PMP Exercise Document Jan 2025 - 1737871690501
PMP Exercise Document Jan 2025 - 1737871690501
PMP Training
Sample Questions
1. Four project managers are having lunch together and discussing their projects. Most of the
time they are just complaining about how hard projects are to manage in their company.
Some complain about the stakeholders and the number of changes they cause. Others talk
about how hard it is to get people to cooperate and perform. One project manager wants to
focus on the advantages of the matrix type organization they all work in for their projects,
which of the following would he mention?
A. Improved project manager control over resources
B. More than one boss for project teams
C. Communications are easier
D. Reporting is easier
2. Two project managers have just realized that they are in a weak matrix organization and that
their power as project managers is quite limited. One figure out that he is really a project
expediter and the other realizes he is really a project coordinator. How is a project expediter
different from a project coordinator?
A. The project expediter cannot make decisions.
B. The project expediter can make more decisions.
C. The project expediter reports to a higher-level manager.
D. The project expediter has some authority.
4. A project manager is trying to complete a software development project, but cannot get
enough attention for the project. Resources are focused on completing process related work
and the project manager has very little authority to properly assign resources.
What form of organization must the project manager be working in?
A. Functional
B. Matrix
C. Expediter
D. Coordinator
5. A project manager has very little project expenditure, but he has been assigned as the project
manager of a new project. Because he will be working in a matrix organization to complete
his project, he can expect communication to be:
Page 2 of 80
Sample Questions
A. Simple
B. Open and accurate
C. Complex
D. Hard to automate
6. A project team member is talking to another team member and complaining that so many
people are asking him to do things. If he works in a functional organization, who has the
power to give direction to the team member?
A. The project manager
B. The functional manager
C. The team
D. Tight matrix
9. All of the following are parts of the team’s stakeholder management effort EXCEPT?
A. Giving stakeholder’s extras
B. Identifying stakeholders
C. Determining stakeholder needs
D. Managing stakeholders’ expectations
Page 3 of 80
Sample Questions
10. A manager and the head of engineering discuss a change to a major work package. After the
meeting the manager contacts you and tells you to complete the paper work to make the
change. This is an example of:
A. Management attention to scope management
B. Management planning
C. A project expediter position
D. A change control system
Page 4 of 80
Sample Questions
1. In which project management process group is the detailed project budget created?
A. Initiating
B. Before the project management process
C. Planning
D. Executing
3. The project team has just completed the initial project schedule and budget. The NEXT thing
to do is:
A. Begin risk identification
B. Begin iterations
C. Determine communication requirements
D. Create a bar (Gantt) charts
5. The person who should be in control of the project during project management planning is
the:
A. Project manager
B. Team leader
C. Functional manager
D. Sponsor
Page 5 of 80
Sample Questions
C. Historical WBSs
D. Project scope statement
7. The project sponsor has just provided the preliminary project scope statement. What is the
NEXT thing to do?
A. Begin to complete work packages
B. Complete scope verification
C. Start integrated change control
D. Start to create management plans
8. The high-level project schedule constraints have just been determined. What project
management process group are you in?
A. Initiating
B. Planning
C. Executing
D. Monitoring & controlling
9. The WBS and WBS dictionary are completed. The project team has begun working on
identifying risks. The sponsor contacts the project manager, requesting that the responsibility
assignment matrix be issued. The project has a budget of $100,000 and is taking place in
three countries using 14 human resources. There is little risk expected for project and the
projects similar to this one. What is the next thing to do?
A. Understanding the experience of the sponsor on similar projects
B. Create an activity list
C. Make sure the project scope is defined
D. Complete risk management and issue the responsibility assignment matrix
10. A project manager does not have much time to spend planning before the mandatory start
date arrives. He therefore wants to move through planning as effectively as possible. Which
of the following would you recommend?
A. Start the WBS after you have a completed preliminary project scope statement
B. Create an activity list before creating a network diagram
C. Document all the known risks before you document the high-level assumption
D. Finalize the quality management plan before you determine quality metrics
Page 6 of 80
Sample Questions
2. You’re the project manager for an industrial design project. Your team members report to
you, and you’re responsible for creating the budget, building the schedule, and assigning the
tasks. When the project is complete, you release the team so they can work on other projects
for the company. What kind of organization do you work in?
A. Functional
B. Weak matrix
C. Strong matrix
D. Projectized
3. Which of the following describes the BEST use of historical records from previous projects?
A. Estimation life cycle costing and project planning
B. Risk management estimating and creating lessons learned
C. Project management planning estimating and creating a status report
D. Estimating risk management and project planning
4. When it comes to changes the project manager’s attention is BEST spent on:
A. Making changes
B. Tracking and recording changes
C. Informing the sponsor of changes
D. Preventing unnecessary changes
Page 7 of 80
Sample Questions
6. All of the following are parts of an effective change control system EXCEPT?
A. Procedures
B. Standards of reports
C. Meetings
D. Lessons learned
8. A project is plagued by changes to the charter, who has the primary responsibility to decide if
these changes are necessary?
A. Project manager
B. Project team
C. Sponsor
D. Stakeholders
10. Which of the following BEST describes the project manager’s role as an integrator?
A. Help team members become familiar with project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole.
Page 8 of 80
Sample Questions
2. The work breakdown structure can BEST be thought of as effective aid for ______
communications.
A. Team
B. Project manager
C. Customer
D. Stakeholder
4. During project executing, a team member comes to the project manager because he is not
sure of what work he needs to accomplish on the project. Which of the following documents
contain detailed descriptions of work packages?
A. Work breakdown structure (WBS) dictionary
B. Activity List
C. Preliminary project scope statement
D. Project scope management plan
5. During what part of the project management process is the project scope statement created?
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
Page 9 of 80
Sample Questions
6. The program was planned years ago before there was a massive introduction of new
technology. While planning the next project to start in this program, the project manager has
expanded the project scope management plan because as a project becomes more complex,
the level of uncertainty in the scope:
A. Remains the same
B. Decreases
C. Decreases then increases
D. Increases
7. A project management plan should be realistic in order to be used to manage the project.
Which of the following is the best method to achieve a realistic project management plan?
A. Sponsor creates the project management plan based on input from the project manager.
B. Functional manager creates the project management plan based on input from the project
manager.
C. Project manager creates the project management plan based on input from senior
management
D. Project manager creates the project management plan based on input from the team.
9. During a project team meeting, a team member suggests an enhancement to the scope that is
beyond the scope of the project charter. The project manager points out that the team needs
to concentrate on completing all the work and only the work required. This is an example of:
A. Change management process
B. Scope management
C. Quality analysis
D. Scope decomposition
Page 10 of 80
Sample Questions
Page 11 of 80
Sample Questions
1. To control the schedule, a project manager is reanalyzing the project to predict project
duration. She does this by analyzing the sequence of activities with the least amount of
scheduling flexibility. What techniques is she using?
A. Critical path method
B. Flowchart
C. Precedence diagramming
D. Work breakdown structure
3. Which of the following are GENERALLY illustrated BETTER by bar charts than network
diagrams?
A. Logical relationship
B. Critical paths
C. Resource trade-offs
D. Progress or status
4. If the optimistic estimate for an activity is 12days, and the pessimistic estimate is 18days,
what is the standard deviation of this activity?
A. 1
B. 1.3
C. 6
D. 3
Page 12 of 80
Sample Questions
6. Lag means:
A. The amount of time an activity can be delayed without delaying the project finish date
B. The amount of time an activity can be delayed without delaying the early start date of its
successor
C. Waiting time
D. The product of a forward and backward pass
7. Which of the following is the BEST project management tool to use to determine the longest
time the project will take?
A. WBS
B. Network diagram
C. Bar chart
D. Project charter
8. You have just been assigned as the project manager for an ongoing project in your company.
You have discovered there is no Project Charter that describes the responsibilities and
authorities of the project manager. When you talked to your project sponsor about this issue
he told you that nobody in the company even knows what a Project Charter is or what
purpose it serves. He also told you that your company has executed numerous projects in the
past without ever using a Project Charter. However, he asked you to prepare one just in case
it is really a necessary project document. Where should you look for a Project Charter
template to update in order to meet your project requirements?
A. Project Business Case
B. Enterprise Environmental Factors
C. Project Statement of Work
D. Organizational Process Assets
Page 13 of 80
Sample Questions
10. Which of the following BEST describes the relationship between standard deviation and
risk?
A. Nothing
B. Standard deviation tells you if the estimate is accurate
C. Standard deviation tells you how unsure the estimate is
D. Standard deviation tells you if the estimate includes a pad.
Page 14 of 80
Sample Questions
1. One way to compute estimate at completion (EAC) is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
3. If earned value (EV) =350, actual cost (AC)=400, planned value (PV) =325. What is cost
variance (CV)?
A. 350
B. -75
C. 400
D. -50
5. Analogous estimating:
A. Uses bottom-up estimating techniques
B. Is used most frequently during the executing processes of the project
C. Uses top-down estimating techniques
D. Uses actual detailed historical costs
Page 15 of 80
Sample Questions
Page 16 of 80
Sample Questions
2. You are working on a project with an SPI of.72 and a CPI of 1.1. Which of the following
BEST describes your project?
A. Your project is ahead of schedule and under budget
B. Your project is behind schedule and over budget
C. Your project is behind schedule and under budget
D. You project is ahead of schedule and over budget
4. A team is using a fishbone diagram to help determine what quality standards will be used on
the project. What part of the quality management process are they in?
A. Perform quality control
B. Perform quality assurance
C. Quality planning
D. Variable analysis
Page 17 of 80
Sample Questions
5. A manager notices that a project manager is holding a meeting with some of the team and
some stakeholders to discuss the quality of the project. The project schedule has been
compressed and the CPI is 1.1. They have worked hard on the project, the team has been
rewarded according to the reward system the project manager put in place and there is a
strong sense of team: The manager suggests that the project manager does not have enough
time to hold meetings about quality when the schedule is so compressed. Which of the
following BEST describes why the manager is wrong?
A. Improved quality leads to increased productivity, increased cost effectiveness and
decreased cost risk.
B. Improved quality leads to increased productivity, decreased cost effectiveness and
increased cost risk.
C. Improved quality leads to increased productivity, increased cost effectiveness and
increased cost risk.
D. Improved quality leads to increased productivity, decreased cost effectiveness and
decreased cost risk.
7. Quality is:
A. Meeting and exceeding the customer’s expectations.
B. Adding extras to make the customer happy.
C. The degree to which the project meets requirements.
D. Conformance to management’s objectives.
Page 18 of 80
Sample Questions
Page 19 of 80
Sample Questions
1. The MOST common cause of conflict on a project are schedule, project priorities, and:
A. Personalities.
B. Resources.
C. Cost.
D. Management
2. What conflict resolution technique is a project manager using when he says , ‘ I cannot deal
with this issue now!”
A. Problem solving.
B. Forcing.
C. Withdrawal
D. Compromising.
3. What does a resource histogram shows that a responsibility assignment matrix does not?
A. Time
B. Activity
C. Interrelationships
D. The person in charge of each activity.
4. You have just been assigned as project manager for a large telecommunications project. This
one year project is about halfway done. The project team consists of five sellers and 20 of
your company’s employees. You want to understand who is responsible for doing what on
the project. Where would you find such information?
A. Responsibility assignment matrix
B. Resource histogram
C. Bar Chat
D. Project organization chat
5. During project planning in matrix organization, the project manager determines that
additional human resources are needed. From whom would he request these resources?
A. Project manager
B. Functional manager
Page 20 of 80
Sample Questions
C. Team
D. Project sponsor
6. A project manager must publish a project schedule. Activities, start/end times and resources
are identified. What should the project manager do NEXT?
A. Distribute the project schedule according to the communication management plan.
B. Confirm the availability of the resource.
C. Refine the project management plan to reflect more accurate costing information.
D. Publish a bar chart illustrating the timeline.
7. During every project team meeting, the project manager asks each team member to describe
the work he or she is doing, and the project manager assigns new activities to team members.
The length of the meeting has increased because there are many different activities to assign.
This could be happening for all the following reasons. EXCEPT?
A. Lack of WBS
B. Lack of a responsibility assignment matrix
C. Lack of resource leveling
D. Lack of team involvement in project planning
8. You are project manager leading a cross-functional project team in a weak matrix
environment none of project team members report to you functionally and you not have the
ability to directly reward their performance. The project is difficult involving tight date
constraints and challenging Quality standards. Which of the following types of project
management power will likely be the MOST effective in this circumstance?
A. Referent
B. Expert
C. Penalty
D. Formal
9. A team member is not performing well on the project because she is inexperienced in system
development work. What is the BEST solution for the project manager?
A. Consult with functional manager to determine project completion incentives for the team
member.
B. Obtain a new source more skilled in development work.
C. Arrange for the team member to get training.
Page 21 of 80
Sample Questions
10. A project manager has just found out that major subcontractor for project is consistently late
delivery work. The project team member responsible for this part of the project does not get
along with sub-contractor. To resolve the problem the project manager says, “You both will
have to give up something to solve this problem. What conflict resolution method is she
using?
A. Confrontation
B. Compromise
C. Smoothing
D. Communicating
Page 22 of 80
Sample Questions
2. The work breakdown structure can be an effective aid for communication in which
situation(s) ?
A. Internal within the project team
B. Internal within the organization
C. External with the customer
D. Internal & external to the project
4. Communications are often enhanced when the sender _______ the receiver.
A. Speaks up to
B. Uses more physical movement when talking to
C. Talks slowly to
D. Shows concern for the perspective of
Page 23 of 80
Sample Questions
6. A project manager has a problem with a team member’s performance. What is BEST form of
communication for addressing this problem?
A. Formal written communication
B. Formal verbal communication
C. Informal written communication
D. Informal verbal communication
10. A large, one- year telecommunication project is about halfway done when you take the place
of the previous project manager. The project involves three different sellers and a project
team of 30 people. You would like to see the project’s communications requirements and
what technology is being used to aid in project communications. Where will you find this
information?
A. The project management plan
B. The information distribution plan
C. The bar chart
D. The communication management plan
Page 24 of 80
Sample Questions
4. You are finding it difficult to evaluate the exact cost of risks. You should evaluate on a :
A. Quantitative basis
B. Numerical basis
C. Qualitative basis
D. Econometric basis
Page 25 of 80
Sample Questions
A. Risk identification
B. Quantitative risk analysis
C. Risk response planning
D. Risk monitoring and control
8. A project manager has just finished the risk response plan for a $ 387,000 engineering
project. Which of the following should be probably done NEXT?
A. Determine the overall risk rating of the project
B. Begin to analyze the risks that show up in the project drawings
C. Add work packages to the project work breakdown structure
D. Hold a project risk reassessment
9. A project manager asked various stakeholders to determine the probability and impact of a
number of risks. He then analyzed assumptions. He is about to move to the next step of risk
management. Based on this information, what has the project manager forgotten to do?
A. Evaluate trends in risk analysis
B. Identify triggers
C. Provide a standardized risk rating matrix
D. Create a fall back plan
10. A project manager has assembled the project team, identified 56 risks on the project,
determined what would trigger the risks, rated them on a risk rating matrix, tested their
assumptions and assessed the quality of the data used. The team is continuing to move
through the risk management process. What has the project manager forgotten to do?
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involvement of other stakeholders
Page 26 of 80
Sample Questions
2. With a clear contract statement of work, a seller completes work as specified, but the buyer is
not pleased with the results. The contract is considered to be:
A. Null and void
B. Incomplete
C. Complete
D. Waived
3. All of the following statements concerning bid documentation are incorrect EXCEPT?
A. Well-designed bid documents can simplify comparison of responses.
B. Bid documentation must be rigorous with no flexibility to allow consideration of seller
suggestions.
C. In general, bid documents should not include evaluation criteria.
D. Well-designed bid documents do not include a contract statement of work.
4. A project manager for the seller is told by her management that the project should do
whatever possible to be awarded incentive money. The primary objective of incentive clauses
in a contract is to:
A. Reduce costs for the buyer.
B. Help the seller control costs
C. Synchronize objectives
D. Reduce risk for the seller by shifting risk to the buyer.
5. All the following statements about change control are incorrect EXCEPT?
A. A fixed price contract will minimize the need for change control
B. Changes seldom provide real benefits to the project
C. Contracts should include procedures to accommodate changes
D. More detailed specifications eliminate the causes of changes
Page 27 of 80
Sample Questions
6. A routine audit of a cost reimbursable contract determines that overcharges are being made.
If the contract does not specify corrective action, the buyer should:
A. Continue to make project payments
B. Halts payments until the problem is corrected
C. Void the contract and start legal action to recover overpayment
D. Change the contract to require more frequent audits
8. A seller is working on a cost reimbursable (CR) contract when the buyer decides he would
like to expand the scope of services and change to a fixed price (FP) contract. All of the
following are the seller’s options EXCEPT?
A. Completing the original work on a cost reimbursable basis and then negotiating a fixed
price for the additional work
B. Completing the original work and rejecting the additional work
C. Negotiating a fixed price contract that includes all the work
D. Starting over with a new contract
Page 28 of 80
Sample Questions
3. Understanding how human resource requirements will be met and how staffing management
will be addressed is useful information for the Project Manager in developing the
Stakeholder Management Plan. This information might be found in the ______________, a
key Input in the Plan Stakeholder Management process.
A. Project Management Plan
B. Stakeholder Register
C. Communications Management Plan
D. Stakeholder Management Plan
4. During stakeholder analysis, PM and team may use different models to classify. The model
that helps to analyze the stakeholder’s ability to impose his or her will or power and
influence the need for immediate attention from the project team along with the legitimacy of
the stakeholder’s involvement is :
A. Power/Interest grid
B. RAM
C. Salience model
D. Stakeholder register.
Page 29 of 80
Sample Questions
7. Which of the following should you be most concerned about, while doing stakeholder
analysis?
A. Their interest in the project
B. Their influence on the project
C. Both A&B
D. Neither A nor B
8. Which is the best way to manage stakeholders who are low on power and interest?
A. Monitor them
B. No need to worry about them
C. Treat all stakeholders equal
D. Keep them informed
9. Which of the following is the tool to assess the current and desired level of engagement of a
stakeholder on a project?
A. Stakeholder registers
B. Stakeholder management plan
C. Stakeholder engagement assessment matrix
D. Impact/power grid
10. Which of the following is an input to the plan stakeholder management process?
A. Stakeholder registers
B. Stakeholder management plan
C. Stakeholder engagement assessment matrix
D. Impact/power grid
Page 30 of 80
Sample Questions
PRACTICE EXERCISE
Answers
Page 31 of 80
Sample Questions
1. Four project managers are having lunch together and discussing their projects. Most of
the time they are just complaining about how hard projects are to manage in their
company. Some complain about the stakeholders and the number of changes they cause.
Others talk about how hard it is to get people to cooperate and perform. One project
manager wants to focus on the advantages of the matrix type organization they all work
in for their projects, which of the following would he mention?
A. Improved project manager control over resources
B. More than one boss for project teams
C. Communications are easier
D. Reporting is easier
Explanation: Remember that if the question doesn’t state what it is comparing to, it is
comparing to a functional organization.
2. Two project managers have just realized that they are in a weak matrix organization and that
their power as project managers is quite limited. One figure out that he is really a project
expediter and the other realizes he is really a project coordinator. How is a project expediter
different from a project coordinator?
A. The project expediter cannot make decisions.
B. The project expediter can make more decisions.
C. The project expediter reports to a higher-level manager.
D. The project expediter has some authority.
Explanation: The project coordinator reports to a higher-level manager and has authority to
make some decisions. The project expediter has no authority to make decisions.
4. A project manager is trying to complete a software development project, but cannot get
enough attention for the project. Resources are focused on completing process related work
and the project manager has little authority to properly assign resources.
What form of organization must the project manager be working in?
A. Functional
Page 32 of 80
Sample Questions
B. Matrix
C. Expediter
D. Coordinator
Explanation: In a functional organization, the project manager has the least support for the
project and has little authorized to assign resources. Choice C and D are forms of weak
matrix.
5. A project manager has very little project expenditure, but he has been assigned as the project
manager of a new project. Because he will be working in a matrix organization to complete
his project, he can expect communication to be:
A. Simple
B. Open and accurate
C. Complex
D. Hard to automate
Explanation: Because a project done in a matrix organization involves people from across
the organization, communications are more complex
6. A project team member is talking to another team member and complaining that so many
people are asking him to do things. If he works in a functional organization, who has the
power to give direction to the team member?
A. The project manager
B. The functional manager
C. The team
D. Tight matrix
Explanation: In a functional organization, the functional manager is the team member’s boss
and probably also the project manager’s boss
Page 33 of 80
Sample Questions
C. Interrelated activities
D. Repeats itself every month
Explanation: Choice D implies that the whole project repeats every month. Generally, the
only things that might repeat in a project are some activities. The whole project does not
repeat
9. All of the following are parts of the team’s stakeholder management effort EXCEPT?
A. Giving stakeholder’s extras
B. Identifying stakeholders
C. Determining stakeholder needs
D. Managing stakeholders’ expectations
Explanation: Giving stakeholders extras is gold plating (see the quality chapter). This is not
effective stakeholder or quality management.
10. A manager and the head of engineering discuss a change to a major work package. After the
meeting the manager contacts you and tells you to complete the paper work to make the
change. This is an example of:
A. Management attention to scope management
B. Management planning
C. A project expediter position
D. A change control system
Explanation: This is an example of a project expediter position because you are evaluating
the change, looking for impacts, etc. You are implementing others requests. In this case, you
are acting as the project expediter and the manager is acting as the project manager.
Page 34 of 80
Sample Questions
1. In which project management process group is the detailed project budget created?
A. Initiating
B. Before the project management process
C. Planning
D. Executing
Explanation: Notice the use of the word “detailed.” Such a budget is created during the
planning process group.
3. The project team has just completed the initial project schedule and budget. The NEXT thing
to do is:
A. Begin risk identification
B. Begin iterations
C. Determine communication requirements
D. Create a bar (Gantt) charts
Explanation: Iterations (choice B) cannot begin until the risks are identified, qualified,
quantified & response developed. These then create the need to revise the WBS and other
parts of the project management plan. A bar chart (choice D) would have been done during
the creation of the schedule, so it cannot be the next thing. Communication requirements and
quality standard are needed before risks(especially risks relating to communication and
quality)can be determined (choice A)
Page 35 of 80
Sample Questions
Explanation: In the project management process, the project budget (choice A), project
management plan (choice C) and detailed risk assessment (choice D) come after the
schedule. The only answer that could be an input is the WBS.
5. The person who should be in control of the project during project management planning is
the:
A. Project manager
B. Team leader
C. Functional manager
D. Sponsor
Explanation: The project manager should be named early in the project initiating if possible.
7. The project sponsor has just provided the preliminary project scope statement. What is the
NEXT thing to do?
A. Begin to complete work packages
B. Complete scope verification
C. Start integrated change control
D. Start to create management plans
Explanation: The preliminary project scope statement is created during the initiating process
group. Therefore the question is asking what is done next in either the initiating process
group or the planning process group. For this type of question, you should look at the choice
that occurs closest to the process group you are in. Choice A is done during the executive
process group. Choice B and C are done during the monitoring and controlling process
group. Choice D is the best choice, as it is part of the planning process group.
8. The high-level project schedule constraints have just been determined. What project
management process group are you in?
A. Initiating
B. Planning
Page 36 of 80
Sample Questions
C. Executing
D. Monitoring & controlling
Explanation: High-level project constraints are determined during the initiating process
group
9. The WBS and WBS dictionary are completed. The project team has begun working on
identifying risks. The sponsor contacts the project manager, requesting that the responsibility
assignment matrix be issued. The project has a budget of $100,000 and is taking place in
three countries using 14 human resources. There is little risk expected for project and the
projects similar to this one. What is the next thing to do?
A. Understanding the experience of the sponsor on similar projects
B. Create an activity list
C. Make sure the project scope is defined
D. Complete risk management and issue the responsibility assignment matrix
Explanation: Look at the order of planning the project the team has chosen. Though
understanding the sponsor (choice A) might sound like a good idea, the sponsor is a
stakeholder and understanding them is part of stakeholder analysis. That should have
occurred before the creation of a WBS. In planning the project scope is defined (choice C is
another name for finalize the project scope statement) and would come before creating a
WBS Choice D cannot be best as the team would be going in the wrong direction. Other
work, like creating a network diagram, should be completed before risk can effectively be
done. Only activity list (choice B) comes after the WBS and WBS dictionary.
10. A project manager does not have much time to spend planning before the mandatory start
date arrives. He therefore wants to move through planning as effectively as possible. Which
of the following would you recommend?
A. Start the WBS after you have a completed preliminary project scope statement
B. Create an activity list before creating a network diagram
C. Document all the known risks before you document the high-level assumption
D. Finalize the quality management plan before you determine quality metrics
Explanation: This question is asking, which of the choices is the most effective way to move
through the planning process? Choice A skips the important steps of finalizing the scope and
other activities. High level assumptions are determined during the initiating processes and all
the risks are documented during the planning processes, making choice C incorrect. Metrics
are part of the quality management plan, making choice D incorrect. Choice B is best, as the
activity list is created immediately before the network diagram.
Page 37 of 80
Sample Questions
2. You’re the project manager for an industrial design project. Your team members report to
you, and you’re responsible for creating the budget, building the schedule, and assigning the
tasks. When the project is complete, you release the team so they can work on other projects
for the company. What kind of organization do you work in?
A. Functional
B. Weak matrix
C. Strong matrix
D. Projectized
3. Which of the following describes the BEST use of historical records from previous projects?
A. Estimation life cycle costing and project planning
B. Risk management estimating and creating lessons learned
C. Project management planning estimating and creating a status report
D. Estimating risk management and project planning
Explanation: Historical records are not generally used for life cycle costing (Choice A)
lessons learned (Choice B) or creating status reports (Choice C).
4. When it comes to changes the project manager’s attention is BEST spent on:
A. Making changes
B. Tracking and recording changes
C. Informing the sponsor of changes
D. Preventing unnecessary changes
Page 38 of 80
Sample Questions
Explanation: Project managers should be proactive. The only proactive answer here is
preventing unnecessary changes.
6. All of the following are parts of an effective change control system EXCEPT?
A. Procedures
B. Standards of reports
C. Meetings
D. Lessons learned
Explanation: A change control system consists of the processes and procedures that allow
smooth evaluation and tracking of changes, lessons learned (Choice D) are reviews of the
processes and procedures to improve them they are not part of the system.
8. A project is plagued by changes to the charter, who has the primary responsibility to decide if
these changes are necessary?
A. Project manager
B. Project team
Page 39 of 80
Sample Questions
C. Sponsor
D. Stakeholders
Explanation: The sponsor issues the project charter and so he should help the project
manage control changes to the charter. The primary responsibility lies with the sponsor.
10. Which of the following BEST describes the project manager’s role as an integrator?
A. Help team members become familiar with project
B. Put all the pieces of a project into a cohesive whole
C. Put all the pieces of a project into a program
D. Get all team members together into a cohesive whole.
Explanation: Integration refers to combining activities not team members (Choice D). Could
the project manager smash two team members together and create one big team member? (I
just wanted to see if you are still laughing about the PMP thing).
Page 40 of 80
Sample Questions
2. The work breakdown structure can BEST be thought of as effective aid for ______
communications.
A. Team
B. Project manager
C. Customer
D. Stakeholder
Explanation: The term stakeholder encompasses all the other choices. In this case, it is the
best answer since the WBS can be used (but does not need to be used) as a communication
tool for all stakeholders to “see” what is included in the project.
4. During project executing, a team member comes to the project manager because he is not
sure of what work he needs to accomplish on the project. Which of the following documents
contain detailed descriptions of work packages?
A. Work breakdown structure (WBS) dictionary
B. Activity List
C. Preliminary project scope statement
D. Project scope management plan
Page 41 of 80
Sample Questions
Explanation: Activity lists (choice B) may list the work package they relate to, but they do
not contain detailed description of work packages. The preliminary project scope statement
(choice C) may contain project scope, but does not describe the work a team member is
assigned. The project scope management plan (choice D) describes how scope will be
planned, managed and controlled. It does not include a description of each work package.
The WBS dictionary defines each element in the WBS. Therefore, descriptions of the work
package are in the WBS dictionary.
5. During what part of the project management process is the project scope statement created?
A. Initiating
B. Planning
C. Executing
D. Monitoring and controlling
Explanation: Did you say project initiating? I guess so you did not read the question. Tricky
I Know. Do you hate me yet? And you were worried about long wordy questions!
6. The program was planned years ago before there was a massive introduction of new
technology. While planning the next project to start in this program, the project manager has
expanded the project scope management plan because as a project becomes more complex,
the level of uncertainty in the scope:
A. Remains the same
B. Decreases
C. Decreases then increases
D. Increases
Explanation: Not all questions will be difficult. The level of uncertainty in scope increases
based on the scale of effort required to identify all the scope. For larger projects it is more
difficult to “catch” everything.
7. A project management plan should be realistic in order to be used to manage the project.
Which of the following is the best method to achieve a realistic project management plan?
A. Sponsor creates the project management plan based on input from the project manager.
B. Functional manager creates the project management plan based on input from the project
manager.
C. Project manager creates the project management plan based on input from senior
management
D. Project manager creates the project management plan based on input from the
team.
Explanation: If we were to rephrase the question, it is asking, “Who creates the project
management plan?” The best answer is that project management plans are created by the
project manager but require input from the team
Page 42 of 80
Sample Questions
9. During a project team meeting, a team member suggests an enhancement to the scope that is
beyond the scope of the project charter. The project manager points out that the team needs
to concentrate on completing all the work and only the work required. This is an example of:
A. Change management process
B. Scope management
C. Quality analysis
D. Scope decomposition
Explanation: The team member is suggesting an enhancement that is outside the project
charter. Scope management involves focusing on doing the work and only the work in the
project management plan that meets the needs of the project charter. The project manager is
performing scope management.
Page 43 of 80
Sample Questions
Page 44 of 80
Sample Questions
1. To control the schedule, a project manager is reanalyzing the project to predict project
duration. She does this by analyzing the sequence of activities with the least amount of
scheduling flexibility. What techniques is she using?
A. Critical path method
B. Flowchart
C. Precedence diagramming
D. Work breakdown structure
Explanation: There are only two choices related to scheduling: A and C. Choice C, however
is diagramming technique that deals with the relationship between activities, not schedule
flexibility.
3. Which of the following are GENERALLY illustrated BETTER by bar charts than network
diagrams?
A. Logical relationship
B. Critical paths
C. Resource trade-offs
D. Progress or status
Explanation: The bar chart (or Grant chart) is designed to show a relationship of activities to
time. This is best used when demonstrating progress or status as a factor of time.
4. If the optimistic estimate for an activity is 12days, and the pessimistic estimate is 18days,
what is the standard deviation of this activity?
A. 1
B. 1.3
C. 6
Page 45 of 80
Sample Questions
D. 3
Explanation: The standard deviation is computed by (p-o)/6. Therefore, the answer is (18-
12)/6 = 6/6 = 1.
6. Lag means:
A. The amount of time an activity can be delayed without delaying the project finish date
B. The amount of time an activity can be delayed without delaying the early start date of its
successor
C. Waiting time
D. The product of a forward and backward pass
Explanation: Total float and free float (choices A and B) are the time an activity can be
delayed without impacting the entire project or the next activity. CPM (Choice D) is a
schedule network analysis technique, not waiting time. Choice C is the correct answer.
7. Which of the following is the BEST project management tool to use to determine the longest
time the project will take?
A. WBS
B. Network diagram
C. Bar chart
D. Project charter
Explanation: The bar chart (choice C) may show an end date, but it is not used to determine
dates and show progress. The project charter (choice D) may include any required end dates,
but not a logical determination of how long the project will take. The network diagram
(choice B) takes the work packages from the work breakdown structure (choice A) and adds
dependencies. The dependencies allow us to look at the various paths through the diagram.
The longest duration path is the critical path. Choice B is the best answer.
8. You have just been assigned as the project manager for an ongoing project in your company.
You have discovered there is no Project Charter that describes the responsibilities and
authorities of the project manager. When you talked to your project sponsor about this issue
he told you that nobody in the company even knows what a Project Charter is or what
purpose it serves. He also told you that your company has executed numerous projects in the
Page 46 of 80
Sample Questions
past without ever using a Project Charter. However, he asked you to prepare one just in case
it is really a necessary project document. Where should you look for a Project Charter
template to update in order to meet your project requirements?
A. Project Business Case
B. Enterprise Environmental Factors
C. Project Statement of Work
D. Organizational Process Assets
Explanation: This is a tricky question. Usually templates for project documents are found in
the Organizational Process Assets. However, since your company has never developed a
Project Charter, you cannot find this template there. You can find templates for a Project
Charter on websites and in commercial databases, which are included in Enterprise
Environmental Factors.
10. Which of the following BEST describes the relationship between standard deviation and
risk?
A. Nothing
B. Standard deviation tells you if the estimate is accurate
C. Standard deviation tells you how unsure the estimate is
D. Standard deviation tells you if the estimate includes a pad.
Explanation: Choice A is not best, as the standard deviation tells you the amount of
uncertainty or risk involved in the estimate for the activity. An estimate can have a wide
range (choice B) and still be accurate if the item estimated includes risks. Choice D cannot be
the best answer since there is no such thing as a pad in project management. An estimate
might be inflated, but it is because of risks, not padding.
Page 47 of 80
Sample Questions
1. One way to compute estimate at completion (EAC) is to take the budget at completion
(BAC) and:
A. Divide by SPI
B. Multiply by SPI
C. Multiply by CPI
D. Divide by CPI
Explanation: This question is asking for the formula for EAC, which is BAC/CPI. Notice
how you will have to remember the formulas to get the answers correct.
3. If earned value (EV) =350, actual cost (AC)=400, planned value (PV) =325. What is cost
variance (CV)?
A. 350
B. -75
C. 400
D. -50
Explanation: CV = EV - AC
5. Analogous estimating:
Page 48 of 80
Sample Questions
the life cycle cost includes the project cost. Choice D is often done by inexperienced project
managers who know of nothing else. Now only does it provide little information, but also it
cannot be used to predict the future. Choice B is the best answer since it looks at the past and
uses this information to estimate future costs.
Page 50 of 80
Sample Questions
2. You are working on a project with an SPI of.72 and a CPI of 1.1. Which of the following
BEST describes your project?
A. Your project is ahead of schedule and under budget
B. Your project is behind schedule and over budget
C. Your project is behind schedule and under budget
D. You project is ahead of schedule and over budget
4. A team is using a fishbone diagram to help determine what quality standards will be used on
the project. What part of the quality management process are they in?
A. Perform quality control
B. Perform quality assurance
C. Quality planning
D. Variable analysis
Explanation: The key phrase her is “will be used.” The team is looking to the future of what
quality will be on the project manager ultimately has the responsibility for quality on the
project as a whole.
Page 51 of 80
Sample Questions
5. A manager notices that a project manager is holding a meeting with some of the team and
some stakeholders to discuss the quality of the project. The project schedule has been
compressed and the CPI is 1.1. They have worked hard on the project, the team has been
rewarded according to the reward system the project manager put in place and there is a
strong sense of team: The manager suggests that the project manager does not have enough
time to hold meetings about quality when the schedule is so compressed. Which of the
following BEST describes why the manager is wrong?
A. Improved quality leads to increased productivity, increased cost effectiveness and
decreased cost risk.
B. Improved quality leads to increased productivity, decreased cost effectiveness and
increased cost risk.
C. Improved quality leads to increased productivity, increased cost effectiveness and
increased cost risk.
D. Improved quality leads to increased productivity, decreased cost effectiveness and
decreased cost risk.
Explanation: Notice in this question that there is a lot of data not relevant to answering the
question? Expect these distracters to occur in almost every question on the exam. Quality
should produce a decrease rather than an increase in cost risk as a result of less rework, so
choices B and C can be eliminated. Quality should also provide increased cost effectiveness
due to less rework. This eliminates Choice D leaving the best answer, choice A.
7. Quality is:
A. Meeting and exceeding the customer’s expectations.
B. Adding extras to make the customer happy.
C. The degree to which the project meets requirements.
D. Conformance to management’s objectives.
Explanation: Choices A and B cannot be the best, because there can be a cost impact (or
time, risk etc.) of exceeding expectations or adding extras. Since a project should meet
requirements, choice C is best.
Page 52 of 80
Sample Questions
A. Inspection
B. Process analysis
C. Pareto chart
D. Fishbone diagram
Explanation: Choice A is done as part of quality control. Choices C and D are done as part
of quality planning or control (depending on how they are used). This leaves only choice B,
which must be the best answer, as process analysis IS a part of quality assurance. Watch out
for “double-negative” questions like this on the exam!
Page 53 of 80
Sample Questions
1. The MOST common cause of conflict on a project are schedule, project priorities, and:
A. Personalities.
B. Resources.
C. Cost.
D. Management
Explanation: Know the top four sources (schedule, project priorities, resources and technical
opinions), so you can answer questions such as this one. Don’t be fooled because
“personalities” is on the list. It is last.
2. What conflict resolution technique is a project manager using when he says , ‘ I cannot deal
with this issue now!”
A. Problem solving.
B. Forcing.
C. Withdrawal
D. Compromising.
Explanation: Delaying the issue is called withdrawal.
3. What does a resource histogram shows that a responsibility assignment matrix does not?
A. Time
B. Activity
C. Interrelationships
D. The person in charge of each activity.
Explanation: Time is shown on a schedule or bar chart. The responsibility assignment matrix
maps specific resources against the work packages from the WBS. On a resource Histogram,
the usage of resources is shown individually or by groups over time.
4. You have just been assigned as project manager for a large telecommunications project. This
one year project is about halfway done. The project team consists of five sellers and 20 of
your company’s employees. You want to understand who is responsible for doing what on
the project. Where would you find such information?
A. Responsibility assignment matrix
B. Resource histogram
C. Bar Chat
D. Project organization chat
Explanation: The responsibility assignment matrix maps, who will do the work. The
resource histogram (choice B) shows the number of resources used in each time period. In its
Page 54 of 80
Sample Questions
pure form, a bar chart (choice C) shows only activity and calendar date. An organizational
chart (choice D) shows who reports to whom.
5. During project planning in matrix organization, the project manager determines that
additional human resources are needed. From whom would he request these resources?
A. Project manager
B. Functional manager
C. Team
D. Project sponsor
Explanation: Did you forget that in a matrix organization the functional manager controls
the resources?
6. A project manager must publish a project schedule. Activities, start/end times and resources
are identified. What should the project manager do NEXT?
A. Distribute the project schedule according to the communication management plan.
B. Confirm the availability of the resource.
C. Refine the project management plan to reflect more accurate costing information.
D. Publish a bar chart illustrating the timeline.
Explanation: The project schedule remains preliminary until resource assignments are
confirmed.
7. During every project team meeting, the project manager asks each team member to describe
the work he or she is doing, and the project manager assigns new activities to team members.
The length of the meeting has increased because there are many different activities to assign.
This could be happening for all the following reasons. EXCEPT?
A. Lack of WBS
B. Lack of a responsibility assignment matrix
C. Lack of resource leveling
D. Lack of team involvement in project planning
Explanation: Resource leveling refers to the maintaining the same number of resources on
the project for each time period. Leveling has nothing to do with assigning activities or
managing meetings.
8. You are project manager leading a cross-functional project team in a weak matrix
environment none of project team members report to you functionally and you not have the
ability to directly reward their performance. The project is difficult involving tight date
constraints and challenging Quality standards. Which of the following types of project
management power will likely be the MOST effective in this circumstance?
A. Referent
B. Expert
Page 55 of 80
Sample Questions
C. Penalty
D. Formal
Explanation: Reward and expert are the best sources of power. Reward is not listed as a
choice.
9. A team member is not performing well on the project because she is inexperienced in system
development work. What is the BEST solution for the project manager?
A. Consult with functional manager to determine project completion incentives for the team
member.
B. Obtain a new source more skilled in development work.
C. Arrange for the team member to get training.
D. Allocate some of the project schedule reserve.
Explanation: The job of the project manager includes providing or obtaining project-specific
training for team members. This kind of training is a direct cost of the project.
10. A project manager has just found out that major subcontractor for project is consistently late
delivery work. The project team member responsible for this part of the project does not get
along with sub-contractor. To resolve the problem the project manager says, “You both will
have to give up something to solve this problem. What conflict resolution method is she
using?
A. Confrontation
B. Compromise
C. Smoothing
D. Communicating
Explanation: The act of both parties giving something defines compromise.
Page 56 of 80
Sample Questions
2. The work breakdown structure can be an effective aid for communication in which
situation(s)?
A. Internal within the project team
B. Internal within the organization
C. External with the customer
D. Internal & external to the project
Explanation: The work breakdown structure allows communication vertically and
horizontally within the organization as well as outside the project.
4. Communications are often enhanced when the sender _______ the receiver.
A. Speaks up to
B. Uses more physical movement when talking to
C. Talks slowly to
D. Shows concern for the perspective of
Explanation: Understanding the receiver’s perspective allows you to direct the
communication to meet his needs
Page 57 of 80
Sample Questions
6. A project manager has a problem with a team member’s performance. What is BEST form of
communication for addressing this problem?
A. Formal written communication
B. Formal verbal communication
C. Informal written communication
D. Informal verbal communication
Explanation: The best choice is D. If informal verbal communication does not solve the
problem, choice A is the next best choice. This does not mean that you do not keep records of
the problem, but this Question is asking about communication between two parties
Page 58 of 80
Sample Questions
10. A large, one- year telecommunication project is about halfway done when you take the place
of the previous project manager. The project involves three different sellers and a project
team of 30 people. You would like to see the project’s communications requirements and
what technology is being used to aid in project communications. Where will you find this
information?
A. The project management plan
B. The information distribution plan
C. The bar chart
D. The communication management plan
Explanation: Although the information is found as a sub-plan to the project management
plan (choice A), the communication management plan (choice D) is the best answer because
it directly answer the question.
Page 59 of 80
Sample Questions
4. You are finding it difficult to evaluate the exact cost of risks. You should evaluate on a :
A. Quantitative basis
Page 60 of 80
Sample Questions
B. Numerical basis
C. Qualitative basis
D. Econometric basis
Explanation: If you cannot determine an exact cost impact to the event, use qualitative
estimates such as Low, Medium, High, etc .
8. A project manager has just finished the risk response plan for a $ 387,000 engineering
project. Which of the following should be probably done NEXT?
A. Determine the overall risk rating of the project
B. Begin to analyze the risks that show up in the project drawings
C. Add work packages to the project work breakdown structure
Page 61 of 80
Sample Questions
9. A project manager asked various stakeholders to determine the probability and impact of a
number of risks. He then analyzed assumptions. He is about to move to the next step of risk
management. Based on this information, what has the project manager forgotten to do?
A. Evaluate trends in risk analysis
B. Identify triggers
C. Provide a standardized risk rating matrix
D. Create a fall back plan
Explanation: The activities of qualitative risk analysis are probability and impact definition,
assumptions testing and probability and impact matrix development.
10. A project manager has assembled the project team, identified 56 risks on the project,
determined what would trigger the risks, rated them on a risk rating matrix, tested their
assumptions and assessed the quality of the data used. The team is continuing to move
through the risk management process. What has the project manager forgotten to do?
A. Simulation
B. Risk mitigation
C. Overall risk ranking for the project
D. Involvement of other stakeholders
Explanation: The process they have used so far is fine, except the input of other stakeholders
is needed on order it identify more risks.
Page 62 of 80
Sample Questions
2. With a clear contract statement of work, a seller completes work as specified, but the buyer is
not pleased with the results. The contract is considered to be:
A. Null and void
B. Incomplete
C. Complete
D. Waived
Explanation: If the seller completes the work specified in the contract statement of work, the
contract is considered complete. That does not mean the same thing as contract closed.
Contract closure must still occur. However, in this situation the contract work is completed.
Tricky!
3. All of the following statements concerning bid documentation are incorrect EXCEPT?
A. Well-designed bid documents can simplify comparison of responses.
B. Bid documentation must be rigorous with no flexibility to allow consideration of seller
suggestions.
C. In general, bid documents should not include evaluation criteria.
D. Well-designed bid documents do not include a contract statement of work.
Explanation: Often the seller is required to inform the buyer of anything that is missing or
unclear in the bid documents (Choice B). It is in the buyer’s best interest to discover missing
items, since it will save the buyer money and trouble to correct the problem early. Bid
documents must contain terms and conditions and evaluation criteria (Choice C) as well as
all the work that is to be done, including the contract statement of work (Choice D). This is
so the seller can price the project and know what is most important to the buyer. Choice A is
an important point for the real world and is the best answer.
4. A project manager for the seller is told by her management that the project should do
whatever possible to be awarded incentive money. The primary objective of incentive clauses
in a contract is to:
Page 63 of 80
Sample Questions
5. All the following statements about change control are incorrect EXCEPT?
A. A fixed price contract will minimize the need for change control
B. Changes seldom provide real benefits to the project
C. Contracts should include procedures to accommodate changes
D. More detailed specifications eliminate the causes of changes
Explanation: Since there can be changes in any form of contract, choice A is not the best
answer. There are always good ideas (changes) that can add benefit to the project so choice B
cannot be the best answer. In choice D the word “eliminate” implies that changes will not
occur. As that is not true, this cannot be the best answer.
6. A routine audit of a cost reimbursable contract determines that overcharges are being made.
If the contract does not specify corrective action, the buyer should:
A. Continue to make project payments
B. Halts payments until the problem is corrected
C. Void the contract and start legal action to recover overpayment
D. Change the contract to require more frequent audits
Explanation: Notice that choice B is really saying “halt ALL payments”. Halting all
payments would be a breach of contract on the buyer’s part. Choice C is too severe and
cannot be done unilaterally. Choice D does not solve the problem presented. A choice that
said “halt payments on the disputed amount” would probably be the best answer, but it is not
offered. Therefore, the best answer is A.
Page 64 of 80
Sample Questions
8. A seller is working on a cost reimbursable (CR) contract when the buyer decides he would
like to expand the scope of services and change to a fixed price (FP) contract. All of the
following are the seller’s options EXCEPT?
A. Completing the original work on a cost reimbursable basis and then negotiating a fixed
price for the additional work
B. Completing the original work and rejecting the additional work
C. Negotiating a fixed price contract that includes all the work
D. Starting over with a new contract
Explanation: The seller does not have the choice to start over. The contract that exists is
binding. Both parties could agree to start over, but this is a drastic step.
Page 65 of 80
Sample Questions
3. Understanding how human resource requirements will be met and how staffing management
will be addressed is useful information for the Project Manager in developing the
Stakeholder Management Plan. This information might be found in the ______________, a
key Input in the Plan Stakeholder Management process.
A. Project Management Plan
B. Stakeholder Register
C. Communications Management Plan
D. Stakeholder Management Plan
4. During stakeholder analysis, PM and team may use different models to classify. The model
that helps to analyze the stakeholder’s ability to impose his or her will or power and
influence the need for immediate attention from the project team along with the legitimacy of
the stakeholder’s involvement is :
A. Power/Interest grid
B. RAM
C. Salience model
D. Stakeholder register.
Page 66 of 80
Sample Questions
7. Which of the following should you be most concerned about, while doing stakeholder
analysis?
A. Their interest in the project
B. Their influence on the project
C. Both A&B
D. Neither A nor B
8. Which is the best way to manage stakeholders who are low on power and interest?
A. Monitor them
B. No need to worry about them
C. Treat all stakeholders equal
D. Keep them informed
9. Which of the following is the tool to assess the current and desired level of engagement of a
stakeholder on a project?
A. Stakeholder register
B. Stakeholder management plan
C. Stakeholder engagement assessment matrix
D. Impact/power grid
Page 67 of 80
Sample Questions
10. Which of the following is an input to the plan stakeholder management process?
A. Stakeholder register
B. Stakeholder management plan
C. Stakeholder engagement assessment matrix
D. Impact/power grid
Page 68 of 80
Sample Questions
PMP Numerical
Page 69 of 80
Sample Questions
2. A project activity has been determined to have the following potential durations:
- Optimistic completion time of 12 days,
- Pessimistic completion time of 25 days
- Most likely time of 15 days.
What is the estimated activity duration using the weighted average technique?
What is range of estimate at 68% & 95% Confidence Interval?
3. The project starts Monday morning and has a 7-day work week.
- Task A (1 day long) is the predecessor to B (5 days), and C (4 days) and D (2 days)
- Task C is the predecessor to E, with a start-start relationship
- Task E is three days long
- Tasks B and E are predecessors to F (2 days long).
- Task D is also a predecessor to F, but with a finish-finish relationship
The Early Finish for the project is the end of the day on a…
a. Sunday
b. Monday
c. Tuesday
d. Wednesday
Page 70 of 80
Sample Questions
4.
5. There is a project to build a 5,000 square foot deck. The budget allows four crew hours for
each 100 sq. ft., at a cost of €100 per crew hour. The Planned Value to date is €10,000. The
work is 40% completed, at a cost of €9,000 to date.
6. Kathy wants to develop a theme park. The volume of exotic plants needed for the theme park is
large. Hence Kathy had to decide whether to set up an internal nursery and grow them or buy from
outside. Since these are exotic plants some of them might not grow in the weather condition and
might need special treatment.
• Growing internally would cost $60K, considering one time set up cost. Buying from outside
would cost about $40K.
• For each decision the weather condition (which is uncertain, and therefore represents a
‘chance node’) is to be considered.
• Growing her own plants: If weather conditions are favorable(70% chance) Kathy would
make a turnover of $80K while she makes only 50k turnover if weather is unfavorable
• Buy Plants from outside : If weather conditions are favorable(70% chance), Kathy would
make a turnover of 60K, while she makes only 40k turnover if weather is unfavorable
Page 71 of 80
Sample Questions
PMP Numerical
Response
1. Critical Path Method (CPM)
2. Solution
Tpert = 12 + 4*(15) + 25 = 16.16
Page 72 of 80
Sample Questions
6
S.D = (Tp – To) = 13/6 = 2.16
6
Lower Higher
68% Confidence
16.16 -2.16 = 14 16.16+2.16 =18.32
(1 Sigma)
95% Confidence 16.16+2 *(2.16)
16.16 -2 *(2.16) = 11.84
(2 sigma) =20.48
3. Solution
4. B
Page 73 of 80
Sample Questions
Page 74 of 80
Sample Questions
7. Solution
Page 75 of 80
Sample Questions
Page 76 of 80
Sample Questions
Page 77 of 80
Sample Questions
Page 78 of 80
Sample Questions
Page 79 of 80
Sample Questions
Page 80 of 80