1.0 Request For Proposal For 50 MW Solar Project at Winder and 100 MW Solar Project at Bela, Balochis
1.0 Request For Proposal For 50 MW Solar Project at Winder and 100 MW Solar Project at Bela, Balochis
REQUEST FOR
PROPOSAL
Winder and Bela Solar Projects
This Request for Proposal (RFP) has been developed in line with
NEPRA Competitive Bidding Tariff (Approval Procedure) Regulations, 2017
Table of Contents
Volume-I : Instruction to Applicants ...........................................................................................4
Abbreviations .................................................................................................................................5
1. Definitions ..............................................................................................................................6
2. Rules of Interpretation ..........................................................................................................0
3. Exhibits ...................................................................................................................................1
4. Invitation to Bid .....................................................................................................................2
5. Background for Development of Projects ...........................................................................4
6. [Not used] ...............................................................................................................................2
7. Land ........................................................................................................................................2
8. RFP Process ...........................................................................................................................2
8.1. Major Project Milestones ................................................................................................... 3
8.2. Reservation of Rights .......................................................................................................... 3
8.3. Communications.................................................................................................................. 4
8.4. Clarification on RFP Documents ....................................................................................... 4
8.5. Cost and Expenses............................................................................................................... 4
8.6. Applicable Law and Dispute Procedure ........................................................................... 4
8.7. Grievance and Redressal Procedure ................................................................................. 4
9. Guidelines for Bid Submission .............................................................................................6
9.1. Bid Documents..................................................................................................................... 6
9.2. Bid Submission Requirements ........................................................................................... 6
9.3. Technical Proposal .............................................................................................................. 7
9.4. Tariff Proposal .................................................................................................................... 8
9.5. Bid Package ......................................................................................................................... 8
9.6. Bid Bond............................................................................................................................... 8
9.7. Performance Guarantee ..................................................................................................... 8
9.8. [Not used] ............................................................................................................................. 9
9.9. Bid Validity .......................................................................................................................... 9
9.10. Basis for Disqualification.................................................................................................... 9
9.11. Fee Structure ..................................................................................................................... 10
10. Bid Evaluation Committee .................................................................................................10
11. Selection of Successful Bidder for each Project ................................................................10
11.1. Requirements after selection of Successful Bidder ........................................................ 10
12. No Lobbying.........................................................................................................................12
13. Disclaimer ............................................................................................................................13
Volume-II : Project Technical Requirements ...........................................................................15
14. Prequalification of Applicants ............................................................................................................. 16
15. Project Requirements .......................................................................................................................... 16
15.1. Solar Panel ......................................................................................................................... 16
15.2. Power Inverters ................................................................................................................. 18
15.3. Gas Insulated Switchgear (GIS) ...................................................................................... 19
15.4. Power Transformer and Other Switchyard Equipment ............................................... 19
15.5. SCADA, Tele-Communication and Protection Schemes ............................................... 20
15.6. Metering System and Back-up Metering System ........................................................... 20
15.7. Weather Station................................................................................................................. 20
15.8. Civil/ Mounting Structure ................................................................................................ 21
15.9. Balance of System.............................................................................................................. 21
15.10. Safety & Security .............................................................................................................. 22
15.11. Plant Monitoring System .................................................................................................. 22
15.12. Interconnection Requirements......................................................................................... 22
15.13. Local Considerations ........................................................................................................ 22
15.14. Local Industry ................................................................................................................... 22
15.15. Design Experience and Capability ................................................................................... 22
15.16. Yield Assessment ............................................................................................................... 23
15.17. Operations and Maintenance ........................................................................................... 23
15.18. HSE..................................................................................................................................... 23
15.19. Warranty............................................................................................................................ 25
Volume-III : Tariff Proposal Requirements .............................................................................26
16. Quoted Tariff and Commercial Requirements .................................................................................... 27
16.1. Bid Tariff .......................................................................................................................... 27
16.1.1. Indexation mechanism 3 SBP Financing .......................................................................... 27
16.1.2. Indexation mechanism 3 Commercial Financing.............................................................. 28
16.2. Bid Tariff Assumptions..................................................................................................... 29
16.3. Pass-through Items ............................................................................................................ 29
Exhibits .........................................................................................................................................30
Exhibit 1 – [Not used] ..................................................................................................................... 31
Exhibit 2 – Confidentiality Agreement.......................................................................................... 32
Exhibit 3 – Form of Covenant of Integrity ................................................................................... 38
Exhibit 4 – Power of Attorney........................................................................................................ 40
Exhibit 5 – Affidavit ........................................................................................................................ 42
Exhibit 6 – Letter of Acceptance by the Applicant/Bidder ......................................................... 44
Exhibit 7 – Bid Evaluation Criteria ............................................................................................... 45
Exhibit 8 – Form of Bid Bond ........................................................................................................ 47
Exhibit 9 – Form of Performance Guarantee ............................................................................... 50
Exhibit 10 – Bid Tariff .................................................................................................................... 53
Exhibit 11 –Energy Purchase Agreement ..................................................................................... 54
Exhibit 12 – Feasibility Study Report ........................................................................................... 55
Exhibit 13 – Form of Letter of Intent to the Successful Bidder .................................................. 58
Exhibit 14 – Financing Structure and Equity Commitment from Sponsors ............................. 63
Exhibit 15 – Prequalification Document ....................................................................................... 64
Exhibit 16 – Waste Management Procedure ............................................................................... 65
Exhibit 17 – Hazard Substance Management Procedure ........................................................... 66
Exhibit 18 – Safety Signs and Barricade Guidelines .................................................................... 67
Exhibit 19 – NOC from Balochistan Environmental Protection Agency ................................... 68
Volume-I : Instruction to Applicants
Abbreviations
BOO Build-Own-Operate
COD Commercial Operations Date
CPI Consumer Price Index (General) of Pakistan
CSR Corporate Social Responsibility
EIA Environmental Impact Assessment
EPC Engineering, Procurement and Construction
EPA Energy Purchase Agreement
IEC International Engineering Council
IPPs Independent Power Producers
KE K-Electric
kW Kilo Watt
kWh Kilo Watt Hour
LOI Letter of Intent
MW Mega Watt
NEPRA National Electric Power Regulatory Authority
NOC No Objection Certificate
PKR/Rs Pakistani Rupees
PST Pakistan Standard Time
RFP Request for Proposals
US CPI United States of America Consumer Price Index (All Urban Consumers)
USD/US$ United States Dollars
1. Definitions
Awarded Tariff The Bid Tariff of the Successful Bidder as per the Tariff Approval.
A company incorporated and existing under the Companies Act, 2017 (or
any predecessor or successor legislation), foreign companies registered
according to the laws of the country of origin, a consortium/joint venture or
Bidder(s)
a natural person that is prequalified by the Relevant Agent and submits the
Bid for the development, financing, construction, operation and
maintenance of the Project
Bid Evaluation Committee The committee formed by the Relevant Agent for bid evaluation.
Bid Processing Fee A non-refundable processing fee of PKR 1,500,000/- for each Project.
Capitalized Term Meaning
A single tariff submitted for the life of the Project in Rs./kWh at the
Bid Tariff
Reference Exchange Rate.
Any Day on which banks are legally permitted to be open for business in
Business Day
Karachi, Pakistan.
The factor of 21.5% approved under the RFP Decision as the knock-off
criteria, calculated as the ratio of annual plant net electrical output recorded
Capacity Factor
by metering system at the 132 kV side of the step-up trafo and the maximum
annual generation capacity in DC.
Commercial Operation
The meaning ascribed thereto in EPA.
Date (COD)
The distribution code 2005 approved by NEPRA which defines the technical
and operational aspects of the relationship between Distribution Company
Distribution Code
and all those entities connected to the Distribution System, as maybe
amended from time to time and as applicable to KE
Energy Purchase The Energy Purchase Agreement in the form provided in Exhibit 11 to be
Agreement (EPA) executed by KE and the Seller and duly approved by NEPRA.
The Grid Code 2023 approved by NEPRA, which sets out the technical
requirements, guidelines, rules and procedures to be adopted by the System
Operator and all Code Participants for effective planning, seeking new
connections or modification in the existing ones, reliable and coordinated
Grid Code protection of the National Grid, precise Metering at the Connection points
and economic System Operation purposes for normal and abnormal
Transmission System conditions, as it may be revised from time to time with
any necessary approval by NEPRA and notified to the Bidder and as
applicable, to KE
Grievance Redressal
The committee formed by the Relevant Agent for redressal of grievances.
Committee
The Site for each Project near the towns of (1) Winder; and (2) Bela, of the
Locations Lasbela district in Balochistan province with each such location fully
described in Section 5.8.
Pre-qualification
A non-refundable processing fee of PKR 50,000/-
Application Fee
Reference Exchange Rate USD to PKR rate of 288.65 determined in the RFP Decision for the purpose
of Open Competitive Bidding.
Capitalized Term Meaning
Relevant Agent K-Electric Limited in its role as bidding agent for carrying out competitive
bidding of tariff in accordance with NCBTR.
The approval of RFP document for the Projects by NEPRA vide its decision
RFP Decision
no. NEPRA/Advisor(CTBCM)/RFP-04/3115-21 dated 29 February 2024.
The SPV that will sign EPA with KE subject to fulfillment of conditions in
Seller
LOI.
Special Purpose Vehicle A company to be formed by the Successful Bidder with the specific purpose
(SPV) of undertaking a Project(s) awarded to it at the allocated Site.
The Bidder selected by the Relevant Agent in the bid evaluation process
Successful Bidder which will be issued the LOI by the Relevant Agent after NEPRA approval
/ ratification of Bid Evaluation Report.
In this RFP:
2.1 Headings are only for convenience and shall be ignored in construing this RFP.
2.3 Other capitalized terms have the meaning given to them in the text of Instruction to bidders,
attachments or exhibits in this RFP, if undefined, the terms will be clarified in the EPA.
2.4 Unless the context requires otherwise, references to times and dates are, and shall be construed to be,
references to Pakistan Standard Time.
2.5 References to clauses and Exhibits are, unless the context otherwise requires, references to clauses
and Exhibits to this RFP.
2.6 A reference to any legislation or legislative provision includes any statutory modification or re-
enactment of or legislative provision substituted for, and any subordinate legislation under, that
legislation or legislative provision; and
2.7 The term <K-Electric Limited= and <Relevant Agent= shall be synonymous with <KE= and vice versa.
3. Exhibits
Exhibits Title
Exhibit 5 Affidavit
4.1 This RFP is being floated in accordance with the NCBTR to the public at large.
4.2 All communication with KE will be through ARIBA. The Applicant/ Bidder shall self-register for
ARIBA by using the below provided link to participate in the bidding process:
http://k-electric.supplier.mn1.ariba.com/ad/selfRegistration
4.3 Pursuant to the RFP Decision for conducting the prequalification process as part of technical
evaluation of the RFP, this document is drafted in a manner that specifies the requirement
accordingly.
4.4 An Applicant intending to participate in the process will be evaluated for prequalification in
accordance with Exhibit 15 of this document as part of their technical evaluation.
4.5 Acting as Relevant Agent as stipulated in the NCBTR, KE hereby invites Applicants/Bidders to
submit Technical and Tariff Proposals for solar projects at Winder and Bela in the Lasbela District
of Balochistan on BOO basis with following capacities depending on the mode of financing:
(i) SBP Financing: In case, the Bidder secure SBP financing for the Project(s), the Bidder
shall bid for projects considering following capacities:
The Bidder will make all reasonable efforts to secure concessionary financing under the State Bank
of Pakistan (SBP) Financing Scheme for Renewable Energy (<SBP Financing=). In case of non-
availability of SBP Financing, the Bidder may be requested to submit documentary evidence for non-
availability of SBP Financing.
A Bidder may submit bids for Winder and/or Bela. In case a Bidder intends to Bid for Bela it shall
bid for both Bela 1 and Bela 2 in case of SBP Financing.
For abundant clarity, the above provisions are applicable in case of availability of SBP financing on
any of the Project(s). However, the bidder may submit bid on commercial financing for the remaining
Projects.
(ii) Commercial Financing: In case, the Bidder is unable to secure SBP financing for
development of Projects it is required to submit their bids considering commercial
financing on following Project capacities:
4.7 The Applicant shall submit its complete Bid for the number of Projects it wishes to bid for. However,
the bid evaluation will be done for the number of Projects it has qualified for as per Exhibit 15. The
Applicants bidding for both Winder and Bela are required to submit only one Exhibit 15 in the Winder
Technical Bid Submission Envelope.
4.8 The Bid should be separate for each Project in accordance with Section 4.5 above since each of these
Projects are planned to be developed under a separate and independent SPV structure. The bids will
be evaluated independent of each other.
4.9 The Bid must comply with the RFP requirements and RFP Decision at all times.
4.10 The Bids along with the Bid Bond must be delivered no later than the deadline specified in Section
9.8.
4.11 The Applicant/Bidder must follow all applicable laws of Pakistan including State Bank of Pakistan
funding requirements where applicable.
4.12 The Applicant/Bidder shall obtain relevant board approvals for participation in the Project(s)
including but not limited to the board approval required under Exhibit 4 and Exhibit 14.
4.13 Relevant Agent will select the Successful Bidder based on evaluation criteria stipulated in Exhibit 7
of RFP. Tariff Proposal for each Project shall remain unopened until the evaluation/scoring of
Technical Proposal for the Project is completed. Once completed, K-Electric will then open the Tariff
Proposal of technically qualified Bidders. The Bidder offering the lowest Bid Tariff will be selected
as the Successful Bidder. In the event that the lowest Bid Tariff of two or more Bidders are equal, the
Bidder offering the maximum discount to the Bid Tariff will be selected as the Successful Bidder. In
case of default or disqualification of a Successful Bidder, the next in line Bidder with the lowest Bid
Tariff will be selected.
4.14 KE and NEPRA reserves the right to reject the bid if found imprudent based on KE9s assessment of
the successful bid.
4.15 The Successful Bidder will only be awarded the LOI after NEPRA9s approval of Bid Evaluation
Report. Upon issuance of the LOI the Successful Bidder shall form the SPV.
4.16 Subsequent to the formation of SPV, the SPV will be required to, interalia, (i) obtain Generation
License/Concurrence and Tariff Approval from NEPRA (ii) enter into EPC contract for the design,
construction and commissioning of the Complex (iii) enter into EPA with KE, and other necessary
Project agreements, (iv) obtain any relevant regulatory and corporate approvals (v) arrange the
necessary financing for the Project(s) and achieve financial close (vi) construct and implement the
Project to achieve COD within the time period allowed by NEPRA in the Tariff Approval, and (vii)
upon commissioning, operate and maintain the Complex for the Term to provide the generated
electricity to KE as per the terms and conditions of the EPA and Tariff Approval.
4.17 The Successful Bidder will implement the Project consistent with this RFP, the LOI, NEPRA9s
requirements stated in Generation License and Tariff Approval, and the EPA, and shall undertake all
activities incidental or ancillary to implementation of the awarded Project in accordance with the
aforementioned documents.
5. Background for Development of Projects
5.1. K-Electric Limited (<KE=) is a publicly listed utility company and the only vertically integrated
power utility, engaged in the Generation, Transmission, and Distribution of electricity in Pakistan.
K-Electric has exclusive distribution rights for Karachi and its adjoining areas including Dhabeji and
Gharo in Sindh and Hub, Uthal, Winder and Bela in Balochistan. The Company has around 2.9
million industrial, commercial, agriculture and residential consumer base and is supplying electricity
to over 20 million people.
5.2. KE produces electricity from its own generation units and also has arrangements with external power
producers. KE9s licensed installed capacity including 900 MW of BQPS III is 2,817 MW. Further,
KE has arrangements with external power producers for over 1,600 MW which includes supply from
various IPPs covering gas, coal and solar technologies, and the National Grid without the backing of
a sovereign guarantee or government's implementation agreement. Besides this, KE9s transmission
system comprises of 1,354 km of transmission lines, 71 grid stations and 179 power transformers.
KE operates under the regulatory regime of NEPRA.
5.3. KE has launched this RFP as an initiative to meet its goal of supplying 30% of its electricity
generation from renewable resources by 2030.
5.4. The Winder, and Bela towns are located in the Lasbela district of Balochistan which falls under KE
distribution franchise. The existing transmission network from Winder to Bela is 66 kV which is
planned to be replaced with new transmission lines and grids of 132 kV. The program of this
upgradation is currently under review with NEPRA for approval. The 132 kV transmission system is
planned to be available before each Project9s COD.
5.5. With the transmission system being upgraded to 132 kV in the Lasbela district, KE is planning to
install under IPP mode, solar projects of 50 MWp Capacity at Winder and a cumulative 100MWp at
Bela through Open Competitive Bidding pursuant to NCBTR. This RFP is a step towards
implementation of this plan.
5.6. Given the low power generation tariffs for solar power generation projects, these projects are
expected to lower the overall generation cost for KE consumers.
5.7. The Projects will be installed at the Sites allocated by GoB situated at Winder and Bela in
Balochistan. The details of interconnection of each of the Project along with the KE9s transmission
network is provided in the FSR attached as Exhibit 12. Brief details of the grid stations and their GPS
Coordinates are provided in the table below. Please refer to Volume II of this RFP for Project9s
technical requirements.
5.8.1. Winder
5.8.2. Bela
7. Land
7.1. BECL will be responsible for land allocation for each Project against lease rentals for the Land Cost.
7.2. Land will be transferred to SPV at or prior to the Financial Close in accordance with the Land Lease
Agreement to be entered between the SPV and BECL.
7.3. The land will be returned to BECL after completion of the lease period i.e., 30 years unless otherwise
extended.
8. RFP Process
The purpose of this RFP is to hold Open Competitive Bidding for the Project(s) under NCBTR.
The Bid shall be a single stage, two-envelope bidding process. The contents required for evaluation of the
Bids are detailed in the ensuing clauses of this RFP.
Any Applicant/Bidder interested in submitting its Bid for a Project pursuant to this RFP will be required to
submit separate envelopes for Technical Proposal and Tariff Proposal for each Project and submit the same
on ARIBA for which Applicant/Bidder registration is mandatory as provided in Section 9.2. In case an
Applicant/Bidder is interested in bidding for more than one Project then it shall submit separate Bids for
each Project. Bids received against each Project shall be evaluated separately in accordance with the
specific requirements of each Project. Based on the results of the bidding process and subject to the
compliance with the RFP as well as regulatory requirements, a Bidder may be declared successful in a
single or multiple Projects for which it has submitted its separate Bids. Selection of the Successful Bidder(s)
to undertake the Project(s) will be pursuant to the evaluation criteria stipulated in Exhibit 7 of this RFP.
As is common practice, Tariff Proposals shall remain unopened until the technical evaluation has been
completed. K-Electric will then open the Tariff Proposal of technically qualified Bidders and select the
Successful Bidder(s) with the lowest Bid Tariff, in accordance with Exhibit 7.
The Applicants will initially be assessed for prequalification as part of the technical evaluation process.
Applicants not satisfying the prequalification criteria outlined in Exhibit 15 will not be eligible for technical
bid evaluation. The Applicants already prequalified by KE will not need to undergo prequalification again.
KE reserves the right to seek clarifications on the Bids received from the Applicants/Bidders. K-Electric
will then issue LOIs to the Successful Bidder(s) for the respective Projects.
8.1. Major Project Milestones
Timeline
S. No. Milestone
Note:
1. These timelines are indicative and subject to change in conjunction with NEPRA approval.
2. Construction activities will be initiated right after Financial Close.
The Bidder shall have the sole responsibility to determine and to satisfy itself by such means as it considers
necessary or desirable as to all the matters pertaining to the execution of Project(s), including the precise
location of Project, the weather conditions, the terrain and geological conditions at the selected site,
availability of resources to be used in Project and all other factors that may affect the cost, duration and
execution of Project.
K-Electric shall assume no responsibility regarding any interpretation made by the Bidder/Applicant from
the information furnished by K-Electric including any studies carried out by its consultants.
No verbal agreement or conversation with any director, officer, employee, representative or agent of K-
Electric shall affect or modify any of the terms or obligations of K-Electric and the Bidder/Applicant
contained in the RFP.
8.3. Communications
All communications from the Applicant/Bidder concerning the RFP process, including any clarification,
scheduling a meeting, shall be submitted through ARIBA. The Applicant/Bidder shall provide the name,
email and telephone contact details for the individual(s) authorized to communicate with K-Electric as per
the Power of Attorney in the format attached as Exhibit 4.
8.4. Clarification on RFP Documents
The Applicant/Bidder may request clarifications on the RFP).
The Applicant/Bidder shall make all clarifications requests if any before 22 April 2024 through ARIBA.
K-Electric will not respond to any clarifications received after the clarification deadline. K-Electric may
also conduct a clarification and/or pre-bid meeting with the Applicants/Bidders and in such case shall notify
each Applicant/Bidder of the date, time and location for the meetings. The clarification meetings, if
required, will be arranged and KE will communicate the venue of such meetings which will be a
combination of physical and online. Applicants/Bidders shall be responsible for obtaining all visas and
necessary travel documents. Any other mode of informal communication will not be permitted during the
RFP process and such communication shall be considered invalid.
Exhibits Title
Technical
Exhibit 5 Affidavit
Financial
Other Forms
Once registration is successfully completed, event access will be provided to the Applicant/Bidder for
bid submission. All communication, including any clarifications to bid documents will be done through
ARIBA.
e) The Applicant shall notify its registration at ARIBA at the following email address:
Email for 50 MW Solar Project at Winder: [email protected]
Email for 100 MW Solar Project at Bela: [email protected]
Any queries related to ARIBA registration shall also be addressed at the above email address.
f) The complete Proposal shall be delivered via courier and through ARIBA to KE no later than 18:00
hours Pakistan Time, 20 May 2024. Any Proposal submitted after the deadline may be rejected and
returned unopened.
g) Documents that require signatures shall be hand signed by the authorized representative before
conversion to PDF format.
h) Failure to submit the Bid either through Ariba or sealed bid will be subject to disqualification.
Furthermore, the Bidder shall ensure consistency between the documents submitted on ARIBA and in
original hard copies. KE will have the right to disqualify any Applicant/Bidder in case of any material
differences between the documents.
9.3. Technical Proposal
In its Technical Proposal, the Bidder must respond to the requirements stated in Volume-II of the document.
The Technical Proposal for each Project will be separate, as these will be evaluated separately and
independently from each other. A technical proposal should be clearly marked so that it is easily identifiable
to which Project it pertains.
Technical Proposal should comprise of the following documents:
The Technical Proposal comprising one paper original shall be in one sealed envelope labelled
"TECHNICAL PROPOSAL", with the Applicant/Bidder's name clearly displayed, and electronically
though ARIBA.
9.4. Tariff Proposal
In its Tariff Proposal the Bidder must respond to the requirements stated in Volume-III of the RFP. Tariff
Proposals shall remain sealed until the assessment of the Technical Proposals has been completed. The
Tariff Proposals are also required to be submitted separately and independently for each Project.
Tariff Proposal should comprise of the following documents;
The Tariff Proposal shall be submitted as one paper original in one sealed envelope labelled <Tariff
Proposal=, with the Bidder's name clearly displayed, and electronically though ARIBA.
[BIDDER'S NAME]
CONFIDENTIAL
1. Any Bid which is conditional, or which contains material deviation from the requirements of this RFP.
3. After submission of the Bid by the Applicant/Bidder, if queries are raised by the Relevant Agent via
ARIBA and the Applicant is non-responsive for 5 business days.
4. The information submitted materially deviates from the requirements and criteria defined in the RFP is
false, misleading, or materially inaccurate upon verification by KE.
5. If the Applicant/Bidder or any of its officers, directors or owners thereof have been in substantial non-
compliance of the terms and conditions of this RFP including the undertakings attached hereto;
6. If the Applicant/Bidder or any of its officers, directors or owners have a history of non-complying with
applicable legal, social environmental and regulatory frameworks.
7. If the Applicant/Bidder or any of its officers, directors or owners have any court or regulatory decision
against them which in KE9s opinion may materially affect their performance and execution of the
Project.
8. If the Applicant/Bidder is currently in willful default of its obligations to any bank or financial
institution within or outside Pakistan.
9. Failure of the Applicant/Bidder to disclose and/or provide any additional information as may be
required by KE during the evaluation process.
10. Failure to report promptly to KE any material change in the circumstances of the Bidder affecting its
eligibility to submit the Bid(s) or to implement the Project(s) following submission of the Bid(s);
11. Failure to report to KE any information that at the relevant time or with the passage of time results in
or is likely to result in any information provided in the Bid or any documents submitted therewith
ceasing to remain accurate or becoming misleading;
12. Failure to comply with the requirements of this RFP including, without limitation, failure to submit
documents and information consistent and compliant with the requirements of this RFP or failure to
commit to the required bidding and project development schedule provided in this RFP; or
13. An Applicant/Bidder appearing in more than one Bid for the same Project shall be disqualified.
14. If the Bid is found imprudent by KE and/or by NEPRA.
15. In case NEPRA issues any directions with respect to any Bidder or the bidding process.
Notwithstanding anything in this section, K-Electric reserves the right to disqualify any Bidder if K-Electric
determines, in its sole judgement, that the Bidder is technically and/or financially or otherwise incapable
of executing the Project(s) and/or the Tariff Proposal does not meet or reflect the requirements of the RFP.
It must be noted that all Applicants intending to participate in the process will be required to submit both
the Bid Processing Fee and the Prequalification Fee along with their Bid. However, if such Applicant fails
to prequalify for the Project(s), Applicant9s Bid Processing Fee will be refunded to the Applicant in due
course of time.
a) One (1) independent consultant having expertise in competitive bidding and fulfilling the independence
requirement of NCBTR.
b) Four (4) representatives from KE having Technical, Commercial, and Financial Expertise.
a) While bidding for the Project, the Bidder shall submit a single tariff for the whole tariff control period
(i.e., 25 years)
b) The Bidder offering the lowest Bid Tariff will be selected as the Successful Bidder. In the event that
the lowest Bid Tariff of two or more Bidders are equal, the Bidder offering the maximum discount on
the Bid Tariff will be declared as the Successful Bidder.
c) Successful Bidder will be finalized after NEPRA approval of Bid Evaluation Report. Both KE and
NEPRA shall have the right to reject the bid if the successful bid is found imprudent.
2. The SPV shall file an application with NEPRA for approval of tariff by NEPRA in accordance with
Part VIII of the NCBTR.
3. KE will sign EPA with the SPV formed for each Project after approval by NEPRA.
4. The SPV must follow the NEPRA's regulatory framework and pay all the fees for Generation
License/concurrence and Tariff Approval. Any other regulatory fees that may materialize on the Bidder
shall also be borne by the Bidder.
5. In the event that a Bidder/Applicant defaults in fulfilling its obligations under this RFP, the NCBTR or
the LOI requirements, or withdraws its Bid after being declared successful, KE shall be entitled to
encash the Bid Bond or the Performance Guarantee (as the case may be) of the defaulting Successful
Bidder upon its failure to rectify the default(s) as notified in writing by KE to the Successful Bidder
within the stipulated period with such rectification period be not less than 10 Business Days. Provided
that if after being notified, the Successful Bidder rectifies the default(s) within the stipulated period,
KE shall not encash the Bid Bond or the Performance Guarantee (as the case may be) and the Successful
Bidder shall be allowed to continue with the requirements under the LOI and NCBTR.
6. In case a Bidder withdraws its Bid after it has been submitted, KE shall encash the Bid Bond of such
Bidder. Additionally, in the event of a default and subsequent disqualification of a Successful Bidder,
KE reserves the right to replace such Successful Bidder with the next in line Bidder with the lowest Bid
Tariff.
7. The SPV will be required to complete the regulatory process to obtain all relevant consents and
approvals and achieve Financial Close in accordance with the timelines specified in the LOI. The SPV
will be required to construct the Project consistent with the technical specifications, equipment details
and design parameters that are consistent with the Technical Proposal of the Successful Bidder received
pursuant to this RFP and agreed with K-Electric in the EPA with the approval of NEPRA. Any
variations to above that are determined to be material by K-Electric, shall result in revocation of the
LOI by K-Electric and encashment of Performance Guarantee provided that K-Electric shall notify in
writing to the Successful Bidder of such material deviations and allow ten (10) Business Days for
rectification of such material deviations.
12. No Lobbying
Any Applicant/Bidder firm, corporation or individual members of an Applicant/Bidder will not attempt to
communicate directly or indirectly with any representative of the KE or any Applicant/Bidder during the
evaluation process except as expressly directed or permitted by KE, or except as may be required and
permitted under another procurement competition, project or other assignment, in which event the
Applicant/Bidder will not have any discussions regarding the Project. KE reserves the right to disqualify
the Applicant/Bidder that, in KE9s opinion, has engaged in lobbying in connection with this Project.
13. Disclaimer
This RFP document is not an agreement or offer by KE to the prospective bidders or any other party. The
information contained in this RFP has been prepared to assist each Bidder in making its own evaluation of
the Project and does not purport to contain all of the information that such Bidder may desire with respect
to the Project.
In all cases, the Bidder is required to conduct its own due diligence, investigation and analysis including
but not limited to Site assessment, interconnection assessment, energy yield etc.
KE shall under no circumstances be responsible or liable to reimburse the cost associated with the
preparation and submission of the Bids regardless of the outcome of the bidding process.
None of KE or its directors, officers, employees or advisors makes any representation or warranty, express
or implied, as to the accuracy or completeness of this RFP or the information contained herein and none of
KE or its directors, officers, employees or advisors shall not be liable for any of the information contained
herein, or omitted from this RFP, nor for any of the written, oral, electronic or other communications
transmitted to the Applicant/Bidder in the course of Applicant/Bidder9s investigation and evaluation of the
Project and submission of its Bid pursuant to this RFP.
Only those representations and warranties that are made in a definitive written agreement, when and if
executed, and subject to any limitations and restrictions as may be specified in such definitive written
agreement, shall have any legal effect.
Each Bidder shall be responsible for its own independent evaluation and assessment of the Project and
should consult its own professional advisors and consultants accordingly.
The Bidder accepts that any disputes arising from or in connection with this RFP or the Relevant Agency,
shall be submitted in first instance to the Grievance Redressal Committee. In case the final findings of the
Grievance Redressal Committee are not acceptable to the aggrieved Bidder, such aggrieved Bidder shall
have the right to submit the dispute before NEPRA being the competent authority on the matter.
Volume-II : Project Technical Requirements
14. Prequalification of Applicants
In pursuant to RFP Decision, any Applicant which intends to participate in the process shall submit the
prequalification application in accordance with the terms of the Prequalification Document attached as
Exhibit 15.
The Applicants already prequalified by KE shall not be required to undergo the prequalification process
again or submit Exhibit 15. KE reserves the right to seek additional information from any Applicant/Bidder.
Only those Applicants meeting the prequalification criteria outlined in Exhibit 15 will be eligible for
technical bid evaluation.
Bidders should consider the technical details provided in Section 15 in relation to the preparation of their
Bid. Bidders are encouraged to provide any additional information or illustrations other than mentioned
below which may best represent their proposal for each Site.
Developer will ensure that the plant is equipped with necessary technology to maximize energy yield and
avoid unnecessary curtailment of power due to technological limitations.
Some of the specifications relating to the site9s condition shall be considered for evaluation after Feasibility
and EIA studies recommendation.
All plant and equipment shall be new and shall be designed, manufactured, and tested in accordance with
the latest IEC standards or other equivalent standards. The verification of the new machinery will be done
by the Independent Engineer at the time of the commissioning of the Complex duly verified by the KE.
15.1. Solar Panel
Panels considered for the Project should be Tier-1 as determined by BNEF. Tier-2 or above shall be
disqualified without any assessment. Bidder shall select the technology of panel considering the site/area
condition.
a) Warranties:
S. No. Description
i Solar panels standard generation warranty of 25 to 30 years will be mandatory.
b) Standards:
Solar PV Modules shall be "Type Certified" on latest IEC/UL/NFPA standards by an internationally
accredited certification body, acceptable to KE. The Solar PV modules will be selected as per below
accepted international standards:
Standard Description
Crystalline silicon (c-Si) terrestrial PV modules 3 Design qualification and
IEC 61215
type approval
IEC 61646 Thin-film terrestrial PV modules - Design qualification and type approval
IEC 60364-4-41 Protection against electric shock
IEC 61701 Resistance to salt mist and corrosion
IEC 62804 System voltage durability test for c-Si modules
Standard Description
Comply with the National Electric Code, Occupational Safety and Health
UL 1703 Administration and the National Fire Prevention Association. The modules
perform to at least 90% of the manufacturer9s nominal power.
IEC 62738 Plant Design
EN-50380 Datasheet and Nameplate information of PV modules as per standard
IEC 61724-1-2-3 Performance monitoring-Capacity Evaluation-Energy Evaluation
IEC 63049 PV System Installation
IEC 62446-2 System Maintenance
IEC 62446-1 Documentation, Test and Inspection
IEC 60904-1 Measurements of PV current-voltage characteristics
Determination of the equivalent cell temperature (ECT) of photovoltaic
IEC 60904-5
(PV) devices by the open-circuit voltage method
Computation of the spectral mismatch correction for measurements of
IEC 60904-7
photovoltaic devices
IEC 61345 UV test for photovoltaic (PV) modules
Scope of the work in progress includes PV module safety qualification
IEC 61730-1
requirements for construction
IEC 61730-2 Photovoltaic (PV) module safety qualification
Scope of the work in progress includes on-site measurement of I-V
IEC 61829,
characteristics for crystalline silicon PV array
Scope of the work in progress includes irradiance and temperature
IEC 61853-1 performance measurements and power rating for PV module performance
testing and energy rating
Scope of work in progress includes spectral response, incidence angle and
IEC 61853-2 module operating temperature measurements for PV module performance
testing and energy rating
IEC 62716 Ammonia corrosion testing of photovoltaic (PV) modules
Grid connected photovoltaic systems 3 Minimum requirements for system
IEC 62446
documentation, commissioning tests and inspection
82/618/NP Specification for solar trackers used for photovoltaic systems.
ISO9001 Type tested and comply ISO9001
NFPA Article 690 Solar Electric Systems
NFPA Article 705 Interconnected Electrical Power Production sources
c) Efficiency:
S. No. Description
Sun to DC efficiency of modules above 17% and loss of efficiency due to rise in
i
temperature as per IEC standard
d) The Bids should clearly indicate the details including the type of units, make and model of the Solar
PV Modules to be installed in the Complex as per the Feasibility Study Report.
e) It is recommended that the Bidders choose solar panels that have increased/improved efficiencies,
extended warranties and insurance coverage.
15.2. Power Inverters
a) Warranties:
S. No. Description
Inverters are procured from Companies in the manufacturing business for atleast 10
i years which are used in Commercial/Utility scale projects (05 MW and above) and
operational
ii Provision of minimum standard warranty is mandatory
b) Standards:
String or central inverters can be used in the Project that comply with the below IEC or equivalent
standards.
Standard Description
Photovoltaic systems4Power conditioners4Procedure for measuring
IEC 61683
efficiency
IEC 61721 Characteristics of the utility interface
Islanding prevention measures for utility-interconnected photovoltaic
IEC 62116
inverters
IEC 62109-1and 2 Safety of power converters for use in photovoltaic power systems
EN 61000-6-2 and4 Electromagnetic Compatibility (EMC)
EN 50178 Electronic equipment for use in power installations
EN 50524 Datasheet and Nameplate for Inverters
Information technology equipment. Radio disturbance characteristics.
EN 55022
Limits and methods of measurement.
Electromagnetic compatibility (EMC). Immunity for residential,
EN 61000
commercial and light-industrial environments
IEC 62548 Installation and Safety Requirements for wiring
IEC 61683 PV systems 3 Power conditioners 3 Procedure for measuring efficiency
Balance-of-system components for photovoltaic systems - Design
IEC 62093
qualification natural environments.
IEEE 519 1992 Compliance to Total Harmonic Distortion levels
Rack Mounting Systems and Clamping Devices for Flat-Plate Photovoltaic
UL 2703
Modules and Panels
UL 3703 Trackers
c) Efficiency:
S. No. Description
i Inverter efficiency 97% or above
Inverter used have built-in tolerance to variation in grid voltages/capable of riding
ii
through voltage sags/tolerance set points configurable to above +/- 5%
iii Over-voltage and Overload protection of inverters
iv THD 2.5% or lesser
15.3. Gas Insulated Switchgear (GIS)
The switchyard of the Complex will be GIS and it will be covered under the project cost. The GIS will be
double bus-bar single breaker scheme comprising four transmission line bays so as to provide 132 kV
double circuit in-out arrangement and remaining bays will be as per plant design.
GIS should comply below mentioned or equivalent Standards and Warranties.
a) Warranty: Standard warranty period is mandatory
b) Standards:
S. No. Description
i GIS complete bay should comply with IEC 62271-203 and IEC 60517 standard
ii Circuit Breaker should comply IEC-62271-100
iii Disconnector & earth switches shall comply IEC 62271-102 01
iv Current Transformers shall comply IEC 61869-2
v Voltage transformers shall comply IEC 61869-3
Routine tests to latest publications of 3
IEC 60233 for hollow porcelains
vi IEC 60137 for bushings
IEC 60168 and 60273 for high voltage post insulators
IEC 60383 and 60305 for cap and pin string insulators
vii Motors shall comply IEC 60034
All outdoor equipment i.e. surge arrestors, line traps, coupling capacitors, capacitive voltage transformers,
line coupling device equipment and etc. shall be provided having adequate rating and as per below given
IEC Standards.
Standards Description
Power transformer selection as per IEC-60076 and IEC 60354 certified for type
IEC 60076/60354
of installation
ISO9001 Transformer supplier is accredited to ISO 9001
IEC 60085 Certified transformers for electrical insulation
IEC 60296 Certified for Oil specification
IEC 60137 Certified for Primary and Secondary Bushings
IEC 60214/ IEC
Certified transformers for tap changers
60542
IEC 61869-1 Instrument transformers - Part 1: General requirements
Instrument transformers - Part 5: Additional requirements for capacitor voltage
IEC 61869-5
transformers
Instrument transformers - Part 3: Additional requirements for inductive voltage
IEC 61869-3
transformers
Surge arresters - Part 4: Metal-oxide surge arresters without gaps for a.c.
IEC 60099-4
systems
IEC 60353 Line traps for a.c. power systems
IEC 60358-1 Coupling capacitors and capacitor dividers - Part 1: General rules
Telco/Tele protection and SCADA system for visibility of the plant in K-Electric's LDC Control room as
per the specs/details provided by K-Electric.
a) Weather station will include the equipment to measure wind speed, tilted irradiance, horizontal
irradiance, ambient temperature, PV panel temperature and etc. panels will be provided which shows
weather conditions at the Project site to collect data and compare remotely with yield figures
b) Alarm Management to flag any element of Power plant that falls outside pre-determined performance
bands via fax/email/text message
d) Provision of Hybrid forecast model where Hybrid Forecast Model means Predictive Tool/Software
prepared and operated by the Forecasting Consultant to generate energy forecast for the Complex
Mounting Systems having tracking system provision should have warranty of 10 years or above for both
movable and non-movable parts., Structures are strong enough to bear wind loads, panel weight and ensure
design operations for the life of the project.
Mounting structure shall also assess the weather conditions to incorporate suitable prevention from
corrosive environment e.g.: galvanized steel, stainless steel, composites or aluminum, specialized coating
such as C5. Pre-cast concrete ballasts/driven piles/earth screws/other type of Mounting systems to be
preferred.
Civil design of Plant must have provision for flood water outlet. Feasibility Study Report will provide
further detailed analysis of flooding at each Site.
Bidder should also consider the topography while designing to cater the shading impact.
b) The developer will be responsible to claim any warranties or replacements that will arise during the life
of the plant
c) The developer will have to ensure operations to maintain availability as per the proposed Capacity
Factor
d) Array inspection and cleaning to maintain the required performance target, inspection of the inverter
and rectification of faults to ensure plant availability.
e) Note: Technical specifications can be updated in light of Feasibility Study Report and subsequent
approval of NEPRA.
15.18. HSE
a) Demonstrate a corporate commitment to safety, proven solutions, safe working practices and culture,
training and supervision.
b) Compliance to KE9s Hazardous Substance Management Procedure as per Document No. KE-SP-017
c) Compliance to Environmental, Health, Safety and Social Clauses for Contractors as per International
Standards
h) Acceptable safety statistics for at least one other Solar Power Project
i) Demonstrate an understanding of the key environmental risks, provide adequate proposals for
monitoring and managing those risks and complying with the environmental requirements of the
Contract.
j) Requirement set out by Balochistan Environmental Protection Agency (BEPA) as outlined in Exhibit
19 will be the responsibility of developer & directives of agency need to be complied.
k) Bidder shall be required to submit information and/or plan on their Environmental & Social
Management System (ESMS) comprised at a minimum of having:
Exclusions
Bidder shall not perform any activity, production, use, distribution, business or trade involving:
1) Forced Labor
2) Child Labor
3) Activities or materials deemed illegal under host country laws or regulations or
international conventions and agreements, or subject to international phase-outs or bans,
such as:
a. ozone depleting substances, PCB's (Polychlorinated Biphenyls) and other specific,
hazardous pharmaceuticals, pesticides/herbicides or chemicals
b. wildlife or products regulated under the Convention on International Trade in
Endangered Species or Wild Fauna and Flora (CITES)
4) Cross-border trade in waste and waste products, unless compliant to the Basel Convention
and the underlying regulations
5) Confirmed cases of occupational, health, and safety incidents or accidents1
6) Confirmed cases of gender-based violence/sexual exploitation and abuse
7) Confirmed cases of discrimination of vulnerable groups, including gender and disability
(checked through media reports, and notification of violations by labor and environmental
authorities)
15.19. Warranty
Standard warranty of all components will be considered while evaluation of bids.
1
The business can be considered if it can demonstrate with reports and documentation that it has been able to
adequately address the issues, and this can be verified.
Volume-III : Tariff Proposal Requirements
16. Quoted Tariff and Commercial Requirements
The tariff shall be consistent with the tariff structure given below. Any Bid which is inconsistent with the
tariff structure shall be rejected.
a) The Bidders shall bid a single Bid Tariff for each Project separately, rounded off to four decimal places
for the Term.
b) The Land Cost shall be accounted for by the Bidder in its Bid Tariff.
c) The Bidders shall attempt to secure SBP Financing at concessionary rates. In case of non-availability,
the Bid shall be based on commercial financing.
d) The indexation applicable to the Bid Tariff as allowed by NEPRA for SBP Financing and commercial
financing shall be in accordance with the mechanism provided in Section 16.1.1 and 16.1.2
respectively.
16.1.1. Indexation mechanism – SBP Financing
Indexation mechanism in case 150 MWp shall be developed as three projects of 50 MWp each with SBP
financing:
AT Awarded Tariff
Rev SOFR quarterly revised Term or Daily SOFR, as the case may be based on GOP
policy decision on the transition from LIBOR to SOFR, as on the last day of
the preceding quarter
ER Rev The revised exchange rate as on the last day of the preceding quarter
ER Rev (one The revised exchange rate is the average of the exchange rates of each day
time) during the maximum construction period of 10 months starting from the date
of Financial Close.
Note: 1st adjustment shall be made for the quarter in which the COD occurs. This adjustment will be
applicable from the COD until the end of that quarter. The subsequent adjustments will be applicable for
the entire quarters.
16.1.2. Indexation mechanism – Commercial Financing
Indexation mechanism in case 150 MW shall be developed as two projects. i.e. one project of 100 MWp
and the other one of 50 MWp with commercial financing:
AT Awarded Tariff
Rev KIBOR Quarterly revised 3-month KIBOR, as on the last day of the preceding
quarter
Rev SOFR quarterly revised Term or Daily SOFR, as the case may be based on GOP
policy decision on the transition from LIBOR to SOFR, as on the last day of
the preceding quarter
ER Rev The revised exchange rate as on the last day of the preceding quarter
ER Rev (one The revised exchange rate is the average of the exchange rates of each day
time) during the maximum construction period of 10 months starting from the date
of Financial Close.
Note: 1st adjustment shall be made for the quarter in which the COD occurs. This adjustment will be
applicable from the COD until the end of that quarter. The subsequent adjustments will be applicable for
the entire quarters.
The actual debt servicing period, financing mix, or any other factor shall not change the structure of the
tariff.
a) All invoicing and payment terms are assumed to be in accordance with the EPA.
b) For the submission of the Bids, the following reference values shall be taken into account by the
Bidders:
Description Values
Reference KIBOR 21.28%
Reference SOFR 5.3671%
Reference Exchange Rate 288.65
16.3. Pass-through Items
Subject to the approval of NEPRA in Determined Tariff, following items shall be considered pass-through:
a) Duties and/or taxes, not being of refundable nature, relating to the construction period directly imposed
on the Successful Bidder up to Commercial Operations Date, will be allowed at actual upon production
of verifiable documentary evidence to the satisfaction of the Authority.
b) In case the Successful Bidder is obligated to pay any tax on its income from generation of electricity
from solar, or any duties, taxes or cess not being of refundable nature, are imposed on the Successful
Bidder, the exact amount paid by the Successful Bidder on these accounts will be reimbursed by KE
on production of original filing documents.
In case of the above scenario, the Successful Bidder shall also submit to KE the details of any tax
savings and KE shall deduct the amount of these savings from its payment to the Successful Bidder on
accounts of taxation. The adjustment for duties and taxes will be restricted only to the extent of duties
and taxes directly imposed on the Successful Bidder. No adjustment for duties and taxes imposed on
third parties such as contractors, suppliers, consultants, etc., will be allowed.
c) Payment into Worker9s Profit Participation Fund and Worker9s Welfare Fund.
d) Withholding tax on dividend will not be a pass-through item.
e) Alternative & Renewable Energy Policy, 2019 (ARE Policy 2019) states certain conditions, fulfillment
of which can result in the exemption of duties on the import of items, being manufactured locally also.
In case any Bidder proposes to import any plant, machinery or equipment that is also manufactured
locally in accordance with the Customs General Order of the FBR, shall be reimbursed to the Successful
Bidder subject to fulfillment of conditions as given in the ARE Policy 2019, for which certification
shall be obtained by the Successful Bidder from AEDB. The Bidder is expected to have knowledge of
applicable laws and regulations and shall not in any case hold KE accountable for information not
provided under this document.
Exhibits
Exhibit 1 – [Not used]
Exhibit 2 – Confidentiality Agreement
(The Applicant/Bidder must execute the Confidentiality Agreement on stamp paper and submit to K-Electric
along with complete Application for Prequalification)
This Confidentiality Agreement (<Agreement=) is made at Karachi on this ____ day of __________, 2019.
By and between
K-Electric LIMITED, a public limited company duly incorporated and existing under the laws of Pakistan
and having its registered office at KE House, 39B, Sunset Boulevard, Phase-II, DHA, Karachi, Pakistan,
(hereafter referred to as <KE or Disclosing Party=).
And
(KE and Company are hereinafter individually referred to as a <Party= and collectively as the <Parties=.)
WHEREAS:
1. KE is in process of obtaining bids for the Development of Solar Projects in the Lasbela District at
2. As part of these discussions, the Parties (either directly or through a representative) have and may
in the future exchange Confidential Information pertaining to the Project.
3. COMPANY and KE wish to enter into this Agreement to safeguard the confidentiality of such
Confidential Information.
NOW THEREFORE, in consideration of the mutual agreements contained herein, the Parties agree as
follows:
1. In this Agreement, unless the context requires otherwise, the following terms shall have the
meaning given below:
<Affiliate(s)= means in relation to a Party, any, corporation, partnership or other legal entity: (i)
that is, directly or indirectly, controlled by such Party; or (ii) that directly or indirectly controls such
Party; or (c) that is, directly or indirectly, controlled by a Party that also, directly or indirectly,
controls such a Party. For the purpose of this definition, a Party is directly controlled by another
Party which owns or controls shares or other interests carrying in the aggregate at least fifty percent
(50%) of the voting rights exercisable at a general or shareholders meeting of the first-mentioned
Party or the right to appoint or dismiss a majority of the directors thereof.
<Confidential Information= means all information (in whatever form, including, but not limited
to, oral, visual, written or electronic, or in any medium or by any method) relating to the Project,
including but not limited to, all manuals, specifications, drawings, letters, telexes and any other
material containing Confidential Information disclosed to the COMPANY by or on behalf of the
KE in writing, in drawing or in any other form or acquired by the COMPANY from the KE
regardless of whether such information was obtained prior to or after the Effective Date.
Confidential Information shall also include all memoranda, reports, valuations, analyses and
summaries of Confidential Information that the Receiving Party or any of its Affiliates derives from
Confidential Information disclosed by the Disclosing Party.
2. Each Party agrees that the Confidential Information received by it shall be kept strictly confidential,
shall only be used in relation to the Project and shall not be sold, traded, published or otherwise
disclosed to anyone in any manner whatsoever, including by means of photocopy or reproduction,
or electronic transmission, without the prior written consent of the Disclosing Party.
Receiving Party further agrees that, unless otherwise expressly permitted in this Agreement, it shall
not disclose, and shall cause its representatives not to disclose (i) the existence or terms and
conditions contained in this Agreement, (ii) the fact that Confidential Information has been made
available to the Receiving Party or its representatives; (iii) the fact that discussions or negotiations
are or were taking place concerning the Project, and (iv) the terms, conditions or other facts with
respect to any such Project, if any, including the status thereof, to any third parties(other than such
third parties who are permitted to receive Confidential Information hereunder) without the prior
written consent of Disclosing Party.
3.1. The Receiving Party may disclose Confidential Information without the Disclosing Party9s prior
written consent only to the extent such information:
(i) was in the lawful possession of the Receiving Party at the time of its receipt and can be
proven by the Receiving Party that it did not had an obligation to keep it confidential;
(ii) was in the public domain at the time of receipt or disclosure or subsequently becomes so
through no fault of the Receiving Party or any person to whom Receiving Party disclosed
Confidential Information;
(iii) is developed by or for the Receiving Party at any time independently of the Confidential
Information disclosed to it, as evidenced by its written records; or
(iv) has been or hereafter is rightfully acquired from third parties who rightfully have
possession of such information without an obligation to keep it confidential.
3.3. The Receiving Party shall not be liable for such inadvertent or unauthorized disclosure if it has used
the same degree of care in safeguarding such Confidential Information as it uses for its own
Confidential Information of like importance.
4. The Receiving Party shall be responsible to Disclosing Party for the compliance of the persons
listed in paragraph 3.1(i) and (iii) to whom the Receiving Party has disclosed Confidential
Information as though such persons and entities were Receiving Party. Prior to any disclosure to
persons listed in paragraph 3.1(iii) Receiving Party shall obtain a written undertaking of
confidentiality from such persons in the same form as this Agreement. The Receiving Party shall
not make any statements and/or issue any press releases concerning the Project without the prior
written consent of the Disclosing Party.
5. Any Confidential Information disclosed by or on behalf of the Disclosing Party shall remain the
property of the Disclosing Party, and the Disclosing Party may demand the return thereof at any
time upon giving written notice to the Receiving Party. The Receiving Party shall not acquire any
right, title, interest or license in Confidential Information it receives pursuant to this Agreement
and no actions pursuant to this Agreement shall be construed as conferring on the Receiving Party
any licence under any patent, copyright or future patent owned by the Disclosing Party, its Affiliates
or any of their shareholders or any other intellectual property right. Within thirty (30) days of
receipt of a request to return Confidential Information, a Receiving Party shall return all original
Confidential Information it has received and destroy, or procure the destruction of, all other
Confidential Information, including any information retained on computer backup system, copies
and reproductions (both written and electronic), in its, its Affiliates and any persons9 to whom it
was disclosed.
6. This Agreement shall terminate on the earlier of the third (3rd) anniversary of the Effective Date or
receipt of written notice of termination. In addition to the obligation to return and/or destroy set
forth in paragraph 5, following termination, the obligations of confidentiality set forth herein shall
continue until the third (3rd) anniversary of the termination date. The provisions of this Agreement
shall however apply retrospectively to any Confidential Information which may have been
disclosed in connection with discussions and negotiations regarding the Project prior to the
Effective Date. Notwithstanding anything else contained herein either Party has the right to
terminate this Agreement at any time by furnishing the other Party with a one (01) month prior
written notice without giving any reason for termination.
7. The Disclosing Party hereby represents and warrants that it has the right and authority to disclose
the Confidential Information to the Receiving Party. The Disclosing Party, by providing such
Confidential Information or otherwise, neither makes nor gives any representation, warranty or
undertaking, express or implied, concerning the quality, reliability, accuracy, completeness or
reasonableness of the Confidential Information. The Receiving Party shall use any Confidential
Information at its own risk and the Disclosing Party shall have no liability to the Receiving Party
resulting from the Receiving Party9s use of such Confidential Information. Nothing contained
herein shall be construed as requiring the Disclosing Party to enter into any business dealings, to
negotiate in good faith, or to hold or to continue discussions concerning the Project with the
Receiving Party. Neither this Agreement nor any actions of the Parties shall constitute or be
construed to constitute a partnership, joint venture or any other cooperative relationship between
the Parties. The obligations and liabilities of the Parties to this Agreement are several, not joint, or
joint and several.
8. The liability of the Parties to each other for breach of this Agreement shall be limited to actual
direct and foreseeable damages. In no event shall the Parties be liable to each other for any other
damages, including loss of profits or business interruptions, or indirect, incidental, consequential,
special, exemplary or punitive damages, decline in market capitalisation, however caused,
regardless of negligence or fault. Receiving Party acknowledges and agrees that Disclosing Party
may be irreparably harmed by the breach of this Agreement and damages may not be an adequate
remedy. Disclosing Party shall be entitled to seek an injunction or specific performance for any
threatened or actual breach of this Agreement by Receiving Party or any other person receiving
Confidential Information pursuant to this Agreement. In addition to the above, the Disclosing Party
may in its sole discretion pursue any and all other remedies available to it for such violation, breach
or threatened breach including recovery of compensatory damages.
9. This Agreement shall be governed by and construed in accordance with the laws of Islamic republic
of Pakistan. All claims, demands, causes of action, disputes, controversies and other matters in
question (<Dispute=) arising out of, relating to, or in connection with this Agreement, including any
question regarding its existence, breach, validity, or termination, which cannot be amicably
resolved by the Parties, shall be settled before a two (02) arbitrators appointed mutually by both
the Parties and one (01) umpire appointed mutually by the two (02) arbitrators. For purposes of
clarity, the arbitrators and the umpire shall be retired confirmed judges of the High Court of Sindh
at Karachi. Such arbitration shall be held in accordance with the provisions of the Arbitration Act,
1940. The venue of such arbitration shall be Karachi, Pakistan and the language of arbitration
proceedings shall be English in effect as of the Effective Date. Judgment upon such award may be
entered in any court having jurisdiction thereof. A dispute shall be deemed to have arisen when
either Party notifies the other Party in writing to that effect. Receiving Party acknowledges that
remedies at law may be inadequate to protect against breach of this Agreement; accordingly, the
arbitrator may award both monetary and equitable relief, including injunctive relief and specific
performance. The Disclosing Party may apply to any competent judicial authority for interim or
conservatory relief; an application for such measures or an application for the enforcement of such
measures ordered by the arbitrator shall not be deemed an infringement or waiver of the agreement
to arbitrate and shall not affect the powers of the arbitrator.
10. This Agreement shall constitute the entire agreement between the Parties with respect to the subject
matter hereof and neither Party shall have any obligation, express or implied by law, with respect
to trade secret or proprietary information of the other Party except as set forth herein. This
Agreement may not be modified or amended except in writing and signed by a duly authorized
representative of each of the Parties. No failure or delay in exercising or any single or partial
exercise, of any right, power or privilege under this Agreement shall operate as a waiver or preclude
any further exercise of any right, power or privilege under this Agreement or otherwise. If any
provision of this Agreement (or part thereof) is or becomes unlawful, invalid or void, the legality,
validity, and enforceability of any other part of that provision or any other provision of this
Agreement shall not be affected but shall continue in full force and effect. The unlawful, invalid or
void provision shall be deleted from this Agreement but only to the extent of the invalidity so as to
preserve this Agreement to the maximum extent possible.
11. All notices and other communications given under this Agreement shall be in writing in the English
language and shall be deemed to have been properly given or made if: (a) personally handed to an
authorized representative of the Party for which intended; (b) sent by postage prepaid, registered
(return receipt requested) mail (airmail if international); (c) transmitted by facsimile with
confirmation of receipt; or (d) transmitted by email (such notice by email shall be contained in an
attachment and not in the body of the email); in each case at or to the address of the Party for which
intended, as indicated below, or other address as may be designated by notice given in accordance
with this paragraph:
Attention: [name]
Telephone: [number] [Attention:
Facsimile: [number] Syed Muhammad Shan Ali
Deputy Manager 3 Business
Email:[[email protected]] Development
K - Electric Limited
BOC Building, 1st Floor, KE House
39-B Sunset Boulevard
Phase II, DHA, Karachi
Pakistan
Notices and other communications given in accordance with this paragraph 11 shall be effective
(a) on receipt by the addressee if personally delivered or transmitted by mail, and (b) on
transmission to the addressee if transmitted by facsimile (with the correct recipient confirmation)
or by email during normal business hours at the place of the addressee or, if so transmitted outside
such hours, at the opening of business on the next business day at such place.
12. This Agreement may be executed in two (02) counterparts and each of which shall be deemed an
original, with the same effect as if the signatures on the counterparts were upon a single
engrossment of this Agreement provided that this Agreement shall not be effective until all the
counterparts have been executed.
IN WITNESS THEREOF, the Parties have caused this Agreement to be signed by their duly authorized
representatives.
The Bidder/Applicant must promptly execute the Covenant of Integrity on its corporate letterhead. The
executed Covenant of Integrity must be submitted to K-Electric.
3.2. Template
[Date]
Attention:
K - Electric Limited
BOC Building, 1st Floor, KE House
39-B Sunset Boulevard
Phase II, DHA, Karachi
Pakistan
Dear Recipient,
The Bidder/Applicant hereby undertakes that the Bid was not concluded under the influence of any
agreement, decision or conduct which influences an open and fair competition negatively. In addition, the
Bidder/Applicant hereby warrants and covenants that neither it, nor its affiliates or representatives has
made, offered, promised, requested, solicited or accepted or authorised regarding the Bid, nor will make,
offer, promise, request, solicit or accept or authorise regarding the matters that are the subject of the Bid,
any payment or any transfer of anything of value, including without limitation any gift, service or
entertainment, or other advantage, or a so-called facilitation payment, whether directly or indirectly, to or
for the use or benefit of:
(i) any public official including without limitation any person holding a legislative, administrative,
or judicial office, including any person employed by or acting for a public agency, or public
international organization or providing a public service;
(ii) any director, officer or employee of a government owned or controlled company or any company
or enterprise in which government owns an interest;
(iii) any political party or political party official or candidate for office;
(iv) any director, officer or employee of any other party or any of their respective affiliates;
(B) would violate the laws of the country of formation of it or its ultimate parent company,
the country where it or its ultimate parent company9s shares are listed, or the countries
where it or its ultimate parent company carry on business; or
(1) influencing the individual receiving such payment, gift, service, entertainment or
advantage to act or refrain from acting in the exercise of his or her official duties;
(2) seeking with a view to obtaining from such individual any undue advantage; or
(3) inducing such individual to act or refrain from acting in the exercise of his or her
official duties in order to obtain or retain business or other undue advantage in
relation to the bid,
In the case of breach of any of the above warranties and/or covenants, without prejudice to any other right
and remedy provided by law, equity or by contract, the Bidder shall indemnify and hold K-Electric
harmless from and against all claims, damages, losses, expenses, fines or any third-party liability claims
(excluding any consequential losses) arising out of or in connection with such breach.
Title: ______________________________
Date: ______________________________
Signature: ______________________________
Exhibit 4 – Power of Attorney
(The Bidder must execute the Power of Attorney on stamp paper and submit to K-Electric along with the
Bid)
POWER OF ATTORNEY
TO ALL WHOM PRESENT, these presents shall come. _________________, having its registered office
at _____________________________________________________ (hereinafter called the <Company=)
send greetings.
WHEREAS, by virtue of the powers conferred upon them by Article ___ of the Company9s Articles of
Association, the Board of Directors of the Company have passed the resolution dated _________ and
entrusted to and conferred upon __________________________, the ________________ of the Company.
The following powers which shall be exercisable by him from the date that a power of Attorney
enumerating the same is executed in his favor by _______________.
1. To sign the application and its ancillary documents on behalf of the Company with respect to the
bidding process for the Project(s) as specified in the Request for Proposal.
2. The Company hereby agrees to ratify and confirm all and whatever the said Attorney shall lawfully
do or cause to be done by virtue of this Power of Attorney.
3. This Power of Attorney, unless earlier revoked, shall be valid until the completion of execution of
bidding process and shall stand immediately revoked upon the execution of the Letter of Intent.
IN WITNESS WHEREOF the Common Seal of the Company has been affixed hereto at _________ on this
__________ by the undersigned _____________ of the Company pursuant to the resolution dated
____________ passed by the Board of Directors of the Company.
Signature of Attorney
__________________________
__________________________ _________________________
Director Director
WITNESSES:
1. _________________________ 2. ____________________
____________________ ____________________
________________________ _ _________________________
____________________ ____________________
____________________ ____________________
Exhibit 5 – Affidavit
(The Bidder must execute the Affidavit on stamp paper and submit to K-Electric along with complete Bid)
AFFIDAVIT
1. That I am the deponent of this affidavit and fully conversant with the facts stated herein and nothing
has been concealed or mis-declared.
2. That the Applicant/Bidder has applied to bid for the Project(s) of K-Electric Limited (<Relevant
Agent=).
3. That the country of origin of Applicant/Bidder is not any country upon which the government of
Pakistan has imposed any trade embargo and/or sanctions, including but not limited to Israel and India.
4. That the Applicant/Bidder and its members, representatives, personnel9s etc. do not have any
restrictions with respect to travel in Pakistan.
5. That the Applicant/Bidder does not have a conflict of interest with any of the parties involved in the
bidding process of the Relevant Agent and further the Deponent hereby agrees that if the Deponent is
found to be in conflict of interest with one or more parties involved in the bidding process, at any time,
the Relevant Agent shall have the right to disqualify the Bidder.
b) a relationship with each other, directly or through common third parties, that puts the
Applicant/Bidder in a position to have access to material information about or improperly
influence the proposal of any other Applicant/Bidder involved in the bidding process or influence
the decisions of the Relevant Agent regarding the bidding process.
7. That the information and the assumptions provided by the Applicant/Bidder are correct and complete
and no material information is concealed by the Applicant/Bidder in its Bid including any supporting
documents;
8. The Bidder, if declared the Successful Bidder, will execute the project unconditionally;
9. That the Applicant/Bidder and its members (in case of the Applicant/Bidder being a consortium/joint
venture) have not defaulted in their payment obligations and/or performance of major contracts over
the past five years.
10. The Applicant/Bidder or any officer, director or owner thereof, has not been in substantial
noncompliance of the terms and conditions of prior project contracts.
11. That the Applicant/Bidder and its members (if any) are solvent and have no liquidation application
pending against them in any court of law.
12. That the information provided by the Applicant/Bidder, on any litigation or arbitration resulting from
contracts completed or under execution over the last five years is accurate and will not adversely affect
the Relevant Agent in any way whatsoever. That the Applicant/Bidder understands that a consistent
history of award against the Applicant/Bidder may result in rejection of the Bid of the Bidder by the
Relevant Agent.
13. That the Applicant/Bidder and its members (in case of the Applicant/Bidder being a consortium/joint
venture) have been compliant of the prevailing regulations over the past five years. The composition
or the constitution of the consortium shall not be altered without the prior consent of the KE.
14. That the Applicant/Bidder and its members (in case of the Applicant/Bidder being consortium/ joint
venture) confirms that all of the parties shall be jointly and severally liable to the KE till the
Commercial Operation Date of the Project(s).
15. The Applicant/Bidder, its owners, directors, and key employees, have not been prosecuted, blacklisted
or barred during the past five years by the Relevant Agent, KE or any federal or provincial agency or
any international DFI and are not subject to any international sanctions;
16. The Applicant/Bidder should affirm that it has not been the cause of any serious health, safety, or
environment hazard in any of its projects in Pakistan or any other place in the world over the past five
years.
17. That the Applicant/Bidder shall submit his statement on separate affidavit, in case the
Applicant/Bidder is claiming no previous or ongoing litigation.
18. The Applicant/Bidder hereby agrees if any provision of this RFP document is, against the Law of
Pakistan the remaining provisions of this RFP document shall remain in full force and effect.
19. The Bidder shall confirm that there has been no material change in records provided at the time of
prequalification. In case of any material change, the Bidder shall submit a separate statement of
changes along with the relevant supporting documents.
20. The Applicant/Bidder has the relevant technical and commercial expertise to successfully undertake
the Project(s).
Whatever stated above is true and correct to the best of my knowledge and belief.
DEPONENT
Signature: _________________
Name: _________________
Dated: _________________
Exhibit 6 – Letter of Acceptance by the Applicant/Bidder
The Applicant/Bidder accept the following in order to proceed with bid evaluation:
1- Applicant/Bidder has accepted all 8terms and conditions’ specified in the RFP.
2- Applicant/Bidder accepts all the terms and conditions mentioned in the 8Energy Purchase
Agreement’ as provided in Exhibit 11 of RFP.
3- The Applicant/Bidder confirms the timelines stipulated in Section 8.1 of the RFP document. Any
change to the project timeline will be communicated by the Relevant Agent to the Successful
Bidder at the time of LOI issuance.
4- The Applicant/Bidder accepts the Land Cost provided in the RFP Document to include in the Bid
Tariff.
5- The Bid complies with all the recommendations provided in the Feasibility Study Report given
with RFP.
Exhibit 7 – Bid Evaluation Criteria
Given below are the technical specifications relevant to technology and energy yield of the solar power
plant, non-compliance to which shall result in disqualification of the Bidder.
Knock-Off Criteria:
Detailed Technical Scorecard is given below according to which, minimum criteria for qualification of
Bidder is 75 out of 100 marks after passing the screening criteria provided in the table above.
(b) The lowest Bid Tariff of a technically compliant Bid, in accordance with Section 11, will be selected
as the Successful Bidder.
Exhibit 8 – Form of Bid Bond
K - Electric Limited
BOC Building, 1st Floor, KE House
39-B Sunset Boulevard
Phase II, DHA, Karachi
Pakistan
KNOW ALL MEN BY THESE PRESENTS, that in pursuance of the terms of the Bid and at the request of
the said Principal, we the Guarantor above-named are held and firmly bound unto the K-Electric Limited
(hereinafter called The <Company=) in the sum stated above, for the payment of which sum well and truly
to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally,
firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that whereas the Principal has submitted the
accompanying Bid numbered dated as above for [the Development of [●] MW Solar Project in the Lasbela
District].
WHEREAS, the Company has required as a condition for considering said Bid that the Principal furnish a
Bid Bond in the above said sum to the Company, conditioned as under:
(1) That the Bid Bond shall remain valid for a period of twelve (12) months from the bid submission
deadline.
(2) That in the event of:
a) The Principal/ Applicant/Bidder withdraws his Bid during the period of validity of Bid, or
b) Failure of the Successful Bidder to furnish the required Performance Guarantee, in accordance
with Request for Proposal,
Then the entire sum be paid immediately to the said Company as liquidated damages and not as penalty for
the successful Bidder's failure to perform.
NOW THEREFORE, if the Successful Bidder shall, within the period specified therefore, on the prescribed
form presented to him for signature enter into a Letter of Intent with the said Company in accordance with
his Bid as accepted and furnish within twenty (20) days of his being requested to do so, a Performance
Guarantee with good and sufficient surety, as may be required, upon the form prescribed by the said
Company for the faithful performance and proper fulfilment of the said Letter of Intent or in the event of
non-withdrawal of the said Bid within the time specified then this obligation shall be void and of no effect,
but otherwise to remain in full force and effect.
PROVIDED THAT the Guarantor shall forthwith pay to the Company the said sum stated above upon first
written demand of the Company without cavil or argument and without requiring the Company to prove or
to show grounds or reasons for such demand, notice of which shall be sent by the Company to the Guarantor
at its address given above.
PROVIDED ALSO THAT the Company shall be the sole and final judge for deciding whether the Principal
has duly performed his obligations to sign the Letter of Intent and to furnish the requisite Performance
Guarantee within the time stated above, or has defaulted in fulfilling said requirements and the Guarantor
shall pay without objection the sum stated above upon first written demand from the Company forthwith
and without any reference to the Principal or any other person.
IN WITNESS WHEREOF, the above bounden Guarantor has executed the instrument under its seal on the
date indicated above, the name and seal of the Guarantor being hereto affixed and these presents duly signed
by its undersigned representative pursuant to authority of its governing body.
Guarantor (Bank)
Signature: ___________________________
Witness:
1. ____________________________ Name: ______________________________
____________________________ ______________________________
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ____________________________
Name, Title & Address (Seal)
SUB: DEMAND FOR PAYMENT ON BID BOND
In accordance with the terms and conditions of your Guarantee bearing No. _________ dated [DATE
GUARANTEE EXECUTED] amounting to _____________, issued by your Bank on behalf of
_______________ [DEBTOR] (enclosed).
Demand is hereby made for payment in full/partial of (amount), which payment must be received by us
through a cashier's check, immediately, at the following address:
[COMPANY]
[ADDRESS]
If you have any questions, call the undersigned immediately at [UNDERSIGNED9S TELEPHONE
NUMBER].
Sincerely.
Exhibit 9 – Form of Performance Guarantee
PERFORMANCE SECURITY
K - Electric Limited
BOC Building, 1st Floor, KE House
39-B Sunset Boulevard
Phase II, DHA, Karachi
Pakistan
Amount of Guarantee:
____________________________________________________
(Express in words & figures)
RFP Date: ____________________________________________________
KNOW ALL MEN BY THESE PRESENTS, that in pursuance of the terms of the RFP (hereinafter called
the Documents) and at the request of the said Bidder being our Client, we, the Guarantor above named
hereby irrevocably and unconditionally bind ourselves to K Electric (hereinafter called the Company)
in the sum of [●] for the payment of which sum well and truly to be made to the said Company to pay the
Company on its first demand in writing without raising any cavil or objection whatsoever.
We understand that the Bidder has been notified dated _______________ by the Company as the Successful
Bidder for the development of [●] MW Solar Power Project at [/Bela/Winder] in the Lasbela District of
Balochistan.
WHEREAS:
A. The Bidder has been declared as the Successful Bidder by the Company to set up the solar power plant
at [location] in accordance with the terms of the Request for Proposal.
B. As required by the Beneficiary prior to the issuance of the Letter of Intent (the <LOI=) to the Successful
Bidder, and in consideration thereof, the Guarantor, at the request and on behalf of the Successful
Bidder, hereby furnishes this irrevocable, unconditional, without recourse, on demand bank guarantee
(hereinafter referred to as the <Performance Guarantee=) in favor of the Beneficiary in order to secure
the performance of the Successful Bidder9s obligations under the LOI.
We, the Guarantor do hereby irrevocably and unconditionally guarantee to pay to the Company
immediately without any delay upon the Company's first written demand without cavil or arguments and
without requiring the Company to prove or to show grounds or reasons for such demands any sum or sums
up to the amount stated above without reference to the Bidder or any other third party. Any demand by the
Company shall be final and conclusive for all the purposes whatsoever. For the avoidance of doubt, time
shall be of the essence of this Guarantee and the liability of the Guarantor shall be valid until expiry date
continuing and co-extensive with that of the Bidder and shall be valid up to (Date) and shall not be
diminished by any partial claim or demand made on the Guarantor under this Guarantee by the Company.
This Guarantee shall be solely governed and construed by the substantive and procedural laws of the Islamic
Republic of Pakistan.
This guarantee shall come into force at once and be valid for a continuous period of thirteen (13) months
ending on [expiry date]. Any demand by the Company should reach the Guarantor before (time and date).
IN WITNESS WHEREOF, the above-bounden Guarantor has executed this instrument under its seal on the
date indicated above, the name and corporate seal of the Guarantor being hereto affixed and these presents
duly signed by its undersigned representative, pursuant to authority of its governing body.
Notwithstanding anything herein above this guarantee is [●] (in words) valid until [●] after which date the
guarantee will become null and void irrespective of whether or not the original guarantee is returned to the
bank for cancellation. Any claim made under this guarantee must be in writing and delivered to the bank9s
office at [●] on or before (time and date) after which we will no longer be liable to make payment to you.
____________________
Guarantor (Bank)
Signature: ___________________________
Witness:
1. ____________________________ Name: ______________________________
____________________________ Title: ______________________________
____________________________ ______________________________
Corporate Secretary (Seal) Corporate Guarantor (Seal)
2. ____________________________
Name, Title & Address (Seal)
SUB: DEMAND FOR PAYMENT ON PERFORMANCE GUARANTEE
(<Guarantee=)
In accordance with the terms and conditions of your Guarantee bearing No. _________ dated [DATE
GUARANTEE EXECUTED] amounting to _____________, issued by your Bank on behalf of
_______________ [DEBTOR] (enclosed).
Demand is hereby made for payment in full/partial of (amount), which payment must be received by us
through a cashier's check, immediately, at the following address:
[COMPANY]
[ADDRESS]
If you have any questions, call the undersigned immediately at [UNDERSIGNED9S TELEPHONE
NUMBER].
Sincerely.
Exhibit 10 – Bid Tariff
Bidders are required to submit separate Exhibit 10 for each Project if the Bidder is bidding for more than
one Project.
Part A – Winder
(the document is a separate attachment to this RFP document)
Part B – Bela 1
(the document is a separate attachment to this RFP document)
Part C – Bela 2
This Letter of Intent (LOI) is executed in Karachi on ________________ (<Effective Date=) between:
1 K-ELECTRIC LIMITED, being a public limited company duly incorporated and existing under
the laws of Pakistan and having its registered office at KE House, 39-B, Sunset Boulevard, Phase-
II, DHA, Karachi, Pakistan (hereinafter referred to as <KE=), which expression shall include
wherever the context permits its successors-in-interest and assigns, of the First Part; and
2 Successful Bidder, (company details) which expression shall include wherever the context
permits its successors-in-interest and permitted assigns, of the Second Part;
Each of KE and Successful bidder are individually referred to in this LOI as a <Party= and collectively as
the <Parties=.
Whereas:
A. The Successful Bidder will be awarded the LOI for formation of 8SPV9.
B. The SPV will be responsible to develop, construct, own and operate the [50/100] MWp Independent
Power Plant (<IPP=) based on solar photovoltaic modules, to be located in [●] as mutually agreed
between the Parties (<the Project=), in accordance with the milestones specified in this LOI for the
Project.
C. Subsequent to the formation of SPV, the SPV will be required to (i) obtain Generation License and
Tariff Approval from NEPRA (ii) enter into EPC contract for the design, construction and
commissioning of the Complex (iii) enter into EPA with KE, and other necessary Project agreements
(iv) arrange the necessary financing for the Project(s) and achieve financial close (v) construct and
implement the Project within the time period allowed by NEPRA in the Tariff Approval, and (vi) upon
commissioning, operate and maintain the Complex for the Term to provide the generated electricity to
KE.
D. SPV shall be duly licensed by National Electric Power Regulatory Authority (<NEPRA=) under the
Regulation of Generation, Transmission and Distribution Act, 1997 (<NEPRA Act=) and the Securities
and Exchange Commission of Pakistan (<SECP=) to undertake this Project.
E. SPV shall develop the Project under the build-own-operate (<BOO=) scheme with the Project life of
not less than 25 years post Commercial Operations Date (<CoD=) and
F. KE and SPV will enter into Energy Purchase Agreement (<EPA=) in accordance with the Exhibit 11
of RFP.
Now, therefore, in consideration of the mutual promises and covenants of the Parties set forth in this LOI,
this LOI as provided under:
1. THE PROJECT
1.1. For the purposes of this LOI, Successful Bidder and/or any of its sponsors and/or its affiliates together
with any other individual or group or entity nominated by and duly accepted by KE, shall be the
Main Sponsor(s) of the Project. It is anticipated that KE will execute a mutually acceptable Energy
Purchase Agreement with SPV for the term agreed under the Energy Purchase Agreement. For the
purposes of this LOI irrespective of any other Sponsor being added to the Project in the future, SPV
or its designated affiliate shall remain as the developer for the Project for all intents and purposes
and in its dealings with KE. The equity shareholding of the Lead Member of the Successful Bidder9s
(in case Successful Bidder is a consortium/joint venture) shall be higher of minimum 20% or greater
than the equity shareholding of other members of the consortium/joint venture and shall maintain
such shareholding for the term of the loan; any change prior thereto shall require approval of KE
which shall not be unreasonably withheld.
1.2. SPV shall make all reasonable efforts to facilitate each other9s internal approvals through mutual
cooperation between the Parties in good faith.
1.3. SPV shall be responsible for raising financing for the Project.
1.4. Land will be transferred to SPV at or prior to the Financial Close in accordance with the Land Lease
Agreement to be entered between the SPV and GoB.
1.5. KE shall ensure the Project could be connected to its grid network. The cost and arrangement of
interconnection up to the interconnection point to be situated at the Project site would be borne by
KE.
1.6. Sponsors of the SPV shall take all the risks and liabilities of development of the Project and shall
contribute the finances, expertise and overall business development in respect of the Project. SPV
shall carry out all the project development activities, as listed in table 1.
1.7. SPV shall comply with all the regulations, which include warranties related to the performance of
such plants in line with standards applied for new IPPs under Energy Purchase Agreement (EPA)
and/or the applicable laws and regulations of the Islamic Republic of Pakistan. In addition, SPV shall
be responsible for obtaining license/authorization from NEPRA under the NEPRA Act as well as
ensuring that all relevant performance standards of NEPRA for the grant of any generation license
in favor of SPV are duly complied with.
1.8. The Parties agree that SPV shall file tariff application with NEPRA and Tariff Approval shall be
used for the purposes of the EPA.
1.9. The SPV will be required to construct the Project consistent with the technical specifications,
equipment details and design parameters that are consistent with the Technical Proposal of the
Successful Bidder received pursuant to this RFP and agreed with K-Electric in the EPA with the
approval of NEPRA. Any variations to above that are determined to be material by K-Electric, shall
result in revocation of the LOI by K-Electric and encashment of Performance Guarantee provided
that K-Electric shall notify in writing to the Successful Bidder of such material deviations and allow
ten (10) Business Days for rectification of such material deviations.
1.10. The Parties agree to complete the milestones listed in Table 1 during the term of this LOI. In the
event that, from the Effective Date of this LOI, any of these milestones has not been accomplished
by SPV within the term of this LOI, KE shall have the right to terminate this LOI and encash the
Performance Guarantee, unless otherwise agreed between the Parties.
1.11. This LOI shall become effective as of the Effective Date and shall remain in force until the earlier of
any one of the events occurring as follows:
(a) Expiry of the term of this LOI, which is 12 continuous Gregorian calendar months from
the Effective Date, without renewal in writing between Parties; or
(c) Termination of this LOI by KE under clause 2.9 or by giving (60) days prior written notice
to the other Party without assigning any reason.
1.11.1. The non-disclosure and non-circumvention requirements and obligations as provided herein will
survive termination or expiry of this LOI and continue for two (2) years thereafter.
1.12. Notwithstanding anything in this LOI, KE shall have the right to encash the Performance Guarantee
to its full outstanding value in case of any breach of the terms and conditions hereof.
1.13. SPV shall regularly update KE on the progress of the Project at monthly intervals. The scope of the
progress report shall include both technical and commercial areas which shall be presented by SPV
to KE9s designated team. Without prejudice to the foregoing, KE shall at times be entitled to demand
and receive from time-to-time specific information/reports/data on the progress of the Project and/or
achievement of milestones.
2. CONFIDENTIAL INFORMATION
2.1. For the purposes of this LOI, "Confidential Information" shall mean any information, knowledge
or data relating to the subject matter of this LOI which is not in the public domain and is disclosed
by the disclosing party to the receiving party and is other than intellectual property of the disclosing
party. All Confidential Information shared by the disclosing party to the receiving party shall
remain the exclusive property of the disclosing party and the receiving party shall not disclose the
same to any other person or entity not being a signatory to this LOI unless:-
(a) the said information/data is already in the public domain;
(b) such disclosure is required by the order of the competent authority or judicial forum
subject to prior intimation to the disclosing party.
2.2. No Party shall issue or make any public announcement or disclose any information regarding this
LOI and its objects unless prior to such public announcement or disclosure it furnishes the other
Party with a copy of such announcement or information and obtains the approval of the other Party
to its terms. However, no Party shall be prohibited from issuing or making any such public
announcement or disclosing such information if it is necessary to do so to comply with any
applicable laws or regulations including but not limited to the listing regulations of the Karachi
Stock Exchange.
2.3. Neither Party may assign, novate, substitute, sub-delegate, sub-contract or otherwise transfer any
or all of its rights and obligations under this LOI, whether in whole or in part, without prior specific
written consent of the other Party.
2.4. This LOI may not be released, discharged, supplemented, interpreted, amended, varied or modified
in any manner except by an instrument in writing signed by duly authorized representatives of both
the Parties to this LOI.
2.5. The validity, construction and implementation of this LOI shall be solely governed by the
substantive and procedural laws of the Islamic Republic of Pakistan. Any disputes or claims arising
under or in connection with this LOI shall be subject to the exclusive civil jurisdiction of the High
Court of Sindh at Karachi to which the Parties to this LOI hereby irrevocably submit.
2.6. Neither of the Parties shall be liable to the other Party in contract, tort, negligence, breach of
statutory duty, trust or otherwise for any indirect, direct and/or consequential losses or damages of
whatsoever nature for any breach of the provisions of this LOI whether intentional or otherwise. In
no way shall either Party be liable to the other for any loss of profits or loss of business opportunities
for any delay or non-achievement of the milestones set out in this LOI whether under the provisions
of the law of contract, tort, trust or any other theory of law.
3. Each Party warrants to the other that the person(s) signing below have all necessary capacity and
authority, corporate or otherwise, to enter into, execute and implement this LOI in good faith on
behalf of the Parties to this LOI.
4. This LOI is signed in two identical counterparts, each of which shall constitute one indivisible
instrument.
5. All notices and other communications required under this LOI shall be given in writing, through
personal delivery, courier mail or by facsimile transmission and shall be addressed to the following:
KE:
Attention: [●]
Designation: [●]
Address: KE House, 39-B, Sunset Boulevard, Phase II, DHA, Karachi
SPV:
Attention: [Name]
Designation: Chief Executive Officer
Address:
5.1. Any notices sent under Clause 6(a) above shall be deemed to be duly received where sent during
normal business hours by personal delivery or facsimile transmission on the same business day as
it was sent, and where sent by courier within three (3) business days of dispatch.
6. The provisions of this LOI are severable in nature and in the event that any one or more of its
provisions are incapable of being implemented for any reason, this shall not affect the validity of
the remaining provisions of this LOI and the Parties shall in good faith enter into negotiations to
come up with an alternative provision which best reflects the understanding and mutual intention
of the Parties at the time of entering into this LOI.
7. Notwithstanding anything to the contrary contained herein, this LOI shall be legally binding on
both the Parties.
8. Neither Party makes any representations or warranties to the other Party under this LOI and each
Party shall be responsible for conducting its own due diligence with regard to the subject matter of
this LOI. Accordingly, each Party shall be strictly responsible for its own costs.
9. For the avoidance of doubt, time shall be of the essence of this LOI for Parties.
10. This LOI is personal in nature and does not create any third-party rights or interests in favor of any
person or entity who is not a signatory to this LOI.
In witness thereof, the Parties hereby put their respective signatures on the date and year first above written.
________________________ ________________________
[Name] [Name]
Chief Strategy Officer Chief Executive Officer
Exhibit 14 – Financing Structure and Equity Commitment from Sponsors
Applicants/Bidders shall provide evidence of available funding mechanism including signed equity
commitment from sponsors.
In addition, the Applicant/Bidder is required to submit its financing structure and in case SBP financing is
not available the Applicant/Bidder is required to share requisite evidence in this regard.
Exhibit 15 – Prequalification Document
(the document is a separate attachment to this RFP document)
Exhibit 16 – Waste Management Procedure
(the document is a separate attachment to this RFP document)
Exhibit 17 – Hazard Substance Management Procedure
(the document is a separate attachment to this RFP document)
Exhibit 18 – Safety Signs and Barricade Guidelines
(the document is a separate attachment to this RFP document)
Exhibit 19 – NOC from Balochistan Environmental Protection Agency
Part A – Winder
(the document is a separate attachment to this RFP document)
Part B – Bela
(the document is a separate attachment to this RFP document)