help in minimizing shadow effects in satellite multi-spectral images. Ground
truth studies were conducted in the area to validate various signals in the satellite images
and correlate them with different land use domains. The image obtained after the vegetation
index, enhancement becomes a single band data Le. The grey set. The grey set was
merged with the colored False Color Composite (FCC). This image was then classified using
the prominent signatures extracted based on the past experience. However, this is only a
preliminary classification which will be refined further. The classified image of the study area
is given as Figure-7.9. The landuse pattern of the study area is given in Table-7.21.
Table 7.21: Land use pattern of the study area of Sach Khas HE project based on
satellite data
S.No Category Area(ha) Area(%)
1 River 15 0.03
2 Dense Vegetation 18443 38.79
3 Open Vegetation 12956 27.25
4 Agricultural Land 4903 10.31
5 Scrubs 404 0.85
6 Snow 6919 14.55
7 Degraded/Barren Land 3758 7.90
8 Settlements 152 0.32
Total 47550 100.00
Source: Satellite Data
The major landuse category in the study area of Sach Khas HE project is dense vegetation,
as it accounts for about 38.79% of the study area followed by open vegetation (27.25%).
Snow covered area accounts about 14.55% of the study area. The area under Agricultural
Land is 10.31% of the study area. Barren land accounts for about 7.9% of the study area.
Settlements account for about 0.32% of the study area. The area under scrub and water
bodies is 0.85% and 0.03% of the study area.
42
L & T Himachal Hydropower Limited
CHAPTER-8
BASELINE SETTING FOR ECOLOGICAL ASPECTS
8.1 GENERAL
Before start of any Environmental Impact Assessment study, it is necessary to identify the
baseline levels of relevant environmental parameters which are likely to be affected as a result
of the construction and operation of the proposed project. A similar approach has been adopted
for conducting the CEIA study for the proposed Sach Khas hydroelectric Project. The baseline
setting for Ecologcal aspects have been covered in this Chapter.
8.2 FORESTS & FOREST TYPES
The Pangi valley is spread over an area of about 1176 sq miles. Out of which, 602 sq miles
falls under grass land, 93 sq miles under forest and 3 sq miles under cultivation (Minakshi
Chaudhary, 1998). The forest predominates with mixed broad leaves to conifer on the
downslopes. Among broad leaves birch and maples are common, however, oak is absent.
Among confers deodar is pre-dominant species followed by pine, spruces and firs. Forest
area of pangi valley valley consist of 8009 Ha RF, 4795 Ha PF, 97503 ha Unclassified forest
and the remaing under others as alpine scrubs, respectively.
The floristic accounts of the Indian cold deserts Lahaul & Spiti including Pangi Valley also
forms a part of Cold Desert of Himalayas, have been largely described under „Western
Himalayas by the early Phytogeographers (Hooker, 1906 and Chatterjee, 1939). Various
authors have described the vegetation of this region as Caragana-Lonicera-Artemisia
formation (Osmaston, 1922); Zone of Dry bushes (Nako, 1955); Alpine Steppe
(Schweinfurth, 1957); Dry alpine scrub (Champion and Seth, 1968) and Alpine stony deserts
(Puri et al., 1989). The vegetation in Cold Deserts, infact, varies from semi-desertic to
desertic, depending upon the prevailing bio-climate.
The Study area has no eco-sensitive area nearby to project vicinity any declared protected
or Reserved Forests under Forest Protection Act -1927, Wildlife Protection Act (1972) and
Biodiversity Conservation Act (2001) is present 10 km radius from project boundary. Mostly,
the unclassified forest including Alpine pasture has been reported on hill slopes above
3500m msl which is far away from project impacted zone located at deep in river bed of
about 2145 to 2220m, msl. No National park or’ Wildlife Sanctuary is reported within 10 km
from the proposed boundary as far as sensitivity is concern for special conditions of EIA
Notification 2006 & 2009.
Therefore, based on the primary survey as well as secondary data sources, the predominate
Forest Types include Broad Leaved and Coniferous Forest, Lower Western Himalayan
Temperate, Moist Alpine Scrubs and Dry Alpine Forests in the study area. However, the
major forest types assessed during field survey according to the classification of Champion
and Seth (1968) are:
leaved forest (36.08%) followed by Cedrus deodara (26.94%), Betula utilis (18.07%), Pinus
wallichiana (11.26%), Corylus jacquemontii (7.30%) and Pinus gerardiana (0.35%) forests.
These species were also found present during the study period conducted in vicinity of Sach
Khas project.
The depicted floral cover is broadly described with dominant groups, however is not able to
give complete account. Therefore, this data has been used as secondary data base where
predominant groups are almost in line with the satellite imager data along with other
supportive communities.
The description of sampling sites w.r.t. Project appurtenances is given in Table-8.1. The
sampling location map is enclosed as Figure-8.2.
Table-8.1: Description of Sampling Sites w.r.t. Project appurtenances
Sampling Location Distance from Dam Longitude Latitude
sites site E N
Submergence area-Catchment U/S Dam Site
Site1 (T1) Chenab river – Near Mujar chow 320 55’24” 076027’3
Catchment Area- confluence with 0”
Submergnece zone chenab (5.0-10.0 km)
Dam Site to Power House Area
Site 2 (T2) Dam site (Plate 1) Left & Diversion Structure 320 57’57” 076025’1
Right Banks 0.0km 5”
Site 3 (T3) Power House Site ~ 300m d/s Dam site
Figure -8.1 : Remote Sensing Map- Satellite Imagery of Pangi Valley with proposed
Sach Khas Project vicinity (H.P.)
U/S Veiw of Sach Khas HEP (Ref. By Mr. D/S Veiw of Sach Khas HEP (Ref. By Mr.
Shakher Damle) Shakher Damle)
L&T 260 MW Sach Khas HEP Dam Axis Left Bridge across Chenab River for Mindhal
Bank Drift village d/s
Catchment-Submergence, Project site and Influence zone on Chandrabhaga river,
Pangi Valley HP
8.4 METHODOLOGY
Floral Study
The present report on the plants of project area is based on field survey of the area. The
seasonal study has been conducted during pre-monsoon (summer), monsoon and winter
seasons. The whole area of the valley was divided into four altitudes i.e. from river bed 2200
to 3000 m, 3000-3500 m, 3500-4000 m, and 4000-4500 m for having an holistic view of
phyto-sociological aspects. The number of quadrats laid in the study area is given in Table-
8.2.
Table-8.2: Number of Quadrats laid in the Study Area
Sampling Trees Shrubs Herbs (1x1) m2
2
Location (10x10) m (5x5) m2 Winter Pre Monsoon
Monsoon
Site I 14 20 15 24 18
Site II 15 20 15 19 22
Site III 15 20 15 17 17
Site IV 12 20 15 21 15
Site V 20 20 15 21 18
To understand community structure, quadrat sampling mode was followed. The vegetation
sampling was done at seven locations. Sampling was carried out by randomly placing
quadrats of 10m x 10m size for trees, 5m x 5m size for shrubs and 1m x 1m for herbs. The
size and number of quadrats needed were determined using the species area curve (Misra,
1968).
Species diversity and evenness index is calculated by using the Shannon-Wiener Diversity
Index formula and Evenness Index formula, respectively.
Where, pi is the pr oportion of total number of species made up of the ith species.
A nested quadrates technique was used for sampling the vegetation. The size and number
of quadrates needed were determined using species area curve (Mishra, 1968) and the
runnings mean method (Kershaw, 1973). To study the phytosociological attributes quadrates
of 10 m × 10 m size for trees, 5 m x 5 m. size for shrubs and 1m x 1m size for herbs and
grasses were randomly laid out at each site at different elevations. Total 10 number of
quadrats were laid at study sites which are representation of from the left and right banks
river Chenab, where each 5 quadrats laid both banks to the uppermost possible slopes. The
terrain is tough nd steep up to the tree lines on Left bank from the Pir Panjal range whereas
right banks at higher elevation has comparately moderate slopes from the Zanskar range.
The enumeration of vegetation in each of the quadrat was done.
The vegetation data collected for phyto-sociological information was quantitatively analyzed
for density and frequency of each species according to the method developed by Curtis and
McIntosh (1950). The size and number of quadrats needed were determined using the
species area curve (Misra, 1968).
The tree species diversity for each stand in different forest types was determined using
Shannon Wiener information function (Shannon and Wiener, 1963) and Evenness Index
formula, respectively.
8.5 FINDINGS OF THE FIELD STUDIES
To understand the community in the proposed project area, the sampling was carried out at
five locations. The results indicate that Deodar (Cedrus deodara) is the dominant species
alongwith Kail (Pinus wallichiana), Fir and Spruce fringe at side slopes of high altitudes in
river course area in the project vicinity. The dominating deciduous trees are Corylus colurna,
Aesculus indica, Juglans regia, and Fraxinus sp. near the river banks. Higher slopes are
dominated by Birches and Mapples with fever patches of pinus gerdiana. These forests
perform protective function, by preventing snow slides and avalanches. The upper fringes
form by Juniperous and alpine scrubs. The undergrowth mainly comprises of Rumax sp,
Rosa sp, Berberis spp. Juniperus communis, J. recurva. The ground flora comprises of
mainly of Artemisia sp., and Polygonum sp.. The prominent feature in vast stretch of nutrition
grasses-alpine pasture during summers followed with patches of alpine scrub, principally
birch, Juniperus spp. The study area also has a variety of medicinal herbs and flowers, e.g.,
Dhup (Jurinea macrocephala), Patis (Aconitum heterophyllum), Karu (Picrorrhiza kurrooa),
Kala Jira (Bunium persicum) are commonly occurring and extracted for commercial
proposes. The details of density and frequency of various trees and shrubs for the sampling
sites is given in Tables-8.3 and 8.4. The details of density and herbs species in summer,
monsoon and winter seasons is given in Tables-8.5 and 8.6 respectively.
comprises of mainly of Artemisia sp. and Polygonum sp. etc. The study area shows the
absent of river bank riparian vegetation due to steep slopes. The cover starts about 3-4
meter above the left banks however at much higher side on the right banks. The river flows
through a confined and narrow valley. The dense patch of deodar has been noticed. Other
vegetation is varied along the side slope to tope hills following a general pattern of
distribution i.e. grassi-pasture land (>4000m), alpine meadows (>3500m), alpine scrubs
(3200-3500m), broad leaves forest-Birches and maples (3000-3200m) and downward
Conifers. The area is reperesned by rich diversity of herbal group. These groups are almost
absent along the river bank at dam site except the members of apeaceae, however, at side
slopes are quite frequent. The density and frequency of taxon observed are given through
Tables-8.3 to 8.6 respectively.
The power house side is located 300m downstream of dam site where the river takes a bend
while flowing through almost same river morphology. Therefore, the same type of vegetation
is present in the power house site. The dominant species along river bank slopes is deodar
followed by Pinus wallichiana, Picea smithiana and Juniperus recurva. The shrub layer
formed is mainly represented by Rosa sp, Berberis sp, A Artemeissia sp, Aesculus sp, and
Salix sp. The dominating deciduous trees are present near to river banks Corylus colurna,
Juglans regia and Fraxinus sp. followed by Aesculus sp and Salix spp of shrubs. Among
herbs apeaceae are dominant group followed by the poaceae and polygoneacae. Details of
floral accounts are given through Tables-8.3 to 8.6 respectively.
Ref.Enclosed: The low plant species richness at lower slopes could also be attributed to soil
erosion, for pastoralists uproot plants such as Krascheninnikovia ceratoides and Caragana
versicolor from these slopes (Rawat and Adhikari 2005b). Some other plants e.g. Caragana,
though it was not observed in the study area however it is reported in the pir panjal and
zanskar range- a leguminous plant is known to enhance soil fertility as its root-nodules have
nitrogen-fixing bacteria (Lu et al. 2009), and it also helps in retaining moisture in the soil
Rhizocarpon geographicum
Vegetation in the study area is dominated by temperate conifers like Juniperus sp., Pinus
sp., Cedrus sp. including broadleaved species of Betula sp., Populus sp. and shrubs like
Hippophae sp. and Rosa sp. Most of the vegetation present in the area are having limited
distribution due to climatic conditions prevailing in the area however locally they are present
in abundance. Numerous herbs species are having economic and medicinal importance and
are being used in ayrveda and yunani medicince by local vaids and even supplied out side
places. The trees are also having importance varies from timber, fodder, fuel wood to
medicinal values.
On the basis of ethanobotanical importance the floral groups are further described under
different heads as follows.
Medicinal Plants
The list of medicinal plants were recorded from the study area are given in Table-8.7.
Family & scientific Local URSV (Mode of IMP( Kirtikar and Basu, 1976),
name name preparation and DIFME (Jain 1991), ECDT (Sood
ailments cured) etal 2001) & Medicincal plants
of HP by N.K.Chohaun and
Bharmaur Area by Dutt etal 2011
FABACEAE Chhushin Whole plant is
Oxytropis spp Darm boiled in water
and the water is
applied
POLYGONACEAE Shomang Extract & Juice of To cure burns and other skin
Rumex spp fresh leaves problems
Polygonum spp Plant powder Also considered as cooling agent
used and taken orally with water to cure
jaundice* Stomach disorders
ROSACEAE T-siya, Flower and fruit Cures hepatitis, jaundice &
Rosa webbiana Seva juice useful stomach pain & juice as tonic to
vigour vitality
Apiaceae Kala zira Seeds are useful Stomach Disorder and add
Bunium persicum flavours to foods.
Apiaceae Gum resins In remedy of whooping cough,
Ferula asafoetida Hing pneumonia, bronchitis in children
F.jaeschkeana and asthma
Boraginaceae Rattan jot Rhizomes Anti HIV activity
Arnebia benthami
Ranunculaceae Pettish Grounded roots to relieve stomach pain.
Aconitum spp meetha-patish
Compositae Gugal dhoop Jhari dhoop As dhuni
Jurinea dolomiaea
Fabaecae Red flower Asthma
Trifolium pratense
Gentianaceae Kaud Leaves to relieve fever.
Gentiana kurroo
Scrophulariaceae Kaud Leaves Antipyretic. As insecticides in
Picrorhiza kurroa wheat fields
Violaceae Banakshan Flowers Cough & Cold treatment
Species of Viola
Asteraceae Kuth Roots, leaves, To relieve from Arthrites, dhuni for
Saussurea costus flowes bed evil spirits, Relief in pregnancy
etc.
Table-8. 11 : Fruit Plants grown in the area or naturally occurring in the area
Malus pumila Apple
Prunus armeniaca Apricot
P. avium Cherry
P. amygdalus Almonds
Juglans regia Walnut
Corylus colurna Hazelnut (wild)
Castanea vulgaris Chestnut (wild and cultivated)
Pinus gerardiana Chilgoza, Neoza (wild)
• For sampling butterflies the standard ‘Pollard Walk’ methodology was used by recording
all the species that were encountered while trekking along the foot trails between these
two sites, daily. Photographs of specimens of species were taken in the field for
identification purpose. Sampling was done for 1 hour in a stretch on each transect(n=4).
• For sampling birds ‘point sampling’ along the fixed transects (foot trails) was carried out
to record all the species of birds observed with the help of binoculars; field guides and
photography for 1 hour on each transect(n=4).
• For sampling mammals, ‘direct count on open width (20 m) transect’ was used on the
same transects (n=4) for 1 hour in each transect. Besides, information on recent
sightings / records of mammals by the villagers and locals was also collected form
these areas.
• ‘Reptiles’ mainly lizards were sampled by ‘direct count on open width transects’ (n = 4)
for 1 hour in each transect.
8.9.1 Mammals
The study area reported occurrence of a total of 19 species of wild mammal mosly
aclimatised of dry temperate climates as per the secondary information collected. These 19
species belong to 17 Genra, 11 families and 5 Order of mammals as confirmed from Pangi
Valley Area (ZSI 2011). Most of the animals are present in the Sechu Tuan Nalla Wildlife
Sanctuary which is located beyond 10km of the study area. This is a high altitude (2550 m -
6072m asl) wildlife sanctuary which is spread over an area of 10,295 ha. Therefore, the
presence in the Zanskar might be viewd from the presence of pasture land zone. These
species are widely distributed in the trans -himalayan zone.
The direct sighting of most of these species in the demarcated study area up to 10km radius
has not found and the presence is only supported from secondary data. The other factor of
not able to direct sighting may be the area is having habitation of few villages and rugged
terrain of Chenab deep cut valley. However, during present assessment in the study area
the possible presence of 18 species are also made out with the information supplied by the
locals and available literatures which belongs to 18 genera and 9 families. About 8 species
are carnivorous in nature and belong to the family Ursidae, Canidae, Mustelidae and
Felidae. These species are found in the forest area and towards snow covered hill peaks,
however, fewever times species of ursidae and canidae also cited near to agricutral field at
the fringes of forests in human habitation for searching the food as per the information
provided by the locals. Some of the common mammals found in the area are Himalayan
brown bear (Ursus arctos), Himalayan black bear (Selenarctos thibetanus), Fox (Vulpes
montana), Goral (Naemorhedus goral), Ibex (Capra sibirica) and Yellow throated marten
(Martes flavigula). Other mammals which are generally remain at higher altitude peaks and
alpine pature land are Musk Deer, Snow Leopards, Jungle Cat, Goral, Bharal--Blue Sheep,
Common Langur, Markhor, Himalayan Mouse-Hare, Serow, Himalayan Tahr, Marmot etc.
The list of mammal species reported in the Study Area and their conservation status is given
in Table-8.12.
As per survey conducted and information retrieved from the locals, presence of Tahr, Gharal
and deers on pasture and alpine meadow slopes below snow scree mountain peaks
(>4000m asl) on left bank Pir Panjal range and right bank Zanskar range, which are located
far away places from the deep river bed project side (2145m, asl) and will not anticipate any
impacts. The maximum submergence level will reaches up to 2220m, asl.
Table-8.12: The mammalian species reported from the Study Area with their status
S. Family / Scientific name IUCN 2013 WPA (1972) Remarks#
No. Species common name
A Mustelidae
1 Himalayan Yellow- Martes flavigula Least Concern Schedule II Indirect
throated Marten evidence*
2 Himalayan Weasel Mustela sibirica Schedule II Indirect
evidence*
B Canidae
3 Fox Vulpes monntana Data deficient Schedule II Direct sightings
C Cercopithecidae
4 Hanuman Langur Semnopithecus Least Concern Schedule II Direct sightings
entellus
D Bovidae
5 Himalayan Tahr Hemitragus Vulnerable Schedule I Direct sightings
jemlachicus
6 Ghoral Naemorhedus goral Near Schedule III Direct sightings
Threatened
* Information from the locals, Secondary data from literature & of forest & wildlife division
**
The information of other domesticated animals and livestocks present in the area are also
collected. These animals are mainly mammals and enlisted in the study area are as given in
Table-8.13.
Table-8.13: List of Domestic Fauna in the Study Area
S. No. Zoological Name Common Name
1 Bos grunniens Yak
2 Bos indicus Cow
3 Cains familieris Dog
4 Capra hircus Goat
5 Equus cabilus Horse
6 Equus hermionus Ass
7 Felis domesticus Cat
8 Ovius polic Sheep
8.9.2 Avi-Fauna
As many as 38 birds species belonging to 18 families were observed in the study area. The
list is enclosed as Table-8.14. Most of the species of birds are protected as their respective
families have been listed under Schedule IV of Indian Wildlife (Protection) Act 1972. On the
basis of their sighting the species are divided into common, rare and categories occasional.
The bird includes the monal and koklas, pheasants, Himalayan tragopan, snow pigeon and
the chukor. Little Forktail, Koklass Pheasant were among the uncommon or rarely sighted
species, whereas Himalayan Monal was reported from high altitude nearby area by the local
inhabitants.
Most of the bird species to be affected in this zone prefer aquatic fresh water habitat, but
these are of common occurrence and distributed all over the Chandrabhaga River e.g.
White-capped Red start, Plumbeous Water Redstart, Brown Dipper, Little Forktail, and
Citrine Wagtail. Similarly, among the species of butterflies and mammals none of the
species is totally dependant or restricted to the submergence area.
There is a paucity of published records on the birds of this Area. However, Singh et al.
(1990) has provided a preliminary list of 16 bird recored in the Sechu Sanctuary Zone
located about 12km distance from the project site. Among them the common species are as
Western Tragopan Tragopan melanocephalus (Globally Threatened), Snowcock
Tetraogallus himalayensis, Himalayan or Impeyan Monal Lophophorus impejanus and
Koklass Pheasant Pucrasia macrolopha are found here but data on general bird life is
WAPCOS Limited 8-23
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
lacking. The site is considered Data Deficient till we have more information on avifauna.
Later on studies in the Pangi valley was conducted by the ZSI (2011) and they have
reported presence of 75 species of Avi fauna. During present studies the species
encountered are illustrated in the Table8.14.
Table-8.14: List of avi-faunal recorded from the Study Area
Common Name Scientific Name Family Abundance
Himalayan Bulbul Pycnonotus leucogenys Pycnonotidae Common
Red vented Bulbul Pycnonotus cafer Pycnonotidae Common
House Sparrow Passer domesticus Passeridae Common
Rock Bunting Emberiza fucata Fringillidae Common
White-capped Bunting Emberiza stewarti Fringillidae
European Goldfinch Carduelis carduelis Fringillidae Common
*Alpine Accentor Prunella collaris Fringillidae Uncommon-
Common Hoopoe Upupa epops Upupidae Occasional
Yellow browed Tit Silvyparus modestus Paridae Common
Rufous-vented Tit Parus rubidiventris Paridae Common
Simla Crested tit Parus rufonuchalis Paridae Occasional
Green-backed Tit Parus monticolus Paridae Ocassional
Ashy Drongo Dicrurus leucophaeus Dicrurinae Common
Western Crowned Warbler Phylloscopus occipitalis Phylloscopidae Common
White-throated Fantail Rhipidera albicollis Rhipiduridae Common
Grey Bushchat Saxicola ferrea Muscicapidae Common
Plumbeous Water Redstart Rhyacornis fuliginosus Muscicapidae Common
White capped Water Redstart Chaimarrornis leucocephalus Muscicapidae Common
Little Forktail Enicurrus scouleri Muscicapidae Uncommon
Brown Dipper Cinclus pallasii Cinclidae Fairly common
Blue Whistling Thrush Myophonus caeruleus Turdidae Common
Streaked laughing Thrush Garrulax lineatus Timaliidae Common
Variegated Laughing thrush Garrulax variegatus Timaliidae Common
Oriental White eye Zosterops palpebrosus Zosteropidae Uncommon
Oriental Turtle Dove Streptopelia orientalis Columbidae Common
Spotted Dove Streptopelia chinensis Columbidae Common
Snow Pigeon Columba leuconota Columbidae Fairly common
Rock pigeon Columba livia Columbidae Ocassional
Himalayan Griffon Gyps himalayensis Accipitridae Common
Yellow-billed Chough Pyrrhocorax graculus Corvidae Common
Red billed Chough Pyrrhocorax pyrrhocorax Corvidae Common
*Himalayan snow cock Tetraogallus himalayensis Phasianidae Fairly common
Chukar Alectoris gracea /chukar Phasianidae Fairly common
Himalayan Monal Lophophorus impejanus Phasianidae Fairly Common
*Koklass Pheasant Pucrasia macrolopha Phasianidae Uncommom
Citrine Wagtail Motacilla citreola Motacillidae Common
Total 7 species of reptiles has been recorded from the area. However, only two species of
herpetofauna i.e. Ladakhi Rock Skink (Asymblepharus ladacensis) and Kashmir Rock
Agama (Laudakia tuberculata) were sighted during the survey. Besides that no any
herpetofauna species was encountered however, description is given based on secondary
information. The information was also collected from secondary source to find out
occurrence of reptiles of Kashmir Himalayas from the locals & from the literature
(Biodiversity of the Kashmir Himalayas by GH. Dar et al. 2002) and from recent studies of
ZSI (2011)on flora and fauna of Pangi Vaalley, which show the presence of 7 reptile species
in the area. However, during priamary survey, no such species was encountered except the
rock agama and skinks. Similarly, presence of pit vipor is also supported from the research
evidence, which shows presence of Himalayan Pit Viper upto Ladakh Himalayas 4800m, asl.
The occurrence of common species of reptiles are enlisted in Table-8.15.
8.9.4 Insects
Among Insects, species of Butterfly and Moths were study. Seondary information with
respect to the occurrence in the study area has also been collected though the area has
paucity of data. Some data from the Pangi Valley is available. The project site is located
within the Pangi valley. Therefore, the secondary information was used for supporting of the
primary data.
8.9.5 Butterflies
During the survey, a total of 16 species of insects were sighted in the study period. Some of
the butterflies like Small copper (Lycaena phlaeas), Satyr (Aulocera sps.), Indian tortoise
shell (Aglais cachmirensis), Indian cabbage white (Pieris canidia indica) and Clouded yellow
(Colias sp.) were common and found throughout the study area. On the basis of their
sighting the species are divided into common, uncommon and occasional categories. The
list of butterflies recorded from the study area is given at Table-8.16. The alpine zone
Himalayas are typical habitat for Appollo butterflies. The ZSI has reported 16 oriental
species and 17 palearctic species of butterflyies from the Pangi Valley. These species are
reported in the moist alpine meadows and pasture land areas however presence of some
the species in the mixed forest area has also been reported. However, during present
investigation total 16 species are observed where presence of Palearctic species (S.No.11-
16) and remaining Oriental species are viewed from the ZSI report and remaining are
sighted in the field.
The occurrence of butterflies has shown interaction with some of the flowering plant species.
Mostly are occurring in the moist alpine meadows area located much higher elevation
(>3500m) beyond the submergence and influenced zone of the proposed project. Some of
the species are also found in the deadar site. The list of community intraction with plant
species has been shown in Table-8.17 (Ref. ZSI 2011).
Table-8.17: Nectar food plants of Butterflies from Pangi Valley (ZSI, 2011)
Plants Plant Family Butterfly species
Saussurea costus (Falc.) Lipschitz Asteraecae Aulocera swaha
Oxytropis spp. Fabaecae Albulina galathea
Anthemis cotula Linnaeus Asteracae Colias fieldii
Medicago falcata Linnaeus Fabaecae Colias fieldii
Scabiosa speciosa Dipsaeaecae Pieris brassicae
Trofolium repens Linnaeus Fabaecae Polyommatus eros,
P.astrarche
Nepeta spicata Benth. Limiaecae Pieris brassicae
Pedicularis pectinata Scrophulariaecae Albulina galathea
Bupleurum falcatum Apiaecae Albulina galathea
Cynoglossum sp. Boraginaecae Polyommatus icarus
Nepeta spicata benth. Lamiaecae Aulocera swaha
Anthemis cotula Linnaeus Asteracae Colias fieldii
Dianthus orientalis Caryophyllaecae A. galathea, P. icarus
Oxytropis sp. Fabaecae Polyommatus icarus
Trifolium pretense (Linnaeus) Fabaecae Colias fieldii
Chaerophyllum reflexum Lindl. Apiaceae Chaetoprocta odata
Taraxacum sp. Asteraceae Colias fieldii
Thymus linearis Benth. Lamiaceae Lycaena phaleas
Sisymbrium orientale Brrassicaceae Pieris brassicae
Cirsium wallichii Compositae Vanessa cardui
Polyommatus icarus
Figure -8.3: River Chandrabhaga Project Influenced Area --through Pangi valley
8.10.2 Methodology
The river /stream morphology is determined to ascertain the type of habitats, substratum and
covers (aquatic vegetation, substratum, large woody debris, Particulate as clay, silt, sand,
gravel, pebble, cobble, boulder, bedrock etc.), bank conditions, flow pattern, and type of
valleys following flood prone area and riparian covers etc has been assessed based on the
criteria described by Rosgen (1996) and habitat inventory described by Armontrout (1998),
Myers and Swanson (1992) and Rosgen (1996). Stream order classification was based on
Horton’s (1954) approach as modified by Strahler (1954, 1957). In this system all ultimate
headwaters are called first order streams. Stream formed by union of two such streams are
designated second order and whenever two streams of a particular order join they form next
order and so on. Habitat structures were observed in the river stretches from down stream
to upstream at a fixed point including longitudinal survey of submergence, dam site and
influence zones of toe dam projects with onsite visual estimation.
Plankton samples were collected using a tericot ring net of a 20 µm net to make. For
enumeration of phytoplankton population, 100 l composite water samples were collected
from the river surface up to 60 cm depth and were filtered through a 20 µm net to make 1 l of
WAPCOS Limited 8-30
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
bulk sample. The bulk samples so collected were preserved in 2% formalin solution and
were brought to the laboratory for analysis. Ten replicate water samples each of 15 ml were
made out of the preserved 1 l bulk sample and were centrifuged at 1500 rpm for 10 minutes.
After centrifuging, the volume of aliquot concentrate was measured. 0.1 ml of aliquot
concentrate was used for enumeration of phytoplankton population in each replicate. A
plankton chamber of 0.1 ml capacity was used for counting of plankton under a light
microscope. Periphyton-Epilithic phytobenthos were obtained by scrapping the surface of
rocks and boulders (4 x 4 cm2) with the help of a hard brush and preserved in 3% formalin
solution for further analyses.
For the quantification of zooplankton and phytoplankton 100 liters of water for each
community was filtered at each site by using plankton net made up of fine silk cloth (mesh
size 25 µm). The filtrate collected for the study of phytoplankton was preserved in Lugol’s
solution, while a part of the unpreserved samples for the study of zooplankton was brought
to the laboratory.
Benthic macro-invertebrates were collected from the pebbles, cobbles and gravels form the
surface collected up to 15 cm sediment depth at different elevations with the help of sieve of
a mesh size of 100 µm.
All collected specimens–organisms of planktons, periphytons, benthoses etc were preserved
in 3 % formalin solution or 70 % alcohol and were identified by using keys formulated by
different workers such as Pennak (1953), Edmondson (1959), Ward and Whipple (1959),
Needham and Needham (1962), Trivedy and Goel (1984), Sarod and Kamat (1984), Hustedt
and Jensen (1985), Battish (1992), Edington and Holdren (1995) and APHA (1992, 1998).
The density of the plankton and benthic samples was estimated by using drop count method
(Bhatt et al., 2005) and standards methods of APHA (1992, 1998).
Fishes occurrence were determined by visual method and by collecting samples using
different fishing gears like cast net, scoop net, hand net, hook-line, pot and open local
devices methods. Fishes were identified up to the species level with the help of keys of
Jayaram (1981), Menon (1987) and Talwar and Jhingran (1997). IUCN Red Data List (2008)
was compared to assess threatened, endangered and vulnerable species in the study area.
Conservation Assessment Management Plan of Biodiversity Conservation Prioritization
Project Workshop (CAMP-BCPP, 1997) was followed to understand the threats and
conservation status of Indian fish species.
The total number of planktons present in a litre of water sample was calculated using the
following formula:
N = (n x v x 100)/ V
Where, N= Number of plankton per litre
n = average number of plankton cells in 0.1 ml of aliquot concentrate
WAPCOS Limited 8-31
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
The species diversity index was calculated using Shannon’s species diversity index (H)
formula taking the density values of each species into consideration.
Shannon index of general diversity (H): - ΣPi log Pi
Where ni = density value for each species
N = total density value
Pi = density probability for each species = ni /N
8.10.3 River Morphology & Habitat Structure
The Chenab river is mainly snow fed. The main drainage channel of the basin is Chenab
river, which is named after the confluence of two streams namely Chandra and Bhaga river
near Tandi (2,573 meters) in the districts of Lahaul & Spiti (H.P.). Chandra river rises in the
snows lying lake of Chandra Tal, located in the southeast slope of the Baralacha La pass
and turns abruptly west after traveling 48-km to flow another 64-km to meet with the Bhaga
River at Tandi in the Lahaul and Spiti district. The Bhaga River rises in a small tarn called
Suraj Tal. The river pursues a southwesterly course for about 64-km and joins Chandra at
Tandi The united stream, called the Chandrabhaga, flowing northwesterly for 46 kms is
joined on its right bank by the Miyar Nala near Udaipur. The latter negotiates a total river
course of 80 km with an average fall of about 24 m/km. The Chandrabhaga, after flowing in
general northwest direction almost parallel to the Pir Panjal range, crosses at El. 1838 masl
the Pangi valley of Himachal Pradesh to enter Padder block of district Kishtwar of J&K.
After sweeping the Lahul and Spiti valley it enters in the Pangi Valley of Chamba district at
Karunalla confluence point (~2400m, asl) downward of Udaipur and leaves the Pangi valley
after confluence of Sansari Nallah to Kishatwar area of J& K (Figure below). Here, the river
is sandwiched between two sub-systems of the Himalayas the Zaskar and the Pir Panjal. It
flows in from Lahaul and passing through the length, it divides Pangi into two unequal parts
while the cliffs sometimes rise vertically to a height of a couple of thousand feet. The
mountains are surroundings the valley range between 5,400 and 6,700 meters. The tiny
villages of this verdant pocket lie between 2,100 and 3,000 meters. On the right bank of the
river Chanderbhaga, the growing settlement of Kilar (2,590 mtrs), is the administrative
headquarter. Thus hill peaks are ranging from river bed 2100m to 6707m. There are many
passes located on the Pir Panjal range which takes to Pangi valley like Cheni Pass, Drati,
Chobia, Kugdi and Sach Pass (4268m to 5300m). At project site, Mindhal village is on the
left bank whereas Sach khas is on the rightbank of river Chenab. At this point, valley spread
out (comparatively open type though V-shaped) and river flows in NW direction to reach
Killar and Dharawas as shown in Figure below. The several streams born on Zanskar range
and feed the Chenab on right banks. These are mainly Karu nallah, Saichu, Parmar, Kiryani,
WAPCOS Limited 8-32
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
Mahlu, Lujai, and the Sansari nallah (the last one in HP) near killer are noticeable. On the
left bank , the Cheni nallah near Mindhal, and Sach Khas nallah near Killar are noticeable.
At project site, hills are showing cover of overhanging snow clad peaks overawe. Vegetation
becomes sparse or even devoid of vegetation except few patches of deodar trees. The river
flows here through deep gorges cutting through the stable and rocky hills of high mountains
in the project site. Thus flows through narrow valley. The river flows through a narrow gorge
exposing bedrock on both the abutments where the diversion site is planned immediately
near to the sharp bend in river. Also immediately downstream of the proposed location the
river width broadens and again constricts to a narrow width at a location where the tailrace
tunnel outlet is planned.
The tract lies in a semi arid zone of inner Himalayas. The climate varies from dry temperate
to alpinetypes. The area remains snow covered for almost six month period where
temperature ranges between –20 oC to +27 oC. The rock system is very fragileand liable to
erosion which is often accentuated by the rigrous of severe winters, avalanches and the
strong winds that accompany them. The valley is surrounded by high mountain peaks and
deep river bed i.e. stable and confined valley (‘U to V’ shapes Plate-8.1). The aspects of the
hills in the area are steep to highly steep. The Pir Panjal range on left bank has much higher
steep slope than the right bank side Zanskar range. The vegetation is sparse and river bank
is devoid of riparian cover. The substratum is rocky which constitute large rocks, boulders
with lesser amount of cobbles, pebbles and absence of sand at banks. River has torrent
flow with bubble formation where rapids and cascade habitat is occur quite frequently. Some
place scour pools, side and pocket pools also formed by the presence of rocks and
boulders. Thus, the river has high gradient at dam site (4-10%) and fluvial morphology. At
dam site and power house sites, rapids habitat dominant whereas no frequent run, pool and
scour pools habitat observed in the river course. The streams are first order category and
consits fall and cascade habitats with torrent flow. The glacial melt water is flowing in the
Chenab and its streams where velocity is found >4m/sec (torrent flow) due to steep slope.
All the streams falling in the influenced area and river Chenab are claasified A-type as per
Rosgen’s (1996) criterion developed for river morphology. The detail geomorphology of the
river Chenab and its streams falling in the project submergence zone and influenced zone is
depicted in Table-8.20.
Table-8.20: River Morphology and Habitat Structures of Chenab & its streams in the
Project Impact Zone
Sites River/Stream Gradient (% Substratum with Habitats
Slope) & Stream stream/river
type morphology
U/S dam Site-Submergence Zone
I Chenab-Snow < 4% and Rocks, Boulders, Rapids. Confined
Fed Category A Banks stable and rocky morphology with
hills, No riparian cover stable rocky hills
(V-U shape)
Dam site to Power House Zone
II River < 4%, and Rocks, Boulders, Rapids. Confined
Chandrabhaga Category A Banks stable and rocky morphology with
(Chenab)- hills, No riparian cover, stable rocky hills.
Snow Fed Valley Narrow and
confined (V-U shape)
Influnced Zone D/s dam site
III River Chenab 2-4% river Rocks, Boulders, Rapids in Chenab
& side streams Chenab and Banks stable and rocky whereas cascade,
-Snow Fed streams above hills, No riparian cover, fall and lesser
10% slope- Valley Narrow and pools in steams.
Category A confined (V-shape) Confined
morphology.
water of oligotropic nature. Thus, the variation in occurrence of phytoplankton taxa is the
reflection of prevailing the water quality, channel morphology, elevation, geomorphology that
occur in the project site in river Chandrabhaga and its tributaries.
Table-8.21: Phytoplankton Species Observed in the project impact zone
Phytoplankton Taxon Influenced
(cells/l or sq cm) Submergence Dam Site to Zone (D/s
Zone (u/s dam Power house Power house
site) Area area)
PM M W PM M W PM M W
Blue Green Algae
Cyanophyceae
Oscillatoria tinues 8 10 12 8 6 14 12
O. limnosa 4 6 8 9 6 8 11 8
Phormidium autumnale 4 4 6 2 8 12 8
Schizothrix fasciculata 8 4 4 8 6
Green Algae-Cholorphyceae
Zygnema himalayense 8 12 26 6 8 12 14 8 18
Spirogyra porticalis 6 12 6 8 18 4 14
Ulothrix zonata 6 8 4 10 4 14
Cladophora glomerata 4 10 9 12 8 8 18
Scenedesmus ellipticus 8 10 14 6 12 16 10 24
Chlorella vulgaris 4 6 14 8 6 8 10
Chlamydomonas moewusii 4 6 16 6 12 10 16
Closterium leibleinii 2 12 12 12 10 14 16
Microspora amoena 3 5 9 4 6 10 8 12 12
Diatoms-Bacillariophyceae
Tabellaria fenestrate 22 26 32 12 18 30 16 22 46
Cocconeis placentula 18 20 16 26 16 26 26
Diatoma hiemale 8 12 12 6 12 24 32 24 42
Flagellaria .pinnata 12 12 18 8 16 20 32 40 40
F. inflata 10 12 12 12 16 30 40
Synedra ulna 10 16 8 12 12 16 20 34
Synedra mediocontracta 6 8 10 6 12 18 20 26 38
Achnanthes linearis 8 6 8 14 24
Achnanthes minutissima 10 12 14 8 12 20 18 26 24
Stauroneis phoenicenteron 8 12 20 14 16 26 20 36
Nitzschia linearis 12 16 14 10 16 16 20 20
Navicula radiosa 22 36 18 12 14 20 22 18
Cymbella affinis 14 32 16 10 18 28 12 16 22
Hannaea arcus 12 8 8 14 14 12 16 24
Gomphoneis herculeana 10 8 18 28 12 18 20
G.geminatum 10 10 8 10 20 16 14 20 28
Amphora ovalis/bitumida 16 8 6 8 16 10 14 24
Meridion circulare 10 16 6 10 24 8 16 32
PM= Pre Monsoon, M= Monsoon, W= Winter
Source: Field Studies
The river waters shows low occurrence /density and diversity that represented by
phytoplankton (56– 432 cells/l), phytobenthos (54 – 406 cells/cm2) and zooplanktons (14-
284 cells/L). Cholorophyceae accounted for the majority of the biotic communities followed
by Bacillariophyceae and Cyanophycae.
8.10.5 Macroflora/ Macrophytes
No growth of macrophytes seen in the area that may be due to rapid currents and fall habitat
which has river wash affects. However, macrophytes that remain attached to the rocks,
boulders; stones, etc. belong to various genera of bryophytes (mosses). These mosses grow
on stone and boulders that protrude a few centimeters above the surface of water
sometimes growth reaches in the flowing water edges stones.
8.10.6 Zooplanktons
Zooplanktons are represented by protozoa, rotifer and crustaceans (Refer Table-8.22).
Among protozoans Arcella, Peridinium, and Ceratium taxon are commonly observed.
Rotifers are represented by Keratella, Brachionus and Philodina taxon. Copepod consists of
Cyclopes species whereas cladocerans are represented by Daphnia and Bosmina sp. The
occurrence are mainly from the edge pools of side stream and river banks, however, the
group in totality is poorly represented due to climate conditions followed by long winters and
torrential flow. The low occurrence is also linked to rapid habitat and rocky substratum in the
deep gorge narrow valley.
Table-8.22: Zooplankton observed in the Project Impact Zone (~10km radius)
Zooplanktons (Cells/L) Submergence Dam Site-Project Influenced Zone
Zone (u/s dam Site (Power house
site) site)
PM M W PM M W PM M W
Protozoan
Peridinium cinctum 4 8 3 6 4 12 14
Arcella crenulata 4 8 10 6 8 6 14 20
Ceratium furca 3 4 4 6 10 14
Rotifers
Keratella quadrata 8 6 6 14 28
Asplanchna priodonta 10 8 8 12 26
Philodena roseola 6 10 6 4 8 12 8 18 12
Brachionus bidenta 12 6 6 12 24
Polyarthra vulgaris 4 18 10 6 10 14 10 16 14
Trichocerca longiseta 6 12 8 4 7 12 8 15 10
Cladoceran
Bosmina longirostris 12 20 6 12 14 20 34
Daphnia pulax 16 12 8 14 16 22 40
Copepods
Cyclops scutifer 4 6 8 4 8 8 14 26
Cyclops glacialis 2 4 8 6 8 16 22
PM= Pre Monsoon, M= Monsoon, W= Winter
Source: Field Studies
on the primary survey collected during field survey carried out in the river Chenab and its
tributaries between 2125 to 2250 m.
Fish species adapted to cold water conditions approx 100C or subzero water temperature
are found in the region. Among 3 species of fish, 1 has been classified under the vulnerable
category on the basis of CAMP criterion. Schizothorax richardsonii. Rainbow, brown and
golden trout are exotic species and introduced by the State Fishery Department. The area
has been found devoid of crucial spawning requiste riffle habitat in the dam site and
upstream zone except d/s areas near to side stream confluence. The d/s area will remain
unaltered and will coninuosly receive environmental flow and tail water flow for lower stream
habitat requirement. Table-8.25 depicts the composition and conservation status of fishes
based on available literature and primary survey. Cultural fishery is absent and there are no
fish farms and hatcheries for the fishery development in this region.
Table-8.25: Fish species composition of Chenab River and their conservation status
S. Zoological name Common name Family IUCN Status
No
1 Schizothorax richardsonii Snow tourt Cyprinidae Vulnerable
2 S. gairdnerii gairdnerii Rainbow trout Salmonidae Least Concerned
3 Salmo trutta fario Brown trout Salmonidae Least Concerned
Source: Field Studies
Out of the reported 3 fish species, Schizothorax richardsonii of Cyprinidae family is the only
species which falls in vulnerable category, though none of the species are found present in
the project area. The remaining species are declared as common or exotic in introduction.
Though, the endemic trout species is widely distributed throughout Indian Himalayan region.
Endemic trout is considered migratory in nature within the river stretch which mostly
localized in nature.
CHAPTER-9
PREDICTION OF IMPACTS
9.1 GENERAL
Based on the project details and the baseline environmental status, potential impacts as a
result of the construction and operation of the proposed Sach Khas hydroelectric project
have been identified. This Chapter addresses the basic concepts and methodological
approach for conducting a scientifically based analysis of the potential impacts likely to
accrue as a result of the proposed project. The Environmental Impact Assessment (EIA) for
quite a few disciplines is subjective in nature and cannot be quantified. Wherever possible,
the impacts have been quantified and otherwise, qualitative assessment has been
undertaken. This Chapter deals with the anticipated positive as well as negative impacts due
to construction and operation of the proposed project. The construction and operation phase
comprises of various activities each of which is likely to have an impact on environment.
Thus, it is important to understand and analyze each activity so as to assess its impact on
environment. The key activities have been categorized for construction and operation
phases.
• Site preparation
• Earthwork and excavation including controlled blasting and drilling
• Construction of a concrete dam of 77 m height
• Intake, Pressure shaft, Power house for underground power house for main power
house
• Intake, Pressure Shaft, Surface Power house for secondary power house
• Underground manpower house to generate (3x86.7) 260 MW of power
• Surface secondary power house to generate (2x7) 14 MW.
• Tail Race Tunnel of length 99.75 m, 113.13 n and 132.35 m
• Construction of new roads and upgradation of existing roads
• Construction of a bridge on river downstream of tail race tunnel
• Project headquarter, offices and colonies
• Disposal of muck and construction wastes
• Transportation of construction material
• Operation and maintenance of construction equipment
• Civil and mechanical fabrication works for construction of various project
components.
• Operation of DG sets
• Disposal of pollutants from workshops, etc.
• Disposal of effluents and solid waste from labour camps and colonies
The various project activities and associated potential environmental impacts on various
environmental parameters have been identified and summarized in a matrix and the same is
outlined in Table-9.1.
TABLE-9.1
Matrix for various project activities and associated potential Environmental Impact on various Environmental Parameters
S. Project Activities Soil & Geolo Hydrolo Water Air Noise Flora/ Employment Socio-
No. Land gy gy quality quality Fauna culture
A. Construction Phase
1. Sire preparation including tree cutting √ √ √ √
2. Earthwork and excavation including √ √ √ √ √ √ √
blasting and drilling
3. Construction of concrete dam over √ √ √ √ √
river Chenab
4. Construction of primary and √ √ √
secondary surge shafts
5. Construction of primary and √ √ √
secondary intakes
6. Widening of approach roads √ √ √ √ √
7. Disposal of muck and construction √ √ √ √
wastes
8. Transportation of construction √ √ √ √
materials
9. Operation and maintenance of √ √ √ √
construction equipment
10. Disposal of sewage and solid waste √ √
from labor camps
11. Acquisition of forest land √ √ √
12. Acquisition of labor population √ √ √ √ √ √ √
B. Operation Phase Activities
1. Diversion of water for hydropower √ √ √
generation
2. Equipment maintenance √ √ √ √
3. Disposal of sewage and solid waste √ √
from project colony
4. Mushrooming of allied activities √ √ √ √ √ √
The impacts which have been covered in the present Chapter are categorized as below:
- Impacts on Water Environment
- Impacts on Air Environment
- Impacts on Noise Environment
- Impacts on Land Environment
- Impacts on Biological Environment
- Impacts on Socio-Economic Environment
- Water quality
- Sediments
- Water resources and downstream users
Based on these assumptions the peak migrant population has been calculated as 6200
persons (Table-9.2). This population is expected to reside in the project area at any given
time.
Table- 9.2: increase in population due to migration of labour and technical staff during
construction phase
A. Migrant Population of Laborers
Total labor force 1000
Married laborers (80% of 1000) 800
Single laborers (20% of 1000) 200
Husband and wife both working Labour (80% of 800) 640
Number of families where both husband and wife work (640/2) 320
Number of families where only husband work (20% of 1000) 200
Total number of laborers families (320+200) 529
Total Migrant Population of Laborers (520 x 5 + 200) 2800
B. Migrant Population of Technical Staff
Total technical staff 400
Married technical staff 200
Single technical staff 200
Total migrant population of technical staff (100 x 5 + 100) 600
Migrant Workforce (Labor plus Technical) 3400
C. Service Providers
Total service providers (2% of total migrant workforce) 68
Married service providers (50 % as assumed) 34
Single service providers 34
Total migrant population of service providers (34 x 5 + 34) 204
3604,
Total Migrant Population say 3600
Immigration of such a large population for a long duration in remote area can cause serious
impact on various environmental resources including socio-economic profile of local
population. The congregation of large number of construction workers during the peak
construction phase is likely to create problems of sewage disposal, solid waste
management, tree cutting to meet fuel requirement, etc. Appropriate mitigating measures
have been suggested in EMP, which needs to be implemented to minimize such impacts.
The domestic water requirement has been estimated as 70 lpcd. Thus, total water
requirements work out to 0.25 mld. It is assumed that about 80% of the water supplied will
be generated as sewage. Thus, total quantum of sewage generated is expected to be of the
order of 0.20 mld. The BOD load contributed by domestic sources will be about 162 kg/day.
It is assumed that the sewage is discharged without any treatment for which, the minimum
flow required for dilution of sewage is about 2.4 cumec.
Detailed DO modelling was done using Streeter Phelp’s model. The D.O. level was
estimated using the following equation:
The D.O. level in the river Chenab was taken as 8.0 mg/l. The minimum flow in the river
Chenab was taken as 8.7 cumec (minimum flow estimated for 90% dependable year in the
month of February). The results of D.O. model are summarized in Table-9.3.
Table-9.3: Results of D.O. Modeling due to disposal of sewage from labour camps in
River Chenab
Distance from outfall (km) D.O. (mg/l)
0.1 8.0
0.2 8.0
0.3 8.0
0.4 8.1
0.5 8.1
1.0 8.2
It can be observed from Table-9.3, that no impact is anticipated on river water quality, as a
result of disposal of sewage from labour camps. Even though no impact is envisaged on
water quality of river Chenab, as a result of disposal of untreated sewage, it is recommended
to provide adequate treatment for the sewage generated from labour camps.
observed to be <0.1 mg/l. The composite value of suspended solids would increase by 0.07
mg/l, which is insignificant. Thus, no adverse impacts are anticipated due to small quantity of
effluent and large volume of water available in river Chenab for dilution. Even then, it is
proposed to treat the effluent from crushers in settling tank before disposal so as to
ameliorate even the marginal impacts likely to accrue on this account.
The major sources of water pollution during project operation phase include:
About 37.5 m3/day of sewage will be generated. The total BOD loading will be order of 11
kg/day. It is proposed to provide septic tank to treat the sewage generated from project
colony. The BOD loading will reduce to 3 to 4 kg/day. The sewage treatment for septic tank
will be discharged into nearby water body. The quantum of sewage so generated will be so
small that no major adverse impact is anticipated as a result of disposal of effluents from the
project colony.
9.2.2 Sediments
When a river flows along a steep gradient, it could carry a significant amount of sediment
load, depending on the degradation status of the catchment. When a hydraulic structure is
built across the river, it creates a reservoir, which tends to accumulate the sediment, as the
suspended load settles down due to decrease in flow velocity. The proposed project is
envisaged as a runoff the river scheme, with a barrage at regular intervals, the gates of the
barrage shall be opened to flush out the sediments. Thus, in the proposed project,
sedimentation problems are not anticipated.
It can be seen from Table-9.5 that number of hours for which peaking power will be
available, in 90% dependable year shall range from 12.5 to 24 hours in monsoon season
from June to September. In the period from October to November and April to May, peaking
will be available for a period of 4.6 to 8.1 hours and 4.3 to 12.1 hours respectively.
In lean season, from December to March peaking will be available for a period of 0.5 to 1.7
hours in 90% dependable year. It can be observed that in lean season, river water will be
stored for a period of 22 to 23.5 hours. As a result, downstream stretch of river from the dam
site will be remain dry for a period of 22 to 23.5 hours, which will be followed by a continuous
flow equal to rated discharge of 428.1 cumec for a period of 0.5 to 2 hours.
The modification of downstream river flow characteristics (regime) by an impoundment shall
have adverse effects upon fish species. These include impact on migration, spawning
grounds, survival of eggs & juveniles, food production etc.
Regulation of stream flow during the migratory period can alter the seasonal and daily
dynamics of migration. Regulation of a river can lead to decrease in a migratory population.
In Sach Khas hydroelectric project, the discharge for 90% dependable year is higher than
WAPCOS Limited 9-10
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
the rated discharge (428.1 cumec) for a period about 70 days from 11th June to 31st August.
The project envisages generation of 260 MW of hydropower using 3 turbines of 86.57 MW
capacity each. Thus, in monsoon months, all of the three turbines can be operated and pre-
project level of discharge will be maintained in river Chenab downstream of Sach Khas
hydro-electric project.
In lean season, i.e. from December to March, the discharge is less and even one turbine
cannot run at 10% capacity. If peaking power is to be generated then the reservoir needs to
be filled up to FRL. This can result in drying of river stretch downstream of dam site of Sach
Khas hydroelectric project for a stretch of 6.0 km, i.e. upto tail end of reservoir of Dugar
hydroelectric project. The drying of river stretch to fill the reservoir upto FRL for peaking
power will last even upto 23.5 hours, after which there will continuous flow equivalent to
rated discharge of 428.1 cumec for 0.5 to 2 hours. Even, if peaking power is not attained and
turbines operate at lower capacity (based on optimization of power generation with respect
to cost) can result in drying up of river stretch followed by continuous flow of rated discharge.
The rated discharge could be 9 to 10 times the lean season flow in a 90% dependable year.
house sites. During crushing operations, fugitive emissions comprising mainly the suspended
particulate will be generated. Since, there are no major settlements close to the dam and power
house; hence, no major adverse impacts on this account are anticipated. However, during the
layout design, care should be taken to ensure that the labour camps, colonies, etc. are located
on the leeward side and outside the impact zone (say about 2 km on the wind direction) of the
crushers.
Blasting Operations
Blasting will result in vibration, which shall propagate through the rocks to various degrees
and may cause loosening of rocks/boulders. The overall impact due to blasting operations
will be restricted well below the surface and no major impacts are envisaged at the ground
level. During various blasting operations, dust will be generated, ID blowers will be provided
with dust handling system to capture and generated dust. The dust will settle on vegetation,
in the predominant down wind direction. Appropriate control measures have been
recommended to minimize the adverse impacts on this account.
The increase in vehicular density is not expected to significant. In addition, these ground
level emissions do not travel for long distances. Thus, no major adverse impacts are
anticipated on this account.
Under the worst-case scenario, considered for prediction of noise levels during construction
phase, it has been assumed that all these equipment’s generate noise from a common point.
The increase in noise levels due to operation of various construction equipment’s is given in
Table-9.8.
Table-9.8: Increase in noise levels due to operation of various construction equipment’s
Distance Ambient noise Increase in noise Increased Increase in
(m) levels dB(A) level due to noise level due ambient noise
construction to level due to
activities dB(A) construction construction
activities activities
dB(A) dB(A)
100 36 45 45 34
200 36 39 39 29
500 36 31 31 25
1000 36 25 25 25
1500 36 21 21 24
2000 36 19 19 24
2500 36 17 17 24
3000 36 15 15 24
It would be worthwhile to mention here that in absence of the data on actual location of various
construction equipment’s, all the equipment have been assumed to operate at a common point.
This assumption leads to over-estimation of the increase in noise levels. Also, it is a known fact
that there is a reduction in noise level as the sound wave passes through a barrier. The
transmission loss values for common construction materials are given in Table-9.9.
Thus, the walls of various houses will attenuate at least 30 dB(A) of noise. In addition there are
attenuation due to the following factors.
• Air absorption
• Rain
• Atmospheric in homogeneities.
• Vegetal cover
Thus, no increase in noise levels is anticipated as a result of various activities, during the
project construction phase. The noise generated due to blasting is not likely to have any effect
on habitations. However, blasting can have adverse impact on wildlife. It would be worthwhile to
mention that no major wildlife is observed in and around the project site. Hence, no significant
impact is expected on this account.
During construction phase, there will be significant increase in vehicular movement for
transportation of construction material. At present, there is no vehicular movement near the
dam site. During construction phase, the increase in vehicular movement is expected to
increase up to a maximum of 5 to 6 trucks/hour.
As a part of EIA study, impact on noise level due to increased vehicular movement was
studied using Federal Highway Administration model. The results of modeling are outlined in
Table-9.10.
Table-9.10: Increase in noise levels due to increased vehicular movement
Distance (m) Ambient noise Increase in Noise levels Increase in
level dB(A) noise level due due to ambient noise
to increased increased level due to
vehicular vehicular increased
movement movement vehicular
dB(A) dB(A) movement dB(A)
10 36 72 72 60
20 36 67 67 55
50 36 61 61 49
100 36 57 57 45
WAPCOS Limited 9-15
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
The effect of high noise levels on the operating personnel has to be considered as this may
be particularly harmful. It is known that continuous exposures to high noise levels above 90
dB(A) affects the hearing acuity of the workers/operators and hence, should be avoided. To
prevent these effects, it has been recommended by Occupational Safety and Health
Administration (OSHA) that the exposure period of affected persons be limited as per the
maximum exposure period specified in Table-9.11.
The noise levels during various construction activities have been compared to various
standards prescribed by Occupational Safety and Health Administration (OSHA), which are
being implemented in our country through rules framed under Factories Act. It can be
observed that as per unprotected exposure period specified by OSHA (Refer Table-9.11)
that for an 8 hour duration, equivalent noise level exposure should be less than 90 dB(A).
The Director General of Mines Safety in its circular no. DG(Tech)/18 of 1975, has prescribed
the noise level in mining operations for workers in 8 hour shift period with unprotected ear as
90 dB(A) or less. Similar norms can be considered for construction phase of the proposed
project as well. The workers who are expected to be exposed to noise levels greater than 90
dB(A), should not work in these areas beyond 6 to 8 hours. In addition, they also need to be
provided with ear plugs. Thus, increased noise levels due to drilling are not expected to
adversely affect the workers operating the drill or involved in other mining activities closely.
The above construction material shall be arranged from the identified quarry sites located at
the confluence of Bakanwal nala with Chenab River, 3.6 Km upstream of dam axis on the left
bank. The quantum of muck generation is 13, 15,000.00 cum, of 3, 94,500.00 cum shall be used
as construction material. Fine aggregate requirement shall be met locally from the river bed
and crushed sand.
For the construction purpose around 70% material from Quarry site, 20% material from
excavated muck & rest 10% material shall be utilized from River bed.
Opening of the quarries will cause visual impacts because they remove a significant part of
the hills. Other impacts will be the noise generated during aggregate acquisition through
explosive and crushing, which could affect wildlife in the area, dust produced during the
crushing operation to get the aggregates to the appropriate size and transport of the
aggregates, and transport of materials.
The quarrying operations are semi-mechanized in nature. Normally, in a hilly terrain like
Himachal Pradesh, quarrying is normally done by cutting a face of the hill. A permanent scar
is likely to be left, once quarrying activities are over. With the passage of time, the rock from
the exposed face of the quarry under the action of wind and other erosion forces, get slowly
weathered and after some time, they become a potential source of landslide. Thus it is
necessary to implement appropriate slope stabilization measures to prevent the possibility of
soil erosion and landslides in the quarry sites.
Efforts must be made to site the contractor’s working space in such a way that the adverse
impacts on environment are minimal, i.e. to locate the construction equipment, so that an
impact on human and faunal population is minimal.
It is clear from Table-9.15, that total 1.01 Mm3 of muck needs to be disposed. Most of the
area, identified for dumping is planned on the banks of nearest drainages & away from River
HFL. The identified areas are mostly gradually sloping near river bank. The drainage side
bank of the area will be properly protected and stabilized with Gabions/ Retaining Walls of
suitable designed sections. The details of muck disposal areas and capacities are given in
Table-9.16.
Table-9.16: Muck Disposal Sites and Capacities
S. Disposal Site Area Average road Capacity
No. distance from Dam
area
(ha) (km) (lakh cum)
1 Area near Bumbal (R/Bank) 5.46 1 2.30
2 Area near Mindhal Bridge 0.77 6 0.20
(L/Bank)
WAPCOS Limited 9-20
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
The capacity of various muck disposal sites is 1.02 Mm3. As such, around 1.01 Mm3 muck to
be disposed hence capacity of the dumping area is sufficient to accommodate the muck
generated from the project.
Muck, if not securely transported and dumped at pre-designated sites, can have serious
environmental impacts, such as:
• Muck, if not disposed properly, can be washed away into the main river which can
cause negative impacts on the aquatic ecosystem of the river.
• Muck disposal can lead to impacts on various aspects of environment. Normally,
the land is cleared before muck disposal. During clearing operations, trees are
cut, and undergrowth perishes as a result of muck disposal.
• In many of the sites, muck is stacked without adequate stabilization measures. In
such a scenario, the muck moves along with runoff and creates landslide like
situations. Many a times, boulders/large stone pieces enter the river/water body,
affecting the benthic fauna, fisheries and other components of aquatic biota.
• Normally muck disposal is done at low lying areas, which get filled up due to
stacking of muck. This can sometimes affect the natural drainage pattern of the
area leading to accumulation of water or partial flooding of some area.
The muck disposal sites will be suitably stabilized on completion of the muck disposal. The
details of stabilization of muck disposal sites are outlined in Environmental Management
Plan covered in Volume-II of this Report.
v) Acquisition of land
The total land required for the project is 125.62 ha. A part of this land is required for labour
camps, quarry sites, muck disposal storage of construction material, siting of construction
equipment, which will be required temporarily and returned once the construction phase is
over. Permanent acquisition of land is required for Dam axis, submergence area, Power
House etc. The details of land required for various project appurtenances are given in Table-
9.17. The entire land to be acquired is forest land.
WAPCOS Limited 9-21
L&T Himachal Hydropower Limited EIA Report for Sach Khas HEP, Chamba, HP
Two bridges are proposed to construct at River Chenab, one at downstream of Tail Race
Tunnel & other on at Ajog Village for the access of Township. The length of the each bridge
shall be in order of 50 m.
One tree produces about 2.5 m3 of wood, thus, about 127,200 trees will be cut to meet the
fuel wood requirements to the labour population, over a construction phase of 9.5 years.
Hence to minimize impacts, it is recommended that the project contractor shall provide
alternate source of fuel be provided to the labour population, so that they do not cut trees to
meet their fuel wood requirements. The details are covered in Environmental Management
Plan covered in Volume-II of this Report.
The other major impact on the flora in and around the project area would be due to
increased level of human interferences. The workers may also cut trees to meet their
requirements for construction of houses and other needs. Thus, if proper measures are not
undertaken, adverse impacts on terrestrial flora is anticipated. Since, labour camps are
proposed to be constructed by the contractor along with necessary facilities, such impacts
are not envisaged.
During construction of various components of the project, e.g., road, colony, dam axis, muck
disposal, etc. trees will have to be cleared. The tree felling or clearing shall be done by the
Forest Department.
During construction phase, large number of machinery and construction workers shall be
mobilized. The operation of various equipments will generate significant noise, especially
during blasting which will have adverse impact on fauna of the area. The noise may affect
the fauna and in the area. . Likewise, siting of construction plants, workshops, stores, labour
camps etc. could also lead to adverse impact on fauna of the area due to increase human
interfererence.
During construction phase, accessibility to area will lead to influx of workers and the people
associated with the allied activities from outside will also increase. Increase in human
interference could have an impact on terrestrial ecosystem. The other major impact could be
the blasting to be carried out during construction phase. This impact needs to be mitigated
by adopting controlled blasting and strict surveillance regime and the same is proposed to be
used in the project. This will reduce the noise level and vibrations due to blasting to a great
extent. Likewise, siting of construction equipment, godowns, stores, labour camps, etc. may
generally disturb the fauna in the area. However, no large-scale fauna is observed in the
area. Thus, impacts on this account are not expected to be significant. However, few stray
animals sometimes venture in and around the project site. Thus, to minimize any harm due
to poaching activities from immigrant labour population, strict anti-poaching surveillance
measures need to be implemented, especially during project construction phase. The same
have been suggested as a part of the Environmental Management Plan (EMP).
b) Operation phase
i) Increased accessibility
During the project operation phase, the accessibility to the area will improve due to
construction of roads, which in turn may increase human interferences leading to marginal
adverse impacts on the terrestrial ecosystem. The increased accessibility to the area can
lead to increased human interferences in the form of illegal logging, lopping of trees,
collection of non-timber forest produce, etc. Since significant wildlife population is not found
in the region, adverse impacts of such interferences are likely to be marginal. The details of
measures to improve terrestrial ecology of the area are covered in Volume II of this Report.
b) Operation phase
The completion of Sach Khas hydroelectric Project would bring about significant changes in
the riverine ecology, as the river transforms from a fast-flowing water system to a quiescent
lacustrine environment. Such an alteration of the habitat would bring changes in physical,
chemical and biotic life. Among the biotic communities, certain species can survive the
transitional phase and can adapt to the changed riverine habitat. There are other species
amongst the biotic communities, which, however, for varied reasons related to feeding and
reproductive characteristics cannot acclimatize to the changed environment, and may
disappear in the early years of impoundment of water. The micro-biotic organisms especially
diatoms, blue-green and green algae before the operation of project, have their habitats
beneath boulders, stones, fallen logs along the river, where depth is such that light
penetration can take place. But with the damming of river, these organisms may perish as a
result of increase in depth.
The cumulative impact of all the above operations is increase in turbidity levels. Good dredging
practices can however, minimize turbidity. It has also been observed that slope collapse is the
major factor responsible for increase in the turbidity levels. If the depth of cut is too high, there
is possibility of slope collapse, which releases a sediment cloud. This will further move outside
the suction radius of dredged head.
In order to avoid this typical situation, the depth of cut be restricted to:
γ H/C < 5.5
Where,
γ - Unit weight of the soil
H - Depth of soil
The dredging and deposition of dredged material may affect the survival and propagation of
benthic organisms. The macro-benthic life which remains attached to the stones, boulders etc.
gets dislodged and is carried away downstream by turbulent flow. The areas from where
construction material is excavated, benthic fauna gets destroyed. In due course of time,
however, the area gets recolonized, with fresh benthic fauna. The density and diversity of
benthic fauna will however, be less as compared with the pre-dredging levels.
The second important impact is on the spawning areas of fishes. Almost all the cold water fish
breed in the flowing waters. The spawning areas of these fish species are found amongst
pebbles, gravel, sand etc. The eggs are sticky in nature and remain embedded in the gravel
and subsequently hatch. Any disturbance of stream bottom will result in adverse impacts on fish
eggs. Even increase in fine solids beyond 25 ppm will result in deposition of silt over the eggs,
which would result in asphyxiation of developing embryo and also choking of gills of young
newly emerged fry. Thus, if adequate precautions during dredging operations are not
undertaken, then significant adverse impacts on aquatic ecology are anticipated.
project. The labour force would stay near to the project construction sites.
The project will also lead to certain negative impacts. The most important negative impact
would be during the construction phase. The labour force that would work in the construction
site would settle around the site. They would temporarily reside there. This may lead to filth,
in terms of domestic wastewater, human waste, etc. Besides, other deleterious impacts are
likely to emerge due to inter-mixing of the local communities with the labour force.
Differences in social, cultural and economic conditions among the locals and labour force
could also lead to friction between the migrant labour population and the total population.
2000 m above sea level. The proposed project is located just above this elevation. Hence,
increase in incidence of mosquitoes is not expected at the project site.
9.8.2 Aggregation of labour
About 1200 labourers and technical staff will congregate in the project area during peak
construction phase. The total increase in population is expected to be of the order of 3600.
Most of the labour would come from various parts of the country. The labourer would live in
dormitories provided by the Contractor. Proper sanitary facilities are generally provided. Hence,
a proper surveillance and immunization schedule needs to be developed for the labour
population migrating into the project area.