National University of Study and Research in Law
Ranchi
CASE ANALYSIS
M/S. Kailash Nath Associates vs Delhi Development Authority & Anr on 9
January, 2015
SUBMITTED TO: SUBMITTED BY:
M/S. SONI BHOLA SHRUTI MINZ
ASSISTANT PROFESSOR OF LAW SEMESTER-II (1560)
1
M/S. Kailash Nath Associates vs Delhi Development Authority & Anr on 9
January, 2015
INTRODUCTION
The present civil appeal arose from a Special Leave Petition (SLP) [(Civil) No. 32039 of
2012]. The case presents a question of law that arose by the circumstances in the present case,
where the Delhi Development Authority (hereinafter, DDA) enters into a contract with a
corporation for the auction of a plot of land for a large sum of money.
As the facts and evidences are presented before the courts, various questions and contentions
appear, which pose a substantial question of law on certain provisions of the Indian Contract
Act, 1872 (hereinafter, Act, 1872).
FACTS OF THE CASE
In a public auction for a plot of land, by the DDA, the appellant, Kailash Nath Associates
made the highest bid for a sum of rupees 3.12 crores. The plot of land was referred to as “Plot
2-A’ situated in New Delhi. The appellant was asked to deposit earnest money, amounting to
25 percent of the amount of the bid, with DDA. Such money was to be paid either in cash or
by demand draft according to the terms and conditions of the auction. The receipt of such
money was acknowledged by DDA on 18th February,1982, and the bid was hereby accepted.
The appellant was directed to pay the residue of the amount, i.e. 75 percent by 17th May,1992.
However, a general recession had taken over the industry due to which the appellant made
representations to DDA in May 1992, seeking extension of such period. To enquire into the
matter, DDA set up a high-powered commission to explore the possibility of such an
extension to the appellant. In a letter by the commission, it gave its recommendation of
extending such a period for payment up to October 1992, along with a rate of interest of 18
percent per annum, which could reach up to 36 percent per annum.
Further, the DDA referred the matter of extension to the Ministry of Urban Affairs
(hereinafter, Ministry) for further examination. This information was conveyed to the
appellant using a letter, wherein it was asked to furnish consent for making the balance
payment with interest within 3 days of receipt of the letter. The appellant provided its consent
to do so and asked for the schedule of the instalments to be made in this behalf. Meanwhile,
the Ministry informed DDA that it had no say over the matter since the given plot of land was
not Nazul land as per prevailing rules and regulations.
The appellant filed a writ petition in the Delhi High Court, under Articles 226 and 227 of the
Constitution of India requesting that new plots of lands be allotted to it, as done in case of
bidders in a similar situation. Article 14, seeking equal treatment by DDA being a public
authority was pleaded. During this time, DDA had auctioned the Plot 2-A for an amount
2
almost three and a half times more than the amount agreed originally between DDA and the
appellant.
ISSUES OF THE CASE
Adjudicating the writ petition, High Court maintained that since the matter was of the nature
of a contract entered into by two parties, in their respective capacities, there lay no
jurisdiction of this court in the matter. There was no force in the appellant’s contention to
invoke Article 14 in the said matter. The court further dismissed the SLP to induce action for
the forfeiture of earnest money deposited by the appellant. However, the appellant was
entitled to file a suit for specific performance of the contract, seeking no additional damages.
Such suit was also dismissed by the Learned Single Judge, but a refund of the earnest money
was ordered with an interest rate of 9 percent.
The following issues emanate from the above proceedings:
Whether Article 14 of the Constitution applies to a body like the DDA, since it
represents itself as a party to the contract in the present case?
Whether Section 74 of the Act, 1872 can be applied to contract(s) demanding
forfeiture of earnest money upon breach of the terms of the contract?
Whether time is an essence of contract between parties in the said case, and does it
remain so throughout the performance of the terms? Or when extension is sought for
performance?
JUDGEMENT
The Apex Court referred to several precedents to conclude whether time was an essence of a
contract seeking payment of a sum within previously stipulated time, as consideration for the
contract. It referred to the judgment in Anandram Mangturam v. Bholaram Tanumal, the
court had pronounced that if time was the essence of a contract, then it must not be waived by
a unilateral act of one of the parties. It can be waived only when both parties consent to such
waiver, reaching consensus ad idem. Time shall no longer remain essence if negotiations go
on while time passes in tranquillity without coming into question. However, it is imperative
to note that a purchase contract must be materialised at some point, it cannot go on till
eternity.
In the present case, there was no breach on part of the appellant since the letter of
cancellation of the bid and subsequent forfeiture was made at the behest of DDA, without
notice to the appellant to deposit the remainder of the purchase amount, i.e. 75 percent.
Therefore, earnest money was not to be forfeited as no breach arose.
As per the judgment in Keshavbhai Lallubhai Patel and Ors. v. Lalbhai Trikumlal Mills
Ltd.[2], time could not be extended to make payment for the purchase without both the
3
parties, namely the buyer and seller agreeing to such extension. However, this would apply
only if the benefit of the extension accrues to the promisee. In the present case, DDA was the
promisee and the appellant was the promisor, in such circumstances, DDA had the liberty to
unilaterally extend the period for payment since the benefit accrued to the promisor directly
in the given circumstances of general recession as claimed by the appellant in his
correspondences. As per the judgment delivered in Citibank N.A v. Standard Chartered
Bank, unilateral acts by parties are valid, under Section 63 of the Act, 1872.
As to the applicability of Article 14, the court observed that the provision intends to eliminate
any kind of arbitrariness from administration, and provide equal, just, and fair treatment.
Therefore, the provision shall be applicable upon DDA, and writs under Articles 226 and 227
shall be allowed.
With respect to the applicability of Section 74 of the Act, 1872, the court observed that it
shall be applicable in cases of forfeiture of earnest money. There exists no breach on the
appellant’s part and the fact that DDA suffered no loss but made a whopping profit out of the
transaction is irrelevant. The law does not provide for a windfall in case of breach when no
damages are suffered by one of the parties to the contract.
CONCLUSION
The case of Kailash Nath Associates v. Delhi Development Authority revolves around
the principles of procedural fairness in administrative law. In this case, the Delhi
Development Authority (DDA) cancelled the land allotment to Kailash Nath Associates
without providing them with an opportunity to present their case or be heard. The Supreme
Court's decision emphasized the importance of adhering to principles of natural justice,
particularly the right to be heard, in administrative actions. The court held that the DDA's
decision to cancel the allotment without affording the petitioner a fair chance to present their
case was arbitrary and unreasonable. This case highlights the significance of procedural
fairness in administrative proceedings. It underscores the need for administrative bodies to
follow fair procedures when making decisions that affect the rights of individuals or entities.
Upholding procedural fairness helps ensure justice, transparency, and accountability in
administrative actions. Moreover, the case serves as a precedent for future administrative law
cases, reaffirming the courts' role in scrutinizing administrative decisions to ensure they are
made fairly and in accordance with the principles of natural justice.
4
5