A Case Study of Shwe Lin Pan Low Cost Project
A Case Study of Shwe Lin Pan Low Cost Project
by
NAY HTUN OO
Nationality: Myanmar
Yangon, Myanmar
Thailand
May 2017
i
ACKNOWLEDGEMENTS
Firstly I am thankful to all the teachers who came and taught us from AIT for the lectures
regarding with project management in construction. Specially thank to Dr. Hardikusumo &
Dr. Chotchai Charoenngam for guiding and supervision on this paper, giving reference books
and helping us along the training period.
Secondly I would like to be grateful to Director Daw San San Aye (DUHD) who allocated me
as a project representative official in "Shwe Lin Pin low cost housing project", Director Daw
Mie Mie Tin (DUHD) who advised me to attend this class, and gave me the chance to attend
this class and Director General U Min Htein (DUHD) for the encouragement of attending the
class.
i
ABSTRACT
The development of Low cost housing has become an urgent and important topic of
discussion in Myanmar. Affordable housing should meet the needs of those eligible
households with a cost low enough for them to afford. The affordable and low cost housing
aims to solve the problems of those who do have the ability to pay for their houses. Although
several public housing programs as a welfare system were undertaken in Myanmar, in order to
address the increasing housing needs of low income people, they are still in need of affordable
housing due to poor housing policy, lack of proper housing finance mechanism and low
affordability for home ownership.
Low cost housing development in Yangon is currently at the initial stage. This study
provides an overview of existing housing situation and affordable housing development
process of Yangon city, technology, material, contractors, land acquisition, permit approval,
Funding, loan and marketing for low cost housing sector in Myanmar, as well as experience of
housing development to find out suggestions for Yangon low cost housing development.
From the analysis of low housing development and lessons from the affordable
housing, it is clear that policy and financial support including long term mortgage loan and
housing provident fund is essential for low income group to be available and accessible to
affordable housing.
Key word , Low cost housing, Yangon, Technology
ii
TABLE OF CONTENTS
Title Page i
Acknowledgements ii
Abstract iii
Table of Contents v- vi
List of Tables vi
List of Figures vii
List of Abbreviations viii
1.0 Introduction
1.1 General Background 1-2
1.2 Problem Statement 3
1.3 Objectives of Study 4
2.0 Literature Review for Housing Project
2.1 Inception Stage 4
2.2 Feasibility Stage
2.2.1 Feasibility Study 5-6
2.2.2 Design 6
2.2.3 Aerial Restriction Site Selecting 6
2.2.4 Land Acquisition 6
2.2.5 Project Execution Plan 6
2.3 Strategy for Low Cost Housing 7
2.3.1 Housing Development Activities 7
2.3.2 Selecting the members of Project Team 8
2.3.3 Cost Planning and Control 8-9
2.3.4 Relationship Between Cost and Quality 9-10
2.3.5 Project Scheduling 10
2.4 Preconstruction Stage
2.4.1 Interlinking with Strategy 10
2.4.2 Design Delivery 10
2.4.3 Project Meeting 10
2.4.4 Risk Mitigation Planning 11
2.5 Construction 11
2.6 Handover 11-12
iii
3.1 Case Description 13-18
iv
(g) Related to contractor 53-54
4.3 Final Recommendation 54-56
Appendix
Appendix 1 Shwe Lin Pan Low Cost Housing Master Plan
Appendix 2 8 Unit 4Soreyed Low Cost Building
Appendix 3 8 Unit 4Soreyed Low Cost Building’s Floor Plan
Appendix 4 6 Unit 4Soreyed Low Cost Building
Appendix 5 6 Unit 4Soreyed Low Cost Building’s Floor Plan
Appendix 6 6 Unit 4Soreyed Low Cost Building’s View
Appendix 7 8 Unit 4Soreyed Low Cost Building’s View
Appendix ( 8 ) 6 Units 4 Storeyed Building’s Foundation
LIST OF TABLES
TABLE TITLE Page No.
LIST OF FIGURES
FIGURE TITLE Page No.
LIST OF ABBREVIATIONS
vi
PPE Personal Protective Equipment
JV Joint Venture
RC Reinforced Concrete
vii
Chapter (1)
Introduction
1
cities such as Yangon and Mandalay while wholly carrying out construction in other areas of
the country using government loans.
Housing Provision system is to set up to appropriate level of income households. There
were upper-middle and high income households who live in housing built by themselves or
built by the private sector, middle income households often occupy formal housing types that
are more likely to be low quality housing and low-income households can be found in slums
and squatter settlements, or informal rental housing. DHSHD now in DUHD and YCDC are
perpetually solving in several ways to meet the housing needs of Yangon city. Since the past
decades, DHSHD has already created low-income housing and rental housing project for low
income households, government servant, and pensioners.
The 2013 Urban Development Conference held in Yangon displayed plans to
transform Yangon into a megacity with sprawling industrial complexes and middle class
housing projects. And then two massive low priced housing estate complexes have already
begun in Yangon’s suburban area. These are being built for the expected influx of people
moving to urban Yangon for better work opportunities.
2
1.2 Problem Statement
Many housing projects have problems such as poor quality, delay and not having
construction permit from YCDC and squatters are living government land. The last one is very
common during these days especially in Yangon. In 2008 we faced Nargis Cyclone at
Ayeyarwaddy division. People were destroyed by natural disaster. The victims and lack of
opportunity people of other states and divisions have moved to Yangon because of jobs. The
land price in Yangon is very expensive and difficult to get flats.
With city rapid growth, more and more people moved to city and as the consequence
city turned to be crowded When large number of people living in city became more
competition, the demand for housing will increase, then the gap between housing demand and
supply will be wide if the construction speed is lower than the increasing housing demand.
Access to adequate and affordable housing is a current and growing problem in many
countries of Asia but some of the countries are good handling for housing provision.
Some of the problems of housing in Myanmar can be assumed that;
- It is not that housing is too expensive but rather that incomes are too low.
- Incomes are relatively high but housing supply and finance is limited and hence
expensive.
3
1.3 Objective of Study
The objectives of this case study are as follows;
4
Chapter (2)
Literature Review for Housing Development Project
Low Cost Housing Projects require significant management skills and co-ordination of expert
people from different professionals. Moreover, it is also need to make sure to complete the
project within the parameters of time, cost and quality. Any construction projects especially
housing projects require to meet client's requirements (Government) and the intended users,
whether the housing is constructed for high-end or middle income people or low income
people, etc.
In the inception stage, it is needed to make clear that the client's requirements, what kind of
services they need and, have to plan the best ways to meet the users (buyers) satisfactions.
In order to get effective feasibility study, the information used should be as sufficient and
accurate as possible. The specialists and experts join in this stage are mostly reimbursed on a
time-charge base and without commitment to take part until the completion of the feasibility
study. Feasibility study report should include the following
Items;
5
Estimated project cost including operation and maintenance cost
Funding assessment
Determining starting date and finished date
2.2.2 Design
Design of low cost housing is mostly very simple (not complex) and structural design should
be same for many building. There are two types in analysis on the dimension of use of space.
The first is analysis on the use of space in simple low income family who are used only the old
simple style furniture in Myanmar. The use of space is really depending upon the setting of
furniture. The use of space can be reduced because of that kind of combination of furniture.
The second analysis is that mostly of the activities are taking in living room, such as sleeping,
praying, relaxing, working and dining. Cooking and dining functions are in kitchen. Most of
the functions are mixing the functions perfectly, the more saving the cost. If dimension is
adequately small, the cost of building can be reduced and then save the unit cost.
2.2.3 Material
In technical sustainability is very important for low cost housing. It implies good quality
materials and serviceability in the environment. We should have to choose the reputation of
supplies. Diversification and innovation of design and building materials have to meet the
needs for durable and safe structure. Mass production system is reduced number of materials
and components which can reduce cost of building, depending on same design.
2.2.4 Worker
6
2.2.5 Project Executing Plan (PEP)
According to the book "Code of Practice for Project Management for Construction and
Development" (Fourth Edition, 2010) by author Wiley-Blackwell, Project Executing Plan
(PEP) is an important document to manage the project successfully. In which policies and
procedures concerning with the project are mostly defined by the project sponsors. The project
manager is commonly developed PEP for the approval of project sponsor. PEP must include
plans and procedures to control project implementation and, to monitor and evaluate project
progress. The roles and responsibilities of all project participants are defined in PEP and the
result is everyone can understand and carried out their responsibilities properly.
The strategy for housing development must include the forming of project organization,
determining the strategies for procurement and delivery (cheaper, faster and better quality and
risk management), commissioning issue until completion and close out of the project. The task
and activities for feasibility study and housing strategy are interrelated to each other in order to
achieve both processes. The sequences of activities for housing development projects are
commonly as follows;
7
Figure (1) Sequences of Activities for Housing Development Project
Feasibility
Study
Inception
Stage
Strategy
Development
Pre-construction
Construction
Commissionin
Hand-over
O&M
For the selection of project team members, the following qualifications are necessary to be
consider;
8
A suitable deputy for each team member should be identified to be sufficiently familiar with
the project in order to act as replacement whenever it is needed. Apart from the above stated
abilities, team members should have the following people skills in order to get smooth relation
among project team members and develop the project successfully.
The objective of cost planning is to allocate budget for the major items of the project.
Although many people think that the terms budget and cost plan are nearly the same, it is
different. Budget is the limit of expenditure determined for the project, whereas cost plan is
the amount of money to be spent on and when. Therefore cost plan should include possible
estimate of the cash flow for the project and should cover the cost for all stages of the project.
Cost plan is used as a reference to manage the project. A cost plan is prepared including all
construction costs, professional fees, contingency, project insurance, surveys and agent's fees
or other specialist advisors. A budget study is undertaken by the determination of total costs
and expected return of the project.
The objective of cost control is to manage project delivery within the approved budget. Only if
all the project team members have correct attitude to control the cost, effective cost control
can be achieved. Moreover, the current budgetary, cost situation and, up-to-date and accurate
cost reports must be informed to the client regularly in order to achieve effective cost control.
9
2.3.4 Relationship between Cost and Quality
If good quality materials are assumed to be used, the key to quality control is working with
skilled workers. The cost of the project is also depends on the skill level of workers. It is
important to choose the appropriate level of skill to meet the quality level of the project. If
over-skill workers are sent to quality B level job, it is a way of wasting money on over-skill,
whereas if workers are under-skill for quality A level job, money will be lost on low
production rates and poor workmanship. Although the former instance is losing money, the
latter one can compromise the reputation and safety problems as well.
It is difficult to deliver top quality in a cost-driven market while other items are competitive.
On the other hand, top quality cannot be guaranteed although top dollars are paid. Responsible
architects have a general sense of quality requirements and make approval to meet their
bailiwick. Poor quality tends to end up in tear out or rework being undertaken and if worse,
monetary concessions or even litigation. Therefore it is very important to do checks and
balances between quality and cost to make sure that work is being executed correctly.
It is the responsibility of project manager to monitor and control for the production of design
information in line with agreed schedule. Therefore, project manager should convene attend
10
regular team meetings to review the progress of design team's functions. The design team
leader will be mostly architect and his/her responsibilities include co-ordination and
integration of the works from other designers, consultants, service providers, statutory
authorities and utilities, etc.
There are usually three kinds of meetings in pre-construction stage. They are project progress
meeting, design team meeting and pre-start meeting. As for the first one, project manager is
responsible to arrange and convene in order to review and control productivity of all aspects.
Design team meetings are chaired by design team leader. Although the project manager has
the right to attend design team meeting, it is not essential to attend all design team meetings.
The last one, pre-start meeting is held together with project team and contractors in order to
establish proper working arrangements, roles and responsibilities, communications and,
procedures. Health and safety plan for the construction stage have to be submitted by the
principal contractors in this meeting before the work starts. Distribution of meeting minutes to
all concerned person is an essential part of the follow-up action.
Possible potential risks throughout the project must be identified at the earliest stage of the
project. In which the project manager should give pressure to contractors to list construction
risks and determine the probable impact of each risk. And then the risks are reviewed by the
project team and prepare method of statement to mitigate the risks. Contingency plan must be
prepared and the risks are regularly reviewed and updated the list by the project team.
2.4.4 Construction
Construction business is not an individual, it is a people business and thus communication and
management and safety over all are the key to succeed a project. The project manager's
responsibilities in this stage involve heading up the professional design and construction team
and, building trust between all parties. The bonding between all parties can be developed by
holding regular meetings and workshops. During this stage, the project team must be hand on
to resolve and eliminate any issue hindering the smooth of construction process. The major
11
issue of construction process is to ensure that contractors and subcontractors receive regular
payments for their works. Normally, the contractor makes a monthly claim for the payment.
The quantity surveyor values the work, contract administrator certifies it and the client pays
for it during the period written in the contract.
2.5 Handover
Completion and handover are interlinking to each other. This is the final stage of work
executed by contractors and consultants in order to accept facilities by the client. In this stage,
client commissioning is carried out by the client's personnel, assisted by the consultants as
required. It is also stated as substantial completion for which AIA (American Institute of
Architects) definition of (A 201:9.8.1) defined as follows;
Substantial Completion is the stage in the progress of the Work when the Work or
designated portion thereof is sufficiently complete in accordance with the Contract
Documents so that the Owner can occupy or utilize the Work for its intended purpose.
(A201: 9.8.1)
After substantial completion, the next step is final completion. The items which are
substantially complete and only require for minor adjustments are listed as a punch list. Final
completion and handover to client must include the following documents.
12
Chapter (3)
Case Study for Shwe Lin Pan Low Cost Housing Project
3.1 Case Description
Shwe Lin Pan Housing Project consists of the design and construction of housing, city plan,
road, park , shopping center, social building and the religious building. Objectives: Housing
focuses on the city development of Yangon and uplift the living standard of the citizens
especially low income people. Our country is now developing country. We emphasize to
construct low cost housing for low income people. This project is situated on the Yangon-
Pathein road (between Yangon and Ayeyarwaddy division ) and not far from the down town
areas. Before implementing Housing Project we make the feasibility study, such as the
environment chances and risk, what options can we get and choice the best way to implement
the project.
The environment is a little quiet and there are affordable housings Projects was
implementing near the projects. Existing the Suladan stream, we can get fresh air and good for
health. Not far from the down town areas, it is convenient for the living people in the housing.
The price of land is expensive and the construction materials will get easily because of the
source of materials not far from the projects. But soils situation is not good because of the side
of the stream. So we make soil investigation. And then prepare the soil situation. So we
choose strip footing because the soil is field land. The project was subsidized with
infrastructure cost and land cost by government because of low income people. But seeing
from the Business plan, this project will get profit because the down town area is more
complicated and crowded with people. So some people move to the surrounding. And then
constructing this project, the city plans is more escalation and develop. The citizen livings
with the high standards and reduce the congestion of living people in the down town.
To implement this project, we hire theWatijone consultants from the local and invite
construction companies, by using bidding.. To implement the project, we draw the urgent plan
for:
• Quality management
• Health, Safety and Environmental management
13
• Programmed & Project management
• Construction management
• Human Resources management
• Risk management
• Administrative management
• Design management
• Communication management
This project, “low cost housing Project” was started in Dec, 2012. Shwe Lin Pan low
cost housing project is located in Yangon on kyansitthar road, next to Shwe Lin Pan industrial
zone in Hlaing Tharyar township and the whole project area is over 27 acres. The project has
been implemented phase by phase in three different phases since August 2013, with a target to
complete the whole project by the year 2015. The whole project is provided with basic
infrastructure such as roads, drainage, electricity, water supply and other services and
facilities. When all completed, the project will provide total housing units of 1908 to low
income people needing housing.
Shwe Lin Pan housing project is the first and foremost affordable housing recently
implemented in Yangon city as a pilot project that can be available and accessible to low and
middle income people who cannot afford the housing the market supply. The people targeted
14
to sell the housing units are low and middle income group that includes government
employees, pensioners, and the people who has regular monthly income.
The project is designed and developed in order that low income people can afford
housing units offered by the department. In order to increase the buyer’s affordability, the
following factors are considered in designing the project to reduce housing cost:
(1) Project site is chosen in new town far away from city center with zero land cost.
(2) Setting housing standard with simple housing design and floor area as minimum as
possible.
(3) Mass production of housing within a short period of time using innovative
technology and quality control like precast system.
(4) Provision of financial support like housing loan with low interest rate and long-
term repayment.
As mentioned earlier, the project has been developed in three phases where the project
implementation phase by phase can be described as follows:
(a) Development phase (1)
Phase (1) is an area of 10.3 acres and targeted to complete within one year,
starting from August 2013 up to August 2014. The project includes 6 unit 4 storey
steel structure (Hall Type) buildings and 6 unit 4 storey RCC buildings (Hall
Type), which will provide total housing units of 768 with minimum per unit floor
area of 468 square feet. Basic infrastructure and services such as roads, drainage,
electricity and water supply are also provided. The project is financed by the
Housing Revolving Fund that accounts for approximately six billion kyats.
15
Table (3.1.1) Phase (I) Project Description
1 Project starting date 7.8.2013
7 Type of building
(a) 6 units 4 storey 22 Nos
Steel structure (Hall type)
Total rooms 528 Units
(b) 6 units 4 storey 10 Nos
RCC building (Hall type)
Total rooms 240 Units
Source: DUHD
16
Table 3.1.2 Phase (2) Project Description
17
Table 3.1.3 Phase (3) Project Description
1 Project starting date 1.5.2014
2 Project ending date 1.5.2015
3 Project period 1 year
4 Total estimated cost (Kyats) 6031100000
5 Total rooms 644 units
6 (a) 8 unit 4 storey 5 Nos
(Ground floor shop
house)
(22’x51’)= 1122sqft 20 Units
(22’x22’)=484sqft 120 Units
(b) 6 unit 4 storey 21 Nos
(residential)
(18’x26’)=468sqft 504 Units
Source: DHSHD
3.2 Housing Development Process
Yangon City in Myanmar has been facing housing problems, particularly for the poor
who make up the majority of the total population. In a recent seminar upon housing
development, the results of studies showed that 37.7% of houses in Yangon urban are built of
bamboo and 19.4% of urban houses are built of rudimentary wood 1. Housing studies and
analysis, as part of the policy preparation which are conducted by DHSHD demonstrated that
low and moderate income families, representing approximately 70% of the urban population,
are in most need of government intervention in the housing market. As a result, these families
constitute the target groups to which special attention is being focused. The main government
agency responsible for housing and settlement development in Myanmar is Department of
Human Settlement and Housing Development (DHSHD) under the Ministry of Construction.
The department has a wide range of well experience in tackling housing development in
Myanmar.
18
3.2.1 Historical Background
The predecessor of DHSHD responsible for the housing development was the
“Rangoon Development Trust” (RDT) formed in 1920 to take over the development functions
and the land management from the Municipal Corporation which could not cope up with both
functions of maintenance and development of the city. The RDT was quite active and effective
in taking over the development function of Yangon. In 1951 RDT was transformed into
“National Housing Board” together with the promulgation of the “National Housing” Town
and Country Development Act. It was changed into Housing Department (HD) in 1972 and
then the Department was reorganized as Department of Human Settlement and Housing
Development (DHSHD) in 1990.
Housing Development activities were restricted and limited to providing government
rental housing, public housing and site and services schemes through government subsides
during the time of 1960s to 1980s’. Myanmar housing sector has drastically changed after
1989 when the State introduced new economic policy on the basis of market oriented economy
and private sector participation.
DHSHD is acting as a facilitator for enabling private sector participation in the housing
development and coordinator with other department and agencies in the activities of housing,
industrial infrastructure and social infrastructure provision and development.
19
blocks. Prior to 1989, the government has annually financed the construction of high-cost
dwellings. After 1989, it was recognized that the conventional housing solutions were no
longer applicable in response to housing problems of growing low income households.
Considerable efforts have been made to improve the housing sector. These may be
summarized as follows –
(1) Large scale planning and development of approximately 160,000 plots for round
about 490,000 persons in three new settlements.
(2) Attempts to recover part of the development costs through charges and the scale
(long-term leasing) of land (industrial and residential land).
(3) Resettlement of squatter households of approximately 51,020 from the central area
and the fabric of inner city to new towns.
(4) Development of financing mechanism for 35,000 civil servants (subsidized housing
loans).
(5) Densification of inner city area particularly along major road.
(6) Cooperation between the public and private sector for the construction of
residential housing.
20
dwellers within Yangon City were relocated to four New Dagon Townships,
Shwepyitha and Hlaingtharyar, and other new towns with the provision of leased land
with basic infrastructure. There are 247,304 plots of site and services land developed in
new satellite towns and villages from 1989 to 2010 and 237, 637 plots have been
allocated to senior government employees, squatter settlements and reassembling of
villages in corporation with new town extension.
(c) Squatter Slum Upgrading (hut to apartment scheme): This program has been
introduced after 1994 in some part of the inner city area through on site relocation by
providing apartment units for squatter families or beneficiaries. Average of minimum
600sq.ft to maximum 1000 sq.ft of floor space equipped with water and power supply
have been provided to the squatter families. There are 44 huts to apartment projects of
more than 1,777 dwellings. Those were constructed in Yangon City area within 6 years
period (1994-2000). The approach of DHSHD in housing development for slum and
squatter has changed from the role of provider into facilitator by mobilizing private
sector participation through cooperation.
(d) Urban Redevelopment Projects: This kind of project has been launched since 1989
as the urban redevelopment program to enhance the general physical appearance of the
urban area and to free important sites for public uses such as park and commercial
development. There are about 56 urban development projects developed and managed
by DHSHD in coordination with private developers through public private partnership
and sharing basic. Those are over 600 nos. of buildings such as high class and high rise
apartments, condominium, plaza, commercial, services and mixed use buildings are
cooperated in the projects.
(e) Low-cost Housing Development: Since 1997, low cost housing programs such as
housing in Dagon, Hlaingtharyar, North Okkalapa and Danyingone have been
introduced and 3,448 apartments units have been constructed for the benefits of lower
and middle-income people. Unit prices have been charged only for the construction
cost of building and basic infrastructure excluding land cost.
(f) Industrial Zone Development: The Private Industrial Enterprise Law promulgated in
November 1990 has allowed the promotion of private sector development and the
direct foreign investment and production. The government has initiated and promoted
21
industrial zone development activities to complement with the economic objective of
the nation. The Department of Human Settlement and Housing Development
(DHSHD) has the responsibilities of establishing new satellite towns incorporating
planned industrial zones to promote the national economy through industrial sector and
create job opportunities in the new areas. There are 8 industrial zones and about 3,000
hectares of industrial land developed by the DHSHD in the satellite towns and
proximity of Yangon City. The locations are selected in an area where vast flat land is
easily accessible and where waste from the factories can be disposed of without
creating any hazard to the environment. The services zones and an area for waste water
facilities are allocated in all the industrial areas. Recreational areas and facilities are
also integrated as part of industrial zone development in Hlaingtharyar, Dagon
Seikkan, Mingalardon and Yangon Industrial park. As the provision of basic
infrastructure is essential for the development of an industrial zone, DHSHD has co-
operated and coordinated with other departmental agencies in provision of
communication, electricity, transportation and irrigation for the flood and erosion
control.
(g) Joint Venture Investment Programs: Foreign direct investment has been attracted by
coordinating joint venture investment on industrial zone development, leased land and
BOT system.
(h) Provision of Social Infrastructure: There are 43 schools facilitated and constructed
by DHSHD in YCDC area and Thanlyin-Kyauktan region during 1997 to 2000.
DHSHD is also taking initiatives for the development of old aged home and cancer
care units in Dagon new town.
22
3.2.5 Housing provision by government budget
It is a system of housing provision with the capital budget allocated by government
from its yearly budget for civil servants’ housing and public housing with rental status as well
as basic infrastructure. The list of dwellings constructed with the capital budget from 2006-
2007 fiscal year to 2010-2011 fiscal year is mentioned in Table ( 3.2.1).
23
Table 3.2.2 Incensement of Revolving Fund
1 1995-1996 406.33
2 1996-1997 1021.12 251
3 1997-1998 562.98 (-)55
4 1998-1999 64.42 (-)11
5 1999-2000 692.50 1075
6 2000-2001 1481.41 214
7 2001-2002 7403.35 499
8 2002-2003 4147.12 (-)56
9 2003-2004 1793.44 (-)43
10 2004-2005 3345.73 187
11 2005-2006 4415.94 132
12 2006-2007 8671.08 196
13 2007-2008 3879.57 (-)45
14 2008-2009 2191.53 (-)56
15 2009-2010 14764.76 674
16 2010-2011 78793.57 534
Source: DUHD
24
3.3 Analyzing development for low cost housing
3.3.1 Construction
(a) Technology
Shwe Lin Pan affordable housing project is not only using simple technology and but
also simple housing design which preferred low cost projects and also short-term. The
foundation types of buildings have been constructed by strip footing. The steel and RCC
structure of building include a partial of main body, beam, wall column, purlin, roof, door and
window ventilating, water supply and sanitation and electrical supply. In this project includes
two types of buildings which have 6 units 4 storey (steel structure) building, 6 units 4 storey
(RCC) buildings and also 8 units 4 storey buildings. The floor areas are not large as minimum
as possible. In this project, total buildings (64) numbers among phase (1) pilot project is
implementing (22) numbers of total steel structure buildings. Steel structural buildings are
very quick to build at low cost housing project but this kind of building lose strength at high
temperature and are not resistance to fire prevention and then other (42) numbers of building
are RCC building.
RCC buildings are very suitable for in this housing because there are durability for long
term. Concrete Frames are very strong and can resist dead loads, live loads, dynamic loads,
wind load and earthquake loads depend on structure design and its life. Although Myanmar is
now developing country but construction technology is lack. The buildings of project have
been building by conventional method (traditional method) and cannot use precast technology
(mass production) because of lack technology. And then if this technology can use, the low
cost building for people cannot be only finished during one and half year but also the units
price of building will be decreased. The project is low cost housing for low income people
(rental people) who pay rental fee is very high in Yangon.
Shwe Lin Pan low cost housing project had used the traditional construction methods. The
detail procedures are as below:
(a) Foundation: Foundation’s depth is about 7 feet depend upon the soil bearing capacity
and building height. And then soil bearing capacity is about 7.0 and has to calculate
building structure (foundation design and superstructure). Excavation is first, second is
lean concreting 6” thick, and 1:4:8 concreting is also 6” thick.
25
(b) Cement concrete: Concrete footing size is about 5 feet around. The concrete mix
proportion of 1:2:4 (cement: sand: aggregate), with column footings is used.
(c) Retaining Wall construction: Hardcore for foundation is constructed for external walls had
used burnt brick masonry of a 9” thick layer and all partition walls always used a 4 ½” thick
layer. First class bricks (quality and burnt) are used for the building.
(d) Plastering: Plastering (1:2 mortar, cement and clean sand) is used for the brick work, (such
as external walling, internal walling and below of the slab). Joints are scraped before
plastering and proper preserving is ensured.
(e) Flooring: After the soil and sand is properly filled and compacted, the ratio of 1:2:4
(cement: sand: aggregate) concrete filled on the floor by using mixer.
(f) Doors and windows: Door and window are used aluminium material because it is very
cheap and easy to work than timber. In project avoided deforestation and not get to easy
timber frames (hard wood) and teaks (good quality). Doors are used ready-made door (Iron
door) including with door lock, frame and iron hinges which is not considered strap iron
hinges and door lock .Before installing aluminium window and ready iron door, brick
walling with plastering work, lintel and window sill concrete work are finished.
(g) Roofing: Before roofing work, roofing bean concreting and rafter (3”x 2” GI-hollow)
and purlin (C-channel 4”x 2”) are finished for it. In low cost housing, roofing sheets are
always used 4 angel aluzinc (25- gauge) because of avoiding maintenance work.
(h) Plumbing: Plumber always checked that medium quality plumbing materials are used or
not passed hydraulic test before using it.
(i) Painting and finishing: After scaffolding work and Plastering work had finished, we can
start painting work such as putty, primer and ready-made paint (external and internal) for
building in this low cost housing project.
26
Table (3.3.1) Strength and weakness of technology for low cost housing
Strength Weakness Recommendation
Strip Footing + Reduced cost of building than
isolated footing - Installation of drilled piers -if high quantities
+ Resistant to earth pressure needs a careful supervision of same materials ,
+ easy to carry out than other QA and QC is
and quality control of all the
footing essential in project
materials used in the -Owner and
+ Pier of any length and size can be
constructed at the site construction contractors are
+ Construction equipment is -The method is cumbersome. required to their
normally mobile and construction It needs sufficient storage goals
can proceed rapidly space for all the materials - Consider
+ Inspection of drilled holes is used in the construction Customers
possible because of the larger -The advantage of increased satisfaction in
diameter of the shafts depend on
bearing capacity due to
compaction in granular soil different quality
that could be obtained in
driven piles is not there in
drilled pier construction
27
3.3.2 Material
In technical sustainability is very important for low cost housing. It implies good
quality materials and serviceability in the environment. We should have to choose the
reputation of supplies. Diversification and innovation of design and building materials have to
meet the needs for durable and safe structure. Mass production system is reduced number of
materials and components which can reduce cost of building, depending on same design.
Project engineers should access good quality cement (ISO-2015), brick, aluminium
window, ready-made iron door and reinforced steel, water supply material and electrical
material. Project avoided bad material and date out of material because of low income people.
The walls are always used good quality brick for external building and ply-wood
walling are used for light partition wall for internal room.
Although concrete block and concrete, can be used ground level of building depend on
local conditions, demand ,standards and price but superstructure cannot use it because
overweight of concrete block is not lighter than brick. And then superstructure is limited over
dead loading according to the designer. Construction could achieve efficiency from concrete
block can get not to plastering work, cracking and waterproofing and easy to painting work.
Timber is one of the most commonly used materials for formwork in the project.
Flexibility in design depends on the type of timber and almost formwork needs of the
contractor. Negative aspects with timber maintenance is needed deforestation in large scale
causes environmental problems, storage needs to be covered, sensitivity to fires and biological
agents.
Aluminium material is can be used door and window. The panels are produced with a
range of different densites, combined with additional isolating materials. Walls need special
accessories in order to provide inter-panel locking . The system has been found to be
structurally resistant, well insulate and easily mounted if handled properly. Negative aspects
with aluminium: not a standard solution, recommendations for use is needed, specially
designed range of fixing accessories, panels must be stored and handled with extra care.
Before roofing work, roofing bean concreting and rafter (3”x 2” GI-hollow) and purlin
(C-channel 4”x 2”) are finished for it. In low cost housing, roofing sheets are always used 4
angel aluzinc (25- gauge) because of avoiding maintenance work to the future.
28
Table (3.3.2) Strength and Weakness of Material
29
3.3.3 Contractors / Subcontractor
30
Between Government and quality third party must include payment system, reporting
system and scope of work, the essential data and document in the report, etc. The forms for
inspection works and ITP must be attached in this contract.
The responsibility of contractor affords the works to attain the end result including
designing, door and window, delivering to site, scaffolding in term erecting and dismantling,
constructing, installing ,concrete testing and making good defects.
The important factor of contractor had implemented starting date and completion date.
The contractor is required skill labors, machines, money, good supplier and safety manager.
Scope of work; Contractor must follow the rule and regulation of time , cost and quality and
starting date , finished date and completion of project.
Fine or penalty for delay: If the contractors do not finished during the project time, they will
pay fine cost to owner according to the contract agreement.
Payment: DUHD payment system is four times, First is 25%, second 25%, third 25% and final
payment is 25% for contractor work done of actual cost.
The building cannot be finished during period of project contractor must pay penalty
charges to the owner (DUHD) as the contract agreement.
31
Table (3.3.4) Strength and Weakness of Contractor
32
j. If the low cost housing j. lack control of labors in reduce accident and
is succeed , can get Myanmar festival near miss.
The government has limited land acquisition to acquiring space for providing
governmental services, such as roads, water and sewer lines, and government offices.
Although land acquisition long has been recognized as an effective management tool to
implement land use and environmental policies, large-scale land acquisition as an urban
growth management tool often has been rejected as too costly and politically infeasible.
Nevertheless, governments frequently acquire land for specific purposes. For example,
governments at all levels regularly acquire land for parks and for wildlife and waterfowl
preserves. Although less common, governments recently have acquired land to promote urban
renewal, to prevent development in hazard areas, and to preserve open space. While the total
amount of land acquired for public use is relatively modest, individual acquisition proposals
33
often generate extreme controversy and strong political opposition. Citing that the federal
government owns approximately one third of the nation's land, critics decry the socialization
of one of our most highly treasured private resources-private property. Although more than
ninety percent of federally owned land is western land that never has been owned privately,
the federal government recently indicated concern over any extension of land ownership by
the federal government. At the state and local levels, opposition to land acquisition proposals
generally centers on the cost of acquisition and the loss of tax revenues. A philosophical
uneasiness with government having anything other than a very limited role in land owner ship
undoubtedly is also a potent underlying factor causing opposition to many state and local
acquisition proposals. In coastal areas, land acquisition can be a tremendously valuable
resource management tool. Wetlands critical to fisheries and wildlife have been developed at
an alarming rate."' Draining, filling, or developing wetlands diminishes their value as fisheries
and waterfowl habitat, destroys spawning and food supply areas, and renders them ineffective
for flood control and water quality protection. Development of adjacent lands can be almost as
disruptive because of the harmful effects of storm water run-off. Preserving these areas
through acquisition is often more equitable and effective, legally and politically, than
attempting to curtail development through regulation. Additionally, strong demand for
recreational use of coastal waters and beaches requires that this land not be left entirely in
private hands. Further, in some coastal areas, the public costs resulting from development, in
the form of subsidies for water, sewer, and transportation services, as well as flood insurance
and disaster relief, are potentially so high that land acquisition is less costly to taxpayers over
the long term. Finally, ownership of key land areas can influence development patterns for an
entire coastal area and affect the type, tuning, and intensity of development of nearby lands.
Public land acquisition generally requires the government to acquire the full fee simple
interest. The reasons are clear: a need to acquire all property rights to adequately protect the
property; the lack of any significant cost savings with alternatives; simplicity for both the
private landowners and the government; and a lack of familiarity with less than fee
acquisition." In most instances, then, acquiring the full fee simple interest is justified and
reasonable. In some situations, however, an alternative to fee acquisition can be used more
34
effectively to benefit all parties involved. The most frequently used alternative is acquiring an
easement. Easements fall between uncompensated regulation and full fee acquisition and are
particularly advantageous when the government is attempting to accomplish a specific
objective, such as preventing future development while preserving the landowner's limited use
of the property. Public easements can be either negative or positive. Negative easements
prevent the landowner from taking certain actions deemed adverse to the public interest. For
example, when the government acquires an easement to preserve a scenic view, the owner
sells the government his right to develop the property in ways that obstruct the view.
Landowners also may sell to the government their right to develop wetland areas. Such a sale
prevents any alteration of the area, but the owner retains exclusive hunting and fishing rights.
This arrangement often meets the principal objective of both the government, which is
interested in habitat preservation and water quality protection, and wetland owners,
particularly those who originally purchased extensive wetland areas for waterfowl hunting. In
contrast, positive easements give the public limited use rights. Examples of positive easements
include public hunting or fishing rights and public use of a strip of upland property as a
walkway to the beach. Whether the public easement is negative or positive, the underlying fee
simple interest remains in private hands, and the owner retains the right to make economically
productive use of the property. ' Easements have advantages and disadvantages as compared to
fee acquisition.
35
Table (3.3.5) Strength and weakness of Land Acquisition
- Easy to carry out the - The farmers don't want to - More compensation
project get compensate - More incentive
- Land Cost is -Government has loss of High rise building should build on
subsidized for low profit especially the land for long term
income people construction tax and land
tax.
-Not consider land cost
- decrease the -insufficient pure water and Should supply pure water system
population density in Security and build police station near the
the city project
Because low income people will be constructed in four storey building, phase (1) project of 32
buildings were built with major to complete in time. Once the project was started, DUHD
supports documentations to negotiate with chief ministers of Yangon, YCDC and other
relating government’s organizations and held many meetings with obligation official to get
BCP as quick as possible. Because the project is directly connected with low income people
and Ministry of Construction (MOC), YCDC issued pre BCP for low cost buildings in phase
(1) project as very importance case.
36
Table (3.3.6) Strength and Weakness of Permit/ Approval
3.6 Funding
3.6.1 Government funding
It is a system of housing provision with the capital budget allocated by government
from its yearly budget for civil servants’ housing and public housing with rental status as well
as basic infrastructure. The department relies on government budget and housing revolving
fund to finance housing. A national level CHDB bank has already been established and has
come into operation since January 2014. It has disbursed development loans to housing
developers and mortgage loan to home buyers.
The department is considering to establish a National Housing Fund with capital
surplus from Housing Revolving Fund, that was established during the heyday of the
department. The fund will finance housing.
Housing finance is the linchpin of a successful housing policy. It demands several
reform in the financial management of the economy and in establishing an effective regulatory
frame work. Without a functioning housing finance system in place, it is difficult to envisage
an effective housing delivery system. At present, financial market is poorly developed.
37
Secondary market does not exist. Thus, formal housing financial system will take some time to
mature.
In line with the reform strategy of the new government-economic liberalization,
decentralization, and privatization, the DHSHD has formulated housing policy and undergone
regulatory and organizational changes. Reform strategy will pave a way to the emergence of
housing finance mechanism, resulting in well-functioning housing sector and low and middle
income people who cannot afford the housing supplied by the market are mainly targeted to
fulfill low cost and affordable housing. It is, therefore, a potential for housing market to be
stable and an opportunity for low and middle income people to own or rent a formal decent
housing. The following diagram shows government’s vision to achieve the goal of housing for
all.
38
Table (3.3.7) Strength and Weakness of Government Funding
- Easy to get budget -Revolving fund is not -not pay rental charges
funding for low cost limited but is not subsized for
housing housing
-Infra cost (1.5) billion -insufficient cost of -try to get more infrastructure cost
kyats was allowed by infrastructure especially ( Budget) to Parliament
Parliament in 2010-12 water supply
Year.
39
Applicants must follow rules and regulations that forbid them to resell, sublet or
mortgage the housing within 5 years starting from the date of his or her possession. If he or
she fails to follow the rules, the unit will be confiscated, and moved out from the apartment, as
well as he will be enlisted in the blacklist.
If the home buyer takes the housing loan from CHDB bank, he must make agreement
with DHSHD and CHDB bank both. According to repayment schedule, the buyer has to pay
down payment that is equal to 30% of house value and the remaining 70% is payable in
monthly repayment within four years with an annual interest rate of 9% and services charge of
1% in the first year and 5% interest rate in the next three years. Eligible criteria for home
buyers can be summarized as follows:
- Applicant must be Republic of the union of Myanmar’s nationality. (show with copy of
NRC card or household ratification)
- Must be over 30 years of age.
- One household one applicant
- If government servant, who must be at least 10 years in service
- Applicant must be head of household and no home in YCDC area.
- This affordable housing is targeted to low-income government servants, pensioners,
company staffs and other low-income people (who has regular income level), so that;
(a) Applicant of Government low income servants must be accomplished with
recommendation of head of department. (show with labor card copy)
(b) In case of pensioners, copy of pensioners’ book and household certificate must be
presented.
(c) If the company staffs, must be show head of company recommended.
(d) As for low income people, two recommended persons are needed for regular
income.
- These affordable housing is available in two ways
(a) monthly installment for four consecutive months step
(b) mortgage loan from CHDB bank
- To purchase the affordable housing unit, the applicant’s household
Income should be kyat 5 lakhs and kyat 7 lakhs per household.
40
- The apartment is not allowed to be transferred within five years. If he fails to follow,
he will be removed from the apartment.
- After 5 years, he may resell his apartment.
- The housing unit can be bought with 4-month installment from the DHSHD.
- If bank loan is preferred, the CHDB bank will offer bank loan payable in four years
with the following rules ,
(a) Cash down payable 30% of housing price and bank service charges 1%.
- Loan payable 70 % with interest rate of 9 %in first year, 5% in second, third, and
fourth years.
- Home buyer who takes housing loans must make mutual contract with both DHSHD
and CHDB bank.
Home buyers can pay in two ways:
(1) Payment in four installments for four consecutive months, and
(2) Payment by housing loan.
For home buyers who take housing loan from CHDB bank, payment schedule
is calculated based on room price, down payment, interest rate and repayment period of
the bank loan. Payment schedule for housing loan is shown in table (3.3.8) and table
(3.9).
41
2 Yearly Rent Deposit
(a) 2nd yr 5% 3.85 3.95 4.02 4.20
(b) 3rd yr 5% 3.85 3.95 4.02 4.20
(c) 4th yr 5% 3.85 3.95 4.02 4.20
Total rent (4 yrs) 19.58 20.09 20.45 21.36
3 Monthly Deposit
(a) Asset value 1.60 1.64 1.67 1.75
(b) Rent per month 0.32 0.33 0.34 0.35
Total 1.92 1.97 2.01 2.10
4 (a) Total rent 19.58 20.09 20.45 21.36
(b) Capital 110.00 113.00 115.00 120.00
Total Payment 129.58 133.09 135.45 141.36
Source: DUHD
42
(c) 4th yr 5% 4.06 4.17 4.27 4.37
Total rent (4 yrs) 20.65 21.20 21.72 22.24
3 Monthly Deposit
(a) Asset value 1.69 1.74 1.78 1.82
(b) Rent per month 0.34 0.35 0.36 0.37
Total 2.03 2.09 2.14 2.19
4 (a) Total rent 20.65 21.20 21.72 22.24
(b) Capital 116.00 119.00 122.00 125.00
Total Payment 136.65 140.20 143.72 147.24
Source: DHSHD
44
- In terms of payment option, 67% of home buyers are willing to pay in four
month installment to DHSHD, and remaining 33% prefer to take housing loan
from CHDB bank.
- Although eligible criteria for home buyers are prescribed, it cannot be practiced
on sale of housing.
(4) Housing survey was conducted by DUHD since in 2014 on 4641 households from
13 townships in Yangon City with high population density and lower middle income
households live in order to provide low cost and affordable housing for the public in
need of housing among 13 townships. – Dawbon, Thaketa, Thingangyun, Dagon
(South), Dagon (North), North Oakkalarpa, Ahlone, Kyimyindine, Sanchaung,
Kamaryut, Hlaing, Insein and Hlaing Tharyar, the highest population live in Dagon
(South) with 297884 people, followed by Hlaing Tharyar with 295345 people. The
number of households is the highest in Hlaing Tharyar with 62178, followed by
Dagon (South) with 59467 and North Oakkalapa with 58344. Survey was undertaken
based on the number of houses so as to find out the housing conditions of the
populace.
45
Table (3.3.11) Strength and Weakness of Market
- Less homeless and - Not easy to get money - Need to reduce less than 100
slums from low income people lakhs for one unit
46
3.8 Related with Final Completion Cost
One building cost is about (2181.14) lakhs. The total floor area is 12992 sqft , the unit
area is 468 Sqft and the floor area cost is 13.75 USD. Thus one unit cost is ( 6435 USD) 77.22
lakhs.
Table (3.3.12) 6 units 4 Storeyed RCC Building cost
47
Chapter (4)
4.1 Findings
Summary Of Results
Technology
-Conventional
method
Material
- Project has not far from raw material
Raw material
 and very cheap labor cost
-Avoid use timber for deforestation
Contractor
LCS (Lease cost
selection)
KMM company
ATY company
KN company  - not created new technology and
they emphasis profit of a project
Land Acquistion
Government land
48
Permit / Approval Â
- Very easy to get permit from local
authority because of low cost housing
Government - Government fund is limited but
Funding  infrastructure cost was subsidized by it.
In order to complete the project without cost overran, reworks must be avoided as much as
possible. Moreover, Variation Orders (VO) should be confirmed by the responsible engineers
to get claim. The engineers for cost estimating of tendering are also an important one to
calculate efficient project cost with profit. In construction projects, there are many items to
waste and only a good project manager can control to minimize the wastage. The plan for
sequence of activities must be correct to reduce undesirable cost overran.
As for the Low cost project, the meeting should be held at least (4) times during
construction period. Therefore, this meeting should be held quarterly or once in every six
months depending on construction period.
49
(b) Related to Design
Before the construction is started, PEP must be prepared by the project manager. In relation
to quality of the finished buildings, PEP must include PQP, in which the necessary documents
for quality such as ITP, the procedure for CAR whenever NCR is issued by quality consultant
are added. And then ITP must also include witness point, hold points and the inspection
procedures. In order to get good quality product, both construction materials and workmanship
must be checked and inspected properly.
One important item to get good quality is the attitude of contractors according to the design.
Some contractors want to keep their dignity and good reputation, they want to make every
work qualified even though there is no one to inspect. Whereas most contractors want to get
cost effective and do not want to care their quality and used to do just acceptable and difficult
to ask rework for defects.
50
own, not every family can afford the housing the market supply. Majority of households prefer
to own a house while the other small segments of households are willing to rent a house. It is
clear that a large segment of households still rely on rental housing due to their low
affordability although they desire to purchase low cost affordable housing. More than half of
the households focus on low cost housing. As they are migrants from States and Regions and
want to settle down in Yangon, they are willing to purchase a house for their permanent
settlement at the price of less than K 100 Lakhs. Households cannot purchase an apartment in
cash payment because the unit prices of the apartment far exceed their monthly expenditure. If
they do not get installment, they would turn to government rental housing if provided.
Providing affordable housing has become an urgent task for Myanmar government.
Affordable housing development targeted to low income people established in late 2012 is
facing many weaknesses and challenges at its initial stage of development. For the sustainable
development of affordable housing available and accessible to low income people in terms of
both supply expansion and increase in affordability, the following recommendations are
proposed, based on findings on current housing development process in Myanmar and
international experiences of affordable housing development.
(e)Related to Material
In technical sustainability is very important for low cost housing. It implies good quality
materials and serviceability in the environment.
The important of material in construction involving such as cement, sand, aggregate stones,
steel, form-work, bamboo for scaffolding etc. The owner can issue the material buying
procedure even before the selection of a contractor in order to avoid low grade materials,
shortages and delays. Shortages may delay work, thereby wasting labor resources or delaying
the completion of the entire project. The building will not be completed by using low grade
material and impure water in construction. The cost of materials is based on prices obtained
through effective bargaining. The transportation costs are directly proportional to price of
materials. The material resources are as close as possible in site, higher prices of material
cannot occur. MOC should help to pass for tax of construction material in this project.
51
(f)Related to Loan
The project is mainly designed to accommodate low income families, including government
employees and pensioners, who cannot access and afford the housing offered in the market, to
make sure that affordable housing units are reached out to low income people needing home,
eligible criteria for home buyers are prescribed.
Applicants must follow rules and regulations that forbid them to resell, sublet or
mortgage the housing within 5 years starting from the date of his or her possession. If the
home buyer takes the housing loan from CHDB bank, he must make agreement with DUHD
and CHDB bank both. According to repayment schedule, the buyer has to pay down payment
that is equal to 30% of house value and the remaining 70% is payable in monthly repayment
within four years with an annual interest rate of 9% and services charge of 1% in the first year
and 5% interest rate in the next three years. Goals of low cost housing project have to reduce
slums, squatters and to increase good opportunity for occupation and development for country.
Most of buyers (Low income people) like housing loan with low interest rate and long-term
repayment. Most of buyers are generally low income people if the interest rate is high and
repayment is short-term, they cannot possess the apartments. DUHD should strive that buyers
can get housing loan with low interest rate, down payment and long-term repayment (20 years
to 30 years). CHDB bank should have to improve bank system more and more and join link
between local bank and international bank for mortgage loan to low cost housing project.
52
The contractors should be followed rule and regulation, fidic (International Federation of
Consulting Engineers) and contract agreement. In tradition construction approach, The
contractors should be afforded (a)well defined scope (b) clear risk allocation and should be
avoided (a) poor information input from construction expert (b) take long period of time (c)
costly change order (d) lack of training (e) poor cleaning and safety in site .
53
(e) Where housing projects are implemented by the government, it is suitable to
practice inclusionary zoning and high-density zoning system to expand the
affordable housing supply. To accomplish zoning system, developers should be
given incentives such as tax deductions, density bonus, direct subsidies, land
grants and bureaucratic and administrative streamlining to reduce processing
costs and time at the central and local level.
(f) The National Housing Agency could be in charge of the preparation and
execution of a National Housing Plan, coordinating central, local and municipal
inputs and their respective financial contributions, and fostering the
participation of the private sector and not-for profit organizations. In addition,
the agency could also take on the role of a national mortgage agency for
affordable housing, in addition to supporting other initiatives to ease the access
of the lowest-income groups to housing finance.
(g) In order to increase affordable housing supply to lower middle income group, it
is recommended that the cost of land and infrastructure should be subsidized to
reduce the unit cost of housing; launching ppp housing projects the profit from
which are cross-subsidized to low cost affordable housing; execute mixed
development projects where low cost housing are proportionality produced by
developers, and encourage redevelopment of public rental housing estate in
deterioration to expand the supply of housing. Reconstruction projects
including the demolition of low-quality housing and slums should aim at
replacing demolished units with affordable housing for the affected persons.
Existing tenants should also be given priority in the allocation of the new units.
(h) It is difficult to envisage a reasonably effective housing delivery system
without a functioning housing finance system in place. It is required to
establish housing finance mechanism, to improve low-income group’s access to
financing. Housing development fund, housing provident fund, housing
mortgage loan with low interest rate and longer term repayment are also
appropriate provided target and eligibility criteria are clearly defined and
strictly enforced. Tax exemption on imported construction material and tax
reduction on domestic building material industry is also required.
54
(i) The government should demarcate the public land and set aside the land
necessary for road, drainages, public open space and to the possible extent,
housing development. It is also recommended to improve the existing land
management system.
(j) Government should endeavor to encourage the innovations in manufacturing
and application of building materials through innovative designs, quality
control, and mass production that can reduce the cost of construction and hence
cause the housing unit price to fall down in terms of economy of scale.
It is literally different from "low-cost housing" or “subsidized housing”, where there is
a strong element of the public sector subsidizing private citizens who have no means of
affording housing on their own means. In such cases, it is common to find that relatively cheap
housing is developed without much consideration of its sustainability.
The low cost housing on the other hands include multi-dimensional factors to put into
consideration which include income levels of target buyer group, consumer buying power,
availability of financing, interest rates, construction cost, land supply, and housing prices.
Such considerations are many and they are all interwoven.
One of the biggest problems that lower and middle income households face today is
finding affordable and appropriate housing which they can live and work for long term.
Suffice to say that a sustainable housing development is more than a roof over head. It
involves and encompasses economic viability, social and environmental sustainability. People
must be able to afford it, they must also be willing to stay there and call it their home.
As a developer attempting to develop a project to meet such challenges, there is a need
to consider many factors other than costs and profits. The key to success requires the
developer to have a broader perspective and understanding of social needs balanced with
market sentiments.
55
Appendix (1) Shwe Lin Pan low Cost Housing Master Plan
pau ;- wpfv u fr =200 ay
, ,
a&Tv i fyef;pu fr IN
rd
KU
?wefzdk;en f; t dr f&mpD
rH
udef;
Ad
kv fat mifau smfv r f;wH
PHASE-II
PHASE-I TYPE-B 8U-4S Residential &G floor shop 4-nos.(112 units) TYPE-B 8U-4S Residential (540 sft) &G floor shop = 5 nos (140 units)
6U-4S Residential Bldg (468 sft)/ Hall TYPE-A 8U-4S Residential Bldg 12-nos.(384 units) PHASE-IV PHASE-III- Project Description 7.4 acres
32 nos -768 units 9.5 acres (including road area)
wm;
9.0acres
10.3 acres total units = 496 units.
6U-4S Residential Bldg (468 sft) = 21 nos (504 units)
t &H
x m;&Sd
ajr
Total number of Buildings = 644 nos
Total number of Rooms = 26 nos
Uti li ties
a&Tv i fyef;acsm
i f;
&Jpcef;
qdkif P ark
rD
;o wf
a&Tv i fyef;acsm
Cant een Rel igious
i f; Ins ti tu ti onal
yef;N
cH
pm
;ao m uf yef;N
cH
a&Tv i fyef;b kef;Bu D
30'
qdkif
pm;ao mu fq dkif
yef;N
cH
v rf;)
U ti li ties
fay;ao m
41
wm;
35 42
;q u fo G
,
36
Ad
U ti li ties
m
oD
u smfv rf;t
72'-58"
46 t &H
xm;&Sd
ajr
kv fat mifa
90'-816"
48 COMMERCIAL
5
45 Ad
;v r f;ESifh
13
U ti li ties
30' 21'-116"
7
m
;(u sefppfo
1
40 43 44 18'-9 " 47
;au smif;
v rf;o G
39 16
34 37 38 30'
ay60v rf
-4 N Os
30'
33
U ti li ties
30'
, f-1
GT GT
30' GT GT
TYPE B
12'
52'-916"
s
GT GT
-12 NO 16'
GT GT
16'
15
TYPE A
16'
yef;N
cH
aq ;ay;cef;
a&Tv i fyef;t r u
u sefppfo m;v r f;
TOTAL PROJECT AREA = 36.74 acres
56
Appendix ( 3 ) 8 Units 4 Storeyed Low Cost Building’s Floor Plan
57
Appendix ( 4 ) 6Units 4 Storeyed Low Cost Building
124'
W2 W2 F F W2 W2 W2 W2 F F W2 W2 W2 W2 F F W2 W2
8'
KITCHEN KITCHEN KITCHEN
13' W2 BATH BATH BATH BATH BATH BATH W2
26'
LIVING ROOM LIVING ROOM LIVING ROOM LIVING ROOM LIVING ROOM LIVING ROOM
13'
UP
UP
D1 D1 D1 D1 D1 D1
W2 W1 W1 W2 W2 W1 W1 W2 W2 W1 W1 W2
58
Appendix ( 6 ) 6Units 4 Storeyed Low Cost Building’s View
59
Appendix ( 7 ) 8 Units 4 Storeyed Low Cost Building’s View
60
Appendix ( 8 ) 6 Units 4 Storeyed Building’s Foundation
61
References
62