New Microsoft PowerPoint Presentation-1
New Microsoft PowerPoint Presentation-1
LOCATION MAP
First of Its Kind The NH-566 ROB-II Bridge is the first cable-stayed Railway Over Bridge (ROB) in India
on a curvature, with a radius of 180 meters.
DESCRIPTION OF BRIDGE
Center Span 78 m Foundation
Back Span 2*46 m (Pile Foundation)
Total Length 170 m Pile Dia. 1m
Radius of curve 180 m Nos of Pile 14 each
Super Elevation 3.8% Pile cap Shape Octagonal
Height of Pylon 35 m
Sub-Structure
RCC Concrete M60
Tie Beam Size(L*W*H) 28.7*3.8*2 m
Main Girder 60 Nos
Cross Girder 114 Nos
Stay cable 52.5 MT.
Total Concrete Quantity 5200 Cum
Total HYSD steel for ROB-II 900 MT
Total Structural Steel 1750 MT
SOIL INVESTIGATION AND TESTS
Standard Penetration Test Dynamic Pile Load Test
The limited space between piers P124 and P125 Two 80 MT cranes were used for launching the
required the use of the end-on method for erection main girders. In areas with tighter space limitations,
and launching. This involved erecting temporary a 250 MT telescopic crane was utilized. The
staging for each girder sequentially and then erection activities over the existing ROB were
moving backward to repeat the process. conducted during late-night hours to avoid
inconvenience to road users & railway movements
and safety standards were thus met.
Safety at work
Erection challenges were met without LTA in
the construction of complex structure.
9 Million safe working hours were achieved
without any accidents.
STAY CABLE INSTALLATION PROCESS
STRAND PREPARATION
Strands cutting was carried out in factory with anti-slip keys fixed on the strands.
Strand cutting length formula:
L= L0+2*(A1+L1) in which
L0——Center line distance between bearing plates of stressing and fixed end (mm),
offered by design.
A1——Length of anchor head (mm);
L1——Length for stressing operation, normal it's 1.5m;
PE sheath at both anchoring ends were removed to calculated length, which will be satisfied
stressing requirement.
PE sheath cutting length calculation:
LS=A1+A2+L1-L2
A2——Length of sealing socket
L2——Length of PE sheath in sealing socket
Strand Cutting Procedure
A) Cautions to strand cutting work:
I. In case of PE sheathing damage occurs, repair were carried out immediately, severe
damaged strands were rejected.
II. Careful check was essential to ensure cut length was accurate.
C. After removing PE sheathing, unwind the stranded steel wires, clean off the wax at
both ends. The galvanized layer was carefully protected from damage during
cleaning. Steel wires was winded back after cleaning.
D. Cutting the out ring 6 wires of strand in 12cm, keeping the center wire and head
button by Head button device LD10K (for strand towing).
Strand Threading and Installation
Preparation of Strand Threading Installation of Stressing Jack Chair
Under 100 meters cables , manual pushing by the workforce is
For Individual strand stressing operation, the
typically sufficient, for cables exceeding 100 meters, methods such
Jack Chair was installed before cable installation.
as cyclic threading or continuous threading are more efficient and
The Jack Chair has screw to connect with the
reduce labor requirements.
anchor head.
The selection of the lifting equipment should account for the initial
stressing force of the first strand and the weight of the strands to be
cyclically threaded.
Winches or strand-pushing machines should be positioned
strategically for safe and efficient operation.
Installation of Stressing Anchorages
Anchor holes should be aligned with holes of sealing plate. Deviation in Holes position is not allowed, trial thread should be
through with a strand.
Anchor holes should be clean to assure its anchoring performance
Fix the sealing plate with stretch tube which is socketed by dot welding to avoid loose contact and corresponding potential
risk during installation.
Adjust the nut at stressing end during stressing.
Before positioning the anchorage ,clean the guide pipe and drainage outlet at lower end.
Anchorages shall be set at top surface of bearing plate at outside pylon. Three centering blocks shall be temporarily welded
on bearing plate, which shall be removed after the first strand be stressed. Use chain block to let anchorage into guide pipe.
During installation, have the grouting port at a lower position and avoid damage on the thread.
Anchorage holes array of both ends shall be horizontally placed and aligned identically by aligning Centerline of both ends
anchorage with that of embedded bearing plate, the deviation shall not be more than 5mm.
The hole of anchorage and saddle should be aligned with each other.
HDPE Pipe Installation
Strand Threading and Stressing
Step 1
Inject special wax into the inner space of the
anchorage.
Step 2
Install caps at both stressing and fixed ends,
filling them with wax.
Wax filling
The Wax filling machine will be used to ensure the anchorage would be completely filled with wax.
Construction Control
2 Inject Wax/Grease
3 Apply Pressure
5 Finish Grouting
Anti-corrosion Measures for Exposed Components
2 Loading Stages
• Apply load in stages: 25% (60MT), 50%(120 MT), 75%
(180MT), and 100%(240 MT).
• Due to Railway tract below, instead of dial gauges prism
was fixed above top of main girders.
• 8 No. of vehicles having weight of 30 MT each totaling
to 240 MT load were placed on specified location a
shown in the Picture.
3 Deflection Monitoring
• During the entire loading and unloading process the
readings were recorded @ one-hour interval.
• During the 100% loading the maximum deflection w at
critical section was 41 mm against the theoretical
deflection as shown in fig.was 44.1 mm which was
within the permissible limit.
4 Recovery
The bridge successfully completed the load test with a
recovery of 95.84%.
Challenges Faced During Execution
Dense Reinforcement
Cup-lock system for bar lap was used due to limited space in the pylon.
Inclined Pylon
Separate support system was used to keep reinforcement in an inclined position.
Restricted Area
Carrying out erection work over the existing ROB during late nighttime due to space constraints was a major
constraint.
Curvature Alignment
Carrying out cable stressing in a cross method to stabilize the structure.
Conclusions
6 95.84%
Cables Stressed Recovery
After stressing six cables, the The ROB II Cable Stay Bridge was
maximum movement in x, y, and z successfully completed with a
directions was 6 mm, 9 mm, and 11 recovery of 95.84%.
mm, respectively.
AERIAL VIEW OF THE PROJECT WITHIN VASCO CITY
AERIAL VIEW OF ROB-2
AERIAL VIEW OF THE PROJECT
AERIAL VIEW OF THE PROJECT
AERIAL VIEW OF THE PROJECT
AERIAL VIEW OF FAÇADE LIGHTING
VIEW OF FAÇADE LIGHTING
Thank You