Contractor internal Minutes of Meeting for communication and project progress # 11
Contractor internal Minutes of Meeting for communication and project progress # 11
MINUTES OF MEETING
PROJECT & MEETING INFORMATION
MEETING
DATE TIME MEETING NO. REV. NUMBER WEEK NO.
LOCATION
26.10.2024 10:00 Am PS10 ABC-USF-MOM-11 0 56
CONTRACT EFFECTIVE CONTRACT CONTRACT
BUDGET ITEMS PROJECT NAME DURATION
NO. CONTRACT DATE END DATE
UPGRADE SECURITY
BI-10-00449-0004 FACILITIES EAST WEST PUMP 6601000190 09-Mar-2023 26-Feb-2025 720 Days
STATIONS (Package 3)
ATTENDENCE
ABC ABC
Attend Attend
S/N NAME DESIGNATION the S/N NAME DESIGNATION the
meeting meeting
1 Amr Mohamed Gaber Project Director N 17 Majed Ahmed Alqulayti Lead Planner Y
Mohsen Abdelhalim
2 Project Manger Y 18 Abdel Rehman Aref Cons/Sup PS PRS1&PS-11 Y
Elhelali
3 Khalil Ur Rehman QA Manager N 19 Ahmed Al- Sayed Cons/Sup PS-8&PS-9 Y
Ahmad Hassan
4 Construction Manager Y 20 Mohamed Goda Cons/Sup PS PRS1&Y/R N
Mohamed
5 Ibral Majid Bhat Engineering Manager Y 21 Roshdy Magdy Mech Engineer Y
6 Muhammad Imran Khan Safety Manager N 22 Shahid Iqbal Safety Supervisor Y
Muhammad Talha
7 QC Manager Y 23 Muhammad Shahid Document Controller Y
Kaleem
8 Attaullah Jilani PQCS N 24 Sayyed Quammer QCS Civil N
9 Mohammed Zaki Procurement Manager N 25 Waqas Ahmed Safety Supervisor N
10 Mohammed Azam Lead procurement expeditor N
11 Ahmed Khairy Procurement Engineer Y
12 Bassem Ahmed Project Engineer Y
13 Atef Omara Lead Electrical Eng Y
19-Aug-24
1.1 Safety officers shall report TUV expiry details on daily basis. Inf0 HSE manager
1.2 Lead engineers will notify about any new and high-risk activity to safety department Info Lead Eng 19-Aug-24
1.3 New safety officers did not received offer letters. Required to transfer sponsorship. Open HR
1.4 Excavation Plan is required for all excavations deeper than 2.4 m Open Lead Eng.
All the JSA has been approved from LPD. (PS-8,9 & 11 Received and for other stations, JSAs
1.6 submitted to operation Forman for signature)
Info
1.7 Concrete Pump operator was found without valid driving License at PS-9 Info
23-Oct-24
Advise Equipment coordinator to check the tiers of all vehicles and submit complete Equip.
1.8 Open
report. Coordinator
1.9 Third party required for 2 WPRs as their cards will expire in January 2025. Open PM
1.10 SAPMT Advise ABC to complete requirements as per PMT safety MOM Open 02/11/202
1|11
CONTRACTOR INTERNAL PROGRESS REVIEW & PLANNING MEETING
MINUTES OF MEETING
4
Quality team informed that kick off meeting shall be conducted prior to start any new activity.
2.1 The quality team will share the list of all activities that required certification / kick of meeting. Info Closed
Already shared the list.
The procurement team must submit all required QC documents along with internal RFI to the
assigned person Mr. Waqar Afzal for materials receiving inspection.
2.3 The procurement team was advised to avoid short names of material. Material name shall be in Open QC/Proc. 19.Oct.24
details with quantity received at site.
QC Manager informed that enough time shall be given to QC inspector for next day RFI.
2.4 Construction Team shall inform Q.C before 3 days for raising RFI and make shore the redline Info Cons/Team
drawing must be approved.
2.5 Construction team shall secure certifications of fire rated sealant installer Open CM/Proc.M 22.Oct.24
Aug-31-24
Al Naheem batching plant CRM needs to be issued on Monday.
2.7 CRM was issued on August 29, 2024. PM advised to expedite the approval from SAPMT.
Open QA/QC/PM 26-Sep-24
26.Oct.24
2.10 Attached the list of delivered but non-inspected materials. Open QC Ongoing
The construction team was advised to share all activity with QC prior to start and get
2.11 Info Const Ongoing
guidance from the quality team to avoid rejection/rework.
The construction team was advised that any changes to the drawings would be made Engineering /
2.12 Info Const
Ongoing
in accordance with approved field change procedures.
The quality team highlighted the issue of material storage and receiving inspection.
CMU plaster, mortar and grout shall be stored at controlled temperatures max 35
Celsius.
2.13 Windows and doors shall be protected from direct environmental effect by providing Open Construction Ongoing
tarpaulin sheet cover.
Damaged material shall be segregated and stored in a quarantine area.
The construction team was advised to complete backfilling around the fence post
2.14 Open Construction Ongoing
without delay to avoid any damage due to heavy rain or wind.
2.15 RFI for cable pulling should be raised by tomorrow at PS-11. Closed
2.18 PM advise QC to share the list of all MOS update for submitted On’s
22-Aug-24
Elect. site engineer requested to Deliver for All remaining PVC conduits&
Pro. 10-Sep-24
3.1 it’s fittings (Buildings, mono pole….). Closed Dept. 11-Sep-24
Reply: Delivered
02-Oct-24
Elect. site engineer requested to Deliver for All special fittings for 22-Aug-24
Pro.
3.2 communication concrete encasement& subduct material. Open Dept.
01-Aug-24
Reply: MTA Approved , P.O Issued, Deliver( 2 weeks for standard material) 30-Sep-24
Tracking Sheet for all delivered and undelivered materials. Pro.
3.3 Info Ongoing
Reply: Already tracking sheet shared in email. Dept.
Terminal Block for lighting pole, cables and lighting fixture holes and Screw,
Delivery.
3.4 Open Tech.Off. 15-Sep-24
Reply: procurement team need confirmation the sample is marching with
our project SPEC from the technical office.
Delivery of transition fitting.
Pro. 01-Sep-24
3.5 Reply: procurement team provided the sample to construction team to take Open Dept. 10-Sep-24
the approval from PMT & PID
Fire Stop Sealant: Pro.
3.6 Open
Reply: payment issue. Dept.
Anchoring Material:
Pro.
3.7 Material approved; Final quotation expected to receive on Sep 8, 2024 Open Dept.
1-Sep-24
Reply: payment issue.
4. Planning & Schedule Status Action By Due Date
The Technical Office was requested to finalize Redline for routing layout for
communication
5.2 Open Eng
All redlines approved
Follow up for PRS1 redline with SAPMT
The Technical Office was requested to finalize MEP Builder work for gate house, Open Eng
SSB& Generator Building.
Submit the Builder drawing for Gate house: 28-Aug-24- Submitted
5.3 22-Sep-24
Submit the Builder drawing for SSB: 27-Aug-24. – 18.09.2024
Submit the Builder drawing for PIC: 31-Aug-24– Submitted
Approval for PS9 Redline for layout& Duct bank types and location.
Prepare redline drawing for shifting lighting poles 69 to 71 for PS 11. Closed ENG
5.16 It’s Urgent. Should be submitted by today. 21-Sep-24
Waiting for confirmation from Site Engineer (Eng.Saad)
5.17 Technical office to follow up the submitted redline drawing with SAPMT. Info ENG
Need to reflect the extension of the fence for MIDS and FEC at PS-09. Open Eng
Need raise TQ for MIDS. It’s Urgent.
5.24 22-Sep-24
Need proposal from NGMSA
Redline submitted for Approval.
Prepared and approved shop drawing for foundation of Raise arm barrier, Open Eng
turnstile and road blocker, Crash beam rated.
5.25
Waiting for response from NGMSA
Shop Drawing for Road blocker submitted for Approval.
Prepare quantity of control cables for gate house related to annotator Panel Closed ENG
5.26 and lighting control panels.
Quantity Shared with Procurement on 10th Oct.2024
3|11
CONTRACTOR INTERNAL PROGRESS REVIEW & PLANNING MEETING
MINUTES OF MEETING
Relocate foundation for camera poles in PS11 & PRS1 Open ENG
PS-11 has been submitted and the PRS1 is remaining.
5.28
PS 11 approved
Waiting for confirmation from Site engineer (Eng Gowda).
Need to make redline for microwave foundation with 2 options. Closed SAPMT
5.32 Already Submitted.
Redline Approved.
5.33 Need MOS for installation of Emergency gate form A-1 Fence. Open ENG 21-Oct-24
5.34 Composing drawing for SSB surrounding for crossing utility. Open ENG
5.35 Send the approved redline drawing for fire tuck buy to A1 fence. Open ENG
5.36 Prepare redline drawing for foundation hook grouting. Open ENG
5.37 Location for monopoles to be finalized for all station Open ENG
6.1 Prepare the list for MOS required and submit all MOS for approval. Open
8.1 CONSTRUCTION – PS-08 Plan: 4.38% Actual: 3.85% Cum Plan: 55.47% Cum Actual: 38% Status Action By Due Date
Accommodation.
Open Management
Need new building with camp boss to open new NG & ABC activities
Need full details coordination dwg for potable line, waste line & dray utilities
lines specially at crossing locations
Open Engineering
New subcontractors send a quotation letter for concrete work,
Need additional subcontractors for the
4|11
CONTRACTOR INTERNAL PROGRESS REVIEW & PLANNING MEETING
MINUTES OF MEETING
Jumper Compactor. Management
Open
Boom truck already on the way to main store
Anchoring material.
Open Management
Procurement update, the payment issue still not released
Asphalt activity.
Need to expedite the closing of the comment, the can resume the activity. Open Quality
8.2 CONSTRUCTION – PS-09 Plan: 3.77% Actual: 0.9% Cum Plan: 73.24% Cum Actual: 51.2% Status Action By Due Date
NG activities on hold
Need prompt action as to submit the required inspection Open Quality
Microwave locations
Open Engineering
Need approved drawing for the microwave locations around the plant
Accommodation.
Managemen
Open
t
Need new building with camp boss to open new ABC activities
Need full details coordination dwg for potable line, waste line & dray utilities
lines specially at crossing locations
Open Engineering
New subcontractors send a quotation letter for concrete work,
Need additional subcontractors for the
Asphalt activity.
Need to expedite the comment closing, the can resume the activity. Open Quality
5|11
CONTRACTOR INTERNAL PROGRESS REVIEW & PLANNING MEETING
MINUTES OF MEETING
Boom loader.
Managemen
Open
Need one Boom loader then can release one forklift operator (quotation t
received)
Subcontractors.
Excavation work on hold as no any excavation subcontractor at site since 1
Managemen
month. Open
t
Need to finalize the Metrotunnel quotation to start the generator bldg. inside
the plant
8.3 CONSTRUCTION - PS-10 Plan: 4.07% Actual: 0.88% Cum Plan: 66.15% Cum Actual: 42.23% Status Action By Due Date
8.4 CONSTRUCTION – PS-11 Plan: 3.31% Actual: 2.18% Cum Plan: 57.99% Cum Actual: 39.54% Status Action By Due Date
FSF requirements
Open SAPMT
Still, they are asking ABC to provide them room, furniture, AC, sunshade …. etc.
Need to submit the required TQ of site grading inside the plant Open Eng
6|11
CONTRACTOR INTERNAL PROGRESS REVIEW & PLANNING MEETING
MINUTES OF MEETING
Need replacement for M. Abdulkarim Open Eng.
8.5 CONSTRUCTION – PRS-01 Plan: 3.57% Actual: 0.85% Cum Plan: 54.96% Cum Actual: 31.76% Status Action By Due Date
Quality &
Need replacement for M. Abdulkarim Open
Eng
Excavation subcontractor
Open PM
The subcon. Has stopped due to his payment issue
7|11