California High-Speed Train ATC System
California High-Speed Train ATC System
TECHNICAL MEMORANDUM
TM 3.3.1
Note; Signatures apply for the latest technical memorandum revision as noted above.
Prepared by
for the California High-Speed Rail Authority
California High-Speed Train Project Automatic Train Control: Concept of System, R0
System level reviews are required for all technical memoranda. Technical Leads for each
subsystem are responsible for completing the reviews in a timely manner and identifying
appropriate senior staff to perform the review. Exemption to the system level technical and
integration review by any subsystem must be approved by the Engineering Manager.
Note; Signatures apply for the technical memorandum revision corresponding to revision number in header and as noted on cover.
Page i
California High-Speed Train Project Automatic Train Control: Concept of System, R0
Page iii
California High-Speed Train Project Automatic Train Control: Concept of System, R0
TABLE OF CONTENTS
ABSTRACT .................................................................................................................... 1
Page ii
California High-Speed Train Project Automatic Train Control: Concept of System, R0
Page iv
California High-Speed Train Project Automatic Train Control: Concept of System, R0
ABSTRACT
The California High Speed Train Project (CHSTP) requires the deployment of an Automatic Train
Control (ATC) system that provides;
• Automatic Train Protection (ATP) functions of train detection, collision and overspeed
prevention, broken rail detection, interlocking control, hazard detection, train separation,
and work zone protection
• Automatic Train Operation (ATO) information and control functions
• Automatic Train Supervision (ATS) functions to provide central supervisors with status
information and the ability to control train operations
• Positive Train Control (PTC) as mandated by the Rail Safety Improvement Act of 2008.
This Technical Memorandum describes the functions within each group and identifies how those
functional groups will be met by the train control design, specification, and implementation
phases.
The prime requirement for the CHSTP ATC system that has been identified in common with all
systems is that the technology must already exist as part of an operating system with proven
experience worldwide on at least one high speed passenger railway.
It is recognized that there are regulatory requirements from authorities such as the FRA, FCC,
and CPUC which must be met and in meeting those requirements it might mandate changes to
the proven system(s) in order to achieve certification from such regulatory bodies.
The purposes of this Technical Memorandum are to;
• Define the concept of the ATC system
• Describe the subsystems of the ATC system and the purpose of each.
• Identify the portions of the ATC system that will interface with and therefore impact the
infrastructure, including the right of way, design.
• Identify the portions of the ATC system that will interface with and therefore impact the
rolling stock design.
• Identify other portions of the ATC system that interface with and therefore impact the
facilities and other subsystems of CHSTP.
• Identify the particular aspects of candidate ATC system that may be impacted by
regulatory requirements from the FRA, FCC, CPUC, and other authorities and
administrations.
Page 1
California High-Speed Train Project Automatic Train Control: Concept of System, R0
1.0 INTRODUCTION
This technical memo addresses the concepts of the Automatic Train Control (ATC) system for the
California High-Speed Train Project (CHSTP), describes the various subsystems, and addresses
design considerations for the specification of the ATC and interfacing systems for procurement.
CHSTP ATC will use existing, proven high-speed train control technology such as that used in
Europe and Asia, or as adapted from proven U.S. ATC equipment, if practical. It is recognized
that these proven high speed rail ATC systems do not meet all FRA regulations and that
adaptation or equivalency must be demonstrated in order to achieve certification. The CHSTP
will follow the Federal Railroad Administration’s Rule of Particular Applicability process to achieve
certification.
Page 2
California High-Speed Train Project Automatic Train Control: Concept of System, R0
• Japanese coded track circuit technology deployed on the Shinkansen and Shinkansen
derivative lines in Japan and other countries including Taiwan.
ERTMS and coded track circuit-based systems have significant differences; ERTMS detects train
position using track circuits but conveys safety-critical information to trains in the form of
movement authorities by means of a data radio network. Coded track circuit-based systems
detect train position using track circuits but also send data to trains through the track circuit
(running rails), similar to the way conventional cab speed signals systems work. Newer digital
track circuits provide higher data rates than conventional cab signaling circuits, and can send
messages to trains in real time that convey much more information than the traditional maximum
speed limit.
Page 3
California High-Speed Train Project Automatic Train Control: Concept of System, R0
As described above, the CHSTP is using TSIs to help define the project regulatory framework.
For ATC, the TSIs do not specify the functional or performance requirements even at a system
level. Therefore, this document defines ATC functional and performance requirements to the
level needed to prepare bid specifications.
This Technical Memorandum describes the functions within the ATC and its ATP, ATO, and ATS
functional sets, describes the locations where the equipment will be installed and the interfaces
the equipment will have with other subsystems, and identifies how these functional subsystem
requirements will be developed and met by the train control design, specification, and
implementation phases.
The prime requirement for the CHSTP ATC system is that the technology must already exist as
part of an operating system with proven experience worldwide on at least one high speed
passenger railway.
Any candidate technology must also meet or be modified to meet the regulatory requirements
from governing authorities including FRA, FCC, and CPUC.
Page 4
California High-Speed Train Project Automatic Train Control: Concept of System, R0
The functional set responsible for the safety-critical functions including those of
interlocking, train detection, signal aspects, broken rail detection, hazard detectors (if
implemented as part of the ATC system), and movement authorities (including speed limit
and cab signal commands if appropriate) that are sent to the train and acted upon by the
on-board train control to enforce safe limits. The ATP functional set includes the
enforcement of the safety-critical functions. PTC functions are part of ATP.
The functional set responsible for the automatic operation of throttle and brake commands
to move trains between stations and other stopping locations (including those required due
to the proximity of other trains and signal status) within the constraints imposed by the
ATP functional set. Provides dwell timing at stations and the control or prompting of the
opening and closing of train doors.
The functional set within the automatic train control system that is responsible for the
centralized supervision and control of train movements; the ATS monitors trains, adjusts
the performance of individual trains to maintain schedules, and provides data to adjust
service to minimize inconveniences otherwise caused by irregularities. ATS also provides
automatic and manual route setting at interlockings and the identification and tracking of
trains, the display of alarms and events, and logging and storage of event data.
These functional sets of requirements are analyzed in Section 3 of this Technical Memorandum.
The ATC system consists of equipment and software onboard the train, along the track, in
wayside equipment rooms, and in central and possibly regional control facilities. The subsystems
consist of;
• On-Board
Page 5
California High-Speed Train Project Automatic Train Control: Concept of System, R0
• Wayside
Equipment located in housings along the right of way including station equipment rooms,
train control equipment houses, and signal equipment cases and cabinets. Wayside
equipment also includes the track circuits and associated hardware, switch machines,
wayside signals, and transponders that are mounted on or about the track itself. The train
control equipment located along the main line is part of the wayside equipment
subsystem.
• Data Communications
The data communications network including dedicated network elements and components
and data radio antennas and towers associated with the train control system. There is a
portion of the data communications subsystem on-board the trains in the form of radios,
antennas, and data networks. The on-board data communications equipment can also be
considered as part of the on-board subsystem.
• Office
Equipment delivering ATS functions located in the Operations Control Center (OCC), at
Regional Control Centers (RCC), and other designated facilities including station control
rooms. Yard control towers will contain an office element for supervision and control of
yard signal equipment but it is likely to be a separate set of equipment from the primary
office subsystem (ATS) although it will be interfaced to that subsystem.
• Field Portable
Equipment for use by Employees in Charge (EIC) of maintenance and construction work
in the field and used to manage track and other field systems access. It is used to
communicate digitally and wirelessly with the office and on-board ATC subsystems to
manage and control train movements through an active work zone.
• Yard
Equipment distributed throughout the yards and maintenance facilities for the operation of
switches, signals, and enforcement devices to control train movements within Yard
territory.
Page 6
California High-Speed Train Project Automatic Train Control: Concept of System, R0
The train control system will also provide safe enforcement of other functions including ATC
responses to hazard event detectors and sensors (provided by other subsystems) including;
• Earthquake
• Excess wind speed
• High water levels
• Excessive rainfall
• Underpass bridge strikes
•
Landslide and rock falls
• Intrusion at trackside and in tunnels
• Intrusion from overhead bridges and at tunnel portals
• Intrusion at stations
•
Dragging equipment
•
Rail breaks
Page 7
California High-Speed Train Project Automatic Train Control: Concept of System, R0
Although the majority of the listed hazard event sensors will be specified by other disciplines,
many will be interfaced to at least one of the subsystems of the ATC, and the ATC will invoke the
system response. In some cases, the ATS functional set will log the event and to display an
event and/or an alarm to the operators for their further action; in other cases the ATP system will
directly cause the train to enforce a braking activation and possibly stop trains in an emergency.
Each sensor interface must be identified and the response of the ATC system to each interface
agreed with Operations and other disciplines.
The ATC wayside equipment will include double-rail track circuits for train and broken rail
detection. Track circuits are an approved means of detecting broken rails and this approach is
acceptable to the FRA. A break in the rail must cause a false occupancy in a track circuit which
in turn will result in a restrictive command being given to an approaching train. For track circuits
to reliably detect broken rails and for the ATC system to protect trains, the ATC system must
normally allow only one train in a track circuit at any one time.
Page 8
California High-Speed Train Project Automatic Train Control: Concept of System, R0
accurately measure speed. The enforcement of the Movement Authority limits enables
the on-board system to provide the required PTC protections.
The onboard ATO functional set will regulate train performance when selected.
Commands received from the ATS functional set may also provide for pacing trains at a
lower speed than their maximum speed or increasing speeds from the pacing speed
called for by the normal schedule. Under no circumstances can these ATO functions
allow the train to operate faster or further than the safety-critical limits determined by the
PTC functions of the ATP functional set.
The on-board ATC subsystem will interface with the rolling stock subsystems to support
the ATP, ATO, and ATS functional sets.
In addition to interfaces required for the ATC system functions, additional train interfaces
will provide remote monitoring capabilities of rolling stock subsystems. Remote
monitoring allows for early diagnosis of trouble. Monitoring can be done using the office
subsystem as part of the ATS functional set. Alarms and event indications can be
displayed at the Operations Control center and the Regional Control Centers, or at ATS
remote workstations at other locations.
On-board passenger information systems, including audible and visual announcements
of real-time performance and other information to the passengers may be provided from
the Office subsystem through the ATC data communications subsystem or by an
independent data communications subsystem.
The on-board ATP functional set equipment will interface to wireless or above-rail
inductive antennas that receive Movement Authority commands from wayside ATP
functional set equipment. A data radio subsystem will provide data transmission between
the train and wayside.
• Wayside – consists of mainly vital equipment located in housings along the right of way
including station equipment rooms, train control equipment houses, and signal equipment
cases and cabinets. The equipment includes track circuits, switch machines, wayside
signals, interlocking equipment, and transponders (or balises), much of which is
considered to be conventional signal system equipment. This equipment includes ATP
electronics that is either integral to or interfaces with the track circuit and interlocking
equipment and to other sensors including intrusion, seismic, and other detectors that will
allow the train control system to react to an event and bring the train to a safe speed if
necessary. The ATP processors obtain track circuit occupancy status, interlocking route
status, and sensor device status in order to output messages to the trains that define the
safe limits (including distance to go and target speeds) for train movement. Equipment
will be housed in a distributed fashion along the rail line to provide continuous coverage
including along aerial structures, through tunnels, in yards, and in stations.
Interlocking functions including route setting, route locking, approach locking, and
sectional release will be performed by wayside microprocessor interlocking equipment.
The wayside subsystem will be linked by the data communication subsystem to allow
supervision and remote control from the Operations Control Center (OCC) and the
Regional Control centers (RCCs).
Site requirements for ATC equipment at the wayside are described in Technical
Memorandum TM 3.3.2; Automatic Train Control (ATC) Site Requirements.
Page 9
California High-Speed Train Project Automatic Train Control: Concept of System, R0
The DCS will carry both vital (ATP) and non-vital (ATO, ATS and management)
information. The DCS itself does not have to be a vital subsystem. Coding and other
techniques in the other ATC subsystems ensure that the data received is of sufficient
integrity and currency that it can be treated as accurate for vital applications. ATP
equipment will reject any data for a vital function that cannot be validated.
Many DCS elements, including electronics, fiber cables, radio equipment, and antennas
will be on CHSTP property. However, the diversity that may be needed to deliver the
specified communication link availability may require the use of leased communications
lines provided by a third party as backup to the primary links. Some radio antennas may
also be located off CHSTP property where propagation considerations indicate a benefit.
The candidate ATC system ERTMS uses 900 MHz GSM-R radio to communicate
movement authorities and safety-critical data between train and wayside. These specific
bands are not available within the U.S. It is essential to identify one or more suitable
bands with sufficient bandwidth and reserve them through licensing and/or other means
for exclusive CHSTP use to ensure reliable system operation.
• Office –The ATC Office subsystem supports the majority of the ATS functional sets. It
consists of a centralized or a distributed computer control system with dispatcher
workstations that provides the overall CHSTP train operation management functions
including remote routing and supervision functions. It includes announcements of events
including critical alarms and a logging capacity for all events. It generates many system
performance reports. Many ATS functions supported by the Office subsystem are
automated, including setting of routes at interlockings, regulation of train movements in
accordance with the schedule, movement planning, and the recovery of the service from
minor interruptions and failures.
At any time, dispatchers can take manual control of route setting and schedule regulation
functions from their ATS workstations in accordance with the rail management plans and
procedures. Recovery from major interruptions and failures will likely require manual
intervention of the dispatchers. The general arrangement of control positions by function
and responsibility, including responses during failures and incidents, will be described in
the Concept of Operations document.
The Office subsystem architecture can be centralized or distributed to provide reliable
computing power and the required workstations that allow supervisors to dispatch the
services, monitor subsystem performances, and intervene to manually supersede
automated processes in the event of incident and emergency. The territory controlled by
each workstation can be adjusted by an appropriate official such as the Chief Dispatcher
to adjust to workload demands as they fluctuate. As workstations can be in centralized or
distributed facilities, or at remote locations, the ATC system can support a flexible
approach to the overall supervision of the CHSTP rail operations.
The Office subsystem communicates with wayside locations, remote workstations, trains,
other ATC elements, and sensors including intrusion, through the data communications
subsystem.
The Office subsystem will provide workstations primarily within the Operations Control
Center (OCC) and the Regional Control Centers (RCCs).
• Field Portable – Equipment for use by Employees in Charge (EIC) of wayside work;
it will be used to manage track and other wayside systems access. EIC portables
will communicate digitally and wirelessly with the ATS and with on-board ATC
subsystems to control train movements through a work zone. Trains may only
operate through established work zones with the agreement of the EIC who can
use the field portable equipment to enforce reduced speeds and track blocks. Although
generally maintenance work on the tracks will be done outside of revenue hours, EIC
portables will protect all
Page 10
California High-Speed Train Project Automatic Train Control: Concept of System, R0
Control of the Yard signaling systems will be from a panel or workstation located in a
control room (or tower) within the yard facility.
Train movements between yards and the main line will be routed through transition tracks
where trains will transition between ATC and Yard signal system modes of operation.
3.2.1 ERTMS
The European Rail Traffic Management System is a candidate technology for the CHSTP ATC
system. It is specified to three levels of functionality;
• Level 1 is a simple fill-in where signal aspects are conveyed to trains by intermittent loops
• Level 2 uses radio to continuously convey track circuit occupancy and other data to
trains. Levels 1 and 2 use track circuits for train detection.
• Level 3 is the most technologically sophisticated system. It does not require track
Level 3 does not use track circuits; instead the on-board ATC equipment will determine train
position with much higher resolution than can be provided by track circuits. A Level 3 ERTMS
system will approach moving block capability. The term moving block describes a system in
which following trains are separated by the braking distance of the following train plus a safety
buffer distance. This separation is typically much closer than that supported by a track circuit (or
fixed block) signaling system.
To date several ERTMS Levels 1 and 2 systems have been implemented and have actual
revenue experience. This is true for both conventional speed railroads and for high speed lines
approaching 200 MPH. ERTMS systems are also being developed and employed outside the
EC. In December 2009, the Chinese high speed line (Wuhan to Guangzhou High Speed
Railway) opened, with a top speed of 245 mph. It is equipped with a Chinese Train Control
Page 11
California High-Speed Train Project Automatic Train Control: Concept of System, R0
System (CTCS) Level 3 train control system. However, the CTCS Level 3 ATC is similar to the
ETCS Level 2 system, using track circuits and radio; it is not similar to the ERTMS Level 3
system.
No ERTMS Level 3 systems have been deployed yet, and the ERTMS Level 3 equipment is not
yet commercially available and viable. Even if and when ERTMS Level 3 is proven in service, for
CHSTP, a significant ERTM Level 3 technical and regulatory issue concerns the use of track
circuits to detect broken rails. Currently all high speed rail operations globally use track circuits
both for basic train detection and for broken rail detection. Since ERTMS Level 3 does not
include track circuits, it cannot fulfill the CHSTP broken rail detection requirement without some
added provision.
Because 49CFR236 requires a proven means of detecting possible broken rails, CHSTP will
specify track circuits. This makes ERTMS Level 2 a contender for CHSTP ATC for the following
reasons;
• ERTMS Level 2 uses track circuits as a primary train location subsystem
• It has been widely deployed on high speed rail routes in Europe and other countries and
is therefore a proven system
• It has been deployed on systems with similar maximum speeds and headways as CHST
design goals
•
There are multiple suppliers of hardware and software; these suppliers have subsidiaries
in the United States
ERTMS includes both the train control data radio and operations voice radio between the wayside
and trains. The EIRENE (radio) component of ERTMS operates in the GSM band that has been
dedicated throughout Europe for railway operations (GSM-R (Railways)); it carries both voice and
train control data circuits. There is no GSM-R band dedicated to railroad operation in the United
States. If ERTMS is to be deployed on CHSTP and appropriate radio frequency channels cannot
be secured from the FCC, ERTMS will require adaptation with respect to data and voice radio
communications.
Page 12
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The following table addresses key operational issues with respect to the ATC system definition.
The following table operating modes and sub-modes are planned for operation of CHSTP trains on main line and in yards and depots;
ATO OR
MODE OF MAX TRAIN
MANUAL ENFORCED BY NOTES
OPERATION SPEED
OPERATION
This is the normal operating mode on the main line which includes
automatic operation of Rolling Stock propulsion and brakes by the ATO
subsystem within ATC.
Requires an action by the Train Operator to select ATO mode. ATP system
Line Speed or as must determine that other factors are correctly set before train can move in
defined by Limit ATO mode (Movement Authority is being received by on-board ATP
ATC ATO ATP
of Movement subsystem, doors are closed and locked, etc.)
Authority
Rolling Stock subsystem requirement must include the incorporation of the
vigilance/alerter device to ensure The Train Operator is in the cab and alert.
Rolling stock vigilance/alerter device is required in all modes of operation
including ATC, RM, Bypass Yard, etc.
This is the operating mode on the main line where movements and speeds
are fully supervised and enforced by the ATC system but the propulsion
and brakes are commanded by the Train Operator
Line Speed or as
Vigilance/alerter function to be provided by Rolling Stock; see note above.
defined by Limit
ATC Manual ATC
of Movement
CHSTP ATC may include a Call-On mode to allow the train to pass a red
Authority
signal under certain controlled conditions. If so, this will be a sub-mode of
ATC/Manual. To enter it, the ATC system will send the train a Call-On
command. ATP will enforce a speed limit of 20 MPH.
Page 13
California High-Speed Train Project Automatic Train Control; Concept of System, R0
ATO OR
MODE OF MAX TRAIN
MANUAL ENFORCED BY NOTES
OPERATION SPEED
OPERATION
A degraded Mode.
In this mode the On-board ATP subsystem will limit train speed to 20 MPH
maximum. Train Operator will work in accordance with procedure and
observe the wayside signals for authority to move.
FRA requirement
of Restricted Movement authorities, including speed commands are not received in this
Restricted Speed. mode.
Manual
ATC on-board
Manual Restricted is 20 In the event of receipt of a speed command or Movement Authority from
subsystem
(RM) MPH or lower, as the wayside while in RM mode, the on-board ATC will automatically switch
required to stop to ATC Manual mode.
within half of
range of vision. RM mode addresses short term ATC failures such as movement through a
failed switch (under procedure) or through a failed track circuit (which can
include a broken rail) outside an interlocking. Movement through an
interlocking with a failed track circuit can be done under Call-On mode (see
above).
The Train Operator will select the transition from ATC Manual mode to yard
and vice versa when a train is stationary on a transition track when entering
or departing a Yard.
Yard signal enforcement is required however the safety criteria used in the
design will not be as restrictive as for the main line ATC system.
ATC
Trains approaching a shop track from the Yard will require a Train Operator
ATC will enforce yard acknowledgement before being allowed to enter a shop track.
Yard or Depot N/A Yard speed limit maximum speed limit
not exceeding 20 mph Yard mode can treat a shop entrance as an end of track and further
per 49CFR236 Subpart movement forward can be in RM mode. This will be considered as part of
I. an Operations Hazard and Risk analysis.
Page 14
California High-Speed Train Project Automatic Train Control; Concept of System, R0
ATO OR
MODE OF MAX TRAIN
MANUAL ENFORCED BY NOTES
OPERATION SPEED
OPERATION
Rolling Stock propulsion A degraded mode.
and possibly braking
subsystems. This mode is used if the on-board ATC fails.
This is a mode NOT Will require a separate Bypass switch that will be sealed normally in the
enforced by ATC. In ATC (not Bypassed) position.
this mode, ATC is in
Bypass mode and is not No secondary enforcement system is required other than a maximum
connected to the rolling speed supervised by the Rolling Stock propulsion subsystem.
stock equipment.
FRA limited
speed is 59 MPH Safe operation of trains
Bypass N/A
per 49CFR236 is maintained by home
subpart I. signal indications, by
rules and procedures,
by regular training and
refresh.
Page 15
California High-Speed Train Project Automatic Train Control; Concept of System, R0
3.3.2.1 Background
In ATO mode, an on-board ATO subsystem that controls the operation of rolling stock propulsion
and brakes, to start a train at a station, accelerate it, regulate its speed to below the speed limit,
move the train between scheduled station stops, and brake the train to a precision stop at the
next station, all subject to Movement Authority limits set by the ATP subsystem. ATO mode is
extensively used in transit systems worldwide, but has had limited use on main line and high
speed lines. ATO is now starting to be deployed on passenger main line tracks including high
speed operations outside the U.S.
The Taiwan High Speed Train (HST) system uses an ATO mode called Programmed Station
Stop Control (PSSC). PSSC slows and accurately stops trains at stations; it does not start trains
from stations or provide speed maintaining between stations. The Train Operator controls the
train acceleration and speed for those phases of a trip. When the Train Operator activates PSSC
on the approach to a station, the on-board ATO subsystem takes control of the train propulsion
and brakes, and using track transponders to determine distance to go, automatically slows and
stops the train in accordance with a programmed speed/distance profile.
ATO station stopping, already in service on the Taiwan HST, overcomes a major difficulty with
operating high speed trains - the inconsistent ability of Train Operators to judge stopping
distances. For a station stop from high speed, braking must start well before the station is in
sight; wayside markers (which might otherwise be used) have little or no value when approached
and passed at high speed.
ATO mode operation will be incorporated into the ATC system design for all phases of station-to-
station running on the main lines and for exit and entry to yards including;
• Acceleration from station stops
• Cruising at safe speeds determined automatically by the schedule regulation function
the
of ATS subsystem, or manually set by console dispatchers through the ATS
workstations, or as determined by an Energy Management function.
Page 16
California High-Speed Train Project Automatic Train Control; Concept of System, R0
• Stopping and restarting for ATC enforced stops defined by movement authorities
• Exit from yard transition tracks within yards to the main line
• Entry to yard transition tracks from the main line
• Station stopping
• Energy management
ATO mode requirements will be incorporated in the interfaces with rolling stock and other
impacted subsystems.
Further consideration must be given during the design phase to the following;
• An important human factors issue is to keep the Train Operator engaged during extended
runs in ATO mode. Considerations include the Train Operator’s interactions with a
vigilance device, the train and the on-board ATC system; and procedures that require
manual driving at intervals to make sure the Train Operator can correctly operate the
train when needed. This is a special concern to the FRA, as noted in the preamble to
49CFR236 Subpart I.
• Are sub-modes required such as full ATO mode and Programmed Station Stop Only
mode?
• Prerequisites to enter ATO mode and start the train, including door interlocks and Train
Operator cab console controls that interface to the on-board ATC equipment. Can ATO
mode be entered or canceled on the fly?
• What are ATO mode requirements for safe and reliable operations during reduced
adhesion conditions because of autumn leaves on the line and light or heavy rain?
• Is ATO required only on the main lines or is it a low speed ATO mode required in the
yards and/or the train wash tracks?
• Operational restrictions and procedures may govern ATO mode use; for example;
– When maintenance personnel are working on or about the track during traffic
– If there are special restrictions on the Peninsula Corridor.
Detailed procedures will be written during the construction and test period. The decision to apply
ATO and its sub-modes is subject to further discussion and will be a decision for the Operator.
3.3.4 Interlockings
Interlocking functions are part of the ATP functional set. Interlocking functions will be provided by
microprocessor interlocking equipment. Use of conventional signal relays will be minimized.
Interlocking requirements will include route clearing, approach locking, detector locking, route
locking, traffic locking, indication locking, time release, sectional release, and other functions.
Page 17
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Approach locking will be provided as the intermediate interlockings between stations will normally
be fleeted. Interlocking equipment will be interfaced with other ATP equipment to send
movement authorities to trains that will ensure safe movement through interlockings.
Wayside signals will only be located at interlockings. The wayside signals will only indicate the
status of routes at their entrances. These wayside signals will not be the primary indication of
route status; the primary indication will be the Train Operator’s display in the cab.
A failure with similar impact on train operations is a broken rail, which will be detected by a track
circuit. Track circuit failures will be treated by the ATC system as a broken rail event until proven
otherwise.
Normal ATC operation will not depend on use of wayside signals. The ATP subsystem design
will provide some visual signals and signs at the wayside for fallback operations. Such signals
are not of practical use when operating at high speeds (e.g., greater than 150 MPH). However,
they will be usable in degraded operating modes when the on-board ATC system that generates
cab displays of movement authorities is not available.
The CHSTP ATC design presently plans wayside signals at the following locations;
• At the entrance to interlocking routes (home
signals)
• In Yards
Page 18
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The prime use for mainline signals is to support safe train operation when the primary on-board or
wayside ATC subsystems is not available and when movement authorities cannot be received
and enforced by the on-board ATC subsystem.
Home signals will be provided on main lines only at the entrance to interlocking routes.
Intermediate signals will not be provided. At high speeds, signals will not be visible in a useful
way to the Train Operator, so the Train Operator must follow the cab signal indications or operate
the train in ATO mode. During failures of the primary on-board or wayside ATC system, the
maximum train speed will be limited to 59 mph, the limit in 49236CFR subpart I, maximum speed
when operating with failed PTC system. In addition, under present rules a train with an ATC
failure that occurs while the train is between interlockings must be operated at Restricted Speed
until it passes a wayside signal that indicates that there is no broken rail in the signal block
ahead.
As noted above, ATP subsystem design criteria will require main line home signals at the
entrance to interlockings and signals to control mainline access from refuge tracks. A headway
requirement to be supported by wayside signals will not be specified.
The ATP subsystem design criteria will specify the type of signal and supporting structure. Dwarf
signals minimize installation cost and reduce life cycle maintenance cost due to easier access for
inspection and repair. The final decision on signal type will depend upon the agreed maximum
speed when operating in degraded mode. 49CFR23 Subpart I specifies a speed of 59 mph or
less for passenger trains operating in degraded mode without PTC functions, although the
CHSTP may petition for a higher speed under the Rule of Particular Applicability that will be
required from the FRA to begin revenue service.
A risk analysis will evaluate factors related to train movement in the event of relevant ATC system
failures. The analysis will consider maximum speeds allowable, signal sighting distances and the
need to enforce the signals or not. If wayside signals will not be enforced, the sighting distance
for each signal will be critical. In that case, high signals may be required, especially on grades
and curves. Approach signals to interlockings may also be required.
Extensive backup signal systems are undesirable in a number of ways;
• With high availability of the prime ATC, the backup system will get only occasional use;
Operations personnel will need refresher training to stay current. This will impact their
availability for normal operations.
•
Added maintenance and regular test will be required for backup wayside and on-board (if
provided) equipment.
• Added cost and technical complexity of the overall ATC system; benefits are yet to be
fully evaluated but current assumptions are that they will be very limited.
• Backup signaling must be tied into the prime ATC system; failures of the backup can
impact normal ATC availability and reliability. In any event, more equipment means lower
overall reliability and an increased level of maintenance activity.
The present design is that speed enforcement in degraded mode will be provided by a speed
governor function in the propulsion subsystem. This governor will be activated by the ATC cutout
switch in the operating cab. If the train speed exceeds the defined maximum (e.g., 59 MPH) then
the propulsion subsystem will cut power to the motors and an audible and visual alarm will sound
in the cab.
The ATC system procurement specification will specify high availability normal operating modes
so that CHSTP can provide dependable, on-time service. Considering the excellent availability,
of HST service worldwide, CHSTP should rarely experience degraded mode operations.
Information from Shinkansen systems experience is that the fallback systems are used sparingly
and operating staff have little experience of their use.
Page 19
California High-Speed Train Project Automatic Train Control; Concept of System, R0
If the fallback system is complex and equipment-intense, this will reduce overall reliability due to
the increase in hardware. This could also reduce availability as fallback system equipment
failures can impact the availability of the prime ATC system under certain circumstances.
Page 20
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Alternatives to utility feeds are being considered, including dedicated signal power feeds from
adjacent ATC sites that have utility power feeds, drops from the OCS, solar panels, and wind
turbines. In each case, the sources will be supplemented with local batteries.
Power supplies for wayside ATC equipment is addressed in Technical Memorandum 3.3.3; Train
Control Wayside Location Power Supply Options.
vailability considerations may require that Office subsystem core equipment including
communications and database servers be located in the OCC, Regional Centers, and possibly
other sites; with options for cold, warm, and hot standby of the backup systems. The purpose is
to ensure that even if a major incident that knocks out the OCC (earthquake, sabotage/terrorist
action, major fire, etc.), centralized Supervision and Dispatching can continue with little or no
interruption to train operations.
Current planning has identified that dispatching of the peninsula corridor will require a regional
center to handle CHSTP and Caltrain services between San Jose and San Francisco. This
Regional center would be staffed 24/7 and could be considered a location that could assume
supervision and control of the full CHSTP network during a major incident.
In emergencies, the control of interlockings can be taken from a Regional Center or a station
control room.
A further level of degraded operation of an interlocking can use the local control panel connected
to the nearby ATC house, in the station control room or the adjacent station. Although ATC local
control facilities will be specified in the stations, the reliability/availability of the communications
subsystem makes the loss of control from the ATS highly unlikely.
Consideration will also be given to a form of field-fallback mode for the remote interlockings in
which they will revert to normal routes being called and fleeted in the event of a loss of
communications with the ATS. This fleeted fallback mode can be overridden from a local control
panel if it is necessary to operate the intermediate interlocking with ATS communications down.
The local control panel in the interlocking control house will allow local control in emergencies
and for maintenance testing needs.
For control of Yard movements, each yard will have a local tower with local control panels or
workstations where a Yard Dispatcher can route trains within the Yard and shops. Electronic
handover of trains between the main lines and the Yard tracks will be accomplished via an
interface between the mainline ATS system and the Yard ATS workstations. See the next section
on Yard signaling.
Page 21
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 22
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Each hazard detection type will be evaluated for the level of risk each hazard can pose to CHSTP
operation; the interface to the ATC system; and the required ATC system response. ATC
system responses can include;
• Automatically change from ATO mode to Manual-ATP mode. (Note that if the ATO
function uses a “hands off” approach, this will apply the service brakes until the Engineer
takes the controller).
• Stop the train immediately with a service brake
• Stop the train immediately with an emergency brake
• Block an affected section of track. The on-board ATC equipment for each nearby train
determines the level of brake needed to avoid entering the blocked track or to stop the
train if it is already entering or in the affected track section.
For track intrusions at stations, the choice is between automatic sensors of intruding passengers
vs. customer/staff operated alarms.
If a hazard detector is connected directly to the ATC system and a train response is forced, the
hazard detector comes under FRA regulation. If the detector is interfaced to the ATS to generate
and alarm at OCC, it is not.
Consideration needs to be given to the response types required for different levels of intrusion.
The EMT will further consider a need for Dragging Equipment Detectors (DED). If not necessary
on the CHSTP tracks themselves, certain DEDs may be required on approach tracks used by
freight or other passenger trains (e.g. Caltrain, Amtrak, and Metrolink) which may occasionally
run on CHSTP tracks. The reason to place DEDs at approaches is to protect the CHSTP tracks
and any track mounted equipment from damage by occasional users. High load detectors to
protect the overhead contact system from freight trains may also be needed.
Where there are physical track connections to other railroad operator’s tracks, the ATC system
will require a function that prevents unauthorized trains, including freight, from being routed onto
CHSTP tracks even on shared corridors.
Page 23
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The CHSTP will also address and comply with Federal Communications Commission (FCC)
licensing requirements for transmitters that include voice and data radios and transponder
antennas, including registration of antenna towers where necessary with the Federal Aviation
Administration (FAA) where CHSTP runs close to airports.
3.4.1 General
• The ATC system specification must provide functional requirements and performance
thresholds. It must be flexible and not mandate particular systems, devices and
methods.
• ATC system interfaces with other systems as well as with the infrastructure and services
must be clearly defined, especially those across contractual boundaries.
• The ATC system specification must preclude experimental devices, prototypes, and
technology or equipment not mature, accurate, or reliable for the HST environment.
The ATC system specification must preclude a contractor from proposing a system which
incorporates immature elements.
The location of the equipment in which certain ATC functions reside depends to some extent on
the architecture of each ATC Supplier. To the extent possible, the ATC system specification will
allow flexibility to the ATC supplier to propose the most cost-effective solution that provides the
required overall ATC system functionality, performance, safety, availability, and reliability.
Page 24
California High-Speed Train Project Automatic Train Control; Concept of System, R0
On-board ATP speed and position sensors must be proven products and must be applied,
combined, and processed so the on-board ATP equipment’s estimate of speed and position is
adequately accurate to ensure train safety. This may require diverse means of obtaining and
processing speed and position data.
Although rolling stock propulsion or brake subsystem tachometers may be used by the ATC
system for non-vital functions, the primary safety-critical function of determination of train position
and speed will use sensors provided and installed by the ATC system supplier.
Page 25
California High-Speed Train Project Automatic Train Control; Concept of System, R0
propulsion and braking subsystems. The signal system supplier will provide dedicated
tachometers which will be installed in locations provided by the rolling stock supplier, as
defined in a detailed interface definition.
• Wayside Transponders; Transponders, where deployed, will be mounted between the
running rails; each one provides a set of fixed or variable data to the train when a
transponder interrogator mounted under the train passes over the transponder. The on-
board ATP equipment uses the data received from the transponder to correct any
accumulating positioning error in the on-board ATP subsystem. The error is generally
due to slip and slide between the wheels and the rails. The on-board ATP subsystem
continuously assesses the worst case for error accumulation and takes account of it in
enforcing Movement Authority limits. Transponders are called balises in the ERTMS
system specifications. The Eurobalise works reliably at 200+ mph to ensure that the
required amount of data capable of being held and transmitted by the balise can be
received by the train.
• Other devices
o GPS is being used to help determine location by some PTC systems, in conjunction
with tachometers. The use of GPS as a prime component of position determination
in a vital signal system will be challenging. There are limits on GPS signal
availability, for example when a train is operating through tunnels or in city areas with
tall buildings that can block satellite reception.
o Inertial navigation systems, although proven in aerospace applications, have little
experience on railroads. Such devices incrementally sum accelerations in the three
axes to determine velocity, distance, and direction moved. They are subject to errors
from train suspension effects and accelerations caused by discontinuities in the track.
o One supplier has developed a laser optical sensor to measure distance traveled and
actual speed with high accuracy. Although tested in a limited fashion on main line
locomotives, the devices have been placed in revenue service on a transit application
with a maximum speed of 50 MPH. Such devices are considered to be experimental
and not fully mature in the railway environment. Any device using sensitive
electronics and optics is likely to have reliability problems operating in the high shock
and vibration and dirty environment around the truck and underside of a train. No
optical device has been placed in service at high speeds.
On-board ATP equipment can determine speed from some of the same devices, as described
above. Tachometers, inertial devices, and GPS can determine speed very accurately when used
in combination.
Position determination using GPS would likely be in combination with tachometers and other on-
board devices. Some development will be required however for a supplier to demonstrate in the
system safety analysis that the specified criteria for reliability, availability, and safety can be met
by the incorporation of GPS and other integrated devices. GPS receivers will likely be used to
determine time for the system to ensure that safety-critical data received from the wayside and
central office is current.
Page 26
California High-Speed Train Project Automatic Train Control; Concept of System, R0
• The fixed data can simply be a unique location identification which the train ATP
equipment compares to its database. The ATP equipment uses the data to correct the
accumulated error in its calculation of its position.
• The fixed location identification data provides an absolute confirmation of the train’s
position. The on-board ATP equipment can use this as a diverse confirmation of train
position. It can provide a positive confirmation of position if the train is operated under
procedure through a switch with unknown status during failures. This is preferred to a
Train Operator data input confirmation, as it enhances safety during failure conditions.
These diverse data uses help the ATC system achieve the required safety level.
• The fixed data can include speed limits which are transmitted to the on-board ATP
equipment. However, the present design intention is that speed limit data will be in the
on-board database and transponders will not upload this information.
• Variable data can include the locations of trains and status of switches and routes in front
of the train.
An ATC system with transponder-only data transmission to trains can only provide intermittent
ATP commands or Movement Authorities. This type of ATC system has performance and
functional constraints when compared to an ATC system with continuous communication of
Movement Authority data. The CHSTP ATC system will be a continuous communication system,
and will receive Movement Authority data either via a radio link (such as with ERTMS) from
wayside equipment or via a digitally encoded track circuit transmission using the track circuits and
running rails (e.g., TVM430, Shinkansen, etc.).
The ATC system design plans to use transponders for either radio or coded track circuit
transmission, to provide the position error correction function for the on-board speed and location
ATP subsystem.
The CHSTP Systems team will coordinate between the ATC, communications, rolling stock, and
operations personnel to discuss the equipment required and to provide in the rolling stock design
for;
• physical space requirements
• mounting provisions
• cables and cableways to connect the equipment
• termination panels
• power and ventilation needs
• other considerations including non-metallic panels around radio and GPS antennas
Page 27
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 28
California High-Speed Train Project Automatic Train Control; Concept of System, R0
standard systems will be considered. This will be done with the communications group working
closely with the ATC group.
3.5 INTERFACES
The ATC system will have interfaces to the following subsystems.
3.5.2 Communications
Interfaces between the ATC system and the Communications system are extensive. If
an ERTMS train control system is selected, data and voice radio communications will be
integral with the overall ATC subsystem.
Page 29
California High-Speed Train Project Automatic Train Control; Concept of System, R0
3.5.4 OCS
It is anticipated that the ATC system may be required to implement two functions;
• On-board commands to the Rolling Stock equipment to isolate between section gaps as
the train traverses the gap. This can be driven by a database function where the section
gaps are identified in the on-board database
• Prevention of trains entering sections of the line where the OCS has been de-energized.
This will require an interface between the OCS energized indication and the ATC system.
This could be done at the OCC level with an interface between ATS and SCADA, or at a
local level. Modified movement authorities would be transmitted to the on-board ATC
and a stop enforced.
3.5.5 Track
The details of the track layout including switch configurations, gradient, curvature, etc. must be
included in the safety-critical ATC database. There will also be physical interfaces between the
switch machines and the switches themselves, between the track and ATC transponders where
the latter must be securely fixed to the track and maintained within strict tolerances, and cable
bonds to the track for track circuit and traction power supply continuity.
In the Yards, derails and other devices used for stop signal enforcement must also be fixed to the
rails requiring an interface definition.
3.5.6 Infrastructure
The ATC system interfaces with infrastructure for installation of equipment houses, cases,
signals, and other elements along the right of way, and to comply with clearance requirements
and access to the various ATC facilities. Basic footprint, equipment size, and access needs have
been provided to the infrastructure group.
Special considerations have been given to tunnel portals for the need to house ATC equipment in
buildings and other structures at these locations.
Page 30
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 31
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 32
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The overall ATC system must incorporate the functional areas of Automatic Train Protection
(ATP), Automatic Train Supervision (ATS), and Automatic Train Operation (ATO). These three
functional areas of the ATC can be briefly defined as;
• ATP – Automatic Train Protection – The functional set responsible for the safety-critical
functions including those of interlocking, train detection, signal aspects, broken rail
protection, hazard detectors (if implemented as part of the ATC system), and movement
authorities (including speed limit and cab signal commands if appropriate) that are sent to
the train and acted upon by the on-board train control to enforce safe limits. The ATP
functional set includes the enforcement of the safety-critical functions. PTC functions are
part of ATP.
• ATO – Automatic Train Operation – The functional set responsible for the automatic
operation of throttle and brake commands to move trains between stations and other
stopping locations (including those required due to the proximity of other trains and signal
status) within the constraints imposed by the ATP functional set. Provides dwell timing at
stations and the control or prompting of the opening and closing of train doors.
• ATS – Automatic Train Supervision – The functional set within the automatic train control
system that is responsible for the centralized supervision and control of train movements;
the ATS monitors trains, adjusts the performance of individual trains to maintain
schedules, and provides data to adjust service to minimize inconveniences otherwise
caused by irregularities. ATS also provides automatic route setting at interlockings and
the identification and tracking of trains, the display of alarms and events, and logging and
storage of event data.
In consideration of the requirements of the signaling related sections of the Code of Federal
Regulations (CFR) to provide a proven means of detecting possible broken rails, CHSTP will
specify track circuits. This makes the European led radio based train control system; ERTMS
Level 2 a strong contender for the train control technology for the following reasons;
• ERTMS Level 2 uses track circuits as a primary train location subsystem
• It has been widely deployed on high speed rail routes in Europe and other countries and
is therefore an in-service proven system
• It has been deployed on systems with similar maximum speeds and headways as
CHSTP design goals
Page 33
California High-Speed Train Project Automatic Train Control; Concept of System, R0
• There are multiple suppliers of hardware and software; these suppliers have subsidiaries
in the United States
The definition of an ERTMS system includes the train control data and operations voice radio
communication between the wayside and the trains. The EIRENE (radio) component of ERTMS
operates in the GSM bandwidth that has been dedicated throughout Europe for railway
operations (GSM-R (Railways)) and carries both voice and train control data circuits. There is no
GSM-R frequency band dedicated to railroad operation in the United States. If an ERTMS-type
system is to be deployed on CHSTP and channels in the appropriate frequencies cannot be
secured from the FCC, the system will require adaptation with respect to data and voice radio
communications.
Other proven ATC systems that possibly meet the high speed experience criteria include the
TVM430 coded track circuit based system (originally developed by CSEE, now a division of
Ansaldo) and related products that are based on coded track circuits, and Japanese coded track
circuit technology deployed on the Shinkansen and Shinkansen derivative lines in Japan and
other countries including Taiwan.
ERTMS and coded track circuit type systems have significant differences; ERTMS detects train
position using track circuits but conveys safety-critical information to trains in the form of
movement authorities by means of a data radio network. coded track circuit type systems detect
train position using track circuits but also send data to trains through the track circuit (running
rails) similar in concept to the way in which conventional cab speed signals systems have worked
for many years. The latest digital track circuits allow for much higher data rates (than
conventional cab signaling circuits) allowing messages to be sent to trains in real time and
convey much more information than the traditional maximum speed limit.
To take advantage of the two general types of ATC system (coded track circuit and radio network
based) with high speed rail proven experience, the design criteria will address an ATC system
specification that focuses on function and performance and allows coded track circuit or radio
based systems to be proposed.
This Technical Memorandum describes the functions within each of the ATC subsystems; ATP,
ATO, and ATS; and identifies how these functional subsystem requirements will be developed
and met by the train control design, specification, and implementation phases.
The prime requirement for the train control system to be used on the CHSTP system is that the
technology must already exist as part of an operating system with proven experience worldwide
on at least one high speed passenger railway.
Any candidate technology must also meet or be modified to meet the regulatory requirements
from authorities including FRA, FCC, and CPUC.
Absolute Block - A section of track on which a train is not permitted to enter while it is occupied by
another train.
Automatic Train Control; (ATC) The collective name for the train control subsystems that typically
comprise the Automatic Train Protection, the Automatic Train Operation, and
Automatic Train Supervision sets of functions that govern train operations on the
main lines.
Page 34
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Automatic Train Control Bypass; A state in which the ATC system is bypassed under failure
conditions that allows the train to be operated manually at speeds that are
mandated by operating procedures.
Automatic Train Control Main Line Territory; Territory equipped with ATC wayside equipment with
full ATP functionality.
Automatic Train Control Yard Territory; Territory equipped with ATC wayside equipment in the
Yard areas.
Automatic Train Operation; (ATO); A mode of operation for onboard train ATC equipment used
to move the train to the next station under ATP supervision.
Automatic Train Protection; Those functions within the ATC that ensure safe train separation,
preclude overspeed operation, and preclude operation outside of safe limits (e.g.
over an improperly set switch).
Automatic Train Supervision; (ATS) Those functions within ATC that are for train dispatching
and allow the monitoring and controlling (both manual and automated) of
operations and traffic on the railroad.
Dwarf Signal A low wayside signal with minimal preview as opposed to a high signal that is
used to provide adequate preview of the aspect displayed to high speed trains.
GSM-R; The radio version of the Global System for Mobile communications (originally from
Groupe Spécial Mobile) used on railroads for control system in Europe and
possibly to be adapted for CHSTP
Guaranteed Emergency Brake Rate; The minimum emergency brake rate achieved under the
range of environmental conditions and brake equipment failure modes which can
normally be anticipated to exist on the CHSTP system
Headway; The time between buses, trains, or other transit vehicles at a given point. For
example, a 15 - minute headway means that one train arrives every 15 minutes.
Home Signal – A fixed signal (wayside or virtual) at the entrance of a route to govern trains
entering or using that route.
Impedance Bond; An electrical device located between the rails consisting of a coil with a center
tap used to bypass insulated joints in order to prevent track circuit energy from
bypassing the insulated joint while allowing the traction return current to bypass
the insulated joint. The center tap can also be used to provide a connection from
the rails to the static wire and/or traction power facilities for the traction return
current.
Insulated Joint; A joint in the running rail used to prevent track circuit energy on one side of the
joint from leaking to the other side of the joint.
Interlocking Signals Fixed signals which govern the movement of trains through Interlockings
that are observed by the train operator under ATC failure conditions at reduced
speed.
Interoperability; In the context of the European High-Speed Lines, is the ability of the European
High-Speed lines railway network to allow high-speed trains to run safely and
Page 35
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Intrusion; An errant vehicle’s exit out of its right-of-way and entry into the operating space of
another transportation system’s right-of-way.
Intrusion Detection; An electronic system that alarms the intrusion event to the Central Control
and to the Train Operators. A dedicated detection system may be used for non-
vehicular intrusion such as for people or animals.
Main Line; The tracks allocated to the high-speed train traffic at normal commercial speed and
not normally used for switching or storage.
Movement Authority; The vital information used by the on-board ATC system to determine the
position on the track (or limit) to which it can safely move under ATC supervision,
including the speed limits both permanent and temporary that must be observed
between its current position and the Movement Authority limit.
Operations Control Center (OCC); A centralized control facility from which railroad
operations are supervised and controlled. The main control enter can be
supported by Regional Control Center(s) from where specific regions or branches
of the system can be supervised and controlled and that can act as a back-up
control facility in the event of a failure of the OCC.
Positive Train Control (PTC); A proactive train control system that prevents train collisions,
derailments due to overspeeding, and protection of work zones on or about the
tracks.
Radio Frequency; The frequency range of the electromagnetic spectrum that is used for radio
communication.
Rail Safety Improvement Act (2008); An Act of Congress that mandates the implementation of
Positive Train Control on certain rail lines (including those over which passenger
trains operate) by the end of 2015
Regional Control Center (RCC); A control facility from which a specific region of the CHSTP is
supervised and controlled. The RCC can act as a back-up control facility in the
event of a failure of the OCC.
Restricted Manual; A mode of operation under wayside signal and procedural protection with train
speed limited by the on-board ATC equipment.
Restricted Speed; Operation at no greater than twenty (20) miles an hour, prepared to stop
within one half (1/2) the range of vision.
Page 36
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Shared Right-of-Way; A CHSTP alignment where high-speed trains operate in proximity to other
transportation systems, including conventional passenger railroads and freight
railroads, without sharing tracks. Also includes highways.
Shared Use Corridor; A CHSTP alignment where high-speed trains operate with other passenger
and freight railroads (e.g., Caltrain, Metrolink, Amtrak, UP, and BNSF) and share
the corridor.
Shared Use Track; Segment along the CHSTP alignment where high-speed trains operate with
other passenger and freight railroads, (e.g., Caltrain, Metrolink, Amtrak, UP and
BNSF) on the same tracks.
Signal Aspect; The appearance of a fixed signal conveying an indication as viewed from the
direction of an approaching train; the appearance of a cab signal conveying an
indication as viewed by an observer in the cab. Flashing or lack of flashing of a
light is a part of the aspect.
Signal Block; A length of track of defined limits, the use of which is governed by the ATC
system; a Signal Block may include one or more Track Circuits.
Track Circuit; A method of determining occupancy of a section of track and/or a broken rail by
sending an electrical signal down the track from the transmit to the received end
of the section of track and indicating that the section of track is compete and not
occupied by detecting a minimum level of the proper signal at the receive end.
Train Operator’s Display; An indication in the Train Operator’s cab that provides the status of
the ATC system and the safe limits within which the train may operate
Virtual Signal; A database element that replicates the function of a wayside signal in the ATC
system but with no physical signal installed at the wayside.
Wayside Signals; Devices located along the right-of-way for providing information to the Train
Operators relative to train operations as opposed to the cab signal displays that
are located within the control compartment of the rolling stock.
Yard Signal System; The train control system that controls safe train movements within the
limits of Yard Tracks.
Yard Track; A section of track used for storage of trains that is auxiliary to the main track and
not used by trains that are carrying passengers. Refuge tracks at stations are
yard tracks. Yards consist of more than one yard track used for storing trains,
inspecting trains, and accessing maintenance facilities. Yard tracks may or may
not have track circuits on them.
Yard Transition Tracks; A section of track used for the transition of trains between the main lines
and Yard Tracks. Transition Tracks are equipped with both the main line ATC
system and the Yard Signal System. Yard transition tracks shall be track
circuited.
Page 37
California High-Speed Train Project Automatic Train Control; Concept of System, R0
6.2.2 Acronyms
Several acronyms have different definitions depending on the technical area in which they are
used. The following list is of acronyms identified thus far by the CHSTP.
A
ATC Automatic Train Control
ATO Automatic Train Operation
ATP Automatic Train Protection
ATS Automatic Train Supervision
C
CTS Communications Transmission System
D
DCS Data Communications Subsystem
E
ERTMS European Railway Traffic Management System
ETCS European Train Control System
F
FCC Federal Communications Commission
FRA Federal Railroad Administration
G
GPS Global Positioning System
GSM-R Global System for Mobile Communications - Rail
O
OCC Operation Control Center
OCS Overhead Contact System
P
PTC Positive Train Control
R
RCC Regional Control Center
S
SCADA Supervisory Control and Data Acquisition
T
TCC Train Control and Communications
Page 38
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The ATC system shall also be subdivided into physical subsystems; each subsystem contains
differing sets of functions drawn from the above three functional groups. The physical
subsystems are as follows;
• Wayside – consists of equipment located in housings along the right of way including
station equipment rooms, train control equipment houses, and signal equipment cases
and cabinets. The equipment includes track circuits, switch machines, wayside signals,
interlocking equipment, and transponders (or balises), much of which is considered to be
conventional signal system equipment. This equipment includes ATP electronics that is
either integral with or interfaces to the track circuit and interlocking equipment and to
other sensors including intrusion, seismic, and other detectors that will allow the train
control system to react to an event and bring the train to a safe speed if necessary. The
ATP processors obtain track circuit occupancy status, interlocking route status, and
sensor device status in order to output messages to the trains that define the safe limits
(including distance to go and target speeds) for train movement. Equipment will be
housed in a distributed fashion along the rail line to provide continuous coverage
including on aerial structures, in tunnels, yards, and stations.
Interlocking functions including route setting, route locking, approach locking, and
sectional release will be performed by wayside microprocessor interlocking equipment.
The wayside subsystem will be linked by the data communication subsystem to allow
supervision and remote control from the Operations Control Center (OCC).
• On-board – This subsystem consists of equipment located on the passenger
trainsets and maintenance vehicles and includes processors, firmware, software and
electronics, operator displays, operator switches, data radios and antennas,
transponder/balise antennas, code pick-up antennas, network components, GPS
receiver and antennas, tachometers and other sensors, and all connections between
train control elements and interfaces between train control and the train
subsystems including propulsion and brakes. Sensors and processors are used to
determine position and speed, computer equipment, and operator controls and
displays. Depending on the train control technology selected, the on-board
equipment may also include data radios and antennas
Page 39
California High-Speed Train Project Automatic Train Control; Concept of System, R0
with which to communicate with the wayside and central control subsystems. The on-
board subsystem may also include antennas and decoding equipment to detect digital
signals transmitted to the train through the rails. The on-board package will receive data
through the radio or the rails that define the movement authorities within which the train
can safely operate. The actual speed of the train will be continuously compared to the
authorized speed. If the train is to operate in ATO, the ATO functional set will handle any
changes in speed called for. If the train approaches an overspeed condition the ATP
functional set will generate a warning to the train operator. If appropriate action is not
taken, the on-board system will intervene to ensure that the train movement stays within
safe limits.
The on-board ATC will use sensors to determine the train’s position to a high level of
resolution both laterally (which track the train is on) and longitudinally, as well as
accurately measure speed. The enforcement of the Movement Authority limits enables
the on-board system to provide the required PTC protections.
The onboard ATO functional set will regulate train performance when selected.
Commands received from the ATS functional set may also provide for pacing trains at a
lower speed than their maximum speed or increasing speeds from the pacing speed
called for by the normal schedule. Under no circumstances can these ATO functions
allow the train to operate faster or further than the safety-critical limits determined by the
PTC functions of the ATP functional set.
The on-board ATC subsystem will interface with the rolling stock subsystems to support
the ATP, ATO, and ATS functional sets.
In addition to interfaces required for the ATC system functions, additional train interfaces
will provide remote monitoring capabilities of rolling stock subsystems. Remote
monitoring allows for early diagnosis of trouble. Monitoring can be done using the office
subsystem as part of the ATS functional set. Alarms and event indications can be
displayed at the Operations Control center and the Regional Control Centers, or at ATS
remote workstations at other locations.
On-board passenger information systems, including audible and visual announcements
of real-time performance and other information to the passengers may be provided from
the Office subsystem through the ATC data communications subsystem or by an
independent data communications subsystem.
The on-board ATP functional set equipment will interface to wireless or above-rail
inductive antennas that receive Movement Authority commands from wayside ATP
functional set equipment. A data radio subsystem will provide data transmission between
the train and wayside.
• Data Communications Subsystem (DCS) – Communicates data, commands,
indications and alarms between ATC subsystems and locations. This consists of
connected networks of wireless, fiber optic, and hardwired equipment.
The DCS will carry both safety-critical and non-safety-critical (management) information.
The DCS itself does not have to be a safety-critical system. Coding and other techniques
in the other ATC subsystems ensure that the data received is of sufficient integrity and
currency that it can be treated as accurate for safety-critical applications. ATP
equipment will reject any safety-critical data that cannot be validated.
Many DCS elements, including electronics, fiber cables, radio equipment, and antennas
will be on CHSTP property. However, the diversity that may be needed to deliver the
specified communication link availability may require the use of leased communications
lines provided by a third party as backup to the primary links. Some radio antennas may
also be located off CHSTP property where propagation considerations indicate a benefit.
The candidate ATC system ERTMS uses 900 MHz GSM-R radio to communicate
movement authorities and safety-critical data between train and wayside. Possible use of
GSM-R in the U.S. is being reviewed by CHSTP Systems Group, as well as alternative
Page 40
California High-Speed Train Project Automatic Train Control; Concept of System, R0
frequency bands, including the use of Long term Evolution (LTE) wireless network
technology.
• The Office subsystem supports the majority of the ATS functional sets. It consists of a
centralized or a distributed computer control system with dispatcher workstations that
provides the overall CHSTP train operation management functions including remote
routing and supervision functions. It includes announcements of events including critical
alarms and a logging capacity for all events. It generates many system performance
reports. Many ATS functions supported by the Office subsystem are automated,
including setting of routes at interlockings, regulation of train movements in accordance
with the schedule, and the recovery of the service from interruptions and failures.
At any time, dispatchers can take manual control of route setting and schedule regulation
functions from their ATS workstations, in accordance with the rail management plans
and procedures.
The Office subsystem architecture can be centralized or distributed to provide reliable
computing power and the required workstations that allow supervisors to dispatch the
services, monitor subsystem performances, and intervene to manually supersede
automated processes in the event of incident and emergency. The territory controlled by
each workstation can be adjusted by users and/or administrators to adjust to workload
demands as they fluctuate. As workstations can be in a centralized facility and at remote
locations, the ATC system can support a flexible approach to the overall supervision of
the CHSTP rail operations.
The Office subsystem communicates with wayside locations, remote workstations, trains,
other ATC elements, and sensors including intrusion, through the data communications
subsystem.
• Field Portable – Equipment for use by Employees in Charge (EIC) of wayside work;
used to manage track and other wayside systems access. EIC portables will
communicate digitally and wirelessly with the ATS and with on-board ATC subsystems to
control train movements through a work zone. Trains may only operate through
established work zones with the agreement of the EIC who can use the field portable
equipment to enforce reduced speeds and track blocks. Although generally maintenance
work on the tracks will be done outside of revenue hours, EIC portables will protect all
worksites and zones on or about the track, from movements of ATC-equipped
maintenance vehicles and passenger trains.
• Yard – Equipment distributed throughout the yards and maintenance facilities for the
operation of switches, and to provide wayside illuminated signals, and enforcement
devices to control trains movements within Yard territory. Red signal aspects shall be
enforced such that trains cannot pass a signal displaying a stop indication and cannot
enter an unlocked switch or stop foul of a train movement authorized on another track.
Control of the Yard signaling systems shall be from a panel or workstation located in a
control room (or tower) within the yard facility.
Train movements between yards and the main line shall be routed through transition
tracks where trains will transition between ATC and Yard signal system modes of
operation.
Page 41
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Although the majority of the listed event sensors will be specified by other disciplines, many will
be interfaced to at least one of the subsystems of the ATC, and the ATC shall invoke the system
response. In some cases, the ATS subsystem shall be required to log the event and to display
an event and/or an alarm to the operators, in other cases the ATP system shall be required to
directly invoke a response of the train, enforcing a braking activation and possibly stopping trains
in an emergency. Each sensor interface must be identified and the response of the ATC system
to each interface agreed with Operations and other disciplines.
Dragging equipment detectors may need to be provided in the event that shared corridors and
tracks become part of the operational requirements.
Page 42
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 43
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The following matrix of operating modes and sub-modes has been identified;
Requires an action by the Train Operator to select ATO mode. ATP system
Line Speed or as must determine that other factors are correctly set before train can move in
defined by Limit ATO mode (Movement Authority is being received by on-board ATP
ATC ATO ATP
of Movement subsystem, doors are closed and locked, etc.)
Authority
Rolling Stock subsystem requirement must include the incorporation of the
vigilance/alerter device to ensure The Train Operator is in the cab and alert.
Rolling stock vigilance/alerter device is required in all modes of operation
including ATC, RM, Bypass Yard, etc.
This is the operating mode on the main line where movements and speeds
are fully supervised and enforced by the ATC system but the propulsion and
brakes are commanded by the Train Operator
Line Speed or as
Vigilance/alerter function to be provided by Rolling Stock; see note above.
defined by Limit
ATC Manual ATC
of Movement
CHSTP ATC may include a Call-On mode to allow the train to pass a red
Authority
signal under certain controlled conditions. If so, this will be a sub-mode of
ATC/Manual. To enter it, the ATC system shall send the train a Call-On
command. ATP shall enforce a speed limit of 20 MPH.
Page 44
California High-Speed Train Project Automatic Train Control; Concept of System, R0
In this mode the On-board ATP subsystem will limit train speed to 20 MPH
maximum. Train Operator will work in accordance with procedure and
observe the wayside signals for authority to move.
FRA requirement
of Restricted Movement authorities, including speed commands are not received in this
Restricted Speed. mode.
Manual
ATC on-board
Manual Restricted is 20 In the event of receipt of a speed command or Movement Authority from the
subsystem
(RM) MPH or lower, as wayside while in RM mode, the on-board ATC will automatically switch to
required to stop ATC Manual mode.
within half of
range of vision. RM mode addresses short term ATC failures such as movement through a
failed switch (under procedure) or through a failed track circuit (which can
include a broken rail) outside an interlocking. Movement through an
interlocking with a failed track circuit can be done under Call-On mode (see
above).
The Train Operator will select the transition from ATC Manual mode to yard
and vice versa when a train is stationary on a transition track when entering
or departing a Yard.
Yard signals shall be enforced however the safety criteria used in the design
shall not be as restrictive as for the main line ATC system.
ATC
Trains approaching a shop track from the Yard will require a Train Operator
ATC shall enforce yard acknowledgement before being allowed to enter a shop track.
Yard (or
N/A Yard speed limit maximum speed limits
Depot)
not exceeding 20 mph Yard mode can treat a shop entrance as an end of track and further
as per 49CFR236 movement forward can be in RM mode. This will be considered as part of an
Subpart I. Operations Hazard and Risk analysis.
If a wayside ATC failure affects Yard mode, RM mode is the most appropriate
mode for further train movement, protected by procedure. If the on-board
ATC fails, then the Train Operator must select ATC Bypass for further train
movement, protected by procedure.
Page 45
California High-Speed Train Project Automatic Train Control; Concept of System, R0
This is a mode NOT Shall require a separate Bypass switch that will be sealed normally in the
enforced by ATC. In ATC (not Bypassed) position.
this mode, ATC is in
Bypass mode and is not No secondary enforcement system is required other than a maximum speed
connected to the rolling supervised by the Rolling Stock propulsion subsystem.
stock equipment.
FRA limited
speed is 59 MPH Safe operation of trains
Bypass N/A
per 49CFR236 is maintained by home
subpart I. signal indications, by
rules and procedures,
by regular training and
refresh.
Page 46
California High-Speed Train Project Automatic Train Control; Concept of System, R0
ATO requirements shall therefore be incorporated in the interfaces with rolling stock and other
impacted subsystems. The decision to employ ATO and possible sub-modes of ATO lies with the
Operator.
6.3.8 Interlockings
Interlocking functions shall be achieved through the deployment of microprocessor technology.
Conventional relays shall be used at a minimum. Interlocking requirements shall be specified
including route clearing, approach locking, detector locking, route locking, traffic locking and other
functions. Approach locking shall be provided as the intermediate interlockings between stations
will normally be fleeted. Interlocking equipment shall be interfaced with other ATC subsystems to
send movement authorities to trains that shall ensure safe movement through interlockings.
Wayside signals shall be located at interlockings and shall indicate the status of routes at their
entrances however these signals shall not be the primary indication of route status; this shall be
achieved through the Train Operator’s display in the cab.
Page 47
California High-Speed Train Project Automatic Train Control; Concept of System, R0
The prime use for signals on the main line is to support safe train operation when the primary
ATC system is not available and when movement authorities cannot be received and enforced by
the on-board ATC subsystem. Home signals shall be provided on main lines at the entrance to
interlocking routes only and intermediate signals will not be provided. At high speeds, signals will
not be visible in a useful way to the Train Operator who must follow the cab signal indications or
allow the train to operate in ATO. During failures of the primary ATC system, the maximum train
speed will be limited to 59 mph which is the current limit incorporated into the 236CFR subpart I;
Maximum speed when operating with failed PTC system. In addition, under present rules a train
with an ATC failure that occurs while the train is located between interlockings must be operated
at Restricted Speed until it passes a wayside signal that indicates that there is no broken rail in
the signal clock ahead.
A headway requirement to be supported by intermediate wayside signals shall not be specified.
Wayside dwarf type signals are favored as they minimize installation cost and reduce life cycle
maintenance cost due to easier access for inspection and repair. The final decision on signal
type shall depend upon the agreed maximum speed when operating in degraded mode. Subpart
I specifies a speed of 59 mph or less for passenger trains operating in degraded mode without
PTC functions.
It is currently assumed that speed enforcement in degraded mode will be achieved by means of a
speed governor function incorporated in the rolling stock propulsion subsystem. This governor
shall be activated by the ATC cutout switch in the operating cab. If the train speed exceeds the
defined maximum (say 59 MPH) then the propulsion subsystem will cut power to the motors and
an audible and visual alarm will sound in the cab.
Page 48
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 49
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Availability considerations may also require that the ATS core equipment including
communications and database servers may need to be located in both the OCC, Regional
Centers, and possibly other sites with options for cold, warm, and hot standby of the back-up
systems given further consideration. This shall ensure that in the event of a major incident that
knocks out the OCC (earthquake, sabotage/terrorist action, major fire, etc.) centralized
Supervision and Dispatching can continue with little or no interruption to operations. In
emergencies, the control of interlockings can be taken from a Regional Center or a station control
room.
Current planning has identified that dispatching of the peninsula corridor will require a regional
center to handle high speed and Caltrain services between San Jose and San Francisco. This
Regional center would be staffed 24/7 and could be considered a location that could assume
supervision and control of the full high speed network during a major incident.
A further level of degraded operation can be achieved by means of local control panels
(connected to the ATC houses) in adjacent station control rooms. Although local control facilities
shall be specified for the ATC in the stations, the reliability/availability of the communications
subsystem makes the loss of control from the ATS highly unlikely.
Consideration will also be given to specifying a form of field-fallback mode for the remote
interlockings in which they will revert to normal routes being called and fleeted in the event of a
loss of communications with the ATS. A local control panel in the interlocking control house shall
also be provided for local control in emergencies and for maintenance testing needs.
For control of Yard movements, each yard shall have a local tower with controls and displays
allowing Yard supervisors to route trains within the Yard and shops with local control panels or
workstations. Handover of trains between the main lines and the yard tracks shall be
accomplished with an interface to the ATS system or ATS workstations which can be located
within the Yard towers. See next section on Yard signaling.
Page 50
California High-Speed Train Project Automatic Train Control; Concept of System, R0
treated by Operations and maintenance personnel as main line track as trains shall be capable of
full ATC operation, including ATO. ATO shall be possible leaving the transition track for the main
line and when entering the transition track from the main line. ATO shall not be available for
movements between the transition track and the Yard in either direction.
Each type of detection will be evaluated for the level of risk each hazard can pose to the
operation and the interface to the ATC system and what kind of response is required of the ATC
determined. The different types of response can include;
• Switch automatically from ATO to manual operation (note if the ATO function is designed
around a “hands off” approach this will typically invoke a service brake until the Operator
takes the controller).
• Stop the train immediately with a service brake
• Stop the train immediately with a controlled emergency brake
• Block an affected section of track and the on-board ATC determines the level of brake
needed to avoid entering the blocked track or to stop the train if it is already entering or in
the affected track section.
In the case of intrusions at stations the choice will be between automatic sensors or
customer/staff operated alarms.
Consideration will be given to the types of responses required for different levels of intrusion.
Dragging Equipment Detectors are to be given further consideration for adding to the list. If not
necessary on the HSR tracks themselves, strategic DEDs may be required where possible freight
or other operators’ trains (e.g. Caltrain) may approach but prior to them actually running on HSR
tracks. High load detectors to protect the overhead contact system from freight trains may also
be needed.
Page 51
California High-Speed Train Project Automatic Train Control; Concept of System, R0
components, for example particular types of tachometer (axle end for example) are not precluded
from the design due to details of body and truck design nor rolling stock maintenance
requirements
The location of the subsystem or module in which certain ATC functions reside is dependent
upon the architecture proposed by the ATC Supplier. To the extent possible, the specifications
shall allow flexibility to the supplier to propose the most cost-effective solution that provides the
required overall functionality and performance, especially safety and reliability, of the system.
An accurate and reliable determination of position and speed is one of the most critical functions
of a modern train control system. In order to do this ensuring fail-safe characteristics as well as
high availability, it is typically done with a combination of devices and techniques, including
tachometers, inertial sensors, GPS, and transponders or balises (mounted between the rails on
the track).
Wayside equipment in the form of track circuits indicates the position of a particular train on the
track which is used to fulfill the interlocking functions and to protect a specific train from following
trains.
Target points shall be established as part of a Movement Authority for a specific train which
defines the maximum limit of a train’s movement along the track and defines the maximum
speeds that the train is allowed to attain between its current position and its target point.
• Each train shall receive its Movement Authority from the wayside based upon factors
including the status of routes through interlockings, the position of switches, occupancy of
track circuits, and other elements of the wayside signal system and relate them to the on-
board database.
• On-board databases shall allow for updates from the central control system for the
temporary modification of database elements including speed restrictions.
• The on-board ATC subsystem shall determine its position in relation to the database and
compare its actual speed with the allowed speed at their current position on the track.
• The Train Operator’s display shall provide sufficient information to allow the operator to
modulate the throttle and brake to allow the train to travel as close to the speed limits
without unnecessary automatic interventions for impending or actual overspeed.
Speed and position sensors shall be based on proven products and also be combined in such a
way that the information derived by the train is truly vital. This may require a diverse means of
obtaining data from which speed and position can be determined.
Although rolling stock supplied tachometers may be used by the ATC system for non-vital
functions, the primary vital function of train position and speed determination shall use sensors
provided and installed by the ATC system supplier.
Page 52
California High-Speed Train Project Automatic Train Control; Concept of System, R0
Page 53
California High-Speed Train Project Automatic Train Control; Concept of System, R0
• Fixed data including speed limits can also be transmitted to the train. It is envisaged that
such data will be contained within the on-board database and transponders shall not be
required to upload this information.
• Variable data can include the status of the railway in front of the train.
• Transponders also provide an absolute confirmation of the train’s position which can be
used as a diverse confirmation of position and therefore support the safety case for the
system and as a means of positive confirmation of position if the train is operated under
procedure through a switch with unknown status during failures. This is preferred to a
manual input confirmation as it enhances safety during failure conditions.
Transponder-only transmission to trains provides only for an intermittent ATC system and this
type of system has performance and functional constraints when compared to a continuous
communications type ATC system. It is therefore envisaged that the ATC system shall receive
Movement Authority data either through a radio link (such as with ERTMS) with the wayside
equipment houses and cases or through a digitally encoded track circuit transmission through the
running rails (TVM430 etc).
Transponders shall therefore be required for both radio and coded track circuit types of system to
provide the position error correction function for an on-board speed and distance traveled
determination subsystem.
The requirements must support multiple, applicable vendor equipment together with defined
functionality allocation (between train control and train subsystems),
Page 54
California High-Speed Train Project Automatic Train Control; Concept of System, R0
were proposed not being able to meet specified standards. Appropriate formal methods will be
reviewed and specified if appropriate.
In the achievement of error free code, the approach of specifying proven systems with a minimum
of new or changed functions will minimize the risk to schedule and budget posed by software
development risks.
The ATC safety requirements shall also include the incorporation into the system design of a set
of safe braking criteria that will be described as part of a model. This safe braking model shall
define the necessary criteria that the ATC and Rolling Stock systems must meet in order to
satisfy the safe separation of trains, enforcement of home signals, and enforcement of speed
limits.
The system design shall include the ability of the ATC subsystem to command both a controlled
emergency brake in which wheel slide protection is active, and an absolute emergency brake in
which wheel slide protection is cut out.
6.3.26 Interfaces
The ATC system shall interface to the following subsystems;
6.3.26.2 Communications
Interfaces between the ATC subsystem and the Communications subsystem are also extensive.
In the event that an ERTMS train control system is selected, data and voice radio
communications shall be integral with the overall ATC subsystem.
Page 55
California High-Speed Train Project Automatic Train Control; Concept of System, R0
6.3.26.4 OCS
It is anticipated that the ATC subsystem may be required to implement two functions;
• On-board switching commands to the rolling stock subsystem to allow isolation between
section gaps as the train traverses the gap; this is likely a database function only where
the section gaps are identified in the on-board database
• Prevention of trains entering sections of the line where the OCS has been de-energized;
this shall require an interface between the OCS energized indication and the ATC. This
could be done at the OCC level with an interface between ATS and SCADA or at a local
level. Modified movement authorities would be transmitted to the on-board ATC and a
stop enforced.
6.3.26.5 Track
The details of the track layout including switch configurations, gradient, curvature, etc. must be
included in the ATC database. There shall also be physical interfaces between the switch
machines and the switches themselves and between the track and ATC transponders where the
latter must be securely fixed to the track and maintained within strict tolerances.
In the Yards, derails and transponders (if used for yard signal enforcement) shall also be fixed to
the track.
6.3.26.6 Infrastructure
The ATC subsystem shall interface with infrastructure as a result of the need to install equipment
houses, cases and other elements such as signals along the right of way and comply with
clearance requirements and access to the various ATC facilities. Basic footprint, equipment size,
and access needs have been provided to the infrastructure group.
Special considerations shall be given to tunnel portals for the need to house ATC equipment in
buildings and other structures at these locations.
Page 56
LEGEND: ATC/DATA/VOICE COMMUNICATIONS OPTIONS
OPERATIONS CONTROL CENTER ••••••••••• GSM-R: BANDSWIDTH SEARCH IN PROGRESS
WILL SUPPORT ATC, VOICE OTHER DATA
EI RENE TYPE OTHER DATA
TRACTION POWER FACILITY
RADIO (ATC/VOICE) RADIO
GPS
(TIME) WAYSIDE ATC EQUIPMENT ROOM
OPERATOR
VOICE OTHER DATA
SOURCES FIBER BACKBONE •----- IEEE 802.16M: DATA COMMUNICATIONS (STD. BY 2013)
RADIO ~ 2.4 GHZ TO 2. 9 GHZ OR 5. 4 GHZ TO 5.9 GHZ
-+- c:::,
INSULATED RAIL JOINT
TRANSPONDER (BALISE)
1111111111111111111111 VOICE RADIO: TRAIN TO WAYSIDE ANTENNA
~ 450 MHZ RANGE - SUBJECT TO NARROW BANDING
- 22 NARROW BAND CHANNELS AVAILABLE
OPERA TOR
CONSOLES l---0 WAYSIDE SIGNAL (MAINLINE) - ALSO REQUIRES 160 MHZ IN SHARED CORRIDORS
& DISPLAYS
l-0 WAYSIDE SIGNAL (YARD)
TACHO
'\j I 220 MHZ MAYBE REQUIRED FOR PTC INTEROPERABILITY IN SHARED/COMMON
TRANSPONDER POWER OPERATED DERAIL/OTHER ENFORCEMENT DEVICE CORRIDORS
GENERA TORS
ANTENNA
TRACK CIRCUITS
(TYP)
.
...
--
C -
0,
u --
-
TRANSPONDER
-
....
q -
--
ANTENNA STATION
'
----
----
:--
.....
--
----
----
_y --
L
0
--
----
ATC ATC
3' -- EQUIP. EQUIP.
....
----
/
,,,,,,,,,,,,,,,,,,,,
---- ATC
"' --
"'/ ---- EQUIP .
if) ----
0, --
C
3
0
ATC
L
0
EQUIP.
Ql
>
+
u
Ql
L
...
0 TPF
/
0
0
q
occ
u
/
I YARD
-
0
REGIONAL I CONTROL
er I
u I TOWER
Ql
Ql
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, I
o_ I
Vl
I
JC
0,
/ YARD
:r:
/ SIGNAL "' 100 SITES
4-
/ EQUIP. CAN BE
0
u I MULTICHANNEL
m I
a, I
en
N
"'/
f-
occ _ ______,
CENTRAL
0
N
" 0 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - DESIGNED
0 --- BY
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - ~ - - - CONTRACT
- - -NO. ----1
"
CD
E. MORTLOCK CALIFORNIA HIGH-SPEED TRAIN PROJECT 1 3259
DRAWN BY
DRAWING NO.
1----+-----+--+----+---+-------------------------< E. MORTLOCK
CHECKED BY - - PARSONS TM 3.3.1-A
1----+-----+--+----+---+-------------------------< H. GLI CKENS TE IN
1 - - - - + - - - - - + - - + - - - - + - - - + - - - - - - - - - - - - - - - - - - - - - - - - - l IN CHARGE
BRINCKERHOFF COMMUNICATIONS AND ATC SCHEMATIC CONCEPT NO SCALE
SCALE
u
> 1----l-------+--+----1----1-------------------------ton,ATTTE---------j
R. SCHMEDES (ERTMS E[RENE TYPE SYSTEMS, VOICE AND OTHER DATA)~sH-EE-,-, 0_----------.
TRANSPONDER (BALISE)
220 MHZ MAYBE REQUIRED FOR PTC INTEROPERABILITY IN SHARED/COMMON
CORRIDORS
OPERATOR
CONSOLES l---0 WAYSIDE SIGNAL (MAINLINE)
~·
& DISPLAYS
l-0 WAYSIDE SIGNAL (YARD)
E~~--------------------------------
s~•· - --
TX/R"...;~:::;,,,,,,,~
ATC
...
' ,~•..,,,,, 0
",,,
TRACK CIRCUITS
(TYP)
........................
C
0,
u
m TRANSPONDER
/
' ANTENNA CAB SIGNAL
STATION
ANTENNA
I
ATC ATC
EQUIP . EQUIP .
"' ,,,,,,,,,,,,,,,,,,,,
"'/
if)
ATC
0,
C
EQUIP.
3
0
L
0
ATC
<lJ EQUIP .
>
+
u
<lJ
L
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,-,,,-,,,,-,,,-,,,,-,,,-,,,,-,,,-,,,,-,,,-1
,,,, - - - - -
/
0
/
0 TPF
0
"u
/
-
occ
0 I YARD
er REGIONAL I CONTROL
u I
<lJ
<lJ
o_
I TOWER ................................................................................................
Vl
,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,,, I
JC
I
0, I
:r: I
I YARD
4-
I SIGNAL "' 100 SITES
0 I CAN BE
u I EQUIP .
m I MUL Tl CHANNEL
a,
en I
N I
"'/
f-
occ 1------___,
CENTRAL
0
N
" 0 1 - - - - - - - - - - - - - - - - - - - - - - - - - - - - DESIGNED
0 --- BY
---------------------------------------------------------------------------- ------1
CONTRACT NO.
"
CD
E, MORTLOCK CALIFORNIA HIGH-SPEED TRAIN PROJECT 1 3259
DRAWN BY
DRAWING NO.
1 - - - - - + - - - - + - - - + - - + - - - + - - - - - - - - - - - - - - - - - - - - - - - - - < o , SOLTERO
CHECKED BY - - PARSONS TM 3.3.1-B
1 - - - - - + - - - - + - - - + - - + - - - + - - - - - - - - - - - - - - - - - - - - - - - - - < H. GLICKENSTEIN
1 - - - - - + - - - - + - - - + - - + - - - + - - - - - - - - - - - - - - - - - - - - - - - - - l IN CHARGE
BRINCKERHOFF COMMUNICATIONS ANO ATC SCHEMATIC CONCEPT
SCALE
NO SCALE
u
> 1----l-----l----l----1-----1-----------------------lniDA:i'iTE~---------r
R, SCHMEDES (CAB SIGNAL SYSTEM, VOICE AND OTHER DATA) SHEE T NO.
g REV DATE BY CHK APP DESCRIPTION
06/08/10