Construction Process Flow Chart

The document outlines the process for controlling incoming and outgoing documents at a project site, detailing inputs, processes, and outputs. It includes procedures for document reception, distribution, approval, and material inspection, ensuring compliance with client requirements and quality assurance standards. The flow charts illustrate the steps for document handling, material approval, and inspection readiness, emphasizing the importance of maintaining accurate logs and timely retrieval of documents.

Uploaded by

steelh880
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
83 views5 pages

Construction Process Flow Chart

The document outlines the process for controlling incoming and outgoing documents at a project site, detailing inputs, processes, and outputs. It includes procedures for document reception, distribution, approval, and material inspection, ensuring compliance with client requirements and quality assurance standards. The flow charts illustrate the steps for document handling, material approval, and inspection readiness, emphasizing the importance of maintaining accurate logs and timely retrieval of documents.

Uploaded by

steelh880
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 5

Control of Incoming and Outgoing Document

DOCUMENT CONTROL (Project Site)


INPUTS PROCESS OUTPUTS
PROJECT(SITE)

Specific Client
Requirements if any

Organization Chart

Updated
Document
Logs/Register
Distribution/Routing

Set up Document Receive all incoming Maintain & Update Maintain Filling
Control Room documents/letters Register/Logs System
Etc.

Remove/Destroy Identify & Stamp


Timely
Superseded Superseded
Retrieval of
Documents Documents
Documents
DOCUMENT CONTROL

Dispatch/Deliver Obtain Process Outgoing


Documents & Obtain Clearance/Approval Documents/Submit
Acknowledgement from Project tals/Transmittals

Maintain File Update


Copies Logs/Register

Approved PQP &


Documents Control
QA/QC

Procedure
Material Approval Process

Material Approval
Submittal Main Contractor Received

Document Review

Main Contractor Main Contractor

Complete Attachment

Send to SC through mail Send to SC through mail


via Doc Controller to via Doc Controller
comply then re-submit
Transmittal preparation to
consultant

Consultant
received/review

Status released

Rejected Approved
25.0 PROJECT QUALITY RECORDS PROCESS:

Flow Chart

Document No Page 124 of 127


Process Flow Chart for Material Inspection

START
INPUTS OUTPUTS

EEC STORE RECEIVED THE DELIVERY NOTE


EEC PO/LPO
DELIVERED MATERIAL FROM SUPPLIER

EEC STORE SUBMIT ALL


EEC INDENT EEC QA/QC
NEEDED DOCUMENTS TO
QA/QC FOR MATERIAL RECEIVED NEEDED
DOCS
INSPECTION

SITE ENGR/QA/QC WILL QA/QC INTERNAL


CONDUCT INTERNAL INSPECTION REPORT
INSPECTION

IF ACCEPTED THEN MDS EEC/MC MDS


WILL BE RAISED TO MC/SC FORMAT

MATERIAL APPROVED BY
SC.

EEC - QUARANTINE STORE - PROPER STORE – LOGISTICS


REJECTED MATERIAL AS STORAGE AND LOGS REPORT/FILLING
PER QA/QC PROCEDURE. MAINTAINED

EEC - IF SAMPLE AND


REMOVAL OF MATERIAL QA/QC – MATERIAL
TESTING REQUIRED IT
FROM STORE IF PROVEN TESTING LOGS /CHECK
WILL BE AS PER MS/ITP
NOT APPROVED SHEET

QA/QC WILL CONFIRM QA/QC – 3RD PARTY TEST


QA/QC – SAMPLE
THE REMOVAL AND IF REQUIRED, SAMPLE
FOR TESTING
INFORM MC/SC AND TEST RESULT TO BE
FORWARDED TO MC/SC.

3RD PARTY TEST AND


RESULTS

SC WILL REVIEW THE


RESULTS AND WILL
ISSUE
APPROVAL/REJECTION EEC – TEST RESULT
AND APPROVAL
STATUS.
LOGS/FILLING

ACCEPTED

END
Document No Page 69 of 127
1. Flow Chart

INPUT START OUTPUT

MC/EEC LOOK AHEAD PROGRAM. SITE ENGR WILL PREPARE IR WITH IR FILLED WITH DETAILS INCLUDING
SITE READINESS AND EXECUTION. COMPLETE ATTACHEMENT AND APPROVED SD/CONTROLLED AND
SUBMIT TO QA/QC DEPT. HIGHLIGHTING THE AREA FOR
INSPECTION.

QA/QC WILL VERIFY AND CHECK ALL


THE ATTACHEMENT IF APPROVED COMPLETE VERIFICATION OF
OR NOT BEFORE ISSUING THE FINAL ATTACHEMENT IN RELATION TO THE
IR. CHECKLIST WILL BE ATTACHED IF AREA REQUESTED FOR INSPECTION.
REQUIRED.

QA/QC AND SITE ENGR WILL


CONDUCT AN INTERNAL
INSPECTION TO MAKE SURE THE SITE VERIFICATION READINESS FOR
READINESS OF THE SITE FOR INSPECTION.
INSPECTION. COMMENTS IF ANY TO
BE RECTIFIED.

QA/QC TO GIVE IT TO DC FOR LOGS


BEFORE SUBMITTING IT TO MC DC.
MAKE SURE THAT THE DATE
REQUIRED FOR INSPECTION IS 24
HRS.

IR TO MC DC FOR LOGS
MC ACKNOWLEDGEMENT OF
AND VERIFICATION THEN
SUBMITTED IR.
FORWARDED TO SC

SC SCHEDULED
INSPECTION SC COMMENTS ON THE
INSPECTION

TO BE
REVISED/RESUBMI APPROVED/APPROVED WITH
T BASED ON THE COMMENTS ON SAME DAY OF
INSPECTION SC INSPECTION.
STATUS
MC TO SEND THE APPROVED IR
COPY TO EEC TO PROCEED TO COPY OF IR SIGNED FROM SC AND
THE NEXT ACTIVITY. STATUS – FOR IR REGISTER

END