Turfing
Turfing
MEDIAN OF EMBANKMENT
Laying Process :
1. The area to be turfed shall have been previously constructed to
the required slope / cross-section or else it shall be prepared to
2: 1 slope and checked by template for continuity & exactness of
slope.
2. The soil on the area to be turfed shall be loosed upto a depth
of 25 mm and made free of all undesirable foreign material.
3. Where required fertilizer / manure shall be spread at a uniform
rate by discing or any other method as approved by the
Engineer.
4. The prepared bed shall be moistened to the loosened depth,
if not already sufficiently moist.
5. The sods shall be cut in strips of not less than 250mm x 300mm
in size.
6. The sods of the specified grass shall be placed thereon, within
24 Hrs. of cutting.
7. Every strip shall be tamped lightly with suitable wooden or
metal tempers so as to eliminate air pockets and to press it into
the underlaying soil.
8. On side slopes steeper than 2 (H) to 1 (V), the laying of sods
shall be started from bottom upwards.
9. After the sods have been laid in position, the surface shall be
cleaned of loose sod, excess soil and other foreign materials.
10. Top dressing shall be done by scattering a thin layer of top soil
and sprinkling the surface with water.
11. Proper watering and maintenance of the surface shall be
done to ensure proper and uniform growth of sods for at least
four weeks.