RA - Installation of Above Ground UPVC Pipes For Rain Water
RA - Installation of Above Ground UPVC Pipes For Rain Water
Page 1 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Describe Activity and Location Risk Assessment for Aboveground UPVC Pipes for Rain Water network
Prepared by Name Sundar Designation HSE Manager Date and Signature 02/09/2024
Approved by Name Tareq Al Sebai Designation Project Manager Date and Signature 02/09/2024
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 2 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Activity:
• Unauthorize • OSHAD approved • PTW shall be
d entry (PTW third party obtained only by
has not certificates required competent and
obtained) for equipment and authorized person.
• Unsafe operator from ADM • Only approved
driving approved /certified vehicles
• Speeding OSHAD-. SF)– consultancy. and equipment
• Poor road CoP 53.0 - • Softeners to be used shall be used
• Fatigue
condition • Injury/ Fatality OSH while securing the • All the vehicles in
Mobilization • Fall of load
equipment, • Untrained/ • Incident/ Management load to avoid the working area
• Run over
1. Transporting Unlicensed Accident During damage. shall have reverse
High
Low
• Vehicle Y 4C 3C 1C 3C 1C 1C 1C 1C
of Materials drivers • Asset / Construction • Appropriate Fire alarm.
collision
to Site • Materials Equipment Work. Extinguisher (DCP) • Vehicles should be
• Falling into
not properly damage OSHAD COP shall be available on entering one by one
excavations
loaded/ 44 Traffic all vehicles/ to the location
secured Management. equipment and in site • Vehicle in good
• Absence of in an easily accessible mechanical
guide/escort location. condition.
• Inexperience • All drivers/ operators • Ensure load is
d/ Untrained shall be competent. properly secured
workers • Vehicle to be with slings/chains
inspected for safety.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 3 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Medium
2. compliance to site entry.
Low
Site Visit control • Property CoP 2– PPE Y 3C 2C 1C 3C be with the site 1C 1C 1C 1C
• Lack of site • Induction tag should
• Lack of site Damage mandatory PPE
rule and site be conspicuously
induction
hazard displayed on their
awareness helmet.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 4 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Very High
structure third-party • Asset and deployed for task at
3. Equipment
Low
• Run over inspection equipment OSHAD-SF - Y 5C 4C 1C 3C site must be trained and flash lights to 1C 1C 1C 1C
and
• Falling into company. damage CoP 44 – and competent be provided in
Operatives excavation. • Unauthorize • Overturning Traffic enough to carry out vehicles route
d entry of equipment. Management during night shift.
the task safely.
• Incompeten • Fatality
and Logistics • All excavation to be • Baton lights to be
t operatives
properly barricaded provided for
• Lack of
compliance and open manholes flagman at night
to site to be covered. shift.
traffic rules • Provide separate • All vehicles and
• Unawarenes equipment to be
pedestrian and
s of hazard installed with
vehicles routes.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 5 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Hazardous
Adequate
substances to be
Firefighting
stored according to
equipment’s are
Material Safety Data
available near to
Sheet provided by
the storage.
supplier.
Avoid storing the
Substances to be in
package in a place
original container
exposed to direct
with clear labels and
sunlight; store it in
hazard warnings – no
well ventilated, cool
decanting
and dark place
injuries OSHAD-SF – Restricted access.
Hazardous Drinking water
Fire property CoP 1.0 Store to be locked
4. and chemical Jointing bottles should not
High
Low
explosion damage Hazardous Y 4C 3C 1C 3C except when in use 1C 1C 1C 1C
Materials materials. use for storage of
spillage environmental materials Minimize che
Storage chemicals.
pollution Designated storage
SDS guidelines to
area will be provided
be followed.
for chemical storage.
COSHH assessment
Spill tray shall be
to be done prior to
providing to avoid
use of any
chemical spillages.
hazardous
Incompatible Paints
chemical.
should not store
3rd party COSHH
altogether.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 6 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
Low
scaffolding. OSHAD-SF - Y 4C 3C 1C 3C 1C 1C 1C 1C
mobile • Falling objects disability, protection for all inspected by
• Improper CoP 23 –
Scaffolding • Collapse of work at edge on roof. authorized 3rd
scaffolding. Materials and Working at
temporary • Handrails to be used party certificate
Edge property Height for scaffolding. holder of
platform.
protection is damage • Proper Housekeeping scaffolding
not proper. • Safety helmets and inspector.
protective footwear. • Appropriate load
• Cross bracing shall be rating.
provided. • Workers instructed
• Base jacks shall be on not to interfere
proper surface. with or misuse
scaffold
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 9 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
Low
Ground • Fatality Y 4C 3C 1C 3C 1C 1C 1C 1C
MEWP/ breakdown / Working at • Ensure all the PTW levelled and if
condition • Crushing
Manlift Mechanical Height assigned in the site necessary
• Bad • Emergency rescue compacted
failure
Weather plan shall be
• Tilting/Tipping
condition communicated to all
workers involved in
the activity,
furthermore, project
emergency response
plan shall also be
communicated.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 10 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Medium
9. keeper. carried
Low
Working with falling from way • Facture Height Y 2C 2C 1C 3C 1C 1C 1C 1C
ladder height. • Slippery or • Injury to the OSHAD-SF - • Step ladder must • Do not erect in
fully open and lock slippery, uneven
• Over reaching uneven person CoP 37–
and the devices to be surface
surface. Ladders as per manufacturer. • Defective ladder
• Do not work from the should not be used
top of two rungs and report it
immediately.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 11 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
Medium
10. Manual equipment • Task Analysis for the utilized, be mindful
Low
• Fall of • Equipment/ Manual Y 2C 2C 1C 3C 1C 1C 1C 1C
handling • Not wearing lifting load to be of the person next
material material Handling and
• Leakage and suitable PPE conducted for to you, keep away
damaged Ergonomics
Spillage • lifting of • Close Supervision your hands and feet
materials • Training provided in from pinching
with more HSE inductions and points
than 20 kgs tool box talks – • Maintain adequate
of weight workers to lift with work supervision
their knees and not • Tripping hazards
their backs shall be eliminated
• Maximum lifting load via Good
weight for single Housekeeping.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 12 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
Low
• Ergonomics training on l Impact Y 4C 3C 1C 3C 1C 1C 1C 1C
(loading & Management should be exclusive mandatory PPE.
• Fall of safe lifting • Property
offloading) and Logistics to those performing
material techniques damage
OSHAD-SF - the task only
• Leakage and • Lack of
• Unloading area
Spillage securing the CoP 14 –
should be barricaded
• Slip, Trip & load Manual and provided
Fall • Lack of Handling and adequate sign
inspection Ergonomics • Adequate training to
workers on safe
lifting technique
should be ensured.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 13 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
hurry • Personal
Low
Manual Y 4C 3C 1C 3C 1C 1C 1C 1C
material • Lack of injuries Proper signage Emergency lights
hoses etc • Storing Handling and
supervision provided for storage. shall be installed in
materials on Ergonomics Adequate lighting the stores.
access
shall be Stopper shall All electrical
• Block access be provided to avoid connections shall
roll of pipes be routed properly.
safe manner and as
per standards.
Appropriate PPE to
be worn while
handling materials.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 14 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
Low
Power Tools Y 4C 3C 2C 3C • Hearing aid to reduce 1C 1C 1C 1C
equipment • Ejection inspection • Equipment • No octopus
• Fire & • Incompeten damage OSHAD-SF - noise exposure connection allowed
Explosion t user • Property CoP 24 – • Equipment must be at site.
• Flying object • Lack of damage LOTO suitable for the task • Ensure Proper
safety • Adequate connection with
device in supervision single industrial
place • Equipment must be socket only.
used by a competent
person
• Adequate training,
instruction and
information must be
given to equipment
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 15 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
High
Low
53 OSH Y 4C 3C 1C 3C information 1C 1C - 1C
Work snakes and facilities Property movement need be
Management provided to
scorpions). Poor damage controlled by
During Contractor and
distraction emergency flagman
Construction necessary permits
preparedne • Flagman shall be
Heat and cold as applicable shall
ss Work provided with
stress. be obtained from
• Poor flashing batten stick.
• Accidents authorities
visibility • Lone working not
concerned.
permitted in the site
for night shift
• 3thd party Trained
first aider from ADM
approved training
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 16 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
• Rest Area
• Cool Drinking water
• Mid-Day Break Rule
• Heat stroke. implemented
• Confusion. • Ensure all operatives
• Heat Stress are acclimatized of • Appropriate
• Nausea the working training shall be
• Stroke environment. given to all
• Dehydration. • Exhaustion • Drinking water employees working
• Heat Stroke OSHAD-SF -
• Burns. • Collapse availability and in high
15. Working in • Fatality CoP 11-
High
Low
• Falling • Rapid weak Y 4C 2C 1C 3C operatives to drink temperature. 1C 1C 1C 1C
hot weather • Heat related Safety in heat
• Fall of person pulse water as frequently • Medical assistance
illness
• Head ache. as possible. ORS to be utilized
• Weakness • Take regular breaks in • When feel unwell,
• Mussels hot weather. inform to
Cramps • Appropriate training supervisor.
• Vomiting shall be given to all
• Unconscious employees working in
high temperature.
• Medical assistance
ORS to be utilized
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 17 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
• Weather condition
must be monitored
daily, work ban
timings implemented
• Poor
strictly during
visibility OSHAD-SF -
summertime from
• Working in • Slippery CoP 11-
June 15-September • Provide heat stress
adverse floor Safety in heat
15 of the year 12:30- training and
weather • Heat stress • Fatality
3:00PM for all emergency
condition e.g. illness • Injury OSHAD-SF
external works, heat response training
16. Adverse sand storm, • Dust • Work Delay, Technical
High
Low
Y 3C 1C 4C 3C stress prevention to workers, TWL 1C 1C 1C 1C
weather high wind, • struck by • Property guidelines –
program level monitored
extreme lightning damage 13.0 – Dealing
implemented, stop every 2 hours and
temperature, • fall from with adverse
all lifting operation communicated to
rain, heights & weather
during thunderstorm, workers
thunderstorm falling condition – V
all work at heights
object due 3.0 2017
activity not limited to
to high wind
roof work and
scaffolding works are
not allowed during
heavy rain.
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 18 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Legal
Risk Assessment Residual Risk Assessment
S Existing Legal Compliance Additional Controls
Hazard Title Hazard Detail Causes Consequences Existing Controls
No. Requirements Proposed
Y N P A E R RI P A E R RI
• Daily clean-up is to
• Slips and
be performed
Trips OSHAD-SF – • Walkways will be
• Housekeeping • Injuries • Personnel will wear
17. • Sharp-edge 54 – Waste kept clear at all times
High
Low
Housekeeping & waste • Cut Y 3C 2C 3C 3C suitable PPE at all 1C 1C 1C 1C
cuttings Management • Proper disposal of
disposal • Broken bone times
• Accumulatio wastes as per
n of waste contractor Waste
Management Plan.
• Delay in
notification /
response
• Lack of OSHAD-SF – • First aid shall be • In case of any
common 4- First Aid provided if necessary emergency
• Movement of • All work will be
resources and Medical workers shall
heavy stopped and staff /
• Unsafe Act • Lack of or Emergency report immediately
equipment workers assembled
18. Emergency inadequate to AD Port duty
High
Low
• Collision of and Treatment Y 4C 2C 1C 4D in nearest assembly 1C 1C 1C 1C
Response emergency phone number
mobile Condition OSHAD-SF – point.
equipment (0505567243) &
equipment 6- Emergency • Emergency vehicle
• Language AD Port Control
barrier Management should be available Room on 800112
• Fatality requirement on site
• Personal
Injury
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 19 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Step 1: Identify Hazards Title (e.g. Physical Hazard, Fire Hazard, and Electrical Hazards).
Step 2: List Hazards Details identified (e.g. Tripping Hazard, Flammable Materials stored, Working in Electrical Cabinets).
Step 3: List Causes of Hazard (e.g. Untidy workplace, Hot work, un-isolated electrical supply).
Step 4: List Consequences of Hazard (e.g. Personnel Injury, Fire, electric shock).
Step 5: Determine Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk Assessment Matrix (Page 2) (this should be the most probable outcome without controls and should be listed as 2A,
3D etc.).
Step 6. Calculate the Risk Index using the Qualitative or Semi-Quantitative Risk Assessment Matrix as deemed appropriate. This is a product of Likelihood and Consequence and should be stated Low, Medium, High or Very High).
Step 7. List Existing Controls. (e.g. Tidy Site Policy, Hot Work Permit, Isolation of Electrical Supply).
Step 8. List Safety Critical Activities and Additional Controls that may be deemed necessary to reduce risk level to ALARP.
Step 9: Recalculate Likelihood and Consequences to People, Assets, Environment, and Reputation from attached Risk Assessment Matrix.
Step 10. Recalculate the Risk Index.
Step 11. If residual risk deemed to be High or Very High then risk must be reduced further before proceeding, if risk is medium then note that risk reduction must be planned, monitored and documented, if risk is low then risk is
acceptable without required further action.
Notes
ALARP
permanent HIGH
disability
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS
©2017 ABU DHABI PORTS , ABU DHABI, UNITED ARAB EMIRATES
System Title
Page 20 of 20
INTEGRATED HEALTH, SAFETY AND ENVIRONMENT STANDARD PROCEDURES Document No. ADM-FRM-005-1
Procedure Title
Effective Date 01 Jan 2018
Likelihoo
Descriptor to assist in Qualitative Assessment of Likelihood/ Frequency of Occurrence.
d
B Has occurred regionally within port industry or judged likely to have occurred.
C Has occurred in port industry within UAE or judged likely to have occurred.
D Has occurred in port industry within UAE on an annual basis or judged likely to have occurred.
Consequences People Environment Assets Reputation IMPROBABLE REMOTE OCCASIONAL PROBABLE FREQUENT
1 in 10,000 1 in 1000 1 in 100 1 in 10 Once in a
Years Years Years Years Year
A B C D E
ALARP
4 - Severe Single fatality or Major damage Major effect National impact HIGH
permanent
disability
1 - Negligible Slight injury or Slight effect Slight effect Slight impact LOW
health effects
DOCUMENT ELECTRONICALLY CONTROLLED - PRINTED COPIES VALID FOR FOURTEEN (14) WORKING DAYS