The document outlines various technical specifications, probable causes of malfunctions, and operational details for the HRV AV-15 vehicle. It includes information on components such as the welding generator regulator, hydraulic circuits, and control mechanisms, as well as maintenance and operational guidelines. Additionally, it lists the types of switches and valves used in the system, along with their functions.

Uploaded by

hanmant123.com
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
192 views21 pages

HMT 1

The document outlines various technical specifications, probable causes of malfunctions, and operational details for the HRV AV-15 vehicle. It includes information on components such as the welding generator regulator, hydraulic circuits, and control mechanisms, as well as maintenance and operational guidelines. Additionally, it lists the types of switches and valves used in the system, along with their functions.

Uploaded by

hanmant123.com
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 21

HRV- AV 15

1. The rope winds on drum incorrectly in HRV AV-15, the probable causes are:-

(A) Broken or worn spring of pressing mechanism


(B) Spring lever pin cut
(C) Control cct pressure drop

2. In HRV AV-15, welding generator regulator is not working. what are the
probable causes: -?

(A) Transformer winding short


(B) Regulator adjustment wrong
(C) Transformer winding open
(D) Winch motor not working

3. The component in which power grain governor fitted in HRV AV-15 is :-

(A) Auto drain valve


(B) Steering servo pump
(C) Fuel injection pump
(D) Air compressor

4. In HRV AV-15 EM pneumatic valve provided for pump drive gear box is:-

(A) Z-18
(B) Z-19
(C) Z-20
(D) None of the above

5. Which type of control is given to engage the PTO drive of HRV AV-15 ?

(A) Electric
(B) Hydraulic
(C) Manual
(D) Electro pneumatic

6. Min speed of HRV AV-15: -

(A) 1.7 Kmph


(B) 3 kmph
(C) 5kmph
(D) 10kmph

7. How much time is required to fit the attachment of bulldozer equipment of


HRV AV-15?

(A) 1 to 1.5 hrs


(B) 3 hrs
(C) 20 minutes
(D) 1 hour

8. The gear pump of bulldozer equipment, in HRV AV-15 takes drive from:-

(A) Cam shaft of engine.


(B) Engine fly wheel.
(C) Front part of the engine crank shaft.
(d) Air blower shaft.

9. Magnetic filter is the main component of hyd system of HRV AV-15:-

(A) Crane
(B) Winch
(C) Aux winch
(D) Bulldozer equipment

10. In bulldozer HRV AV-15 max operating pressure required is


AV-15?

(A) 100 kg cm2


(B) 90 kg cm2
(C) 190 kg cm2
(D) None of these

11. Minimum speed of during operation of Bulldozer of HRV AV-15 is:-

(A) 1.7 kmph


(B) 3 km/ph
(C) 1.0 kmph
(D) 2.9 kmph

12. EM Pneumetic valve Z-17 is provided in HRV AV-15 for :-

(A) Engine off


(B) Engine RPM control additional device
(C) Veh clutch control additional device
(D) None of the above

13. Basic fuel consumption of Tatra HRV AV-15 is :-

(A) 110-130 ltrs/100km


(B) 50 ltrs/100km
(C) 60-70 ltrs/100km
(D) 40-50 ltrs/100km

14. In HRV AV-15 micro switch K-9 is use for :-

(A) Crane preselection


(B) Winch preselection
(C) Aux winch operating switch
(D) All of the above

15. In HRV AV-15 micro switch K-10 is use for: -

(A) Aux winch operation


(B) Crane preselection
(C) Winch preselection
(D) Main clutch disengagement
16. In HRV AV-15 push button A-11 is use for: -

(A) Switch of crane preselection


(B) Switch of crane winch preselection
(C) Aux winch operating switch
(D) Switch operation 0-1-2-3
17. In HRV AV-15 Electromagnetic DCVs Z- 02 work for:-

(A) Crane boom up


(B) Crane boom down
(C) Crane slewing (Left)
(D) Crane slewing (Right)

18. How many Z valve provided in HRV AV-15 :-

(A) 21
(B) 19
(C) 13
(D) None of these

19. Electromagnetic Pneumatic Valve Z-17 is provided in HRV AV-15 for: -

(A) Engine off


(B) Engine RPM control additional device
(C) Veh clutch control additional device
(D) None of the above

20. In HRV AV-15 EM pneumatic valve provided for pump drive gear box is: -

(A) Z-18
(B) Z-19
(C) Z-20
(D) None of the above

21. The causes of Crane Hydcyl not functioning of HRV AV-15 is due to:-

(A) Hyd pump N/W output low


(B) Hydcyl seal internally leaking
(C) Hyd fluid leaking from tank
(D) All of these

22. The proballe causes of dozer blade not functioning are:-

(A) Hyd pump N/W output low


(B) PRV spring tension weak nad adjustment wrong
(C) Dozzer flexible pipe leaking
(D) None og these

23. What are the probable causes, of cardan shaft too noisy even after lubrication: -

(A) Loose connection screw


(B) Worn cardan parts
(C) Excessive lubricated
(D) None of these

24. Which type of oil pump is fitted in lubrication system of HRV AV-15 :-

(A) Gear type


(B) Vane type
(C) Rotary type
(D) Crescent type

25. In HRV AV-15, selection crane or winder not possible rotation blocking eqpt out of order, the probable
causes are :-

(A) Failure in control elect circuit


(B) None of these
(C) Worn blocking eqpt eqpt parts
(D) Damaged sealing

26. How many out lets are provided in PTO drive in main gear box of AV-15 ?

(A) Three
(B) One only
(C) Two
(D) Four

27. Which type of control is given to engage the PTO drive of HRV AV-15 ?

(A) Electric
(B) Hydraulic
(C) Manual
(D) Electro pneumatic

28. The cutting angle of bulldozer blade of HRV AV-15:-

(A) 40 degree
(B) 50 degree
(C) 60 degree
(D) 70 degree

29. How much time is required to fit the attachment of bulldozer equipment of HRV AV-15?

(A) 1 to 1.5 hrs


(B) 3 hrs
(C) 20 minutes
(D) 1 hour

30. The gear pump of bulldozer equipment, in HRV AV-15 takes drive from:-

(A) Cam shaft of engine.


(B) Engine fly wheel.
(C) Front part of the engine crank shaft.
(d) Air blower shaft.

31. Magnetic filter is the main component of hyd system of HRV AV-15:-

(A) Crane
(B) Winch
(C) Aux winch
(D) Bulldozer equipment

32. The rope winds on drum incorrectly in HRV AV-15, the probable causes are :-
(A) Broken or worn spring of pressing mechanism
(B) Z 18 faulty
(C) Control cct pressure drop
(d) None of these

33. In HRV AV-15, welding generator regulator is not working. what are the probable causes: -

(A) Transformer winding short


(B) Regulator adjustment wrong
(C) None of these
(D) Winch motor not working

34. The component in which power grain governor fitted in HRV AV-15 is :-

(A) Auto drain valve


(B) Steering servo pump
(C) Fuel injection pump
(D) Air compressor

35. In HRV AV-15 Centrifugal oil filter valve opens at:-

(A) 160 kpa


(B) 190 kpa
(C) 90 kpa
(D) 60 kpa

36. In HRV AV-15 Electromagnetic DCVs Z 02 work for:-

(A) Crane boom up


(B) Crane boom down
(C) Crane slewing (Left)
(D) Crane slewing (Right)

37. In HRV AV-15 Micro switch A-11 is use for :-

(A) Switch of crane preselection


(B) Switch of crane winch preselection
(C) Aux winch operating switch
(D) Switch operation 0-1-2-3

38. In HRV AV-15 Limit switch K-10 is use for:-

(A) Aux winch operation


(B) Crane preselection
(C) Winch preselection
(D) Main clutch disengagement

39. Basic fuel consumption of tatra HRV AV-15 is :-

(A) 110-130 ltrs/100km


(B) 50 ltrs/100km
(C) 60-70 ltrs/100km
(D) 40-50 ltrs/100km
40. In HRV AV-15 Limit switch K-9 is use for :-

(A) Crane preselection


(B) Winch preselection
(C) Aux winch operating switch

41. Max operating pressure of hydraulic circuit no 1&2 of AV-15 is

(A) 195 kg/cm2


(B) 105 kg/cm2
(C) 210 kg/cm2
(D) 107 kg/cm2

42. Fuel tank capacity of AV-15 is :-

(A) 2x210 ltrs


(B) 2x230 ltrs
(C) 2x110 ltrs
(D) 2x165 ltrs

43. Arresting brake of winch is out of order in HRV AV-15. what may be the probable causes: -

(A) Loose fixing screws


(B) Control cct pressure drop
(C) Worn lamellas
(D) Failure inside brake

44. In HRV AV-15,maximum loading capacity of crane on support is:-

(A) 10,000 kg
(B) 15,000 kg
(C) 17,000 kg
(D) 20,000 kg

45. How many oil coolers are provided in lubrication system of HRV AV-15 ?

(A) Five
(B) Three
(C) One
(D) Two

46. How many Electromagnetic DCVs are provided in HRV AV-15 :-

(A) Ten
(B) Three
(C) Thirteen
(D) Thirty

47. HRV AV-15 main winch is not operating. What are the probable causes?

(A) Winch gear box not engaging


(B) Pneumatic valve leaking
(C) Hydraulic cyl leaking
(D) Solenoid not operating
48. Air blower of HRV AV-15 takes drive from: -

(A) Oil pump


(B) Rear timing gear timing through fluid coupling
(C) Fuel injection pump
(D) Front timing gear accessory

49. Air compressor of AV -15 takes drive from: -

(A) Accessory
(B) Alternator
(C) FIP cam shaft
(D) None of above

50. Which type of oil pump is fitted in hydraulic circuit of crane and winch HRV AV-15?

(A) Double gear pump


(B) Two piston pump
(C) Vane type rotary pump
(D) Two axial regulation pump

51. Which type of lubrication system is provided in HRV AV-15 :-

(A) Wet sump force feed


(B) Petroil
(C) Splash
(D) Force feed dry sump, recirculating

52. In which sub assy, emergency boom lifting valve is fitted of HRV AV-15?

(a) Driver cabin


(B) PTO drive
(C) Cranes swiveling base
(D) Auxiliary winch

53. In HRV AV-15 switch A-1 to A-29 are called: -

(A) Micro switch


(B) Limit switch
(C) Circuit breaker
(D) EM DCVs

54. How many micro switch provided in HRV AV-15.

(A) 28
(B) 29
(C) 30
(D) 21

55. In HRV AV-15 switch K-1 to K19 are called: -

(A) Circuit breaker


(B) EM DCVs
(C) Micro switch
(D) Limit switch

56. In HRV AV 15 crane rope may be pulled out by: -


(a) Axillary winch
(b) Main winch
(c) Secondary winch
(d) None of these

57. HRV AV-15 Engagement of claw clutch of dozer pump should be done when engine is:

(a) High RPM


(b) Stopped
(c) High speed
(d) None of these

58. In HRV AV-15 aerial for radio communication operated by :-


(a) Electrically
(b) Pneumatically
(c) Manually
(d) Hydraulically

59. In HRV AV-15 veh unwinding of auxiliary winch can be done through: -

(a) Pneumatically
(b) Electrically
(c) Manually
(d) None of these

60. In HRV AV-15 veh winding of auxiliary winch can be done through: -

(a) Manually
(b) Pneumatically
(c) Hydraulically
(d) Electrically

61. HRV AV-15 Hydraulic circuit No: 1 pressure will be maintained through: -

(a) PV-6
(b) PV-4
(c) PV-1
(d) PV-5

62. HRV AV-15 Hydraulic circuit No: 3 pressure will be maintained through: -

(a) PV-5
(b) PV-6
(c) PV-1
(d) None of these

63. HRV AV-15 Hydraulic circuit No: 4 pressure will be maintained through: -

(a) PV-5
(b) PV-6
(c) PV-1
(d) PV-2
64. In HRV AV-15 Z-05 EMHV Provided for: -

(a) Telescope retraction


(b) Both A&B
(c) Telescopic extending
(d) Crane left

65. In HRV AV-15 Z-06 EMHV Provided for: -

(a) Hook up
(b) Crane left
(c) Telescopic extending
(d) None of these

66. In HRV AV-15 Z-07 EMHV Provided for: -

(a) Crane left


(b) Crane pre-selection
(c) Aux winch rope wind on
(d) Radio set aerial folding

67. In HRV AV-15 Z-08 EMHV Provided for: -

(a) Crane right


(b) Radio set aerial folding
(c) PTO engage
(d) Aux winch rope wind on

68. In HRV AV-15 Z-09 EMHV Provided for: -

(a) Boom up
(b) Recovery winch wind off
(c) Hook up
(d) Radio set aerial folding

69. HRV AV-15veh K-2 limit switch provided for: -

(a) Load on tyrescutt off front


(b) Crane rope tractive force 15 ton
(c) Load on tyrescutt off rear
(d) Telescopic extreme

70. HRV AV-15veh K-3 limit switch provided for: -

(a) Telescopic extreme


(b) Telescopic extreme
(c) Crane rope tractive force 15 tn
(d) Boom horizontal posn 0 deg

71. HRV AV-15veh K-4 limit switch provided for: -

(a) Cabin protection 10 deg top


(b) Crane Pre-selection
(c) Crane rope tractive force 15 tn
(d) Telescopic extreme

72. HRV AV-15veh K-16 limit switch provided for: -

(a) Crane rope tractive force 15 ton


(b) Telescopic extreme
(c) Crane Pre-selection
(d) None of these

73. In HRV AV-15 Hydraulic pumps are get drive from: -

(a) PTO gear box


(b) Engine
(c) Gear box
(d) PTO gear box

74. In HRV AV-15 PV-3 Pressure control valve located in: -

(a) Oil tank


(b) Power pack
(c) Inside boom
(d) Crane base

75. HRV AV-15 Hydraulic circuit No: 2 pressure will be maintained through: -

(a) PV-7
(b) PV-6
(c) PV-4
(d) PV-1

76. HRV AV-15veh K-6 limit switch provided for: -

(a) crane rope tractive force


(b) Hook left
(c) Crane base left
(d) Crane base right

77. HRV AV-15veh K-11 limit switch provided for: -

(a) Boom posn 55 deg


(b) Crane Pre-selection
(c) Crane rope tractive force 15 tn
(d) Telescopic extreme

78. HRV AV-15veh K-1 limit switch provided for: -

(a) Telescopic ext


(b) Crane base left
(c) Hook left
(d) None of these
79. HRV AV-15veh K-19 limit switch provided for: -

(a) Crane rope tractive force 15 tn


(b) Winding out aux winch rope
(c) Hook left
(d) None of these

80. HRV AV-15veh K-9 limit switch provided for: -

(a) Load on tyrescutt off rear


(b) telescopic extreme
(c) None of these
(d) Crane Pre-selection

81. HRV AV-15 veh K-10 limit switch provided for: -

(a) Winch pre-selection


(b) telescopic extreme
(c) Crane Pre-selection
(d) Crane base left

82. HRV AV-15veh K-1 limit switch located at :-

(a) Inside boom


(b) crane rope tractive force
(c) Crane rope winding
(d) Load on tyres

83. HRV AV-15 veh K-2 limit switch located at :-

(a) Crane base


(b) Top of boom
(c) Boom junction
(d) Rotary distributor

84. HRV AV-15veh K-4 limit switch located at :-


(a) Boom junction
(b) Aux winch
(c) Rotary distributor
(d) None of these

85. HRV AV-15veh K-16 limit switch located at :-

(a) Top of boom


(b) Boom junction
(c) Top of boom
(d) Blocking mechanism

86. HRV AV-15veh K-19 limit switch located at :-


(a) Top of boom
(b) Crane base
(c) Aux winch
(d) None of these

87. HRV AV-15veh K-10 limit switch located at :-


(a) telescopic extreme
(b) Rotary distributor
(c) Blocking mechanism
88. PV-6 & PV-7 Pressure control valve located in

(a) Hyd power pack


(b) Gear box
(c) Transfer case
(d) Oil tank

89. In HRV AV-15 Z-11 EMHV Provided for :-

(a) Crane pre-selection


(b) Telescope retraction
(c) Crane pre-selection
(d) Hook down

90. In HRV AV-15 Z-01 EMHV Provided for :-

(a) Hook down


(b) Boom up
(c) Hook up
(d) None of these

91. In HRV AV-15 Z-02 EMHV Provided for :-

(a) Hook up
(b) Telescope retraction
(c) Boom down
(d) Telescopic extending

92. In HRV AV-15 Z-03 EMHV Provided for :-

(a) Boom down


(b) Crane left
(c) Boom up
(d) Hook up

93. In HRV AV-15 Z-04 EMHV Provided for :-

(a) Telescopic extending


(b) Hook down
(c) Telescope retraction
(d) Crane pre-selection

94. In HRV AV-15 Z-10 EMHV Provided for :-

(a) Telescopic extending


(b) Aux winch rope wind on
(c) Recovery rope wind in
(d) PTO engage
95. In HRV AV-15 Z-12 EMHV Provided for :-

(a) Winch pre-selection


(b) Crane right
(c) Boom up
(d) Radio set aerial folding

96. In HRV AV-15 Z-13 EMHV Provided for :-

(a) Aux winch rope wind on


(b) Telescopic extending
(c) Engine RPM increased
(d) Crane right
97. In HRV AV-15 Z- 15 EMPV Provided for: -

(a) Boom up
(b) PTO engage
(c) Radio set aerial folding
(d) Hook up

98. In HRV AV-15 Z-17 EMPV Provided for: -

(a) Crane right


(b) Engine RPM increased
(c) Boom up
(d) Telescopic extending

99. Technician ‘A’ says that Hydraulic fluid capacity of bulldozer is 110ltr, Technician ‘B’ says 220ltr &
Technician ‘C’ says 150ltrs. Who is correct? (110 ltr)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

100. Technician ‘A’ says working pressure of No 5 circuit is 200kgcm2, Technician ‘B’ says 150 kgcm 2
& Technician ‘C’ says 100 kgcm2. Who is correct? (100 Kg cm2).
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

101. Technician ‘A’ says that control circuit pressure is in HRV AV 15 is 25+5 kgcm2, Technician ‘B’ says
35+5 kgcm2 & Technician ‘C’ says 30+5 kgcm2. Who is correct?
(30+ 5kgcm2)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

102. Technician ‘A’ says that Hydraulic fluid capacity of crane sys is 400 ltr, Technician ‘B’ says 350 ltr
& Technician ‘C’ says 300 ltr. Who is correct? (300 ltr)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

103. Technician ‘A’ says the cutting of bulldozer blade is 50 deg, Technician ‘B’ says 45 deg& Technician
‘C’ says 55 deg. Who is correct (50 deg)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

104. Technician ‘A’ says that four drain plugs are provided in Hydraulic tank of bulldozer equipment,
Technician ‘B’ says Two hydraulic tank and Technician ‘C’ says Three. Who is correct?
( Three)
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

105. Technician ‘A’ says that Magnetic filter provided in crane, Technician ‘B’ says for Bulldozer eqpt &
Technician ‘C’ says for Genr eqpt. Who is correct (Bulldozer Eqpt)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

106. Technician ‘A’ says that basic fuel consumption of HRV AV 15 is 50ltr/100km, Technician ‘B’ says
80ltr/100km & Technician ‘C’ says 75ltr/155km. Who is correct?
(50 ltr/ 100 km)
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

107. Technician ‘A’ says that K-9 limiter switch use for Winch Pre selection, Technician ‘B’ says for
Crane pre selection & Technician ‘C says for PTO. Who is correct?
( crane pre selection )
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

108. Minimum speed of the veh of HRV AV-15 is:-

(A) 1.7 kmph (B) 2.8 kmph

(C) 1.0 kmph (D) 2.9 kmph

109. Technician ‘A’ says that there are three (0,1,2) position of crane master switch, Technician ‘B’ says
four (0,1,2,3) & Technician ‘C’ says two (0,1). Who is correct?
Four (0,1,2,3,)
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

110. Technician ‘A’ says that direction control valve Z -01 use for crane boom up, Technician ‘B’ says for
boom down & Technician ‘C’ says for hook down. Who is correct?
(Crane boom up )
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

111. Technician ‘A’ says that there are 9 Electromagnetic Hyd valve provided in HRV AV 15, Technician
‘B’ says 21 & Technician ‘C’ says 13. Who is correct? (13)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

112. Technician ‘A’ says that Electromagnetic pneumatic valve Z-17 is provided for engine RPM,
Technician ‘B’ says main clutch engage & disengage & Technician ‘C’ says PTO engage. Who is correct?
(Engine rpm control)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these
113. Technician ‘A’ says that Electromagnetic valve provided for PTO clutch is Z18, Technician ‘B’ says
Z-17 & Technician ‘C’ says Z-20. Who is correct? (None of these)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

114. Technician ‘A’ says that there are three axial pump fitted in HRV AV -15, Technician ‘B’ says two &
Technician ‘C’ says four then who is correct? (Two)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

115. Technician ‘A’says that No 1 & No 2 Hydraulic circuit pressure is 180+10kgcm, Technician ‘B’ says
170+5kgcm & Technician ‘C’ says 190+5kgcm. Who is correct?
(190 +- 5 kgcm )
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

116. Technician ‘A’ says that aux winch not work due to Electromagnetic valve No Z-13 defective,
Technician ‘B’ says Z-16 & Technician ‘C’ says Z-14. Who is correct?
(Z-13)
(i) Technician ‘A’ (ii) Technician ‘B’
(iii) Technician ‘C’ (iv) None of these

117. Technician ‘A’ says that Centrifugal oil filter valve open at 1.2 kgcm 2, Technician ‘B’ says 1.5 kgcm2
& Technician ‘C’ says 1.6 kgcm2. Who is correct? (1.6 kgcm2)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

118. Technician ‘A’ says that the limit switch K-9,K-10 are located on the blocking mechanism, Technician
‘B’ says on the rotary distributer & Technician ‘C’ says on the winch gear box. Who is correct?(Rotary distributer)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iv) None of these

119. In HRV AV 15 Technician ‘A’ says that in limit switch K-19, is located on the Hyd tank, Technician
‘B’ says on gear box & Technician ‘C’ says on the winch drum. Who is correct? (None of these)

(i) Technician ‘A’ (ii) Technician ‘B’


(iii) Technician ‘C’ (iii) None of these

120. In HRV AV-15 Centrifugal oil filter PRV opens at .


(a) 1.6 kgcm2 (b) 1.5 kgcm2
(c) 1.4 kgcm2 (d) 1.2 kgcm2

121. In HRV AV-15, Engine valve arrangement is


(a) Over head (b) Side Head
(c) Both (d) None of these

122. Main winch rope length of HRV AV -15 is .


(a) 200 Mtrs (b) 150 Mtrs
(c) 300 Mtrs (d) 320 Mtrs

123. In HRV AV-15 crane over all swing angle is

(a) -50 to 550 (b) 00 to 550


(c) 00 to 600 (d) Non of the above

124. Tech A says in HRV AV 15, PV 6 & PV 7 combined function in main winch circuit. Tech B says in
No 1 Hyd circuit and Tech C says in No 2 Hyd circuit. Who is correct?
(a) Tech A (b) Tech B
(c) Tech C (d) None of above
125. The hydraulic circuit of HRV AV-15 in whichdouble gear type pump is fitted?
(a) Bulldozer equipment (b) Auxiliary winch
(c) Crane boom telescope (d) None of the above

126.. How many drain plugs are provided in hyd tank of bulldozer eqpt of HRV AV-15?

(A) Three
(B) One
(C) Two
(D) Five

127. Tech A says in AV-15 veh, No-8 EMPV is used for T/case low speed, Tech B says T/case high speed
and Tech C says gear box low speed. Who is correct?
(a) Tech A (b) Tech B
(c) Tech C (d) All are correct

128. In HRV AV-15 the gear pump of bulldozer equipment takes drive from .
(a) Cam shaft gear (b) crank shaft front end
(c) FIP gear (d) Idle gear

129. In HRV AV-15 how many position of Rotary switch of Generator control panel.
(a) 0-1-2-3 (b) 0-1-2-3-4
(c) 1-2-3 (d) None of these
Short Questions HRV AV -15

Q.1. Write down the special feature of HRV AV-15?

Q.2. Explain PTO removing procedure of HRV AV-15?

Q.3. Explain the power flow of pump drive gear box of HRV AV-15?

Q.4. Explain the function of generator drive gear box A HRV AV -15 veh has
reported to your wksp with the defect of welding and cutting device not working.
After investigation it is found that rotary switch is defective in an AV-15.

Q.5. Explain emergency boom lowering procedure of HRV AV-15?

Q.6. Explain emergency Hook lowering procedure of HRV AV-15?

Q.7. Explain emergency telescope retraction procedure of HRV AV-15?

Q.8. Write down the pre selection procedure of crane/winch of HRV AV-15?

Q.9. A HRV AV-15 veh reported to your wksp with the defect of crane rope
broken. How will you replace the crane rope? Explain briefly?

Q.10. Explain working procedure of rotating base with recovery winch of HRV
AV-15?

Q.11. Write down the oil changing procedure for Hydraulic system of HRV AV -
15?

Q.12. Write down the working of hydraulic No 4 circuit (Pilot circuit) of HRV AV-
15?
Q.13. A veh report to your wksp in defect of crane rope broken. How will be
replace the crane rope Explain briefly?

Q.14. Write down the brake adjusting procedure of main winch of HRV AV-15?

Q.15. Write down the brake adjusting procedure of crane of HRV AV-15?

Q.16. Write down the brake adjusting procedure of aux winch of HRV AV-15?

Q.17. Explain emergency crane base rotation of HRV AV-15?

Q.18. Explain the function of PV-6 & PV-7 of HRV AV-15?

Q.19. Explain adjusting procedure of back pressure valve of HRV AV-15?

Q.20. Write down the location & function of Z valve fitted in HRV AV-15?

Q.21. Explain the operating procedure of welding generator of HRV AV-15?

Q.22. During operation of HRV AV-15 if you need assistance of welding/cutting,


how will you operate the welding machine.

Q.23. Explain recovery winch pre-tensioning mechanism of HRV AV-15?

Q.24. Explain the function of bulldozer equipment fitted in HRV AV-15 vehicle?
Q.25. Write shorts about hydraulic motor & hydraulic cylinder fitted in HRV AV-
15?

Long Questions HRV AV-15

Q.1. A Tatra HRV AV-15 vehicle has reported to your wksp with the defect of
pump drive gear box is not engaging with PTO. Explain power flow from the
engine to pump drive gear box & generator drive gear box with neat line
diagram?

Q.2. Explain the function of hydraulic circuit No -1 of HRV AV-15 with neat &
clean diagram?

Q.3. A HRV AV-15 veh has reported to your wksp with the defect of Boom not
operating & winch not work, after investigation it was found that hydraulic
circuit No 1 faulty. Explain the causes & remedies action with diagram wherever
necessary.

Q.4. What are the main components of hydraulic circuit No 3 and 5 of HRV
AV-15? Explain the function of any one circuit briefly?

Q.5. A HRV AV-15. veh has reported to your wkps with the defect of Z- valves
(Direction control valve) not functioning properly. Explain the function of Z- valve.

Q.6. A HRV AV-15 veh has reported to your wksp with the defect of bulldozer
equipment not work. Write down the most probable cause of the defect. Neatly
explaining with circuit diagram?

Q.7. Write down location and function of safety switch (limiting switch) of HRV
AV-15?

Q.8. How will you operate the crane and winch of HRV AV-15 during
emergency?

Q.9. Write down the brake adjusting procedure of main winch, hook & aux
winch of HRV AV-15?

Q.10. Explain the location and function of PV-1, PV-2,PV-3,PV-4,PV-5,PV-6 &


PV-7 of HRV AV-15?

Q.11. Explain the function of hydraulic circuit No -2 of HRV AV-15 with neat &
clean diagram?

Q.12. Explain the function of hydraulic circuit No -4 of HRV AV-15 with neat &
clean diagram?

Q.13. Explain emergency boom lowering & crane base rotation procedure of
HRV AV-15?

Q.14. Explain emergency telescope retraction & hook lowering procedure of


HRV AV-15?

Q.15. A HRV AV-15 reported to your wksp with the defect of main winch rope
winding not properly & damage, how will you adjusting & what are the causes &
remedies?