Control of Incoming and Outgoing Document
DOCUMENT CONTROL (Project Site)
INPUTS PROCESS OUTPUTS
PROJECT(SITE)
Specific Client
Requirements if any
Organization Chart
Updated
Document
Logs/Register
Distribution/Routing
Set up Document Receive all incoming Maintain & Update Maintain Filling
Control Room documents/letters Register/Logs System
Etc.
Remove/Destroy Identify & Stamp
Timely
Superseded Superseded
Retrieval of
Documents Documents
Documents
DOCUMENT CONTROL
Dispatch/Deliver Obtain Process Outgoing
Documents & Obtain Clearance/Approval Documents/Submit
Acknowledgement from Project tals/Transmittals
Maintain File Update
Copies Logs/Register
Approved PQP &
Documents Control
QA/QC
Procedure
Material Approval Process
Material Approval
Submittal Main Contractor Received
Document Review
Main Contractor Main Contractor
Complete Attachment
Send to SC through mail Send to SC through mail
via Doc Controller to via Doc Controller
comply then re-submit
Transmittal preparation to
consultant
Consultant
received/review
Status released
Rejected Approved
25.0 PROJECT QUALITY RECORDS PROCESS:
Flow Chart
Document No Page 124 of 127
Process Flow Chart for Material Inspection
START
INPUTS OUTPUTS
EEC STORE RECEIVED THE DELIVERY NOTE
EEC PO/LPO
DELIVERED MATERIAL FROM SUPPLIER
EEC STORE SUBMIT ALL
EEC INDENT EEC QA/QC
NEEDED DOCUMENTS TO
QA/QC FOR MATERIAL RECEIVED NEEDED
DOCS
INSPECTION
SITE ENGR/QA/QC WILL QA/QC INTERNAL
CONDUCT INTERNAL INSPECTION REPORT
INSPECTION
IF ACCEPTED THEN MDS EEC/MC MDS
WILL BE RAISED TO MC/SC FORMAT
MATERIAL APPROVED BY
SC.
EEC - QUARANTINE STORE - PROPER STORE – LOGISTICS
REJECTED MATERIAL AS STORAGE AND LOGS REPORT/FILLING
PER QA/QC PROCEDURE. MAINTAINED
EEC - IF SAMPLE AND
REMOVAL OF MATERIAL QA/QC – MATERIAL
TESTING REQUIRED IT
FROM STORE IF PROVEN TESTING LOGS /CHECK
WILL BE AS PER MS/ITP
NOT APPROVED SHEET
QA/QC WILL CONFIRM QA/QC – 3RD PARTY TEST
QA/QC – SAMPLE
THE REMOVAL AND IF REQUIRED, SAMPLE
FOR TESTING
INFORM MC/SC AND TEST RESULT TO BE
FORWARDED TO MC/SC.
3RD PARTY TEST AND
RESULTS
SC WILL REVIEW THE
RESULTS AND WILL
ISSUE
APPROVAL/REJECTION EEC – TEST RESULT
AND APPROVAL
STATUS.
LOGS/FILLING
ACCEPTED
END
Document No Page 69 of 127
1. Flow Chart
INPUT START OUTPUT
MC/EEC LOOK AHEAD PROGRAM. SITE ENGR WILL PREPARE IR WITH IR FILLED WITH DETAILS INCLUDING
SITE READINESS AND EXECUTION. COMPLETE ATTACHEMENT AND APPROVED SD/CONTROLLED AND
SUBMIT TO QA/QC DEPT. HIGHLIGHTING THE AREA FOR
INSPECTION.
QA/QC WILL VERIFY AND CHECK ALL
THE ATTACHEMENT IF APPROVED COMPLETE VERIFICATION OF
OR NOT BEFORE ISSUING THE FINAL ATTACHEMENT IN RELATION TO THE
IR. CHECKLIST WILL BE ATTACHED IF AREA REQUESTED FOR INSPECTION.
REQUIRED.
QA/QC AND SITE ENGR WILL
CONDUCT AN INTERNAL
INSPECTION TO MAKE SURE THE SITE VERIFICATION READINESS FOR
READINESS OF THE SITE FOR INSPECTION.
INSPECTION. COMMENTS IF ANY TO
BE RECTIFIED.
QA/QC TO GIVE IT TO DC FOR LOGS
BEFORE SUBMITTING IT TO MC DC.
MAKE SURE THAT THE DATE
REQUIRED FOR INSPECTION IS 24
HRS.
IR TO MC DC FOR LOGS
MC ACKNOWLEDGEMENT OF
AND VERIFICATION THEN
SUBMITTED IR.
FORWARDED TO SC
SC SCHEDULED
INSPECTION SC COMMENTS ON THE
INSPECTION
TO BE
REVISED/RESUBMI APPROVED/APPROVED WITH
T BASED ON THE COMMENTS ON SAME DAY OF
INSPECTION SC INSPECTION.
STATUS
MC TO SEND THE APPROVED IR
COPY TO EEC TO PROCEED TO COPY OF IR SIGNED FROM SC AND
THE NEXT ACTIVITY. STATUS – FOR IR REGISTER
END