PV-Technical Specifications-Master File
PV-Technical Specifications-Master File
Page 1 of 1
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
Table of Contents
Contents
1. SCOPE ........................................................................................................................................................ 2
2. LIST OF STANDARDS .................................................................................................................................. 2
3. TERMINOLOGY .......................................................................................................................................... 2
1. MATERIALS ................................................................................................................................................ 3
Chemicals ........................................................................................................................................3
2. SUBMITTALS .............................................................................................................................................. 3
3. WORKMANSHIP ......................................................................................................................................... 3
3.1 Treatment for the building without basement ........................................................................3
Treatment to top surface of plinth filling .........................................................................................3
Treatment at junction of wall and floor ...........................................................................................4
Treatment of soil along external perimeter......................................................................................4
Treatment of soil surrounding pipes and conduits ............................................................................4
Treatment for expansion joints ........................................................................................................4
3.2 Treatment for building with basement ...................................................................................4
Treatment to soil below raft ............................................................................................................4
Treatment to soil along the retaining wall .......................................................................................4
Treatment to soil along the external perimeter of the building .........................................................4
Treatment of soil surrounding waste pipes and conduits ..................................................................4
3.3 Essential requirements ...........................................................................................................5
4. QUALITY MANAGEMENT ........................................................................................................................... 5
5. SAFETY CONSIDERATION AND REQUIREMENTS ........................................................................................ 5
6. ENVIRONMENTAL CONSIDERATIONS AND REQUIREMENTS ..................................................................... 5
10. . COMPLETION AND DELIVERY .................................................................................................................. 6
11. METHOD OF MEASUREMENT & RATE ....................................................................................................... 6
12. ANNEXURES ............................................................................................................................................... 6
Page 1 of 6
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
1. SCOPE
1.1 The anti termite treatment mentioned below is to create a continuous chemical barrier zone below
and around the building which is under construction and / or which has already come up-to plinth
level.
2. LIST OF STANDARDS
2.1 Work shall be carried out as per latest version of Indian Standards and Code of Practices. List given
hereunder is not to be considered as conclusive and is for reference and guidance only. Any
discrepancies /conflict noticed shall be directed to the Owner /Owner’s Authorized Representative
for his direction/approval. However as a general rule more stringent specification shall take
precedence.
1 IS 4015 (Part-I & II) Guide for handling cases of pesticide poisoning
2 IS 6313 (Part-I) Code of practice for Anti- termite measures in buildings
constructional measures
3. TERMINOLOGY
The following terms and abbreviations shall have the specific meanings as described hereunder. For
terms that are not described herein, the definitions as stated in the applicable Indian Standard
Specifications shall apply.
Plinth: a plinth is the base or platform upon which a column, pedestal, statue,
monument or structure rests.
Basement: Are one or more floors of a building that are either completely or partially below
the ground floor.
Retaining Wall: is built in order to hold back earth which would otherwise move downwards. Their
purpose is to stabilize slopes and provide useful areas at different elevations.
Page 2 of 6
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
1. MATERIALS
Chemicals
Spraying Equipment
A pressure pump shall be used to carry out spraying operations to facilitate uniform
spraying and penetration of chemical into the earth. The chemicals, concentration and dosage
for horizontal and vertical surfaces are based on the IS code of practice for Anti- termite
measures in Buildings. IS 6313 (Part-II).
2. SUBMITTALS
2.1 Contractor shall submit for approval of the Owner /Owner’s Authorized Representative all details of
Material / Product which conforms to the specification laid down in documents.
Submittals shall include
□ Product data sheet
□ Manufacturers certificates
□ Test report of laboratories
□ Alternative product if any with tabulation for confirmation that alternatives proposed
meets / exceeds specification.
2.2 The contractor shall submit the Schedule of work to be carried out.
3. WORKMANSHIP
The principle of the treatment is to create a continuous chemical barrier below and around the
building so as to deny entry to the subterranean termites into the buildings. Treatment is designed
depending on the type of building and is described below.
Page 3 of 6
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
the chemical emulsion at 5 liters per sq.m. Light roding may be carried out in the soil surface to
facilitate absorption of the emulsion.
Page 4 of 6
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
When waste pipes and conduits enter the soil inside the area of the foundation, the soil
surrounding the point of entry must be loosened around each such pipe, waste or conduit for a
distance of 15 cm and up to a depth of 7.5 cm and loosened soil shall be treated with chemical
emulsion.
4. QUALITY MANAGEMENT
4.1 The contractor shall provide experienced supervision and work force to ensure that workmanship
is of specified quality.
4.2 Work shall not be subjected to harmful, dangerous, damaging or deleterious exposures while it is
in progress or on completion during contract period.
4.3 Contractor to undertake quality assurance by documenting a comprehensive Quality Assurance
Plan.
Page 5 of 6
Anti-Termite Treatment Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/01 Technical Specifications
8.4 Care should be taken in the application of chemicals to see that they are not allowed to
contaminate wells or springs which serve as sources of drinking water.
Rate
The rate shall include the cost of all materials and labor involved in all the operations
described above including making holes and refilling and making good the same.
12. ANNEXURES
NIL.
Page 6 of 6
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
Contents
1. Scope ............................................................................................................................................. 2
2. Standards and codes ..................................................................................................................... 2
3. Terminology, definitions and abbreviations .................................................................................. 4
4. Materials........................................................................................................................................ 4
5. Submittals and Certifications required .......................................................................................... 7
6. Workmanship ................................................................................................................................ 8
7. Quality Management ................................................................................................................... 13
8. Safety considerations .................................................................................................................. 14
9. Environmental considerations ..................................................................................................... 14
10. Method of measurement ........................................................................................................ 14
11. Annexes ................................................................................................................................... 15
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
1. Scope
This specification applies to all concretes including Plain Cement Concrete, Reinforced Cement
Concrete and Pre-stressed Concrete. It covers all concrete made for the projects of Godrej
properties Ltd. and shall include concrete manufactured at site or procured through RMC plants
14 IS 3025 Methods of Sampling and test (Physical and Chemical for water
)
15 IS 4926 Specification for ready mixed concrete
4. Materials
4.1 Cement:
The type of cement to be used in concrete shall be as per the approved Concrete Mix Design.
Generally, the following types of cement may be used:
4.1.1 Ordinary Portland cement of grade 53 or 43
4.1.2 Portland Pozzolana Cement
4.1.3 Portland Blast Furnace Slag Cement
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
Cement shall be received in bags of 50 kg or loose in bulkers and each batch shall be
accompanied with a test certificate of the factory. In case cement has been stored for over 3
months or for any reasons the stored cement shows signs of deterioration or contamination, it
shall be tested as per the direction of Engineer, and will be used in the works only if found
suitable.
4.2 Coarse aggregate:
4.2.1 Coarse aggregate shall be obtained from natural sources such as stone, gravel, etc crushed or
uncrushed or a combination thereof from approved quarries. Aggregate shall be hard, strong,
dense, durable, and clean and free from veins and adherent coatings. It shall be free from soft,
feeble, thin, elongated or laminated pieces and shall be roughly cubical in shape. It shall consist of
coarse material, most of which is retained on 4.75 mm IS sieve and shall contain only as much fine
material as is permitted in IS 383 for various sizes and grading.
4.2.2 Coarse aggregate shall conform to all requirements laid down in IS: 383
4.2.3 The maximum size of coarse aggregate should not be greater than one fourth of the minimum
thickness of the member and it should be restricted to 5 mm less than the minimum clear
distance between the main bars or 5 mm less than the minimum cover to the reinforcement.
4.2.4 Source of aggregate shall be from an approved location. Each source of aggregate shall be
approved by Owner / Owner’s Authorized Representative on the basis of tests conducted on
samples of aggregates from the source at an approved testing laboratory. In case available
aggregates do not meet certain requirements of IS 383 or any other specification, required
processing shall be carried out by the contractor to make the aggregates conform to IS: 383.
4.2.5 Coarse aggregate shall have a specific gravity of 2.6 (Saturated surface dry basis). Aggregate
below this specific gravity shall not be used without the special permission of the Engineer.
4.2.6 Once a specific source of supply of coarse aggregate is approved, the source shall not be changed
without the prior approval of the Engineer.
4.3.7 Grading of fine aggregate shall conform to IS and shall fall within limits of one of the grading
zones given in IS 383. Fine aggregate falling in grading zone IV shall not be used in concrete.
4.4 Water
4.4.1 Water used for mixing and curing shall be clean, reasonably clear and free from
objectionable quantities of silt, oils, alkalis, acids, salts, sugar so as not to weaken mortar, or
concrete or cause efflorescence or attack the steel in RCC while curing. It shall be free of
elements, which significantly affects the hydration reaction or otherwise interferes with
hardening of concrete during curing or those elements which produce objectionable stains or
deposits.
4.4.2 Potable water is generally satisfactory but it shall be tested prior to use in the works.
4.4.3 Water used for mixing and curing shall satisfy the requirements of IS: 456.
4.4.4 Water shall be tested in accordance with IS 3025.
4.4.5 The PH value of water shall not be less than 6 nor more than 9.
4.4.6 The source of water shall be tested and got approved in writing from the Engineer prior to use in
the works.
4.4.7 Use of sea water shall not be permitted for any purpose related to making concrete.
4.5 Admixture
4.5.1 Admixtures shall be permitted to be used to modify the properties of concrete for single, or a
combination of purposes. This shall be used for specific purpose and the type and dosage of
admixture shall be as per the approved mix design of concrete.
4.5.2 Admixture shall comply with the requirements of IS: 9103.
4.5.3 Admixtures shall be free from chlorides and sulphates or any other material which may cause
problems to the concrete in the due course of time.
4.5.4 Admixtures are manufactured and sold by various companies under brand names. The contractor
proposing to use any one of them shall submit to the Engineer the technical literature with its
chemical composition, purpose of use and method recommended by the manufacturer.
4.5.5 The contractor’s proposal shall accompany the following with his request to use admixture.
4.5.6 The trade name of the admixture, its source and the manufacturer’s recommended method of
use.
4.5.7 Typical dosage rates and the possible detrimental effects of under and over-dosage.
4.5.8 Whether the admixture contains chloride in any free form or any other chemical present as an
active ingredient which is a likely cause of corrosion of reinforcement or deterioration of
concrete.
4.5.9 The average expected air content of freshly mixed concrete containing an admixture which causes
air to be entrained when used at the manufacturer’s recommended rate of dosage.
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
If required by the Engineer, contractor shall maintain and submit photographs indicating
compliance to various requirements of this specification and ITP.
6. Workmanship
6.1 Mix Design:
6.1.1 All concrete except that used in PCC and having grade more than or equal to M: 20 shall be made
as per approved mix design.
6.1.2 The contractor or the RMC supplier, as the case may be, shall submit the mix design document for
review and approval of the Engineer. The mix design shall be carried out by methods laid down by
Indian or International standard. In case the contractor / RMC supplier proposes to use his own
method of mix design, the step-by step method and various charts /tables used for the mixed
design shall be submitted along with the mix design document.
6.1.3 Unless otherwise permitted by the Engineer, the maximum content of fly ash /ggbs in the
concrete mix shall be limited to 35% by weight of total cementitious material. Content of micro
silica shall similarly be limited to 10% of total cementitious material.
6.1.4 Special characteristics of the concrete for specific situations like large pours [thermal properties],
long transportation distance [open time] etc. shall be identified, established and demonstrated
during the design mix approval process.
6.1.5 On review of the mix design document, trail mixes shall be carried out to validate the design mix.
The mix design shall be approved by the Engineer based on the tests conducted on the trial mixes.
6.1.6 Approval of the mix design by the Engineer shall not relieve the contractor / RMC supplier of their
responsibility to comply with the technical requirements.
6.1.7 In case of any major change in the constituent of the mix or required properties of concrete or
construction method, a new concrete mix shall be designed and got approved as per the
procedure detailed above.
6.1.8 Any modification in the mix, except for daily adjustment arising out of moisture content of the
aggregates, shall require the written approval of the Engineer.
6.1.9 Any concrete produced / delivered without the approval of the mix shall be liable to be rejected.
6.2.3 Needle vibrators shall conform to the requirements as laid down in IS: 2502 , screed vibrators to
IS: 2506 and form vibrators to IS: 4656. The vibrators shall be maintained so as to fulfil the
performance requirements laid down in the applicable I.S.
6.2.4 All equipments used for mixing, transporting and placing of concrete shall be maintained in clean
condition. All pans, buckets, hoppers, chutes, pipe lines and other equipments shall be thoroughly
cleaned after each period of placement.
6.2.5 All measuring devices shall be periodically calibrated and the calibration record maintained at all
time. The Engineer may disallow the use of any equipment if it’s effective is in doubt or if it has
not been calibrated.
6.5.5 Detailed information and guidelines, preferably in graphic format, dealing with the correct
method of carrying out the tasks shall be available and prominently displayed at the work place.
6.7 Transportation
6.7.1 All means of conveyance shall be adopted to deliver concrete of the required consistency and
plasticity without segregation or loss of slump whatever method of transportation is employed.
6.7.2 Concrete that has lost workability by the time it reaches the placement point shall be rejected.
Tempering of the concrete in the transit mixer by addition of water or cement slurry or admixture
shall not be permitted.
6.7.3 Placement: No concrete shall be placed in any part of the structure until the approval of the
Engineer has been obtained in writing.If concreting is not started within 24 hours of the approval
being given, it shall have to be obtained again from the Engineer-in-charge.
6.7.4 The open time of concrete shall be established and approved during the process of mix design.
Concrete shall be placed in the forms within such approved open time from leaving the mixer, and
once compacted, the concrete shall not be disturbed.
6.7.5 Concrete shall, in all cases, be deposited as nearly as practicable directly in its final position and
shall not be rehandled or caused to flow in a manner which will cause segregation, loss of
materials, displacement of reinforcement, shuttering or embedded inserts or impair its strength.
6.7.6 For locations where direct placement is not possible, and in narrow forms, contractor shall
provide suitable prop and Elephant Trunks to confine the movement of concrete. Special care
shall be taken when concrete is dropped from a height, especially if reinforcement is in the way,
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
particularly in columns and thin walls. Except when otherwise approved by Engineer-in-Charge,
concrete shall be placed in the shuttering by shovels or other approved implements and shall not
be dropped from a height more than 1.5 m or handle in a manner which will cause segregation.
6.7.7 Concrete may be conveyed and placed by mechanically operated equipment e.g. pumps or
pneumatic placers. In such cases, the slump shall be held to the minimum necessary for conveying
concrete by this method.
6.7.8 When pumping is adopted, before pumping of concrete is started, the pipelines shall be
lubricated with one or two batches of mortar composed of one part cement and two parts sand.
The concrete mix shall be specially designed to suit pumping. Care shall be taken to avoid
stoppages in work once pumping has started.
6.7.9 When pneumatic placer is used, the manufacturer’s advice on layout of pipeline shall be followed
to avoid blockages and excessive wear. Restraint shall be provided at the discharge box to cater
for the reaction at the end. Manufacturer’s advice shall be followed regarding concrete quality
and all other related matters when pumping/ pneumatic placing equipments are used.
6.7.10 Concrete shall be placed in successive horizontal layers of uniform thickness ranging from 30 cm.
to 90 cm. as per the approved pour plan. These shall be placed as rapidly as practicable to prevent
the formation of cold joints or planes of weakness between each succeeding layers within the
pour. The thickness of each layer shall be such that it can be deposited before the previous layer
has stiffened.
6.7.11 Placement of concrete shall normally be carried out when the ambient temperature is more than
10 degree Celsius and less than 40 degree Celsius. Provisions of IS: 7861 part 1 shall be followed
when placing concrete under hot weather and IS: 7861 part 2 when placing concrete under cold
weather conditions.
6.8 Compaction
6.8.1 Concrete shall be compacted during placing, with approved vibrating equipment, until the
concrete has been consolidated to the maximum practicable density, is free of pockets of coarse
aggregate and fits tightly against all form surfaces, reinforcement and embedded fixtures.
Particular care shall be taken to ensure that all concrete placed against the form faces and into
corners of forms or against hardened concrete at joints is free from voids or cavities. The use of
vibrators shall be consistent with the concrete mix and caution is to be exercised not to over
vibrate the concrete to the point of segregation.
6.8.2 Immersion vibrators shall be inserted vertically at points not more than 450 mm. apart and
withdrawn when air bubbles cease to come to the surface. Immersion vibrators shall be
withdrawn very slowly.
6.8.3 In no case shall immersion vibrators be used to transport concrete inside the forms. Particular
attention shall be paid to vibration at the top of lift, e.g. in a column or wall.
6.8.4 The immersion vibrator shall penetrate the layer being placed and also penetrate the layer below
while the under layer is still plastic to ensure good bond and homogeneity between the two layers
and prevent the formation of cold joints.
6.8.5 Care shall be taken to prevent contact of immersion vibrators against reinforcement steel.
Immersion vibrators shall not be allowed to come in contact with reinforcement steel after start
of initial set. They shall also not be allowed to come in contact with forms or finished surfaces.
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
6.8.6 When form vibrators are proposed to be used, the design of forms, spacing and type of vibrators
and their operating sequence shall be submitted for approval of the Engineer. If required, a mock
up shall be made to validate the process of form vibration.
6.8.7 Large flat elements of small thickness shall be compacted with screed vibrators.
6.9 Finishing
6.9.1 The type of finish for formed concrete surfaces shall be as follows, unless otherwise specified by
the Engineer.
6.9.2 For surfaces against which backfill or concrete is to be placed, no treatment is required except
repair of defective areas.
6.9.3 For surfaces below grade, which will receive waterproofing treatment, the concrete shall be free
of surface irregularities which would interfere with proper application of the water-proofing
materials which is specified for use.
6.9.4 Unless specified, surfaces which will be exposed when the structure is in service shall receive no
special finish, except repair of damaged or defective concrete, removal of fins and abrupt
irregularities, filling of holes left by form ties and rods and clean up of loose or adhering debris.
6.9.5 Surfaces which will be exposed to the weather and which would normally be levelled shall be
sloped for drainage. Unless the drawing specify a horizontal surface or shows the slope required,
the tops of narrow surfaces such as staircase treads, walls, curbs and parapets shall be sloped
across the width approx. as 1 in 30. Broader surfaces such as walkways, roads, parking areas and
platforms shall be sloped about 1 in 50.
6.10Curing
6.10.1 All concrete shall be cured by keeping it continuously damp for the period of time required for
complete hydration and hardening to take place.
6.10.2 Preference shall be given to the use of continuous sprays or ponded water, continuously
saturated covering of sacking, canvas, hessian or other absorbent materials. Special care shall be
taken of edges and corners of slabs to ensure the coverage of such places by curing water.
6.10.3 Extra precautions shall be exercised in curing concrete during extremes of cold and hot weather.
The quality of curing water shall be the same as that used for mixing concrete.
6.10.4 Concrete made with OPC shall be continuously cured for a minimum of 7 days and that made with
fly ash or ggbs shall be cured for a minimum of 10 days. Curing shall be un-interrupted and shall
also continue through the night.
6.10.5 The curing of horizontal surfaces exposed to the drying winds shall begin immediately the
concrete has hardened
6.10.6 Water shall be applied to formed surfaces immediately upon removal of forms. Surface coating
type curing compound shall be used only on special permission of Engineer. Curing compounds
shall be liquid type and pigmented.
6.10.7 No curing compound shall be used on surface where bonding with subsequent layer of concrete,
water proof membrane or paint is specified, unless the efficacy of bond between concrete cured
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
with curing compound and the subsequent layer / membrane is established to the satisfaction of
the Engineer.
6.10.8 Such compounds shall be applied to all exposed surfaces of the concrete as soon as possible after
the concrete has set or the forms are removed. Before application of the curing compound, it
shall be ensured that the concrete is in saturated surface dry condition.
6.11Construction Joints: The position and orientation of construction joints shall be as shown on the
drawings by the design engineer. In the absence of such information, the location of construction
joints shall be got approved from the Engineer.
6.11.1 The construction joints shall conform to the requirements stipulated in IS: 11817.
6.11.2 Construction joints shall be placed at accessible locations to permit cleaning out of laitance,
cement slurry and unsound concrete, in order to create rough/uneven surface. It is recommended
to clean out laitance and cement slurry by using wire brush on the surface of joint immediately
after initial setting of concrete and to clean at the same immediately thereafter. The prepared
surface should be in a clean saturated surface dry condition when fresh concrete is placed,
against it.
6.11.3 Where high shear resistance is required at a construction joint, suitable shear keys should be
provided.
6.11.4 If stopping of concreting becomes unavoidable anywhere, a properly formed construction joint
shall be made where the work is stopped. Joints shall be either vertical or horizontal, unless
shown otherwise in drawing. Vertical joints in walls shall be kept to a minimum. Vertical joints
shall be formed against a stop board, horizontal joints shall be level and wherever possible,
arranged, so that the joint lines coincide with the architectural features of the finished work.
7. Quality Management
7.1 The contractor shall put in place a comprehensive Quality management plan to ensure that the work
is carried out as per specifications and compliance to all requirements are established and
demonstrated through comprehensive documentation. The contractor shall engage a qualified Quality
Manager to implement the quality plan.
7.2 Unless annexed to these specifications the contractor shall submit an inspection and test plan [ITP] for
the approval of the Engineer. The ITP shall cover tests on incoming materials, supervision of the
process and test on the completed work.
7.3 The ITP shall lay down the characteristics to be tested/inspected, frequency of tests, acceptance
criteria and the manner of documenting the results. Any test, compliance to which is mandatory for
further progress of the next stage of work shall be identified as a ‘Hold point’.
7.4 In the absence of an approved ITP, provisions of IS: 456 and any other Indian Standard referred there
in shall apply with regard to acceptance criteria and tolerances.
7.5 In case of any dispute about the interpretation of the test results or inspection of the concrete, the
decision of Engineer shall be final.
Concrete Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/02 Technical Specifications
8. Safety considerations
8.1 Apart from general safety and health hazards like working at heights, falling objects etc., the
contractor shall assess the hazards associated with concrete works and shall take specific action to
mitigate against the same. Some of the hazards associate with rebar works are listed for general
guidance below.
a. Bursting of pipelines during pump concrete
b. Uncontrolled movement of end hose of the concrete pump
c. Inhalation of fine particles of cement, fly ash and micro silica
d. Hazard associated with the use of needle vibrator
All workmen shall be made aware of the specific hazards that they face while working with concrete
and shall be provided with specific personal protective equipment to protect them.
9. Environmental considerations
9.1 Apart from general environmental impact of construction activities, the contractor shall assess the
environmental impact associated with concrete works and shall take specific action to mitigate against
the same.
9.2 As a general guide, the following safety hazards are identified as associated with concrete
construction
9.3 Discharge of wash water from batching plant and transit mixers
9.4 Noise pollution due to operation of vibrators
9.5 Particulate pollution due to dust in the aggregates, cement, fly ash and micro silica.
9.6 Completion and delivery: Work related to concrete construction shall not be deemed as complete till
such time all the following conditions are fulfilled:
9.7 All concrete in various parts of the structure is shown to have complied with the compressive strength
requirement at 28 days.
9.8 There are no defects in the concrete or all defects are repaired to the satisfaction of the Engineer.
9.9 All quality tests and inspection records are furnished to the Engineer.
a. Ends of dissimilar materials e.g. joists, beams, posts, girders, rafters, purlins, trusses, corbels,
steps etc. Up to 500 sq cm. in cross section.
b. Opening up to 0.1 sqm. (1000 sq cm)
c. Volume occupied by reinforcement.
d. Volume occupied by pipes, conduits, sheathing etc. not exceeding 25 sq cm. each in cross
sectional area.
e. Nothing extra shall be paid for leaving and finishing such cavities and holes.
10.7 Rates: The unit rate for concrete shall include the cost of all materials, labour, tools and plant required
for mixing, placing in position, vibrating and compacting, finishing as per directions of the Engineer,
hacking of concrete surfaces if required, hydro test of water retaining structures,curing and all other
incidental expenses for producing concrete of specified strength to complete the structure or its
components as shown on the drawings and according to these specifications.
10.8 All expenses likely to be incurred by the contractor in transporting materials to the site of works, the
expenses incurred in improving the quality of materials to acceptable levels (such as screening,
washing, etc.) and expenses incurred in proper storage of materials as directed by the Engineer,
expense incurred in testing, supervision, Quality, Safety and Environment management, repairs etc.
are to be included in the unit rate.
11.Annexes
NIL
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
Contents
1. Scope ..................................................................................................................................................... 2
2. IS Standards ..................................................................................................................................... 2
3. Terminology .................................................................................................................................... 3
4. Materials ......................................................................................................................................... 3
5. Workmanship .................................................................................................................................. 4
6. Quality Management ...................................................................................................................... 7
7. Submittal & Certification Required ................................................................................................. 8
8. Safety Management ........................................................................................................................ 8
9. Environment Management ............................................................................................................. 8
10. Completion & Delivery ................................................................................................................ 8
11. Method of Measurement ............................................................................................................ 8
12. Annexures: NIL........................................................................................................................... 9
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
1. Scope
This specification applies to all reinforcement work provide in R.C.C. and Pre-stressed concrete
construction. It covers reinforcement work carried out with all grades of reinforcement steel and
applies to all projects of Godrej properties Ltd. It does not cover the work associated with
provision of high tensile steel bars, wires or strands used in pre-stressed concrete.
2. IS Standards
Work shall be carried out as per latest version of Indian Standards and Code of Practices. List
given hereunder is not to be considered as conclusive and is for reference and guidance only.
Any discrepancies /conflict noticed shall be directed to the Owner /Owner’s Authorized
Representative for his direction/approval. However as a general rule more stringent
specification shall take precedence.
3. IS 280 Specification for mild steel wire for general engineering purpose.
4. IS 432 Specification for mild steel and medium tensile steel burn and hard drawn
steel wires for concrete requirement.
Part 1 Mild steel and Medium tensile steel bars.
6. IS 816 Code of practice for use of metal arc welding for general construction in mild
steel
7. IS 961 Specification for structural steel : high tensile steel bars
12. IS 1786 Specification for high strength deformed steel bars and wires for concrete
reinforcement.
13. IS 2751 Code of practice for welding of MS bars.
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
14. IS 2502 Code of practice for bending and fixing of bars for concrete reinforcement.
17. IS 9417 Recommendation for welding cold worked steel bars for reinforced concrete
construction
18 IS 13920 Ductile detailing of RC structures subjected to Seismic Forces
3. Terminology
The following terms and abbreviations shall have the specific meanings as described hereunder.
For terms that are not described herein, the definitions as stated in the applicable Indian
Standard Specifications shall apply.
3.1 Reinforcement: is a common steel bar, and is commonly used as a tensioning device
in concrete structures holding the concrete in compression. It is usually formed from carbon
steel, and is given ridges for better mechanical anchoring into the concrete
3.2 Rust: is a general term for a series of iron oxides. In general usage, the term is applied to red
oxides, formed by the reaction of iron and oxygen in the presence of water or air moisture.
3.3 Splicing: Connection of two or more pieces of linear material.
3.4 Shop Drawing: is a drawing or set of drawings produced by the contractor, supplier,
manufacturer, subcontractor, or fabricator. Shop drawings are typically required for pre-
fabricated components.
3.5 Binding wire: is a steel annealed wire used to tie the rebar together at their points of
intersection with each other.
3.6 Cover block: Is a block of approved material and appropriate size used to position the rebar
such as to result in the required distance between the rebar and concrete surface [cover]
3.7 Coupler: Is a special mechanical splicing device used to connect two pieces of rebar placed
end to end. Couplers are used in place of laps
4. Materials
4.1. Rebar: Unless otherwise specified in drawings, the steel bars shall be of “High strength
deformed steel bars and wires” conforming to the IS 1786 (latest revision), in the following
strength grades:
a. Fe 415, Fe 415D;
b. Fe 550, Fe 550D; and
c. Fe 600
Where “Fe” stands for specified minimum 0.2% proof / yield stress in N/mm2 and
“D” stands for same specified minimum 0.2% proof / yield stress but with enhanced
specified minimum percentage elongation.
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
4.2. Binding Wire: The wires used for tying rebar together shall be 16 or 18 gauge, annealed
mild steel wires conforming to IS: 280 (latest revision). If specified in the BOQ the binding
wires may be PVC coated.
4.3. Cover Blocks: Cover blocks shall be of non-corrosive material such as mortar / concrete
blocks and plastic but not wooden or broken bricks or stone. Designed custom made PVC
cover spacers shall be permitted to be used in the Works.
4.4. Mechanical couplers: The Taper/ parallel Treaded Mechanical Splicing system should
conform to Type – II Mechanical Splice as classified under ACI-318 OF 2005, ( Defined as; A
full mechanical Splice shall develop in tension or compression, as required at least 1.25fy of
the bar and shall develop the specified tensile strength of the spliced bar)
Mechanical properties of the couplers shall be as under:
4.5. The Physical Dimensions (these are indicative & may vary from manufacturer to
manufacturer)of the couplers shall be as under:
2 20 27 71 29
3 25 35 85 35
4 28 38 91 38
5 32 44 96 40
5. Workmanship
5.1. Storage: Reinforcement bars received at site shall be stored clear of the ground with the
use of timber sleeper, concrete sleeper or any other means. Each diameter of bars shall be
stacked separately. In the event of the rebar having to be stored through the rainy season,
adequate protection shall be provided by way of coating of cement slurry and covering by
tarpaulin sheets.
5.2. Bar Bending Schedule: Unless provided by the Engineer, the contractor shall generate a bar
bending schedule showing the shape, size, cut lengths and other details of each bar type.
The bar bending schedule shall be submitted for the approval of the Engineer.
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
5.3. Cutting: All reinforcement shall be cut cold, unless otherwise permitted by the Engineer.
The cutting lengths of bars to be cut shall be calculated so as to result in the cut/bent bar of
correct dimensions facilitating the bars to achieve the desired cover when placed in the
forms. The ends of the bars shall be cut square and sharp edges, if any, shall be ground.
5.4. Bending:
5.4.1. All bars shall be accurately bent according to the sizes and shapes shown on the
detailed working drawing / bar bending schedules. They shall be bent gradually by
machine or other approved means. Reinforcing bars shall not be straightened and re-
bent in a manner that will injure the materials.
5.4.2. Bars containing cracks or splits shall be rejected. They shall be bent cold, except bars of
over 25 mm. in diameter which may be bent hot if specifically approved by the
Engineer.
5.4.3. Bars that depend for their strength on cold working shall not be bent hot. Bars bent
hot shall not be heated beyond cherry red colour (not exceeding 6450C) and after
bending shall be allowed to cool slowly without quenching.
5.4.4. Bars incorrectly bent shall be used only after straightening and re-bending such as not
to injure the material. No reinforcement bar shall be bent when in position in the work
without approval, whether or not it is partially embedded in hardened concrete. Bars
having kinks or bends other than those required by design shall not be used Placing &
Tying
5.4.5. Where reinforcement bars are bent aside at construction joints and afterwards bent
back into their original position, care should be taken to ensure that at no time the
radius of the bend is less than 4 bar diameters for plain mild steel or 6 bar diameters
for deformed bars. Care shall also be taken when bending back bars to ensure that the
concrete around the bar is not damaged.
5.5.7. It should be ensured that the ends of the binding wire are turned inwards and do not
project into the cover region.
5.5.8. Reinforcement rods which are likely to remain exposed for a period of more than 3
months shall be adequately protected against corrosion by painting them with a coat
of cement wash.
5.5.9. Unless otherwise specified, reinforcement shall be placed within the following
tolerances:
5.5.10. Tolerance in spacing
5.6. Cover
5.6.1. Nominal cover is the design depth of concrete cover to all steel reinforcements,
including links. It is the dimension used in design and indicated in the drawings. It shall
be not less than the diameter of the bar.
5.6.2. The amount of cover to reinforcement shall be as shown on the drawings. In the
absence of this information on the drawings, cover shall be provided as per guidelines
of IS 456.
5.6.3. The actual cover provided shall be not less than the cover shown on the drawing nor
shall it exceed the nominal cover by 5mm.
5.6.4. The correct cover shall be maintained by cement mortar cover blocks or other
approved cover blocks. When precast concrete blocks are used to provide the cover,
their strength shall be equal to or more than the strength of concrete in the member.
5.6.5. The strength and spacing of cover blocks in slabs should be adequate to sustain the
load of the reinforcement cage and other construction loads imposed on it.
5.6.6. Cover blocks shall be properly tied to the reinforcement in such a manner that they
cannot be displaced from their position during erection of reinforcement, formwork
and during concrete placement.
5.7.5. When splicing of welded wire fabric is to be carried out, lap splices of wires shall be
made so that the overlap measured between the extreme cross wires shall be not less
than the spacing of cross wires plus 100 mm.
6. Quality Management
The contractor shall put in place a comprehensive Quality management plan to ensure that
the work is carried out as per specifications and compliance to all requirements are
established and demonstrated through comprehensive documentation. The contractor shall
engage a qualified Quality Manager to implement the quality plan. Till such time a Quality
Management Plan and ITP is approved, the following provisions shall apply.
6.1. The rebar shall be procured only from pre-approved manufacturers. Rebar shall not be
procured from secondary manufacturers / re-rollers unless approved in writing by the
Engineer.
6.2. Contractor shall procure and provide reinforcing steel bars conforming to IS specified and
shall comply with all physical, chemical and mechanical tests. Bars without “ISI’ /
identification marking shall not be brought to site.
6.3. Any rebar brought to site shall not be used in the works unless its characteristics are tested
and found complying with the requirements of the applicable specifications. Till such time
the rebar is not permitted to be used in work, it shall be separately stored and identified to
preclude its use.
6.4. Unless specified agreed in the approved ITP, at least one sample shall be drawn from every
50 MT of rebar received at site of each diameter.
6.5. Cover to rebar shall be ensured by providing adequate numbers of cover blocks and chairs.
At the time of approval of the pour card, integrity of the cover blocks and their spacing shall
be inspected to ensure that they have not been displaced during installation of formwork.
6.6. The position of the rebar shall be inspected after placing concrete in the forms to ascertain
that the rebar are not damaged or displace from their original position and the desired
cover has been achieved.
6.7. Any rebar that has been installed in the works but is likely to exposed for a prolonged
period before concreting takes place shall be protected by application of a coat of water
cement grout.
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
8. Safety Management
Apart from general safety and health hazards like working at heights, falling objects etc., the
contractor shall assess the hazards associated with concrete works and shall take specific
action to mitigate against the same. Some of the hazards associate with rebar works are
listed for general guidance below.
a. Touching of hot objects
b. Flying sparks, metal chips or pieces
c. Piercing by falling or tripping on sharp objects
9. Environment Management
Apart from general environmental impact of construction activities, the contractor shall assess
the environmental impact associated with rebar works and shall take specific action to mitigate
against the same. Some of the environmental aspects associate with rebar works are listed for
general guidance below.
10.1. There are no defects in the rebar work or defects have been rectified to the satisfaction
of the Engineer. Specifically, the cover required for the rebar should have been achieved as
per permissible tolerances, as seen after the completion of concrete pour.
10.2. The concrete of which rebar forms a part has been accepted by the Engineer, unless the
rebar is meant to be permanently protruding outside concrete
10.3. All quality documents, test certificates have been submitted
11.1. Lengths of different diameters of bars actually used including authorized overlaps shall be
measured nearest to a centimeter and their weight calculated.
11.2. If rebar is procured by the contractor, weight per metre given in table 3.8 shall be used.
Rebar Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/03 Technical Specifications
11.3. If rebar is supplied by the client free of cost on tonnage basis to the project site, per
metre weight for each diameter of the bar shall be fixed by the Engineer from actual
stocks of steel available at site or weight per meter given in table 3.8 shall be used.
11.4. Chairs and spacer bars shall not be measured and paid for. For reconciliation purpose it
will be taken into account, if steel is supplied free of cost by the Owner.
11.5. In case of welded coupled joints, measurement for payment shall be equivalent to the
length of overlap, as per design.
11.6. Quoted rates shall include, in addition to cost of material,
a. Cover blocks
b. Cutting, bending, placing and fixing in position.
c. Binding wire as approved.
d. Cleaning of bars
e. Decoiling of steel
f. Double handling if any.
g. All necessary scaffolding
11.7. In case rebar is supplied by the Owner free-of-cost, the quoted rate shall include, in
addition to 4a) to 4d) above, loading, Transportation & Unloading from Owner’s store to
work site and returning surplus material back to store.
Contents
1. Scope........................................................................................................................................................................ 2
3. Terminology ............................................................................................................................................................. 3
4. Material............................................................................................................................................................ 4
5. Submittals ........................................................................................................................................................ 6
6. Workmanship .......................................................................................................................................................... 6
7 Quality Management............................................................................................................................................. 13
11 Measurements ........................................................................................................................................... 17
12 Annexures .................................................................................................................................................. 19
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
1. Scope
This specification applies to requirements for providing, fabricating and erecting of
Cast-in-situ formwork and all other supports to the concrete during its setting and
subsequent removal of forms and applies to all projects of Godrej properties Ltd
2. List of Standards
Work shall be carried out as per latest issues of Indian Standards and Codes of Practices.
The list of Indian Standards given hereunder is not to be considered as conclusive and
is for reference and guidance only. Any discrepancies/conflict noticed shall be directed
to the Owner/Owner’s Authorised Representative for his direction/approval. However
as a general rule the more stringent specification shall take precedence.
3. Terminology
3.1 Back form: Formwork to the top surface of a sloping slab
3.2 Bearer (Runner): Horizontal member supporting joists.
3.3 Bracings: The system of members, usually diagonal, which acts in compression or
tension and stiffens a frame against deformation.
3.4 Diagonal: Member transferring horizontal and wind loads through props.
3.5 False work (staging, centering): Temporary structure used to support a
permanent structure during erection and until it becomes self-supporting.
3.6 Formwork (Shuttering): is the term given to either temporary or
permanent molds into which concrete or similar materials are poured.
(Ref: Annexure Image no E,F & G)
3.7 Four way head: To support to I-section beams below slab or beam bottom.
3.8 Joist (Batten): Horizontal member supporting sheeting (slabs & beams).
3.9 Prop base: Seating for prop( Punching shear).
3.10 Prop cap: seating for bearer. Prop footing (Spreader): Member transferring all
loads on unyielding strata.
3.11 Prop: Vertical member supporting bearer (Axial load)
( Ref: Annexures Image no A )
3.12 Reinforcement: is a common steel bar, and is commonly used as a tensioning
device in concrete structures holding the concrete in compression. It is usually
formed from carbon steel, and is given ridges for better mechanical anchoring
into the concrete.
3.13 Riband: Horizontal member laid flat to resist horizontal pressure from formwork.
3.14 Scaffolding: is a temporary structure used to support people and material in the
construction or repair of buildings and other large structures. (Axial load)
( Ref: Annexures Image no B )
3.15 Sheeting (Sheathing): Supporting membrane in contact with the wet concrete.
3.16 Shikanja: To hold the two opposite formwork or to hold the two right angle
formwork.
3.17 Soldier: A vertical member, acting as a beam or cantilever, and used in
conjunction with form ties or struts to support and prevent movement of forms.
3.18 Starter (Kicker): Small height of wall or column cast along with the footing.
3.19 Stop-end (Bulkhead): Vertical formwork to form a construction joint in concrete.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
4. Material
4.1 Material used in form work shall be a combination of timber, plywood, steel props,
steel plates, or specially designed and manufactured moulds of plastic or reinforced
fiber glass or steel or aluminum alloy or a combination of these.
4.2 Use of timber shall be limited to beam bottoms and runners; it shall not be used for
soffit of slab, except in edge panels.
4.3 Use of material shall depend upon its location, type of finish specified and subject to
acceptability by the Owner/Owner’s Authorised Representative. Recommendations
are as under:
a. Steel Props:
Heavy duty, drop head and adjustable type or as per standard system to be
adopted.
b. Steel Plates
MS angles 45 x 45 x 4 mm thick frame work with minimum 16 gauge thick sheet.
c. Ply wood -
Marine ply - Plastic coated
- 12 mm thick with timber framing for sides of beam
- 18 mm thick with timber framing for beam bottom and wall panels.
- 12/18 mm thick for slab depending upon slab thickness and supporting
system.
d. Bracing
40 NB medium duty MS steel pipes with clamps.
NB (Nominal Bore) is pipe size specified with two non-dimensional numbers.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
e. Timber
I.Jungle wood timber in the form of planks and battens (runners), which are
strong, durable.
II.Teak wood /good quality jungle wood shall be used for special decorative
moulds. Moulds used in work shall be smooth planed or finished with
laminate.
III. Silver wood shall be used for bracing to raker props, walkway battens and
planks, beam bottom topi etc.
4.4 System /Form work designed with proposed material in use shall be able to retain
its shape, lines, and dimensions as shown in the approved drawings. It shall safely
carry the full load of concrete together with any live load and impact loads likely to
occur during concreting, especially when concrete pumps and large buckets with
crane are deployed.
4.5 Material used shall conform to appropriate Indian Standards. It shall be the solely
the Contractor’s responsibility to entirely achieve the standard expected and to the
satisfaction of the Owner/Owner’s Authorised Representative.
4.6 Standard rolled steel sections shall be used with due fabrication for standard special
moulds, unitized form work scaffolds, staging, etc.
4.7 System
Patented, proprietary designed, metal (steel, aluminum or fiber glass) form work
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
5. Submittals
5.1 The contractor shall maintain a comprehensive record of the formwork material as
per the approved ITP. All records shall be in hard copy, signed by the Quality
manager, unless electronic records are permitted by the Engineer.
5.2 Submittals shall include
5.2.1 Product data sheet
5.2.2 Design & drawing of proposed formwork system
5.2.3 Manufacturers certificates for Plywood
5.2.4 Test report of laboratories for Plywood
5.2.5 Pre Pour Check list
6. Workmanship
6.1 Designing
The Contractor shall design, draw, prepare and submit method statement backed by
designed calculations, taking into account the points noted in clause 6 hereinbelow at
least six weeks prior to the start of any activity Or as per approved schedule. Required
drawing and sketches shall be enclosed along with statement for the proposed area to
be taken up for working. The statement shall give
Loads considered
6.1.1 Materials proposed
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
6.2 Experience
The Contractor shall provide
6.2.1 Site supervisors and foremen who shall be well qualified and have an experience
of at least 5(five) years on similar nature of form work.
6.2.2 Semi skilled/skilled labour shall have a minimum experience of 3(Three) years in
doing similar nature of form work.
6.3 Supervision
The Contractor shall be responsible to provide experienced foremen (with at least Five
years’ experience) in supporting/executing similar nature and magnitude of work and
the latter shall be able to read drawings and shall be capable of guiding and getting
work executed to desired quality.
6.4 Equipment
The Contractor shall provide all required tools, plants, equipment including their proper
maintenance during construction at site.
6.8 The Contractor shall account for all material and labour etc. to achieve the above
finishes to the satisfaction of the Owner/Owner’s Authorised Representative.
a. Erection of form work may be from pre-moulded, pre-fabricated, pre-assembled
plates or forms reasonable enough to transport and erect at site to correct line
and level as set out at site.
b. Supports shall be firm and maintained in position by nails, cross bracings, tie
rods, locking bolts and nuts. It shall be rigid and stiff so as to retain its shape
during and after concreting.
c. Joints between adjacent shuttering plates shall be water-tight and no cement
slurry shall be allowed to slip through. This shall be achieved by providing foam
tapes between two plates. Joints of shuttering plates for the all slab soffits not to
be plastered subsequently shall be ground flush to achieve even and smooth
surface.
d. Pre-fabricated or site forms shall be assembled in such a way, so as to ensure de-
shuttering without any jerk to the green concrete. For this purpose, double
wedges shall be used. Wedges shall be nailed, with the nail heads reasonably left
out, allowing easy removal while de-shuttering.
e. Pre-fabricated or on-site fabricated forms shall be of sufficient thickness and
with the required supporting runners in either direction. Supporting runners
shall be standardized in size for easy replacement and universal use at site.
f. Props shall be of steel only. Their spacing and size shall be as per approved
design. Care shall be taken to ensure that all props are installed in plumb. The
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
base of the props shall be a proper steel plate or timber plank, for equal
distribution of load.
g. In repeated use, panels shall be clearly marked for using at defined locations.
h. Successive lift shall be tightened with previous lift by fixing foamed strips at
joints to avoid slurry leakage.
i. Infill pieces and panels shall be well dressed, leveled and jointed with main
formwork so as to achieve smooth, even natural finish.
j. Props, soldiers, wailings, shores, bearers, clamps, wall & ties etc. shall be
provided at required spacing as per approved scheme.
k. Inserts and pockets shall be provided and fixed to correct line and level and with
sufficient rigidity to keep them in position while placing concrete and when
vibration is in progress.
l. Sloping, brackets, chhajjas, etc shall be well secured and firmly restrained.
m. Adequate access and working platforms shall be arranged with required safety to
avoid reinforcement displacement, damage to shuttering and easy movement of
concrete gang.
n. Props and scaffolds are to be erected to correct plumb, lines, and levels and with
required ties. Load carrying capacity of props shall be as per recommendations
of the manufacturer.
o. Props and scaffolds shall not be loaded beyond their permissible capacities as
allowed by manufacturer of props /scaffolds. No additional prop or support
beyond what is shown on the approved drawing/scheme shall be erected.
p. Heavy, medium and light duty props shall not be mixed up.
q. Beams and slabs shall have a camber of 4 mm per meter subject to a maximum
of 20mm or as directed by the Owner/Owner’s Authorised Representative.
r. All angles and corners shall be sharp and well defined. In places where concrete
edges are permanently exposed and require no further treatment, they shall be
chamfered in a triangle of 25x25mm.
s. Steel props shall be provided with adequate horizontal and cross – bracing as per
approved design/scheme using steel pipes and steel couplers.
t. At the design and erection stage, the following additional points shall be
considered and incorporated into the shutters.
u. Openings for cleaning prior to start of concreting.
v. Pouring points shall avoid high drops and provide easy access to vibrator
needles.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
6.9 Surfaces shall be treated with Form release Agents or emulsion as approved by the
Owner/Owner’s Authorised Representative prior to laying of reinforcement. The
following point shall be observed very carefully:
6.9.1 Joints of mould shall be water-tight. It is easy to check from bottom by
making sure that no light is visible.
6.9.2 Props shall be on solid base, be in plumb, in one straight line, and braced
horizontally and diagonally as per approved design / scheme.
6.9.3 Tie bars in beams, walls and columns shall be at the correct place and
fully tight.
6.9.4 All saw dust, dirt; shavings and any other unwanted materials shall be
cleaned and hosed out preferably using compressed air.
6.9.5 Provision shall be made for observing form work while concreting and
any other platform needed for movement of workers without any
disturbance to the reinforcement.
6.10 Opening/inserts
All required openings and pockets shall be provided as detailed in the drawing. The
Contractor shall provide for the required materials, labour for fixing and supporting
during concreting, in his quoted price. It is imperative that all openings and pockets
shall be de-shuttered with care and all corners of openings shall be preserved. All
openings/pockets shall be in a correct line and level. After concreting, the openings
shall be secured by proper covering against any accident and guard rail and warning
notice, if any, will be provided.
6.11 In case of multistory building, any upper floor shall be suitably supported on at
least one floor below the same or as approved by the Owner/Owner’s Authorized
Representative. The concreting of upper floor shall be done only after concrete in
lower floors has attained the desired strength.
6.12 If formwork to columns is erected to the full height, one side shall be left open
and built up in sections as concrete pouring proceeds. Windows shall be left for
pouring concrete from the sides to limit the drop of concrete to 1 (one) metre or as
directed by the Engineer.
6.13 For liquid retaining structures no sleeves for through bolts shall be used nor shall
through bolts be removed. Bolts, in this case, shall be cut at 25mm. depth from the
surface and the hole made good by sand and cement mortar of the same
proportions as the concrete just after striking the formwork.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
6.14.3 For other cements, the stripping time shall be suitably modified in
consultation with the Owner/Owner’s Authorised Representative
/Owner/Owner’s Authorised Representative’s Authorized Representative.
6.14.4 Where the shape of elements is such that the form work has re-entrant
angles, the form work shall be removed as soon as possible after the
concrete has set, to avoid shrinkage or cracking that might occur due to
the restraint imposed.
6.14.5 For precast moulds, the stripping time shall be 24 hours. The mould may
be lifted and stored in the yard within 24 hours to 48 hours as approved
by the Owner/Owner’s Authorised Representative.
6.14.6 Invariably mortar curb is provided for curing of slabs by ponding water
Removal of side forms of peripheral beams damages the curbs. To
prevent this, removal of side forms at all such locations shall be done not
before 2 day of slab concreting.
6.14.7 Casting dates shall be written on all RC surfaces immediately after
stripping of formwork.
finished Condition. No additional cost due to this shall be paid by the Owner/Owner’s
Authorised Representative.
6.15.1 On completion of concreting, inserts shall be cleaned and required treatment
such as oiling, greasing, covering with plastic/plywood boxes, painting, etc. shall
be carried out by the Contractor subject to approval of the Owner/Owner’s
Authorised Representative. Inserts and pockets shall be protected from any kind
of damage during the course of construction.
6.15.2 Opening and pockets shall be de-shuttered with due care not to damage edges,
falling of debris within pockets etc. Further, all openings and pockets shall be
preserved, secured against accident by covering, putting up guard rails, warning
notice etc. as approved by the Owner/Owner’s Authorised Representative.
Guarding and protecting pockets shall be the responsibility of the Contractor at no
extra cost to the Owner/Owner’s Authorised Representative.
7 Quality Management
7.1 Checking prior to concreting
a. All props and struts are in plumb, at right spacing, properly tightened and locked.
b. Formwork is correctly aligned and leveled.
c. Stop ends are properly secured and sealed.
d. All ties are properly tightened.
e. All inserts, pockets etc are at desired levels and secured.
f. Joints are sealed so as to ensure no possibility of leakage of grouts
g. Reinforcement has proper covers and required spacers.
h. All forms are cleaned, free from rubbish, tie wires etc.
i. Proper access for concreting and compaction is available.
j. Required guard rails and toe guard are provided
7.2 The following gauges/templates shall be used by the contractor for ensuring
proper formwork. These gauges shall be made available for the Owner/Owner’s
authorized representative to check the formwork dimensions:
a. Cover vibrator gauge of 40mmX65mmX1200mm long.
b. Winged cover gauge for column cover for the full set of columns to be provided
and shall not be removed earlier than 4 hours before concreting commences.
c. Beam width gauge at the time of shuttering checking and before laying of
reinforcement for slab.
d. Wooden battens of various thicknesses for beam stopper to be placed at
construction joint locations.
7.3 Tolerances
7.3.1 Tolerance is a specified permissible variation from lines, grade or dimension given
in drawings. No tolerances specified for horizontal or vertical building lines or
footings shall be considered to permit encroachment beyond the legal boundaries.
Unless otherwise specified, the following tolerances will be permitted.
b. Variation from the level or from the grades indicated on the drawings
I. In soffits of slab, ceilings, beam and in arises
Upto 2.5 m span : 5 mm
Between 2.5 & 5m : 8 mm
Spans more than10 m : 10 mm
II. For exposed lintels, sills, parapets, horizontal grooves and other conspicuous
lines,
Upto 5 m span : 5 mm
More than 10 m span : 8 mm
c. Variation of the linear building lines from established position in plan and
related position of columns, walls and partitions.
I. In any bay up to 5 m maximum : 5mm
II. In 10 m or more : 10 mm
d. Variation in the sizes and locations of sleeves, openings in walls and floors 5mm
(except in the case of and for anchor bolts for which the tolerance shall be
1mm).
e. Variation in cross-sectional dimensions of columns and beams and in the
thickness of slabs and walls – 5 mm + 10 mm
f. Footings
I. Variation in dimension in plan
- 5 mm + 50 mm
II. Misplacement or eccentricity
2% of footing width in the direction of misplacement but not more than 50
mm
III. Reduction in thickness
5% of specified thickness subject to a maximum of 50mm
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
g. Variation in steps
Riser Tread
I. In a flight of stairs 3 mm 5 mm
II. Consecutive steps 1.5 mm 3 mm
e. Variation in the thickness of slabs, walls, arch sections, and similar members
:(-) 5 mm (+) 10 mm
All workmen shall be made aware of the specific hazards that they face while working with
formwork material and shall be provided with specific personal protective equipment to
protect them.
9 Environmental considerations
9.1 Apart from general environmental impact of construction activities, the contractor
shall assess the environmental impact associated with Formwork and shall take specific
action to mitigate against the same.
9.2 As a general guide, the following hazards are identified as associated with formwork.
a. Noise pollution due to operation
b. Formwork activity involves following type of waste :
I. Non-hazardous waste: like Scrap wood, Fixtures, Metal scraps, Electrical
wiring and components.
II. Hazardous waste like Used oil, solvents, sealers, thinners, Cleanup materials
(such as rags) contaminated with the items listed above Drums and
containers that once contained the items listed above.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
9.3 When wastes are produced at the site, the contractor or subcontractor who produces
the waste typically is responsible for ensuring its proper handling and disposal.
11 Measurements
Wherever it is not specifically stated in description of the item that form work shall be paid for
separately, the rate of R.C.C. item shall be deemed to include the cost of the form work.
11.1 Formwork shall be measured as the area (in square meters) of shuttering in contact
with the concrete.
11.2 It shall be measured to the nearest centimeter and the areas worked out corrected to
second decimal place.
11.3 No deductions shall be made for openings less than or equal to 0.4 sq m in size.
11.4 Formwork to secondary beams shall be measured up to sides of the main beams but no
deduction shall be made from the form work of the main beam.
11.5 No deduction shall be made from the formwork of column at intersection of the beam.
11.6 The quoted rate shall be applicable for all working conditions and heights, depths or
lifts specified in the BOQ. The rate shall include the cost of materials and labour for various
operations involved, such as, Splayed edges, notching, allowance for overlaps and
plastering at angles, battens, centering, shuttering, strutting, propping, bolting, nailing,
welding, casing, striking and removal.
11.7 Filling to form stop chamfered edges or splayed external angles not exceeding 75 mm
to footing and 25 mm to beams, columns and like. Temporary openings in the forms for
pouring concrete and removing rubbish.
11.8 Dressing with oil/approved emulsion/soap solution to prevent adhesion of concrete
with shuttering.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
11.9 Racking or cutting Fixing inserts and openings at the correct line and level and any
required stage to support the same at the directed height and place.
11.10 Platforms, if any, required to keep check on form while the concreting is in progress.
11.11 Filling and making joints water-tight to the satisfaction of the Owner/Owner’s
Authorized Representative or Owner/Owner’s Authorized Representative’s Authorized
Representative.
11.12 Cleaning the shuttering.
11.13 Inserts shall be measured by weight or enumerated as specified in the BOQ.
11.14 Any work damaged through premature or careless removal of form shall be removed
and reconstructed at the Contractor’s cost.
11.15 Holes for electrical conduits, hooks for fans and for plumbing shall be deemed to be
included in the price of items.
11.16 Precast units shall be measured as detailed in BOQ including Casting, lifting, curing and
stacking
11.17 Lifting and placing in position at various slab levels including required staging and
shuttering, and de shuttering for concreting.
11.18 If the specified type of finish is not obtained the Contractor shall only be paid 50% (fifty
percent) of the quoted rate for the defective area. The balance shall only be paid after
completion of the rectification and certification by the Owner/ Owner’s Authorized
Representative.
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
12 Annexures
A. Adjustable Props
B. H-Frame Scaffolding
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
E. Slab Shuttering
F. Slab Shuttering
Formwork System Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/04 Technical Specifications
Contents
1. Scope ............................................................................................................................................................ 2
2. List of Standards ........................................................................................................................................... 2
3. Terminology .................................................................................................................................................. 2
4. Submittals and Certifications ........................................................................................................................ 3
5. Materials ....................................................................................................................................................... 3
6. Workmanship ............................................................................................................................................... 3
7. Quality Management .................................................................................................................................... 7
8. Safety Considerations and Requirements..................................................................................................... 7
9. Environmental considerations ...................................................................................................................... 8
10. Measurement ........................................................................................................................................... 8
11. Completion and delivery ................................................................................................................................. 9
12. Annexures ................................................................................................................................................. 9
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
1. Scope
This specification applies to an installation and placing of APP membrane waterproofing sheets
for different structural components at different locations in the structure. This specification
does not cover any waterproofing technique other than APP Membrane. Also it doesn’t
comment on any manufacturing technique or specifications of the constituents used for the
manufacturing of APP Membrane sheets.
2. List of Standards
Work shall be carried out as per latest version of Indian Standards and Code of Practices. List
given hereunder is not to be considered as conclusive and is for reference and guidance only.
Any discrepancies /conflict noticed shall be directed to the Engineer for his direction/approval.
However as a general rule more stringent specification shall take precedence.
3. Terminology
The following terms and abbreviation shall have the specific meanings as described hereunder.
For terms that are not described herein, the definitions as stated in the applicable Indian
Standard Specifications shall apply.
1.1 APP Membrane: Membrane is the term used for the object with a negligible thickness or
small thickness. APP (Atactic Polypropylene) membrane is nothing but sheets of polymer /
bituminous material with an ability to resist the unnecessary passage of water.
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
4. Materials
4.1 Primer: The bitumen primer shall conform to the requirements laid down in IS 3384.
4.2 APP Modified Membrane:
It is a polymeric water proofing membrane manufactured to high standards. It is five
layered APP modified polymeric membrane with centre core as 20 micron HMHDPE/100
micron HMHDPE (High Molecular High Density Polyethylene Film), is the heart of the
membrane and protects against water and moisture. The center core is sandwiched on
both sides by high quality polymeric mix with properties of high softening point, high heat
resistance and cold resistively to make it ideal for all water proofing treatment. The
polymeric mix is protected on both sides with 20 micron HMHDPE film. The membrane is
available in variable thickness and weights. Usual width is 1.0 m.
4.3 Bonding Material:
This shall consist of blown type bitumen conforming to IS 702 or residual bitumen 85/25
conforming to IS 73 heated to the correct working temperature of 180°C. The penetration
of the bitumen shall not be more than 40 when tested in accordance with IS 1203, unless
otherwise specified each coat of bonding material shall be of blown type bitumen of grade
85/25 heated to a working temperature of 180 degree C and applied @ 1.20 kg / sq.m of
the surface area.
4.4 Surface Finish:
Surface finish shall be with brick tiles of class designation 100 grouted with cement mortar
1:3 (1 cement : 3 fine sand ) with 2% integral water proofing compound by weight of
cement over a 12 mm thick layer of cement mortar 1:3 (1 cement: 3 fine sand) and finished
neat and Finish shall be measured and paid for separately.
6. Workmanship
6.1 Preparation of Surface:
6.1.1 The surface to be treated shall have a minimum slope of 1 to 120. This grading shall
be carried out with cement concrete or cement plaster with coarse sand, as
desired, to the average thickness required and finished smooth. Such grading shall
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
be paid for separately. Junctions between the roof and vertical faces of parapet
walls, chimneys etc. shall be chased by running triangular fillets 7.5 x 7.5 cm. size,
cement concrete. At the drain mouths, the fillets shall be suitably cut back and
rounded off for easy application of water proofing treatment and easy flow of
water. Cement concrete shall be 1:2:4 mix (1 Cement: 2 Coarse sand: 4 Graded
stone aggregate 20 mm Nominal size).
6.1.2 The provision of fillets shall be deemed to be covered by the item of water proofing
and shall not be measured or paid for separately. In existing roof where gola and
drip course are provided at the junction of roof and vertical face of parapet wall,
chimney stacks, etc. These shall be dressed suitably and finished smooth so as to
ensure an easy and gradual turning of the flashing.
6.1.3 Any dismantlement or forming and finishing smooth the junction for forming the
base of the flashing shall not be measured or paid for separately and shall be
deemed to form part of the preparation of the surface. While the grading of roof
surface is being done, it shall be ensured that the outlet drain pipe has been fixed
and mouth at the entrance have been eased and rounded off properly for easy flow
of water.
6.1.4 When any pipe passes through the roof to be treated, angular fillet of shape shall
be built around it for the water proofing treatment to be taken over it. These fillets
shall not be measured or paid for separately. For carrying over and tucking in the
water proofing felts into the parapet walls, chimneys stacks etc. a horizontal groove
6.5 cm. deep, 7.5 cm. wide section with its lower edge at not less than 15 cm.
above the graded roof surface shall be left on the inner face of the same; during
construction if possible. When such groove has not been left, the same shall be cut
out neatly and the base at rear of the groove shall be finished smooth with cement
plaster 1:4 (1 cement: 4 coarse sand). Such cutting of the groove and its finishing
smooth shall be part of the water proofing or paid for separately.
6.1.5 No deduction shall be made either for not making the groove or when the latter
has already been left in the masonry by the construction agency. Tucking in the
water proofing felt will be required where the parapet wall exceeds 45 cm. in the
height from the graded surface. Where the height is 45 cm or less, no groove will be
required as the water proofing treatment will be carried over the top of the parapet
wall to its full thickness. In the case of low dividing walls of height 30 cm. or less,
outlets therein shall be cut open for full height and the bottom and sides shall be
rendered smooth and corners rounded and such treatment shall not be measured
and paid for separately.
6.1.6 Where expansion joints are left in the slab the provision of dwarf walls and/or RCC
slabs for covering them and finishing the surface smooth shall be the responsibility
of the construction agency, which had laid the roof slab and will not be included in
the operation of water proofing.
6.1.7 The graded surface of the roof and concrete fillets and the faces of walls shall be
thoroughly cleaned with wire brush and all loose scales etc. removed. The surface
shall then be dusted off. Any crack in the roof shall be cut to V section, cleaned and
filled up flush with cement mortar slurry 1:4 (1 cement : 4 coarse sand) or blown
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
membrane in a six course treatment shall overlap the roof water proofing by not less
than 20 cm. while the upper layer shall overlap the roofing felt by 10 cm. The
minimum overlap of the flashing membrane in five course treatment over the
roofing membrane shall be 10 cm. The flashing shall consist of the same five or
seven course treatment as for the roof except that the final course shall be replaced
by an application of 12 mm thick cement plaster 1:3 on the vertical and sloping faces
only, of the flashing. The overlap along the length of flashing shall stagger with those
in the second layer of flashing membrane (in a seven course treatment and with the
joints in the roof membrane). The upper edge of the finishing membrane shall be
well tucked into the flashing grooves in the parapet, chimney tacks etc. to a depth of
not less than 6.5 cm. Corresponding applications of bonding material shall also be
made. The flashing treatment shall be firmly held in place in the grooves with wood
edges at intervals and the grooves shall be filled up with cement mortar 1:4 (1
cement: 4 coarse sand) or cement concrete 1:2:4 (1 cement: 2 coarse sand : 4
graded stone aggregate 6 mm nominal size) and surface finished smooth with the
rest of the wall. The cement work shall be cured for 7 days. When dry, the exposed
plaster joints of grooves shall be painted with bitumen and two coats of bituminous
solution shall be applied on the vertical and sloping surface of flashing. After the top
flashing membrane layer has been fixed, the penultimate layer of bonding material
shall be applied over the roofing membrane and the horizontal overlaps and vertical
and sloping surfaces of the flashing at the specified rate.
6.3.6 Low Parapet Walls:
Where parapet walls are of height 45 cm. or less, membrane flashings shall be
provided in the same manner as for flashings in the case of high parapet walls
except that the upper edge shall be carried upto the full height of the wall and taken
right across the top of the parapet and down on the external vertical faces to a
minimum distance of 5 cm.
6.3.7 Low Dividing Walls:
Where low dividing walls or inverted beams are met with, the same shall be covered
with a four or six layer treatment as for the main roof, the latter bearing carried
down both sides of the wall and overlapping the roofing treatment as in the case of
flashing of high parapet walls. Drain outlets where formed in the low dividing walls,
shall be given water proofing treatment of the same number of courses as specified
for the flat roof surface. The bottom and sides shall be so treated that all overlaps
are in the direction of flow of drainage.
6.3.8 Expansion Joints:
Where the expansion joints are provided in the slabs, the joints and their cover slabs
shall be suitably treated with water proofing. A typical sketch of an expansion joint
with the RCC slabs on either side of the joint turned vertically up and dwarf walls by
not less than 7.5 cm. and are provided with throating on their underside along their
length. The water proofing treatment shall be taken up the sloping junction fillets
and the vertical faces of the walls to the underside of the cover slabs. The cover
slabs are given the water proofing treatment like the roofs slabs, after the cross
joints between adjacent cover slabs are first sealed with 15 cm width of roofing felt
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
struck to them with bitumen. The water proofing treatment shall be carried own the
sides of the cover slabs to their full thickness. Care shall be taken to see that
overlaps if any in the roofing over the cover slabs stagger with the joints between
cover slabs. The formation of the expansion joints and provision of the cover slabs
shall be the responsibility of the construction agency. The formation of the junction
fillets and the water proofing treatment of the joint and cover slabs shall be carried
out by the water proofing agency. Nothing agency extra shall be paid for the sealing
of the cross joints in the cover slab with 15 cm. width of bitumen strips.
6.3.9 Pipes:
Where vertical pipe outlets are met with, 7.5 x 7.5 cm fillets of lime or cement
concrete of the type and section shall be provided and flashing of four or six course
treatment, same as for the roofing treatment shall be laid. The upper edge of the
flashing shall be laid sloping down forward and butted against the pipe and annular
depression so formed shall be filled with hot bitumen. A circular metal collar in the
shape of an inverted truncated cone shall be fixed on the pipe to throw off the rain
water clear of the flashing and this shall be paid for separately.
7. Quality Management
7.1 The contractor shall put in place a comprehensive Quality management plan to ensure
that the work is carried out as per specifications and compliance to all requirements are
established and demonstrated through comprehensive documentation. The contractor
shall engage a qualified Quality Manager to implement the quality plan.
7.2 The standardized Inspection and Test plans [ITP] shall be adopted for the purpose of
testing material and establishing documentary evidence of conformance to technical
requirements. If the contractor proposes to adopt his own ITP, the same shall be
submitted for the approval of the Engineer. Any dilution of the testing frequency,
acceptance criteria from the standardized ITP shall have to be supported by well-
articulated arguments.
8.2 All workmen shall be made aware of the specific hazards that they face while doing
installation and placing of APP membrane waterproofing sheets and shall be provided with
specific personal protective equipment to protect them.
9. Environmental considerations
9.1 Apart from general environmental impact of construction activities, the contractor shall
assess the environmental impact associated with installation and placing of APP
membrane waterproofing sheets and shall take specific action to mitigate against the
same.
a. APP Membrane Waterproofing Works activity involves following type of waste :
i. Non-hazardous waste : like Scrap wood, Fixtures
ii. Hazardous waste : like used Waste pieces of APP Membrane sheets, Concrete
waste, oil, paint, solvents, sealers, thinners, Cleanup and materials contaminated
with the items listed above Drums and containers that once contained the items
listed above.
b. For Environmental considerations during concrete works refer PV/TECH
SPEC/CIVIL/02.
c. For Environmental considerations during Form works refer PV/TECH SPEC/CIVIL/04.
9.2 When wastes are produced at the site, the contractor or subcontractor who produces the
waste typically is responsible for ensuring its proper handling and disposal.
10.Measurement
10.1Measurement:
Length and breadth shall be measured correct to a cm. The area shall be calculated in
square meters correct to two places of decimal. Measurements shall be taken over the
entire exposed area of roofing and flashing treatment including flashing over low parapet
walls, low dividing walls and expansion joints and at pipe projections etc. Overlaps and
tucking into flashing grooves shall not be measured. Vertical and sloping surfaces of water
proofing treatment shall also be measured under the five or seven course treatment as
the case may be, irrespective of the fact that the final course is replaced by bitumen
primer. No deduction in measurements shall be made for either openings or recesses for
chimney stacks, roof lights and neither the like, for areas up to 0.4 sq.m nor anything shall
be paid for forming such openings. For areas exceeding 0.40 sq.m deduction will be made
in measurements for full opening and nothing extra shall be paid for forming such
openings.
10.2Rate:
The rate shall include the cost of all labour and materials involved in all the operations
described above. The top most layer shall be paid separately.
WP Membrane Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/05 Technical Specifications
12.Annexures
NIL
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Table of Contents
1. Scope .......................................................................................................................................... 2
2. List Of Standards ........................................................................................................................ 2
3. Terminology ............................................................................................................................... 4
4. Materials .................................................................................................................................... 5
5. Submittals ................................................................................................................................ 14
6. Workmanship........................................................................................................................... 14
7. Quality Management............................................................................................................... 22
8. Safety Considerations And Requirements .............................................................................. 23
9. Environmental Considerations And Requirements ................................................................ 23
10. Completion And Delivery ..................................................................................................... 24
11. Method Of Measurement & Rate........................................................................................ 24
12. Annexures ............................................................................................................................ 28
Page 1 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
2. List of Standards
The work shall be carried out as per latest versions of Indian Standards and Code of
practices. List given hereunder is not to be considered as complete and is for reference/
guidance only. Any discrepancies / conflicts noticed shall be directed to the Engineer for
his direction / approval.
However as a general rule the more stringent specification shall take precedence.
IS 269 Specification for ordinary and low heat Portland cement grade
33
IS 383 Specification for coarse and fine aggregates from natural sources
for concrete.
IS 456 Code of Practice for plain and reinforced concrete.
IS 1077 Common burnt clay building bricks.
IS 1121 Methods of determination of properties and strengths of natural
(Part I) building stones (Part-I compressive strength).
IS 1122 Methods for determination of specific gravity of natural building
stone
IS 1123 Methods of identification of natural building stones
IS 1124 Method of test for determination of water absorption, apparent
specific gravity and porosity of natural building stones
Page 2 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 3 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
3. Terminology
The following terms and abbreviations shall have the specific meanings as described
hereunder. For terms that are not described herein, the definitions as stated in the
applicable Indian Standard Specifications shall apply.
3.1. Bond: The arrangement of the bricks in successive courses to tie the brick work
together both longitudinally and transversely. The arrangement is usually
designed to ensure that no vertical joint of one course is exactly over the one in
the next course above or below it, and there is greatest possible amount of lap.
3.2. Bed Joint: Horizontal joint in brick work or masonry.
3.3. Block: A concrete masonry unit, either hollow (open or closed cavity), or solid
(other than units used for bonding, such as a half block), any one of the external
dimension of which is greater than the corresponding dimension of a brick.
3.4. Bushing: It is the finished projection provided on the rock surface.
3.5. Cross Joint: joint other than a bed joint normal to the wall face
3.6. Closer: Any portion of a brick used in constructing a wall, to close up the bond
next to the end brick of a course
3.7. Coping or Weathering : The cover applied over or the geometrical form given to
a part of structure to enable it to shed rain water
3.8. Corbel: A cantilever projecting from the face of a wall to form a bearing
3.9. Cornice: Horizontal or ornamental feature projecting from the face of a wall
3.10. Course: A layer of bricks/blocks/stones including bed mortar
3.11. Efflorescence: A powdery incrustment of salts left by evaporation. This may be
visible on the surface or may be below surface. In the latter case, this is termed
as crypto Efflorescence.
3.12. Header: A brick laid with its length across the wall. Selected long stones used to
hold a wall together transversally.
3.13. Hearting: The infilling which forms the core of a rubble wall.
3.14. Jamb: The part of the wall at the side of an opening.
Page 4 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
3.15. Quoin: A quoin is the external angle of a wall or building. The term is also applied
to a stone specially selected and neatly dressed for forming such an angle.
3.16. Spandrel: The space between the haunches and the road decking of an arch.
3.17. Stretcher: A brick/stone/block laid with its length in the direction of the wall.
3.18. String course: horizontal course projecting from a wall usually introduced at
every floor level or windows or below parapet for imparting architectural
appearance to the structure and also keeping off the rain water.
3.19. Toothing: Bricks left projecting in alternate courses to bond with future work.
4. Materials
4.1 Cement
4.2.1 The type of cement to be used in concrete/mortar shall be as per the
approved Concrete Mix Design. Generally, the following types of cement
may be used:
Ordinary Portland cement of grade 53 or 43
Portland Pozzolana Cement
Portland Blast Furnace Slag Cement
4.2.2 Cement shall be received in bags of 50 kg or loose in bulkers and each
batch shall be accompanied with a test certificate of the factory. In case
cement has been stored for over 3 months or for any reasons the stored
cement shows signs of deterioration or contamination, it shall be
tested as per the direction of the Engineer, and will be used in the works
only if found suitable
4.2 Coarse Aggregate
4.2.1 Coarse aggregate shall be obtained from natural sources such as stone,
gravel, etc. crushed or uncrushed or a combination thereof from
approved quarries. Aggregate shall be hard, strong, dense, durable, and
clean and free from veins and adherent coatings. It shall be free from
soft, feeble, thin, elongated or laminated pieces and shall be roughly
cubical in shape. It shall consist of coarse material, most of which is
retained on 4.75 mm IS sieve and shall contain only as much fine material
as is permitted in IS 383 for various sizes and grading.
4.2.2 Coarse aggregate shall conform to all requirements laid down in IS: 383
4.2.3 The maximum size of coarse aggregate should not be greater than one
fourth of the minimum thickness of the member and it should be
restricted to 5 mm less than the minimum clear distance between the
main bars or 5 mm less than the minimum cover to the reinforcement.
4.2.4 Source of aggregate shall be from an approved location. Each source of
aggregate shall be approved by Engineer on the basis of tests conducted
on samples of aggregates from the source at an approved testing
laboratory. In case available aggregates do not meet certain
requirements of IS 383 or any other specification, required processing
Page 5 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 6 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
4.4.4 The source of water shall be tested and got approved in writing from the
Engineer prior to use in the works.
4.4.5 Use of sea water shall not be permitted for any purpose related to
making concrete.
4.5 Concrete Blocks
4.5.1 Concrete blocks may be hollow (open ended for ease of laying conduits)
or solid and shall be referred to by its nominal dimension. The term
nominal dimension includes the thickness of the mortar joint. Actual
dimensions of the block shall be 10 mm short of the nominal dimensions.
4.5.2 Blocks shall be made in sizes and shapes to fit different construction
needs. It includes stretcher, corner, double corner or pier, jambs, header,
bull-nose, partition block and concreted floor units. Nominal dimensions
of concrete blocks shall be, Length – 400, 500, or 600 mm
Height – 200 or 100 mm
Width - 100, 150, 200, 250, or 300 mm
4.5.3 Maximum permissible variation shall be ± 5 mm in length and ±3 mm in
width and height of the block. Actual dimensions of block shall be 10 mm
short of nominal dimensions.
4.5.4 The average crushing strength shall be determined as per I.S 2185.For
load bearing wall density of hollow block shall be not less than 1500 kg
/mm3 and minimum average compressive strength of units shall be 3.5 to
7 N/mm2. For block density less than 1500 kg /mm3 but not less than
1000 kg /mm3 average compressive strength of units shall be 2.0 to5
N/mm2 .
4.5.5 For non-load bearing wall, hollow block density shall be not less than
1000kg / mm3 and minimum average compressive strength of units shall
be1.5 N/mm2.
4.5.6 Face shells and web dimensions shall not be less than the values given in
IS 2185 Part I – Table 1 “Minimum face shell and web thickness”.
4.5.7 Concrete shall be mixed in mechanical mixers. Blocks shall be moulded,
laid and compacted With automatic machines. No hand/manual
compaction shall be permitted unless approved by the Engineer in writing
for special blocks. Care shall be taken to see that the mix is placed in
layers and each layer thoroughly tamped until the whole mould is filled
up. Blocks shall be protected until they are sufficiently hardened to
permit handling without damage.
4.5.8 Blocks shall be cured in the curing yard by keeping them continuously
moist for at least 14 days.
4.5.9 Steam-cured blocks shall be preferred. Cured blocks shall be allowed to
dry for a period of 4 weeks before being used. The blocks shall be
allowed to complete their initial shrinkage before they are laid in the wall
4.5.10 All blocks shall be sound and free of cracks or other defects. Where faces
are exposed, they shall be free of chips, or other imperfections, and the
Page 7 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
4.6 Bricks
4.6.1. Common Burnt Clay Bricks
Common Burnt Clay Bricks shall conform to IS:1077 and shall be hand
moulded or machine moulded. They shall be free from nodules of free
lime, visible cracks, flaws warpage and organic matter, have a frog 100
mm in length 40 mm in width and 10 mm to 20 mm deep on one of its
flat sides. Bricks made by extrusion process and brick tiles may not be
provided with frogs. Each brick shall be marked (in the frog where
provided) with the manufacturer’s identification mark or initials.
4.6.2. Fly ash bricks
a. Fly ash bricks (cement bonded) shall be locally made. Bricks shall
have smooth rectangular faces with sharp and square corners.
Bricks shall be hand or machine moulded and shall be made from
the admixture of suitable good quality of fly ash, sand and cement
as per the composition mentioned below :
FLY ASH: 50-60%
SAND: 32-40%
CEMENT : 8-12%
b. The fly ash bricks will be as per latest relevant IS code. The bricks
will be of dimension as per standard clay brick, suitable for
making 230mm thick full brick wall, 115mm thick half brick wall
and 75mm thick minor partition walls, as applicable, as per
drawing/specification/BOQ. A maximum tolerance of (+/-) 2mm
shall be allowed as the manufacturing tolerance. The bricks shall
Page 8 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 9 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
4.7 Stone
4.7.1. The stone shall be of the type specified such as granite, trap, limestone,
sand stone, quartzite, etc. and shall be obtained from the quarries,
approved by the Engineer-in-Charge. Stone shall be hard, sound, durable
and free from weathering decay and defects like cavities, cracks, flaws,
sand holes, injurious veins, patches of loose or soft materials and other
similar defects that may adversely affect its strength and appearance. As
far as possible stones shall be of uniform colour, quality or texture.
Generally stone shall not contain crypst crystalline silica or chart, mica
and other deleterious materials like iron-oxide organic impurities etc.
4.7.2. Stones with round surface shall not be used.
4.7.3. The compressive strength of common types of stones shall be as per
following Table and the percentage of water absorption shall generally
not exceed 5% for stones other than specified in following Table For
laterite this percentage is 12%.
Type of stone Maximum Water Minimum
Absorption Compressive
Percentage by weight Strength kg./sq.cm
Page 10 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
from the stones brought from the approved quarry. Stones having
sharp corners or round surfaces shall, however, not be used.
d) Random rubble masonry brought to the course is similar to
uncoursed random rubble masonry except that the courses are
roughly levelled at intervals varying from 300 mm to 900 mm in
height according to the size of stones used.
4.7.5. Dressing: Each stone shall be hammer dressed on the face, the sides and
the beds. Hammer dressing shall enable the stones to be laid close to
neighbouring stones such that the bushing in the face shall not project
more than 40 mm on the exposed face.
4.8 Mortar
4.8.1 Mortar shall be prepared by mixing graded fine aggregate with cement
and approved non shrinking compound (as specified by engineer in
charge and as per instructions laid down by manufacturer) in the
proportion specified for respective items of work as detailed in the BOQ.
4.8.2 Mixing of mortar shall be done by mechanical mixers only. Hand mixing
may be permitted in specific cases with the written permission of the
Engineer.
4.8.3 Mortars shall be specified by proportion. Volumetric mixing shall be
based on dry volumes of each ingredient. For convenience, measurement
boxes shall correspond to volume of one cement bag i.e. 0.035 cum.
Boxes shall be of size 33.33 x 30 x 35 cm (L x B x D). These shall be marked
as mortar mixing boxes. Hand mixing or mechanical mixing shall be done
with the use of these boxes.
4.8.4 Cement mortar shall be prepared by mixing cement and sand in specified
proportions. Proportioning shall be carried out as detailed above. Sand
shall be suitably added to allow for bulking, if required. Bulking shall be
determined as laid down in IS 2386 Part III. Cement and sand added to
mixer shall be thoroughly mixed and water shall be added to it gradually.
After addition of water the mixer shall run for a minimum of 2 minutes.
The mortar so mixed, shall be consumed within 4 hours.
4.9 Damp Proof Course
4.9.1. It shall consist of a layer of concrete 40 mm thick in the ratio of 1:2:4
(1cement: 2 sand: 4 stone aggregate of 10 mm nominal size). The
concrete layer shall be provided with a water proofing treatment which
may either be a surface treatment or integral waterproofing compounds.
For surface treatment of concrete, hot bitumen at the rate of 1.7 kg/100
sqm may be used.
4.9.2. Alternatively Slate and Cuddappah stone slabs can also be used which
shall be of minimum 40 Mm thickness with exposed edges finely dressed,
true and square. These slabs be embedded in Cement mortar 1:3 with
non-shrinking compound additive as per manufacturers
recommendations.
Page 11 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
4.10 Admixture
4.10.1. Additives or admixtures may be added to the cement or concrete mix
conforming to the Indian Standard specifications IS 9103.
4.10.2. Admixtures shall be permitted to be used to modify the properties of
concrete for single, or a combination of purposes. This shall be used for
specific purpose and the type and dosage of admixture shall be as per the
approved mix design of concrete.
4.10.3. Admixtures shall be free from chlorides and sulphates or any other
material which may cause problems to the concrete in the due course of
time.
4.10.4. Admixtures are manufactured and sold by various companies under
brand names. The contractor proposing to use any one of them shall
submit to the Engineer the technical literature with its chemical
composition, purpose of use and method recommended by the
manufacturer.
4.10.5. The contractor’s proposal shall accompany the following with his request
to use admixture.
a) The trade name of the admixture, its source and the
manufacturer’s recommended method of use.
b) Typical dosage rates and the possible detrimental effects of under
and over-dosage. Whether the admixture contains chloride in any
free form or any other chemical present as an active ingredient
which is a likely cause of corrosion of reinforcement or
deterioration of concrete.
c) The average expected air content of freshly mixed concrete
containing an admixture which causes air to be entrained when
used at the manufacturer’s recommended rate of dosage.
4.11 Joint Fillers
04.11.1. Bituminous impregnated, pre-moulded joint filler board shall be of
approved quality, from approved manufacturer and shall conform to IS
1838 part I
4.12 Metal Reinforcement
04.12.1. Expanded metal used shall comply with IS 412
4.13 Bonding Agent
4.13.1. Bonding agent of approved make shall be used for application on RCC
surfaces having interface with block work.
4.14 Delivery & Storage of Material
4.14.1. Bricks: The Contractor to ensure the following:
a. Bricks shall be stacked in regular tiers as and when they are
unloaded to minimize breakage and defacement. These shall not
be dumped at site.
Page 12 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
b. Bricks stacks shall be placed close to the site of work so that least
effort is required to unload and transport the bricks again by
loading on pallets or in barrows. Building bricks shall be loaded or
unloaded a pair at a time unless palletized. Unloading of building
bricks or handling in any other way likely to damage the corners
or edges or other parts of bricks shall not be permitted.
c. Bricks shall be stacked on dry firm ground. For proper inspection
of quality and ease in counting the stacks shall be 50 bricks long,
10 bricks high and not more than 4 bricks in width, the bricks
being placed on edge, two at a time along the width of the stack.
Clear distance between adjacent stacks shall not be less than 0.8
m. Bricks of each truck load shall be put in one stack.
d. Bricks of different types, such as clay bricks, clay fly ash bricks, fly
ash lime bricks, sand lime (calcium silicate) bricks, auto-clave
bricks etc. shall be stacked separately. Bricks of different
classification and size consideration (such as, conventional and
modular) shall be stacked separately.
4.14.2. Concrete Blocks: The Contractor to ensure the following:
a. Blocks shall be unloaded one at a time and stacked in regular tiers
to minimize breakage and defacement. These shall not be
dumped at site. The height of the stack shall not be more than 1.2
m. The length of the stack shall not be more than 3.0 m, as far as
possible and the width shall be of two or three blocks.
b. Load, unload deliver, store all concrete blocks with due care, at
site so as to be free from damage, dirt, intrusion of foreign
materials etc. Normally blocks cured for 28 days only should be
received at site. In case blocks cured for less than 28 days are
received, these shall be stacked separately. All blocks should be
water cured for 10 to 14 days and air cured for another 15 days;
thus no blocks with less than 28 days curing shall be used in
building construction.
c. Blocks shall be placed close to the site of work so that least effort
is required for their transportation. The date of manufacture of
the blocks shall be suitably marked on the stacks of blocks
manufactured at factory or site.
d. All blocks shall be handled carefully from manufacture to laying
and properly stacked in position convenient for the work. They
shall be kept free from standing water and protected from rain,
mud and contamination by other materials.
e. Protect blocks from any extreme weather conditions.
Page 13 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
5. Submittals
The contractor shall maintain a comprehensive record of the block works as per
the approved ITP. All records shall be in hard copy, signed by the Quality
manager, unless electronic records are permitted by the Engineer.
5.1 Concrete Block Masonry /Brick Masonry
5.1.1. The following documents shall be submitted to the Engineer for approval
and record:
a. Manufacturer’s Test Certificates for concrete blocks /bricks
brought to site.
b. Records of tests performed on blocks/bricks.
c. Detailed methodology for carrying out repairs for any defect
d. Record for correction / repairs carried out
5.1.2. Prepare sample panels of approximately 1 m2 of faced blockwork
/brickwork including pointing, and obtain approval before proceeding
5.1.3. If required by the Engineer, contractor shall maintain and submit
photographs indicating compliance to various requirements of this
specification and ITP.
5.2 Stone Masonry: A sample wall, 10 m2. In area shall be built and approved by the
Engineer and all works shall match with this sample.
6. Workmanship
6.1 Concrete Block Masonry
6.1.1. Concrete blocks may not be wetted like brick masonry prior to use. In
total dry climate top & sides of block shall be moistened to avoid
absorption of water from mortar.
6.1.2. The window sill levels shall be properly ascertained by the Contractor
prior to commencement of blockwork. All surfaces on which blockwork is
to be built shall be cleaned of any foreign matter influencing the bond
between the surface and blockwork. The use of chipped or defaced
blocks will not be permitted in any facework. Concrete blockwork shall be
laid in English bond.(Fig. 1 as annexed). Height of block work constructed
in one day shall be restricted to 1.2 meter.
6.1.3. Cut blocks shall not be used. Special solid precast blocks at site shall be
cast well in advance to be used as spacers and to adjust breaking of
vertical joints. Blocks can be cut horizontally or vertically for use as
spacers and to adjust breaking of vertical joints at approval of Owner or
Owner’s representative.
6.1.4. All cross (vertical) joints shall be filled by well buttering the ends of the
block with mortar and then sliding it against its neighbour.
6.1.5. Cracks in block masonry are due to shrinkage or expansion of blocks
or due to load settlement, thermal expansion or changes in moisture
content in the structural members enclosing the block walls. The
Page 14 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 15 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 16 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
regular intervals for a period not less than six hours. The bricks required
for masonry work using mud mortar shall not be soaked. When the bricks
are soaked they shall be removed from the tank sufficiently early so that
at the time of laying they are skin-dry. Such soaked bricks shall be stacked
on a clean place where they are not again spoiled by dirt earth etc.
6.2.2. The window sill levels shall be properly ascertained by the Contractor
prior to commencement of brickwork. All surfaces on which brickwork is
to be built shall be cleaned of any foreign matter influencing the bond
between the surface and brickwork. The use of chipped or defaced blocks
will not be permitted in any facework. Brickwork shall be laid in English
bond.(Fig. 1 as annexed). For brick work in half brick wall, bricks shall be
laid in stretcher bond. No part of the wall during its construction shall rise
more than 1.0 metre above the general construction level. Parts of wall
left at different levels shall be raked back at an angle of 45 degrees or less
with the horizontal. Toothing shall not be permitted as an alternative to
raking back. For half brick partition to be keyed into main walls, indents
shall be left in the main walls. Mortar joints shall be kept uniformly 10
mm thick.. Joints shall be raked 10 mm deep while mortar is green.
6.2.3. Broken bricks shall not be used. Cut bricks shall be used if necessary to
complete bond or as closers.
6.2.4. Bricks shall be laid with frogs upwards over full mortar beds. Bricks shall
be pressed into mortar and tapped into final position so as to embed fully
in mortar. Inside faces shall be buttered with mortar before the next
bricks is placed and pressed against it. Thus all joints between bricks shall
be fully filled with mortar. Brickworks two bricks thick or more shall have
both faces in true plane. Brickwork of lesser thickness shall have one
selected face in true plane.
6.2.5. Half or cut bricks shall not be used except as closer where necessary to
complete the bond. Closers in such cases, shall be cut to the required size
and used near the ends of the wall. Header bond shall be used preferably
in all courses in curved plan for ensuring better alignment.
6.2.6. Where required, damp proof course layer shall be laid as specified
Exposed faces and corners of masonry damaged during construction shall
be removed and repaired in a manner acceptable to Engineer.
6.2.7. All pipe fittings and specials, spouts, hold fasts and other fixtures which
are required to be built into the walls shall be embedded, as specified, in
their correct position as the work proceeds unless otherwise directed by
the Engineer-in-Charge.
6.2.8. Top courses of all plinths, parapets, steps and top of walls below floor
and roof slabs shall be laid with brick on edge, unless specified otherwise.
Brick on edge laid in the top courses at corner of walls shall be properly
radiated and keyed into position to form cut corners as shown in Fig 6.4.
Where bricks cannot be cut to the required shape to form cut corners,
cement concrete 1:2:4 (1 cement :2 coarse sand : 4 graded stone
Page 17 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 18 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 19 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 20 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
6.2.8. Stones shall be laid with its grains horizontal so that the load transmitted
is always perpendicular to the natural bed.
6.2.9. Green work shall be protected from rain by suitable covering. Masonry
work shall be kept constantly moist on all the faces for a minimum period
of seven days for proper curing of the joints.
6.2.10. Scaffolding
a. Single scaffolding having one set of vertical support shall be used and
the other end of the horizontal scaffolding member shall rest in a hole
provided in the masonry. The support shall be sound and strongly tied
together with horizontal pieces over which the scaffolding planks shall
be fixed.
b. The holes which provide resting space for horizontal members shall
not be left in pillars less than one metre in width. The holes left in the
masonry work for supporting the scaffolding shall be filled and made
good with concrete of M-15 before plastering /pointing.
c. The scaffolding shall be strong enough to withstand all loads likely to
come upon it and shall meet the requirements specified in IS 2750:
1964.
d. For pillars less than one metre in width or for first class masonry or for
building having more than two storeys, double scaffolding having
two sets of vertical support shall be provided.
6.3 Coursed Rubble Stone Masonry (First Sort)
6.3.1. All stones shall be wetted before use. All courses shall be laid truly horizontal
and shall be of the same height in any course. The height of course shall
not be less than 150 mm and not more than 300 mm. The width of stone
shall not be less than its height.
6.3.2. Face stones shall tail into the work for not less than their height and at
least 1/3rd the number of stones, shall tail into the work for a length not
less than twice their- height but not more than three-fourths the
thickness of the wall whichever is smaller. These should be laid as
headers and stretchers alternately to break joints by at least 75 mm.
6.3.3. The face stones shall be squared on all joints and beds; the bed joints
being hammer or chisel dressed true and square for at least 80 mm back
from the face and the side joints for at least 40 mm. The face of the
stone shall be hammer dressed so that the bushing shall not be more
than 40 mm on an exposed face and 10 mm on a face to be plastered. No
portion of the dressed surface shall show a depth of gap more than 6 mm
from a straight edge placed on it. The remaining unexposed portion of
the stone shall not project beyond the surface of bed and side joints.
6.3.4. No spalls or pinning shall be allowed on the face. All bed joints shall be
horizontal and side joints shall be vertical and no joints shall be more
than 10 mm in thickness. When plastering or pointing is not required to
be done, the joints shall be struck flush and finished as the work
proceeds. Otherwise, the joints shall be raked to a minimum depth of 20
Page 21 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
mm by a raking tool, during the progress of the work while the mortar is
still green.
6.3.5. Hearting shall consist of flat bedded stones carefully laid on their proper
beds and solidly bedded in mortar. The use of chips shall be restricted to
the filling of interstices between the adjacent stones, in hearting and
these shall not exceed 10 percent of the quantity of the stone masonry.
Care shall be taken so that no hollow spaces are left anywhere in the
masonry.
6.3.6. The through or bond stones shall be provided at 1.5 m to 1.8 m apart
clear in every course but staggered at alternate courses.
6.3.7. The quoins which shall be of the same height as the course, in which they
occur, shall not be less than 450 mm in any direction. Quoin stones shall
be laid as stretchers and headers alternately. They shall be laid square on
their beds, which shall he rough chisel dressed to a depth of at least 100
mm from the face. These stones shall have a minimum uniform chisel
draft of 25mm width at four edges, all the edges being in the same plane.
6.4 Coursed Rubble Stone Masonry (Second Sort)
6.4.1. Shall be same as of Coursed Rubble Masonry(first Sort) explained above
except that the use of chips shall not exceed 15% of the quantity of stone
masonry and stone, in each course need not be of the same height but
not more than two stones shall be used in the height of a course.
7. Quality Management
The contractor shall put in place a comprehensive Quality management plan to
ensure that the work is carried out as per specifications and compliance to all
requirements are established and demonstrated through comprehensive
documentation. The contractor shall engage a qualified Quality Manager to
implement the quality plan.
7.1. Unless annexed to these specifications the contractor shall submit an
inspection and test plan [ITP] for the approval of the Engineer. The ITP
shall cover tests on incoming materials, supervision of the process and
test on the completed work.
7.2. The ITP shall lay down the characteristics to be tested/inspected,
frequency of tests, acceptance criteria and the manner of documenting
the results. Any test, compliance to which is mandatory for further
progress of the next stage of work shall be identified as a ‘Hold point’.
7.3. In the absence of an approved ITP, provisions of IS: 2185 and any other
Indian Standard referred there in shall apply with regard to acceptance
criteria and tolerances.
As general guidelines, Care shall be taken to keep the perpends properly
aligned within following maximum permissible tolerances for brick work:
a. Deviation from vertical within a storey shall not exceed 6 mm per 3 m
height.
Page 22 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 23 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 24 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 25 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 27 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
12. Annexures
Page 28 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 29 of 30
Masonry Work Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/06 Technical Specifications
Page 30 of 30
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
Table of Contents
Contents
1. SCOPE ...................................................................................................................................................... 2
2. LIST OF STANDARDS ................................................................................................................................. 2
3. TERMINOLOGY......................................................................................................................................... 3
4. MATERIALS .............................................................................................................................................. 3
5. SUBMITTALS AND CERTIFICATIONS ......................................................................................................... 4
6. WORKMANSHIP ....................................................................................................................................... 4
7. QUALITY MANAGEMENT ......................................................................................................................... 7
8. SAFETY CONSIDERATIONS AND REQUIREMENTS ..................................................................................... 8
9. ENVIRONMENTAL CONSIDERATIONS AND REQUIREMENTS.................................................................... 8
10. COMPLETION AND DELIVERY ............................................................................................................... 9
11. METHOD OF MEASUREMENT .................................................................................................................... 9
12. ANNEXURES ....................................................................................................................................... 10
Page 1 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
1. SCOPE
1.1 The Scope of Work covered under this specification will consist of following:
Plastering work to correct line, level and plumb within acceptable tolerances, preparing surfaces,
applying plaster, providing reinforcement such as beads (where applicable), chicken mesh,
scaffolding and curing for the prescribed period. Work may be in single coat or multiple coats as
specified under relevant items of BOQ.
1.2 Finish shall be as specified and approved by Owner / Owner’s Authorized Representative
1.3 Finishing of grooves, jams, sills, bands, motifs, etc. shall be part of the work.
1.4 Work shall include providing required material and labour at all locations with requisite lead and lift.
Internal single coat cement sand mortar plaster minimum 12 mm thick.
Internal to ducts double coat cement sand mortar plaster minimum 18 mm thick with approved
waterproofing compound.
External double coat cement sand plaster minimum 20 mm thick with approved waterproofing
compound
2. LIST OF STANDARDS
2.1 STANDARD
Indian standards for this section shall be as listed below. In case any discrepancies or ambiguities
are noticed it shall be brought to the notice of the Owner / Owner’s Authorized Representative and
clarification/confirmation sought. The decision of the Owner/ Owner’s Authorized Representative
shall be final. However as a general rule the more stringent specifications shall be followed.
Page 2 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
3. TERMINOLOGY
The following terms and abbreviations shall have the specific meanings as described hereunder. For
terms that are not described herein, the definitions as stated in the applicable Indian Standard
Specifications shall apply.
3.1 PH Value: pH is a measure of the acidity or basicity of an aqueous solution. Pure water is said to be
neutral, with a pH close to 7.0 at 25 degree Celsius.
3.2 Mortar: Mortar is a workable paste used to bind construction blocks together and fill the gaps
between them. The blocks may be stone, brick, cinder blocks, etc. Mortar becomes hard when it
sets, resulting in a rigid aggregate structure. Modern mortars are typically made from a mixture of
sand, a binder such as cement and water.
3.3 Chicken Wire/ Mesh: Chicken Wire/ Mesh is a mesh made out of thin, flexible galvanized steel wire.
The chicken mesh is used as a matrix to hold cement or plaster.
4. MATERIALS
4.1 CEMENT
Cement shall be Ordinary Portland Cement conforming to IS and shall be of grade 43 or Portland
Pozzolana Cement approved by the Owner/Owner’s authorized representative. The cement shall be
received in bags of 50 kg and each batch shall be accompanied with a test certificate from the
factory. It shall be tested before use to ascertain its strength, setting time, etc. In case cement has
been stored for over 2 months or for any reasons the stored cement shows signs of deterioration or
contamination, it shall be tested as per the direction of the Owner/Owner’s Authorized
Representative prior to use in the works
4.2 WATER
Water used for mixing and curing shall be clean, reasonably clear and free from objectionable
quantities of silt, oils, alkalis, acids, salts etc so as not to weaken mortar. The water shall conform
to IS 456.
Water tested shall be in accordance with IS 3025. The contents of deleterious materials in water
shall not exceed the maximum values as given in IS 456 Table 1 “Permissible Limits for Solids (in
water)”.
4.3 COLOURED CEMENT
Colored cement may be either ready-mixed material or may be obtained by mixing pigments and
cement at site. The pigments to be mixed with cement shall conform to Appendix “A” of IS 2114
code of practice for laying in-situ Terrazzo Floor Finish.
4.4 SAND
Sand shall conform to IS 1542 specification for sand for plaster. For white or coloured renderings,
only quartz or silica sand shall be used. For textured finishes produced by treatment of freshly
applied final or finishing coat with a tool, coarser particles used shall be screened through 2.36 mm
IS sieve. For torn texture a slightly larger portion of material coarser than 4.75 mm IS sieve shall be
used.
4.5 INTEGRAL WATERPROOFING COMPOUND
Page 3 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
Integral water proofing compound shall conform to IS 2645 (specification for integral water proofing
compound).
4.6 FIBROUS MATERIAL
Certain natural fibers, such as flax, sisal, manila, jute hemp, and coconut fibers may be used in the
mortar. They shall be clean, dry and free from oil and other impurities.
4.7 EXPANDED METAL
Expanded metal used as background for rendering shall comply with requirements of IS 412.
4.8 GI OR POLYPROPYLENE CHICKEN MESH
Chicken mesh of 26 gauge with opening of 25 x 25 mm hot dipped galvanized shall be provided over
junctions of any two dissimilar materials about 150 mm wide as directed by the Owner / Owner’s
Authorized Representative.
4.9 BEADS
Zinc coated steel for exterior work shall be used. Nominal sizes to be provided are 5 mm bead with
60 mm minimum expanded metal wings. Gauge and size shall be as recommended by the approved
manufacturer.
4.10 BONDING AGENT
Chemical bonding adhesive of approved chemical admixture manufacturers shall be used over
concrete surface as per recommendations of manufacturer.
4.11 BINDER
Fiberglass fibers free of dirt, oil, grease, deleterious material or other impurities about 12 to 50 mm
long of approved manufacturer in proportion as recommended by manufacturer shall be used to
achieve dense mix as per instruction of the Owner / Owner’s Authorized Representative.
6. WORKMANSHIP
7.1 MORTAR
Page 4 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
7.1.1 Mortar shall be prepared by mixing fine graded aggregate with cement in the proportion
specified for respective items of work as detailed in the BOQ. Mixing of mortars shall be done
by mechanical mixers only. Hand mixing may be resorted to in specific cases only after obtaining
the written permission of the Owner / Owner’s Authorized Representative.
7.1.2 Mortar shall be specified by proportion only and not by strength. Volumetric mixing shall be
based on dry volumes of each ingredient. For convenience, measurement boxes shall
correspond to volume of one cement bag i.e. 0.035 cum. Boxes shall be of size 33.33 x 30 x 35
cm (L x B x D). These shall be marked as mortar mixing boxes by red paint. Hand or mechanical
mixing shall be done with the use of these boxes.
7.1.3 Sand shall be added to adjust for bulkage if required. Bulkage shall be determined as specified in
IS 2386 Part III. Cement and sand added to mixer shall be thoroughly mixed and thereafter
water shall be added to it gradually. After addition of water the mixer shall run for a minimum of
2 minutes. The mortar mixed shall be consumed within 4 hours of adding of water.
Preparation of surfaces
a) Surfaces to be plastered must be clean and free from dust, loose material, oil,
grease, mortar droppings, sticking of foreign matter, traces of moss, etc. It is very
important to ensure that there should not be any chance of the plaster getting
separated due to presence of materials harmful for bonding.
b) Raking out of joints ensures a good key between block work & plaster and is
expected to be carried out along with masonry. However, the quality of raking
shall be rechecked thoroughly prior to start of plastering work and if required the
joints shall be raked as instructed by the owner/ owner’s authorized
representative.
c) Raked Joints shall be grouted / pointed with square crushed aggregates.
d) Rust remover shall be applied to any metal surfaces which are in contact with
plaster.
e) Actual plastering shall be commenced only after completion of block masonry
works , electrical conduiting works and curing of electrical chasing works (if any)
and after obtaining the approval of the Owner / Owner’s Authorized
Representative. Plaster work should follow the steps mentioned below:
Surface must be thoroughly cleaned, hacked and applied with approved
chemical adhesive over concrete surface to receive scratch coat.
Plastered area must be provided with level dabs or spots for checking with
2-3 m straight edge. Thickness of plaster must not be less than the
thickness specified.
Corner beads may be fixed at locations shown in drawing or as required by
the Owner / Owner’s Authorized Representative.
Page 5 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
Plaster stops shall be fixed to correct line, level and plumb where plaster
terminates or abuts with other surfaces.
Requisite concealed services must be completed and tested.
No further cutting of masonry shall be permitted.
Repairs carried out to masonry or concealing work must be cured and dry.
Masonry surface must be sufficiently damp to prevent absorption of
moisture from plaster, while concrete surface can be pre-wetted and
surface dried before starting of plaster.
Plaster dabs shall be checked for plumb and level by the Owner / Owner’s
Authorized Representative. Joints, concealing and repairing areas must be
covered with GI mesh as per the instruction of Owner / Owner’s Authorized
Representative.
Any unavoidable projections in masonry and concrete surfaces shall be chiseled back. Care shall be
taken that surrounding surfaces are not damaged and reinforcement is not exposed.
Page 6 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
shall be treated with 150 mm wide reinforcing chicken mesh (approved by the Owner / Owner’s
Authorized Representative) fixed over joints by GI nails before the area is plastered.
7.6 CURING PLASTER
Date of carrying out plaster shall be painted on the surface in large visible letters to ensure
adequate curing. Plaster shall be cured for 14 days by wet curing. During this period plaster shall be
protected from exposure to extremes of temperature and weather.
7. QUALITY MANAGEMENT
8.1 All materials used shall be tested as per standards and samples approved by Owner/Owner’s
Authorized Representative
8.2 GI corner beads shall be of approved quality.
8.3 Metal reinforcement used shall be as specified and conforming to applicable Indian Standard.
Page 7 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
8.4 Mockups
Prior to start of the work, the Contractor shall prepare mockups for each type of finish and
application required to verify samples submitted and to observe / test aesthetic effect, quality of
material and workmanship.
The Mockup shall:
a) Demonstrate the proposed range of aesthetic effect and workmanship.
b) Be of full size and thickness including joints, supporting system if any, using proposed
material.
c) Be submitted within 7 days from the advance notice given to the Owner /Owner’s
Authorized Representative
d) Be retained till ordered to be removed by the Owner /Owner’s authorized representative.
Page 8 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
12.2 RATE
12.2.1 Description of item in the BOQ, unless otherwise stated, includes, wherever necessary,
conveyance and delivery handling, unloading, storing, fabrication, hoisting, all labour for
finishing to required shape and size, setting, fitting and fixing in position, straight cutting and
waste, return of packings, clearing off the work place on completion of works and other
incidental charges.
Page 9 of 10
Plaster Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/07 Technical Specifications
12. ANNEXURES
NIL
Page 10 of 10
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
Contents
1. Scope .......................................................................................................................................... 2
2. List of Standards ......................................................................................................................... 2
3. Terminology................................................................................................................................ 3
4. Materials .................................................................................................................................... 3
5. Submittals ......................................................................................................................................... 4
7. Workmanship - Fabrication ........................................................................................................ 5
6. Quality Management................................................................................................................ 13
7. Safety Management ................................................................................................................. 15
9. Environmental Management ................................................................................................... 15
10. Completion & Delivery.......................................................................................................... 16
11. Method of Measurement ..................................................................................................... 16
12. Annexures: Nil .................................................................................................................. 16
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
2. List of Standards
All work shall be carried out as per the latest version of relevant Indian Standards. The
list of IS standards given hereunder is not to be considered as conclusive and is for
reference and guidance only. Any discrepancies /conflict noticed shall be directed to the
Engineer for his direction/approval. However as a general rule more stringent
specification shall take precedence
IS Code
S.N. Title
No.
Code of Practice for use of structural steel in general
1 IS: 800
building construction
Code of Practice for use of steel tubes in general building
2 IS 806
construction.
11 IS 2062 Hot Rolled Low, Medium and High Tensile Structural Steel
3. Terminology
The following terms and abbreviations shall have the specific meanings as described
hereunder. For terms that are not described herein, the definitions as stated in the
applicable Indian Standard Specifications shall apply
3.1. Fabrication: as an industrial term refers to building a metal structure by cutting,
bending, joining and assembling of steel elements.
3.2. Shop Drawing: is a drawing or set of drawings produced by
the contractor, supplier, manufacturer, subcontractor, or fabricator. Shop drawings
are typically required for pre-fabricated components.
3.3. Joist: is one of the horizontal supporting members that run from wall to wall, wall
to beam, or beam to beam to support a ceiling, roof, or floor.
3.4. Camber: an upward curvature of a joist to compensate for load deflection due in
buildings.
3.5. Welding: a fabrication process that joins materials, usually metals by fusing them
at high temperature.
4. Materials
4.1. Structural Steel: Structural steel used in the works shall be either of the following
types : -
4.1.1. Mild steel conforming to IS 2062: 2006 - Hot Rolled Low, Medium and High
Tensile Structural Steel
4.1.2. All steel tubes shall be hot finished seamless steel tubes (HFS) or cold drawn
seamless (CDS) of the specified strength and as approved by the Engineer and
shall conform to IS: 1161.
4.2. Threaded Fasteners: All bolts and nuts shall be delivered as per technical conditions
specified in IS: 1367.
4.3. Black bolts, nuts and screws shall be In accordance with IS: 1363.
4.4. Wherever counter sunk screws are specified, they shall be precision grade, slotted,
counter sunk head, machine screws conforming to type ‘R’ of IS : 1364.
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
4.5. Wherever high tensile special quality bolts and nuts are specified, they shall comply
with provision of IS: 3757 and IS: 800.
4.6. Coach screws shall be in accordance with IS: 1120 and wood screws shall conform
IS: 451.
4.7. All plain washers shall conform to requirements of IS: 2016.
4.8. Wherever spring washers for bolts, nuts and screws are specified, they shall be in
accordance with the provisions of IS: 3003.
4.9. Cast Iron: Cast iron shall conform to IS: 210. All cast iron goods shall be of best
quality and make and as approved by the Engineer.
4.10. Cast steel shall conform to IS: 1030. Unless specified otherwise, the steel shall be
grade 2 and shall cater for all tests specified in the said standard.
4.11. Rails for the cranes shall comply with the requirements of IRST-12-64 or IS: 3443
if so instructed by the Engineer. They shall be obtained from an approved
manufacturer.
4.12. Electrodes: Electrodes used for metal arc welding of mild steel shall be heavy
coated type electrodes conforming to IS: 814 (Part l & II) and shall be of best quality
approved by the Engineer.
4.13. Handling and Storage: Structural steel shall not be stored in mud and dirt and
proper drainage of the storage area shall be provided. Steel shall be protected from
damage or from being spoilt by adjacent construction operations.
4.14. Fabricated steel shall not be handled until the paint has thoroughly dried. Care
shall be taken to avoid paint abrasions and other damages. Steel work shall be
transported in the largest practical lengths and in such a way as not to overstress
the fabricated sections.
4.15. All pieces bent or otherwise damaged shall be replaced by the Contractor at his
own cost.
4.16. Storage of fabricated steel at the job site shall be the responsibility of the
Contractor. Material shall be stored at the Job site in a manner which does not
overload the existing or newly constructed structures. Materials shall be protected
against excessive deflection, corrosion or deterioration.
4.17. As far as practicable, stacking of fabricated steel shall be done in sequence of
erection, but heavy members shall not be stacked on top of the light ones.
5. Submittals
5.1. Prior to start of delivery of structural steel, the Contractor shall submit the
following to the Engineer for review.
5.1.1. Certified copies of mill test reports including chemical analysis and physical
properties as required by the applicable Indian Standards for each consignment
of steel.
5.1.2. Where such mill certificates are not available the Contractor shall employ an
approved testing laboratory to perform the required tests and chemical analysis
at his own cost.
5.2. Before commencement of any structural steel fabrication work, the Contractor shall
submit the following to the Engineer for his approval:
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
6. Workmanship - Fabrication
6.1. Shop Drawings:
6.1.1. The Contractor shall prepare required detailed shop drawings giving complete
information necessary for the fabrication of the structure. All information should be
clearly given and the drawings shall be in conformity with best modern practices. A
marking diagram allotting distinct identification marks to each separate piece of steel
work shall be prepared in sufficient detail to ensure convenient assembly and
erection. Symbols used for welding in the drawings shall be in accordance with IS:
813.
6.1.2. The Contractors shall prepare comprehensive details of material sheets for each shop
drawings giving therein all the items shown on the drawings together with their
weights, marks, numbers, cutting lengths etc. Three copies of all working drawing and
bill of material sheets shall be submitted to the Engineer for approval.
6.1.3. Fabrication shall not commence until the approval of the relevant drawings has been
obtained from the Engineer. While the shop drawings prepared by the Contractor
and approved by the Engineer are deemed to represent the correct interpretation of
the work to be done, the Contractor is not relieved of the responsibility for accuracy
of detailed dimensions shown thereon.
6.1.4. The Contractor shall not commence detailing unless design drawings are officially
released for preparation of shop drawings. The Contractor shall be responsible for
the correctness of all fabrication drawings. Fabrication drawings shall be revised by
the Contractor to reflect all revisions in design drawings as and when such revisions
are made by the Engineer.
6.1.5. No fabrication drawings will be accepted for OWNER’S approval unless checked and
approved by the Contractor's qualified structural engineer and accompanied by an
erection plan showing the location of all pieces detailed.
6.1.6. The Contractor shall ensure that connections are detailed to obtain ease in erection
of structures and in making field connections.
6.1.7. The shop drawings prepared by the Contractor and all subsequent revisions etc. shall
be at the cost of the Contractor for which no separate payment will be made.
6.1.8. Templates: All fabrication shall be carried out in accordance with IS: 800. Extensive
use of templates shall be made. The templates shall be steel bushed where
considered necessary by the Engineer.
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
6.1.9. In case actual members are used as templates for similar pieces, it will be at the
discretion of the Engineer to decide whether such pieces are fit to be incorporated in
the finished structure.
6.1.10. The Contractor shall arrange for corresponding part of each unit manufactured
from the same drawings to be interchangeable as far as economic manufacturing
conditions permit, and shall advice the Engineer of the precise arrangement made in
this respect, but prior approval of a gas torch, but prior approval of the Owner or
Owner’s Authorized Representative, in writing, should be taken.
6.2. Cutting:
6.2.1. Gas Cutting shall normally be permitted for mild steel only. Gas cutting of high tensile
steel may be permitted provided special care is taken to leave sufficient metal to be
removed by machining so that metal hardened by flame is removed. Gas cutting shall
preferably be done by machine; Hand flame cutting may only be permitted subject to
the approval of the Owner or Owner’s Authorized Representative. Gas cut edges shall
be free of gouge. Any gouges that remain after cutting shall be removed by grinding.
6.2.2. Rolled sections shall be sawn or flame cut to length. Small plate pieces like gussets
may be sheathed or chopped to size. Sawing, shearing and chopping shall be clean
and free from any distortion. If necessary the edges shall be ground afterwards.
6.2.3. For tubular construction, cutting of the pipe and preparation of joint surface shall be
done in a neat manner for a good fit up. The ends of the tubes may be flattened or
otherwise framed for connections, provided that the methods adopted for such
flattening do not injure the material. The change of section shall be gradual.
6.3. Straightening: All materials shall be straight unless required to be of curvilinear form
and shall be free from twists. If necessary the materials shall be straightened and/or
flattened by pressure. Heating of rolled sections and plates for purpose of straightening
will not be permitted. Limited straightening may however be effected by local
application of heat with
6.4. Drilling
6.4.1. Holes shall preferable be done by drilling. Punching shall not be restored to unless
previously approved by the Owner or Owner’s Authorized Representative. In any
case, punching of holes in materials having a thickness in excess of the connector
diameter or in the materials thicker than 16mm shall not be permitted. Where
punching is permitted the holes shall be punched 3 mm less in diameter than the
required size and reamed after assembly to the full size.
6.4.2. Holes shall be drilled or punched at right angles to the surface of the member, not
more than 1.5 mm/2.0 mm (as the case may be depending upon whether the
connector diameter Is less than or more than 25 mm) larger than the connector
diameter. Holes shall not be formed or enlarged by burning or gas cutting. Holes shall
be clean-cut without torn or ragged edges. Outside burrs resulting from drilling
operations shall be removed.
6.4.3. Holes through more than one thickness of material of members such as compound
stanchions and girder flanges shall be drilled after the members are assembled and
tightly clamped or bolted together. They shall then be separated and burrs removed
if so directed by the Owner or Owner’s Authorized Representative.
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
6.4.4. Steel member’s adjustment shall be provided with slotted holes as shown on the
drawings. Suitable templates shall be used for proper location of the holes.
6.5. Fabrication Tolerances: Cutting, punching, drilling, welding and fabrication tolerances
shall be generally as per relevant IS codes.
6.5.1. Unless otherwise shown on the drawings, the fabricating tolerances shall generally be
as follows:
a. Compression members shall not deviate from straightness by more than 1/
1000 of the axial length between points which are to be laterally supported.
b. A variation of 1 mm is permissible in the overall length of members with both
ends finished for contact bearing.
c. Members without ends finished for contact bearing which are to be framed
together in parts of the structure, may have a variation from the detailed length
not greater than 2mm for members 10 meters or less in length and not greater
than 3 mm for members over 10 meters In length.
6.6. Assembly:
6.6.1. All connections shall be either bolted or welded as shown on the drawings.
Contractor shall not redesign or alter any connection without prior approval of the
Engineer.
6.6.2. The component parts shall be assembled in such a manner that they are neither
twisted nor otherwise damaged and shall be prepared so that the specified camber if
any is provided. Drifting done during assembly shall not distort the metal or enlarge
the holes. Poor matching of holes shall be cause for rejection. However if permitted
by the Owner or Owner’s Authorized Representative holes that must be enlarged due
to mismatch, shall be reamed.
6.7. Bolting:
6.7.1. All steel work which is bolted together shall be in close contact over the whole
surface. Where two bolted surfaces are to be in permanent contact after assembly,
each shall be thoroughly scraped free of loose scales, dirt and burrs and a heavy coat
of red oxide, zinc chrome or other approved paint applied after cleaning and drying.
6.7.2. All bolts shall be provided with washers under the nut tapered on the inside of the
flanges of R.S. Joists and channels. Bolts and studs shall project not less than one full
thread through the nut after tightening. Unless otherwise specified, the ends of the
bolts shall be enlarged by hammering after erection to prevent the removal of nuts.
6.7.3. High strength bolts shall be used in bearing or friction as shown on the drawings.
6.7.4. High strength bolted joints shall be made without the use of erection bolts. Bolts shall
be of a length that will extend not less than 6 mm, or three times the pitch of the
thread whichever is higher, beyond the nuts. Bolts shall be entered into holes
without damaging the threads. Members shall be brought tightly together with
sufficient high-strength fitting up bolts which shall be retightened as all the bolts are
finally tightened. Bolt-heads shall be protected from damage during placing. Bolts
that have been completely tightened shall be marked for identification. Bolted parts
shall fit solidly together and shall not be separated by interposed compressible
materials. The contact surface in high strength bolted connections shall be free of oil,
paints, lacquer, loose scale or other coatings. The facing surfaces shall be machined
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
welded. When the end of the tube is not automatically sealed by virtue of its
connection by welding to another member the end shall be properly and completely
sealed. Before sealing, the inside of the tube shall be made dry and free from loose
scale.
6.8.10. Order of assembly of the tubular sections shall consist of welding the tensile
member to the main member first. Compression members shall be cut back to
overlap the tensile member and then welded to both of these members.
6.8.11. No welding shall be done when the surface of the member is wet nor during
periods of high wind. No welding shall be done on base metal at a temperature below
5oC. Base metal shall be preheated to the temperature as per relevant IS codes.
6.8.12. Each layer of multiple layer welds except root and surface runs may be
moderately peened with light blows from blunt tool. Due care should be taken to
prevent scaling or flaking of weld and base metal from over peening.
6.8.13. Electrodes other than low-hydrogen electrodes shall not be permitted for
thicknesses of 32 mm and above.
6.9. Shop assembly:
6.9.1. Steel work shall be temporarily shop erected completely or partially as directed by
the Owner or Owner’s Authorized Representatives so that the accuracy of fit may be
checked before dispatch. Due notice shall be given to the Owner or Owner’s
Authorized Representative so that the accuracy of fit may be checked before
dispatch. Due notice shall be given to the Owner or Owner’s Authorized
Representative when the work is ready for inspection and the assembly shall not be
dismantled until it has been inspected and approved by the Owner or Owner’s
Authorized Representative.
6.9.2. The parts shall be assembled with a sufficient number of parallel drifts to bring and
keep the components in place. In the case of parts drilled or punched through steel
jigs resulting in similar parts being interchangeable for portion of the steel work,
trial assembly shall be carried out to the extent required by IS : 1915.
6.9.3. All erection marks shall be die-stamped and also distinctly stencilled in paint. The
marking shall be as per the marking diagram approved by the Owner or Owner’s
Authorized Representative.
6.10. Erection:
6.10.1. As far as possible, the Contractor shall deliver the fabricated steel work to the site
in the same sequence as that which he wishes to follow for the erection. Dispatch
should be scheduled to avoid cluttering up of the site. The bolts required for
erection shall be bagged according to size prior to dispatch.
6.10.2. All structural work shall be erected in accordance with IS : 800/IS : 806 and as per
the approved erection drawings. The Contractor shall be responsible for setting out
the works. The suitability and capacity of all plant and equipment used for erection
shall be to the Satisfaction of the Engineer. These equipments shall be regularly
serviced and maintained. Occupational safety practices shall be strictly adhered to
and shall be to the satisfaction of the Owner or Owner’s Authorized Representative.
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
6.10.3. Individual pieces shall be plumbed, levelled and aligned. Drift pins may be used only
to bring together the several parts. They shall not be used in such manner as to
distort or damage the metal. Temporary bracing, guy line and staging shall be
provided to ensure proper alignment and to adequately protect all people’s
property and to withstand all loadings to which the structure may be subjected
during erection.
6.10.4. Attachment of such temporary steel work to the permanent steel work shall only
be done with the approval of the Owner or Owner’s Authorized Representative.
Temporary steel work shall remain in position until the structure is stable and self-
supporting and permanently bolted or welded to the satisfaction of the Owner or
Owner’s Authorized Representative. After removal of temporary steel work, the
permanent structure shall be made good to the complete satisfaction of the Owner
or Owner’s Authorized Representative.
6.10.5. No permanent bolting or welding shall be done until proper alignment has been
obtained. Erection of the parts with any moderate amount of reaming, chipping
or cutting shall be immediately reported to the Owner or Owner’s Authorized
Representative. The steel work shall be rejected unless corrective action is
approved by the Owner or Owner’s Authorized Representative.
6.10.6. No erection shall be permitted more than 2 storeys above a complete bolted
and/or welded floor or above a decked surface.
6.10.7. Placement of joists shall not start until the supporting work is secured. Temporary
bracing, connections and anchors shall be provided to ensure lateral stability during
erection. Bracing to steel joists shall be installed immediately after joist erection,
before any construction loads are applied. Horizontal or vertical bracing shall be
provided in accordance with the drawing or type / span of the joists. Alternatively
ends of the bracing lines shall be anchored at node point that is laterally
restrained either by wall or by elevational bracing.
mm or ± 20 mm whichever is
less
1.4 Deviation in straightness in ± 1/1000 of column height
longitudinal and transverse planes of column in:mm or ± 10 mm whichever is
at any point along the height less
1.5 Difference in erected position of ± 10 mm
adjacent pairs of columns along length or
across width of building prior to connecting
trusses/beams with respect to true distance
1.6 Deviation in any bearing or seating ± 5 mm
level with respect to true level
1.7 Deviation in differences in bearing ± 10 mm
levels of a member on adjacent pair of
columns both across and along the building
2.0 Trusses And Beams
2.1 Shift at the center of span of top ± 1/250 of height of truss in mm
chord member with respect to the vertical or ± 15 mm whichever is less
plane passing through the center of bottom
chord
2.2 Lateral shift of top chord of truss at ± 1/1500 of span of truss in mm
the center of span from the vertical plane or ± 15 mm whichever is less
passing through the center of supports of the
truss
2.3 Lateral shift in location of truss from ± 10 mm
its true vertical position
2.4 Lateral shift in location of purlin true ± 5 mm
position
2.5 Deviation in difference of bearing i) ±20 mm for trusses
levels of trusses or beams from the true
difference
ii) For beams with:
Depth < 1800mm ±6mm
Depth > 1800mm ±10 mm
2.6 Deviation in sag in chords and 1/1500 of length in mm or 10mm
diagonals of truss between node points whichever is smaller
2.7 Deviation in sweep of trusses, beams 1/1000 of span in mm subject to a
etc. in the horizontal plane maximum of 10 mm
3.0 Crane Girders & Rails
3.1 Shift in the center line of crane rail ± 5 mm
with respect to center line of web of crane
girder
3.2 Shift in plan of alignment of crane rail ± 5 mm
with respect to true axis of crane rail at any
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical
Specifications
point
3.3 Difference in alignment of crane rail ± 1 mm
in plan measured between any two points 2
meters apart along rail
3.4 Deviation in crane track with respect
to track gauge
For track gauges upto and including 15 ± 5 mm
meters
For track gauges more than 15 meters ± [5 + 0.25 (S-15)] where S in
meters is true gauge
3.5 Deviation in the crane rail level at any 1/1200 of the gauge distance or ±
point from true level 10mm whichever is less
3.6 Difference in the crane rail actual ± 2 mm
levels between any two points 2 meters
apart along the rail length
3.7 Difference in levels between crane
track rails at
Supports of crane girders ± 15 mm
Mid span of crane girders ± 20 mm
3.8 Relative shift of crane rail surfaces at 2 mm subject to grinding of
a joint in plan and elevation surfaces for smooth transition
3.9 Relative shift in the location of crane 1/1000 of track gauge S in mm
stops (end buffers) along the crane tracks subject to maximum of 20 mm
with track gauge S in mm
4.1 Out of plumb (verticality) from the 1/1000 of the height of the
true vertical axis chimney or tower in mm
5.0 Bunkers
6.14. Cleaning and paint touch up: After erection, exposed surfaces of field connections,
unpainted areas adjacent to tie connections and damaged area of the shop coat
shall be cleaned to the same standards required as the shop coat. These shall then
be painted with the same paint used in the shop coat.
6.15. Inserts and Embedments: Various steel inserts and embedments are required under
the Contract to be fabricated, positioned and secured firmly into place inside the
formwork prior to concrete being poured. There are also requirements of jointing,
threading, bolting and welding inserts and embedments of structural steel elements
in order to establish structural continuity and connection. Great care shall be
exercised by the Contractor in executing all aspects of the work related to inserts
and embedments, including tolerances, so that the final assembly of the concrete
elements can meet satisfactorily the continuity and contiguity requirements
intended in the structure.
7. Quality Management
The contractor shall put in place a comprehensive Quality management plan to ensure
that the work is carried out as per specifications and compliance to all requirements are
established and demonstrated through comprehensive documentation. The contractor
shall engage a qualified Quality Manager to implement the quality plan. Till such time a
Quality Management Plan and ITP is approved, the following provisions shall apply
7.1 The Contractor shall give due notice to the Engineer in advance of the materials
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
7.3 End milling: Where compression joints are specified to be designed for bearing, the
bearing surfaces shall be milled true and square to ensure proper bearing and
alignment.
8. Safety Management
Apart from general safety and health hazards like working at heights, falling objects etc.,
the contractor shall assess the hazards associated with concrete works and shall take
specific action to mitigate against the same. This shall be achieved by development of a
Safety management manual. The manual shall be built around a Hazard Identification
Risk Analysis and Control matrix [HIRAC] and control measures based on the same.
Some of the hazards associate with steel works is listed for general guidance below:
8.1 All hazards associated with working with Electricity / electrical equipment
8.2 All hazards working with industrial gasses & related fire hazards
8.3 Flying sparks, metal chips or pieces
8.4 Till such time a Safety manual / HIRAC is developed and control measures
implemented, the following provisions shall apply.
8.5 Contractor shall maintain first aid facilities at site. All workmen must wear Helmets,
Safety belts, shoes etc. All required precautions including medical check-up shall be
taken for working at heights.
8.6 All critical industrial injuries shall be reported promptly to Engineer and a copy of
contractor’s report covering each personal injury requiring the attention of a
physician shall be furnished to Engineer.
8.7 The contractor shall provide, and maintain barricades, guards, guard rails, temporary
bridges and walkways, watchmen, night illuminations and danger signals illuminated
from sunset to sunrise, and all other necessary appliances and safeguards to protect
the work, life property, equipment and materials. Barricades shall be of substantial
construction and shall be painted such as to increase their visibility at night.
8.8 Notwithstanding any stipulations by Engineer, the contractor shall be solely
responsible for initiating maintaining and supervising all safety precautions and
programs in connection with the work, and shall comply with all laws, ordinances,
codes, rules, regulations and lawful orders of any public authority having jurisdiction
for the safety of persons or property or to protect them from damages, injury or loss
during the entire contract period including non-working hours.
8.9 The contractor shall perform any and all operations and shall furnish any materials
and equipment necessary during an emergency endangering life or property without
waiting for Engineer’s instructions and, in all such cases, shall notify, the ENGINEER
of the emergency as soon as practicable.
9. Environmental Management
Apart from general environmental impact of construction activities, the contractor shall
assess the environmental impact associated with rebar works and shall take specific
action to mitigate against the same. Some of the environmental aspects associate with
rebar works are listed for general guidance below.
Structural Steel Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/08 Technical Specifications
Table of Contents
1. Scope ........................................................................................................................................................ 2
2. List of Standards ....................................................................................................................................... 2
3. Terminology.............................................................................................................................................. 2
4. Materials................................................................................................................................................... 2
5. Submittals and Certifications .................................................................................................................... 3
6. Workmanship ........................................................................................................................................... 3
7. Quality Management ................................................................................................................................ 5
8. Safety Considerations and Requirements ................................................................................................. 5
9. Environmental considerations .................................................................................................................. 6
10. Completion & Delivery.............................................................................................................................. 6
11. Method of Measurement: ........................................................................................................................ 6
12. Annexure .................................................................................................................................................. 7
Crystalline Waterproofing Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/09 Technical Specifications
1. Scope
This specification applies to waterproofing work by the method of Crystallization provided
in construction. It covers waterproofing work carried out at any location in the structure
and applies to all projects of Godrej properties Ltd. It does not cover the work associated
with provision of other water proofing techniques. For the other techniques the separate
specifications which are provided, can be referred. In case of any conflict between the
provision of this document and technical recommendations or/ specifications of
manufacturer of the Crystalline water proofing compound, the later shall prevail.
2. List of Standards
Sr. No Code No. Description
3. Terminology
3.1 Crystallization: It is a catalytic reaction between the sealant and the water which forms
crystals inside the pores of the member on which it has been applied.
3.2 Pores: These are the air pockets present in the concrete member formed during the
process of hydration.
3.3 Capillary: It’s a phenomenon associated with surface tension and resulting in the
elevation or depression of liquids in pores.
4. Materials
Crystalline Waterproofing compound: This is a prepackaged, gray-colored chemical that,
when mixed with water and other approved materials and applied, penetrates into concrete
and concrete unit masonry and reacts chemically with the byproducts of cement hydration
in the presence of water to develop crystalline growth within substrate capillaries to
produce an impervious, dense, waterproof substrate. Names of some of the manufacturers
of Crystalline compound and their products are listed below.
American PERMAQUIK Inc.; Super 200.
Crystalline Waterproofing Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/09 Technical Specifications
6. Workmanship
6.1 Floor Area:-
6.1.1 The bottom of the foundation shall be leveled both longitudinally and
transversally or stepped as directed by the Engineer.
Crystalline Waterproofing Specifications PORTUS VENTUR
PV/TECSPEC/CIVIL/09 Technical Specifications
6.1.2 Before the PCC is laid, the surface shall be slightly watered and rammed. When
rock or other hard strata is encountered, it shall be freed of all loose and soft
materials, cleaned and cut to a firm surface either level, stepped, or serrated as
directed by the Engineer.
6.1.3 All seams in the bed rock shall be cleaned out and filled with PCC M10 or grout
to the satisfaction of the Engineer.
6.1.4 PCC of M10 concrete minimum thickness 100mm shall be laid over the above
compacted finished surface.
6.1.5 A layer of cement slurry admixed with approved waterproofing compound (in
the proportion recommended by manufacturer) shall be spread evenly over the
PCC layer and finished smooth.
6.1.6 The surface applied with the water proofing compound shall be cured properly
for a period of 1 to 2 days.
6.1.7 Providing and applying Chemical Crystallization Based waterproofing treatment
(from approved manufacturers) over the P.C.C. as a slurry application in 2 coats
to a total dosage rate of minimum 1.5 to 1.6 Kg. Per Sqm. or as per
manufacturers’ specification.
6.1.8 The above chemical application is protected by a coat of cement, sand mortar in
the proportion 1:4 admixed with approved waterproofing compound and
specialized acrylic based shrinkage compensating plasticizing admixture in the
proportion recommended by the manufacturer. The thickness of the treatment
shall be average 40mm.
6.1.9 The layers of sand cement mortar to be spread by grouting process. The surface
prepared to be cured properly for a minimum period of 1 to 2 days.
6.1.10 The tying of the reinforcement bars with proper cover blocks is to be undertaken
after the above layer is cured.
6.2.3 The applied waterproofing compound should be water cured for a minimum
period of 3 days before back filling.
6.2.4 All construction joints and honey combed areas in the external surface of the
retaining wall shall be chased open and treated with two coats of Crystalline
slurry application or Crystalline plugging materials.
6.2.5 All back filling work to be done only after seven days of completing the water
proofing treatment. Only murum / soft soil free from rocks / boulders should be
used for back filling near the wall, taking adequate care to avoid damage to
water proofing treatment.
7. Quality Management
7.1 The contractor shall put in place a comprehensive Quality management plan to
ensure that the work is carried out as per specifications and compliance to all
requirements are established and demonstrated through comprehensive
documentation. The contractor shall engage a qualified Quality Manager to
implement the quality plan.
7.2 The standardized Inspection and Test plans [ITP] shall be adopted for the purpose of
testing material and establishing documentary evidence of conformance to technical
requirements. If the contractor proposes to adopt his own ITP, the same shall be
submitted for the approval of the Engineer. Any dilution of the testing frequency,
acceptance criteria from the standardized ITP shall have to be supported by well-
articulated arguments.
9. Environmental considerations
9.1 Apart from general environmental impact of construction activities, the contractor
shall assess the environmental impact associated with crystalline waterproofing
works and shall take specific action to mitigate against the same.
9.2 As a general guide, the following hazards are identified as associated with Crystalline
waterproofing works.
9.2.1 Noise pollution due to operation
9.2.2 Crystalline Waterproofing Works activity involves following type of waste :
a. Non-hazardous waste: like Scrap wood, Fixtures
b. Hazardous waste like used Concrete waste, oil, paint, solvents, sealers,
thinners, Cleanup and materials contaminated with the items listed
above Drums and containers that once contained the items listed above.
9.3 When wastes are produced at the site, the contractor or subcontractor who
produces the waste typically is responsible for ensuring its proper handling and
disposal.
12. Annexure
NIL